Thanks, Bella, and good afternoon, everyone; we're glad you could be with us on today's call. Joining us as speakers today are George Sakellaris, Ameresco's Chairman and Chief Executive Officer, Nicole Bulgarino, Co-President of Ameresco, and Josh Baribeau, Chief Investment Officer. Also, Julie Bradshaw, Vice President of Finance and Interim Principal Financial Officer, will be on hand during Q&A to help field questions. Before handing the call to George, I'd like to offer a brief statement about forward-looking remarks. The earnings materials released today include forward-looking statements, among them statements about our expectations. Every forward-looking statement carries risks and uncertainties. For a discussion of the major risk factors that could cause our actual results to differ from those in our forward-looking statements, please refer to today's earnings materials, the safe harbor language on Slide 2 of our supplemental information and our SEC filings. We also use several non-GAAP measures in presenting our financial results. Reconciliations of these measures, along with additional information, are included in our supplemental slides that were posted to our website. Please note that, unless otherwise noted, all comparisons we will be discussing today are on a year-over-year basis. I'll now turn the call over to George. George?

George Sakellaris

executive
#2

Thanks, Leila, and good afternoon, everyone. We kept up our strong momentum in Q3, with excellent execution and financial performance across every one of our business lines. We also posted another great quarter of new business activity, and that added a great deal to our multiyear project backlog. Importantly, contract conversion was strong during the quarter: $737 million of awards converted into contracted backlog, among the highest amounts in the company's history, and that new business development momentum has carried on into Q4. In certain markets, projects moved through our sales cycle faster than we've historically seen. What drove those results was the huge demand for upgrading existing buildings and public energy infrastructure, plus the urgent requirement for new power generation. With decades of experience delivering energy savings and a range of on-site power solutions, Ameresco is in a unique position to serve those customer needs. As I mentioned, each of our three major business lines grew excellently in Q3. In our projects business, we saw strong performance from both of our core market pillars: buildings and public energy infrastructure, and power infrastructure. Within the markets we serve, our buildings and public energy infrastructure pillar continues to deliver solid results, supported by the ongoing strength of our federal business. Across every market and region, clients are dealing with sharp increases in energy expenses along with the obligation to fund upkeep that was put off for many years, which is why our sustainable, budget-neutral offerings fit perfectly as a way to address both issues at once. Beyond our main energy efficiency products, we continue broadening what we provide under this pillar, positioning us as a single source for a wide spectrum of energy infrastructure answers for our partners; and the power and infrastructure segment of our company sits in a distinctive spot to serve fast-rising demand for dependable and adaptable power. We offer a wide range of generation solutions, and these can deliver essential backup power to utilities, along with behind-the-meter on-site power for commercial and industrial customers who want to fuel growth and keep operations running without interruption. This represents a growing opportunity for us that is increasingly important, especially as power constraints get tighter and customers seek solutions that can be brought online fast and customized to their particular requirements. We're seeing that momentum across regions—from large-scale infrastructure projects in Canada that use things like natural gas turbines and battery energy storage, to the ongoing expansion of renewables through our SOL joint venture in Europe. I'm really happy to report that both of our recurring revenue segments — energy assets and O&M — kept expanding and now represent a significant piece of Ameresco's business as a whole. In our view, these two areas will keep delivering strong growth to our recurring revenue and earnings over the long run. Taken together, our three main business lines provide Ameresco with excellent diversification across end markets, customers and solutions. We expect that to drive our growth over the long term and also give the business considerable resilience. Finally, I'd like to take a moment to discuss the election results that came in last week. One thing stood out clearly: everywhere in the country, people are concerned about rising energy costs and affordability. In this environment, we think Ameresco is positioned exceptionally well. Our budget-neutral built-in and public energy infrastructure solutions assist customers in modernizing aging facilities, enhancing efficiency and resiliency, and lowering energy costs without the need for significant upfront capital. At the same time, our power and infrastructure solutions are helping to meet the growing demand for reliable, cost-effective power. Taken together, these capabilities speak directly to many of the energy challenges our customers face today. and we believe this environment will keep generating meaningful opportunities for our business. And now I'd like to hand the call over to Nicole, who will share additional details on the success we are seeing in our business development activities. Nicole?

Nicole Bulgarino

executive
#3

Thanks, George, and good afternoon, everyone. I'd like to begin by highlighting our business development wins, which underpin our expectation of continued revenue growth in the years ahead. New project awards came in at $875 million, one of the strongest quarters for awards in the company's history. Awarded backlog surpassed $4.5 billion, more than 70% above where it stood at this time last year; that underscores the strong momentum in our business, fueled by a confluence of favorable industry catalysts. Our federal business posted record growth, stemming from large energy efficiency and infrastructure projects with both military and civilian agencies; we're also continuing to see robust demand in the C&I sector, where the need for power and resiliency fueled activity in this increasingly important end market. Combined, our federal, C&I and European projects represented roughly $675 million, or more than 75%, of new awards in the quarter, which reflects the meaningful diversification within our backlog. We also added about $200 million to awarded backlog tied to our data center projects. That stems from scope expansion as development of these projects moved forward. We continue to chase new data center opportunities that benefit from on-site power solutions. What sets our offering apart is that we generate power right at the site, so there's no additional burden placed on the grid or on what people in the community pay for electricity. Our solutions additionally cut back on reliance on the municipal water supply and bring advantages to the community. Going forward, we plan to maintain our strategy of carefully choosing industry partners that fit best and taking full advantage of our use of federal land we already hold. You might have caught our recent announcement with the Army about developing on-site nuclear power generation projects meant to boost mission readiness and resilience while supplying clean power to the wider grid; in our view, nuclear technologies could be a major contributor to the future of clean firm power. We're in active collaboration with a number of nuclear technology firms to build an integrated offering for our customers, and we've just executed our inaugural EPC contract covering balance of plant scope at a microreactor project. Given how our backlog has grown, I'd like to call attention to contract conversions, an area where we turned in outstanding execution during the quarter. Conversions picked up pace in a number of our major end markets—federal, Canada and Europe among them—fueled by solid relationships and repeat work from customers we already serve. One strong illustration is the U.S. Department of Veterans Affairs, with which we're presently involved in numerous infrastructure upgrade efforts at facilities spanning multiple states. Because of how hard the team worked during this quarter, the combined awarded and contracted backlog has climbed to just about $7.2 billion, which is roughly 40% higher than where it stood a year ago, and that provides us with revenue visibility stretching across many future years. At this point I'll hand things over to Josh, who will walk through our robust Q3 financial results in greater depth. Josh?

Joshua Baribeau

executive
#4

Thank you, Nicole, and good afternoon to all of you. Before I get into our Q3 results, I'd like to take a short moment to explain an accounting change and a shift in our non-GAAP methodology, both of which affected the way we present our results and our forward guidance. First, during the third quarter, we finished an additional accounting assessment of the Neogenyx transaction. Working alongside external accounting partners, we concluded that HLBV accounting is the more suitable approach for reflecting this joint venture in our financial statements. Under HLBV, income or loss is allocated according to what each partner would receive if the joint venture were liquidated at book value on each reporting date. This method is common in tax equity and complicated partnership arrangements. The key point is that none of this changes the fundamental economics, the cash flows, or how our business operates. Moving on, because HLBV outcomes can vary substantially between quarters, our non-GAAP EPS and adjusted EBITDA now reflect 100% of the operating results from our consolidated joint ventures, Neogenyx Fuels and Ameresco SUNEL Energy, which simplifies comparisons across periods. Our ownership positions in the joint ventures have not changed. We continue to hold 70% of Neogenyx and 51% of the SUNEL JV. So that our results stay transparent, we have provided net income and adjusted EBITDA for each JV in our press release. The Neogenyx business is reported within our Renewable Fuels segment, and it accounts for nearly all of that segment. Now for our strong quarterly performance. Revenue on a total basis increased 10%, reaching $580 million, driven by solid execution throughout our three main business lines and by outstanding business development work. Project revenue climbed 9% to $446 million, led by notable strength in Federal, C&I, and our Sunel JV. Our energy asset business posted another robust quarter, helped by growth in our portfolio of owned operating assets, as revenue rose 21% to $75 million. We now have 827 megawatts of operating energy assets, plus another 500 megawatts under development. While the asset revenue is consolidated, the megawatt numbers represent Ameresco's 70% stake in the Neogenyx JV. We're also steadily adding O&M contracts, which pushed revenue for this business up 20% to $37 million. Our O&M backlog has now surpassed $1.5 billion, giving us the recurring, profitable revenue visibility we expect to rely on for many years. Gross margin rose to 18.7%, with substantial gains both sequentially and year over year. That margin improvement came from a mix of favorable business composition and solid execution. Earlier in the quarter, we revised how long we assume our energy assets will be useful, moving the estimate from 20 years up to 30 years, which aligns us better with typical industry practice; as a result, depreciation tied to those energy assets went down starting in Q3 and will stay lower going forward. That decrease in Q3 was mostly offset by higher depreciation stemming from our anticipated switch to tax-based accounting for transferable investment tax credits, something I'll address shortly. Net income attributable to common shareholders was $31.9 million, equal to $0.59 per diluted share, while non-GAAP EPS reached $0.88. The quarter's results benefited substantially from a tax gain connected to our planned move to a tax-based accounting policy. We believe this method aligns the earnings advantage from investment tax credits more closely with the period when those credits arise, rather than distributing that advantage over the useful life of the associated assets. Applying this tax accounting policy retroactively is reflected in our results for the year to date and in the 2025 recast comparisons too. Adjusted EBITDA climbed to $92 million, incorporating the full consolidation of our JVs as covered earlier. To make comparisons with your prior models easier, absent that full consolidation, non-GAAP EPS in Q3 would have come in at $0.60 per share and adjusted EBITDA would have been $78 million; in our press release we have included supplemental quarterly details for all of 2025 and '26 that reflect both the retrospective application of our new tax-based accounting policy and the full consolidation of our JV results. Now on to our balance sheet. Unrestricted cash stood at $129 million, with total corporate debt of $380 million. Corporate leverage was 2.9x, comfortably under our 3.5x covenant. During the quarter we secured $106 million in fresh financing commitments. That ought to give us more financial flexibility for funding the growth we expect, meeting working capital requirements, and expanding our energy asset portfolio in a disciplined manner. As our press release lays out, we are giving Q4 guidance and revising our full-year 2026 guidance. Those updates capture the accounting changes I referenced, along with bringing 100% of the operating results from our consolidated joint ventures into our non-GAAP EPS and adjusted EBITDA presentations. The guidance incorporates just those items and reflects no shift in our operational outlook. Apart from that, our guidance for full-year adjusted EBITDA and non-GAAP EPS would have stayed the same; with that said, I'll turn the call back over to George for his closing remarks.

George Sakellaris

executive
#5

Thank you, Josh. As you've heard, we delivered a strong quarter of execution that drove excellent financial results and significant new business activity. That momentum has carried forward into the fourth quarter, which puts us in position to wrap up a tremendous year of execution and development activity. Given our growing backlog and the strength of our recurring revenue businesses, we believe we're well positioned to deliver continued profitable growth in '27 and beyond. We look forward to connecting with many of you at upcoming meetings, conferences and events. In closing, I want to thank our employees, customers and stockholders once more for their continued support and confidence in Ameresco. Operator, we'd like to open the call to questions.

Manish Somaiya

analyst
#6

Congratulations on converting backlog and on margins. I suppose, George, you have to be quite pleased with how the quarter turned out. But I want to return to what was said about the post-election picture. And maybe, George, you could help us grasp what you are seeing on the data center side, which I think is the question on everyone's mind right now. How are customers responding? Have you gotten any word from regulators or customers regarding timelines moving? Perhaps you could help us grasp what is going on, what the first reaction has been? And how are you planning for the coming weeks and months?

George Sakellaris

executive
#7

Thanks, and that is a good question. I will add some detail, offer a few remarks, and then I will let Nicole add a bit more detail on the data center. But on the whole, the election benefits us. You have to keep in mind what I said earlier: our core bread and butter business is energy efficiency and the budget-neutral solutions we give customers. And I believe the election demonstrated that affordability and rising energy costs are a top concern. And I believe we have a very, very solid solution. And given that we saw a shift in Congress and some key government changes around the country, I believe on the whole it will work in our favor; and regarding the data center, I believe Nicole will have good detail, but I believe the targets we have changed and the projects we are working on, particularly since 50% of our data centers sit on federal land, will be easier to permit. And in the end, I believe the value proposition for those sites we control, which is 5 of them, I believe, will be good for us and for what is happening in the industry. Nicole, would you like to add something?

Nicole Bulgarino

executive
#8

Absolutely. We continue to feel confident and genuinely enthusiastic about the backlog we have with data center customers. As I mentioned in the script, what sets our solutions apart is that they provide on-site power—in certain cases, they're even islanded. So when you consider what's been raised regarding data centers and power, the key point is that they don't want any grid impact, and they definitely don't want electricity costs affected. By taking the approach we're taking, we're very well aligned with what everyone has been discussing over the past couple of months. And now that the elections are finished, that resolves the pause we'd been in while waiting to see what would happen in anticipation. So now that we're moving forward, we have a diverse pipeline, as George mentioned, on federal lands and also commercial lands with various types of end user tenants. So we're very excited about that, but these are large power plant projects; and as with anything, these projects must go through the development process; and so we'll work through challenges as they arise. But at this point, we very much believe that our solution is in line with what the overall landscape is calling for right now.

Manish Somaiya

analyst
#9

And Nicole, if I could squeeze in one more question about data centers. I believe I noticed a $200 million data center award this quarter. My understanding is that it represented an expansion of a project already underway. Could you perhaps give us additional detail on what shifted regarding the customer's commitment, the project design, or the capacity needed to accommodate that larger scope? Then, stepping away from data centers, maybe George could also address the momentum in federal and Europe awards. Clearly, we saw some meaningful awards on that front in 3Q. What I think would help is grasping the pace and the visibility on conversion into 2027.

Nicole Bulgarino

executive
#10

Sure. Both are excellent questions. On the first one, the $200 million expansion, really this reflects our project development maturing, which lets us firm up the capacity, the type of generation we're using, and simply align it with the data center load. So we're seeing some of the megawatts rise to meet that design. That's the source of it. Turning to your question about the federal movement, we had many contracts convert, especially with the VA that we referenced in the script, large infrastructure projects supporting both energy efficiency and also greatly needed infrastructure, mechanical and electrical upgrades across the VA hospitals. In a similar way, we had another agency too, with Coast Guard being another one we converted this quarter, plus another Army site. So we had strong momentum. Again, having that established relationship with the customer we've already worked with for many years certainly aids those conversions.

George Sakellaris

executive
#11

And one remark I'd made earlier in my script was that I felt especially good about how widely the conversion of awards into contracts was spread — covering, say, C&I, the federal government, a number of the smaller utilities or cooperatives, and so forth. And naturally, in Europe we're seeing truly tremendous momentum, particularly with the funds they're putting into solar installations. It's going to be an extremely strong business. The other development on the C&I side is that electricity demand is so big, and they're starting to worry about dependable power so they can grow their business. That's why, for the first time in quite a while, we're witnessing really tremendous momentum in that market; and those contracts move more quickly since the need exists and they want to expand; and what has come about from bringing industries back into the United States is speeding up that demand.

Craig Irwin

analyst
#12

This is Andrew speaking in place of Craig, and congratulations on the impressive momentum. So my first question. As the O&M contract base grows, we've been watching revenue climb, but we also saw fairly strong gains in profitability this quarter. So could you speak to how much of that comes from greater operating leverage versus contract mix, and what margin level is sustainable?

George Sakellaris

executive
#13

Yes. Thanks, Craig. I'll handle the first one, since I'm very, very pleased with the progress we're seeing on the O&M. At this point, we're nearing 4 gigawatts of solar, O&M and batteries. And naturally, that will grow tremendously. Beyond that, with the federal government business, you win more contracts, you get more O&M there. And now as we move into the data center and, say, we've built a couple of these power plants down the road and some of the O&M contracts I see coming along with us, they are very, very, very good. So I'm very excited about that part of our business; and naturally, it doesn't take that much capital in order to expand that business to the assets that we own. And would you like to add a bit more color, Josh?

Joshua Baribeau

executive
#14

Sure. Specifically on margin—if you mean O&M alone, then O&M margins improved quite substantially over the past two quarters. I believe we covered this last time when we mentioned certain price hikes we managed to implement that, in fact, had been in the works for a good while. So those price increases contributed to some of that. That said, O&M can be fairly variable. I wouldn't want any of you to assume that an EBITDA margin in the mid-20s percent range is necessarily the steady level to use going forward in your models. Still, we're quite pleased with that business, and it remains a source of value. If instead your question concerned consolidated gross margins, then yes, we had an excellent quarter. It came in slightly above our guidance. That guidance range was 17% to 18%, which may be somewhat conservative for the full year. But it is definitely up significantly versus last year, and that has come from some energy assets entering service, as well as from a strategic initiative we've discussed aimed at generating higher-margin projects across the business. We've been pursuing that in Europe. We've been pursuing it in U.S. regions, and so on. As with all the positive developments George and Nicole mentioned, customers need the solutions, and that produces considerable value. So we're able to capture a bit of additional margin on those.

Nicole Bulgarino

executive
#15

Yes. Execution was strong for us in this quarter as well, and that worked in our favor; as we wrapped up projects, we managed to capture some margin improvements.

Craig Irwin

analyst
#16

Got it. I really value that level of detail; and then just one more from me, a broader question. You mentioned this during the opening remarks, but could you share a bit more insight into how things are going with Neogenyx, how the operating plants are doing, and any headway on the development pipeline would be terrific.

Joshua Baribeau

executive
#17

Sure; regarding Neogenyx, we're extremely pleased with that deal. In our view it was transformative for us in terms of the way we generate value from our assets and how we can finance the expansion of our assets, both within this segment and possibly others. I believe there were certain matters beyond our control following the closing of the transaction when it came to power plant availability, as I mentioned, mostly beyond our control; yet when it comes to the pipeline, when it comes to business development, when it comes to HASI's commitment, everything is precisely as we modeled.

George Sakellaris

executive
#18

Yeah, if I may add, working with those folks has been a great partnership. And at a couple of the plants — at one of them a transformer blew up, and that meant an outage of more than 6 weeks there. And then at the other one, Woodland, we had another issue develop at the plant, and both of them, by the way, have now been fixed.

Eric Stine

analyst
#19

Perhaps we could return to those data center items you brought up — the $200 million expansion. From what I recall, last quarter your backlog held five contracts, and I believe you gave $1.5 billion combined, plus a total of what those might become if expansion occurred. So I'm just curious what you're seeing among the additional projects sitting in your backlog? And regarding other prospects out there that you're pursuing, should we expect something like a shift toward bigger projects?

Nicole Bulgarino

executive
#20

Yes. To address that first part, I'd say this expansion related to one specific project. And once more, the reason we were adding capacity was really just to match it to customers' needs for their data center build-out. As we said on the last earnings call, we certainly anticipate that we expect to reach — so that will keep getting refined as we keep developing them. At this point, we've been working through the development process. And as we move along, that's how we've approached all large projects, just making sure we're doing it as development matures. Based on where we stand now, I think the AI market keeps growing, and we're also going to see more and more momentum toward behind-meter on-site solutions. So certainly, I think there'll be additional opportunities for us to keep growing this pipeline — not only with those in awarded backlog, but more coming too, especially even more so after the elections.

Eric Stine

analyst
#21

Yes. No, that helps a lot. So maybe on the project conversion side—obviously you brought up federal and Europe, which is great. But a lot of the factors you described, those have sort of been the market backdrop for a while now. So I'm wondering whether anything stood out as a specific driver this quarter? Or was it simply that you happened to have a number of projects nearing completion, or a high percentage of them got across the finish line?

George Sakellaris

executive
#22

A bit of both, I'd say. There were plenty of projects where we'd put in a great deal of groundwork and they were set to be signed, and given the need, customers sped things up. But some projects—particularly in Europe—now take far less time from award to executed contract than used to be the case. And the C&I customers work on a much shorter timeline. A couple of the co-ops, some of the contracts, moved faster than we had anticipated; so that's why I'm quite pleased it was broad-based. And I think we all concentrate heavily on data centers and the effect that has on our business. But a side effect of strong electricity demand or insufficient power supply is that many of what I call co-ops, smaller utilities, larger industrial commercial customers—ones that never previously spoke with us about backup power or whatever the situation may be—are now doing so; and that's why a good portion of our backlog today sits in that space, that specific market segment; and we feel very good about it. And that's why we feel good about our business model, the diversification we have across the various types of markets and customers and solutions we offer.

Eric Stine

analyst
#23

All right. And then just quickly on this one. I mean, this came out — I don't know — about a month ago, and there are probably very few details, but the project fortress discussion about every military site needing to produce its own power and run that to the grid. I mean, that would appear to line up pretty well with what your core capabilities are. Wondering whether there's anything there that's further out.

Nicole Bulgarino

executive
#24

I believe that is further out, but it certainly is among the objectives. Resiliency and reliability have been goals of the federal government for a good while, and now this latest push — because of the constrained grid at present — is going to speed that up even more. We are seeing more, and again, not only onsite generation, but also greater energy efficiency that cuts load as well. That suits us very well, since those objectives are complementary to one another.

Ryan Pfingst

analyst
#25

Perhaps one more follow-up regarding the data center side. Out of those five projects sitting in awarded backlog, how many do you expect to shift into contracted within the next, let's say, 12, 18, or 24 months? Alternatively, if you'd rather not comment on timing, could you simply remind us of some milestones these projects are awaiting before you're comfortable moving them into contracted backlog?

Nicole Bulgarino

executive
#26

Well, yes. I mean, I think for those five projects, 12 to 18 months is on target with what we're seeing there. And each one tells a slightly different story, but permitting is one, finalizing customer contracts and securing equipment are the three major milestones we're working on for each of them.

Ryan Pfingst

analyst
#27

Understood. Would you be able to expand a bit more on the Army project in general, including the nuclear piece? What's the right way for us to view the next steps there? And who ends up carrying the first-of-a-kind risk on the nuclear stages?

Nicole Bulgarino

executive
#28

Absolutely. That's a fair question. So the first of a kind is distinct from those two Army sites we put out information about. It's a different project, and we've teamed with a microreactor partner that will take on the risk on the nuclear portion of it. Our part there is simply to balance the plant, to build around the building concrete generator, and to connect the generation — so exactly what we do routinely. That said, we're enthusiastic about the Army announcement, since it has genuinely shifted the strategy into something real, and we're now actually seeing what the future holds for nuclear. And so with these two sites that came from the Army to Katan Aberdeen in Maryland, they give us the chance to have multiple phases. So we're at an early stage in development. We have to work through permitting. We have to work through design scope. We have to work through a number of other lease negotiations with the Army for these to turn into something. Even so, we're doing it in phases, which lets us capture early wins and then pursue the longer stretch with various nuclear technologies, from microreactors, which have a shorter time on the permitting, to SMR technology. So on both of these, we have a combination of battery storage and also even clean technology such as fuel cells, and then leading into the Phase 2 with the nuclear solutions. Yes, it's great to see the Army backing that, because that is a key objective with them — having nuclear solutions.

Stephen Gengaro

analyst
#29

I've got two, I think. First, could you discuss a bit the supply chain situation and a few of those inflationary pressures we're seeing, and how the way the contracts are set up helps cushion that?

Nicole Bulgarino

executive
#30

Absolutely. I'd say supply chain is a fascinating topic. It really hinges on the market you mean. But first, we will certainly witness a rise in supply chain activity as some data centers that were formerly tied to the grid, or had other equipment, now hold surplus equipment that will flow into the secondary market. Still, speaking generally for us, supply chain has posed difficulties for years at this point; so we maintain a broad network of distributors for distributors — for electrical equipment as well as generation equipment. That lets us act fast and stay flexible in designing these systems; yet in the end, too, the contracts we're handling will include safeguards and truly collaborate with it so as to shield against tariffs, shield against cost shifts, simply because we've witnessed such a rise — I mean, within just the last 12 months, a 30%, 40% jump on certain electrical equipment, with similar increases there. So for us, it's something we've addressed on every contract and ensured we're protected, but also just to see it still doesn't eliminate the need for this; and so the drivers remain. Thus there isn't truly an option except to keep moving forward with it.

Stephen Gengaro

analyst
#31

And following up on that: we've observed multiple companies where, clearly, the cash needed for ordering — particularly power gen equipment — runs quite high. Will your customers help finance that? Or does that end up being funded by you in some way?

Nicole Bulgarino

executive
#32

That's a good question — yes, excellent question. Our business model doesn't involve going out and purchasing equipment; we've stated that very plainly to our customers; so we definitely aren't depending on them to make that commitment, since doing so also indicates they're prepared to proceed and have a project. So that's how we've been proceeding on our projects, and certainly we don't fund equipment procurement ourselves.

Ben Kallo

analyst
#33

Nicole, perhaps I could just pick up on a few of the points you made earlier regarding the various technologies; and I realize it's quite early in some of these states as they adopt rules around data centers. But have you noticed any change, whether from a simple cycle turbine over to a fuel cell, or from a simple cycle turbine over to a reciprocating engine, or anything you're observing in terms of shifts driven by the pushback backyard? And I have a follow-up.

Nicole Bulgarino

executive
#34

That's a really good question, I think, and there are two distinct angles to it. The first is that the need for speed to power remains, but also balancing that against minimizing water consumption and achieving cleaner emissions. So across most of our projects, what we're seeing is a combination of fuel cells, reciprocating engines and simple cycle turbines, with a later phase drawing on combined cycle technology, which would involve more water usage there. I mean, I think as well that you still have hyper scalers seeking to have offsets with clean energy. So at some of these campuses, it wouldn't surprise me to see solar and battery storage included as part of the overall solution once the base speed to power project is implemented; but I think right now it's still more or less the same mix, because you need that speed to power, and reciprocating engines and fuel cells are the fastest route to getting there.

Ben Kallo

analyst
#35

Understood. And George, I believe during your prepared remarks you brought up energy efficiency—you said it hasn't been this robust in a long while. Could you expand a bit on that, like whether it's mainly government work or where exactly you're seeing that strength?

George Sakellaris

executive
#36

We're seeing really, really strong momentum in energy efficiency, since energy prices sit higher than they used to and keep staying that way; and it shows up in every market—colleges, universities, cities and states across the board, plus commercial and industrial customers. And there's another factor at play: aging infrastructure. Essentially, the fact that we're able to take those energy savings, securitize them, and then deliver new boilers, new chillers, sometimes new windows, we upgrade bathrooms. We complete a great many upgrades at customer facilities; and Nicole, perhaps you'd like to add something.

Nicole Bulgarino

executive
#37

It's actually a combination of factors. I mean, you've got rising energy costs on one side and outdated, inefficient infrastructure on the other. So when we can swap that out for the newest technology—equipment that's also cheaper to maintain—we're seeing the benefit even in something as straightforward as swapping out boilers; controls and similar upgrades definitely contribute to better energy efficiency, though the whole thing is ultimately pushed along by higher expenses.

George Sakellaris

executive
#38

Take a look at what's happening on the water side. Pomerico water is now a really strong business line for us nationwide. It got its start down in Texas, and these days it's spread throughout the street line. So I could keep going on and on about this. That's exactly why we feel so good about how diversified our business model is. And between 60% and 70% of our business still comes from what I'd describe as bread and butter.

Ben Kallo

analyst
#39

Yes. And if I could just follow up on that, regarding the additional controls and technology, are you finding that customers are now more willing to participate in virtual power plants or demand response programs?

Nicole Bulgarino

executive
#40

Absolutely, on the demand response side, simply because of these time-of-use rates and the peak capacity, with us going higher and higher each year. So I believe that's a significant element of these projects we're seeing — the controls needed to generate peak power.

George Sakellaris

executive
#41

Yes, and regarding the other item — the controllers, the built-in automatic features and all of that — it's quite sophisticated. We've acquired 3 small firms focused on built-in controllers, and performance has been excellent, truly excellent. We intend to expand that specific part of our operations, since it's gaining really strong market traction out there.

Moses Sutton

analyst
#42

And thanks for the useful updates on that $1.7 billion data center. I'm wondering whether any of these data centers have all their permits in hand and are simply waiting on other things — maybe on the turbines, cells, and so forth. Then, for the ones that don't yet have their equipment, do they usually have slots and pricing locked in? I'm just trying to get a sense of where those two sites stand, since they seem to be what would move things toward conversion into contracted backlog.

Nicole Bulgarino

executive
#43

I'd say permitting is quite close on a few of them, particularly our federal site, where we don't have some of the other local permits that are required at some of the commercial sites. As for equipment, either we hold reserves or we're indicating our schedule and cost based on when we finally lock that in. So there is room to adjust that.

Moses Sutton

analyst
#44

Great. Then perhaps a few quick follow-ups regarding the data center side. Arizona and Texas have come up from you before. Would it be fair to describe it as weighted toward either of those states? Is Texas the largest among them? And are these mostly bridge sites, in terms of the customer's power use? Or do they sit in more islanded situations over the longer term?

Nicole Bulgarino

executive
#45

So second, island in case longer term is what we're providing on these projects; so they'll be behind meter potentially could have the ability to connect to grid later, but for now they're islanded energy plants; and then on the first question.

Joshua Baribeau

executive
#46

The mix leans much more toward Arizona, it's fair to say. Still, at present we're looking at, I believe, 4 or 5 or 6 separate states, with a potential set of roughly 10 — 5 of those sit in the awarded backlog today, and the other 5 are working their way through the process. That said, Texas doesn't account for a heavy share; yet, as Nicole mentioned, that holds even for the projects located entirely behind the meter.

Moses Sutton

analyst
#47

Understood. That's really useful; and I suppose one final point — Josh, I believe you mentioned to me previously, regarding one of those solar projects, that there was in fact a project where the capacity ratio was oversized at 4 or 5x in order to run behind-the-meter solar as the main generation source. Does that remain part of the plan there? Or is this really entirely 6 turbines, fuel cell, and so on?

Joshua Baribeau

executive
#48

Yes. So my recollection isn't that it exceeded 4 to 5. It could have been around 2x or something along those lines, but this is the project we announced last year; although I believe it has been rescoped somewhat in California, correct?

Nicole Bulgarino

executive
#49

At this point it is entirely fuel cell, simply matching up with the federal targets for gas solutions on the federal side.

Operator

operator
#50

That brings our Q&A portion to an end. Thanks to each of you for being with us. You're welcome to disconnect at this point. Have a wonderful day, everybody.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ameresco, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Ameresco, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ameresco, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.