Aspen Aerogels, Inc. (ASPN) Earnings Call Transcript & Summary

July 28, 2022

New York Stock Exchange US Materials Chemicals earnings 73 min

Earnings Call Speaker Segments

Laura Guerrant

executive
#1

Thanks, Soram. Hello everyone, and I appreciate you being here for our conference call covering Aspen Aerogels' financial results for the second quarter of fiscal year 2022. Joining me on the line are Don Young, our President and CEO, along with Ricardo Rodriguez, our Chief Financial Officer. Before handing things to Don, I want to go over a handful of logistical reminders. You can locate the press release with Aspen's financial results and business developments, plus a reconciliation of management's non-GAAP financial measures against the most comparable U.S. generally accepted accounting principles, or GAAP, measures, in the Investors Section of Aspen's site, www.aerogel.com. That release contains a summary statement of operations, a balance sheet summary, and a summary of key financial and operating statistics covering the 2022 second quarter that closed on June 30, 2022. Also, please be aware that a slide deck has been posted to our site to go along with what we discuss today. It's available in the Investors section of our site. A recording of today's webcast will remain accessible on our site for roughly 1 year. Be advised that today's discussion contains forward-looking statements, which include anything about outlook, expectations, beliefs, projections, estimates, targets, prospects, business plans, and any other statement that isn't a historical fact; such forward-looking statements carry risks and uncertainties. Aspen Aerogels' actual results could differ materially from what those forward-looking statements express. Factors that might impact the company's actual results are listed in Aspen's press release from yesterday, on Page 1 of the presentation, and get more detailed treatment in the reports Aspen files with the SEC, especially the company's most recent annual report on Form 10-Q. You can also find Aspen's press release from yesterday and its SEC filings in the Investors Section of Aspen's site. The forward-looking statements given today reflect the company's views as of today, July 28, 2022, and Aspen Aerogels accepts no obligation to revise these forward-looking statements to account for future events or circumstances. On this call, we'll touch on non-GAAP financial measures, adjusted EBITDA among them. Such financial measures aren't prepared in accordance with GAAP. They shouldn't be viewed on their own or as a replacement for results prepared in accordance with GAAP. Definitions and reconciliations of these non-GAAP financial measures against the most directly comparable GAAP financial measures, along with an explanation of why we present them, appear in yesterday's press release. One last thing: during the Q&A session, to keep things moving, we'd ask that you restrict yourselves to two questions at a time. Should you have more questions past those first two, please rejoin the queue, and we'll address every question. I'll now hand the call to Don. Don?

Don Young

executive
#2

Thanks, Laura. Good morning, everybody. I appreciate you being with us on this Q2 2022 earnings call. I'll begin by giving you an update on how our financing efforts are going and what's new in the business, as I noted before, and then Ricardo will cover results and the outlook; after that we'll take questions. During the last 16 months, we brought in more than $300 million in order to grow a company aiming at $1.6 billion in revenue along with $400 million in EBITDA, as we work toward fully using our second aerogel production facility in the years ahead; the manufacturing capacity we already have supports our 2x revenue goal of $240 million for 2023, and we anticipate using Phase 1 of Plant 2 to hit our 3x revenue goal of $720 million for 2025. We anticipate continuing to bring in capital so we can construct the infrastructure needed to seize our complete opportunity. On June 29, we let it be known that we would not move forward with simultaneous public offerings of common stock and convertible notes. Even though investor demand was substantial, including a $100 million indication of interest from Koch Strategic Platforms, the broader market backdrop was not favorable. Consequently, it was decided that the terms of those offerings would not serve the best interests of Aspen shareholders. As we've previously stated, and as is particularly accurate given today's financial markets, we are pursuing an all of the above strategy for financing our growth plan. While we look into various possible sources of capital, we've stayed focused on strategic investors who are familiar with our company and the markets we operate in, and who could potentially make equity investments in the business, just as Koch Strategic Platforms did previously and expressed interest in doing once more during our June financing effort; beyond possible strategic investors and the public equity and debt markets, we are working with government programs as possible 2023 sources of capital for Plant 2; we submitted an application for a $150 million U.S. Department of Energy grant for advanced battery materials under the Bipartisan Infrastructure Act, which aims to back U.S. based companies committed to the electrification economy. We're also looking into additional DOE programs centered on battery performance and safety. These programs aim at American Manufacturing as a way to tackle supply chain resiliency in the U.S., particularly for projects in crucial sustainability areas like energy storage and related materials. Although these DOE programs may take time and can be unpredictable, we think we're a very strong candidate and that pursuing them aligns with our all of the above strategy for securing the capital we need to carry out our long-term strategy. We also think that as more public market investors get to know Aspen's story — with its secular growth trends and themes focused on sustainability — those investors, along with the ones we already have, will once more provide capital for a fast-growing, dynamic company such as Aspen Aerogels. Even with tough markets, we're confident we'll secure the funding needed to carry out our strategy of becoming cash flow positive in 2024 and delivering value to our shareholders. Thank you for your ongoing support. Our Q2 business results stayed solid even amid persistent supply chain and staffing difficulties. Q1 gave us a strong beginning to the year, with revenue growth of 37% year over year, and Q2 extended that momentum, posting 44% year-over-year revenue growth. First half results showed continued penetration in the EV market along with high activity levels in the energy industrial market. Given this commercial momentum and, naturally, our already awarded programs with General Motors and Toyota, we're confident we'll see high year-over-year growth rates in 2022, and we think we're well positioned to hit our $240 million revenue target for 2023. PyroThin thermal barrier revenue came in at $11 million, nearly $11 million in Q2, versus $7.6 million in Q1 and under $7 million across all of 2021; we expect multiyear thermal barrier revenue to be substantial, and we're investing now so we can meet that demand. We also acknowledge that automotive OEMs will occasionally be hit by their own supply chain difficulties, which could affect their growth ramps in any given period. We're working to build in optionality so we can manage overall revenue growth during this early phase of the EV megatrend, by keeping a deep order book on the energy industrial side of our business. The robust outlook for energy industrial is driven by pent-up maintenance demand, elevated energy prices, and strong long-term activity levels in LNG. This flexibility nicely illustrates the benefit of our strategy of leveraging the Aerogel technology platform across a diverse set of large and dynamic markets. I'd also like to give a quick update on Plant 2, our aerogel manufacturing facility being built in Georgia; with long lead time items purchased beginning in Q4 of last year, the first phase of Plant 2 is still on a projected timeline for completion in late 2023. Although the project isn't immune to challenges tied to supply chain disruptions and inflation, our team, supported by Koch Project Solutions, is focused on constructing a first-class aerogel manufacturing facility. The first phase of Plant 2 targets $650 million in annual revenue capacity and will lift our total annual revenue capacity to roughly $900 million. As we approach full capacity utilization at that revenue level, we're targeting EBITDA of approximately $225 million per year. There are reports suggesting the auto sector plans to put $0.5 trillion into the shift toward electric vehicles over the next 5 years, and given that, we think our position is strong when it comes to playing a meaningful role in battery performance and safety. Beyond what we're investing in Plant 2 over in Georgia and our high-volume assembly facility down in Mexico, we keep putting significant money into people, systems and automation. Thanks to those steps, we can scale quickly, reach positive cash flow in 2024 and cash in on what we've put into growing our dynamic business. We're also still putting money into the strategy of taking our Aerogel technology platform into other high-value markets that carry sustainability themes. Our teams have gotten a tremendous amount done this year, growing our intellectual capital position throughout the Aerogel technology platform, with more than 60 new inventions captured across 33 patent families filed or in draft year-to-date. Our belief is that these technology and new business development investments will keep proving how rich our aerogel technology platform is and build substantial shareholder value. Within Aspen battery materials, we expect our carbon aerogel initiative to be the next one in line for product commercialization. ABM has wrapped up the development phase for its next-generation silicon added material, which aims at both lower costs and higher energy density, and it's now getting qualifying materials ready for select automotive and battery OEMs. These enterprise-wide investments do call for capital and weigh on margins near term, but our view is that they set us up structurally so that — so that once Plant 2 is fully utilized, we're positioned to bring in $1.6 billion of revenue and $400 million of EBITDA, while also having the chance at potential additional breakout value from new businesses. There's still important work in front of us, but the progress we're making toward our goals gives me encouragement. And last, I'd like to keep up the practice of shining a light on our ESG work during quarterly earnings calls; for the past two decades, ESG has been tied to our business's success; exploring new uses for our aerogel technology platform, with the aim of improving environmental performance and safety in our customers' products and processes, is a natural fit for us. Respecting and celebrating our employees by working to build a diverse and inclusive environment also sits at the core of our culture. We believe we're responsible for making a positive impact on our communities, and we're dedicated to building a corporate culture that pursues its mission while holding to the highest standards of integrity; in the coming days, we'll release Aspen's inaugural ESG highlights report and launch our ESG web page, which will give a comprehensive overview of our overall ESG strategy. We look forward to hearing your feedback. I'll now hand the call over to Ricardo.

Ricardo Rodriguez

executive
#3

Thanks, Don. I'll begin on Slide 4 with our financial highlights for Q2. Turning to revenues: strong demand in every market we serve, plus successful execution of multiple throughput-improvement initiatives, let us deliver $45.6 million of revenue in Q2. That figure comes close to the company quarterly revenue record of $46.5 million set in Q4 of 2019, and it represents 19% growth versus the prior quarter along with 44% growth year-over-year. On a year-to-date basis, the team has grown revenue 40% year-over-year, reaching $84 million. Although we've noted that EV thermal barrier opportunities are materializing faster than initially anticipated, I'll first point out that our energy industrial revenues rose 13% from the prior quarter, hitting $34.9 million; the driver here is very strong distributor demand as we keep working through a meaningful backlog of deferred maintenance demand, keep displacing competitors' materials, and keep serving new projects built to tighter efficiency standards on shorter timelines. Achieving that degree of growth in our core business while also lifting our EV thermal barrier revenues to $10.8 million — a 42% sequential increase — shows our team's ongoing ability to produce the growth needed to hit our long-term objectives. Now I'll walk through our main expenses, while reminding everyone that even with the growth delivered this quarter, neither of our business segments is yet running at the annual revenue run rate required to properly absorb fixed expenses and achieve our target profit objectives. So we keep managing every cost element to make sure all our recent productivity investments begin producing results. I'll come back to this point in more detail and explain how implementing operational elements beyond merely having a bigger revenue base will drive meaningful gross profit increases; luckily, these elements call for no radical new process invention or development. Putting them in place and validating them is all that's needed. Material expenses for the quarter were $26 million, which accounted for 57 percentage points of sales — more than 10 percentage points above where we want them long term; right now this variance stems mainly from the scrap levels required to accelerate our EV thermal barrier throughput with processes designed for lower volumes, plus nonrecurring inbound freight expenses to ensure uninterrupted production. Several product design changes aimed at simplifying our assembly and cutting the number of parts in the bill of materials for our EV thermal barriers will help us tackle these nonrecurring costs. Conversion costs of $20.8 million reflected the final quarter of our thermal barrier assembly facility in Rhode Island delivering most of our production. To illustrate the burden of this, our temporary hourly labor cost at that facility was $4.5 million to deliver $10.7 million of revenues during the quarter. Taking a wider view, our energy industrial segment's increased revenue run rate allowed overall conversion costs to fall by 4 percentage points of sales versus the prior quarter, landing at 46%, or $20.8 million. OpEx — critical to hitting our 2023 revenue and profitability targets and beyond — came in at $21.4 million. That figure rose $4.6 million from the previous quarter, against a $6.7 million sequential rise in Q1. Entering the back half of the year, our OpEx growth will be smaller and aimed squarely at three deliverables: first, concrete productivity gains via new process development and rolling out systems that simplify how we work and lift productivity; second, fresh business wins from our EV thermal barrier technical sales push; and third, distinct milestones in R&D. Those cover our silicon anode and carbon aerogel work, plus R&D on our silica aerogel-based installation formulations. Such developments cut chemical waste costs through reformulation and open the door to throughput gains like extended rollings and quicker line speeds, all while holding the same quality standards. Consequently, our net loss widened to $24 million, or $0.68 per share, against a net loss of $6.7 million, or $0.23 per share, in 2021's comparable quarter. Adjusted EBITDA came in at negative $18.3 million for Q2, versus negative $3.4 million in last year's Q2. As a reminder, adjusted EBITDA means net income or loss before interest, taxes, depreciation, amortization, stock-based compensation expenses, and other items we don't view as reflecting our core operating performance; for Q2, those other items comprised $2.3 million of stock-based compensation and $1.4 million of interest expense. Now I'll move to cash flow and our balance sheet. Cash used in operations totaled $10 million, reflecting our adjusted EBITDA of negative $18.3 million plus an $8.3 million drop in operational cash needs, largely from a $12.9 million rise in accounts payable. Capital expenditures for the quarter reached $37.9 million, covering ground clearing and foundations, construction of Plant 2, assembly equipment for a higher-volume thermal barrier operation, and R&D lab upgrades for our carbon aerogel battery material work. With Plant 2 still on schedule to come online at the end of 2023, we have capitalized $62.5 million toward it through the close of Q2. Cash provided by financing activities during Q2 was $4.9 million, including $4.8 million in net proceeds from our ATM offering transactions at a gross average price of $20.18 per share. Year-to-date, we've raised $67.9 million opportunistically via ATM offering transactions at an average price of $14.46 per share. As Don said earlier, we are pursuing an all-of-the-above approach to raising capital. When we look across every market and channel, ATM products contribute only a minor piece of our overall financing activity; we closed out the quarter holding $162.2 million in cash, with zero amounts drawn on our revolving credit facility, and shareholders’ equity stood at $164.7 million. Our guidance for the year hasn’t changed. We’re positioned to bring in $180 million of revenue, with the possibility of reaching as high as $200 million, alongside a net loss somewhere between $79.8 million and $86.8 million, and adjusted EBITDA ranging from negative $55 million to $62 million. Capital expenditures this year should land somewhere from $250 million to $300 million, and generating $100 million to $120 million in revenue across the back half of the year would mean a 10% to 32% rise over our Q2 revenue run rate. That gain depends on a number of outside forces we don’t control, including whether our thermal barrier customers can hit the vehicle production volumes they’ve stated, plus the supply chain for our raw materials — things like silanes, batting, CO2 — and the local labor market, especially for our Aerogel facility in Rhode Island. We’re actively staying on top of supply chain risks and have made sure we’re stocked on silanes and batting so we can carry out our production plans. The recent CO2 shortages nationwide, combined with a tight labor market, pose the biggest near-term threats to keeping our plants running at higher throughput.

Ricardo Rodriguez

executive
#4

When it comes to managing CapEx, the inflationary pressures from Q1 aren't showing up in the same way, and we're being careful to make sure we're paying current prices on certain key commodities that go into Plant 2, rather than what some contractors paid when they stocked up earlier in the year. Moving to Slide 5, let me return to what I said before about profitability. In the quarter, our EV thermal barriers segment operated at an annual run-rate of about $40 million, and our energy industrial business was at an annual revenue run-rate of roughly $140 million. At those levels, we still aren't fully leveraging our overhead and fixed asset base. Once we exceed a run-rate of $150 million per year, our energy industrial business is capable of delivering gross margins of 20% or more. For our EV thermal barriers segment, we need an annual revenue run rate of approximately $120 million before it can deliver gross margins of 15% or more as production ramps in Mexico. Bringing in simpler designs and additional automation will help bring that run rate requirement down. Our EV thermal barrier business has been quoted to hit our target margins at capacity, and pricing conditions in our energy industrial segment are strong enough to allow price increases that apply to every order fulfilled in 2023. In addition to fixed cost absorption, our operating plan contains several initiatives we're carrying out across both segments to pave our way to 35% gross margins at full capacity. On this slide, we want to show you how executing specific initiatives in our operating plan will produce gross margin gains as our revenue grows at the same time. As I said before, we aren't reinventing processes and take on no technical risk in doing this; it's just about completing these initiatives, as we've done year-to-date with the successful start-up of our thermal barrier assembly facility in Mexico. A significant operational transition is underway in our EV thermal barrier business. As mentioned earlier, output over the last three quarters has come from a set of low-volume processes at a manual facility in Rhode Island. To give you a sense of this, thermal barrier assembly hourly staff at that facility grew from 278 at the end of November of 2021 to a peak of 428 in June of this year. As of today, we're back to 280 people, and we have roughly 600 people in Mexico, ready for the volumes of the remainder of this year and 2023. As this work shifts to Mexico and we bring in processes built for higher volumes, our conversion costs will drop substantially and lift our gross margins by more than 30 percentage points in 2023. For Q1 of next year, we've also planned a range of automation processes for Aerogel encapsulation and thermal barrier part assembly; these will cut our conversion costs further by shortening cycle times and lowering labor cost per part, while also raising our production yields. Cutting down on the number of parts by rolling out different engineering modifications and collaborating alongside our customers is likewise simplifying how we operate, helping us on pricing, and pushing productivity across the coming 2 years; over in our energy industrial business, managing the portfolio, running products for longer stretches with fewer changeovers, and reformulating our base chemistry so we spend less on chemical waste will keep fueling decreases in conversion cost. Extending how long insulation production rolls and boosting line speeds will lift productivity by Q4 of this year. Our supply chain group, which we recently grew, is also doing more than offsetting the added fixed costs through smoother logistics and by pushing raw material negotiations in line with our bigger scale. Georgia's Plant 2 will additionally strengthen our overall cost position thanks to a linear process needing minimal manual material handling plus circular processes for key chemicals including CO2 and ethanol; this will cut our material costs substantially, together with our environmental footprint and what that footprint costs us. The margins we're aiming for also account for the DNA of Plant 2, which will take effect once it starts up in 2024 and as we expand into its full capacity. As is clear here, our strategies don't simply depend on bigger revenues to lift profitability. The bulk of the gains stem from successfully executing productivity enhancements and starting up operations in flexible, more productive sites with processes built for larger volumes. This approach sits comfortably within what our present team can deliver, and recent milestones keep our motivation high to stay on our course toward 35% gross margins of capacity. Moving to Slide 6. We'd like to give a quick market update covering what we're observing in the automotive EV space, how those dynamics confirm our strategy, and what impact they're having on our commercial talks with the most significant OEMs globally. Here, you can see that seven of the top eight OEMs, which are projected to control more than 65% of the EV market, are concentrating on high energy density, high nickel content chemistries. They're also concentrating on prismatic or pouch cell form factors. Such configurations are the most compatible with cell-to-cell barriers such as PyroThin. A number of OEMs are additionally assessing lower energy density chemistries like LFP, and we're actively quoting LFP programs too. Looking at the market, we find PyroThin incompatible with no fewer than 19 million vehicles. And what Piper Sandler projects as a 24.7 million unit market in 2025. We're establishing the market for aerogel-based cell-to-cell barriers. We achieve this by capitalizing on the creative thermal isolation, fireproofing and mechanical characteristics of our material, taking a system-level approach and establishing unmatched scale. Ultimately, the market's size and the distinctive solution that PyroThin's positioning offers make for an ever more persuasive opportunity. Moving to Slide 7. At this point, we have additional positive developments to share, along with a recap of certain key United Nations worldwide transport mandate changes concerning EV safety, which are drawing greater attention to thermal propagation and thermal runaway globally. At present, this matter isn't foremost in buyers' thinking, given that EVs account for under 10% of the new vehicle market, yet it will grow in importance once EVs represent a larger portion of the worldwide vehicle fleet and exceed 25% of global new vehicle sales in 2025. These revisions to international transport mandates aim to give motorists a 5-minute alert designed to allow time to exit the car when a hazard arises from thermal propagation or runaway within one cell. Existing battery management systems are capable of setting off such an alert already, though the challenge lies in delivering 5 minutes or more of protection. Through PyroThin, we can help OEMs transform what is today a catastrophic occurrence into one that can be serviced. The GTR changes turned into compulsory new vehicle regulation for new vehicles during the previous year in China, South Korea and Japan; implementation in the U.S. is under review.

Ricardo Rodriguez

executive
#5

Later this year, with implementation in India occurring next year, this will assist OEMs in satisfying those warning mandates while also delivering genuine safeguarding in those uncommon instances involving thermal propagation and runaway. Plus, proactively building up our capabilities and scale so we can match their specifications guarantees we hold onto our leading spot as we establish this market. On Slide 8, you can see how our market building work has paid off, where we aim to give everyone a precise and useful picture of what we've accomplished commercially. Within this graphic, each circle's diameter represents the projected vehicle volume in millions that Piper Sandler anticipates for these OEMs during 2025, while its position indicates roughly where their headquarters sits. The circle's hue indicates whether we've secured an award from that OEM, are currently quoting them, are in testing, or have no activity with them. Unsurprisingly, GM and Toyota appear as the red circles, corresponding to 2.3 million vehicles across North America and 0.5 million vehicles in Japan, respectively. As you can observe, our group has managed to reach the quoting phase during the past 18 months with the biggest customers throughout Europe and Asia, who will matter globally in 2025. We're confident in their capacity to turn this engagement into further awards within the coming 12 months, and we're pleased that the worth of these quotes exceeds the worth of our existing awards with GM and Toyota. As everyone is aware, when these awards land depends on an OEM's own readiness to grant the business, and we'll communicate as openly as we can once these awards take shape. Gauging the worth and likelihood of these quotes sets us on a course to become an organization with $1.6 billion in yearly revenue capacity, producing more than $400 million in EBITDA soon after we hit our near-term targets through 2025. With that said, I'm pleased to hand the call back over to Don.

Don Young

executive
#6

Thanks, Ricardo. Ahead of opening things up for questions, let me restate a couple of key items. To start, our EV and energy industrial segments are both performing well and giving us a supportive environment as we work toward the revenue goals we've set for 2023 and 2025. And next, we're putting all our attention on converting the money we're investing right now into an operation that generates positive cash flow in 2024 and is moving toward its longer-range objective of $1.6 billion in revenue and $400 million in EBITDA. Param, please open the Q&A. Thank you.

Eric Stine

analyst
#7

Good morning, everyone.

Don Young

executive
#8

Hi, Eric.

Eric Stine

analyst
#9

Hi there, and to begin with, I appreciate what you did with Slide 8. That’s an excellent slide, really full of useful detail. So thank you for putting it in. Maybe if we just consider how much more is happening on the EV front, I’d like to know what role scarcity value plays in that, and how it factors into your conversations and the planning you’re doing on your end as you move toward Phase 1 of Plant 2?

Don Young

executive
#10

Well, I’ll begin simply by noting that showing we can expand our capacity matters. Like we’ve often stated, we already have enough capacity to hit our 2023 targets, and for our 2025 revenue targets we’ll be depending on Phase 1. Yet there’s more to it than that. We understand that even looking at the 2025 timeframe, when you add up energy, industrial, General Motors and Toyota, that accounts for a substantial majority of that capacity. So it matters that we keep proving to this next wave of OEMs that we’ll be able to supply them. And we believe we’re doing well at getting that across.

Eric Stine

analyst
#11

So at this point, I mean, it seems like right now that isn't really something OEMs are worried about, even though I'd imagine it's the kind of thing that pushes them to — since this matter carries so much weight, they might want to move ahead in the queue when it comes to the choices they're making regarding the quoting work you've completed?

Don Young

executive
#12

I'd say that's reasonable, Eric. I'd say that instinct of theirs is reasonable. And it's — once more, it's a piece of how we communicate when we head out and secure this upcoming group of awards.

Eric Stine

analyst
#13

Right. Then regarding the second item, namely the fire containment capability — that appears to be something quite significant that you can deliver? So, which kinds of learners are you observing across the industry — and how does that factor into the speeding up of activity too, turning it into more of a service occurrence instead of something catastrophic, as you described it?

Don Young

executive
#14

Well, the way I view it, and Ricardo, I believe, put it clearly, both in the script and on the related slide, is that we are starting to see some regulatory standards put into practice. Those, I believe, are favorable to us, without a doubt. The majority of the OEMs we work with are establishing a safety benchmark that is higher than those minimum requirements. And we have talked about this publicly before: our efforts and the way we design our products aim not just to reduce the spread, but to separate out the faulty cell; and that represents a very significant shift in mindset compared with having that catastrophic fire that everyone knows about, moving instead toward a service event affecting a cell or a module itself that can be swapped out, once again, in a way more oriented toward service rather than replacing the entire vehicle. So we consider those standards to be great. We have never truly depended on regulatory factors to propel our business, yet we regard those as fundamental and highly beneficial for our business.

Eric Stine

analyst
#15

Okay, thanks a lot.

Don Young

executive
#16

Thank you, Eric.

Ricardo Rodriguez

executive
#17

Thanks.

Alex Potter

analyst
#18

Excellent, many thanks. Hey, everyone. I only have one thing I wanted to ask about. This slide is quite interesting — number 8 — and it's good to see so much quoting going on, even, I believe, in places beyond North America. That said, one thing I'm wondering about: clearly, Altium will mostly be a platform for North America. Yet a number of these other OEMs, whether in Europe or Asia, obviously have their own platforms and their own regional strategies. A lot of those spots sit quite a distance from Georgia. So how big a worry is this when more and more customers want localized battery supply chains? Can you serve everything they need from Georgia? Or are some of them demanding additional localized capacity in Europe or Asia to back their own ramps?

Don Young

executive
#19

Yes, that's a really good point. The way we look at it right now, and the way we've explained it to the OEMs, is this: we'll have our first $1.6 billion of revenue capacity in North America, split between our plants in Rhode Island and Georgia; however, we're also making a commitment to have fabrication assembly facilities on a regional basis. And much like our North American operation, which is mainly growing very fast in Mexico, it's obvious to us that a European OEM is going to want that capability and want to shift that supply chain — that piece of the supply chain — nearer to its own assembly plants. So — and I suppose I'd add that even though we put the circle, so to speak, on their home turf, a lot of these firms operate globally, so in their locations. The regional locations, I mean. Anyway, so we're keeping that in mind, Alex. And I believe that depending on how demand develops for us over time and as we get Plant 2 fully utilized, we'll definitely keep in mind that mix, the geographic mix of our business, when we consider building a second plant. Right now, we're very focused on Phase 1 and Phase 2 of Plant 2 and on reaching that $1.6 billion of revenue together with the $400 million of EBITDA target.

Alex Potter

analyst
#20

Great. Perfect. Yes, one thing at a time. Okay. So for my second question, you brought this up a few times during the prepared remarks. I'm hoping you might be able to go into more detail. It sounds like you may be dealing with some staffing bottlenecks. It sounded like that was mainly in Rhode Island, but it also sounded like you had — now that the Mexico facility has opened up, you're able to, I guess, downsize a bit in Rhode Island. So if you could just maybe go into more detail on hiring, staffing, any potential problems you're having either in Rhode Island or in Georgia, that would be helpful as well? Thanks.

Don Young

executive
#21

Yes, thank you, Alex. Over the last six months, we've boosted the number of workers at the aerogel production plant. Late last year was somewhat difficult for us — especially the fourth quarter — as we moved into this year and the second quarter. Now that it's July, we've achieved solid improvement in getting people into that site. Because of that, it's a smaller problem for us now. Also — and Ricardo basically touched on this during the margin discussion when talking about what steps we're taking to get better — right now, while we're ramping up, we've got duplicate efforts taking place. So, regarding the shift from the Rhode Island assembly operation over to the Mexico assembly facilities — Mexico is genuinely intended for the large volumes we're scaling toward. At present, we've essentially got both running, and that won't be necessary moving forward. I'll always keep some capability here, though it will lean more toward prototyping or the very early-stage work we take on. So by removing those duplicate activities, and by clearing out — by getting certain non-recurring activities off our income statement, we will see our gross margins improve substantially. That's something we're highly focused on.

Ricardo Rodriguez

executive
#22

Absolutely. One more important point I'd highlight, especially regarding the aerogel facility located in Rhode Island: an incentive program has been developed by our HR group together with the operations group, and its purpose is to help us hold on to employees. I realize I already noted that more than 200 individuals remain on the thermal barrier assembly side in Rhode Island, and that figure is going to fall to under 100 prior to the close of this month too. So in Q3, that shift is genuinely happening quite fast. Therefore, even as we are calling attention to the risk, we believe the team has put sufficient measures in place to bring it under control.

Don Young

executive
#23

Sure.

Alex Potter

analyst
#24

All right. That's great. Appreciate it, everyone.

Don Young

executive
#25

Thanks, Alex.

Chris Souther

analyst
#26

Hi, everyone. I appreciate you fielding my question. Would you mind giving us some additional detail regarding the commercial progress slide? How exactly ought we to interpret quoting and testing relative to how you previously framed the three stages? Is it reasonable to view testing or quoting as essentially the final milestone prior to Toyota and GM orders arriving, and perhaps the durations involved from the various steps with GM and afterward Toyota, plus how that timeline either contracted or stayed the same, would be useful.

Don Young

executive
#27

Sure, the quoting phase definitely falls within the Stage 3 portion of what we previously called the Stage 1, Stage 2, Stage 3 serve concept; and testing, I'd say, sits firmly in what would likely be the later portions of two, applying those same concepts. However, at the point we quote, we've already completed a substantial amount of testing and qualification, covering quality systems all the way through to product performance and specifications. So this represents quite a late point in our development efforts with any given OEM; therefore, those blue circles visible on Slide 8 certainly reflect Stage 3 activity that we're working to convert into awards across the next two, three, four quarters.

Chris Souther

analyst
#28

Understood. Alright, so next, when we look at that awarded OEM projection you're anticipating, plus the ranges you've mentioned, those relate to content per vehicle. It seems you folks are taking a fairly cautious stance with that $540 million 2025 PyroThin goal, whether on volumes or on content per vehicle. So perhaps you could walk us through where you believe you're positioning yourselves especially well, because clearly, if it lands toward the midpoint of that, we're already talking about filling Phase 1 of Plant 2 quite fast; so I just wanted to understand how we ought to frame that, and also whether our content per vehicle is still arriving in that range you initially discussed — or not initially, but later on, the one you're referring to?

Ricardo Rodriguez

executive
#29

Yeah. This is a fascinating one, I'd say. What we're observing is a disparity in content per vehicle when comparing prismatic cell setups with those OEMs where our technology is being placed between pouch cells; so, for instance, Altium uses pouch cells; consequently, their content per vehicle — some are far beyond $1,000 per vehicle, yet we believe it will stabilize near $600 per vehicle. And you're correct. When we consider all the outside estimates of GM's volume, or Piper Sandler's figure here on Slide 8 at 2.3 million in 2025, that would place us considerably higher than the $540 million we've stated thus far for thermal barriers. We're in the process of forming our own evaluation of where GM's volumes will actually end up and where the CPV will settle. As of now, we continue to believe that tripling revenue, with that blend of thermal barrier and energy industrial revenues in 2025, remains correct based on the best of our knowledge and with all the visibility of the information we possess. But yeah, there's certainly an opportunity to — in which we might very well end up in a scenario here, needing to speed up the construction of Phase 2 so as to handle an enlargement of the existing awards along with these additional awards that the commercial team is in the final stages of.

Don Young

executive
#30

There's another point I'd like to bring up, Chris. When you consider the full range of General Motors' lineup along with the vehicle — the model we're partnered with Toyota on — GM honestly began with some rather sizable vehicles. And when you examine the rollout schedule they've laid out so clearly spanning 2023, 2024, and 2025, you end up with a pretty wide assortment of vehicles, among them some smaller ones with higher volume. We're aware that those particular vehicles contain fewer modules within the battery pack, and CPV tends to follow from that. So your question is quite a valid one, and we're keeping it in mind. I believe we've kept working to get people to concentrate on CPV somewhere in that $300 to $350 area, despite the fact that today's figures sit above that level.

Ricardo Rodriguez

executive
#31

This also explains, I suppose, the reasoning behind how Phase 1 was defined in scope. When examining the CapEx for Phase 1, it comes to roughly $200 million in equipment, situated within a $375 million building that's already set up to accommodate both phases. That means we can pull in Phase 2 with roughly 12 months' notice whenever we need to. So at this point, if those quotes turn into awards, accelerating Phase 2 is quite possible; that's exactly why we're thinking about the $1.6 billion revenue mark and $400 million of EBITDA down the road.

Don Young

executive
#32

Correct. The money we’re putting into Phase 1 to build out the infrastructure that will serve both phases — Phase 2 included — we figure will run about another $125 million. Obviously, though, we’re laying out that cash early so we can stand up that second wave of capacity at Plant 2 more quickly. That’s yet another illustration, and Ricardo and I covered this in our prepared remarks, of the investments we’re currently making so we can handle the volumes we expect across 2023, ‘24, and ‘25. Whether it’s people, processes, or automation, we’re plowing a substantial amount of that money in right here in 2022 to get ourselves ready for those bigger volumes. We recognize it’s squeezing our margins right now, but we genuinely believe that when you combine it with the steps Ricardo laid out in his script — those two things, sound business practices plus what’s in our margin walk, along with capturing the benefit of those larger volumes — the arithmetic comes out quite favorably for us as we chase that 35% gross margin figure we’ve been talking about.

Chris Souther

analyst
#33

All right. No, that's quite useful. And if you total up everyone you're already mentioning, 1.6 probably isn't sufficient in this case. If you managed to win it all, correct? So I'm wondering, how would you consider capacity past that point? Is there more room near the facility where a Phase 3 could go, or do you figure you'd seek to construct somewhere else, building on what someone else asked?

Don Young

executive
#34

Yeah. That's — those are excellent questions; and given that, we genuinely attempt to concentrate on getting ready for success, and we believe we're accomplishing that through many of the investments we're making at this time. I think that once we've got a plant running at full capacity to reach that $1.6 billion revenue level and producing a substantial amount of cash within the business, we'll probably want to put up our third aerogel manufacturing facility in a different place and very possibly at an international site, which circles back somewhat to Alex's question too, that those OEMs might quite well desire to make that supply chain shorter. And we believe it would make a great deal of sense for us to proceed that way, to consider it in those terms.

Ricardo Rodriguez

executive
#35

Right, and one more item to point out regarding Slide 8 — what we have here aren’t really the quantities we’re committing to with those OEMs; rather, this reflects the market sizing for the EVs that the 5% forecast projects those OEMs will sell in 2025. For a lot of these quotes, the platform we were quoting represents only a portion of their overall EV volumes, or a nameplate still being introduced beyond 2025. So we believe we can operate comfortably inside the 1.6 billion over the coming 3 years to 4 years.

Chris Souther

analyst
#36

Okay. That’s very helpful.

Don Young

executive
#37

Thank you, Chris.

Colin Rusch

analyst
#38

Sorry about that — Colin here. I'm on the call now, everyone. So, looking at the energy industrial revenue and how varied the customers are, it seems like you're doing well when it comes to growing that customer base, and also the visibility on growth between this year and next year, which appears quite substantial.

Don Young

executive
#39

It's genuinely rewarding. This market is where we started. Naturally, we've got a very strong team worldwide supporting that business. It remains a business, even as we're experiencing tremendous growth here in the U.S. Outside the U.S., it's still the majority of the business. So I really like the geographic footprint of the business, so to speak. I'd add that the diversity is also quite outstanding when it comes to the range of applications we serve. Maintenance work remains a key part of that business, and maintenance work has always struck us as being a lot like base load. Setting aside the COVID interruption, that business has grown nearly every quarter since we brought those products out on the maintenance side. Then we get somewhat bigger swings on the project side. And we're seeing interesting project opportunities in our traditional sort of pipe and pipe, subsea pipeline activities, but also, of course, in the LNG business, both on the liquefaction side and on the receiving terminal side, really in all regions. So we're really excited about that business. Sometimes, I think it gets lost in our discussions about the EV mega trend, for sure, but it's a significant business that we think we can keep growing. And we also believe that our products focused on efficiency, asset resiliency and safety are spot on as these facilities think about their own ESG goals and sustainability commitments. So, again, I appreciate the question. It's really an important part of our business.

Colin Rusch

analyst
#40

All right, that's great. Now regarding the capital expenditure figures, it appears roughly $66 million to $67 million was used by the close of 2Q. There's still a pretty significant chunk remaining — 200 or perhaps a bit above that for the rest of this year's plan. Could you give some detail on how that spending is expected to be timed? And is any portion of it something you could push into next year without genuinely affecting timelines?

Ricardo Rodriguez

executive
#41

Yes. What I'd say is there's a solid opportunity to push back part of the Q4 outlay, which would be roughly $150 million; and for this quarter, capital expenditures look likely to land somewhere from $70 million to $100 million. What we're actually finding is that costs are arriving afterward compared with what we initially anticipated. Even so, there's a strong possibility that something like 15% to 20% of the entire capital expenditure budget for this year carries over into the following year.

Colin Rusch

analyst
#42

All right. That's really useful. Thanks a lot.

Don Young

executive
#43

Yes. We're paying close attention to that, Colin. As you'd expect, we need to weigh, clearly, our balance sheet and how important it is to get Plant 2 built on schedule. So, we're concentrating hard on ensuring we're in solid position on both of those matters. Thank you.

Colin Rusch

analyst
#44

All right, thanks.

Tom Curran

analyst
#45

Thanks, and good morning.

Don Young

executive
#46

Morning to you, Tom.

Tom Curran

analyst
#47

Regarding thermal barriers, my modeling of your guidance indicates you ought to reach an annual revenue run rate of $120 million during the second half of next year — so possibly only 12 months to 15 months away — and at that run rate you anticipate achieving a gross margin of 15%. Ricardo, could you please walk us back through and bridge the anticipated gross margin climb from the deeply negative level currently being posted at $40 million up to 15% at $120 million. Would you kindly itemize and quantify how much each driver is expected to contribute toward that targeted margin gain?

Ricardo Rodriguez

executive
#48

Certainly; so, by conversion, I noted in my script that over 30% of an improvement, at least in 2023, when we look at the full year, we think that will be closer to 35% as we think about that; next, our capacity to better absorb fixed expenses, that accounts for roughly another 10% improvement. Then certain engineering changes we are putting in place are in fact bringing down total material cost too. And that is — I believe we are being somewhat conservative in how we evaluate that, but it might land anywhere from 1 to 5 percentage points of sales here once things settle out. Logistics, as we shift from shipping aerogel from — as we move toward shipping less aerogel since our yields in Mexico are getting better, that represents roughly a 6 percentage points improvement in 2023. And once we combine all of these, that is what brings us to that positive 15 plus on a run rate basis nearer to the third quarter of next year. That is, I think, the way it would break down. I mean I think the negative 66% of Q2 cannot be entirely walked to the 2023 point because of the variable labor expense — of the temporary labor expenses that I outlined, right. So, if we take that out…

Tom Curran

analyst
#49

Right. That explains why it wasn't included in that $40 million annualized figure, since it was at a full negative 66%, just deeply negative, correct?

Ricardo Rodriguez

executive
#50

Precisely. So I think when we look at Q2 — Q1 was better, Q2 got worse. Q3 will likely be roughly flat, and then our improvements should really take hold in Q4.

Don Young

executive
#51

And it really goes to a lot of these…

Tom Curran

analyst
#52

So should we really treat the first half of 2023 as the major inflection point?

Don Young

executive
#53

Correct.

Tom Curran

analyst
#54

That shift to being profitable, and then reaching a gross margin in the double digits.

Don Young

executive
#55

Correct. Most of the overlapping operations we currently have will be gone. A great deal of the one-time costs we're carrying while we ramp up right now will also have been dealt with, and those items are significant factors behind these figures too, particularly when you set them against where we sit in Q2 and Q3.

Tom Curran

analyst
#56

Excellent. That's useful. I appreciate it. Now regarding that DOE grant application for $150 million, when would the following milestone occur on the road to approval, and what would it involve? And assuming you meet the criteria — which, to my mind, you clearly ought to, since you strike me as a perfect fit — when ought the grant to be disbursed?

Don Young

executive
#57

Our capital would feel the effect during 2023. As for how this unfolds, Tom, it will take shape across the coming 6 months. Such matters tend to be somewhat unclear, yet our advisors are solid and our involvement is deep, plus we believe the application we've put together for this grant is outstanding. Our engagement with DOE is strong. So once more, it's somewhat tricky to — as I believe my script noted, these situations develop in a rather unpredictable fashion. Still, I'd say we're a strong contender, and it aligns perfectly with our all of the above approach. Where we currently sit leaves us, I'd say, feeling encouraged. That said, we'll provide updates — on a quarterly basis, without fail — as we move forward through the process DOE has laid out.

Tom Curran

analyst
#58

That's great. Wishing you the best with it. Thank you.

Don Young

executive
#59

Thank you, Tom.

Amit Dayal

analyst
#60

Thank you. Good morning everyone.

Don Young

executive
#61

Good morning Amit.

Amit Dayal

analyst
#62

I think everything I wanted to ask has been covered already. Only thing left is on the battery development front. Is there anything new you can share? Has the company gotten any nearer to starting tests and so forth with customers?

Ricardo Rodriguez

executive
#63

Yeah. On that front, the testing possible with coin cells has essentially been maxed out, and we're now shifting over to work on bigger pouch cells. While doing so, it clearly makes sense to partner with companies whose specialty lies in producing larger form factor cells, and that is precisely where the team's attention is at present — genuinely working to establish the right relationship, which would let us speed up our testing given the encouraging results seen so far with coin cells; and once that happens, that is when the pace of validation will really pick up in the second half, as we work toward hitting our goals for the year.

Don Young

executive
#64

Over the last 12 months, we've put some significant money into that team as well as equipment, and it's paying dividends. As I mentioned in my script, we're now capable of — and are in the middle of — turning out what we call qualifying materials, and those are headed to a chosen set of automotive and battery OEMs. So we'll watch that unfold over the next few quarters. This isn't something that happens quickly. We don't underestimate how this works, and the technical progress we're achieving, we believe, is outstanding, from both a performance standpoint and a cost standpoint. And we also have real faith in the market itself — meaning the significance of bringing silicon in at higher percentages into lithium-ion batteries as a way to boost energy density and drive range.

Don Young

executive
#65

Got it — that covers everything from my side, folks. I appreciate it, thanks. Don Young here: thanks, Amit.

Chip Moore

analyst
#66

Thank you. Good morning.

Don Young

executive
#67

Good morning.

Chip Moore

analyst
#68

I'd like to ask a bit more about the DOE funding. You ought to be a strong contender for that grant, and I agree with that; however, what really interests me is Altium getting their conditional loan approved. Could that speed up PyroThin sales, or is that mostly already baked into what they've planned?

Don Young

executive
#69

Yes; that was fantastic. It came under another program, yet the themes were the same, correct? Also, that was a loan, while we went after a grant; even so, what General Motors and LG, I believe jointly, received through that process gave us encouragement, since I think the reason we haven't raised our figures to GM is that. Still, it's just really encouraging to us that the business gets strong backing, internally from General Motors and LG and externally through programs like this one worth $2.5 billion from the DOE.

Chip Moore

analyst
#70

Got it; that helps. One last thing from me. Regarding Battery Materials, you mentioned certain qualifying materials. Could you provide some indication of how big a substitute for graphite these initial materials might represent, and perhaps some sense of the roadmap toward later versions?

Don Young

executive
#71

Sure, a great deal of this is what we're currently working through. Targets of 20% to 40% replacement — or rather, silicon content — have been laid out by our team. Obviously, that's quite a wide band; and often, that band relates as much to the chemistry overall and the system, so to speak, as to what our material can do. Thus, we believe that band will shift depending on the cell maker and the battery's own design. But significant gains compared with the comparatively modest quantity of silicon found in certain lithium-ion batteries today, which is typically single-digit at best.

Chip Moore

analyst
#72

Prefect. Alright. Thank you.

Ricardo Rodriguez

executive
#73

Thanks Chip.

Don Young

executive
#74

Thanks, Chip.

Don Young

executive
#75

Appreciate it, Soram. Grateful for the assist. We're thankful that everyone's taking an interest in Aspen Aerogels. The work we're doing has us really enthusiastic, and we're wrapping up the year on a strong note, plus we're eager to share our third quarter 2022 results when October comes. Cheers. Enjoy the rest of your day. Many thanks.

Operator

operator
#76

That wraps up the conference call for today. We appreciate everyone for joining in. At this point, you're free to disconnect your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Aspen Aerogels, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Aspen Aerogels, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Aspen Aerogels, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.