Atalaya Mining Copper, S.A. (ATYM) Earnings Call Transcript & Summary

November 12, 2026

London Stock Exchange GB Materials Metals and Mining earnings 32 min

Earnings Call Speaker Segments

César Sánchez

executive
#1

Good morning, everyone. This is the Q3 financial result presentation for Atalaya Mining; in the presentation, we start with a disclaimer, which I recommend you go and read if you're going to rely on any of the numbers included in the presentation. Today, unfortunately, Alberto isn't with us. He had a last-minute issue, so it's just going to be me presenting. I'm César Sánchez, the CFO of the company, and I'll do my best to give you a good presentation today. If we go through the presentation, you'll see these main topics summarized here on this slide. We're going to talk about operations and how we're well on track to basically meet the guidance we reported to the market. We'll also go through the quarter's financials and the year-to-date financials, and we'll describe the revenues, the EBITDA, and the figures we're reporting as of today. On the corporate side, I'm going to pause here for a second as I run through these four points you have there. All resolutions were passed at the AGM. That's good news. Some of them came in below 80%, so if you're a shareholder or a significant shareholder, we've probably contacted you about those resolutions below 80% just to understand how we can do better. That's part of the commitment of management and the Board of Directors to get all resolutions above 80%. Also, in early Q2 this year, we announced the acquisition of 7.3% of Lara Exploration; this is something we want to keep an eye on, this asset in the base in Brazil. We want to see how it develops and whether there's any opportunity to explore for business with them. We also completed, that was in January 2026, an equity offering for GBP 130 million, or EUR 150 million, and that was to support the development of the Atalaya Copper growth pipeline, which I'm happy to describe and stop. We have a couple of slides on the acquisition we completed yesterday; this is Tharsis Mining, which owns past-producing deposits such as Tharsis and La Zarza, and we're located quite well close to Riotinto; as I was saying, we have a couple of slides for this transaction. Moving on to the next steps, the next is assets; we're going to describe how we're getting on with Touro, the investment in San Dionisio, and the polymetallic at Riotinto, Masa Valverde. These are some of the topics we'll be touching base on during the presentation. Finally, on the sustainability side, we continue with our commitment to improve not only the rating, but also the information, the quality of information for the ESG, and I think we're getting much better this year. If I give a quick description of what we did in Q3 2026, from a production standpoint, we turned out close to 14,000 tons of copper. That matches what we expected, so it lines up with our forecast. You can see in the graph here that Q1 of this year came in a bit low, and this quarter is essentially making up for some of the copper we didn't produce in the first quarter. Throughput and recovery were once more slightly above our expectations. We processed 4.1 million tons of ore, which had an average grade of 0.4% copper, allowing us to recover about 84.26% of that copper and produce a concentrate containing 17.07 copper. That concentrate is a bit below the standard 20%, but given the situation in the copper concentrate market, we aren't facing any kind of problem. Quite the opposite, we're getting good TC/RC, which is helping the company's revenue line. On a year-to-date basis, sorry, in the Q3 financial result, meaning the standalone quarter, we are again reporting record revenue and EBITDA for the quarter. You can see the revenue figures there at up to EUR 187.9 million, and after deducting operating costs, we arrived at EUR 90.1 million EBITDA and a profit of EUR 62.9 million. You can see again the revenues in that graph at the top right. You can see the revenues graph and how this revenue stacks up against historical quarterly revenues. On the cash flow statement, we report an operating cash flow of EUR 57 million. Again, that's somewhat above the same period last year; on investing cash flow, we report an investment of EUR 19.8 million, which is to sustain all the capital work we're doing at San Dionisio and Cerro Colorado. On financing cash flow, we report cash used of EUR 38.7 million. That's mainly made up of EUR 20 million of debt repayment, and you'll see here the borrowing, how it came down significantly from the prior quarter, plus the dividend we paid during the quarter. Altogether, free cash flow, which is operating cash flow minus investing cash flow, for the quarter we report EUR 37.2 million, which again, I think is a good number, and it's increasing the company's cash position. You can see here that we report a cash position of EUR 354.1 million, which, after deducting the EUR 11.9 million in borrowings we have, leaves the company with a net cash position of EUR 342.1 million. Working capital surplus of EUR 333 million. I should note here that we had two shipments of concentrate that were sold, but we didn't have enough time to cash the two invoices as of September 30th. So the cash came in over the next few days, but what that means is our accounts receivable went up by roughly EUR 35 million because of those two invoices. Those invoices have now been received. Clearly, cash will end up much stronger than what we're showing here. Turning to the financial result on a year-to-date basis, once again we're reporting a record nine-month EBITDA and operating cash flow. You'll note that EBITDA for the nine-month period stands at EUR 216.3 million. That's a pretty solid figure. Essentially, the operating cash flow we generated from that EUR 216.3 million of EBITDA comes to EUR 165.6 million. Again, I'd say that's a good number when you set it against the investment we made during the period, which was EUR 69.7 million. Financing cash flow, at EUR 93.4 million, is higher on a year-to-date basis, largely because of the equity raise we completed early in the year. Free cash flow, once again figured as operating cash flow minus investing cash flow, is EUR 95.8 million. On cost, as you can see on this slide, overall cost has been in line with guidance.

César Sánchez

executive
#2

During the quarter we saw a modest effect, primarily on mining and processing costs. That effect stems largely from increased prices for diesel, explosives, and electricity. It has nothing to do with Atalaya; it is tied more to inflation stemming from the continuing geopolitical conflict. On offsite costs, you can see we keep getting solid, adequate byproduct credits from silver. If you make the comparison with credits in the prior quarter, though, you will notice the credit is a bit lower, and there are two main reasons for that. First, silver prices have come down relative to earlier in this year. Second, we recorded some unfavorable negative settlement adjustments on prior sales of silver in concentrate. Freight this year, along with all offsite costs, remains near 0.38. Compared with the prior year, I would call that fairly low, driven mostly by TC/RCs and by the negative TC/RC we get on spot sales. On freight, comparing again, it is holding in the $70-$80 per ton range. Overall, cash cost for the quarter came in at $2.89 per pound. Once more, that is a touch above the prior quarter. Year to date, we stand at $2.60 per pound, and although inflation has had some effect, we remain in line with the guidance we gave the market; there is another slide now showing that guidance, and we are confident we will land inside the range. There is nothing to flag in the step from cash cost to all-in sustaining cost. Essentially all of the quarter's cash cost increase carries through into all-in sustaining cost, and no specific line within all-in sustaining cost needs highlighting. Corporate cost and sustaining capital came in as expected, along with capitalized stripping costs and other costs. Nothing there requires comment, and that gives us, year to date, a cash cost of $2.60 per pound rising to all-in sustaining costs of $3.11 per pound. When you look at these all-in sustaining costs reported per pound of payable copper in U.S. dollars and set them against other operations worldwide, I believe we remain well positioned, especially against companies such as 29Metals, Capstone Copper, First Quantum Minerals, Constancia Mine. This too is consistent with the prior quarter, and nothing here deserves note as a consequence of the modest inflation increase during this quarter. We turn now to 2026 guidance. Guidance from the prior quarter is unchanged. It includes throughput between 15.8 million and 16.2 million tons. Grade falls in a range of 0.36% to 0.39%, with recovery of 80%-83%. For copper production, we expect the low end of the range we guided to the market, which is 50,000. We could be a bit over 50,000, but as you can see, the 14,000 tons of copper we turned out this quarter are essentially making up for that weak copper output in Q1 2026 caused by the heavy rains, and we're well on track to essentially hit that guidance. On cash cost and all-in sustaining cost, it's exactly the same. You can see that both cash cost and all-in sustaining cost on a year-to-date basis sit at the bottom end of the range, and we don't expect anything different in the current quarter. Non-sustaining capital investment, we changed that slightly in the previous quarter, and it stays unchanged this quarter. I think total investment for the full year will land in the range of around EUR 60 million-EUR 65 million, which is right at the midpoint of that EUR 52 million-EUR 80 million; on exploration and other project expense, we're slightly higher. That used to be between EUR 5 million — EUR 7 million, and now we're going to go from EUR 7 million — EUR 9 million, mainly because of exploration and other costs in other assets. If we now turn to the strategic focus for Atalaya. This slide summarizes — there's nothing new in it — it summarizes what the plan is for the existing asset; we have San Dionisio, and those of you who had the chance to be here in Riotinto on site have seen the work we've done at San Dionisio, and we're progressing. We have some minor delays due to the need to move an electric line, which is basically not significant. Again, we can carry on, and we're processing some of the ore coming from San Dionisio as expected. Nothing to report there. We continue as expected. On the Riotinto polymetallic circuit, we're finalizing the detailed engineering for the circuit. This adds, as you can see here in red, some differential flotations, basically to process the polymetallic ore coming from Masa Valverde, coming from San Dionisio, and in the future, from San Antonio; this is something we keep looking at and we keep finalizing the engineering work. Proyecto Masa Valverde, you'll see a couple of pictures in the next slide, the work we've been doing at Masa Valverde on the surface and the portal. Again, we continue. We've started the portal, and we've started the surface. As soon as we start going deep, we'll report to the market at the right time, but nothing to report there. This is a project that is well on track to essentially be in production in approximately 18 to 24 months from now. On Proyecto Touro, here on Proyecto Touro, I mean, for some of you who follow Spanish politics, the central government called a general election at the end of this month. Nothing to be impacted in the Touro permit. The permit is proceeding as we anticipated. We have full confidence and complete commitment that we will get a positive permit for the Touro project. That comes from the discussions that are ongoing with the regional government. As I mentioned, Spain is holding a general election for the central government, and although those elections do not directly affect the region, in my view the broader political climate is causing things to move somewhat more slowly than they otherwise probably would. Again, nothing has changed in our expectation of obtaining the Touro permit soon. As I mentioned, this is Proyecto Masa Valverde, so here you can see all the surface work we have completed on the left-hand side of the screen; on the right-hand side of the screen, you can see how we began the work, with somewhat more detail on the portal and the work we are carrying out. Hopefully, in the coming days or weeks, we can announce the start of the ramp. This slide has not changed in this presentation compared with the previous one. We still believe that Touro will be the company's next growth asset. Again, we have completed all the work for the permit.

César Sánchez

executive
#3

Continuing from my earlier point, that permit requires talks and involvement with the regional government, and those efforts are progressing nicely. We don't expect any significant holdup when it comes to the permit being granted, though this is a matter we've been looking forward to for a great many months, perhaps years, and we're now right at the last step of the permitting process, which basically amounts to getting it from the government. My feeling is that the government is finishing up and closing out all the work that has been done, and with luck we can secure this permit within days instead of weeks. We made public yesterday our purchase of Tharsis Mining. For the past few years we'd been quietly collaborating with the proprietor of that privately held firm, Tharsis Mining, and yesterday the deal for the asset finally closed. We also ran a dedicated, ad hoc presentation for the market. Let me walk through the transaction's key numbers. We're buying 100% of the ownership, giving us immediate control of the company. That control has been in place since we signed and executed yesterday, and starting Monday of next week we'll begin holding meetings with Tharsis's management. Through that acquisition, we clearly gain a substantial footprint in the Pyrite Belt along with a regional presence, as we aim to build on the solid reputation and strong results we have delivered over recent years — something that will hopefully assist us in getting this asset to production during the years ahead. Consideration for the deal totaled EUR 125 million, entirely in cash; an upfront payment of EUR 75 million was made yesterday. Those EUR 75 million were drawn from our cash balances, meaning that following the payment we still hold a robust net cash position of approximately EUR 260 million. For the remaining EUR 50 million, we have committed to paying it over the coming 12 months. We felt that was the optimal consideration available; it had worked well and proven successful for the prior owner, and essentially we're buying 100% of an asset with zero dilution for Atalaya's existing shareholders. On the following slide, a map shows where the operational and administrative synergies between these two assets could be realized. There's considerable exploration upside throughout the land package, and within a 50 km or 25 km radius you've basically got Riotinto and Masa Valverde, and the next slide will show you a picture of that area. As I mentioned, Tharsis contains two past-producing assets. Given our extensive operating history there, we can leverage the entire infrastructure at Riotinto, along with local expertise, staff capabilities, and our strong relationships with government authorities. That combination, I believe, leaves us well positioned to bring these two former producers back online. The mineral resource package we are purchasing totals 227.7 million, with 199.2 million of that suitable for open-pit extraction. The seller carried out substantial drilling — really thorough work — and that data now belongs to us, allowing us to continue exploration and advance the operational project. Inside this mineral resource, we have 1.5 million tons of copper, and together with that copper there is zinc, lead, gold, and silver. There is a certain amount of polymetallic content, and these resources provide us with significant optionality, and we will choose the appropriate time to integrate this with the current plant and the potential building of a new plant at Tharsis. As I noted, here is a regional map on which you can plainly see Riotinto, the current plant, as well as San Dionisio and San Antonio and Masa Valverde, located approximately 29 km away. So what you're looking at is La Zarza — that's one of the assets we're acquiring — along with Tharsis, the other one, and then everything in orange, which represents the full mining license we hold from Tharsis, and that basically adds to the Atalaya license shown in green. Taken together, I believe this gives us a strong position in the region when you stack us up against another operator like Sandfire, which really has Aguas Teñidas, Magdalena, and Sotiel, right? So what does Tharsis mean for Atalaya and for Atalaya's growth potential? We previously had a slide quite similar to this one, which is essentially just the subject at hand here. The slide laid out the route Atalaya intends to take in expanding from its current output of roughly 50,000 tons of copper metal to 100,000 tons. Getting there would involve bringing in copper ore from San Dionisio and from Masa Valverde, polymetallic material from Riotinto, and then of course Touro, once the permit is in hand and the plant has been constructed, which would contribute about 30,000 tons of copper metal. The Tharsis acquisition hasn't altered any of that. In my view, Touro will be the next asset to add copper to the Atalaya portfolio. Beyond Touro, there's a chance we continue the work for Tharsis Mining, and we'll see how far that goes, but our view is that we can get to roughly 130,000 tons of copper metal once the two assets I mentioned, Tharsis and La Zarza, are both in operation; that's what this presentation covers. At this point I'd like to open the floor to any questions you may have about the asset or about the financial or operational side for this quarter.

Pavel Kirjanovs

analyst
#4

Morning, and thanks for the presentation and the chance to ask questions. I'll keep it to just one about Touro, if that's alright. I realize this comes up a lot, but perhaps you could give us a bit more detail. After the DIA comes through, which other approvals do you need before construction can begin? And on top of that, is the 18-month construction schedule still the target, or has it moved by now?

César Sánchez

executive
#5

Yes. No, thanks for asking. The permit situation hasn't changed. Essentially, the DIA is what we're waiting on at this point. The DIA is the key permit, and it's the one we've been awaiting for quite a while. Alberto has said for some time that we could get the permit at any moment. Honestly, we have no idea when it will arrive, but our view is that the DIA permit will come within the next weeks, correct? Not far off now. After we get the DIA, the following permit will be approval of the strategic project. From the DIA to the strategic project permit, it'll be roughly two months, 2.5 months. But that period isn't all that important. The moment we hold the DIA permit, we'll begin placing orders for the long lead items, and we'll keep on with land acquisition and start wrapping up all the engineering work; so the significant permit is the DIA. We expect to receive the DIA in the coming weeks. Once the DIA is in hand, we'll still need approval of the PIE, the industrial strategic project, and that's when building can start. We can get some work done in the interim, and we still believe 18 months will be sufficient for us to get the plant up and running.

Pavel Kirjanovs

analyst
#6

Great, and thanks for those details. If it's alright, may I ask just one more question about San Dionisio? Does that power line holdup alter your 0.4 grade forecast for 2027, or is it possible to make up part of the stripping progress that was lost?

César Sánchez

executive
#7

Some of that we can make up. The power line accounts for only a minor share of San Dionisio. Essentially it means we have the option of routing around the pole, or around the electric line. I bring it up since we ran into certain delays previously, and we simply chose to proceed through San Dionisio while treating the pole as an island. The 0.4% grade and the plan we laid out before—both remain essentially as they were.

Pavel Kirjanovs

analyst
#8

All right, great. Thanks for the color today, and thanks as well for the presentation.

César Sánchez

executive
#9

Thank you.

César Sánchez

executive
#10

Alright, thanks a lot for making the time today and for sticking with us. It's been a busy year, I'd say, and it stays busy through the 2 months still in front of us. Even so, we're all pulling together to essentially build a solid, strong production asset at Atalaya, and I appreciate every bit of your backing. Many thanks, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Atalaya Mining Copper, S.A. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Atalaya Mining Copper, S.A. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Atalaya Mining Copper, S.A. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.