Leila Dillon

executive
#1

Thanks, Dustin, and good afternoon to all of you. We're glad you could be with us on today's call. Joining us as speakers will be George Sakellaris, who serves as Ameresco's Chairman and Chief Executive Officer, along with Mark Chiplock, our Chief Financial Officer. Also, Josh Baribeau, our Chief Investment Officer, will be on hand throughout Q&A to assist with answering questions. Prior to handing things over to George, I'd like to offer a short statement about forward-looking remarks. Forward-looking statements, among them statements about our expectations, appear in today's earnings materials. Risks and uncertainties apply to all forward-looking statements. For a discussion of the major risk factors that might cause our actual results to differ from those in our forward-looking statements, please see today's earnings materials, the safe harbor language on Slide 2 of our supplemental information, and our SEC filings; beyond that, we use several non-GAAP measures when presenting our financial results. Reconciliations to these measures, plus additional information, are included in our supplemental slides that were posted to our website. Be aware that every comparison discussed today is on a year-over-year basis, unless otherwise noted. I'll now turn the call over to George. George?

George Sakellaris

executive
#2

Thanks, Leila, and good afternoon to all of you. To start, I want to express appreciation to the whole Ameresco team as we mark 25 years since the company was founded. It has been a remarkable ride, building Ameresco into a leader in our industry and delivering more than $16 billion in customer solutions focused on cutting energy consumption, strengthening energy infrastructure and resiliency, and creating proven pathways toward decarbonization. Even though conditions right now are difficult, the forces driving our business stay powerful. Demand for power around the world is climbing, electricity prices keep going up, and grid reliability keeps getting worse, as we witnessed in Europe just a few days ago. All of that is going to boost the need for distributed, diversified, resilient energy solutions. The team's exceptional execution produced a strong beginning to the year, with results beating what we expected. In the first quarter, revenue and adjusted EBITDA rose 18% and 32%, respectively. Those results also showed how strong our diversified business model is, since we saw meaningful growth in both our projects business and our energy asset business, including solid performance in Europe and Canada. We also lifted our total project backlog to nearly $5 billion, which brings total revenue visibility across our businesses to almost $10 billion. It was yet another quarter of substantial success in converting contract execution, producing a contracted project backlog of $2.6 billion, which represents a growth rate of nearly 80% year-over-year. And those favorable business trends have carried over into the second quarter. I also want to address some of the widely known difficulties our industry faces and share some perspective on how the Ameresco team is working to get past them. Let me begin with our work with the federal government. That business makes up roughly 30% of our current total project backlog, with military-related customers representing approximately 2/3 and GSA or civilian agency-related project work representing approximately 1/3. We have included a breakdown of our backlog by end market in our supplemental slides. Since these federal contracts have multiyear execution cycles, they should represent less than 30% of our 2025 project revenue. We mentioned on our last conference call that we had run into one cancellation on a project contracted earlier in January and a pause on 2 other contracts. We are happy to report that the project that was canceled has now been rescoped, and the other 2 contracts have now been unpaused. In addition, we have not run into any further cancellations or delays in our federal contracts. So although it is too soon to claim there will be no further disruptions ahead, we are cautiously optimistic. And as the current administration's priorities become clearer, we believe our broad and deep technical expertise in our agnostic and budget-neutral approach will help us promote our offerings. Interestingly, we are now seeing a significant number of recently issued federal RFPs focused on our core competencies of resiliency and increasing the power supply through new energy infrastructure. The government recently put out a request for information regarding potential use of Department of Energy land to meet rising data center demand. After that, DOE pinpointed 16 sites that are uniquely suited for building data centers quickly, with energy infrastructure already in place and the capability to expedite permitting for additional power generation. As an illustration, we're finding more chances to make use of federal acreage for important energy infrastructure work. A great demonstration of this approach is the Kupono project — 44 megawatts of solar plus a 44-megawatt battery; at Pearl Harbor, we used an enhanced use lease with the Navy to construct this vital energy infrastructure serving both the base and Hawaii's electric grid. At the same pace, we're also building a 99-megawatt firm power plant along with an advanced microgrid project. With the Department of Defense, we're employing comparable arrangements, enhanced use leases among them, to create data center energy infrastructure projects. As shown on another new slide in our supplemental deck that breaks down our project backlog by technology, Ameresco has a highly diversified set of expertise spanning efficiency, resiliency and power production solutions. Roughly 50% of our overall project backlog consists of energy infrastructure projects that use generation technologies like gas turbines, engines, solar, hydroelectric, plus resiliency technologies such as large-scale battery storage and microgrids. Our solutions, we believe, fit well with the changing energy landscape, which calls for ever-growing quantities of electricity and greater resiliency; we're quite enthusiastic about what lies ahead for our work with the federal government as well as all our customers throughout our core markets, among them utilities, data centers, co-ops and large C&I. I also want to talk about the shifting tariff environment that we, just like every other firm in our sector, must contend with. To begin, I'd note that a large share of equipment for projects currently underway and energy assets under development has already been procured and is either inside the country or already at the job sites, which we think protects us against near-term price hikes. Over the longer run, we'll strive to lessen price increases through contract negotiations and reprice wherever we can; it's worth noting that most of our solar and battery projects are international, so they aren't subject to U.S. tariffs. As a lot of our shareholders are aware, Ameresco has dealt with tariffs and inflation before, and we've come through comparable tough pricing conditions. We hold strong ties with both domestic and global vendors and have a solid project backlog, which gives us a position of strength with our value and partners. I'll now hand the call to Mark so he can discuss our financial performance and 2025 outlook. Mark?

Mark Chiplock

executive
#3

Thanks, George, and hello everyone this afternoon. We posted robust results for the first quarter, with total revenue up 18% and adjusted EBITDA up 32%. Revenue from our projects business rose 23%, which shows excellent execution and our intense dedication to turning backlog into revenue. In addition, as George noted, we ran into no further postponements or cancellations involving the federal government and those contracts we called out on our fourth quarter call, all of which have now been unpaused or rescoped. Outside of federal project work, we also enjoyed a solid quarter across Europe, Canada and a number of U.S. regions. That outcome illustrates the variety of our customers, geographies and solution types that distinguishes the Ameresco business model. Energy asset revenue climbed 31%, mainly because of an increase in assets in operation versus last year, with our operating asset base now at 742 megawatts. We have likewise acted to offset weaker RIN prices for the year using our dynamic hedging strategy, leaving only 20% of our anticipated 2025 RIN exposure remaining. The drop in revenue for our other line of business stems directly from the divestiture of our AEG business at the close of 2024. Gross margin came in at 14.7%, essentially matching what we expected, and reflects a heavier mix of revenue from sizable European EPC contracts. Keep in mind that although these design-build projects carry a thinner gross margin profile, they assist in diversifying our business and generate significant operating leverage, since they demand very little additional operating expense relative to the gross profit dollars they deliver. Net income attributable to common shareholders came to a loss of $5.5 million, or $0.10 per share. Adjusted EBITDA reached $40.6 million, up 32%, which mirrors our robust revenue growth, disciplined cost controls and the strength of our lean, scalable business model. We keep seeing considerable expansion in our total project backlog, which rose 22% to $4.9 billion. Notably, we converted $330 million of awards into contracts during the quarter, lifting our contracted project backlog by 80% to $2.6 billion. Our project teams keep delivering on contract conversion and execution to boost revenue and cash flow generation; we also brought $367 million of new project awards into our awarded backlog during the quarter. Now to our balance sheet and cash flows; we finished the quarter in a healthy cash position with roughly $72 million in cash and total corporate debt of $270 million. In the first quarter, we successfully completed approximately $334 million in financing commitments, among them extending and upsizing our senior secured credit facility to support funding our growth. Given our strong first quarter results and forward visibility, we are happy to reaffirm our guidance ranges for 2025 revenue and adjusted EBITDA of $1.9 billion and $235 million at the midpoint. Our team's excellent execution produced faster implementation during the first quarter of roughly $30 million of project revenue. As we think ahead to how the rest of the year will take shape, we're keeping our view unchanged: revenue timing across the latter half of 2025 should come in at roughly 60% of overall revenue. Given how well Q1 turned out, our expectation for Q2 sits at somewhere between about $400 million and $425 million. At this point, I'll hand things back over to George for his closing remarks.

George Sakellaris

executive
#4

Thanks, Mark. So, as you've already picked up on, we got off to a really strong beginning this year, and that same momentum has carried over into Q2; across a span of more than 25 years, we've assembled a company whose know-how in creating, arranging and executing energy projects has no equal. Thanks to our long-term recurring revenue operations, plus the robust multiyear visibility that's baked into our project backlog, the bulk of our adjusted EBITDA comes from sources that make our business model durable. On top of that, we're confident our project business will keep expanding, since we anticipate taking a larger share of the infrastructure and resiliency build-out that's now emerging. We're a worldwide company too, with diversification across end customer, technology and geography, and that lets us keep backing policy shifts in any geography, which will maximize our growth and earnings; to wrap up, I want to express my gratitude once more to our employees, customers and stockholders for sticking with us. Operator, let's go ahead and take questions on the call.

Noah Kaye

analyst
#5

From the fourth quarter until today, it's obviously been a favorable shift in the federal business. Could you walk us through a bit of what happened over the quarter that perhaps helped bring the visibility on certain contract situations to a better spot? I believe we begin with the assumption that for whatever assets these projects serve, they save energy and are net positive. But perhaps share how things unfolded, and maybe describe what some of these new RFPs you're encountering look like.

Mark Chiplock

executive
#6

Yes. Noah, Mark speaking. Let me address the first portion of your question regarding the federal contracts. Again, we consider ourselves lucky that the single contract that got cancelled and has since been rescoped should, in our view, return under a future mod; ultimately, then, it stays roughly neutral relative to where it began, and we see that as a terrific result. Then, regarding the remaining 2 that had been paused and are no longer paused, those too will eventually be rescoped. Our sense is that rescoping likely produces a modest haircut on them, yet that's definitely not the worst scenario, which would have involved those being cancelled. So overall, I'd say the outcome was favorable for the 3 contracts we mentioned at the outset.

George Sakellaris

executive
#7

The key point here is that these agreements are mainly about energy efficiency, they don't affect the budget, and every administration tends to favor this kind of project. My guess is that the fact they were signed in January likely played a role in that. That explains why people pulled them out to examine them — once they see the government benefits, they intend to proceed. Also, with the GSA involved in the contract that got cancelled, a couple of the buildings are going to be sold off; so that work was shifted over to other buildings. That's the reason we feel quite positive about our position with this administration. I believe we can collaborate with them, since they appreciate the budget neutral approach as well as resiliency and additional power generation at federal facilities to meet the resiliency needs. Another point — and this is why I attempted to address it in my notes — is how they can get the most use and greater return from some of the land within the federal portfolio that sits unused; that's what took place in <<inaudible>> and so forth.

Noah Kaye

analyst
#8

Mark, I believe during the prior quarter you provided some guidance regarding how we should think about the shape—not just of revenue, but perhaps also around margins. Clearly, I understand that project timing can cause things to shift quite a bit; but is there any color on how margins might be shaped either for 2Q or for the remainder of the year?

Mark Chiplock

executive
#9

I'd say we feel quite positive regarding our full year guide, particularly the gross margin range, which came in at 15.5% to 16%. Again, Q1, I think, came in somewhat below what we had expected. But as I noted, we saw a heavier mix of European EPC contracts, which carry a somewhat lower margin profile. Still, I feel fairly good about that margin range for the rest of the year.

Noah Kaye

analyst
#10

All right. Perhaps this is the final one I can squeeze in; resisting the urge to inquire about what's just happened is never easy, and honestly, in this situation, it feels pretty fitting. Those blackouts across Southern Europe. My understanding is that the cause is still being determined. Still, it raises the issue of how reliable the infrastructure we build on the grid really is. And I'd like to hear your thoughts on what Ameresco's opportunity set looks like when events like this occur, plus the kinds of projects and possibilities you're observing throughout Europe generally.

George Sakellaris

executive
#11

A few days earlier, it had happened in part of Greece. The thing is, with so many nations adding such large amounts of renewable power, which comes and goes intermittently, you're going to witness this occurring increasingly across the United States too — like what took place in Texas a while back during that freeze. And as we keep adding ever more renewables to the system, without battery storage or what I refer to as firm renewable power available 24 hours a day, 7 days a week — 24 to 7 — this is bound to keep happening. In my view, distributed generation will end up playing a far larger role in responding than the big power plants and transmission lines will, since I don't believe we'll manage to construct the transmission lines needed to make the grid more resilient — I recall back when I worked at the utility on one big transmission line running from Massachusetts to Rhode Island, obtaining the right of way took 10 years. So it's extremely hard. There's another issue too: after those transmission lines get built, when an outage occurs and you sometimes lose 2 of them, you lack the spinning reserve to cover whatever might follow, which is exactly how these outages come about. During my utility days, when I handled long-range planning, we typically kept 5% to 10% spinning reserve. That's simply not there anymore.

George Gianarikas

analyst
#12

Could you provide an update on projects whose economics are affected by shifts in the Inflation Reduction Act? How does the landscape appear there? Which of those projects are continuing to advance? Might there be a slight postponement while waiting for things to calm down? I'm simply interested in whether you have any thoughts to offer on this.

Mark Chiplock

executive
#13

Regarding the projects set to come online during this year, particularly those involving RNG, we secured safe harbor for the ITC tied to them, so we're fairly confident about that. Beyond those, for roughly 3/4 of the projects within our asset development pipeline, we've also safe harbored the ITC. I believe we brought this up during the prior quarter, approximately $200 million in extra ITC. The teams have therefore performed excellently in taking the required actions to attempt that safe harboring. As for assets not connected to RNG, once more, I believe we've managed quite well in safe harboring the majority of those. Thus, I don't anticipate any near-term effects should anything occur with the IRA.

George Gianarikas

analyst
#14

And then perhaps to piggyback on that, did the shifting situation across the sector affect how you weigh projects against your appetite for holding assets? I'm asking, how would you say that — in what ways has your thinking evolved on that point across roughly the past 3 to 6 months?

George Sakellaris

executive
#15

Right. Rates are somewhat elevated relative to where we'd prefer them to sit; that's obvious to everyone, and it explains why you're witnessing a bit more expansion on the project side. Our attention has tilted somewhat more toward projects. That said, they do throw off quite attractive cash flow, and within that market we hold a fairly solid niche; and with the way things are developing now — greater resiliency plus additional power generation — we'd like to capture a meaningful share of that opportunity, and it fits squarely within what we do best. On the flip side, though, we've got more than 600 megawatts of assets under development, enough to keep us busy for the coming 2, 3 years; so we aren't easing off the gas pedal there — if anything, we're pressing harder on it. Still, projects are something we're very fond of, and we've carried those out quite successfully; so we're directing somewhat more of our focus in that direction.

Kashy Harrison

analyst
#16

Congratulations on 25 years. It's really good to hear those projects that were on hold are back underway now. I wanted to ask, has the smaller federal workforce caused any negative effects on your business? Or does the approval process, and just the everyday work with the federal government, keep moving along with no interruptions despite fewer workers?

Mark Chiplock

executive
#17

Yes. No, that's a good question. Honestly, we haven't observed anything so far, but we definitely could envision a scenario where what's going on with personnel might affect the timing of how awards turn into contracts, or simply administrative difficulties that could affect how quickly our projects move forward. I believe we've attempted to incorporate a certain degree of conservatism into our guide, into this year's numbers; but in the near term, we haven't seen anything as of yet.

George Sakellaris

executive
#18

Yet looking further ahead, since our initiatives are designed to be budget neutral — as you may remember, when the earlier Trump administration was in office, we completed a greater number of performance contracts than during the Biden administration, given that they favor this approach. So although there could be, say, a slight postponement in the shift from awards into contracted backlog, the count of contracts along with proposals will in all likelihood increase.

Kashy Harrison

analyst
#19

That's useful extra detail. Perhaps just two additional quick questions from me. George, I believe you mentioned that you're sitting in a solid position regarding storage, and the exposure isn't even particularly large, or isn't that significant in any case, to the U.S. — it's more international; and after that you said demand — it seems demand really hasn't been hit by tariffs. But I'm simply wondering, are there any further consequences for your business stemming from tariffs that we ought to be considering across any of the individual segments that perhaps weren't addressed during the prepared remarks?

George Sakellaris

executive
#20

I mean regarding the batteries, the projects we're executing this year and next year, for this year, all of them were bought in advance prior to any tariff impact. For next year, I believe half of them are going to be repurchased. The remaining half, what we've managed to arrange with a number of our customers, dollar for dollar, it's stipulated in the contracts that the purchase power agreements that regardless of what the tariff amounts to, it will be passed through. We recompute the rate, it will be passed through. So that — and the same approach applies with a portion of the panels. But the other item we've been attempting, procuring as much domestically as we can; yet even so, when tariffs exist, domestic pricing rises too. But up to now, we have handled things very, very well given where we stand.

Kashy Harrison

analyst
#21

Thanks for that detail. And perhaps just one last thing from my side. I was wondering if you've noticed any gaps in valuation between private deals — or what parts of your portfolio might fetch in the private market — compared with what you're seeing publicly, and whether there's any interest in demonstrating to the public markets what your assets are worth through transactions.

George Sakellaris

executive
#22

I believe that's for Josh's team to decide.

Josh Baribeau

executive
#23

Appreciate that, George. So my response would be affirmative. Our view is that strong private-market values persist for the kinds of projects and assets we're putting into place. There isn't anything specific we can discuss at this point. Still, I'd say public-market valuations across our entire industry have clearly been—to use a phrase—hit out of proportion, perhaps because of reasonable and unreasonable anxieties regarding shifts in the administration, the news cycle, and so forth; yet the underlying strength of what we offer in energy efficiency, our RNG assets, our pipeline, our portfolio, and our platform is remarkably solid, and those who can evaluate these matters through a project finance lens, or some of our develop-and-sell equity investors, those private equity folks, continue to appreciate what they're seeing, and we remain capable of converting the value we generate into cash.

Eric Stine

analyst
#24

Let's stay on the subject of tariffs. It's obviously excellent news how matters are lined up for '25 and a portion of the following year. Still, when I consider it, should this stretch of uncertainty persist beyond that, I simply want to probe a bit into how these contracts are structured. Is that pass-through wording fairly typical? What I'm really asking is whether this amounts to a laborious renegotiation done one contract at a time, or is it instead fairly standard, already written into the agreements, and more or less embraced by your buyers?

George Sakellaris

executive
#25

Honestly, I've instructed our team that with new contracts, we include wording that shields us from tariffs. And at times, when a great deal of equipment originates overseas, foreign exchange swings too. That has only just now turned into the standard. Yet it differs from one customer to the next. Take this specific customer, for instance — it's a sizable contract. It concerns a battery storage project, and they had a set deadline for getting the project operational, and we needed to commit funds for the transformer so we could secure the IPC and such, and we agreed that was acceptable. However, should tariffs emerge and prices climb, you must bear that burden too, for the transformer and such; and they rose to the occasion; and we're noticing increasingly that some of the biggest industrial customers are seeking resiliency, battery storage and such. So ultimately, I believe they'll have to take whatever steps are required to safeguard their operations.

Mark Chiplock

executive
#26

Yeah, look, I'd say even setting the contracts aside, we keep broadening where our supply comes from, you know? We've picked up a fair number of lessons coming out of COVID. So our attention has been on getting materials onto our projects more quickly, widening the supply base, and checking out sources here at home. So I'd say pairing those safeguards written into the contracts with, sort of, holding onto that diversification should let us soften the bulk of the tariff exposure going forward.

Eric Stine

analyst
#27

Understood. Fine, that helps. Then perhaps regarding the federal government projects — this was already asked, yet I simply wanted to get clarity. About the smaller staff, it seems you're treating this as more of a holdup — possible holdups instead of outright cancellations; and I realize what you've observed thus far includes the single project that's going to be rescoped. There are 2 that have sort of returned; however, is this mainly about the approval procedure and scheduling needed just to work through all the steps required to proceed, instead of a larger danger of fewer buildings, housing that reduced workforce, and altering the total scope.

George Sakellaris

executive
#28

Well, I wouldn't claim possible holdups exist. It's going to be immaterial since — that's exactly what I attempted to highlight, given how strong the value proposition behind what we offer is, plus the administration desires it so intensely, or rather they require this type of work, because ultimately they receive the infrastructure upgrade without dipping into their budget to make it happen. No capital is needed from them, so there will be greater pressure to save money. Thus even with fewer personnel. Ultimately, my expectation is that we'll witness additional contracts being signed with these folks.

Mark Chiplock

executive
#29

Right. That said, in a broad sense, when risk does come up, our view is that it tends to be on the administrative side — really just possibly making things move more slowly when it comes to converting awards or getting contracts done. So — and once more, nothing of that sort has turned up so far.

Craig Irwin

analyst
#30

George, Mark, everybody, thanks for the information about your RIN hedging position. I'm certain you know about a few of the contentious projections that different analysts have put out regarding RINs potentially being reduced by 50%, which isn't something one of the major oil desks would typically say. But could you remind us of the steps you take to assess possible profitability on your assets prior to committing capital, how you put these agreements together when it comes to splitting the RINs and other incentives, and how you stress test these projects before you ever spend money breaking ground to build, so that profitability is ensured throughout the cycle.

George Sakellaris

executive
#31

Josh, I believe you can handle that for me.

Josh Baribeau

executive
#32

Craig, we actually put RNG projects through a fairly rigorous review all the way along as they're being built, and that includes several rounds with our investment committee. On top of that, we've got financing partners who've been with us a long while, and we bring them in on many of these projects at an early stage so we can confirm their view of the RIN curve lines up with ours, or at least with what's sensible for the market. Then we build in the financing assumptions — how much debt, what it costs, the tenor, and so forth — alongside what our models tell us and what the development team comes up with. Under a base case and under a stress case, provided those clear our hurdle rates — which, as we've discussed, means roughly a levered teens IRR on a risk-adjusted basis — we move ahead through the subsequent steps, those gates across development. So there's quite a bit in all of that, but we certainly aren't relying on historical RIN rates or even today's win rates. It's genuinely a curve that slopes downward, built off forecasts from all sorts of market participants plus our own proprietary work on supply and demand within the RVO, and so on.

Craig Irwin

analyst
#33

Got it. Now I'd like to ask about operating expenses. Your revenue grew by more than $50 million, yet for the first quarter your OpEx declined compared with the past couple of years. Could it be that you're shifting headcount toward project execution away from development work? Is something happening with onetime costs or re-budgeting when it comes to the OpEx line? And if personnel did move over to execution, can you put a number on what that meant for margin?

Mark Chiplock

executive
#34

Sure. From an allocation standpoint, utilization looks like it's a bit improved, I'd say, when you examine OpEx and the pattern there. Also keep in mind that a year ago we carried extra OpEx tied to our AEG business, and that was divested. So those costs are gone from the P&L, and that shows up as a direct decrease. Broadly though, it's really the cost discipline on OpEx that's keeping it flat or even lower, since we manage the timing of hiring new people and bring them on only when needed. With many of the bigger projects we're winning, we continue to enjoy fairly strong operating leverage.

Joseph Osha

analyst
#35

I have a couple of things to ask. To start, George, you mentioned exposure outside the U.S. and your backlog specifically in solar plus energy storage. Could you give us some approximate figures for that? Clearly, 63% of your energy asset backlog sits in those 2 sectors. For the project backlog, figuring out that number is tougher. But can you help us get a sense of how that might roughly split between U.S. and non-U.S. business? Then I have another question.

George Sakellaris

executive
#36

The bulk of the work in Europe and Canada is probably 1.5 gigawatts, though mostly through EPC. Only a very small share, I believe, is something we'll hold, and that's up in Canada. Across Europe, every project we have, apart from a small one — perhaps 10 megawatts — is under EPC contracts.

Joseph Osha

analyst
#37

Okay. I suppose I'm failing to follow. You have 618 megawatts of energy assets being built, and 63% of those are solar or battery. What I want to know is how much of that falls inside the U.S. and how much outside it.

George Sakellaris

executive
#38

Josh, could you provide the precise figure?

Josh Baribeau

executive
#39

Practically everything is confined to the U.S. My apologies, Joe — we were responding to what was asked about the project backlog. I hadn't realized that you were the one addressing the <<inaudible>>.

Joseph Osha

analyst
#40

That really helps clarify things. Alright, so when it comes to the project backlog, there's a wider geographic spread, whereas the energy asset backlog leans more heavily toward the U.S.

Josh Baribeau

executive
#41

Exactly right.

Joseph Osha

analyst
#42

All right. Excellent. Moving on to my next item — I picked up on a few remarks regarding spreading out where you source things, which sounds good, and you've got a handful of choices when it comes to solar modules. But wow, LFP manufacturing here in the United States is pretty scarce at the moment, and nearly all of it is already committed. Regarding your storage division, can you purchase domestically? Will you go with nickel-based cells? Or did you uncover a plant that's off everyone's radar? I'm also eager to hear your approach to procuring cells. And my guess is you're primarily relying on LFP.

Josh Baribeau

executive
#43

Joe, this is Josh. Yeah — apologies, we keep tossing this one between us. Essentially, the bulk of it is conventional lithium ion. And sadly, there aren't any freshly built facilities that are unknown to everyone that we can reveal during tonight's call. We're purchasing from the very same large worldwide suppliers that many others use, particularly when it comes to bankability and performance, since — as I believe you're aware — we've experimented with other options, and the results weren't nearly as good. With that said, the crucial point is that what we hold at assets under development for this year, like George said, has largely been safe harbored and/or is already on site; one sizable project will reach COD around midyear, and that represents most of the assets and operations we previously guided to. As for fresh projects, it's not so much about sourcing and more about how contracts are structured. For those new projects, we're adding change in law clauses, like George said, roughly a dollar-for-dollar adjustment tied to tariff or IRA-related shifts. So sourcing matters less than collaborating with our customers to secure fair terms amid this unpredictable landscape.

Joseph Osha

analyst
#44

All right. As one final add-on regarding that topic, folks elsewhere in this industry have referenced those pass-through arrangements, yet they've also suggested caps exist that restrict how much exposure there is. Thus, imagine that 12 months from now we find ourselves paying 130% LFP tariffs — do you intend, and do you believe, that the entire amount can be handed down to your customers? Or would a portion of it fall on you?

George Sakellaris

executive
#45

Our aim is to hand it down to our customers. If the project margin happens to allow us to soak up part of it, then we would — we examine the economics extremely carefully prior to accepting that type of risk or cost. Ultimately, it comes down to the project's economics.

Operator

operator
#46

That wraps up the Q&A portion — we have nothing else queued up. And with that, the conference call is finished as well. Thanks to everyone for being on the line. You're free to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ameresco, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ameresco, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ameresco, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.