Adani Power Limited (ADANIPOWER) Earnings Call Transcript & Summary
October 30, 2025
Earnings Call Speaker Segments
Moderator
operatorGood day, ladies and gentlemen, and welcome to the Adani Power Limited Q2 FY 2026 earnings conference call. Just a reminder that every participant line stays in listen-only mode, and once the presentation wraps up, you'll get a chance to ask questions. If you require any help during this call, please signal an operator by pressing star and then zero on your touch-tone phone. Kindly be aware that this conference is being recorded. I'll now hand things over to Mr. Mohit Kumar from ICICI Securities Limited. Thank you, and over to you, sir.
Mohit Kumar
analystThank you, Sagar. Speaking for ICICI Securities, I'd like to extend a welcome to everyone joining this Q2 FY 2026 earnings call for Adani Power Limited. Joining us today from the management team are Mr. S. B. Khyalia, CEO; Mr. Dilip Jha, CFO; and Mr. Nishit Dave, Head Investor Relations. We'll begin with opening remarks, and after that we'll move to Q&A. The floor is yours, sir.
S. B. Khyalia
executiveI'd like to give a warm welcome to all of you joining us today for our second quarter 2025 to 2026 earnings call. I appreciate that you've taken time from your busy schedules to connect with us. Before we get started, I encourage you to download and review our quarterly results along with the analyst presentation, which have been made available on the stock exchanges. Joining me on the call are our CFO, Mr. Dilip Jha, and Nishit Dave, our Investor Relations Head. Over the past several years, the Adani portfolio company has consistently shown its strength and resilience. The portfolio's scale in terms of investment revenues, EBITDA, and cash flows has grown by multiples. Turning to Adani Power, I'm proud to say that during this period our company has contributed significantly to the group's earnings growth. We've navigated a range of challenges in the market, and each time we've emerged stronger. Our team has turned these challenges into opportunities, leveraging our experience and agility to drive sustainable growth. Now we are firmly set on our path to raise our generation capacity from 18 GW to 42 GW by 2032, with even faster growth in earnings and cash flows.
S. B. Khyalia
executiveWe're poised to significantly grow our share of the thermal power market. Out of the 14.5 GW of bids the state has awarded so far, we've secured new long-term PPA bids for over nine GW. During the quarter that just wrapped up, we announced the award of a 2,400 MW PPA in Bihar along with 1,600 MW in Madhya Pradesh. Beyond that, we recently also secured a 570 MW long-term PPA for 25 years from Karnataka, and that power would be supplied from our existing capacity at Raipur. A further 17 GW of bids are currently in various stages of submission. States and the central government are taking proactive steps to satisfy the project's long-term power requirement across all sources. We have high confidence that we'll tie up our upcoming capacities through these emerging opportunities. These PPAs will be value-accretive for the company. They'll let us earn higher returns on investment while also delivering steady cash flows. Our capacity expansion drive is moving ahead quickly. Four projects are presently under construction, with a combined capacity of 6,120 MW. They'll be finished in stages between 2026 to 2027 and financial year 2028 to 2029.
S. B. Khyalia
executiveWe've completely removed risk from our project execution pipeline, with 100% advance ordering in place for boilers, turbines, and generators. This is mostly brownfield development, and land availability stands at 100%. In the same way, the majority of environmental clearances have either been granted or are at an advanced stage of approval. Our in-house project management capabilities, combined with our financial strength and proactive strategy, will let us remain well ahead of the competition and deliver projects on time while keeping capital cost leadership. We have revived operations at the 600 MW Butibori plant of Vidarbha Industries Limited, which was acquired in July 2025, in just two months. This plant had been shut down for almost 10 years. We have also recently signed a 500 MW PPA for this plant with Maharashtra DISCOM for five years. Now, let's discuss our performance in the second quarter of 2025 to 2026. We have registered more than 7% growth in power sale volumes for the quarter at 23.7 billion units, compared with 22 billion units in quarter two of 2025. The year 2025 has seen an unprecedented early onset and a much-delayed retreat of the monsoon in recent memory. This has adversely affected overall power demand and peak demand.
S. B. Khyalia
executiveMerchant power tariffs have been soft as well, and that's due to the rainy season lasting longer than usual. So for quarter two of 2026, we ended up with a PLF of 62.8%, whereas quarter two of 2025 came in at 66.9%. For the first half of 2026, the PLF we achieved was 64.8%, against 72.3% in the first half of 2025. Even so, we managed to deliver volume growth, supported by our competitive PPAs, low-cost merchant plants, and added generation capacity. That said, the long-term drivers of demand remain in place, since they are linked to India's robust economic growth. We anticipate our PLF will strengthen once the residual weather effects fade and demand recovers. Adani Power recorded total continuing revenue, excluding any one-time prior period items, of INR 13,707 crores in quarter two of 2026, a modest increase over quarter two of 2025. Our EBITDA performance in quarter two of 2026 is fairly steady as well, even with lower tariff realization, thanks to cost-efficient operations and remunerative PPAs. Continuing EBITDA of INR 5,325 crores for quarter two of 2026 is near the continuing EBITDA posted in quarter two of 2025. Profit after tax for quarter two 2026 is healthy too, at INR 2,949 crores, and comparable to the PAT for quarter two of 2025, which shows our tight control on debt and finance costs even as the scale of operations grows and expansion continues.
S. B. Khyalia
executiveAs we look ahead, we anticipate that growth in our power demand will accelerate once more, which should lead to better offtake under long-term contracts and stronger traction in the short-term market. We plan to contract more of the open capacity through PPAs, along the lines of our recent 1 GW arrangement. I'm eager for the commissioning of new capacities that begins with the next financial year, which will drive the next cycle of rapid earnings growth. Adani Power is thrilled to play a key role in reliably meeting India's growing energy demand and in strengthening its energy security. At this point I'd like to turn the call over to our CFO, Mr. Dilip, who will elaborate further on the quarter two results. Thank you, and over to you, Dilip.
Dilip Jha
executiveThank you, Khyalia, and good afternoon to all of you. It's a privilege for me to walk you through Adani Power's robust and resilient financial results for Q2 and the first half of FY 2025 to 2026. Even with unprecedented weather patterns and power demand growth running at a slower pace, Adani Power turned in a remarkably strong and steady showing in quarter two. Subdued power demand along with weakness in tariffs held back revenue growth, even though we sold a higher volume of power. Total continuing revenue in quarter two of FY 2026 came in at INR 13,639 crores, a touch above the INR 13,465 crores posted in quarter two of last year — evidence of how resilient our business model is. One-time prior period income recognized in quarter two totaled INR 669 crores, largely tied to an old matter and late payment surcharge. In quarter two of FY 2025, that item stood at a broadly comparable INR 598 crores. Across the first half of FY 2026, total continuing revenue reached INR 27,807 crores, versus INR 28,577 crores in FY 2025. Prior period revenue for H1 2026 was INR 1,075 crores, once again close to the H1 2025 number of INR 1,020 crores. Turning now to costs: fuel expenses rose modestly in Q2 FY 2026, up 2.4% to INR 7,205 crores from INR 7,032 crores in quarter two of last year, driven by higher volumes and the plants we recently acquired.
Dilip Jha
executiveLooking at H1 2026, fuel cost came down 2.8%, landing at INR 14,514 crores versus INR 14,930 crores during the same half a year earlier. Other expenses rose 24%, reaching INR 814 crores in quarter two 2026 compared with INR 655 crores in quarter two of the prior year — mainly because recently acquired plants ran for the full period and because scheduled overruns brought extra maintenance spending. As a follow-on effect, continuing EBITDA for quarter two FY 2026 came in solid and stable against last year. Across the first half, continuing EBITDA was broadly similar, at INR 11,076 crores versus INR 11,692 crores in H1 of last year. Depreciation charges went up, tracking the power plant acquisitions made over the past one year. We kept our finance costs in check even while growing our operations. With EBITDA flat, continuing profit before tax for quarter two FY 2026 was INR 3,298 crores, broadly similar to the continuing PBT of INR 3,537 crores recorded in quarter two of last year. Continuing PBT for H1 2026 came to INR 7,096 crores against INR 8,020 crores for H1 of last year, consistent with the continuing EBITDA and depreciation rates.
Dilip Jha
executiveDeferred tax went up, and that pushed the tax charge higher for quarter two and H1 2026 versus the same period a year earlier. As a result, profit after tax for quarter two FY 2026 came in slightly lower but still very healthy at INR 2,906 crores, against INR 3,298 crores in quarter two of last year. Likewise, for the first half, profit after tax was commendable at INR 6,212 crores, compared with INR 7,210 crores in H1 of last year. Total debt as of 30 September 2025 is INR 47,254 crores, versus INR 38,335 crores at the end of March 2025. That rise is mainly attributable to bridge financing for capital expenditure and working capital requirements that support our ambitious growth plan. Our net debt position stays steady and healthy at INR 36,776 crores. We are putting our strong and steady cash equivalents to work in capacity expansion. Our capital structure policy is efficient, and we do not lean heavily on debt. Thank you for your continued support. We will now open the floor for question and answer. Moderator, over to you. Thank you.
Moderator
operatorThanks so much. At this point we'll move into the Q&A portion. If you'd like to pose a question, you can press star followed by one on your touchtone phone. Should you want to drop out of the queue, just press star and then two. We ask that participants use handsets when asking a question. Ladies and gentlemen, we'll pause briefly while the queue is put together. Once more, to sign up for a question, please press star and then one. Our first question is from Manish Somaiya of Cantor Fitzgerald & Company. Please go ahead.
Manish Somaiya
analystThanks, gentlemen, and congratulations. I have a couple of questions. First, could you discuss what you expect for merchant and PPA tariff realizations in the second half, given the softness in merchant pricing we've seen up to now?
Dilip Jha
executiveRight. So let me restate what you asked. What you're after is a sense of what we expect for PPA and merchant price movement over the back half of this year?
Manish Somaiya
analystSure. Could you give us the broad-strokes view on how we ought to be thinking about the second half compared with the first half?
Dilip Jha
executiveYes. Good afternoon, Manish. On the subject of PPA rates, no change is going to happen there, since those rates are, clearly, long-term ones. And when demand is lower, that only has an effect on offtake. So no different expectation exists when it comes to PPA rates. Our average realization this quarter came to INR 5.70 per unit, and we expect that same rate to keep being realized, because under the PPA rates do not shift much. Turning to merchant realization, we achieved INR 5.37 as the rate in quarter two. And for the remaining period, we anticipate an average realization of roughly, let us say, INR 6 or thereabouts, which was the rate seen over the last few years. That is our expectation. Thank you.
Manish Somaiya
analystRegarding the merchant share itself, I believe it currently sits at 88%. SBK, do you have any plans aimed at raising that figure, thereby avoiding pricing volatility, and what's your thinking there?
S. B. Khyalia
executiveLike I mentioned during my presentation, or in this section, we recently signed a PPA with Maharashtra for a medium-term period of 5 years at a rate of INR 5.55, and just recently we received an LOI from the state of Karnataka at roughly INR 5.79. So we've already contracted beyond what we mentioned before, about 1,100 MW, so if I look at the overall portfolio, I think it should now be coming out to 92%-93%. So we're taking steps to contract more and more under long-term or medium-term PPAs so that we can lower the volatility impact. Thank you.
Manish Somaiya
analystAll right, that’s really useful. I was aiming for that 92%-93%, and ideally, with additional PPAs, it’ll come in higher. So I appreciate that response. My other question concerns CapEx. Clearly, you have a substantial pipeline, a locked-in pipeline. How should we think about CapEx in 2026 and past 2026? And how should we also think about the funding mix between internal and external? Thank you.
Dilip Jha
executiveWhen it comes to our CapEx program, a meaningful share of the cash flow is being generated by our operating assets. That meaningful share, we'll finance out of our internal accruals. Over the coming 2 to 3 years, there will be an interim bridge need for the CapEx, and we'll raise that from the market — either through a short-term mix, the domestic capital market, or domestic banks. The meaningful share, we'll finance from our internal accrual fund. The interim gap, we'll raise from the market. That comes as a mix of, perhaps, the domestic capital market and domestic banks.
Manish Somaiya
analystAlright. Great. Thanks a lot for your assistance, and congratulations once more.
S. B. Khyalia
executiveThanks, Manish. Appreciate it.
Moderator
operatorThanks. We’ll take the next question from Abhinav at ICICI Securities. The line is yours—please continue.
Abhinav Nalawade
analystYeah. Good evening, sir. Thanks for the chance. My first question is about the Assam bid. Has the bid for 3.2 GW been floated? What's the status there?
S. B. Khyalia
executiveAre you referring to Assam?
Abhinav Nalawade
analystYes.
S. B. Khyalia
executiveAll right. The bidding process is finished, and we hold the L1 position. We've also obtained the commission's approval. So we're hopeful that we'll hear something favorable before long. As things stand, all that's publicly known is that the commission has issued its orders.
Abhinav Nalawade
analystGot it, thanks. For my second question, could you provide the revenue, EBITDA and PAT figures for H1 for the two plants we acquired, Coastal and Amarkantak?
Dilip Jha
executiveOkay, one second. For quarter two, Mahan's revenue came to INR 1,049 crores. Tuticorin stood at INR 677 crores. And Korba was INR 339 crores. On the EBITDA side for Tuticorin, this quarter's EBITDA was INR 54 crores. Then Korba's was INR 84 crores. And Mahan's was INR 521 crores. Let me go over that once more. Mahan's revenue for the quarter was INR 1,049 crores, versus EBITDA of INR 521 crores. Tuticorin's revenue was INR 677 crores, against EBITDA of 54 crores. Korba's revenue was INR 339 crores, and EBITDA was INR 84 crores. What I'm referring to here is operating revenue from the plant. Thank you.
Abhinav Nalawade
analystUnderstood — thanks.
Moderator
operatorThanks. We move to the next question, which is from Shirom Kapur at Jefferies. Go right ahead.
Shirom Kapur
analystOkay. Sharon, can you hear me?
Moderator
operatorYes, sir. We can hear you.
Shirom Kapur
analystYes. Thanks. Yeah, so like I was mentioning, you brought up roughly 17 GW of bids at different stages. Could you perhaps split that out by which states are putting forward those bids, and if you could just give us the numbers state by state?
S. B. Khyalia
executiveThe bids are publicly available: Rajasthan accounts for 200 MW, Uttarakhand 1,320 MW, Maharashtra 1,600 MW, Uttar Pradesh 4,000 MW, and West Bengal 2,260 MW — adding up to 12,000 MW. Beyond those, some bids are at an advanced stage of being finalized: Karnataka at 1,600 MW, Gujarat at 4,000 MW, and Assam at 3,200 MW. Taking the most recent numbers, the total comes to roughly 22,000 MW rather than 17,000 MW, since Gujarat recently floated a 4,000 MW bid that, I believe, wasn't part of the earlier figures. So the approximate figure comes out to 22,000 MW. Thank you.
Shirom Kapur
analystThanks. Thanks. That's really useful. I just want to make sure I understand. So during your presentation, you said roughly 91% of operational capacity is committed under PPAs. And looking at the later pages, roughly 8.5 GW of the upcoming capacity is committed as well. So is it accurate that of your 42 GW target, around 25 GW is currently committed under PPAs?
S. B. Khyalia
executiveThe planned new capacity stands at 23.5 GW. Within that 23.5 GW, 8.5 GW has already been contracted under the PPAs. So that figure is accurate. And as I mentioned, on top of this, we are L1 on the 3.2 GW Assam bid. Also, we have recently secured roughly 1,100 MW from the existing capacity — that is, as I noted, 500 MW in Maharashtra and 570 MW in Karnataka.
Shirom Kapur
analystOkay, that helps. Just to make sure I understand: out of the operating capacity of just 18,150 MW, what portion in gigawatts is currently committed under PPA, counting the 1.1 GW you signed recently? Could you give that as a gigawatt figure, since one of your pages shows 91% while the others show 88%? I just want some clarification on that.
S. B. Khyalia
executiveJust a moment. Broadly speaking, the number comes to roughly 16,700 MW, since the agreement is sometimes measured at the bus bar and sometimes at the state periphery, so there are a few small variations here and there. But broadly, that works out to 16,700 MW of the 18,150 MW.
Shirom Kapur
analystThanks, and understood. So my final question is this: you've clearly raised your goal recently—from 30 GW by FY 2030 to 42 GW by FY 2032. What I'd like to clarify is whether, from a planning standpoint, we remain on schedule for 30 GW by FY 2030, with that then building up to 42 GW by FY 2032. And within that original 30 GW plan for FY 2030, what share is covered by PPAs? Leaving aside whatever comes after FY 2030, I just want to get a sense of that.
S. B. Khyalia
executiveSo when we refer to 30 GW, what that means is an addition of 12 GW. I think that should be clear to you. So we're talking about an addition of 12 GW and then another addition of 12 GW. That comes to roughly 23.5 GW in total. And the first 12 GW is well on track. We're going to commission, let's say, around three GW next year. After that, we're going to commission 2.4 GW. In the year right after that, 3.2 GW, and in 2029 to 2030, 7.2 GW. So we're going to commission more than the 12 GW of capacity that was planned earlier. In fact, from the second stage of 12 GW as well, to some extent, the capacity will get commissioned before 2029 to 2030. So there's no issue when it comes to commissioning of the first 12 GW.
Shirom Kapur
analystUnderstood, and that includes it.
S. B. Khyalia
executiveAnd at that point.
Shirom Kapur
analystThe power purchase agreements are locked in.
S. B. Khyalia
executiveYes. Those PPAs we’ve already signed are included in this through 2029 to 2030.
Shirom Kapur
analystAll right, got it. So let me just fit in one final question here. On your side — you've already placed orders for the full 100% of equipment tied to the upcoming 23.7 GW capacity. So I'd just like to get a sense of how much of that you'd be able to share, how much has been awarded to BHEL, and how much has gone to L&T. A rough split would be useful.
S. B. Khyalia
executiveI can provide the broader figure rather than an exact one. To L&T we've supplied 8 machines, 8 units at 800 MW, and the remainder goes to BHEL.
Shirom Kapur
analystUnderstood, sir, and many thanks. That's genuinely useful. Wishing you all the best.
S. B. Khyalia
executiveThank you.
Moderator
operatorThanks. The next person to ask something is Aniket Mittal of SBI Mutual Fund, so please go ahead.
Aniket Mittal
analystYes. Thanks for the chance to ask. A couple of questions about Godda. First, I believe we've received approval to hook the Godda power plant up to the Indian grid. I just want to get a sense of when we can actually be connected to the Indian grid, and what the process looks like from here? And related to that, once we are connected, would we be permitted to sell power from Godda into the Indian market even though we're in a PPA with Bangladesh?
S. B. Khyalia
executiveWe expect that connection to happen by December 2025. As for your second question, it is permitted under specific conditions. Those conditions are already spelled out in the regulations covering when you may sell. So the conditions are either there is persistent no scheduling from Bangladesh because they don't have demand, or there is a payment default under the PPA. Under these two conditions, we will be allowed to sell the power in the Indian grid. And these are the precisely two conditions in which we would also like to sell. Otherwise, why should we be interested in selling in the Indian grid? So perfectly, it is basically going to address the issue. So if because of any reason, if the power is not being scheduled or because we are not getting the payment, so both the conditions will get addressed. Thank you.
Aniket Mittal
analystUnderstood — that helps. Regarding Godda, could you share what the PLF was for the second quarter? And as of the close of 2Q, what does total receivables for Godda stand at now?
S. B. Khyalia
executiveJust a moment. PLF. At the close of quarter two, PLF stood at 72%, versus 73% a year earlier. So the PLF is roughly unchanged. Godda's PLF is considerably stronger than that of the Indian grid, since across most thermal power projects on the Indian grid, PLF falls in the 60%-65% range. As for outstanding payment, the outstanding now amounts to just one and a half months. In any case, one month is not yet due. So of the overdue portion, only half a month is actually overdue. Thank you.
Aniket Mittal
analystGot it. It only covered the bids portion. I mean, the two bids I recall being at fairly advanced stages were Rajasthan and Uttarakhand. Could you give your estimate or timelines on where things stand with the bids for those two states, and when do we expect finalization to occur?
S. B. Khyalia
executiveAs for estimating anything on behalf of states, I don't believe that's something we can do. All we can provide is where things stand right now. So for Rajasthan, I believe the bid submission date falls next month. And as for Uttarakhand, the documents are still with the regulator for approval. That's the current status. Thank you.
Aniket Mittal
analystUnderstood. One final question from me. Earlier in your remarks, you noted that the merchant tariff for this quarter came in at roughly INR 5.37. For comparison purposes, what did that figure stand at during the same quarter a year ago?
S. B. Khyalia
executiveIn the same quarter a year ago, our average realization came in at INR 5.88. This year, that figure stood at INR 5.37. So this quarter saw a realization that was roughly 50 paisa lower.
Aniket Mittal
analystGot it. That's really useful. Those were the things I wanted to ask.
S. B. Khyalia
executiveThat's roughly 10% of what you'd call the tariff.
Aniket Mittal
analystYep, got it. Thanks. Those were all the questions I had.
S. B. Khyalia
executiveThank you.
Moderator
operatorThanks. Before we move on to the next question, a quick reminder for everyone on the line: you can press star and one to ask a question. Our next question is from the line of Vipul Agrawal, an investor. Please go ahead.
Vipul Agrawal
analystYes. Good afternoon, sir, and once more, congratulations on the outstanding results we delivered in Q2 and H1. From my end, I just have two questions. For the 23 GW expansion we're now planning, what is the total estimated CapEx?
S. B. Khyalia
executiveSo you're asking about the total capacity of 23.5 GW?
Vipul Agrawal
analystYes, sir.
S. B. Khyalia
executiveThe figure comes to roughly INR 2 lakh crore.
Vipul Agrawal
analystOkay, okay. And you've already covered the gearing question. The second one is about the extra 23 GW of capacity — regarding fuel linkages, will those be supplied to us together with the PPA, or will we be the ones applying for them?
S. B. Khyalia
executiveNo. As we've already said we'll be wrapping things up via the PPA, these days each bid arrives with a fuel linkage attached to the state utility. So across all of this capacity, the utility will supply the fuel as part of the bid.
Vipul Agrawal
analystAll right, and for the third question: the new PPAs we sign will involve a capacity charge for the fuel, with the fuel charge passed through. It won't be a single levelized tariff, which — I mean, because of that structure, we ran into problems with Mundra and so on previously.
S. B. Khyalia
executiveNo. When it comes to the new standard bidding documents, your quotation covers just the first year. Quoting a fixed figure across 25 years isn't permitted. So the number you provide applies to year one only. As for fuel, that's entirely passed through, calculated by a formula incorporating the escalation rate and similar operating parameters. On capacity charge, states differ somewhat. In certain states, capacity charge rises by 30% of PPA with a 2% decrease annually, while in a handful of states it rises by 30% of PPA with a 1% reduction. Broadly speaking, then, capacity charge stays roughly stagnant, and fuel charge is passed through.
Vipul Agrawal
analystAlright, final question from me. A news report came out on 11 September in which management provided guidance to hit INR 70,000 crores of EBITDA within 6 years. So does that figure account for the full 42 GW of capacity, or does it cover only the 30 GW?
Nishit Dave
executiveYes. Mr. Agrawal, that actually came from a media report. No guidance of that kind has been provided by management. So it was the media's own analysis, and that is what it was based on. That said, I think we would hope to achieve a better EBITDA than the one they projected.
S. B. Khyalia
executiveActually, my understanding is that the figure in that report came from 30,000.
Vipul Agrawal
analystAll right. Thanks, sir. Appreciate it. That’s sufficient. Thanks.
Moderator
operatorThanks. Manish Somaiya from Cantor Fitzgerald & Company has our next follow-up question. The line is yours — go ahead.
Manish Somaiya
analystThanks for letting me rejoin. SBK, I believe you said that critical components for the expansion pipeline have already been pre-ordered. Could you give us an idea of equipment pricing relative to what you paid previously? My assumption is that it will be higher, but I'm just trying to figure out whether the return dynamics shift given the inflationary pressure that has hit equipment costs. So if you could help us with that, it would be great. Thank you.
S. B. Khyalia
executiveI don't think it's really appropriate to get into equipment pricing on a public call. So I wouldn't be able to give you the exact pricing for the equipment, because sharing that kind of number would be, let's say, not appropriate. That's clearly confidential information, and in a competitive market, disclosing those numbers isn't appropriate. Thank you.
Manish Somaiya
analystI'd like to pose something else. Regarding getting the equipment delivered, my assumption is that this will hit your schedules given what you've discussed with your partners. We can feel at ease about that, correct?
S. B. Khyalia
executiveRight. The delivery timelines we've settled on span 38 months to 75 months overall. And these deliveries are staggered. We're confident we'll receive them according to that schedule, since as we said, four projects are under construction. And all four of those projects are ahead of schedule when it comes to both delivery and execution. So we have strong confidence that the deliveries will arrive on the agreed timetable. And as a result, no cost overrun is likely.
Manish Somaiya
analystAll right, thank you very much.
Moderator
operatorThanks. Just a quick reminder for everyone: if you'd like to register for a question, press star followed by one. Up next, we have Nirav Shah from GeeCee Holdings on the line. Please go ahead.
Nirav Shah
analystYeah. Hi. Good evening, sir. Thanks for the opportunity. Most of the questions have been answered. Just one last question. So we've commissioned the Dhirauli mine, and there was an incentive involving a waiver of the cess. But at this point, the cess has already been fully waived. So at present, in what form are we going to be incentivized on the mining?
Dilip Jha
executiveAt the Dhirauli mine, compensation cess is among the activities involved. Beyond that, the Dhirauli mine sits quite close to the Mahan plant. We already run one unit there. Two additional phases are on the way at that location as part of extended management. Compensation is one piece of it. On top of that, there will be substantial logistics benefits tied to the Dhirauli mine. As for Dhirauli mine, our expectation is that box cutting will happen by the end of this year alone. Starting next year, coal will come from that mine.
Nirav Shah
analystSo with the incentive — if we use the coal inside the state, that INR 400 incentive that existed, I mean, it won't be there anymore now? Is that a fair way to put it?
Dilip Jha
executiveSo where the compensation cess is concerned, there’s no incentive involved. The compensation cess is governed by the GST Act—it doesn’t come from any other state incentive.
Nirav Shah
analystSo the incentive works differently, then?
S. B. Khyalia
executiveIt was, you could say, a comparative incentive rather than an incentive in real terms. And under the new structure, there’s no negative impact.
Nirav Shah
analystRight, but there isn't anything positive, and that's the reason it comes out neutral?
S. B. Khyalia
executiveFor most of the domestic market, the effect is positive. But whether the change in law turns out positive or negative, it gets passed through to the customer as a change in law. So for the company, it's hardly anything.
Nirav Shah
analystUnderstood. Excellent, sir. Yes. That covers what I had to say, and best wishes to you, sir. Thanks.
S. B. Khyalia
executiveThanks.
Moderator
operatorThanks. Attendees, you can hit star followed by one to pose a question. The next one in the queue is from Nikhil Nigania at Bernstein. Go right ahead.
Nikhil Nigania
analystHello, and thanks for taking my question. I have a couple of things I'd like to ask. First, it's quite noteworthy that we're seeing so many tenders for thermal capacity, and that includes from states with abundant renewables such as Gujarat, which is simultaneously running a large number of battery tenders while battery prices keep falling. So I'd like management's perspective on what is behind this trend. We recognize the requirement for baseload power, but it remains surprising given that states like Gujarat, as you mentioned, have also begun seeking thermal PPAs. I'd appreciate your thoughts on this.
S. B. Khyalia
executiveWhat's your question?
Nikhil Nigania
analystSo considering how inexpensive renewables have become—
S. B. Khyalia
executiveRight, right. Go ahead.
Nikhil Nigania
analystNo, I was simply making the point that with batteries getting so inexpensive and renewables plus storage together being where they are, it strikes me as surprising that we're seeing so many additional thermal tenders come through — even from states with abundant renewables, like Gujarat, which, as you noted, is itself pursuing a thermal PPA. So I'd like to hear your perspective on what's behind this robust appetite for thermal contracting recently.
S. B. Khyalia
executiveI think you yourself have noted that this is meant for baseload. So clearly, thermal serves baseload. And as for the battery tenders that have come out so far, they are, let's say, for a token quantum. It really won't satisfy the baseload requirement. Even the Government of India's projection for battery installation through 2030 amounts to a fraction of total demand. So thermal is expected to be the only source supplying baseload power. That's why every state is issuing tenders for thermal project supply. And if you look at the resource adequacy report from the Government of India, they have laid out all these resources — solar, wind, battery — and after that worked out how much thermal installation is needed. So the tenders the states are issuing already factor in the possibility of battery installation. The tenders are coming after taking the battery plant into account under these studies.
Nikhil Nigania
analystUnderstood, sir. Got it. A follow-up on that: for most of these tenders, is there a requirement that the thermal plant be located inside the state, or are they okay with it being somewhere else while the coal resource is allocated to the state?
S. B. Khyalia
executiveEach state is making its own call on coal, since having a power station in-state or at the pithead comes with plenty of pluses and minuses. When you build the plant at the pithead, you save on transportation cost, but then transmission charges and losses come into play. Beyond that, states are also weighing what happens if you site the power plant within the state. You get a substantial amount of GST — not just on capital expenditure but also during operations, because GST is a consumption-based tax. So it lands in whichever state the ultimate product is consumed. In the case of operations, if the project is installed in the state, the coal gets consumed there. So there's a big GST revenue benefit on both CapEx and OpEx. There's also a huge possibility of employment generation as well as ancillary industries being set up in and around a thermal power project. So those are the benefits. On the negative side, if you put up a power plant in the coal-bearing states, every state is asking for something at variable cost. In Chhattisgarh's case, it is 5%. In Odisha's case, it is 12%. So if you supply 5% or 12% power at variable cost, that means the capacity charge for that quantum has to be loaded onto the rest of the power.
S. B. Khyalia
executiveSo those are the pros and cons of situating the power plant at the pithead versus inside the state. So each state is making its own calculated decision. Thank you.
Nikhil Nigania
analystGot it, and thanks for the additional detail. My final question ties to the point you just raised. GST has now gone up, but the cess on coal has been removed. So on a net-net basis, most plants ought to see their fuel cost come down. Have states begun any discussion about treating that as a change in law within the tariffs, or is nothing happening on that front at present?
S. B. Khyalia
executiveSo the position varies from one state to another. A number of states have already issued the change in law notice, and others may issue theirs in due course, since this only happened last month. But either way, because it has happened, from the date of notification it must be passed on in any case. So it is just the process part, where they need to issue the notice of change in law and then file a petition before the regulatory commissions, where they have to get it determined. And CERC, as you may be aware, has already initiated a few suo motu petitions to pass an order in this regard.
Nikhil Nigania
analystThat’s great. I really appreciate it. That covers everything I wanted to ask. Thanks for taking the time to respond.
S. B. Khyalia
executiveAppreciate it.
Moderator
operatorThank you. Participants, you can press star followed by one if you'd like to ask a question. Since no more questions have come in from the participants, I'll now turn the conference over to management for closing remarks.
Dilip Jha
executiveThanks a lot for taking the time and being patient enough to hear us out. We're hoping for that same degree of collaboration in the quarters ahead. Thanks. Many thanks to all of you. Enjoy a wonderful evening. Thank you.
Moderator
operatorThank you. That brings this conference to a close on behalf of ICICI Securities Limited. We appreciate everyone for participating, and you are welcome to disconnect your lines at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Adani Power Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Adani Power Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Adani Power Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.