29Metals Limited (29M) Earnings Call Transcript & Summary

October 22, 2024

Australian Securities Exchange AU Materials Metals and Mining earnings 46 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone joining us and thank you for holding. This is the 29Metals Limited conference call for the September Quarter of 2024, and you're welcome here. <<operator_script>> At this point I'll turn the conference over to the CEO, Mr. James Palmer. Kindly proceed.

James Palmer

executive
#2

Morning, everyone. This is James Palmer, and I appreciate you being here for this 29Metals update covering the September quarter of 2024. We'll be walking through the presentation that came out this morning together with our September quarter report. With me today are Ed Cooney, our Chief Operating Officer; Peter Herbert, our Chief Financial Officer; and Kristian Stella, our Group Executive, Corporate Development. It's genuinely good to be back speaking with all of you today and to take you through what the team delivered in a strong quarter — one that brings us nearer to our 2024 objectives and beyond. Before diving into the quarter's results, a quick pause on Slide 3 to restate the 29Metals investment proposition, in particular our substantial copper endowments located in Australia and the considerable upside potential. On Slide 4, our key priorities for 2024 are set out, and they haven't changed since I addressed you 3 months ago. Health and safety come first, always, and throughout the group we're focused on discipline in productivity and in cost improvements, with the team notching up some excellent wins on that front during the quarter. At Golden Grove, the emphasis is on the drumbeat of delivery so as to maximize free cash flow and progress toward a final investment decision at Gossan Valley. And at Capricorn Copper, the focus is squarely on the imperatives for a sustainable restart, with water reduction as the immediate priority.

James Palmer

executive
#3

Slide 5 gives you a recap of the September quarter. Where safety is concerned, our TRIF came in a little higher this quarter, and safety stays our #1 priority and our focus. On the operational side, the team at Golden Grove turned in a robust quarter, with 4.4 kilotonnes of copper and 19.1 kilotonnes of zinc produced, which puts us in good shape to hit our full year metal production guidance. Beyond that, the asset brought in $42 million of operating cash flow along with $26 million of free cash. So that's a terrific outcome. At Capricorn Copper, we were really pleased with the headway made on our near-term priority of bringing down water levels at site, with the team advancing what sits within our control to get the asset positioned for the best possible water reduction during the upcoming wet season. In particular, starting treatment of the water at the Mill Creek Dam, in preparation for controlled releases of treated water over the wet season, was a significant milestone this quarter. I'll hand over to Ed now to walk through Golden Grove in a bit more depth. After that I'll give an update on Capricorn Copper before Peter takes us through the corporate and finance update for the quarter. So over to you, Ed.

Ed Cooney

executive
#4

Thanks, James, and good morning, everyone. Moving on to Slide 7. As James said, the Golden Grove team delivered a strong quarter, producing 4.4 kilotonnes of copper and 19.1 kilotonnes of zinc, which puts us in a good position to meet our full year metal production guidance. As we flagged in the June quarter report, higher zinc production in the second half of this year is being made possible by paste filling finished earlier in the year and by progress on Xantho Extended development advance, which gives us access to high-grade ore through the second half of the year. And on the chart at the top right-hand side of the screen, you can see that the share of Xantho Extended ore was around 50% over the last 2 quarters. To that end, the 19.1 kilotonnes of zinc produced during the quarter represented roughly a 300% increase compared with the March quarter and a 25% increase compared with the June quarter. Zinc grade milled came in at 6.3% versus 4.8% in the prior quarter, and the higher feed grade lifted zinc recovery from 83% to 85%. Our copper output is also tracking well year-to-date, with 4.4 kilotonnes produced during the quarter, which takes our year-to-date copper production to 16.6 kilotonnes and positions us well against the full year guidance range of 18 to 22 kilotonnes.

Ed Cooney

executive
#5

On the Xantho Extended side, development carried on at rates that support our full-year metal production guidance, with development there coming in at roughly 700 meters for the quarter versus a bit more than 900 meters in the June quarter — that decrease reflects the lower planned activity as we put in the next sublevel of fresh air infrastructure in the deeper sections of Xantho Extended. Turning to Slide 8, unit costs had another good quarter, with C1 costs of USD 2.52 and all-in sustaining costs of USD 3.42 per pound of copper sold. Absolute site costs rose slightly quarter-on-quarter, driven by a planned 8-day extended shutdown in the quarter plus some extra maintenance spending that was required. The sequential rise in unit costs came mainly from the reversal of the June quarter's $33 million stockpile movement credit into a $21 million charge, along with higher treatment charges tied to larger zinc sale volumes and the recent strength in the zinc price, given the zinc treatment charge escalator linked to pre-IPO offtake agreements. Higher byproducts in the quarter partly offset the effects of stockpile movements and treatment charges. On Slide 9, work tied to capital expenditure on the TSF 4 project stepped up considerably during the quarter, and we now also hold the final key approval needed to complete construction from the Department of Water and Environmental Regulation.

Ed Cooney

executive
#6

Slide 9's photos illustrate how well the project is advancing, and hopefully they give you a sense of just how large the facility is. Completion is still expected in Q1 of 2025, on schedule. And given its size and the thickened tailings deposition methodology, TSF 4 should allow lower deposition costs across the mine's life. Beyond that, investing upfront in long-term tailings capacity is really seen as a way to derisk future tailings permitting requirements, compared with the incremental approach used at Golden Grove in earlier years of building stage lifts on smaller facilities. Moving to Slide 10. Production efficiency initiatives remain a major focus for the Golden Grove team and, in fact, throughout the business. Collaborating closely with our contract partners on site, productivity initiatives aimed at raising metal production and cutting unit production costs have been a key focus throughout the year. A couple of recent wins here are shown, namely the BlastIQ project, which in fact took an award at the recent Australian Mining 2024 Prospect Awards and allows digital reporting, analytics and information sharing between underground operators and production engineers, along with the implementation of some 3D stope and drive scanning technology.

Ed Cooney

executive
#7

Those are actually 2 more instances of making use of the fiber optic backbone we put in underground during 2023, which lets us achieve quicker work cycles, greater mobile fleet availability, and better safety. Moving on to Slide 11. We're continuing to move Gossan Valley toward a final investment decision, and during the quarter our work was really centered on reviewing the results of geotechnical assessments at both the box-cut and raise bore locations, receiving and analyzing tenders for surface infrastructure and underground mining, and refining the economic model. Gossan Valley has been drilled from surface to date, but history certainly demonstrates that mining fronts at Golden Grove tend to expand over time. And the team is very excited about the prospect of getting underground and the chance to really test how far the known mineralization extends. Once developed, Gossan Valley is expected to boost overall ore production and scheduling flexibility by supplying an additional independent and relatively shallow production front at Golden Grove. I'll hand back to you, James, to talk through Capricorn Copper.

James Palmer

executive
#8

Thanks, Ed. Yes, there were some genuine standout points at Golden Grove. Now, at Capricorn, lowering the water levels at the site is still the top priority. As we explained after the June quarter, releasing treated water in a controlled way is necessary to reset site water levels in the nearer term and to properly handle possible high-rainfall wet seasons ahead. Releases of treated water are, naturally, dependent on flow rates in Gunpowder Creek, and flows that allow those controlled releases generally happen in the wet season, running from November to April, which is nearly here. With the amount of water at the site, a meaningful reduction will probably require more than 1 wet season. On the substantial investment made so far this year to optimize controlled treated water release outcomes before the '24-'25 wet season and beyond, it's important to emphasize that this spending delivers a step change in the site's treatment and release capability relative to last wet season. In particular, the Mill Creek Dam, or MCD, water treatment and release infrastructure, together with the refurbishment of the lime slaking plant, now allows water at the MCD to be treated through water circulation and in-line lime dosing, and allows pre-treated water to be released in a controlled manner straight from the MCD into Gunpowder Creek.

James Palmer

executive
#9

That gives us a tenfold gain compared with the water release flow rates we could actually achieve in the '23-'24 wet season. So starting lime dosing of water in the MCD through the new water treatment infrastructure was a major milestone in the quarter, and it puts the team in a really strong position to release optimally treated water in the wet season ahead. Given this substantial investment in water treatment and release capability, we're confident we'll be ready to release water once the creek flows start. Beyond that, we've lodged applications to amend the existing EA, and the regulator is now assessing them. While that process is ongoing, we're simultaneously collaborating with the regulator to lock in an acceptable interim mechanism that will streamline water release outcomes for the '24-'25 wet season. Commissioning of the repurposed processing plant as an interim water treatment plant got underway after quarter end, which adds to the lengthy list of wins the team delivered in the quarter. As water is released from the MCD, we'll be able to rely on the repurposed processing plant to treat water from EPit so the MCD can be refilled for additional controlled treated water releases. We anticipate this will be a more efficient process than refilling the MCD with water from EPit and treating it only with the MCD infrastructure, or, as happened last wet season, treating the water from EPit by lime dosing in ponds 3 and 4.

James Palmer

executive
#10

Either way, that's a step change compared with the last wet season. Beyond the near-term lowering of water levels, the other things that must happen for Capricorn Copper to restart successfully and sustainably in the future are a new water treatment plant as a long-term water solution and life of mine tailings capacity. These weren't the immediate focus, but we kept making progress on both during the quarter: detailed design for a new water treatment plant moved forward, and we continue to assess multiple tailings options so we maintain optionality. On Slide 14, the picture on the left shows water being treated in the Mill Creek Dam as it progresses, in preparation for controlled releases of treated water during the wet season. There in the middle of the picture you can see, on the bank of the MCD, the bulk treatment and release infrastructure, which takes water from the dam, doses it with lime, and then circulates it back into the dam. On the right are the mechanical evaporators running at EPit, where on-site water inventory went from 3.7 to 3.5 gigalitres through this mechanical and natural evaporation during the quarter. Slide 15 shows the vehicles in the plan view photos of the bulk treatment and release infrastructure and the enhanced diversion dam photos, which convey the scale of the projects undertaken to date — something that can be difficult to appreciate when you're not on site.

James Palmer

executive
#11

That entire round of spending leaves the asset on a fundamentally stronger footing when it comes to environmental compliance and water management, and it delivers a step change in our ability to handle high-rainfall wet seasons and to make meaningful wet season releases that bring down water levels on site. Moving on, Slide 16 presents the strong drill results we received at the start of the quarter, but more broadly it speaks to the significant value that gets unlocked at Capricorn Copper once the water is dealt with. So, shiny core and big copper intervals aside, what's great about these drill results is that the team could confirm both continuity and orientation of a new mineralized zone lying east of the Portal Fault, in an area that was previously thought to be unmineralized. So in that area, previously thought to be unmineralized, we now have results such as 45 meters at 2.5% copper, and 36 meters at 3.9% copper, within a broader zone of 228 meters at 1.2% copper. So it turns out to be very mineralized. And every one of these results sits around an existing 64.8 million tonne resource with established development and infrastructure, both underground and on the surface, all within a 1,900 square kilometer land position in the highly prospective Mount Isa Inlier.

James Palmer

executive
#12

There's a substantial amount of copper in that ground. The only thing we need to sort out is the water problem, so that we can begin operating in a way that's sustainable and successful, and thereby unlock the value of the copper sitting there. With that said, I'll pass things to Peter, who will give a finance and corporate overview of the September quarter. Peter?

Peter Herbert

executive
#13

Thank you, James. Turning to Slide 18, I'd like to begin by covering how our revenue came out this quarter. For the September quarter, 29Metals recorded unaudited revenue of $177 million, which was up 39% compared with the result in the prior quarter. The drivers here were a 52% lift in sales at Golden Grove, partly offset by lower sales at Capricorn Copper following the suspension of operations. At Golden Grove, the higher revenues reflect quarter-on-quarter growth in sales volumes of copper, zinc and gold. Copper accounted for 47% of total revenue, down from roughly 50% in the prior quarter result, which reflects the runoff of production and sales at Capricorn Copper during the prior quarter, along with a greater proportion of zinc and gold byproduct revenue in Golden Grove sales. That strong sales outcome for the quarter meant Golden Grove generated $42 million of operating cash flow and $26 million of free cash flow during the quarter. Cash outflows at Capricorn Copper came to $23 million, with investment in water management capabilities and environmental compliance projects ahead of the 2024 wet season. We expect outflows to keep reducing through 2025 as these projects are completed and operating costs come down to reflect lower steady-state activity levels. Reducing cash outflows during the production suspension period at Capricorn Copper remains a focus.

Peter Herbert

executive
#14

So for that purpose, the site's power supply agreement was changed from 12 megawatts down to 5 megawatts, effective July 2024, which brought fixed power supply costs down. In addition, hauling of stockpiles by truck to Mount Isa for processing and sale began after the quarter closed. Corporate cash flows in the quarter included stamp duty installment payments tied to the 2021 IPO-related acquisition of Golden Grove. Those installment payments started at the beginning of the September quarter. The $27 million stamp duty figure, plus interest, is to be paid across 12 equal installments. Also, 29Metals kept amortizing its senior liabilities, with another USD 2.5 million principal repayment plus interest made during the quarter. Progress was achieved on the insurance claim for the loss and damage caused by the extreme weather event at Capricorn Copper in March 2023, both during the quarter and after quarter end. 29Metals and its insurers are moving discussions forward, seeking settlement of the service component of the claim and pressing for that on a basis as soon as possible. 29Metals ended the quarter with unaudited available liquidity of $104 million, made up of $60 million of cash and an undrawn offtake facility amounting to USD 30 million. That compares with available liquidity of $130 million at the end of the June quarter.

Peter Herbert

executive
#15

Thanks a lot, everybody, and over to you again, James.

James Palmer

executive
#16

Thanks, Peter and Ed. As we discussed on Slide 4, to wrap up, the team and I have a clear picture of what needs immediate attention in the business through the remainder of 2024, and we're gaining solid traction. Our focus has to stay on safe, sustainable gains in productivity along with tight cost discipline right across the company. We need to maintain the steady rhythm of delivery that Golden Grove is now building, given that we're well and truly into Xantho Extended, so that we hit guidance. And at Capricorn Copper, we need to keep on top of our environmental obligations, keep costs in check and move forward on the critical steps toward a sustainable restart of operations, with the most pressing focus being on bringing water levels down. And we have to accomplish all of that while never wavering in our dedication to health, safety and well-being. So I'm eager to deliver another strong quarter and finish the year on a high note, and to meet many of you in the days, weeks and months ahead. With that, we're ready to take your questions.

Operator

operator
#17

<<operator_script>> The initial question this session is from Daniel Morgan of Barrenjoey.

Dan Morgan

analyst
#18

Let me start with Tailings Dam 4 at Golden Grove. It's good to see that it's been approved and is now being executed. I'd like to understand a bit more—if you can quantify it in any way—what the benefit is to your operating costs going forward compared with, say, a 2024 baseline, perhaps in dollar millions. I just want some sense of what the benefit is from a better tailings solution.

James Palmer

executive
#19

Yes. I’ll take <<inaudible>>. Perhaps I’ll begin with capital intensity. So our TSF 3, the lift we’re currently depositing into, that required roughly an $8 million capital investment for 2 years’ capacity. This facility comes in at sort of circa $30 million for a broadly 10- to 15-year mine life. So from a — I guess, from a capital intensity standpoint, that’s probably a 20% to 30% reduction per cubic meter of capacity. When it comes to operating costs, that’s probably a little bit trickier to answer. I’ll probably respond by saying qualitatively, it’s a much lower risk facility by its very nature, being thickened tailings. So you don’t have the same level of systems of governance, which will enable the operations team to be sort of freed up and focus on other productive activities. But hopefully that gives you some flavor for the benefits.

Dan Morgan

analyst
#20

Yes. For the second question, I’d like to get a clearer picture of the stockpiles you had available at quarter end. Taking Q2 as an example, it seemed there were roughly 3,000 tonnes of copper and 5,000 tonnes of zinc that you had produced during that quarter but hadn’t sold. Now looking at this quarter, it appears to me that 2,000 tonnes out of those 3,000 tonnes was unwound, while only a negligible amount of the zinc was. What I’m getting at is whether you could outline the potential cash flow or working capital benefit, or the unwinding, at some point down the road?

Peter Herbert

executive
#21

Thanks a lot. I’ll take that question. This is Peter speaking. We had a — I mean, when it comes to sales during the quarter, we did move strong zinc volumes out the door. So we’d expect those stockpiles to be largely back to normal versus the prior quarter. Naturally, there’s always a bit remaining, but we did a solid job getting shipments out, and you can see that in the robust cash flows for the quarter. I think what we’re focused on going forward at Golden Grove is keeping that healthy share of Xantho Extended ore in the feed, so we can sustain that run rate for production and sales and make it as steady as possible from quarter to quarter, which is always both the challenge and the opportunity for a business like Golden Grove.

Dan Morgan

analyst
#22

Alright, a question about the terms on your copper concentrate — specifically TCRCs. Is there a link to benchmark pricing? I’m just trying to get a sense of whether you could soon gain from a decrease in TCRCs in 2025 at face value.

James Palmer

executive
#23

Right, those are tied to the benchmark. So you won't observe an instant decrease until the terms get renegotiated annually. That makes it hard to forecast how it will shift. Of course, spot prices give an indication, though they don't determine where the market heads. So yes, once those contracts reach renewal and that negotiation wraps up, we'll see it pass through. Positive or negative, we always keep an eye on it, naturally.

Dan Morgan

analyst
#24

And one final question, if I may. Are you currently in talks or negotiations with lenders about a revised debt facility or facilities?

James Palmer

executive
#25

Yes. Thanks, Dan. I think if we look at our facilities right now — and we've been fairly clear about this previously — they were established back in 2021. Since that point, the business has shifted considerably, particularly given what happened at Capricorn Copper. But beyond that, as we consider fresh opportunities for the company, whether that's Gossan Valley or other avenues for growth, we want to ensure the balance sheet sits in the right position to back those efforts. Our dialogue with lenders remains solid. We're in regular contact with them, and we've begun discussing what the business's profile ought to look like going forward, so that we can fit our objectives and priorities as a company. So yes, we're initiating those conversations, Daniel. On timing, we'd regard the next significant milestone regarding that senior debt profile as the step down in October — in October of next year — of the working capital facility, which is the item that essentially drives us. That's obviously not imminent, but we clearly want to get in front of it as early as we can.

James Palmer

executive
#26

The next question is from Alex Papaioanou with Citi.

Alex Papaioanou

analyst
#27

The announcement mentioned the advancement achieved during the quarter regarding the surface insurance claim. Could you provide additional detail on what progress was made, along with the possible size and timing of the claim that remains outstanding?

Peter Herbert

executive
#28

Yes, absolutely. Peter here once more. I'm glad to address that. Obviously, these conversations are quite sensitive in nature. As a result, I'm unable to provide any indication of the quantum, but I will do my utmost to describe the type of work taking place behind the scenes. To give a little context, we have moved past the indemnity cover period following the loss event in 2023 — that's March '23. So, to a significant degree, the information we're discussing is backwards-looking, and there is considerable work involved in going through the detail of it, along with substantial effort from the teams on site and in supporting functions, as well as from the loss adjusters and the insurers themselves. On that — we've made very good progress in resolving a great many of the queries, and we would see and assess that we are certainly nearer the end of that process than the start and beginning to see the finish line come into view. So we're pushing hard. I believe everyone on all sides of that process accepts that this is a lengthy process, and everybody is eager to bring it to a conclusion as quickly as they can. And frankly, we're encouraged by the efforts of everybody to try to reach that conclusion.

Peter Herbert

executive
#29

All right, solid headway is happening. We hope to share news as soon as possible about how this will shape up, though we'll hold off and see what the quantums turn out to be as we work through that conversation and wrap up any remaining queries.

Alex Papaioanou

analyst
#30

Right, got it. So on the underground piece — does the claim need complete underground access in place before it can move forward? Or is something else keeping that claim from advancing further?

James Palmer

executive
#31

What's at issue is the policy itself and whether there's agreement on what it covers. So this isn't really about what the company is or isn't doing on that front right now. It's more about whether the policy addresses that point, which I believe we've disclosed previously. So our team and the insurers are concentrating on pushing forward the service portion of the claim, since that part isn't disputed. So as that process nears completion, attention will shift more to whatever remains unresolved at that stage. That's probably how things will unfold from here, and it should give you a sense of where our focus and effort are moving at the moment.

Operator

operator
#32

Ben Lyons of Jarden has our next question.

Ben Lyons

analyst
#33

I have just a couple of quick questions. First, at Golden Grove, I've noticed quite a lot of variability in the development rates at Xantho Extended over the last few quarters. That's probably in line with the mine plan. But when you consider the sustainable development rate needed to keep increasing the share of Xantho Extended ore in the mix, what kind of figure do you have in mind on a monthly or quarterly basis for those development rates?

James Palmer

executive
#34

Yes, Ben, I might hand that over to Ed for the specifics. But when you ask that question, it was definitely among the things I was looking for, and getting down into Xantho, just taking a look at how far the team has come. Again, really solid progress, I think, as Ed mentioned at the start. It's in line with the plan, since it all centers on ventilation as we establish those new levels. So definitely good progress and on plan — cutting variability across the board is what we're aiming for at Xantho. And then perhaps Ed can give some of the detail on Ben's question.

Ed Cooney

executive
#35

Yes. Yeah, so in Q3 we had expected activity to be somewhat lower, since we were establishing the next infrastructure at the lower level. We also likely carried out a bit more rehab work in certain operational areas at Gossan Hill and Scuddles. But to answer your question, look, I think the rates we're at now are where we need to be. Broadly speaking, that's probably around 3 to 4 kilometers per annum. That will decline over the life of mine, though. I wouldn't say. But in the near term, provided we keep those levels up, we should maintain the proportion of Xantho ore in the mill feed.

Ben Lyons

analyst
#36

All right, great. And perhaps to look at it more conceptually, now that you have some extra development at the lower levels, what kinds of constraints are you dealing with at present? Is vent still the issue? Or is it your pace cycles or trucking? I realize the bottleneck likely keeps shifting, but what is the constraint and challenge right now, roughly speaking?

Ed Cooney

executive
#37

Correct, it's going to be a combination. As additional stopes are opened, backfill will inevitably face strain, Ben, simply because of how the stope sequence works. Making sure paste fill reaches the voids promptly is what will determine whether the next source is available. And in the end, trucking at depth and ventilation are the two main constraints. So we'll continuously examine ways to make improvements there. Enabling technologies are emerging that we intend to investigate. Still, at the end of the day, ventilation, trucking, and paste fill for turning around stopes are what matter most.

Ben Lyons

analyst
#38

Alright, let's shift gears and talk about Cap Copper for a moment. I believe guidance earlier this year pointed to roughly $18 million in holding costs across the second half of the year. And I noticed that $23 million was spent in the September quarter by itself. Now, I may have missed an update somewhere between that March quarter figure of $18 million and where things stand right now. But it does look like there's still a meaningful amount of cash going out at Cap Copper while you're doing the rehab work. So I'm just curious what level of cash outflow you expect in the December quarter.

Peter Herbert

executive
#39

Yes. Thanks, Ben. So maybe just to start off first, we incurred roughly $18 million to $19 million in costs during the quarter, along with cash outflows of $23 million. So there was a bit of a working capital unwind relative to earlier quarters <<inaudible>>. In the June quarter, we guided that expected costs for the remainder of the year would fall between $10 million and $15 million for — sorry, $10 million to $15 million on capital costs, and $20 million to $22 million on operating costs for the quarter. So that's — sorry, for the half, apologies. Apologies. So if you exclude the cost incurred this quarter, we're sort of on track to land within that guidance for the December spend. And what I can tell you is that the current focus is on reducing people and gear and contractors from site as the projects meant to get us ready for the wet season reach completion, which they are, in readiness from the 1st of November, when the wet season officially begins. So that figure remains our guidance, and we're comfortable tracking inside that range.

James Palmer

executive
#40

Yes. And Peter, maybe I’ll just — Ben, I’ll add one more point again, just from being on site: some of that is visible, a, the work that the investment has bought us and, b, certainly compared with the previous time I was on site, you can just see the reduction in the project work — just simple things like you’d count, and that type of thing. So those costs are certainly coming off.

Operator

operator
#41

Our following question is from Adam Baker at Macquarie.

Adam Baker

analyst
#42

Turning to Gossan Valley, could you remind us what remains outstanding on the permitting side there? And will an updated study be released to the market before you move ahead with FID, given that the most recent study came out in late 2022?

James Palmer

executive
#43

On the permitting side, we filed an application for that — I recall it was during the March quarter. So we'd expect to get a response from the department, likely early in the new year. That covers the timing on permit approval and works approval. As for updates, yes, look, we've gone out to tender. Pricing has come in. There's a bit more work to do. On some of the technical supporting information, we'll be refreshing it with all those inputs going forward, yes.

Adam Baker

analyst
#44

All right, so the potential optimization study would be slated for the first half of calendar 2025 — is that right?

Ed Cooney

executive
#45

Likely before then. James is really pressing me to finish all of that work. So right now it's still in progress. We're moving as fast as we can, though we probably can't say exactly when — but I'd say it will come sooner than the timing you mentioned.

Peter Herbert

executive
#46

Absolutely. <<inaudible>> driving the team hard, and all that <<inaudible>> it appears to be a solid project. We are definitely aiming to move it ahead, not delay it.

Adam Baker

analyst
#47

And perhaps regarding Golden Grove, what are you observing with the workforce there? Over the last 12 months, I've seen quite a few redundancies across the mining sector in various commodities. Are you finding it easier to get workers on site? Are some of those positions being filled more quickly? Just a brief comment on that, please.

James Palmer

executive
#48

Yes, I’ll take that question. I’d say yes. I think we’ve faced some difficulties throughout the year when it comes to labor availability at various points, whether that’s underground operators on trucks or bringing in technical professionals. But on the technical professionals side, I think we’re certainly in a good position right now, and we’re seeing some relief when it comes to operator availability. So it’s always a challenge, but I think right now we’re probably in a better position than we have been at any point during the calendar year.

Operator

operator
#49

<<operator_script>> We'll take our next question from Daniel Roden at Jefferies.

Daniel Roden

analyst
#50

I was hoping to get a clearer picture of the options available at Capricorn Copper. Could you take us through the timeline once more — covering permitting, development, and operations as they relate to the tailings considerations? So which alternatives carry which time frames? And when should we expect those to be carried out?

James Palmer

executive
#51

Correct, Daniel — I'll begin at a broad level, then pass things over to Ed if more specifics are needed. The key point is that we've been stating this plainly both inside the company and outside it, and in our dealings with government and regulators. Everything comes down to <<inaudible>> water. That's the critical path. So that has certainly been where the team's attention has been concentrated. Then the next 2 items, as we mentioned, water treatment plant. Yes, some progress has occurred there. But again, returning to some of the — how do we bring holding costs down. We're cutting back on work relating to items that aren't on the critical path. So long-term water treatment, and then long-term tailings. On tailings, as we noted last quarter, the suspension gives us a chance to examine alternative options, clearly, and we included that last quarter, with TSF 3 the most mature. But in fact, we have a couple of further alternatives there that might come in at lower cost, though they are less mature when it comes to permitting. But the focus, especially whenever we speak with anyone in government, Coordinator-Generals or DESI or others, is entirely on releasing water during the wet season, which typically begins at the end of next week.

James Palmer

executive
#52

Ed, is there anything you'd like to add?

Ed Cooney

executive
#53

One more point I'd add concerns the water inventory at the site: we've indicated that, in all likelihood, more than a single wet season will be needed before the site water balance reaches a level we believe can support restarting the operation. That should give you a sense of the timeline, hopefully. And across that timeline, it lets us advance tailings options at the same time.

Daniel Roden

analyst
#54

Yeah. All right. I suppose I’m simply attempting to view this through the lens of how much cash you might be able to accumulate before that point, since bringing the asset back online will require a fairly substantial amount of capital. So perhaps what is the — FY ’25 has been — sorry, calendar year ’24 is being guided to, but for 2025, what would the normalized care and maintenance cost be with copper not in production?

Ed Cooney

executive
#55

Right now we're in the middle of putting together the budget for next year and the years after that. What I'd tell you is that the spending pace you're seeing currently is clearly investment aimed at getting the site ready so it can release water. So those are, to a big extent, one-time investments. And after that, it will mainly be about keeping the site maintained through that period and managing water levels through that infrastructure. So investment is definitely high at the moment, and we intend to bring it down as we move into 2025, but we're not in a position to provide guidance on that yet.

Daniel Roden

analyst
#56

Alright. Perhaps just one final question. Regarding the Capricorn Copper stockpiles currently being toll treated, could you give some sense of what the opportunity looks like there — perhaps quantifying it in terms of cash flows?

James Palmer

executive
#57

Yes. I mean, just so we're clear, it isn't huge. That's 40,000 tonnes of material at roughly 1.5% copper. So you can run some quick back-of-the-envelope math on what that might look like on a toll trading basis. But I'd say a result in the single-digit millions. In that sense, it isn't life changing.

Operator

operator
#58

David Radclyffe of Global Mining Research has the next question.

David Radclyffe

analyst
#59

My question concerns Golden Grove. If you look at the volumes, a strong current quarter is needed to hit the low end of guidance for both ore mined and ore milled versus the tonnage guidance you've issued. So could you speak to your confidence in reaching that, and how the quarter has begun?

James Palmer

executive
#60

Yeah, so I’ll make a few points on that. As I mentioned earlier, some of the operator availability issues in the WA context across the calendar year when it comes to managing TKMs have probably made moving the volumes difficult for us. So we’ve directed the TKMs we do have toward the highest-grade material at depth, which is Xantho Extended. We also had some remote loads and bolting stopes during the second quarter. But as far as Q4 goes, everything is progressing well when it comes to delivering the grade we need to produce the metal. That said, I’d say volumes for the full year will definitely land at the low end of the guidance range.

David Radclyffe

analyst
#61

Okay. Then perhaps, as a follow-up, when we look at volumes for next year, since we're at the low end this year. And clearly, you expect Xantho Extended to ramp up. But is something like getting close to that 1.6 million rate that's been mentioned before still achievable in '25?

James Palmer

executive
#62

Yeah. I mean, that's the goal we'll always strive for. In the last calendar year, 2023, we likely hit roughly 1.5 million, or slightly above 1.5 million — 1.55 million. It really comes down to the unpredictable operational hurdles we run into over the year, having enough people available and so on, but trying to maximize volumes and keep the mill full will always be what we aim for.

Operator

operator
#63

The next question is from Timothy Hoff at Canaccord.

Tim Hoff

analyst
#64

I want to jump into that question about concentrate volumes that Dan was examining earlier. So, noting that you've opened up a new mining front of sorts at Xantho Extended, where there's a significant shift in the ore's constituents — have you come across any contaminants or deleterious elements affecting your concentrate qualities? And is that maybe a read-through to your TCRCs, which appear to have shifted quite a bit this quarter?

James Palmer

executive
#65

There's no indication that any harmful substances are present that would affect that. Regarding the TCRCs, they are definitely higher this quarter compared with the prior one. A couple of factors are behind what you're observing in TCRCs. First, a larger share of zinc in the sales mix, which as a rule tends to draw a higher TC. Beyond that, a greater volume of sales went to pre-IPO offtake contracts, where the TC is tied to zinc price escalators. And so zinc prices have stayed strong, which has had an effect on those. So it's very much a result of the contractual terms already in place for offtake and of increased zinc output and sales during the quarter — it has nothing to do with the quality of the concentrate itself.

Tim Hoff

analyst
#66

Also, on those pre-IPO offtakes, is there a hard deadline attached to them? Or do they expire at some stage <<inaudible>>?

James Palmer

executive
#67

Yes, those are set tonnages. So this year we'll be delivering 100,000 tonnes into it. And across the rest of the next 2 years, 140,000 remains to be delivered. The escalator also gets better over the next — over that outlook period. So holding price constant, we'd expect that to be smaller as we move forward. But yes, that — so yes, we would see it coming down. And as we ramp up zinc production in the years ahead, it clearly turns into a smaller share of overall sales as well.

Operator

operator
#68

<<operator_script>> Seeing that no more questions remain right now, I'll return the call to Mr. Palmer for closing comments.

James Palmer

executive
#69

Great. Thank you. Yes. Well, I appreciate you making time for us. Thanks for the questions. From where we sit, this was yet another quarter of strong delivery. And we've definitely started this final quarter at full speed so we can close out the year and meet guidance. So I think the potential you can see for 29Metals over the next 2 years is quite different from what the last 2 looked like. So thank you. Have a safe and productive day.

Operator

operator
#70

That brings today's conference to a close. We appreciate you joining us. You're welcome to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete 29Metals Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to 29Metals Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in 29Metals Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.