AtkinsRéalis Group Inc. (ATRL) Earnings Call Transcript & Summary

March 9, 2021

Toronto Stock Exchange CA Industrials Construction and Engineering earnings 68 min

Earnings Call Speaker Segments

Operator

operator
#1

Hello everyone, and thank you for joining us for SNC-Lavalin's conference call covering results for the fourth quarter of 2020. I'd like to note that everyone is currently in listen-only mode, and this call is being recorded. Following the presentation, we'll open things up so you can ask questions. To get into the question queue, simply press star followed by one on your phone's keypad. Should you require help at any point during the call, you can reach the operator by pressing star then zero. With that, I'll hand things over to Denis Jasmin, Vice President, Investor Relations. Denis, please go ahead.

Denis Jasmin

executive
#2

Thank you, and good morning to all of you for being on the call. We put out our Q4 earnings announcement this morning, and a matching slide deck is now posted in the Investors section of our website. A recording of today's call, along with its transcript, will be up on our site within 24 hours as well. Joining me are Ian Edwards, our President and Chief Executive Officer, and Jeff Bell, our Executive Vice President and Chief Financial Officer. Before we get started, I'd ask each of you to keep it to one or two questions so that every analyst gets a chance to participate. Feel free to rejoin the queue for any follow-ups. I'd like to point you to slide two. Statements made on today's call may include forward-looking information. By its very nature, such information carries risks and uncertainties, and actual results could therefore differ materially from the views expressed today. For more detail on those risks and uncertainties, please see the company's relevant filing on SEDAR. Those documents are available on our website too. In addition, we may reference certain non-IFRS measures during the call. Definitions of these measures and reconciliations to comparable IFRS measures appear in our MD&A, which you can find on SEDAR and on our website.

Denis Jasmin

executive
#3

In management's view, these non-IFRS measures give extra insight into the company's financial results, and some investors might use this information to assess how the company has performed from one period to the next. Now I'll hand the call over to Ian Edwards. Ian?

Ian Edwards

executive
#4

Thanks, Denis, and good morning, everyone. If you turn to slide four, 2020 has truly been a year of transformation for SNC-Lavalin on a number of fronts. We carried out a series of actions centered on two goals. First, lowering the company's risk profile when it comes to our legacy LSTK business. Second, speeding up SNC-Lavalin's shift toward becoming a leading professional services and project management company. Among the steps we took were the closure, sale, and strategic divestment of the great majority of the resources business, including a binding agreement to sell the oil and gas business that we announced on February 9th. We also reviewed every significant litigation matter and claims receivable so as to give the fullest possible assessment of outstanding risk, and we continued winding down the LSTK projects backlog by roughly CAD 1 billion. Through the COVID-19 pandemic, we further showed both our agility in reacting to unprecedented global events and the resilience of our engineering services business. We moved quickly to respond to the challenging environment brought about by the pandemic, shifting to remote working, cutting costs, and strengthening our digital transformation. We have also worked alongside our clients to create new risk-capped contracting models, and we have drawn on our public sector expertise and diverse service offering in our core markets to win new work—in many cases groundbreaking—that reflects our ability to meet the changing needs of a post-COVID world.

Ian Edwards

executive
#5

This covers several significant projects in nuclear transport infrastructure and social housing. As we head into 2021, engineering services is in a robust position to serve our clients' requirements for fresh infrastructure investment and the creation of low carbon assets. Moving to slide five, I will now take you through the Q4 highlights and the 2021 outlook for every engineering services segment, beginning with EDPM. EDPM concluded the year on a strong note throughout all regions, supported by solid results in our roads, railway, and defense service offerings. On the whole, EDPM produced robust cash flow and its backlog expanded 8.9% in 2020, driven by road and rail contract wins in the U.K., rapid transit in the U.S., and new water and O&M projects in Asia Pacific, among other things. With a solid pipeline of CAD 27 billion ahead going into 2021, together with governments' commitments to infrastructure spending, we are genuinely optimistic regarding a return to growth in our core geographies, especially during the second half of the year. We have an ambitious growth plan centered on areas where we expect increased investment and where our expertise runs deep, specifically transportation infrastructure, water, environment, and defense. When it comes to geographies, the U.S. is a central focus.

Ian Edwards

executive
#6

We think there's considerable room to grow our presence in the U.S. market. In our view, a considerably bigger infrastructure spending bill might get through now that the Biden administration is in place. If you turn to slide six, I'll cover highlights of the EDPM project wins we've had lately. Back in February, SNC-Lavalin and its partners were awarded a CAD 1.3 billion contract for designing and building Phase 2 of the East West Rail project, which ranks among the biggest rail efforts in the U.K. Under this project, a new alliance contracting model applies, where every partner operates as one integrated team and risk is shared and capped among them. That points to a fresh, collaborative method of working alongside partners and clients. We're hoping to replicate this model on other projects in other countries. Now on slide seven, here are highlights from our nuclear segment. Through Q4, nuclear kept delivering strong results. During the quarter, several multi-year project extensions were granted on contracts in the U.S. and Canada. As we move into 2021, the pipeline looks robust. Looking ahead, we see substantial opportunity in nuclear, driven by market demand and our own market leading position. These opportunities cover nuclear new build and reactor support, with a number of projects soon to be put out for tender by the U.S.

Ian Edwards

executive
#7

The Department of Energy is an area where SNC-Lavalin has already compiled a solid record of wins, along with nuclear decommissioning and environmental opportunities. If you turn to slide eight, you'll see a few of the recent wins and industry awards, covering contracts in Canada and the U.S., plus service support for the CANDU fleet both in Canada and internationally. On slide nine and infrastructure services, that segment posted a strong quarter, which reflects how essential infrastructure services are in supporting critical infrastructure through the pandemic. Operations and maintenance kept running at full service levels, with strong activity in power, grid, and industrial solutions. Linxon contributed strongly to the quarter as well and posted a healthy intake of orders. Looking ahead to 2021, we see a strong pipeline of opportunity for Linxon, especially in the transportation and transmission sectors. We're also concentrating our business development in O&M on the U.S., U.K., and Canadian transportation sectors, as governments keep investing in new infrastructure. On slide 10, you can see how broad the work in the infrastructure services backlog is, ranging from design, building, and refurbishment of hydro plants to defense work and COVID-19 related contracts, including a medical supply contract and delivery of mobile health units.

Ian Edwards

executive
#8

Now if you go to slide 11, the capital segment. Traffic on the 407 fell 44% in Q4 because of the return to lockdown, so no dividends were paid during the quarter. As the province exits lockdown, we expect traffic levels to rise, and we still have faith in the long-term fundamentals of that highway in the largest city and economic hub of the country. The rest of our concessions keep performing well and haven't been materially affected by the pandemic. On slide 12, infrastructure EPC projects. As we talked about in our February announce update, the three remaining Canadian light rail projects are still moving along nicely. By the end of 2021, we expect to bring the backlog down by roughly CAD 1 billion. Two of these projects should wrap up by the end of 2022, and the final one, the REM, will be delivered in 2024. As these LSTK projects wind down, we genuinely view light rail as a major growth opportunity, given that governments are investing in low-carbon rapid transit. SNC-Lavalin will keep drawing on its expertise in light rail. With a focus on collaborative, risk-capped project management and construction management services. Now slide 13, the resources segment.

Ian Edwards

executive
#9

Once we’ve agreed to divest the oil and gas business, what remains in our resources segment centres on providing services to mining and metallurgy clients. We’ve been in M&M for a long time; that operation brought in CAD 163 million of revenue during 2020 and will sit within the engineering services offering we continue to run. If we go to slide 14, I want to wrap up my remarks by looking at SNC-Lavalin’s strategic priorities for 2021. As I said near the start of today’s call, our attention is on reducing risk in the business and producing steady earnings along with cash flow. That stays our emphasis, and there are five key priorities. Completing the sale of oil and gas, successfully running off the LSTK projects, keeping up consistent performance in engineering services, creating a connected and collaborative organization able to work with and support clients remotely from any location worldwide, and above all, generating growth and sustainable outcomes for clients throughout the company. On slide 15, we’re concentrating on several growth drivers. The first centres on our core markets — the U.S., the U.K., and Canada — where our expertise in nuclear and transportation infrastructure, among other areas, lets us broaden market penetration across the full range of services we offer.

Ian Edwards

executive
#10

The second one, as I said before, involves growing our major projects business across Canada, the U.S., and the U.K. by way of risk-capped opportunities. We're equally focused on growing our operations and maintenance business, along with our water, environment, and defense work, in core geographies where we see a chance to build our footprint. Underpinning these efforts are enhanced digital capabilities, which boost productivity and delivery while lowering the carbon footprint for our clients. That emphasis on digital transformation ties closely to another key growth driver and company priority, namely sustainability. As engineers who design, build, and service the built environment, we play an integral part in enabling countries and companies to hit their carbon reduction targets. As part of that push, we offer a comprehensive range of services aimed at helping our clients engineer net zero. Beyond that, we're further developing our own ESG strategies, and in Q2 we will share our targets with you. During the second half of the year, we'll also be ready to share the specifics of an overall growth strategy for the business as we head into 2022, and we very much look forward to sharing that with you. With that, I'll now hand the call over to Jeff.

Jeff Bell

executive
#11

Thanks, Ian, and good morning to all of you. If you'll turn to slide 17. The fourth quarter, as we had anticipated, featured a robust contribution from SNCL Engineering Services, whereas SNCL Projects recorded a substantial loss. On February 9th we announced that Q4 2020 SNCL Projects carried an aggregate CAD 480 million in charges, adjustments to provisions and reductions to claims receivable, along with a reassessment of costs on the remaining Canadian LSTK infrastructure projects. Adjusted EBIT for the Capital segment came to CAD 19 million, versus CAD 32 million, since no dividend was received during the quarter from Highway 407. Corporate SG&A expenses were CAD 96 million, and that figure included CAD 48 million of negative adjustment to the provision for the Pyrrhotite case litigation, CAD 4 million of pension equalization provision, and CAD 6 million invested in digital transformation initiatives. All of this produced an IFRS net loss from continuing operations of CAD 323 million, or CAD 1.84 per diluted share in Q4 2020, against a net loss of CAD 180 million, or CAD 1.03 per diluted share for the corresponding period of 2019. The adjusted net loss from PS&PM in Q4 2020 came to CAD 269 million, or CAD 1.53 per diluted share, versus adjusted net income of CAD 110 million or CAD 0.62 per diluted share in the corresponding period of 2019.

Jeff Bell

executive
#12

Let's go through the segments a bit more closely. If you turn to slide 18, you'll see that SNCL Engineering Services posted solid results and has stayed resilient throughout COVID-19. Revenue for Q4 came to CAD 1.5 billion, which is a 3% decline versus Q4 2019 and matches what we expected, yet it was 5% above Q3 2020. Segment adjusted EBIT reached CAD 153 million, below Q4 2019, but up 7.5% from Q3 2020, and the margin came in at 10.1%, better than we had anticipated. Backlog stayed robust, totaling CAD 10.9 billion. Over in EDPM, revenue was CAD 943 million, with segment adjusted EBIT of CAD 85 million, a margin of 9% that falls within our long-term target range of 8%-10%. That EBIT figure was under Q4 2019, largely because of COVID-19's effects in certain markets like aviation and commercial property, along with weaker revenue from the Middle East. Partly offsetting that was strength in transportation and defense markets in the core region of the U.K. and Europe. EDPM backlog finished the year strong at CAD 2.9 billion, up almost 9% from the close of 2019. At the nuclear segment, revenue was CAD 245 million and segment adjusted EBIT was CAD 36 million, a margin of 14.8% that sits within our long-term target range of 13%-15%.

Jeff Bell

executive
#13

EBIT came in below the Q4 2019 level, and the main reason was reduced activity on some large Canadian projects that had already hit key delivery milestones earlier in 2020; a bigger contribution from the U.S. and Europe partly offset that decline. Revenue for Infrastructure Services was CAD 334 million, essentially flat against Q4 2019. Adjusted EBIT for the segment reached CAD 32 million, up 58% versus Q4 2019 and 27% versus Q3 2020. That EBIT gain came largely from more revenue on certain operation and maintenance contracts, greater activity in project management and construction management services, reduced overhead costs, and a larger contribution from Linxon. Moving to SNCL Projects on slide 19: consistent with our LSTK exit strategy and the anticipated continued backlog runoff on our major LSTK construction projects, revenues kept declining in Q4 2020. SNCL Projects revenue dropped 57% from Q4 2019, to CAD 152 million. The Repo resources segment and the infrastructure EPC project segment posted negative adjusted EBIT of CAD 93 million and CAD 319 million, respectively, driven chiefly by charges, provision adjustments, and reductions in claims receivable, along with a cost reassessment of the remaining Canadian LSTK infrastructure projects, as we announced on February 9th.

Jeff Bell

executive
#14

Turning to slide 20. In 2020, net cash generated from operating activities came to CAD 122 million, versus a use of CAD 355 million in 2019. For the quarter, net cash generated from operating activities was CAD 105 million, compared with CAD 312 million in Q4 2019, and the lower cash generation was mainly driven by a usage of cash from discontinued operations in Q4 2020. SNCL Engineering Services kept producing strong cash flow from operations, with CAD 250 million in the quarter, thanks to strong EBIT conversion and a low day sales outstanding of 64 days in the EDPM segment, a nine-day improvement compared to 2019. For 2021, the strong operating cash flow attributes of SNCL Engineering Services are expected to be partially offset by our return to a more normalized day sales outstanding level, as early government payment programs related to COVID-19 are expected to wind down during the year. In addition, SNCL Projects are expected to see a usage of operating cash flow as a result of the significant backlog to be run off during the year and the timing of the collection of COVID-19 related claims. As a result, operating cash flow is expected to be largely breakeven this year.

Jeff Bell

executive
#15

As of the end of December 2020, cash on hand stood at CAD 933 million for the company, while recourse debt was unchanged versus December 2019. On the revolver credit facility, the ratio of net recourse debt to EBITDA — computed under the provisions of the company's credit agreement — came in at 2.1x, comfortably under the 3.75x covenant requirement. Now, if we move to slide 21. For 2021, the company anticipates that SNCL Engineering Services revenue ought to rise by a low single-digit percentage relative to 2020. Since the COVID-19 pandemic began materially affecting the business only in Q2 2020, the company foresees a low single-digit percent decline in SNCL Engineering Services revenue during Q1, followed by year-over-year revenue growth in this year's second, third, and fourth quarters. We further expect the adjusted EBIT margin for the SNCL Engineering Services segment to land between 8% and 10%, and we will keep aiming at the same long-term EBIT margin percentage for every segment. That brings my presentation to a close. The line is now open for your questions. Thank you.

Operator

operator
#16

Thank you. We’ll now start the question-and-answer portion. To enter the question queue, you can press star and then one on your phone’s keypad. A tone will sound to confirm your request. If you’re on a speakerphone, please lift the handset before you press any keys. To take back your question, press star and then two. We’ll wait briefly while callers join the queue. Our first question is from Yuri Lynk at Canaccord Genuity. Please go ahead.

Yuri Lynk

analyst
#17

Morning, everyone.

Ian Edwards

executive
#18

Morning, everyone.

Yuri Lynk

analyst
#19

Ian, regarding the 2021 outlook — as I believe Jeff noted, the margin guidance is essentially consistent with what Engineering Services has delivered over the past several years, which is impressive given this environment. I'm curious about what levers you can pull going forward to enhance Engineering Services margins, and perhaps you could connect that question to some of the digital initiatives you referenced on the call and how those might translate into improved margins going forward.

Ian Edwards

executive
#20

Absolutely, and thanks for raising that. What matters most for us right now, I'd say, is that we've shifted away from reducing risk in the business and are now concentrating on growth — organic growth in particular. Holding our margins where they are is significant, and clearly continuing to optimize costs matters too, especially drawing on what COVID-19 taught us, like remote working and digital technologies that cut down on the number of people involved in content. Our real emphasis is on taking that and directing our efforts toward organic growth. Looking past this year, that's one of our main priorities. Of course, that doesn't mean we've stopped pursuing efficiencies — we certainly are. Margin expansion isn't really our central focus.

Yuri Lynk

analyst
#21

Alright. You also said EDPM has a growth focus in the U.S., and I believe you'd like to be bigger there. At this point, is that plan solely organic? Or when might you begin considering some acquisitions — tuck-in or otherwise — to grow in some of the markets where you might be subscale?

Ian Edwards

executive
#22

Yeah, that's a fair question. Well, definitely both. What matters most for us at the moment is organic growth. It isn't only EDPM. Our business is mainly concentrated on infrastructure across the Southern states, and we're eager to expand that through growth in the Northwest, the Northeast, and California. Clearly, we have a very robust nuclear environmental management business with the U.S. Department of Energy, and from that we're seeing genuinely strong growth potential. That, of course, is entirely from an organic standpoint. We see substantial potential coming from federal government investment, especially the rhetoric surrounding the new administration. Past that, we'll be assembling our capital allocation plan, along with our longer-term plan, toward the second half of this year, and we'll communicate it at that moment. Our priorities at present really are organic growth, closing the oil and gas deal, carrying on running off our LSTKs, carrying on performing, and carrying on achieving good cash conversion from the businesses we've got.

Yuri Lynk

analyst
#23

Alright, that all adds up. I’ll hand it back and rejoin the queue. Thanks, everyone.

Ian Edwards

executive
#24

Appreciate that, Yuri.

Yuri Lynk

analyst
#25

Thanks.

Operator

operator
#26

The following question is from Chris Murray at ATB Capital Markets. You have the floor.

Chris Murray

analyst
#27

Yeah. Thanks. Good morning, everyone. So turning to 2021 — I appreciate the detail on the guidance and the pattern — but looking at that CAD 1 billion you mentioned would be consumed as backlog for the remaining LSTK project: how should we view that now, given the adjustments and write downs you've made? How should we view it across 2021? Both in terms of margin or cash use, and just the revenue pattern.

Ian Edwards

executive
#28

All right, so you're talking specifically about the LSTK business segment, correct?

Chris Murray

analyst
#29

That’s exactly right, yes.

Ian Edwards

executive
#30

Correct.

Chris Murray

analyst
#31

I'd say we've largely put the surprises behind us at this point.

Ian Edwards

executive
#32

All right, I’ll have Jeff walk through the cash flow piece. From both a margin and a risk standpoint, as we mentioned on the ninth regarding these three jobs—we’re now down to three: Trillium, the REM, and Eglinton. We’re working our way through them and have solid visibility into where they stand. COVID has impacted them. We made the choice not to recognize revenue tied to COVID, even though we believe we have entitlement. We genuinely think these jobs are in good shape for us as we progress through this year and, obviously, as we move toward closing them out. On the cash profile specifically, I’ll ask Jeff to address that as we work through them.

Jeff Bell

executive
#33

Yeah. I guess the first point I'd make on the revenue side is that across those four quarters they're pretty much even, with a little extra tilt toward Q2 and Q3, since those are the summer months and it's simpler to get more of them deployed then — especially the construction pieces. So there's a slight weighting in that direction. On the cash flow side, as I mentioned, we do anticipate that at the operating cash flow level they'll be a use of cash in 2021. Two factors really drive that, because taken as a whole, among those projects that remain, we expect the portfolio to be cash flow neutral to positive across their life. During 2021, the mix — as we discussed on February 9th — of keeping a prudent stance on COVID-related costs and on our capacity to recover those from the clients, which we believe we're contractually entitled to, while remaining prudent about not recognizing that revenue until we have greater clarity via either commercial negotiations or third-party arbitrations, should that prove necessary. We'd anticipate that persisting at least through the first half of this year, certainly. Placing that much backlog delivery into the year also means that at various points during the year, our cash usage will be outpacing the actual payment reprofile coming from the joint ventures or from the customers themselves.

Jeff Bell

executive
#34

That clearly pays off eventually, though it was somewhat of a timing drag during 2021 too. I believe cash flow will keep looking like that going forward.

Chris Murray

analyst
#35

All right, that's fair. Coming back to a few of the points you made about Infrastructure Services margin, even in Q4. You mentioned that Linxon played a large part, and perhaps that ties partly into what Yuri asked regarding M&A and growth. How willing would you be to consider possibly more joint ventures? I realize you currently have several of them as a means of perhaps driving some extra growth while keeping risk more contained.

Ian Edwards

executive
#36

That's a fair question. The Linxon joint venture, as a particular type of business venture, has been genuinely successful for us, since we've combined the strongest of our project management capabilities with the ABB and now Hitachi ABB equipment. It gives customers a complete solution. In a manner of speaking, one plus one equals three. One of the main areas where I believe joint venturing will go forward is major projects. We were truly pleased about the East West Rail win in the U.K., because that is precisely where we want to position our ability to deliver major projects going forward. For us it's a liability capped contract, so it isn't an LSTK. Our payment is on an alliance-style target cost basis. On that project we collaborate with two other joint venture companies so the customer gets the best solution, and that's how we win. What's exciting about that type of arrangement, I think, is that we're actually seeing this collaborative, risk-capped method of delivering major infrastructure being taken up in many other countries and with many other clients and governments. Canada is among them, as are Australia, some locations in the U.S., and throughout the U.K.

Ian Edwards

executive
#37

My view is that by shifting our positioning toward this type of project, we're able to occupy the gap created when we exited the LSTK and put our capabilities to work.

Chris Murray

analyst
#38

Alright, that's quite intriguing. Thanks a lot.

Ian Edwards

executive
#39

Appreciate it.

Operator

operator
#40

Frederic Bastien from Raymond James has the next question. The floor is yours.

Frédéric Bastien

analyst
#41

Thanks. Ian, I’m curious whether you feel satisfied with the management team you currently have leading the three businesses within Engineering Services, or is there a need to bring in some additional talent from outside?

Ian Edwards

executive
#42

Yeah. Well, clearly, during the past 18 months while I've served as CEO and led this company, you'll have noticed that we've grown talent from inside the organization, promoting people into the leadership team as well as into the group reporting to that team. On top of that, we've recruited senior-level talent from outside, along with people just under that senior level. From my perspective—especially regarding the growth plans we're pursuing—having the strongest talent available so we can win and deliver work matters a great deal. I don't view this as a static situation. To me, it's dynamic. As we expand other areas of the company, we'll aim to develop our existing people while continuing to attract top talent. I'm extremely pleased with the leadership team currently in place, though for me this remains a moving, evolving, growing sort of environment.

Frédéric Bastien

analyst
#43

All right, I appreciate the question. My next question concerns the CAD 6 million that you invested in a new digital transformation initiative. Could you talk a bit about that investment? And more broadly, what objectives do you have for the company regarding developing or acquiring new technologies? Is it a combination of developing things internally and possibly acquiring additional businesses via tuck-ins?

Ian Edwards

executive
#44

From my perspective, technology helps us execute customer projects with greater efficiency and effectiveness. In fact, if you consider design, you consider that design progressing into build, and you consider the build progressing into asset operation—whether those are power assets, nuclear assets, railways, or infrastructure assets. Technology truly is the golden thread running through the entire process, enabling us to deliver successfully. As SNC-Lavalin, our approach involves pairing that technology with the capability we have built up over many decades to collaborate with customers on delivering a complete asset. This may be somewhat different from what you have heard. To us, it serves as an enabler. Our investment goes into building teams, onboarding tools, and developing people so they can deploy those tools. We are not attempting to create new technologies, since we believe those technologies already exist and are already available. It is their adoption—and becoming highly capable in applying them to benefit our customers—that represents the real market and the real benefit for us.

Frédéric Bastien

analyst
#45

Thanks a lot — I really appreciate it.

Operator

operator
#46

We'll take the following question now.

Ian Edwards

executive
#47

I appreciate it.

Operator

operator
#48

We'll take our next question from Benoit Poirier at Desjardins Capital Markets. Go right ahead.

Benoît Poirier

analyst
#49

Morning to you both, Ian and Jeff.

Ian Edwards

executive
#50

Good morning, everyone.

Benoît Poirier

analyst
#51

Thank you so much. I appreciate the detail you gave on the free cash flow outlook for 2021, and on the point that SNCL Engineering Services will be mostly offset by EPC. Looking past 2021, could you give us perhaps a fuller picture of what to expect for the entire entity and in particular for service engineering, regarding free cash flow capabilities after 2021?

Jeff Bell

executive
#52

Sure, Jeff, let me handle that one. I believe you're completely correct, Benoit. In my view, 2021 is somewhat of a transitional year. A few items are in there that we wouldn't necessarily anticipate seeing as we move into 2022 and beyond. First, I mentioned the day sales outstanding, or the gain we've realized from certain early payment programs, and some of that will reverse during 2021. The sales tax deferrals that we observed in a couple of countries will also reverse. I think we've discussed before that this is roughly CAD 100 million to CAD 150 million. You should assume that won't be present in 2022 and beyond. As a result, the EBIT conversion percentage should naturally be quite high, given our typical tax rate in the low 20% range. You'd anticipate a fairly strong EBIT percentage conversion in 2022 and going forward. Obviously, as the LSTK on the project side winds down and we gain more clarity on claims tied to COVID that we believe we're entitled to, and how that will unfold. Again, once you reach 2022, you'd expect things to be far more normalized. I hope that's helpful.

Benoît Poirier

analyst
#53

Okay. Yeah, that's really helpful context, Jeff. Do you have any perspective on how free cash flow tends to be seasonal—not quarter by quarter, but looking at the first half versus the second half—regarding the overall expectation for 2021?

Jeff Bell

executive
#54

Yes. My sense is that it will lean more toward the second half than the first. Clearly, we’ll be doing — and as we did throughout 2020 — a great deal of emphasis on cash flow. That’s just the way it works out, so we expect a heavier tilt toward the second half than the first.

Benoît Poirier

analyst
#55

All right, that's excellent. So with the major announcement made on February 9 regarding the sale of the oil and gas business, how should we think about the mining services business you'll still have? I'm just curious whether it might make sense to sell that too and concentrate on core Engineering Services, since it now represents a much smaller share of your business.

Ian Edwards

executive
#56

What I'd say is that right now, our aim is to keep expanding that operation as a services operation within Mining and Metals. When you look at it, SNC-Lavalin has, for quite a while, actually been stronger and carried more weight in mining than it ever did in oil and gas. In a sense, that's embedded in the DNA of the operation. That's correct. We concentrate heavily on particular clients. We concentrate heavily on particular geographies. It isn't a particularly large piece of our engineering services businesses, but it does make money. At present we continue to back it and plan to grow it organically.

Benoît Poirier

analyst
#57

All right, that's excellent, Ian. One final question from me. Looking at your leverage ratio, you managed to bring it down to 2.1x by year-end. As we consider 2021, with EBITDA improving given the free cash flow expectations, how should we think about your net recourse debt to EBITDA ratio for 2021, and what would you view as your optimal balance sheet over the longer term when it comes to leverage ratio and the chance to eventually deploy capital?

Jeff Bell

executive
#58

Sure, Benoit — I'd tackle that in two parts. First, based on the outlook we've provided, we expect to stay comfortably inside our covenant ratio metrics all year long; as was the case in 2020, they'll probably fluctuate somewhat, but they ought to sit well under all of our thresholds. Over the longer term — and we'll return to this in the second half, as Ian mentioned, when we discuss our longer-term growth strategy in more detail along with the capital allocation tied to it — that will encompass what we regard as the optimal capital structure for the business going forward. As you've heard from us repeatedly, we'd keep aiming to have financial metrics consistent with being an investment grade company — from a balance sheet standpoint, for example. Exactly how that aligns with our overall growth strategy and our thinking on capital deployment is something we'll revisit later this year, for certain.

Benoît Poirier

analyst
#59

All right, that's excellent. Appreciate you taking the time.

Jeff Bell

executive
#60

I appreciate it.

Operator

operator
#61

Michael Tupholme from TD Securities has our next question. The line is yours.

Michael Tupholme

analyst
#62

Thank you. I'd like to ask about the 2021 guidance you gave for SNCL Engineering Services. You're forecasting revenue growth in the low single digits for this year. I was hoping you could go a step further and say a little about the sub-segments — specifically how you see EDPM, nuclear, and Infrastructure Services performing.

Ian Edwards

executive
#63

Right. Obviously that low single digit reflects the situation we're in at present. The pandemic is still with us, and pinning down precisely when things will get back to normal is rather hard. Our expectation is that growth will begin moving back toward something closer to normal during the second half of this year. We're seeing that as well across our core geographies — Canada, the U.S., and the U.K. — where nearly 75% of our business sits today, the go-forward business. Every one of those geographies has a very strong commitment from governments to put money into infrastructure. There's a strong commitment to invest in nuclear, certainly, though the approach differs in each geography. Nuclear new build in the U.K., plus environmental management — nuclear environmental management — in the U.S., and life extension along with environmental management in Canada. In our end markets across those core geographies, we see fairly solid commitment and fairly strong opportunities for growth. I wouldn't single out any particular difference in how we view those segments when it comes to the low single digit for this year. When we return with our longer term growth plan in the second half of this year, we'll be clear on that, and on where we see the greatest growth potential and the sub-segments within those sectors, if you like.

Michael Tupholme

analyst
#64

No, I appreciate that, thank you. Similarly, regarding the 2021 outlook and margin expectations, I think if we look at 2020, EDPM came in around the 8% level, so sort of toward the bottom end of the range you provided for 2021. Is it reasonable to think about the midpoint of that range and think about expecting some improvement in EDPM in 2021? What would be the factors that would sort of drive that improvement, if that's the case?

Jeff Bell

executive
#65

This is Jeff, and I'll take that question. I'd like to direct your attention to 2020, when EDPM's first quarter was quite difficult in terms of EBIT percentage. Looking at quarters two, three, and four, those are far more representative of the quarter-on-quarter EBIT percentages we would consider typical, and much more in the middle portion of the 8%-10% range. Overall, 2020 was affected by that first quarter, which we wouldn't expect to see happen again this year.

Michael Tupholme

analyst
#66

All right, thanks, Jeff. Just one final question. I didn’t notice anything specific about this in terms of any changes, so could you just give an update on the last remaining mining metallurgy LSTK project? I believe it’s expected to be finished in Q2—any update there would be helpful.

Ian Edwards

executive
#67

Yeah.

Michael Tupholme

analyst
#68

Do you still see any spots where risk remains?

Ian Edwards

executive
#69

No, it's coming along nicely. That figure of CAD 75 million, I believe, comes from the backlog at the end of the year, and we expect to close it in Q2, around the middle of this year. Up to now, yeah, nothing out of the ordinary has come up regarding that project. Things are going well.

Michael Tupholme

analyst
#70

All right, thanks.

Operator

operator
#71

The following question is from Devin Dodge at BMO Capital Markets. The line is yours.

Devin Dodge

analyst
#72

Thank you. I'd like to return to Infrastructure Services. Margins in Q4 were genuinely robust — almost 10%. I'm simply attempting to gain a clearer picture of what is powering those Q4 margins and, more broadly, 2020's, and why the 5%-7% guidance for next year basically suggests a degree of margin compression in the coming year.

Ian Edwards

executive
#73

Right. Infra services consists of a few distinct pieces, including Linxon, which sits in the joint venture company with ABB. Our entire operations and maintenance business falls under infra services. Then there's the services portion, which essentially delivers services to hydro and power, to the medical industries, and to industrial solutions. Actually, every one of those performed extremely well and proved very resilient — in fact, they even picked up some good wins during the COVID period, given the very nature of those businesses. Without question, they're doing very well, and as you correctly noted, did particularly well in the last quarter. On the quarter margin specifics, I'll just have Jeff address that.

Jeff Bell

executive
#74

Yes, indeed. It was quite robust, and Devin, you're correct that we wouldn't necessarily anticipate seeing that continue indefinitely. Several factors came together. This is a business with a relatively lean overhead structure, and during the quarter they proved especially adept at cutting expenses. A portion of that stemmed from COVID, which was encouraging to observe. I'm not certain we'd see that persist, especially since we hope to move past COVID later in the year. We also witnessed solid execution on certain O&M projects, where we achieved improved margins on a handful of those major efforts. Once again, that was tied specifically to conditions in 2020. Looking ahead on a continuing basis, we'd anticipate those coming back to a more typical level within the 5%-7% range.

Devin Dodge

analyst
#75

All right, thank you. That was helpful context. Perhaps just one more for you, Jeff. There's still a substantial amount of cash sitting on the balance sheet. I believe it stood at slightly below CAD 1 billion at year-end. Could you give us some detail regarding that cash balance? Is that an appropriate level, or might there be a chance to streamline that cash position and perhaps deploy that capital in other parts of the business?

Jeff Bell

executive
#76

Sure, that's a fair question. It won't come as a shock that throughout 2020 our stance centered on keeping the balance sheet flexible and liquid, especially with COVID-19 in the picture. Looking ahead, though, we feel more assured about getting the most out of the cash sitting on our balance sheet. Let me offer a few points. There's a baseline cash level we maintain, and given the big infrastructure projects we run, plus the oil and gas business and how wide-ranging that is, I'd say our typical natural cash balance lands at roughly CAD 600 million or so — that's what we'd ordinarily anticipate, since some of that cash sits in joint ventures, or is spread across different regions, or is required to fund working capital for things such as infrastructure projects. We do carry a certain amount of surplus cash. We'll be watching, for example, how we put that to work. In the first quarter here, a small debenture bond of ours matures. Right now, we don't really expect to refinance that in the market. There are various avenues we might pursue to lower that cash balance and optimize our position.

Jeff Bell

executive
#77

In terms of the cash the business needs, it does carry a sensible amount of working capital. Hopefully that's helpful.

Devin Dodge

analyst
#78

Appreciate that—very useful. Thanks a lot. I'll hand it over now.

Jeff Bell

executive
#79

I appreciate that.

Operator

operator
#80

Mark Neville from Scotiabank has the next question for us. Go right ahead.

Mark Neville

analyst
#81

Morning, everyone. I’d like to pick up where we left off on the cash flow discussion. I want to be sure I’ve got a handle on all the moving pieces. Jeff, I believe you cited CAD 100 million to CAD 150 million. Did that figure cover only tax, or did it also reflect the working capital investment for the year?

Jeff Bell

executive
#82

Well, no — it comes down to a mix of working capital factors, mainly tied to days sales outstanding. As we mentioned in the MD&A and as I said in my prepared remarks, we ran roughly nine days better. In EDPM, for example, we sat at 64 days, while under more normalized conditions we'd anticipate being in the low 70s. Don't misunderstand me — we're examining every opportunity to make that improvement stick over the long run. We're pursuing working capital initiatives aimed at freeing up cash from the balance sheet, if we can identify them. Our stance is that, to stay prudent, you'd assume this reverts to a more normalized level. That roughly explains the CAD 75 million to CAD 100 million or so of cash flow benefit in 2020 that you'd expect to reverse in 2021. The second piece, I'd say, is that we did observe — for example, a U.K. VAT deferral program existed for the middle of 2020, which the government announced to help businesses with COVID-19 and cash flow. In large part, that pushed payment of that VAT tax out to 2021. We saw some of that in the U.S. too. Combining those elements is how you arrive at close to CAD 150 million.

Mark Neville

analyst
#83

All right, that CAD 150 covers tax plus working capital. To me, it looks like—assuming operating cash flow is roughly neutral—the drag on the project comes across as pretty substantial. I might be mistaken here, but I'm curious whether you could share some figures on what you anticipate the investment in the projects will be this year.

Jeff Bell

executive
#84

Yeah. What I'd note is that this is — and we expect it to be — negative, and it largely offsets what we're seeing in engineering services. Obviously, part of that is that, early in the year here, we're still taking a prudent stance on things, as I mentioned, such as how we recover COVID-19 claims on those projects. As I think the year unfolds, I think we'll get more clarity on that, and then our ability to book the revenue related to those and see the cash coming in will allow us to then assess where we are as we go through the year. I think that's the color I'd provide at this point.

Mark Neville

analyst
#85

All right, let me just lean on this so I have it straight. On that 2.1x, are you able to kind of strip out every claim and provision you booked in Q4 from the calculation, or does that actually remain in the EBITDA?

Jeff Bell

executive
#86

In that calculation, we left out what we viewed as one-time items — mainly the fair value adjustment on oil and gas, plus the adjustments we made for legacy litigation matters and claims reassessment. What we did not exclude, since we regard it as part of the business's ongoing operations, is primarily the charge of roughly CAD 90 million we took on the live projects here in Canada, and then a smaller piece that was tied to the one remaining resources project.

Mark Neville

analyst
#87

Alright, sounds good. I'll hand things off now. Thank you.

Jeff Bell

executive
#88

All right, thank you.

Operator

operator
#89

The next person in the queue is Sabahat Khan with RBC Capital Markets, and you have the floor.

Sabahat Khan

analyst
#90

Thanks. Good morning, and appreciate it. I just have one question about the new JV model you mentioned for undertaking projects — and I believe you pointed to the one here on the East West Rail project. I'm just trying to get a sense of how this would have been handled previously, I suppose, if you were on the design side here. Relative to what we'd have seen before on the EDPM side, what does this new project structure mean for the risk profile?

Ian Edwards

executive
#91

Right. So those alliance, target cost, or collaborative contracting models — whatever catchall term you prefer — there are various nuances within that theme, but the key distinction is that liability gets capped on our side. Our fee is put at risk, yet past that fee, we wouldn't carry any liability for cost overruns, schedule overruns, or events of that kind. With traditional lump sum turnkey contracts, you bear responsibility for every cost overrun, and obviously you have to pursue whatever you believe is recoverable from the client. That's the reason so many of these arrangements wind up in litigation. This model works in a completely different way. I think a lot of governments and a lot of clients now broadly recognize that the lowest cost wins LSTK model isn't producing the outcomes we're all actually seeking. We want jobs finished on time. We want them to be more sustainable from an energy standpoint and in terms of client impact. We want them to be innovative. A model of this type makes all of that possible. It lets companies such as SNC-Lavalin, which has a very large breadth of capability, bring all of those capabilities to bear for the customer to achieve the best outcome.

Ian Edwards

executive
#92

We are observing quite a few of them. We notice these in Canada—British Columbia and Ontario. Contracts are appearing under this structure. In the nuclear sector, nearly all contracts get awarded on that basis, simply because clients there are unwilling to introduce time and cost pressure into the process, given that safety takes precedence. At SNC-Lavalin, we regard this as a highly important growth area. The prospect of pivoting away from LSTK toward this reduced-risk model has us genuinely enthusiastic.

Sabahat Khan

analyst
#93

All right, thanks. Turning to nuclear, as we hopefully emerge from the pandemic at some point this year, could you discuss how work is advancing on the projects you already have? During 2020, did you see ongoing progress and conversations on the nuclear front, in the U.S., the U.K., or Canada? How do you feel about that wider market as we move into 2021?

Ian Edwards

executive
#94

Yes. It varies across each of the three main regions where we operate. There are slight differences. Taking the U.S. first, the focus is really on environmental management — cleaning up nuclear waste and decommissioning power plants. The U.S. Department of Energy is showing a very strong commitment to keep investing in that cleanup, with some very, very significant contracts, including the Hanford contract we won in 2020, and in fact an extension to an existing contract in 2020. We would view that as an important component. In the U.K., obviously we're involved in the new build at Hinkley, and I think it's likely that new build will continue in the U.K. through to Sizewell, and that's a very significant opportunity for us, as well as decommissioning and helping some clients actually keep their power plants running for life extension through engineering contracts. Canada is all about our CANDU technology and supporting reactors around the world from the CANDU technology, but also the reactor life extension work that we do at Darlington and Bruce. I think, when you consider all of those different components and the market that's out there, the potential for growth in our particular sectors within the end markets within nuclear is quite strong.

Sabahat Khan

analyst
#95

Okay, thank you. Turning to infrastructure EPC, you've clearly booked several provisions tied to certain projects where talks with the client are ongoing. Could you take us through what to anticipate on the accounting front should a recovery, or perhaps a partial one, materialize? Would revenue be recognized along with costs — essentially full income statement recognition? Or would it simply flow through to EBIT or EBITDA? If you could outline how a positive recovery might look at some point, and perhaps any sense of timing on that over the next 1 or 2 years.

Ian Edwards

executive
#96

Okay, I’ll take part of that, and then Jeff can address the details around revenue and margin recognition. The first thing I’d say is that you’re right. On all three of the jobs we currently have underway, we’ve taken what I’d call a cautious stance regarding COVID recovery. Those jobs have obviously been affected, and obviously the contract gives us mechanisms to seek compensation for that loss. The onus is on us to prove it. We need to work through a process with our clients—ideally by negotiation rather than litigation—in order to actually chase those recoveries and those entitlements. This is complicated because these are extremely large contracts with many moving parts and a lot of labor, and the effects are hard to substantiate from a productivity standpoint. I don’t want to make any commitment about when those recoveries will show up, but our discussions with customers are constructive and positive. Jeff, maybe you can speak to the specifics and how you see it.

Jeff Bell

executive
#97

Naturally, we'd anticipate recognizing the revenue once we've settled those matters with the client. That's conditional, since this project is accounted for using percentage of completion. In practice, that revenue is folded into the total revenue we expect across the whole project, and the revenue, cost, and margin resulting from it get recorded on that basis. If a settlement occurs at some point, you wouldn't necessarily see the full amount in that specific quarter, though it would flow through across what's left of the project's life.

Sabahat Khan

analyst
#98

All right, that's excellent — I really appreciate the detail.

Jeff Bell

executive
#99

Appreciate it.

Operator

operator
#100

Mona Nazir from Laurentian Bank has the next question. You're up.

Mona Nazir

analyst
#101

Morning, and thanks for taking my questions.

Ian Edwards

executive
#102

Morning, everyone.

Mona Nazir

analyst
#103

To start with, on the SNCL Engineering Services outlook and that low single-digit growth: you mentioned federal stimulus across your main markets — the U.S., Canada, and the U.K. What I'd like to know is whether that guidance already includes stimulus, or a meaningful amount of it — any color you can give there?

Ian Edwards

executive
#104

Right, okay, and that's a fair point. My answer would likely be no, since we remain in the pandemic and are still working to figure out what the exit from it will look like, and we are still trying to determine when that might arrive in each of those core geographies, and at this moment it is somewhat dynamic and somewhat unspecific. Certainly, if you consider the current commitment for the infrastructure bill in the U.S., it will get passed at some point, and it will be very significant. My expectation is that the improvement and the flow-through probably will not occur this year. If it does happen this year, it is going to be toward the end of this year. In the U.K. and Canada, there is an ongoing commitment. Throughout COVID, we have seen new contracts and new investment. Similarly, there are some fairly major projects out there, particularly in Canada, where I do not think we are going to see the revenues flowing this year, but we are going to see revenues flowing beyond this year. I think the real impact and the benefit that we are going to see is probably beyond this year, just to try and give an overview of that question.

Mona Nazir

analyst
#105

All right, that's excellent. And then second, if we look at the pro forma business through the lens of geographic footprint and mix — I know you said you're still working through the capital allocation plan later this year. I'm just curious whether we should anticipate a meaningful shift from where things stand now. Going forward, might the U.S. account for a considerably bigger share of your mix? I'm wondering, since the decision to sell oil and gas came together rather quickly, whether we could likewise see a swift trigger pulled should an acquisition opportunity come your way. At this point, is it really just an organic growth story?

Ian Edwards

executive
#106

Absolutely, the U.S. is a major priority for us, no question. Right now, 20% of our revenue is generated in the U.S., compared with 30% in the U.K. and high 20s there as well. Certainly, with 5,000 employees in the U.S., we don't operate at the same scale as our competitors. We see substantial opportunity in both nuclear and infrastructure. Yes. I'd say the straightforward response regarding the U.S. is yes, organic growth is going to happen. When it comes to our inorganic growth strategy and where we'd deploy that capital, we'll return with much greater clarity on that. It will track the end markets and geographies that we currently view as opportunities. The company's trajectory won't be altered. It will be strengthened.

Mona Nazir

analyst
#107

All right, that's excellent, and thanks for that. One final item from me: I know you've discussed spending on the IT front. I'm simply curious whether, in your view, you believe IT has been accelerating its integration—or weaving—into what you offer alongside work-from-home setups. Would you say customers are placing greater demands on you, or is it really the capability requirements you see as necessary, or perhaps rivals are providing more forward-looking solutions? I'd just like you to elaborate a bit further on the present and possible upcoming IT spending and what's driving it. Thank you.

Ian Edwards

executive
#108

Yeah. Well, I think the engineering and construction sector is generally viewed as one that adopts technology, digital technologies, and the use of data slowly. Obviously, through COVID-19, remote working as a whole and the entire way of thinking about how technology can help the building process have come much more into focus, both from the industry itself and also from what customers are looking for. I see all of that as an opportunity. I see all of that as an opportunity for SNC-Lavalin because we have the basic abilities, certainly within the Atkins acquisition we made in 2017 and the way we've nurtured that and built upon it within the company. I see this as an area to offer our capabilities, yeah.

Mona Nazir

analyst
#109

All right, I have nothing further. Thanks.

Ian Edwards

executive
#110

I appreciate that.

Operator

operator
#111

That brings the Q&A portion to a close. At this point I'd like to hand the conference back to Denis Jasmin for any closing remarks.

Denis Jasmin

executive
#112

Much appreciated for being with us today. Should anything else come up that you'd like to ask about, feel free to reach out to me. I hope everyone has a wonderful day. Many thanks to all of you. Take care.

Ian Edwards

executive
#113

I appreciate that.

Operator

operator
#114

That brings us to the end of today's conference call. Your lines can now be disconnected. We appreciate you joining us, and we hope the rest of your day is a pleasant one.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete AtkinsRéalis Group Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to AtkinsRéalis Group Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in AtkinsRéalis Group Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.