ADF Group Inc. (DRX) Earnings Call Transcript & Summary

December 7, 2022

Toronto Stock Exchange CA Materials Metals and Mining earnings 20 min

Earnings Call Speaker Segments

Operator

operator
#1

Good morning, everyone, and thank you for joining us for ADF Group's conference call on the third quarter 2023 results. Right now, every line has been placed in listen-only mode. After the presentation, there will be a question-and-answer session. Should you need immediate help at any point during this call, just press star zero to reach the operator. Today is Wednesday, December 7th, 2022, and this call is being recorded. I'll now hand the conference over to Jean-François Boursier, our Chief Financial Officer. Please go ahead.

Jean-François Boursier

executive
#2

Thank you. Good morning, everyone, and welcome to ADF's conference call for the third quarter and the nine-month periods that ended October 31, 2022. To start, I'll bring you up to date on the quarterly and year-to-date results, which we disclosed earlier this morning through a press release, and after that I'll give you an update on operations. Before that, a note of caution: please be aware that certain matters we discuss today could contain forward-looking statements. Those are documented in ADF Group's management report for the third quarter and nine-month period ended October 31, 2022, filed with SEDAR this morning. Revenue for the quarter ended October 31, 2022 was CAD 65 million, versus CAD 110.2 million a year earlier, and year-to-date revenue came in at CAD 199.4 million, versus CAD 233.7 million for the comparable period a year ago. The revenue for the three- and nine-month periods that ended October 31st, 2021 benefited from fabrication of projects that had high output but low margins. You can see this by looking at gross margin as a percentage of revenue, which rose from 5.6% for the quarter ended October 31st, 2021 to 15% for the quarter ended this October 31st, 2022. Year to date, margins as a percentage of revenue also went up, at 13.3% for the nine months ended October 31st, 2022, versus 8.4% for the same period a year ago.

Jean-François Boursier

executive
#3

Beyond the fast-track projects with thinner margins that I just referred to, profitability for the nine months closing October 31st, 2022 also got a favorable boost from a CAD 1.3 million loan being forgiven — that loan had been extended to a U.S. affiliate of the corporation. That forgiveness was booked during the second quarter, which wrapped up last July 31st, 2022. Worth keeping in mind: the year-to-date stretch that closed a year earlier, on October 31st, 2021, had the benefit of a COVID-related subsidy from the Canadian government, and that lifted gross margins in the quarter finishing April 30th, 2021 by CAD 1.6 million while adding CAD 1.9 million to Adjusted EBITDA. With those gross margin improvements in mind, Adjusted EBITDA came in at CAD 7.5 million and CAD 20.2 million for the three- and nine-month periods ending October 31, 2022, respectively, versus CAD 4.7 million and CAD 13.9 million in the matching periods a year earlier. On top of the item I noted earlier, Adjusted EBITDA in the nine months through October 31st, 2022 gained from a CAD 800,000 gain on fixed asset disposals, recorded in the second quarter that ended last July 31st, 2022, which brought selling administrative expenses down by that same amount. As a result, we finished our 3rd quarter with net income of CAD 2.9 million, or CAD 0.09 per share, against CAD 2.8 million, or CAD 0.09 per share, in the equivalent quarter one year prior.

Jean-François Boursier

executive
#4

For the year so far, net income came in at CAD 12.6 million, or CAD 0.39 per share, versus CAD 8.7 million, or CAD 0.27 per share, in the comparable period that closed October 31, 2021. Cash inflows from operating activities totaled CAD 14.5 million for the three months ended October 31, 2022, which lifted year-to-date cash flows from operating activities to CAD 7.7 million. As I mentioned earlier, we also kept up our CapEx investment program at the Terrebonne facility. With that program included, cash flows from investing activities required outflows of CAD 10.5 million year to date over the nine-month period ended October 31, 2022. Since our automation investment program is essentially finished, we anticipate full-year CapEx of CAD 12 million. As previously confirmed, we received the first amounts of our new financing with Investissement Québec, totaling CAD 15 million, in the quarter ended April 30, 2022. Given that total available financing is CAD 20 million, we still have CAD 5 million available to draw on in upcoming quarters. Our balance sheet remains strong, with working capital of CAD 58 million as at October 31, 2022, versus CAD 38.7 million as at January 31, 2022.

Jean-François Boursier

executive
#5

So that brings our third quarter, which ended October 31, 2022, to a close with CAD 15.8 million in cash and cash equivalents. That leaves us really well positioned to go after backlog growth and to deliver on the backlog we have, which was CAD 344 million as of October 31, 2022. We're still working through some uncertain conditions, inflationary pressures among them, but once again we managed to raise both our growth margin and Adjusted EBITDA — in dollars and as a share of revenues. The positive effects of our recent investments, specifically our new turbine automated fabrication line, keep showing up, and we expect more efficiency gains over the coming quarters. In the weeks ahead we'll be able to confirm a new contract signing. That extra volume, together with the efficiency improvements, is a very good sign for the quarters ahead and will turn into better returns for our shareholders. Ladies and gentlemen, thank you for your interest in ADF and for your confidence in us. I'll now take your questions.

Operator

operator
#6

Thank you. Ladies and gentlemen, we're now starting the Q&A portion, and it's open to analysts only. If you have a question, kindly press the star key and then the one on your touchtone phone. To withdraw your question, press the star key followed by the two. When on a speakerphone, please pick up the handset before pressing any keys. Please hold for a moment while we take the first question. Our first question is from Edward Collery of Pelham Investment Partners. Please go ahead.

Edward Collery

analyst
#7

Hello there, Jean-François.

Jean-François Boursier

executive
#8

Good morning, everyone.

Edward Collery

analyst
#9

I’ve just got a couple of quick questions. The first is that I was hoping for an update on how the company is thinking about capital allocation—specifically, whether there might be greater returns to shareholders, and perhaps something about when that could happen. I believe last time you mentioned something along the lines that, with the backlog growth, that could be a bit further out, but I just wanted to confirm that nothing has changed.

Jean-François Boursier

executive
#10

Right. And in the near term, that hasn't shifted, and it likely won't over the coming year either. To begin with, on our end, capital investment will return to more typical levels. We haven't begun the budget work yet, but I can foresee CapEx declining back to roughly the CAD 5 million range for the next fiscal year, since that will mostly be maintenance CapEx. Beyond that, we're still working to grow the backlog. We remain conscious of the working capital needs involved in growing that backlog. At least in the near term, we want to begin producing free cash flow and make sure we maintain a strong balance sheet. Once we get there, hopefully next year, with what's in backlog and what we see coming at lower CapEx, we ought to be able to produce free cash flow. Perhaps later next year, we'll be in a position to start examining the other option with our free cash flow. As things stand, we're still striving to stay prudent in that regard, given that we still have targets to sustain and in fact grow backlog levels.

Edward Collery

analyst
#11

Alright, so on that — have shifts in the economy across the past, as you put it, 3 or 6 months affected how the company sees its capacity to expand the backlog?

Jean-François Boursier

executive
#12

To this point, we have not observed any significant shifts—nothing has been delayed, and no project has been moved to the right. As I said just a few minutes ago, we anticipate being able to announce new contracts within the coming weeks. We feel quite positive regarding the potential for additional contracts over at least the next few—perhaps the first six months of the next fiscal year. We have not seen any. As I noted, we have not encountered any pushback. Clearly, based on what we know today and depending on future developments, we remain hopeful that the market will continue to be fairly active. We continue to see many projects. The Architecture Billings Index is still above the 50 mark, which is a positive sign, indicating that projects are entering the pipeline. We remain hopeful. As I also mentioned during this call, certain uncertainties exist. Inflation has not gone away. There are, of course, still many questions about the situation in Ukraine and what impact it will have. We know what we know at this point, but we also recognize that many people—there are many infrastructure programs that want to get underway. The U.S. government has committed substantial funding.

Jean-François Boursier

executive
#13

Folks want to put those to use. Even with interest rates going up, even with inflation, we continue to see plenty of projects. At some point, will we hit a moment when people say, "Oops, let's pause"? Possibly, but that hasn't shown up yet. We're quite optimistic, certainly for the next... Well, for what's left of this fiscal year and for next fiscal year, though we'll stay prudent beyond that. From what we can tell right now, things still look good.

Edward Collery

analyst
#14

Thanks. One more item from me—it concerns what you disclose about backlog and the fabrication hours inside it. This may be more detail than you care to get into, but in the prior quarter backlog stood at CAD 348 million, and the Q noted that fabrication hours made up 59% of it. In the current quarter it is CAD 344 million, with 48% consisting of fabrication hours. So fabrication hours within backlog moved from CAD 205 million down to CAD 165 million. During the quarter, we recognized only roughly CAD 12 million of fabrication—sorry, CAD 14 million of fabrication. I’m simply trying to understand what happened there that produced such a large decrease in fabrication hours in backlog.

Jean-François Boursier

executive
#15

When we look at the actual fabrication hours for the quarter, the backlog also comes into play, and we recognize that backlog in Canadian dollars. As you're aware, a significant portion of our backlog is.

Edward Collery

analyst
#16

Uh-huh.

Jean-François Boursier

executive
#17

That originates from U.S. projects, so our backlog took a sizable currency hit, which could distort those figures as well when you examine them.

Edward Collery

analyst
#18

Understood.

Jean-François Boursier

executive
#19

Looking at things broadly from one quarter to the next, it's really quite normal, when there are no fresh projects entering the picture, that when you examine the overall backlog on a quarter-over-quarter basis, the percentage — we handle fabrication first, then installation — the fabrication share of total backlog declines faster than the installation share. Once new projects do come in, and as I said, as we're hoping we can manage in the weeks ahead, you'll see that fabrication portion rise back to a higher level. Under ordinary circumstances, and once more, given the kinds of projects we're seeing at present, that's not unusual. Measured across a 12-month period.

Edward Collery

analyst
#20

All right.

Jean-François Boursier

executive
#21

Looking at a longer time horizon, we'd see fabrication accounting for 45%-50% of our backlog, with installation making up another 45%-50%, plus or minus, and the remainder split between design and raw materials. You'll see the quarter-over-quarter movement.

Edward Collery

analyst
#22

All right, I get that you're going to draw it down. What I'm really saying, I suppose, is that it dropped by CAD 40 million. The backlog — the fabrication backlog — declined by CAD 40 million, but my understanding is that fabrication accounted for just 21% of revenues in the quarter, so fabrication revenue for the quarter came to only roughly CAD 14 million. As you mentioned, it could have been the FX. I haven't taken a look at that.

Jean-François Boursier

executive
#23

Well, it did make a difference, so that could be it.

Edward Collery

analyst
#24

Sure.

Jean-François Boursier

executive
#25

We have to get into the.

Edward Collery

analyst
#26

All right.

Jean-François Boursier

executive
#27

That amount of specificity could account for a substantial portion of it.

Edward Collery

analyst
#28

Alright, got it. That clears things up. I’m all set on my end. Thanks so much. Appreciate it.

Operator

operator
#29

Ladies and gentlemen, just a quick reminder — if you'd like to ask a question, press star then one. Our next question is from Murray Knight Engel, a private investor. Please go ahead.

Murray Knight-Engel

unknown
#30

Thanks. Nice work on the numbers, guys. I've got a question about what comes next. A lot of new projects are being announced in the States. I mean, there's the infrastructure spending that the government, the U.S. government, announced last year. I'm wondering, are you starting to see some business from that? You're seeing a lot of companies, new companies being. There's sort of this reshoring back in America, and that's all non-residential stuff. It's all commercial stuff. Are you starting to see some interest from those kind of projects that perhaps you wouldn't have anticipated, say, two or three years ago? Those are my questions.

Jean-François Boursier

executive
#31

On the first set of questions, yes, as I said when addressing the earlier one. Bidding activity remains very much alive, and we continue to see plenty of it. And yes, that volume of activity does encompass projects stemming from the various infrastructure programs that have been introduced in the States and, to some degree, in Canada as well. Many of these involve public funding, so obviously they fall under the Buy American Act, meaning we are able to bid on them but must fabricate them out of our Great Falls plant. That said, a lot of this public infrastructure also spurs private investment around those public investments, which is good for us too, and those projects could actually be — since they are not subject to the Buy American Act — fabricated out of our Terrebonne plant. All in all, yes, we do see a significant improvement. We still see a good market. I don't believe the full effect of the infrastructure program coming from the different governments has fully impacted the entire market. Some of that might be to some extent offset by what we're seeing from the interest rate standpoint and the pricing increase. Obviously, having access to subsidies or to an infrastructure program is one thing, but the fact of the matter is project costs are going up just because of the inflation.

Jean-François Boursier

executive
#32

Broadly speaking, we're still seeing plenty of opportunities on the bidding side. On your second question, I wouldn't be able to answer that. I'd have to look into it specifically. In general terms, regarding the market, I can't put an exact figure on where the extra opportunities, or where the strongest ones, are originating. I'm certain a portion of it could stem from bringing some fabrication back. Honestly, North America has a great deal of capacity for steel fabrication. I think for a U.S. or Canadian project, offshoring wasn't really all that prevalent. I'm confident, and I'm aware, that many European fabricators, or fabricators from outside Canada and the U.S., were bidding on larger projects in North America, since this is genuinely the strongest steel fabrication market worldwide. At least for now, it's stronger than Europe, simply from a capacity perspective. Without getting into all the specifics, and as I mentioned, I personally don't have that level of detail, I'm sure those projects returning to North America are likely also part of the improved backlog pipeline we're currently seeing.

Murray Knight-Engel

unknown
#33

Got it. All right, thanks.

Jean-François Boursier

executive
#34

Appreciate it.

Operator

operator
#35

Mr. Boursier, that brings us to the end of the question-and-answer session. You may go ahead.

Jean-François Boursier

executive
#36

I'd like to express my appreciation for your interest in ADF Group. We hope the holiday season brings you safety and happiness. Have a nice day.

Operator

operator
#37

That brings today’s conference call to a close, everyone. We appreciate your participation, and we ask that you kindly disconnect your lines at this time. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete ADF Group Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to ADF Group Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in ADF Group Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.