Akobo Minerals AB (publ) (AKOBO) Earnings Call Transcript & Summary

September 27, 2024

Oslo Bors NO Materials Metals and Mining earnings 72 min

Earnings Call Speaker Segments

Jørgen Evjen

executive
#1

Good morning, everyone, and welcome to the First Half-year 2024 presentation, and happy Meskel to all our Ethiopian friends. We're a bit spread out today. Joining me is Helge Rushfeldt, head of operations on the mining and processing side, and also Dr. Matt Jackson, who will walk us through some of the exploration slides today. I apologize for my voice. I hope it holds up through the whole presentation. I've just been out traveling and caught a small bug. So, let's begin. A lot has happened during this first half year. Many milestones achieved, and probably the most important thing is that we have now reached, what I would say, a long-awaited stage of daily mining, stockpiling, and also batch processing from the Segele ore body. This is what we've been working towards for, well, the last couple of years, and I would say, happy to say that we're finally there. We've successfully commissioned the processing plant. We have produced the first gold from the Segele ore body. Again, we have achieved daily mining operations and consistently moving ore from the mine to the processing plant. This is mostly what it's all about going forward. It's about, yeah, taking the ore out of the mine and bringing it to the processing plant and producing gold out of it.

Jørgen Evjen

executive
#2

It may sound like a pretty simple task, and it isn't the most complex one either, but the work we're doing is underground. We're operating in a mine, and naturally there are plenty of safety and other health concerns we must factor in while carrying this out. I'm pleased to report that we've also submitted an application for a new large exploration license. We need to begin looking ahead, making sure the company's future growth and sustainability are secured. Naturally, as Matt will walk you through, there are many, many interesting targets within our current license area, yet we must consider what lies ahead, and this area is a very, very exciting one for us to begin exploring. As you may have observed, the gold price is at a record high. Naturally, this affects our profits and our revenues. It will give a significant boost to our future mine cash flow. Still, as everyone knows, gold prices are capable of swinging, but at present the trend appears favorable for us and seems likely to remain at these levels as we move forward. We've also begun holding talks with financial, industrial, and strategic partners alike to look into possible cooperations. A key, well, a truly major event in Ethiopia was the successful introduction of financial reform, which arrived alongside the agreements with the IMF and the World Bank, and that meant the local currency was floated in Ethiopia.

Jørgen Evjen

executive
#3

Up to this point, the reform appears to have gone very well, and from our perspective as a mining company and a national company, that seems extremely, extremely interesting, and my hope is that it will serve as something of a fresh start for the Ethiopian economy. Key events. Dr. Matt Jackson — or Matt, as I prefer to call him — will unfortunately be transitioning to a new position outside of Akobo Minerals. He has spent several years with us, putting in hard work under quite difficult circumstances. We have collaborated closely on every different facet of this, of building up this company. He will definitely be missed, though he won't be departing entirely. He will stay on as our competent person and will also assist us considerably with strategic guidance and certain exploration-related work. So we're glad to keep him involved, albeit in a reduced capacity compared with today. Next slide. For anyone who doesn't know the company, I'll walk through a few of the more standard slides. As you can see here, our base is in Oslo, Norway. Our listing is on the Euronext Growth exchange, with trading on the OTCQX. We are a gold exploration mining company.

Jørgen Evjen

executive
#4

The sole asset we hold is located in Ethiopia, which makes us a pure-play mining and exploration company focused on that country. To date, the Segele mine is the one asset we have. Our mining and exploration licenses sit in the Gambela region. By now we have been operating there for over 14 years, and we enjoy excellent relations with every community and everyone in that area, so we have built a solid local presence. Doing things properly is essential, and properly is how we are doing them. So we have been present there and have truly made ourselves part of the community. And considering how the Ethiopian mining sector is structured — still only a handful of participants, yet with tremendous potential — we believe our position is unique and lets us grow into a major industry player in the years ahead. We also believe this region and our project hold considerable potential for gold production. As the map shows, we sit right up against the South Sudan border. It is a very pleasant, peaceful area. Since we began operations there, we have had virtually no incidents, major or minor. Our exploration license covers 182 sq km. Our mining license covers 16 sq km. We possess plants, machinery and equipment — some of it state-of-the-art and, I believe, among the finest processing plants available anywhere today, which will efficiently produce our gold going forward.

Jørgen Evjen

executive
#5

So here you can see the Segele mineral resource, as estimated by SRK. It isn't the largest resource around, but the grade, as you can see, is fantastic — among the highest grade anywhere in the world. This is a 68,000, 69,000 oz gold deposit averaging 22.7 g/t. The indicated portion, the part closest to surface, comes to 41,000 oz at an average grade of 40.6 g/t. That ranks among the highest grades found anywhere globally, which is why we believe there's real potential for high-margin gold production. And to refine our gold, once it's finally produced at site, we'll ship it to MKS PAMP in Switzerland — one of a handful of LBMA-approved refineries worldwide — where it gets processed into LBMA-approved gold bars and sold on the London bullion market stock exchange. Next slide, yes. We can't operate in a place like Gambela, mining and searching for gold, without a strong ESG policy. We've worked hard on this, and our hard work and good work have earned us recognition through various awards, along with collaboration with some of the best people in the industry.

Jørgen Evjen

executive
#6

We feel genuinely good about having a robust, well-founded ESG policy in place, and for me, doing things properly is the whole point — and that is exactly what we are doing. There is simply no alternative. As for the financial effect of this, you can tell from the fact that we managed to reach an agreement, or to become a partner and client of MKS PAMP. Without this, we would never have become their client, and selling our gold at a spot price in the market would not have been possible for us. We would have had no choice but to sell into a different market at a significant discount. All of this makes sense, first of all, because it is the right thing to do, but it also carries a financial impact that is really considerable. They have worked hard over the last six months, particularly on the operational readiness and compliance side, since we are now beginning production. They also followed up on the sustainable natural resource management plan and the health and sustainability schools program, along with continuous community engagement. We are active, and we are doing it right. To return to what I said earlier, the gold price is at a record high.

Jørgen Evjen

executive
#7

Right now it's, I believe, perhaps even past $2,600 an ounce. As the figures shown here make clear, that makes a big difference to cash flow and to what the Segele resource is worth as well. So when you consider the Segele resource valuation, on the basis of the gold price at the point where we began — well, began this project aimed at constructing the mine — at today's gold price it stands closer to $180 million. The same holds true regarding operational cash flow from Segele. So the value you see here rests on the financial model we used in the share issue earlier this year. And when you examine the various gold price scenarios under that same model, the cash flow value alone has risen by nearly $30 million since the start of the year. Naturally, then, the gold price exerts a major influence on cash flow from the Segele gold mine. So, the financial development during the year. Of course we, we still aren't earning — or we haven't earned any money thus far across the first six months. We're currently in the process of — and Helge will discuss this further — putting the second batch from the mine through the processing plant.

Jørgen Evjen

executive
#8

It’ll be interesting to see whether we can get a small gold bar out of that, but the financial development over the year has been the same as before. So, looking at what we’ve done this year, we carried out the financial restructuring and finished it earlier in the year. We brought in additional equity, we turned all convertible debt into equity, and we restructured the gold loan we had with Monetary Metals. So at this point, Monetary Metals is our only external debt provider. Everything else has been converted into equity. Of course, production and revenues from gold production going forward will have an impact on our financial situation. We have produced the first small batch of very low grade. The ramp-up phase is ongoing. As I said, the second batch is in production. It’s still hard to estimate how much gold we will produce in this current ramp-up phase, but we will come back to that when we have more knowledge and understanding from the first batches that we run and see what comes out. We do have a lower burn rate than previously anticipated, and with every day we are stockpiling and mining, we’re getting closer to breakeven.

Jørgen Evjen

executive
#9

Like I said before, we’ve been having discussions—and those discussions are still going on—with partners in finance, industry, and strategic areas, again, to look into possible cooperation, and that also covers short-term capital needs, which will strengthen our liquidity buffer. A few of these conversations have been running for quite a long time. They’re mature, and we’ll come back with additional details once there’s more we can share with the market. But these are exciting and very interesting dialogues that we’re working on. Thank you. So, Helge, over to you. Give us some operational updates, beginning with mining.

Helge Rushfeldt

executive
#10

Yes, thanks, Jørgen. There's a great deal of exciting activity on the mining side right now, and one very significant milestone we've just reached is that the first crosscut linking the Eastern and Western winzes — essentially the eastern and western sections of the mine — was finished on September 18. For us that's a major step forward on two fronts: for mine safety, since it gives everyone a second way out no matter where they are underground, and it also improves airflow and makes logistics smoother. Most importantly, though, it marks where stoping begins. We've also been doing work on the winze lengths, but going forward the main priority will be getting trial stoping underway. Right now we're simply making safe the newly blasted crosscut, and once that's done, we'll kick off the first trial stoping from this prospect drive. While carrying out the crosscut work, we hit several exceptionally rich ore zones with visible gold, so we're quite optimistic about what this first trial stoping can deliver. We've also faced some difficulties this time around.

Helge Rushfeldt

executive
#11

Let me start by saying that, despite these challenges, development has gone quite well—though we have still seen some delays, particularly at customs. Our procurement operation has improved considerably, yet delays still pop up from time to time at customs; it's somewhat random regarding timing and which equipment is affected, and that's something we're working on with the government. We've had a few extreme rain events again, and in the past that kind of thing almost crippled us, but now it's far less of an issue than it used to be. The heaviest rain we experienced—a truly severe rain event—caused us only about 1 day of delays because of additional pumping. So we've managed to resolve that problem fairly well, and we'll improve it even further going forward. Next. This is essentially how things stand right now with the winzes. If you can see, the green sections are what we've already been mining. So the Western winze and the Eastern winze are now linked by this green crosscut at the bottom, and as you can see, the crosscut runs very near what we refer to as the trial stope and the stope 01.

Helge Rushfeldt

executive
#12

At this point we can mine both stopes, or begin doing so, from this crosscut. The trial stope is what we'd prefer to launch with, since its grade is a bit lower, yet it works really well for putting the newly commissioned plant to the test. Running your best ore right at plant start-up isn't advisable, because you want the plant optimization finished and the recovery rate sitting high, yeah. So the key mine metrics come down to the resource we've discussed previously. With the current model, we have a conservative 81% extraction rate for the mine, yes. We'd also like to note that our mineralization remains open at depth. So when we've mined out what the model currently contains, what happens then is a rather interesting upside for the future. Yeah, next. So this is exactly how it appears underground when they blasted through this crosscut, going from the Eastern winze and then through to the Western winze. So this marks the first time anyone walks through. Psychologically and physically, it's a major milestone, and it genuinely improves the mine's safety and logistics as well.

Helge Rushfeldt

executive
#13

All right, let's turn to the processing plant. I'm quite fond of this photo — it shows the facility at dusk, lights blazing, with everything in place. Essentially, we've now arrived at a point where the commissioning of the existing setup is finished, the first gold has been poured, and we're shifting our attention to enhancements, processing, and recovery across each step of the flow. A bit more detail: here you can see the mill rotating, and in this image it isn't merely spinning — it's grinding gold ore as well. So what we've done lately is commission each of the 5 generators located on site and link them together, giving us high load capacity plus redundancy. That means should 1 generator fail, the remaining 4 will ramp up and cover it. Commissioning at the plant is done, and the facility has additionally been converted to batch operation. The rationale for switching it to batch operation rather than continuous operation is that, in our view, some time will pass before we can pull sufficient ore from the mine to supply it nonstop. Having the plant available far more often is the benefit if we begin with this batch operation, and that's exactly what we're doing at present.

Helge Rushfeldt

executive
#14

We've already put the initial ore batch through the plant, all the way to smelting. That's the approach we'll take from here on. We'll finish the lab building as well and get the lab fully functional — that area has fallen somewhat behind, but we're now moving toward expanding our capabilities there, along with all the testing we'll conduct and the samples drawn from both the mine and the plant. All right, so first gold produced. In the picture you can see the ore as it appears before being dumped into the crusher circuit and sent to milling, after which it moves to gravity, then into ILR, then electrowinning, and smelting, which appears in the bottom left picture. And the initial result is what's shown there. That came from the first batch. It's fairly low-grade ore, so consequently there's just some gold — call them pearls or droplets — rather than a full bar, yet it's a proof of concept, which matters greatly to see, that every stage and every step of the process truly works. So this is the first trial batch.

Helge Rushfeldt

executive
#15

I've spent over 20 years in mining, and I've started up a number of plants. Honestly, I'm surprised by how much went right on the first attempt at this plant. Anywhere on earth, launching something new like this brings some problems, yet the issues we've hit on site have actually been quite few. With the local competence and the local people, we've managed to fix things fast. So at present, as we mentioned, the current process setup has been commissioned. We've run the initial trial batch. The first gold has been produced, right through to smelting. Moving ahead, we're already making a bigger batch with richer ore. That's been produced, and we're waiting to put it through the ILR, a cyanide process, and then onward to electrowinning and smelting. Before long, we'll have the next result from that, which will be very exciting to see. Our plan is that as we move forward, batch sizes will go up in line with the higher output from the mine once trial stoping begins.

Helge Rushfeldt

executive
#16

With the trial stoping, we think that would raise the ore volume quite a bit versus what we've been doing up to now, which is closer to development feeding into ore. On top of that, we're optimizing every stage of the plant for greater efficiency, so total recovery will go up — meaning more gold we can extract. We also take the approach of continuously developing the organization to match what the plant requires. So as the plant gets bigger and the batch gets larger, we'll grow the organization as well. The key people we need are in place; we'll simply need to add to that as we move ahead, yes. Then I believe it's over to Matt.

Matt Jackson

executive
#17

Thanks a lot, Helge.

Helge Rushfeldt

executive
#18

Thanks.

Matt Jackson

executive
#19

Thanks. It's good to be back again. This slide is just a brief one covering exploration activity during the first half of 2024. As the earlier slides showed, an enormous amount of work has been going on at the mine, and most of the company's resources have gone toward developing the mine and reaching the point where we are today. Because of that, exploration and the attention paid to it have been kept to a minimum. Still, some work has taken place, and I'm very proud of the exploration team and what they accomplished during this period. They've been trenching near West Segele. They've been drilling holes — some quite exciting ones, actually — near the Segele gold mine, and they've also finished 70 line kilometers of magnetic surveying. All of this work has the potential to unlock new mineralized zones close to the Segele gold mine, which has us very excited and will clearly make a significant difference to the company's economics and its growth potential. So the work done in the first half of the year and in Q2 has been truly excellent, and we're very pleased with it.

Matt Jackson

executive
#20

And it sets the stage for some great discoveries down the road, so but the bulk of this presentation is going to cover why we're enthusiastic about exploration in the area. And Jørgen talked about a license application we've filed that cements our growth ambitions going forward. So just as background for anyone who hasn't seen these presentations before. The Segele gold mine and our exploration areas sit within the Arabian-Nubian Shield. A great deal of exploration is taking place in the Arabian-Nubian Shield. The majority of it is in Saudi Arabia and parts of North and East Africa where we have no involvement. Some enormous companies operate there. There's Ma'aden in Saudi Arabia, which has very large gold production. They also work together with the major gold miner Barrick to produce copper in those areas. There's also the prolific Sukari mine, owned by Centamin in Egypt, which has resources and reserves of over 15 million oz, and almost 500,000 oz of gold produced every year in those areas. Not many parts of the world are this prospective and have not been really investigated by large mining companies, so we're very lucky and very proud to be one of the most exciting companies working in this area.

Matt Jackson

executive
#21

Okay, if we go back to the prior slide, you'll notice we're focused on the yellow-boxed region, which is western Ethiopia. This next slide displays the dark green zone up north, where Allied Gold is preparing to spend hundreds of millions of dollars to develop the Kurmuk Project. KEFI Minerals is likewise putting in substantial effort toward committing a comparable level of capital expenditure for its Tulu Kapi project. So in the northern portions of this slide, a fair amount of work has taken place. And many years back — 20 years ago now — I finished my PhD in this region, so I have a solid grasp of the geology. Around the Allied Gold project and the Tulu Kapi project, a good deal of exploration has occurred. Those areas still hold more to be discovered, but in the Gambela region, within the same rock package and the same part of the Arabian-Nubian Shield, I know as a matter of fact that investigation there has been extremely limited — in fact, almost none. Some regional work has been carried out, a bit of regional mapping, which honestly reveals very little about the geology, yet we know the gold potential there is highly exciting, since we operate the Segele gold mine, which has some of the highest grades globally, along with the other exploration targets we hold, particularly at the Segele gold mine.

Matt Jackson

executive
#22

Our team in Ethiopia, with Bezabeh at the helm, stepped up and submitted an exploration license application that we refer to as Gilo. The Ethiopian team deserves genuine praise for this, since they demonstrated real initiative. They identified an open area with good prospectivity. The very same structures that host the Segele gold mine in the south extend all the way north into the Gilo license, and they run right past the Tulu Kapi gold mine, which holds 1.7 million oz. That region — this whole region inside the yellow circle — as I mentioned earlier, is one we've barely examined. So we're in a truly excellent position to leverage our first mover advantage in the Gambela region, where we've operated for 14 years, in order to open up this part of the Arabian-Nubian Shield for exploration. As far as we're aware, only one drilling program by another company has taken place across this entire region, and that company was forced to halt for logistics reasons, whereas we can keep operating. We have relationships — very strong relationships — with the Gambela region authorities, so we're highly confident in our capacity to explore here, and we're very excited about the discoveries that can be made, because we know this area hasn't been examined before and it has all the right structures.

Matt Jackson

executive
#23

Now, if we take a closer look at the Gilo license, the purpose of this slide is simply to show you roughly where the license sits. It's still an application at this point. It hasn't been granted yet, though naturally word will get out the moment it is. A single road runs through it. A river also passes through it, which gives us access to the area. We're able to reach it. For exploration, we can make use of both the river and the road to open things up and take a look. It's uninhabited savannah grassland. From what I can see, no settlements exist there. Perhaps there are very few settlements, yet access remains possible thanks to that road. So it's 1,220 sq km of unexplored greenstone belt. There is. By the term greenstone belt, I mean a phrase geologists apply to a particular suite of rocks and the kind of alteration found in regional areas that hold promise for gold and other minerals worth exploring for. And genuinely unexplored greenstone belt exists in very, very few places around the world. If you looked at other junior mining companies, they might claim to hold unexplored or underexplored stretches of greenstone belt, but the reality is that two or three companies may well have come before them and previously held those licenses.

Matt Jackson

executive
#24

As we begin operations here, we're confident that we'll be the first to ever explore this area, so that's really exciting. And, you know, with the Segele mine now close to breaking even, we're confident we'll have the resources required to truly open up this area and make the discoveries we're confident are there. This slide briefly covers the potential of the Akobo license. Now, going forward, we'll be discussing the Akobo license, exploration within the Akobo license, and exploration within the Gilo license, but returning to the Akobo license, we remain very excited about this area. Just last week, I visited the Gingibil area and other targets in the license together with an independent international expert, and we're very excited about the area around Gingibil and Korarima and Mitmitta because these are essentially bulk targets, what we call bulk targets, which are, unlike Segele, big quartz veins that have much lower concentrations of gold than Segele but nevertheless the kind of concentrations that can be mined by open pit. So very simple, straightforward, and cheap exploration methods can be used to uncover the potential of these areas.

Matt Jackson

executive
#25

We're really looking forward to getting that work underway once the company's priorities shift, and that shift is going to come very soon. On top of that, we continue to see fantastic results from Joru Central, where drilling took place previously. High-grade intersections exist there. High-grade potential also exists at Joru South and in other spots around the project. So we've got our own drill rig. Exploration can be done cheaply. The logistics are in place. As a lot of our shareholders are already aware, this has been on hold for some time now so that we could get the Segele mine going, but this presentation makes that point very clear. We've reached the stage now where the Segele gold mine sits in a very good position and, you know, production is going to make a huge difference to our financial situation, so we're very excited to keep exploring here and to find out what we call bulk targets. This slide shows what makes us different from other junior mining companies. A lot of junior mining companies, as I mentioned earlier, might be exploring areas where discoveries have already been made by companies or where exploration has happened before. Every one of these dots here represents a target that we think has the potential to become a mine.

Matt Jackson

executive
#26

It's true that not every one of these targets is going to become a mine, but the truly strong explorers are the ones with lots of dots sitting in that funnel. That's really no different from the sales funnel you'd see at other listed companies. Our aim is to move as many of these projects as possible along through advanced resource definition, drilling, feasibility studies, and infrastructure development. That comes down to careful prioritization of them, but beyond that, to really boost the odds of success, we need many more dots going into this funnel. Discovering 1.5 million-2 million oz has us genuinely excited, particularly in the Akobo license, yet to truly capitalize on our first mover position in Gambela, which is a completely unexplored area, we plan to add far more dots to the concept beyond the Gilo license, plus other Arabian-Nubian Shield targets outside of the Akobo and Gilo licenses. In the period ahead, we'll be moving them toward desktop and target generation, and as soon as finances permit, plenty of these targets can be prioritized and drilled. The right people, the right equipment, and the right logistics are all in place for us to do this.

Matt Jackson

executive
#27

And the expert review we had last week, you know, confirmed how excited we are about this. So the step we've taken over the last few months to submit an application for the Gilo license just demonstrates that intention and our plans to push this forward. So looking strategically at the next few years, how are we going to do this? What are the plans? Needless to say, we'll be working at the Segele gold mine for some time now. Our exploration team has been developing near-mine targets to grow the production that can go into the process plant as much as we possibly can, so that drilling will continue. It's happening now, and it will continue. We'll also be — many of our shareholders will have heard the terms Gingibil and Joru and Mitmitta and Korarima and Wolleta. We've decided that all these targets will be explored together. There are some very effective exploration geophysics methods that can be used. And then we'll carry on doing the shallow drilling that we have done before. We'll even do trial mining of the surface, of the loose gold-bearing rocks at the surface. Once we get the mining license extended, that can be put into the Segele gold mine as well.

Matt Jackson

executive
#28

Naturally, a few technical studies still need to be completed regarding this. We're quite optimistic that the bulk targets at the Akobo license can genuinely deliver something that will propel the company's value forward in a fantastic manner over the years ahead. After the Gilo license receives approval, we will in fact keep pursuing additional license acquisitions within the area. We'll also be launching airborne geophysical surveys along with reconnaissance exploration, applying every method that our fantastic Ethiopian team employed to discover the Segele mine. We'll be pushing that forward over the next few years and steering it toward resource drilling. We're excited about uncovering 1.5 million-2 million oz within the Akobo license bulk targets area. And in the months ahead, we'll likewise be expanding toward Gilo. And we're very, you know, we're very optimistic and very eager regarding the opportunities to truly drive value in the company. So this marks my final quarterly presentation. I will remain involved with the company, offering strategic direction on exactly what we're examining here in order to guide the Ethiopian team in advancing these projects and growing the company's value.

Matt Jackson

executive
#29

I remain, and always will be, the biggest supporter of Akobo Minerals, and going forward I will certainly stay closely engaged with the project. That said, now that we can see the Segele mine is the success we always believed it would be, the moment has come for me to move on and take a different position at another company. Even so, as I mentioned, I still have the ability to stay involved here and to give the strategic guidance required to reach what appears on this slide. So many thanks, and I will pass things back to Jørgen for the final slide.

Jørgen Evjen

executive
#30

Thank you, Matt. Yeah, I doubt that's the final time we'll be hearing from you. So, to wrap things up: our strategy remains clear. We're executing on the near-term plan — bringing the Segele mine online, which is happening right now as we speak, moving gold production into the ramp-up phase, and building the steady day-to-day output we're seeing today, but at a larger scale as well. Then, coming back to what Matt mentioned: honestly, the upside still sitting in this company is everything we see across the licensed area, plus the new license we've applied for. There's definitely potential here to build an attractive resource base at a significant scale. That remains the plan right now, and it's something we want to focus hard on — getting exploration back on track. Again, on the long-term vision, we still see the opportunity and the possibility of becoming the leading mining company in Ethiopia. There are a few other players, as you saw on the map Matt had — Allied Gold and KEFI Minerals. They're in the process of establishing their mines. Naturally, that will take a few years before they're up and running, but the area and the potential in Ethiopia as such tells me this is not — this has nothing to do with competition.

Jørgen Evjen

executive
#31

It comes down to competence and the fact that you understand how to operate in Ethiopia and have gone through every phase that we've gone through. That's where the real value lies. And there's lots of land, and there's lots of opportunity in Ethiopia. It's entirely unexplored. If you compare Ethiopia with other nearby African nations, its potential has not been tapped at all. We're very much looking forward to getting exploration back on track and letting the mine do what it's meant to do by producing gold and cash flow for us. Okay, I believe that covers that. On the financial side, there isn't much to say. We're still in the process of the first half year of developing the mine. We've had only costs, no revenue. You can see here, of course, that there's some change in the operating costs. There was some higher cost in Q2 compared to Q1. That relates to the activity level and finalizing of the plant. We see, as I said earlier, that the cash burn in general is lower than what we expect, and especially now that we see the company getting into a more steady-state production, then it'll be easier for us also to make better estimates on the cash flow going forward once we're in a more steady-state production.

Jørgen Evjen

executive
#32

On the equity debt side, that mirrors the most recent restructuring we completed. All we had left was the Monetary Metals loan. At a group level, there's negative equity, which as such has no impact and doesn't carry any consequences, so there's nothing to worry about there. Naturally, our goal is to get that positive, but nothing is required of us on that front. Matt, <<inaudible>>. Turning to the corporate structure, we remain listed on Euronext Growth in Oslo and the Frankfurt Stock Exchange. We trade on the OTCQX market platform in New York. Once again, a strong group of active Norwegian shareholders stands behind the company. Most of them have been with us since inception. The top 20 shareholders barely shift. In fact, there is no change. They stay with us and are supportive. Beyond that, we have roughly 3,000 retail shareholders across Norway and Sweden. The gold loan from Monetary Metals now stands at 7,300 oz, and that's, yeah, once more, the Monetary Metals U.S.-based investor that has lended us. That we, yeah, this dates back to the start of the Segele mine. It formed part of the financial package that got the project going. Okay, I think the remaining figures here you can review in detail if you'd like to.

Jørgen Evjen

executive
#33

And if you have particular questions about the numbers, feel free to send me a message or shoot me one—though honestly, there aren't any major shifts in what we're doing. We operate this business very lean. There is no excess cost whatsoever on our side. Every dollar we spend goes toward Ethiopia and toward the project, as we try to keep overhead as lean as we can and work really hard to reach a cash flow position—a cash-positive position—as soon as possible. So, on to the Q&A. Some questions have come in.

Matt Jackson

executive
#34

There are a few things we'd like to ask about.

Jørgen Evjen

executive
#35

I think, Matt and Helge, are you with me to answer?

Matt Jackson

executive
#36

Yeah. Should I go ahead and read the questions out loud?

Jørgen Evjen

executive
#37

Sure, I can begin with a couple of things. Questions have come up regarding the true size of the resource. "We're referring to the SRK resource estimate of roughly 68,000 oz. In our financial modeling, it comes in a bit lower." So let's tackle that while we're watching some good videos of ongoing production at Segele. I hadn't seen this before, and it grabbed my attention, but I'll do my best — we'll do our best — to respond to it. Matt, since you were involved in the scoping study and all the early work we did, perhaps you could just walk through the 68,000 oz. It may be more, and of course it may be less. That depends on how we mine it and how we bring it up. But if you'd like to offer a brief comment.

Matt Jackson

executive
#38

Right. During planning, before construction began, we made a strategic choice to keep our estimates on the conservative side as we planned with this. That's for every reason you'd likely anticipate. So the resource estimate from SRK was itself fairly conservative, but we figured it's normal, when mining underground, that you don't extract the whole resource. So in the scoping study, we decided, based on comparisons with other mines, that 81% of it would be extracted. And that, as I said, is conservative. So we effectively took out 19% of the resource from it to allow for some of the rock basically being left underground, for safety purposes, to support the mine from the inside. Even so, given what I know about the project and the technical details of the rock structures and the rock competence I've seen, I'm very confident we'll extract at least some of the value from that 19% left in the ground, or perhaps even all of it. But right now, it's best that we do our financial planning on essentially leaving that 19% in the ground, yeah. But obviously, at the end of the mine, at the end of the planned mining cycle, the company will obviously look at extracting as much value as possible from the mine before it is closed down.

Matt Jackson

executive
#39

Even so, the point at which the mine gets shut down remains quite distant, since we hold numerous exploration targets, it stays open at depth, and substantial opportunity exists to keep mining, yeah. That probably covers it, I think.

Jørgen Evjen

executive
#40

Yes. Yes. So that was, yeah, that was actually the follow-up question — namely, how long is this mine going to keep on mining. And from a general perspective, once you've started the mining, you know, they tend to. Is it like in the oil industry that we see here in Norway, that once you hit the discovery, it tends to increase and you find more veins or you find more gold in vicinity? And you continue developing the mine over the years even though this first resource estimate, very first resource estimate, is, you know, we have a three, four years of mining. But I, the question is, will this close down in four years?

Matt Jackson

executive
#41

Of course, we can't make any promises, but the reason we're drilling so close to the Segele mine at the moment is that we believe there's mineralization—additional mineralization—in that area. I mean, we actually know additional mineralization exists there. We simply don't know how big it actually is. In earlier presentations, you'd have seen signs that we've carried out sampling in artisanal pits located very near the mine, for instance, that produce really strong results. You know, no resource estimate has been completed on that. We can't provide figures for how much mineralization is there. We know something is present, so drilling will take place close by the Segele mine that we're excited about. It's underway right now. And then there's the West Segele area, where we're also seeing signs of rocks that closely resemble those surrounding the Segele mineralization. And in earlier presentations, again, you'd have seen that, in one of those areas roughly 1.5 km from the mine, we even pulled a 24 g nugget out of what we call sheared ultramafics that are very closely tied to the Segele mineralization. So we're excited about that, and we believe more targets are going to open up and turn into new resources, and that will extend the mine life of Segele.

Matt Jackson

executive
#42

And then, as I said, at Gingibil there are those shallow, loosely consolidated rocks that we refer to as the Akobo bulk targets. A portion of that material can likely also be processed through the Segele plant. We have strong confidence that the mine life will keep going for quite a while. Beyond the Segele mine simply running, the plan is for us to achieve a significantly larger discovery, which would mean, you know, a very substantial expansion of mining activity in that region, yeah.

Jørgen Evjen

executive
#43

Again, it's worth pointing out that it stays open at depth — meaning we've drilled holes showing mineralization considerably deeper down. I'm no mining expert, but once we get further down into the tunnels at the Segele mine, we'll then begin drilling from those tunnels rather than from surface, right, in order to keep developing the mine deeper, correct?

Matt Jackson

executive
#44

If it’s possible at all, yeah, mm-hmm, yeah.

Jørgen Evjen

executive
#45

Alright. I have another question that came in, and it's a broader one: why is this taking so long? That's a fair question. Of course, it may have to do with how we on our side have managed expectations, but even so, this project has in fact been carried out in what is almost record time. Helge, you mentioned that you've worked with processing plants nearly your whole life. Perhaps you could say a bit about what we've actually accomplished here. And this isn't a small project of the kind you see on Discovery Channel and elsewhere, so maybe you'd like to elaborate on that a little.

Helge Rushfeldt

executive
#46

Sure, I can do that. On those Discovery Channels and with those gold miners, usually they bring a small lorry carrying some of that compact equipment, and they can begin straight from the surface. This is a totally different matter. This is a purely underground mine, and it requires a complete mining crew along with full mining infrastructure. As you can see in this video now, it is a plant constructed like a modern processing facility, with the capacity to process 10 tons per hour of material. So the setup is completely different. One more thing I want to mention: quite often, when you build a mine, say in Norway, Canada, South Africa, and so on, you have infrastructure and everything surrounding you. Here, we have essentially constructed an entire mine and a full processing plant in the middle of nowhere at all. There is no electricity in that area, there was no water, there is nothing, so that also adds to the difficulty of starting up, but it is something we have managed to accomplish in a very short period of time. And as I mentioned earlier, whenever you start up any factory anywhere in the world, there are always issues and always problems.

Helge Rushfeldt

executive
#47

Honestly, I'm genuinely surprised by how smoothly things have gone and how quickly we've been able to resolve the minor issues we've run into up to now.

Jørgen Evjen

executive
#48

Great. I think we can also mention — or I can — that just for comparison, it looks like KEFI Minerals is getting closer to their production, or not production but to the start of their project, but they received their mining license in 2015. So depending on the project, depending on where we are, depending on a lot of factors, that will have an impact on how fast you can actually progress these projects. If you look at Allied and KEFI and their project right now, if you compare it to what we've done, of course, it's a bigger operation, but still we're talking about several years of development before they will even get into any kind of production. Of course, we all want to see this producing tons of gold every day and as soon as possible, but it is a process. But now we have all the tools and we have everything ready. It is in operation. We are mining, and to put it a bit, well, the simple one here, it's now about logistics from the mine to the plant, get as much ore out and produce it. Not very complicated, but still it has to be done in a safe and efficient manner, and given the high value of the gold, you don't wanna lose anything on the way here.

Jørgen Evjen

executive
#49

You need to fine-tune the system and make sure it's efficient, so we can approach the 80%, 90%, or 100% recovery rate we're aiming for. Yes, I believe some of the questions I received were about that. Matt, I have one more, and it relates to exploration going forward. If you'd like to touch on the XRF system we have in place, now that we're starting to drill, and the fact that we don't necessarily have to wait several months to see results or ship samples to ALS or other labs to get exploration results back.

Matt Jackson

executive
#50

Yes, absolutely — we did bring this up during earlier presentations. There's a system we use, detectORE, made by Portable PPB out of Western Australia. It's a very new company, and it's been collecting innovation awards. It's among the rare ones — in my view, it's one of the rare breakthroughs in rock analysis that's going to transform the industry. Basically, what it allows is getting genuinely high-quality gold analysis finished at site within 24 hours. In the past, as our shareholders who've been with us for years are aware, whenever we drilled core and hit those bonanza grades, we had to ship it to Addis Ababa for preparation and then on to Ireland for analysis, and roughly two months of turnaround time passed before we actually knew the grades. With the system we've now got up and running at site already, producing analyses for us, turnaround currently runs a few days — you know, from kicking off that analysis to getting the number back. And eventually it will come in at around about 24 hours. It can deliver results from soil sampling and from rock sampling too. And it speeds up how long it takes to advance, you know, an exploration target to the point where resource definition begins.

Matt Jackson

executive
#51

Right now, we still understand that for resource definition we’ll continue to need the standard lab process outside Ethiopia, but getting a target to the point where resource definition begins can now be many months faster than it used to be. So we’re among the first companies globally to be using this system. And it’s, you know, it’s operational. Our laboratory manager is using it, and so far, we’re really pleased with the system.

Jørgen Evjen

executive
#52

Yeah, great. Matt, there are a few questions we also got that <<inaudible>>.

Matt Jackson

executive
#53

There are quite a few questions coming in here, actually.

Jørgen Evjen

executive
#54

Yeah.

Matt Jackson

executive
#55

We are at exactly 1 hour now. Should we continue?

Jørgen Evjen

executive
#56

Correct.

Matt Jackson

executive
#57

Alright, good. So there’s a question here asking, "These regions are impacted by civil war. How are you handling things in and around those problems?" Maybe I can speak to that. That falls within my area, more or less.

Jørgen Evjen

executive
#58

Yes.

Matt Jackson

executive
#59

Sure, there are certain parts of Ethiopia dealing with civil war. The closest one to where we operate sits hundreds of kilometers away. In Gambela, we've never encountered civil war issues. Crime does exist around us, of course. We've got quite solid security arrangements in place, though I won't go into detail about them here. The Ethiopian Federal Police back us up substantially, giving dedicated protection to our operations. Once more, our region has no civil war problem. It's never happened for us. One could argue it's the calmest part of Ethiopia. Personally, I feel quite safe whenever I'm there, and we've never run into any trouble in that area. Beyond that, we monitor the security picture closely at both the national and regional level across Ethiopia, and nothing suggests any worsening is coming. That leaves us very pleased. Should I go on to the following one?

Jørgen Evjen

executive
#60

Yes.

Matt Jackson

executive
#61

What's your view on how the gaps in gold exports from Ethiopia can be addressed? If I'm mistaken, please correct me. In Ethiopia, gold may be sold to the National Bank of Ethiopia at a premium above the bank rate. Does that make it workable? Perhaps Jørgen? This is your area of expertise.

Jørgen Evjen

executive
#62

Once more, we're moving forward. There's an opportunity and a possibility for us to export our gold. There are various methods by which the gold can be sold. Naturally, we could sell it to the national bank, but considering the value or the manner in which we're producing the gold, it makes sense for us to export it and have it refined at the MKS refinery in Switzerland. All of this forms part of our agreements and is part of the setup. And there's really nothing—not an issue at all with that—so it makes sense to produce this into an LBMA-approved bar. So yeah. But we also have the opportunity to sell directly to the national bank if we want to.

Matt Jackson

executive
#63

All right. Should I move on to the next question, then?

Jørgen Evjen

executive
#64

Yes.

Matt Jackson

executive
#65

Okay. First question: who's taking over from Matt? And is there anything new on AISC costs? Let me say a bit about myself. Much of what I've done over the past few years — since joining full time, and before that as a consultant — includes writing the Competent Person's Report and providing strategic advice. A great deal of that work involved collaborating closely with Jørgen to expand the company, get the Segele mine operational, handle all the contracts and related work, set up structures, manage those structures on the operational side, and of course assist on exploration. As for actually running the company day to day, we've already implemented changes enabling us to function very efficiently with a strengthened Ethiopian management team. Those systems, I'm quite confident, will work. So apart from that, there's no need for a replacement in that sense. On exploration, I'll clearly continue providing direction remotely. Not remotely — I'll remain very involved with the project.

Matt Jackson

executive
#66

Prior to going full time, I was consulting for the company as well, so I see this as somewhat returning to that type of setup alongside my other new position. Now, regarding AISC costs, Jørgen, would you like to address that? Is that something?

Jørgen Evjen

executive
#67

Yeah. Yeah, I'll add a quick note on our plans as well. Outside of Ethiopia, we won't be bringing on additional staff. What we'll do is reinforce our on-site expertise. Also, we've entered into agreements with several top consultants and specialists who will handle much of the work Matt previously did, but they'll be based nearer to and directly at the site. That's the place where value gets generated, and that's the place where the daily work happens. So we'll build up capability within Ethiopia and at the site, at the mine, essentially to ensure we make solid progress there. So that's all. On the cost front, the scoping study showed very low all-in costs. In our most recent financial modeling and the share issue from earlier this year, we were, I'd say, somewhat more conservative, and it came out a bit higher. We're now seeing costs below what we expected. It remains a little premature to draw a firm conclusion about where this ends up. We need to reach a steady state, but if I had to suggest a direction, likely somewhere between the figures we've previously published.

Jørgen Evjen

executive
#68

It's still going to be a very low-cost operation, that's for sure. The industry average, I think, is now getting closer to $1,300 per ounce. We'll be far from that, so it will be a very cost-efficient operation. Any more questions?

Matt Jackson

executive
#69

All right, so we do have several questions that also tie into security, so I figure we should tackle all of them at once. Let me go ahead and read them out.

Jørgen Evjen

executive
#70

Alright.

Matt Jackson

executive
#71

Then someone asks how we plan to move the gold, considering the security conditions in Ethiopia and in Wollega. I'll address that shortly. "Will you require a standard gold bar before you can make your initial shipment and get paid? That looks like quite a distance to travel from little gold droplets." We can cover that too, but also, what about security around the stored and refined gold, all the way from storage through transport to the broker? So let's go through Wollega and security, plus the transport arrangements. Now, Wollega. For those who don't know, the person posing this question is asking specifically about the security situation surrounding the Tulu Kapi gold mine. Things are quite different in Wollega. The security picture there is very, very different from where we are right now. It's also not nearby. There's no direct road. You can't head straight from our site all the way north to Wollega. You'd have to go nearly back to Addis and then across again. So Wollega isn't close. It's a different region. The security situation isn't the same. And as I mentioned earlier, we feel very comfortable and very pleased with the way security is set up at our site.

Matt Jackson

executive
#72

And, you know, the fact that we've built a working gold mine shows this, so needless to say we're very pleased with that, and we have the ability to ship whatever quantity of gold we like. It doesn't have to be a standard gold bar of some kind. Whatever amount we want, we can move it. Obviously, every movement of gold comes with a cost. I'm not going to discuss the details of how the gold gets transported or our security setups for any of this, but it has been arranged that a well-known, internationally recognized shipping firm that operates in Ethiopia will handle shipping the gold, and it will take the gold all the way from our processing plant through to the refinery. Again, the Ethiopian Federal Police will support them, and in my opinion they are the best armed security force in the country. And I have. You know, our security manager knows the procedures well. All the procedures are in place. They work. I've checked them myself. And the security manager is heavily involved, so we're entirely confident in the processes. And from one ounce up to thousands of ounces, we can ship any amount of gold.

Matt Jackson

executive
#73

That’s not a concern for us in any way, yep. So there are a number of security-related questions. Here’s one, in Norwegian, about the share issue. <<foreign_lang>>? So it’s asking when the next share emission will be. And at what level will it be carried out? I suppose, Jørgen, that one’s for you.

Jørgen Evjen

executive
#74

If and when that happens, the market and all shareholders will hear about it simultaneously. So from my end, there’s genuinely no speculation on that point.

Matt Jackson

executive
#75

And that's really all there is to it, I'd say.

Jørgen Evjen

executive
#76

Alright.

Matt Jackson

executive
#77

Thanks.

Jørgen Evjen

executive
#78

All right. We've run a bit past our time, but the questions were worth taking, and I hope everyone now has a clearer picture of what we're doing, where we stand, and will keep following Akobo Minerals' progress. And thanks to all of you for joining. Thank you, Helge, and thank you, Matt, for taking part. And yeah, that's all for now. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Akobo Minerals AB (publ) transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Akobo Minerals AB (publ) earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Akobo Minerals AB (publ) or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.