29Metals Limited (29M) Earnings Call Transcript & Summary

July 25, 2023

Australian Securities Exchange AU Materials Metals and Mining earnings 50 min

Earnings Call Speaker Segments

Operator

operator
#1

Appreciate everyone joining us and thanks for holding. This is the 29Metals Limited webcast and call for the June quarter, and you're all welcome here. Everyone attending is currently muted, so you'll only be listening in. We'll run through a presentation first, and after that there will be a Q&A session. Should you want to raise a question, press the star key and then the number one on your phone's keypad. At this point I'll pass things over to Mr. Mike Slifirski, Group Manager, Investor Relations. Over to you.

Mike Slifirski

executive
#2

Thank you, Melanie. Good morning, everyone. I'm Mike Slifirski. We'll be discussing 29Metals' June quarterly report, which went out to the ASX this morning. This call, along with a parallel webcast, is being recorded and can be replayed through the 29Metals website and the Openbriefing website. 29Metals Managing Director and CEO Peter Albert, our COO Ed Cooney, and CFO Peter Herbert will each walk you through the highlights of the June quarter before we open things up for your questions. At this point, I'd like to pass things to Peter Albert to get the discussion started. Thanks, Peter.

Peter Albert

executive
#3

Thanks, Mike, and welcome, everyone, and thank you for being with us this morning. During the June quarter, our main focus was Capricorn Copper and preparing for a restart in the third quarter, along with progressing the de-bottlenecking work at Golden Grove to accelerate production in the second half of the year. I'll return to the specific activities shortly. At 29Metals, safety and well-being always come first. TRIFR was largely stable during the quarter, though we did record one lost time injury. Naturally, there's no production to report yet from Capricorn, since we remain in suspension. Golden Grove lifted production in quarter two relative to quarter one, largely consistent with our plans. Copper output at 4,200 tons represented a 31% increase on Q1, and zinc at 13,400 tons was up 54% on Q1. Gold and silver production also rose versus Q1. Two main factors drove the higher production: first, the easing of the mill throughput constraint after the TSF3 lift approval came through in late April, and second, better production from Xantho Extended. Total production from Xantho Extended reached 76,000 tons, a 73% increase on Q1.

Peter Albert

executive
#4

We likewise saw a substantial rise in development meters at Xantho Extended, reaching 570 meters versus 410 meters in Q1 — that is, an increase of 39%. Importantly, this growth in Xantho Extended development comes ahead of the ventilation updates and upgrades involving the new booster fans, which are due to come online this quarter. Ed will discuss the booster fans in greater detail shortly. Today we have provided a guidance update, directing copper and zinc toward the bottom half of guidance and revising our gold and silver guidance to 15,000 to 17,000 ounces and 750,000 to 850,000 ounces, respectively. As previously guided, gold and silver production stays weighted toward the second half; the lower gold and silver output in the first half has led to a revision of full-year guidance. Cost guidance, including Capricorn Copper recovery costs, is unchanged. Absolute site costs in Q2 fell relative to Q1, even with activity levels rising. Again, this occurs despite ongoing inflationary pressure and shows early results from the cost out program we are implementing. Peter Herbert will walk through some examples shortly. C1 and AISC costs are recorded as increases on Q1, driven by several factors — notably reductions from byproduct credits due to lower prevailing zinc prices and higher charges tied to stockpile movements, with a significant rise in Golden Grove concentrate stocks sold during the June quarter.

Peter Albert

executive
#5

Q2 results shouldn't be taken as indicative of how the full year will go. When it comes to the longer-term projects that reduce operational risk, apart from the Xantho Extended booster fans, our attention is on submitting the life of mine tailing storage facility to the regulator during this third quarter, along with the Gossan Valley submission, which has been pushed back a little to the fourth quarter of this year. Conversion drilling carried on at Cervantes over the quarter, and so far roughly four kilometers of the seven-kilometer program for 2023 has been finished. The aim of that program is converting a substantial share of the existing inferred resources into indicated, so that feasibility studies for the project can be informed. That would probably take place in the second half of 2024, following the release of our next update to mineral resources and all reserves estimates early in the new year. At Capricorn Copper, our attention has naturally been on recovery, and the planned work for the first phase of restarting operations is on schedule. Initially, that means a restart at the Mammoth and Greenstone mines and the process plant in the quarter we are currently in, with dewatering of Esperanza South planned to begin in the fourth quarter of this year.

Peter Albert

executive
#6

Near the close of this quarter — that is, the last quarter — the regulator, the Department of Environment and Science, DES, asked us for extra technical information so it could proceed with approving the ETSF lift. That lengthier approval process, of course, places added strain on tailings storage capacity. With throughput reduced, plus several other near-term tailings options, we still feel confident we can lock in tailings solutions before our planned life of mine tailings storage facility outcome is implemented. We will soon put the life of mine tailie storage facility proposal in front of DES, and depending on any initial comments DES gives, we will move quickly into detail design and the approval submission. On financial outcomes, Peter Herbert will go through these in more detail, but a couple of highlights. Revenue of AUD 99 million, in line with expectations, lower for the quarter versus the first quarter. That, of course, stems from Capricorn Copper being suspended and from weaker revenue at Golden Grove, mainly because of lower zinc prices. Cash balance at quarter's end of AUD 127 million, noting the unwinding of AUD 31 million favorable working capital — unfavorable working capital at the end of the first quarter — and the drawdown of the $40 million revolving credit facility.

Peter Albert

executive
#7

For the quarter, the average copper price we received was $3.75 US per pound, while zinc came in at $1.13 US per pound — those are down 9% and 17%, respectively, versus the March quarter. During the quarter, 29Metals lenders gave covenant relief under the group's corporate debt facilities. On the insurance side, we've made significant progress with 29Metals insurers. The magnitude of the claim, how extensively facilities were damaged, and the complexity of the claim are key factors in our submission. Insurers now have all the information they need to confirm their view on policy response, and we'll be engaging closely with them about a progress payment to help with recovery costs at Capricorn Copper. I should note that, despite the liquidity available to the company at the 30th of June, we remain focused on enhancing our liquidity by delivering higher production in the second half at Golden Grove, pursuing an interim payment from our insurers as a result of the extreme weather event at Capricorn, reviewing all non-essential capital items, including those tied to recovery efforts, and reducing costs across the group. There are also other moving pieces, such as the restart of Capricorn Copper coming soon, strong support and engagement from our lenders, as well as positive engagement with insurers.

Peter Albert

executive
#8

Naturally, we'll keep the market informed about major developments once they take shape. At this point I'll pass things to Ed Cooney, our COO, for an update on production activities at the two operating mines, and then Ed will pass to Peter — to Peter Herbert — for a discussion of financial and commercial results. Ed, over to you, please.

Ed Cooney

executive
#9

Peter has discussed our safety metrics and production results for the quarter, so I'll start with how we're tracking against the recovery plan at Capricorn Copper. The team's main focus has been on moving forward the various water reduction initiatives that we outlined in our May strategic update. Over the quarter, we recommissioned existing additional evaporative capacity on site, and procurement of new high-efficiency evaporators has also moved ahead, with commissioning expected in early August. With the existing water treatment plant still inaccessible, reestablishing water treatment to support mining and processing operations is well advanced through existing settlement ponds three and four, with commissioning of this new system expected in early August. This project is intended to reduce reliance on additional freshwater drawn from the adjacent lake, contributing to an improved salt water balance over the medium term. In addition, detailed engineering is underway on expanded treatment of water contained within on-site storage structures ahead of release opportunities during the upcoming wet season. Engagement with the regulator remains constructive and ongoing. Further technical matters related to our application for ETSF Lift Two have been raised, and we are working with our external subject matter experts to address these matters. This delay to approval has necessitated a need to progress and accelerate alternative options, which were already previously being considered available to Capricorn Copper to address near-term tailings storage.

Ed Cooney

executive
#10

Also worth noting is the Esperanza Pit, where tailings were placed in the past, before the current lift at the ETSF. That choice is still contingent on the water reduction results we plan to achieve across the next six months, as well as on approval of an application already in place to expand water storage capacity inside the pit. At the same time, planning for a life-of-mine facility remains a top priority. On the mining side, the Mammoth and Greenstone ore bodies are both set to restart production, with recent work centered on extra paste fill reticulation so that we can maximize the conversion of tailings into underground backfill. Byrnecut resources are being remobilized — they were reallocated to other Byrnecut projects after the extreme rainfall event — and alongside that, we are progressing the design and procurement of dewatering infrastructure for the Esperanza South ore body. In addition, several personnel seconded to Golden Grove are coming back to Capricorn Copper ahead of the planned restart of phase one in August. Turning to Golden Grove, commissioning progress on the new booster fans for Xantho Extended has slipped slightly, owing to completion of the necessary civils infrastructure and the subsequent interruption to Gossan Hill access after portal remediation, following the activities carried out in the late March quarter.

Ed Cooney

executive
#11

Access has been restored, and the priority now is finishing the remaining civils work, then proceeding to mechanical installation of the fans, with commissioning to follow. We don't need to procure anything further, and we expect the fans to be commissioned in August. As noted before, these fans will support greater volumetric flows into Xantho Extended, which allows for higher mining activity levels at depth during the second half. Despite this booster fan delay, and as Peter said earlier, development performance at Xantho Extended rose by roughly 40% quarter-on-quarter, which is pleasing. Construction at TSF3, approved in early May, has progressed excellently, and we expect construction to wrap up ahead of schedule in August. Our attention has been on preparing the application for our new life of mine tailings facility, TSF4, and we anticipate submitting it this quarter. With our regulatory efforts concentrated on life of mine tailings facilities at Golden Grove and on recovery and tailings capacity at Capricorn Copper, submission for the Gossan Valley project is now expected later in 2023, and we don't anticipate any impact on the longer-term GG outlook we presented to the market in May. Turning to production outcomes at Golden Grove, June quarter performance delivered a 23% rise in mill throughput compared with the March quarter.

Ed Cooney

executive
#12

We saw better recoveries and more metal output in copper, zinc, gold, and silver. Going ahead, we expect second-half production to exceed the first half, particularly in Q4 for zinc, much like what we saw in 2022. At this point I'll pass things to Peter Herbert to go through the financial results for the quarter. Peter?

Peter Herbert

executive
#13

Thank you so much, Ed, and I appreciate all of you being on the call this morning. I'll begin with the revenue results for the quarter. 29Metals recorded unaudited revenue of AUD 100 million in the June quarter, a 39% decline versus March, hit by the suspension of operations at Capricorn Copper, and no sales were reported to Capricorn in the current quarter. Golden Grove revenues likewise came in below the prior quarter, mainly because of weaker commodity prices, even though the March quarter had high sales volumes, which also included the sale of the lead parcel. Those high concentrate sales volumes at Golden Grove were achievable thanks to the removal of throughput constraints, with managed available cavern capacity put in place. Turning to costs, Golden Grove costs were down quarter on quarter, as Peter noted, at AUD 78 million. That came despite activity levels overall being higher than in the last quarter. The decrease in site cost shows our ongoing focus on managing costs in an inflationary environment, with efforts undertaken to rationalize contractors, including insourcing pipeline operations, cutting headcount on site, re-tendering contracts, including drilling, village, and aircraft services, and deferring non-essential expenditures. The push for improved productivity and lower costs will continue through the remainder of 2023 and beyond.

Peter Herbert

executive
#14

Selling costs at Golden Grove came in higher for the period, though, which mirrored both a larger volume sold and the sales mix — more specifically, a substantial rise in zinc concentrate sales. Even with site costs coming down, unit costs at Golden Grove for the June quarter stayed elevated. Those higher unit costs mainly stem from materially lower by-product credits, since weaker zinc prices weighed on zinc revenues, along with the effect of negative QP adjustments tied to sales from earlier periods. Stockpile movement charges of AUD 11 million likewise pushed unit costs up, reflecting a drawdown in raw material stockpiles as mill throughput rates rose ahead of the last quarter. There was also a drawdown of concentrate stock profits alongside higher sales volumes during the period and lower concentrate zinc prices in the quarter. If foreign exchange and commodity prices hold steady, unit costs should decline in the second half as production rises and as cost reduction efforts keep making progress. At 30 June, year-to-date total capital costs at Golden Grove are tracking toward the bottom end of our guidance range. Capricorn Copper total costs for the quarter are AUD 28 million, and those were predominantly recovery costs as the site gets ready for the first stage of restart operations in August.

Peter Herbert

executive
#15

Although we’re still early in the recovery process, spending is tracking as expected—and cash outflows at Capricorn Copper for the quarter came to AUD 37 million, materially above costs, which reflects the unwind of working capital at Capricorn Copper after operations ceased in the last quarter. As recovery works move forward, we’ll keep assessing ways to improve the shape of recovery expenditures. 29Metals ended the quarter with unaudited cash of AUD 127 million following these key movements during the quarter. The unwind of positive working capital gains from the March quarter, roughly AUD 31 million, as we showed in the March quarter report. Weaker cash flows at Golden Grove on materially lower zinc prices during the quarter, including the impact of negative QP adjustments from prior uploaded sales. Cash outflows of AUD 37 million at Capricorn Copper, as working capital from the March quarter operations unwound, in addition to the recovery works undertaken. The drawdown of the group's $40 million US working capital facility and repayment of AUD 60 million for the group's term loan facility principal, as well as the net interest costs. On a net debt basis, the group had unaudited net debt of AUD 124 million at the end of the quarter, an increase on the March quarter position of AUD 34 million.

Peter Herbert

executive
#16

As we said earlier, 29Metals got a waiver from its lenders on certain covenants at June 30, acknowledging how the extreme weather event affected group performance. 29Metals is still talking with its insurers about that extreme weather event's impact regarding property damage and business interruption, and is working toward a possible interim payment. The company keeps assessing ways to strengthen its near-term cash flow profile, including, as noted, pushing forward discussions with our insurers, including the possibility of an interim payment. It is looking into opportunities to cut or delay recovery expenditures and non-essential capital across the group, and on top of that, lowering costs group-wide, as discussed earlier. Lastly, stamp duty tied to the Golden Grove acquisition is still outstanding. 29Metals carries an AUD 26 million provision for stamp duty. Thank you very much for your time. I'll now hand back to Peter Herbert.

Mike Slifirski

executive
#17

Appreciate that, Peter. Melanie, let’s move on to the Q&A portion now.

Operator

operator
#18

Thank you. Should you want to pose a question, kindly press star one on your phone and hold until your name is called. To withdraw your request, press star two instead. Should you be using a speakerphone, please lift the handset before asking your question. Our first question is from Rahul Anand at Morgan Stanley. Go ahead, please.

Rahul Anand

analyst
#19

Hello, Peter and the team. This is Rahul Anand calling in from Morgan Stanley. Morning, everybody. If I could, I'd like to begin with the fact that gold and copper came in lower. I appreciate that grades turned out weaker. I was just keen to get a sense of what some of the drivers are. Is it mostly a change to the mine plan? Are dilution problems involved, or was it that you couldn't get to particular areas of the mine? What was behind the silver and gold shortfall during this period as well as the downgrade to guidance?

Ed Cooney

executive
#20

Appreciate it. I believe you caught that slip yourself, Rahul. Initially you mentioned gold and copper, though clearly gold and silver are what hold your attention.

Rahul Anand

analyst
#21

Yeah. My apologies.

Peter Albert

executive
#22

Morning, Rahul. Eddie, I'll handle that question. There are, I think, several factors that played into gold and silver and our choice to reduce guidance on those metals. To begin with mill throughput: that bottleneck earlier in the year lasted longer than we expected, since it stemmed from delays in getting that approval. On top of that, zinc metal output has been lower year to date, and really the gold — the precious metals — is tied mostly to some of that zinc mineralization. A third factor would be, you know, some underperformance, which I believe we reported in the first quarter as well, with a bit of dilution at one of the production sources that carried gold. Then there's the deferral of another ore source that's heavy in precious metals but has a lower base metal content — one of those stopes pushed into 2024. Those are probably the main reasons.

Rahul Anand

analyst
#23

All right. Just to follow up on that point about throughput — clearly, Q1 came in below where we wanted, which I get, but milling throughput did improve during this quarter. It looks like, for the most part, the grades we received were considerably weaker on both gold and silver. If you could sort of unpack that for us: on the dilution side, did that carry over into this quarter? What are you expecting, and what's assumed in guidance for the remainder of the year, maybe?

Peter Albert

executive
#24

Yes. In Q1, one particular scuttle stope caused fairly substantial dilution — it was a remnant stope that had been mined between two backfilled stopes. To reduce that risk going forward, when it comes to future sources, we're now leaving larger pillars around it. That was really the main dilution source. But you'll agree, Rahul, that we do cycle through a large number of stopes. Occasionally we get some that do worse than expected, whether through recovery or dilution, while others do better. Which ones are affected depends somewhat on the period and on the character of the precious metal content.

Rahul Anand

analyst
#25

Alright, that's great. So maybe we move on to a couple of other items — first the insurance claim, and then capital availability. Of course, to start with, that $61 million draw on the revolver. Could you give us an update on capital availability as we head into the second half, and when you expect to have an update or some sort of resolution on the insurance claim?

Peter Herbert

executive
#26

On the insurance side, Rahul, we are of course putting pressure on the insurers. We have already made clear that they need to handle our claim and carry out an assessment. As I said, they now have every piece of information they asked for so they can move to that position. We cannot say precisely when that will happen, but naturally we are pushing for an interim payment while we wait. I am unable to advise, since at this moment we do not know when that might be.

Rahul Anand

analyst
#27

All right. With the claim now filed, could you maybe walk us through how we ought to approach the claim itself — I mean, will it cover the lost production? Will it also take in damage as well as, you know, recovery, ramp-up, and the losses tied to those? How should we be thinking about that claim?

Peter Albert

executive
#28

Basically, there are two main pieces here: the equipment loss, which is infrastructure, and then a business interruption piece. Those are distinct pieces. So they have the information that was requested. It's up to them now. We expect the final outcome to take a while, which is typical in these processes. And as I mentioned, we're pressing for an interim payment in the meantime.

Rahul Anand

analyst
#29

Alright, the last question was about having capital available and flexibility. Maybe just a quick reminder or recap on the debt facilities we have available right now, and on capital budgets, and whether everything still looks comfortable for you? Thanks.

Peter Herbert

executive
#30

Thanks, Raul. I'll just give a quick outline — Peter Herbert here. For the remainder of this year, our cash flow profile really centers on three items. The first is delivering against the latter goals. The second is examining how the rest of recovery expenditures are shaped and where we can do better on that, along with cutting costs throughout the group. Sorry — and that comes on top of pursuing an interim claim from insurers. As Peter mentioned, some of that sits outside our control to a degree. So those are the areas we're concentrating on as we work to strengthen our profile. On your specific question about debt facilities: at this moment they are fully drawn.

Rahul Anand

analyst
#31

Got it — that’s completely clear. Thanks so much. I’ll make sure to share it.

Peter Albert

executive
#32

Thanks, Raul.

Operator

operator
#33

Thanks. Our following question is from Daniel Morgan at Barrenjoey. You have the floor.

Dan Morgan

analyst
#34

Hello, Peter and Tim. Regarding Capricorn Copper and that tailings approval — do you think the approval is necessary before restarting the mill in August, or would you be comfortable moving ahead with putting tailings into the Esperanza pit if that becomes necessary? Thanks.

Peter Albert

executive
#35

Let me begin with that first comment. Dan, thank you for raising it — Ed may want to add something here. We feel quite confident about carrying on and kicking off the startup at Mammoth and Greenstone. Naturally, there has been no output during the past five months. As we have said before, we do not expect to run the mill at 100% throughput, but between now and when Esperanza South is recommenced, restarted around the middle of the first half of next year, there will be a fairly meaningful decrease in the volume of material requiring placement in the tailings storage facility. Looking ahead, we have numerous alternatives that we are working through alongside DES. As Ed mentioned earlier, one short-term possibility involves putting tailings back into the Esperanza pit — whether by re-engaging or replacing — since that pit has always historically served as a disposal location. We remain strongly focused on our life-of-mine tailings storage facility, and as we have said, we are progressing and presenting that to DES in the very near term, aiming to move it forward as rapidly as possible over the coming months. From a confidence standpoint, we are highly confident in our tailings position and in our ability to manage the current production profile, and we certainly expect to resolve tailings storage facilities over the next few months.

Peter Albert

executive
#36

Ed, is there anything you’d like to add to that?

Ed Cooney

executive
#37

Maybe a few more things to add. Running Mammoth and Greenstone means you keep the essential expertise and equipment on site to handle the different water-reduction projects that, frankly, are non-discretionary for us. We have to restore the site, bring down the site water inventory, and get the site back into compliance on that front. On top of that, when ore is processed and tailings are deposited up on the Esperanza TSF, that does carry a substantial volume of water onto what is a fairly large evaporative pan — the Esperanza TSF — along with entraining extra surplus water in paste that goes underground as backfill. Operating Mammoth and Greenstone opens up a few further water-reduction opportunities we can take advantage of, beyond the revenue it also brings in.

Dan Morgan

analyst
#38

To pick up on the water reduction efforts, what really stands out as crucial in my view is the upcoming wet season and being able to get water into, say, creeks that are running high or similar spots. What steps are required for that? Is it necessary to have the water treatment facility operating again? What's the current status there?

Peter Albert

executive
#39

Yeah, no, absolutely. That’s a really important initiative we’re focused on. We’ve got a dedicated team and resources assigned. Detailed engineering is underway to treat water held in the site storage facilities in anticipation of release. Engagement with the regulated DES is constructive and ongoing as well. Just one clarification point there, Daniel. If you were thinking or suggesting that we need the water treatment facility in full operation to be able to do that, that’s not the intention through this period. What we intend through this period is to treat water, bulk treat water to get it into a condition for release. We’re not reliant on a new water treatment facility, if that was the point of your question.

Dan Morgan

analyst
#40

Alright, thanks — that clears things up for me. That was my final question.

Peter Albert

executive
#41

Thanks, Dash.

Operator

operator
#42

Thanks. We’ll take the next question from Mitch Ryan at Jefferies. The line is yours.

Mitch Ryan

analyst
#43

Good morning, Peter and everyone on the team. I'd like to zero in on Cap Copper and ask whether you could give us a bit more detail on the recovery, particularly the underground water at Greenstone and Mammoth. What level are the water readings at? Are those areas accessible to you again, and what sort of ground conditions are you finding as you go back into them?

Peter Albert

executive
#44

Sure, Mitch, Eddie, I’ll handle that question. To make it clear: Mammoth and GST are the locations where we’ll restart operations—and production—in August. Those two ore bodies are completely dewatered, and we have full access to them. Esperanza South is the one that still contains a fairly substantial volume of water. We’ve kept the water level steady, so there has been no further water inflow. That’s being managed with some smaller pumps while we purchase the larger dewatering units before the full dewatering work begins later in the year. Obviously, we can’t inspect beyond the present water level. Based on everything observed so far—inspecting only up to that level—conditions are fine. We do expect that ground support will need rehabilitation once dewatering starts, so dewatering and rehabilitation will proceed in parallel, and the recovery costs include an allowance for that.

Mitch Ryan

analyst
#45

Yeah, thank you. Turning to Golden Grove — when do you think mine production would be limited inside upper Xantho if you don't get out, or, yeah, without relying on Xantho Extended, at what point does Xantho become constrained?

Peter Albert

executive
#46

Regarding the Gossan Hill complex, I can't recall the exact count, but there are possibly 8 separate ore bodies located there, and the Scuddles mine is also part of it. During the most recent quarter, roughly 80,000 tons came from Xantho Extended out of approximately 350,000 tons, which gives you a sense of the proportion.

Mitch Ryan

analyst
#47

All right.

Peter Albert

executive
#48

Looking at the medium-term picture, if you go back to the outlook statement we issued in May, the share of output coming from Xantho Extended rises annually. Next year, from memory, it was around 600,000 or 700,000 tons, then the following year it goes up again, and eventually it ramps to roughly 850,000 to one million tons, more or less. The rest of the material will come from the other Gossan Hill ore bodies along with Scuddles. Hopefully that answers your question?

Mitch Ryan

analyst
#49

Yes, that’s correct.

Peter Albert

executive
#50

Let me offer a slightly different remark there, Ed. We're genuinely very happy with how Xantho Extended has performed over the most recent quarter. As we've gotten deeper in there and opened up the development headings, and so on and so forth. The gain in development rate, along with production tons, even without those new booster fans — which will arrive very shortly — we're beginning to observe that extra throughput, sorry, that extra production coming from Xantho Extended, and things can only improve from this point as we bring that added ventilation online and are able to send more equipment down there.

Mitch Ryan

analyst
#51

I appreciate that.

Operator

operator
#52

Thanks. Our following question is from David Radclyffe at Global Mining Research. Kindly proceed.

David Radclyffe

analyst
#53

Morning, Peter, and hello to everyone on the team. My first question concerns the insurance payment and the fact that you're now pursuing what would essentially be an interim payment, if you're able to. I just want to get a clearer picture: does this relate to only part of the claim, and why would it genuinely serve the insurer's own interest to agree to it?

Peter Albert

executive
#54

David, I missed the first part of that. Insurers do commonly make these interim payments — certainly when it comes to bigger claims like the ones we have. I think that sort of situation is pretty typical, nothing out of the ordinary. Could you repeat the first part of your question?

David Radclyffe

analyst
#55

Obviously, whether it would be allocated to that was the question. That's a detail point we'll work through with our insurers, I think. Thanks, Peter.

Peter Albert

executive
#56

All right, thanks for clearing that up. On the debt restructure — you had kind of mentioned that you were looking at possibly doing a debt restructure in 2024, given the fact that there's some uncertainty around the potential timing of an insurance payout. I'm just wondering whether you've moved that process up?

Peter Herbert

executive
#57

Not really, no. I mean, in the end, you know, a proper process for insurance payments is something we can have. That would of course be an input, but I think it's fair to say that, you know, when it comes to a, yeah, a refinancing, our lenders, you know, quite rightly, want to see where we get to in terms of progress of the recovery and the ramp on Golden Grove. I think, you know, given... You know, I think we come at the process in 2024 with a lot more certainty about where we are on those two key things. That'll be a key, a key consideration, you know, for that process. I think doing it in the absence of some greater certainty there obviously makes that process much more challenging, if I can put it, you know, around in the way. You know, it's not irrelevant, of course, but insurance is not the driver of that timing.

Peter Albert

executive
#58

Alright, thank you. Perhaps, if I may, just one final question. A few of your competitors have clearly reported some fairly significant impairments on the base metal side. I'm just curious whether, for you, this is something you examine on a half-yearly basis or whether it's an annual exercise — and obviously it may not be a fair question, because without knowing the size of the insurance payment, it might not be something you could even assess. I'm simply trying to get a sense of when you review those carrying values.

Peter Herbert

executive
#59

Right, so under the accounting standards we’re required to assess that at every balance date, which means both the half-year and the full-year balances count. As you mentioned, there are plenty of moving parts in all of it, and we’re working our way through that. Pulling together the half-year financials is, you know, an active process right now.

David Radclyffe

analyst
#60

All right, thanks. I'll hand it over.

Operator

operator
#61

Thanks. As a reminder, if you’d like to ask something, just hit star one. Our next question is from Adam Baker at Macquarie. Please go ahead.

Adam Baker

analyst
#62

Morning, everyone. Regarding Golden Grove, there's a fairly solid rise in development rates. I believe you cited a 40% increase. I'm curious about what's behind that. Is it a change in how the mining fleet is set up? Did you add more jumbos, or could you give us a bit more detail on that, please.

Peter Albert

executive
#63

Yeah, thanks. Good question. I mean, look, this is something we've really been concentrating on quite a bit recently. We've put in place some restructuring when it comes to various organizational factors, added some resources aimed at execution in that specific area, stepped up our compliance with plan, metrics, and disciplines, and also worked on alignment of objectives between 29Metals and burn cuts. There's a whole multitude of factors there, and it's pleasing that the site team is achieving some benefits as a result.

Adam Baker

analyst
#64

Sure, that's definitely a good thing. Regarding your guidance, you reduced the guidance that's based on byproducts. On copper specifically, at this stage of the year, if you look at the first half, that comes to roughly 44% of your target. For zinc, it's approximately 41% for the half year when annualized. I'm just curious — you mentioned that some of that Xantho Extended ore comes in during the fourth quarter. Should we expect a comparable increase in copper too?

Peter Albert

executive
#65

Yes. In the back half of the year—especially during Q4—a larger share of output will come from the higher-grade Xantho Extended ore body, and that, as you know, lifts grade, which in turn lifts the metal. We observed a fairly comparable pattern and improvement during the fourth quarter of 2022. For zinc specifically, we anticipate that Q4 will deliver the strongest zinc output, while copper production, you know, will likely stay fairly steady across the second half. Adam, from the very start we have consistently guided toward a heavier weighting in the latter half. We, you know, feel quite comfortable—or confident—that things will unfold the way we anticipated.

Ed Cooney

executive
#66

Thanks, Peter. One more thing to add — throughput was mentioned again, and obviously we won’t face the same restriction we had during, well, effectively the first four months of the year. For the rest of the year, we’re unconstrained.

Adam Baker

analyst
#67

Okay, if I could just touch on recoveries — that was a pretty solid improvement, around 87.5% for copper and 88% for zinc. Should we expect something comparable in the second half of the year? And can that level be sustained going forward?

Peter Albert

executive
#68

Yeah, no, it was a really strong quarter on the recovery side. A couple of factors fed into that. Iron content was quite low this quarter compared with the grades, and the grades we treated, that has a very meaningful impact. If we set the Q2 recoveries against full year 2022, then they come in higher. I wouldn't really expect the Q2 performance to be reached across the rest of the year. Of course it's pleasing and it's something we'll always aim for, but we can't promise it. It's probably somewhat of a one-off.

Adam Baker

analyst
#69

Perfect. I’ll pass it along. Appreciate it, everyone.

Operator

operator
#70

Thanks. The following question is from Kate McCutcheon at Citi. Go right ahead.

Kate McCutcheon

analyst
#71

Hello, and good morning. I might have two questions for Peter H. Regarding that covenant relief, which particular one was waived, or which one had been a worry? You mentioned it briefly earlier — is there any room to push back debt repayments?

Peter Herbert

executive
#72

On the second part of your question, Kate, I think first — as I said, that's probably something we'd more likely look at next year when it comes to refiners. Let me expand on that. The key point here is that when you think about routes, plans and the integrated setup, especially with things like cost and value, we need to make sure our debt facility reflects our property in line with that profile, and that's the central reason for looking at a refinance, which is what we've been discussing. On that front, finding the right price for this business is more likely to be a 2024 exercise, as I planned. Going back to your first question about money, Kate, the covenants there relate to profitability and cash flow for this period. As you can see, obviously we consume cash, and the costs and lack of production also hit our earnings. Those metrics are measured against the net outstanding covenants that were put in place.

Kate McCutcheon

analyst
#73

Got it. Are there any other catalysts you're watching, or balance sheet timing gates, I suppose? Is there some point where you're reliant — where that insurance money has to arrive, and then you'd need to come to the market or maybe take another look at the Cap Copper restart spend? Based on my figures, there isn't much headroom, so I'm trying to get a sense of how you think about the timing internally and what hurdles you're looking for.

Peter Herbert

executive
#74

No, I wouldn’t describe it as a major milestone you have to pass through. Naturally, it’s something we watch very carefully, as you’d expect, and we want all of those matters handled as fast as we can. As I said earlier, our attention is on what’s within our control. The optimization of that profile you mentioned isn’t a gating item for us. It’s simply something we continue to monitor. Clearly, we’re concentrated on achieving stronger output in the second half to underpin our cash flow profile. Our cost-cutting work is a continuing effort. I wouldn’t tie any of those items to a stage gate. They’re all just matters we stay on top of, watch closely, and keep pushing where we have control. Beyond that, the effort with the insurers is moving ahead quickly. To be clear again, that’s not ultimately something we control, but we’re doing all we can to move it forward as fast as possible.

Kate McCutcheon

analyst
#75

Alright, understood. This is my final question, and it builds on what Dan asked regarding water treatment. In what way do you make Cap Copper resilient going forward? You are investing mid AUD 100 million into the recovery, yet from what I understand, a new water treatment plant is not part of that, and absent such a facility — with your water storage being limited — how do you guarantee, in the event of another extreme weather occurrence, that this asset is future-proofed, I suppose?

Peter Albert

executive
#76

Sure, Kate, I'll handle that question. There are a number of key actions around reducing water. One that we've mentioned before involves reusing and recycling water from the site within the existing settlement ponds three and four. That's clearly an interim measure, of course, since we don't yet have access to the current water treatment plant. Our goal is to commission it very soon. That's a crucial step toward putting the site water balance on a stronger footing. Over the longer term, of course, we're eager to have the existing water treatment plant infrastructure inspected. We want to replace that plant with one appropriately sized for the purpose, situated in a somewhat different location. That's one item. A second is our spending on extra high-efficiency mechanical evaporators. Those likewise help lower water volumes over time. There's also continued treatment of water so it can be released when opportunities come up during the wet season, plus the efforts we're making to invest in permanent infrastructure that makes this possible. Those are likely a handful of the main items. As you know, once we succeed in cutting the site water inventory, the water balance modeling we've carried out shows that, with that added investment, the water situation does reach a very sustainable position.

Kate McCutcheon

analyst
#77

All right, understood. Then just refresh my memory — did the insurance settlement cover the water treatment plant?

Peter Albert

executive
#78

That’s right—exactly.

Kate McCutcheon

analyst
#79

That's right.

Peter Albert

executive
#80

I’d like to clarify one thing. Ed mentioned a few parts of the water management strategy. Broadly speaking, what we’re aiming for is a negative water balance result. In the past, this site has taken water from a nearby lake, which of course puts more water into the system. With our updated water management approaches, we plan to cut that down as far as possible—just enough for potable water needs—and to recycle and reuse water at the site using the methods Ed described, Kate. That is really the direction we need to take.

Kate McCutcheon

analyst
#81

So basically, the approach here might be to get as much storage capacity as possible in place for the next kind of extreme event?

Peter Albert

executive
#82

Right, that's accurate.

Kate McCutcheon

analyst
#83

Alright, thanks.

Operator

operator
#84

Thank you. At this point we have no more questions. I'll turn things back over to Mr. Albert for some closing remarks.

Peter Albert

executive
#85

Okay, thank you, Melanie, and many thanks to everyone for all those excellent questions during this webcast and call. We appreciate all of you online joining us this morning. We've certainly gone through quite a lot of material here. There are several areas getting us excited, including of course bringing Mammoth and Greenstone back online, plus the ongoing gains at Xantho Extended, which, as we mentioned, will only improve once the new fans are running in the very near future. We didn't really discuss the conversion drilling at Cervantes. That work continues, and we look forward to that and to turning it into a feasibility study in due course. Our attention is on the longer-term project supporting the long-term sustainability of the business, Gossan Valley and life of mine tailings at both sites. And of course, there's also the chance to restart the tremendous exploration prospects we hold at Capricorn Copper. Thanks again, everyone. As always, for any follow-up, please reach out to Mike or any of us with any questions you may have, and have a good day.

Operator

operator
#86

That brings today's conference to a close. We appreciate everyone joining us. You're welcome to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete 29Metals Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to 29Metals Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in 29Metals Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.