Aura Minerals Inc. (AUGO) Earnings Call Transcript & Summary
November 9, 2022
Earnings Call Speaker Segments
Gabriel Sapucaia
executiveHello, everyone, and good morning. Thanks for joining us for Aura's call about results from the third quarter. Joining us today are Rodrigo Barbosa, our CEO, and Kleber Cardoso, our CFO, and both will be speaking. Following their remarks, we'll open things up for questions, and you're welcome to submit yours whenever you like — whether that's while the presentation is underway or afterward — using the Q&A button in Zoom. You can already find the presentation, the earnings release, the MD&A, and the financial statements posted on our IR website. Rodrigo, over to you.
Rodrigo Barbosa
executiveI appreciate that, Gabriel, and I want to thank everyone for joining us for this quarter. I'll walk through the key highlights for the period, production included, and after that Kleber will take you through the results in greater depth. I'd also like to extend an invitation to everyone to take part in our Aura Day, where we'll lay out the company's full strategic agenda in more detail; that takes place next Thursday at 8:00 A.M. Eastern Time, which is 10:00 A.M. Brazil Time. Please join us there, because we'll be in a position to bring the entire market of investors up to date on our strategic agenda. A few things are already underway. I'll speak in broader terms during this presentation, and afterward we'll dig deeper. This presentation contains some forward-looking statements, so I ask you to read our cautionary statements. Those can be found on our website and in this presentation too. On the production side, for the quarter we had been expecting a stronger period than Q2. As the majority of you are aware, in mining you sometimes run into lower grades, higher grades, better recovery, weaker recovery, so some quarter-to-quarter fluctuation is only normal. During Q2, we faced difficulties with recovery in Honduras, where we hit sulfates and mixed ore, which brought our recoveries down, while our expectation was for an increase in Q3 and Q4. Aranzazu delivered a very strong quarter for us. Once again, we processed over 313 tons at the mill. Following the ramp-up we finished last year, we managed to hit 100 tons per month, 100,000 tons per month. At this point we're above that level. Aranzazu remains on track and on budget to achieve this year's guidance. What we have done is lower some guidance as a result of the weaker copper price, and I'll get into that later. At EPP, as we were also disclosing to the market during this year's second semester, we are reaching higher grades at phase II in Ernesto Pit. That is already taking place in Q3, and it will step up further in Q4. Because of that, we were able to raise production in EPP during Q3 by almost 40%, almost 50%, a 48% increase, and we ought to keep raising it through Q4; on the other side, San Andrés, in Honduras, gave us a quarter that was challenging and worse than anticipated, mainly for two reasons. First, too much rain. We saw 70% more excess rain than the historical values. Second, as we are doing across all our mines — in Brazil at the start of the year, in Aranzazu last year — renegotiating contracts and changing specifications in an effort to better offset inflation. We identified a chance to switch the mine contractor in Honduras, which we carried out during Q3. But through that transition, productivity was lost. That, together with the excessive rain, left us with production below what we had projected. So, as we shift into Q4, get Honduras back to full productivity, start mining the higher-grade zones at Brazil, and keep Aranzazu running at a strong pace, we expect a really solid fourth quarter — somewhere in the range of 70,000 to 75,000 ounces of gold equivalent, versus 58 gold equivalent ounces in Q3. That's a big jump. If you look at what we produced in September and October, roughly 22,000 to 23,000 ounces each month, and we're now ramping up further, we have a lot of confidence we'll hit that guidance. On the guidance side, we're updating the market for the full year. Add the 70,000 to 75,000 ounces from Q4 to what we've already delivered across Q1, Q2, and Q3, and we see 245,000 up to 250,000 ounces of gold equivalent for the market. That's below our previous estimate of 260 to 275, and there are two main drivers. The first: 8,000 ounces tied to a weaker copper price. As everyone in the market knows, we produce both gold and copper — copper out of Aranzazu, gold from all our other mines. About 75% of revenue comes from gold and 25% from copper, and we convert copper output into gold equivalent. If copper prices fall, you end up with fewer gold equivalent ounces. Once you factor that price adjustment into our forecasts, it works out to 8,000 fewer gold equivalent ounces for the full year. The second driver: weaker-than-expected output from Honduras for a variety of reasons in Q2 and again now in Q3. There's also — and Kleber will walk you through this — some effect from non-recurring losses this quarter, largely tied to the lower copper price, since you true up the copper price on concentrate 120 days after the shipment date. When copper drops, you have to adjust to the new price after 120 days, and that hit our EBITDA by $10 million. EBITDA for the quarter came in at $17 million, or $27 million excluding that non-recurring copper adjustment. On the flip side, it was a very significant quarter strategically for the company — we put $81 million to work, mostly for the Borborema acquisition, the Almas build, plus some other exploration and mining rights. With that spending, we're locking in our growth agenda, and we're now handing the market a new long-term guidance: those projects don't just get us past 400,000 ounces annualized by 2024, they get us above 450,000 ounces by 2025. That's meaningful growth we're delivering to shareholders through a portfolio, all while keeping operations generating solid, healthy cash flow, which lets us sustain a good dividend. Just a quick update on Almas. We acquired Borborema. We're moving Almas forward. At Almas, construction is nearing 80% completion. That project remains on schedule and within budget. Operations kick off in April of next year, and we'll reach full output, ramping up to that full production level, by Q3 2023. As for Borborema, we're currently refreshing the studies; those were originally prepared under Australian standards and JORC. We've now switched them over to NI 43-101. A new feasibility study ought to come out sometime next year. That project already carries 1.9 million ounces in measured and indicated resources. Turning to Matupá, we also published a feasibility study for it during the quarter. Let me remind our investors that Matupá is a project which, back when Rio Novo acquired it, arrived with geology that hadn't been fully explored, yet sufficient for us to expect a highly attractive return. Our plan last year was to turn the resources into reserves and put out a feasibility study as quickly as possible so we could begin producing as quickly as possible, and then keep exploring afterward. With just the 300,000 ounces of reserves, this project already delivers a payback of 2.3 years along with a leveraged return reaching 50% annually over a seven-year mine life.
Rodrigo Barbosa
executiveBut at this point we're in the middle of a drilling campaign, and as we put out in the first half of the year, we hit some interesting intercepts — 3.89 grams per tonne across 81 meters, and 3.14 grams per tonne across more than 50 meters. Those results make us confident that, alongside building Matupá, we can grow both resources and reserves, and we'll get into much more detail on that at Aura Day. Over the quarter we also kept up our share buyback. If you take the past 12 months of buybacks plus dividends together, you'll see we're delivering a 7.8% return — a dividend yield that includes share buyback — to our shareholders, which shows we're able to keep growing, keep investing in our projects, and keep paying dividends under our policy. Thanks to all the new strategy and all the enhancements we've made at Aura, we once again took the number one performance spot on the TSX. If you look at the TSX30, which tracks how shares performed over the last three years, we earned that in 2021. We earned it again in 2022. Even so, we still trade at a discount relative to our peers, and hardly any companies can show this kind of growth — from 250,000 ounces up to more than 450,000 ounces by 2025. We're also working to raise awareness of this company in the North American market. That's the reason we listed on OTCQX, the over-the-counter market in the U.S.A., so we can spread the word about the company's story. Number one performance on the TSX, and the highest dividend yield of any company in the sector worldwide. And still very few investors know about Aura in the U.S. and Canada, which gives us a very strong chance to build awareness and bring new investors into our portfolio. Next slide, please. On safety, we recorded one lost time injury at EPP in Brazil. It involved a pinky finger hurt during maintenance. That person has already made a full recovery and won't face any kind of problems going forward. Meanwhile, at Aranzazu, Almas, and San Andrés, we had a period with zero lost time injuries. On stopping COVID, we're now phasing out a lot of the schedule and a lot of the process we had to contain, since contamination is already coming down. We had under 1% of our workforce contaminated during the quarter, with mild or no symptoms. On the stability of our structures, as you know, we use third-party auditors and consultants to check them. We also have an internal program where we follow up on all the structures monthly, at a high level, weekly, and at a more detailed level, together with third parties who audit and advise us on how to improve our operations. We had GE21 Consultoria Mineral. It's a well-known company and consulting firm in Brazil. During this quarter, they toured our Honduran sites as well as Aranzazu, and every geotechnical structure sits at a satisfactory level. On the production front, as the left side of this slide shows, we move from 58,000 ounces in Q3 up to 75,000 ounces in Q4, which is below Q4 2021; even so, our AISC is lower and copper prices are higher, so we're climbing toward record-high output in Q4 2022, and with what September delivered plus the October figures we're now releasing, we have strong confidence we'll hit those numbers. Looking at the right side, mine by mine, in more depth: EPP shows notable growth. That's Ernesto, and as we'd projected, it's arriving with better grade. At San Andrés, we had that higher range, and also, when we transitioned the mine contractor, we lost productivity. San Andrés came down. Aranzazu, as expected, holds at 26,000 ounces of gold equivalent. Right in line. Aranzazu right in line. EPP, San Andrés — yes, the quarter was tougher, but we're now heading into the final quarter, where productivity is improving, and the payoff from switching the mine contractor — better productivity plus lower cost — should arrive in Q4 and then carry into 2023; on cash cost, Q3 came in under Q2, matching our projection. We'd projected a big drop, just not $971. The biggest factor shifting our guidance from $800-$853 per ounce to $875-$899 now is San Andrés, with recovery changes in Q2 and weaker productivity in Q3. EPP and Aranzazu are essentially aligned with the guidance we issued earlier in the year. At EPP, the exchange rate was less favorable, but mine improvements — partly grades running somewhat above plan, plus our ability to cut costs — offset that currency effect too. Today, as I said alongside the quarter, we've taken a major step toward firming up our long-term agenda. We're now updating things here, factoring in the Borborema projection, the project we picked up during the quarter. More detail on that slide to come. We'll be able not only to surpass 400,000 ounces annualized by 2024, but now reach 450,000 ounces of gold equivalent by 2025. Still on the strategic agenda, here's some information on the Almas project. On the left, you can see photos showing how fast construction is advancing. We're already at 79% of construction finished, on time, on budget. Civil works follows the action plan. Assembly and erection runs ahead of schedule. A few items also came in earlier than planned; the bulk of the CapEx has either been settled through negotiation or already disbursed; 91% of overall CapEx along with 99% of service equipment materials are now committed. As of yet, we anticipate no form of cost overrun while construction proceeds. We're being reminded at this point that we're the ones carrying out this build; construction got underway early in the current year; production ought to begin in April of next year, backed by $74 million of CapEx. Kleber, over to you now, Kleber, you'll walk us through further specifics regarding the results.
Kleber Cardoso
executiveAppreciate it, Rodrigo, and good morning to all of you. Thanks for joining us today. On this slide, like we always do, you'll find a recap of the key financial KPIs the company reports for the quarter, for recent quarters, and for the trailing twelve months at the close of each reporting period. Beginning with net revenues on the left-hand side at the top of the page. Net revenues for this quarter came in at $81 million. As Rodrigo mentioned, there was no recurring effect tied to the offtake agreement involving our Aranzazu mine and Trafigura as a customer. Under that agreement, a price adjustment occurs four months following the first invoice's issuance, since copper prices fell sharply across February, March, and April in Q3. A $10 million price adjustment landed in the clients' favor, and that weighed on our revenues this quarter. Should copper prices hold at third-quarter levels, we don't anticipate this impact going forward. In fact, with copper prices sitting where they are right now, roughly $363 per copper, we ought to see a gain as soon as next quarter. Naturally, if copper prices return to where they stood at the start of the year, that ten million impact should come back to us down the road. Excluding that $10 million effect, revenues would have reached $91 million, which is nearer to what we posted in the prior quarter, even with copper prices lower by 19% in Q3 versus Q2, and with both copper and gold prices down 9% between the third quarter and the second quarter. Higher production on our end partly made up for the drop in metal prices during the quarter. Still at the top of the page, moving to the right-hand side, adjusted EBITDA: we're reporting $17 million for this Q3. Same story here — adjusted EBITDA took a hit from weaker metal prices this quarter, plus that $10 million offtake price adjustment at Aranzazu. Without this non-recurring item, adjusted EBITDA would have come in at $27 million for the quarter, nearer to what we reported in the prior quarter. Once again, even with metal prices lower, this reflects stronger production in the quarter, along with a reduced cash cost, which we already observed in Q3 relative to Q2. Turning to the bottom of the page, net income was barely above zero — a positive $0.1 million this quarter. On the next page, I'll walk through the details of net income for the third quarter of the year. Lastly, on net debt and cash, we ended the quarter with $80 million of net debt. The rise in net debt this quarter was anticipated, since the company put over $80 million into growing the business — chiefly the Big River acquisition, but also faster construction at Almas, mineral rights purchases by Apoena, and some exploration CapEx and exploration expenses. Looking at Q4, we anticipate net debt will decline once more, since several of those items won't be present. The key point is that no asset acquisition will occur in Q4. Per Rodrigo's explanation, production-wise it will be our strongest quarter. Moving to the next page. Here we present the bridge from adjusted EBITDA to net income, walking through net income for the quarter. On the left-hand portion of this page, as I mentioned, you can see what EBITDA for the quarter would have been absent those non-recurring price adjustment effects. That EBITDA figure would have come to $27 million. Once the price adjustment impact is factored in, the adjusted EBITDA we're reporting stands at $17 million. Then there's amortization and depreciation of $9 million, plus financial results of $2 million. Both of those lines have been largely in line with what the company reported over prior quarters and with our own expectations. During this quarter, we recorded a non-cash effects loss of $4 million. That stems from the Brazilian real depreciating against the U.S. dollar during the quarter. When the Brazilian real weakens, that's actually a positive for our Brazilian operations, since they become more competitive and bring their cash costs down. From an accounting standpoint, though, there's a negative effect when translating the reais we hold in working capital. We hold reais in Brazil, and when we translate them into our U.S. dollar accounts, that shows up. Income tax expenses came to $5 million. Lastly, for this quarter, we're reporting a gain of $4 million tied to the Serrote promissory notes. As a quick reminder, the company sold the Serrote project a few years back. As part of the payment structure, the company received a $10 million promissory note, payable subject to certain conditions. To date, many of those conditions have been satisfied. Construction of the Serrote project was finished. The project finance has been secured by the owners of Serrote. More recently, Serrote declared commercial production. Given all of those facts, the expectations and the chances that the full $10 million amount gets recovered have gone up. As a result, we're booking an additional $4 million gain this quarter in our accounts receivable. Next page. Here we provide a detailed analysis of the changes in the company's cash and equivalents across the third quarter of the year. On the far left of the page, we see the cash position at the start of the quarter, which was $280 million. That opening cash position sat above the historical cash level we would typically hold at Aura, because we had prepared for all the investments we expect to make during the third quarter. Here on the left side of the page is what we call adjusted free cash flow to firm, meaning the free cash flow to firm generated by the mining operations on a recurring basis, excluding positive or negative non-recurring working capital items. Even though this quarter proved tougher, largely due to metal pricing and the price adjustment effect at Aranzazu, our mining operations still produced positive cash flow totaling $7 million. Moving to the center of the chart, we show the extent of the company's growth investments during the quarter. That figure came to $81 million. The biggest component was the Big River acquisition at $54 million, while exploration and expansion CapEx of $23 million also used cash during the quarter. The bulk of that, close to $20 million, went toward building Almas. As I noted earlier, Mineração Apoena also acquired mineral rights, which we anticipate will assist us in extending the life of the Apoena mine. In addition, we put money into exploration expenses. Lastly on this page, we present the identical analysis, only covering the full year — the nine months of 2022. Once more, on the left side of the page, we show adjusted free cash flow to firm, a stronger figure of $34.39 million; next, in the center of the chart, the largest cash users, with growth investment reaching $110 million across the first nine months of 2022. Brownfield work at Almas accounted for the primary items, though a meaningful share of cash also went to exploration activities, including at Matupá and Aranzazu, plus other mines that will help us extend the life of mine across our operations. Then, on the right side, there are some additional proceeds and uses. Debt financed a portion of those investments, and we also gave back $10 million in dividends along with $9 million in stock repurchases to our shareholders so far this year, which brought cash to $121 million at the end of September. That concludes our presentation. We're ready for questions. Thank you.
Gabriel Sapucaia
executiveAppreciate that, Kleber. Our opening question comes from Edgard Souza at Itaú BBA. Edgard, your microphone is live, so go ahead and ask.
Edgard Souza
analystAll right. Hello there. Hello, everyone. I appreciate you taking the question. My first one concerns the effect that the offtake agreement at Aranzazu has. In the fourth quarter, ought we to anticipate further price adjustments stemming from this offtake agreement? And then my second one: for the 400,000 gold equivalent ounces targets of 2024, which copper prices are you taking into account? Thanks, everyone.
Rodrigo Barbosa
executiveThank you. Kleber, please go ahead.
Kleber Cardoso
executiveAbsolutely. I appreciate the questions, Edgard. Regarding your initial question about those price adjustments — assuming copper prices stay at their current level, we don't anticipate any negative effect. Quite the reverse: we ought to see a positive effect on Q4, though not the $10 million, just some favorable movement, since adjustments can go either way. As you're aware, during Q3 we experienced a sharp and rapid drop in copper prices, and now there's some recovery taking place. Given where copper prices currently sit, we should actually record some gain in Q4. Should copper prices return to their levels from the start of the year, the entire $10 million would come back to the company as a positive impact. Naturally, if copper prices decline and reach $3, for instance, we'd then face some extra negative effects. On the whole, should they remain at present levels, no positive or negative impacts are expected. As for your second question, for 2024 and 2025 we rely on consensus metal prices; the figure is roughly $3.65; we draw on a report from certain investment banks, and unless I'm mistaken, the assumption for long-term copper prices is $3.65.
Edgard Souza
analystOkay. Thank you.
Kleber Cardoso
executiveYou're welcome.
Gabriel Sapucaia
executiveThe next person in the queue is Conrado with Safra.
Conrado Vegner
analystHello there, and good morning. I appreciate you taking the call. I want to kick things off with a few items about exploration. To begin, regarding those newly acquired mining rights at EPP, could you let us know whether those parcels sit near the properties where you're currently drilling, and what timeline do you have in mind for kicking off exploration or any activity on those new parcels? In addition, please share any updates you might have about the Serrinhas prospects, and whether we might see even stronger return rates there, given how close it sits to X1 and the existing infrastructure. Then one more item, switching topics to inflation: I'd like to understand whether you build any buffer into the CapEx forecasts for your new projects to account for contingencies and potential cost escalation. Thank you.
Rodrigo Barbosa
executiveConrado, thank you. I'll take those now. The first thing you raised concerns the mineral rights purchase we completed at EPP, and you wanted to know whether it sits near the mine — either the operating mine or the plant. Indeed, it lies right beside our Japonês pit. The distance to the plant comes in under 5 km. Our rationale for acquiring it: having mined at Japonês, and holding certain data on this new parcel too, we can see the mineralization trending in that direction, which gives us strong confidence that drilling can begin quite soon. At present we're wrapping up the entire acquisition process, after which drilling should get underway by the close of this year or the start of next year. Our projection is an updated resource and reserve statement for that parcel by the end of next year, with the mine plan in place as early as 2024. Your other point concerned Serrinhas. As for what will unfold with X1, we're constructing the plant extremely close to the X1 deposit. Serrinhas sits roughly 20 km away from X1. Trucking remains viable, so erecting a second plant beside Serrinhas is not part of our plans. What will occur instead, once resources and reserves are established there, is that we'll simply haul the material and rely on the full infrastructure already set up for X1. Serrinhas will contribute additional return on top of the Matupá project, building on the X1 investment. As I noted, we've already reached 50% leverage return on that project. Once we proceed and enhance Serrinhas, we'll push beyond that 50% figure. That's the basis for our confidence that return on equity for the project will exceed 50%, alongside a meaningful extension of mine life. Then came your contingency question. Indeed, contingency is built into every CapEx we forecast. Contingency can run at 15%, varying with the project's stage. Once you shift further into the feasibility study phase and start moving toward construction, that contingency drops to 10% or occasionally even below 10%. Right, every one of our CapEx figures does include a contingency, and the figure we put out already bakes in a certain amount of contingency.
Conrado Vegner
analystAll right, excellent. Many thanks.
Gabriel Sapucaia
executiveCaio Greiner from BTG Pactual has the following question.
Caio Greiner
analystHey there, good morning, everyone. I've got two things to ask. First off, when it comes to 2023 output — so if we look at the guidance range you provided for 2022, the upper end you originally announced came in at almost 290,000 ounces for that year. I was hoping to get some clarity on how we should frame that for 2023. For the operations excluding Almas, they ought to land close to that same range. Had we relied on older copper price assumptions, we might have figured on roughly 300,000 ounces. But given that you said expectations needed to be lowered by about 8,000 ounces — let's round that to 10,000 ounces — we could estimate the top end of output excluding Almas at approximately 280,000 or 290,000 ounces for 2023. Does that logic hold up in your view? Once Almas is factored in, you noted it should ramp up and reach full capacity by Q3 of next year. So we might figure on tacking on an additional 20,000 ounces. Putting it all together, is it reasonable to anticipate roughly another 300,000 ounces of production from Aura in 2023? Is there some other factor we're overlooking in our assumptions? I realize you'll likely share this at Aura Day, but perhaps we could get a sense of your thinking, and whether this whole line of reasoning checks out. I'll pose my second question after you respond to this one. Thanks.
Rodrigo Barbosa
executiveCaio, thanks. I must apologize, but I'm unable to respond to that, since we're currently finalizing all the projections for 2023, and we can't give you that guidance until it's issued as a press release. What you can do is this — naturally, we intend to launch Almas by April of next year, building up to full output over the course of Q3 next year. Naturally, you'd then incorporate that production into our growth. Still, I'm not able to discuss the 2023 guidance.
Caio Greiner
analystAll right. No problem.
Rodrigo Barbosa
executiveOkay.
Caio Greiner
analystSure, that's fine. For my follow-up, I want to ask about the fresh contractor over in San Andrés. There are a couple of things I'd like to cover. First, I'm simply attempting to figure out whether the softer ramp-up that hit third quarter volumes had been anticipated beforehand. When you fellows brought that contractor on board, was this already part of the plan? Then, on the second matter, what sort of productivity improvement do you anticipate getting out of this new contractor? Perhaps you could frame it around costs, or around volumes — either would be useful. Thanks.
Rodrigo Barbosa
executiveAll right, let me take the first stab at it. Kleber, if you happen to have the cost per ton handy, we can also just — Caio, we are shifting some dollars per ton, and going forward we'll be running at a cheaper cost. My sense is we'll bring it down by 10%, though Kleber will verify that. As for what you asked regarding the difficulties: whenever a contractor gets swapped out, we invariably budget for a certain amount of inefficiency, since you've got fresh equipment, fresh employees, and an entirely new setup, and all of that drags on productivity. We were aware there would be certain hurdles. In the end it proved harder than we'd assumed, correct? In Honduras, you simply don't find a large pool of contractors available. Getting every piece of equipment moved in consumed additional time. Bringing new staff aboard consumed time. The ramp-up, the training, the productivity — every bit of that has hurt our output; we don't anticipate this carrying over into Q4. In fact, we're already seeing productivity get better. Kleber, do you have that price per ton? If it isn't available, then an answer ought to be inserted in that spot.
Kleber Cardoso
executiveRight. I don’t have that figure in front of me. What we do know is that it’s well under where we were, and at this point it’s higher than historical prices. With the new agreements, we’re not seeing that old inflation carry through.
Rodrigo Barbosa
executiveYeah.
Kleber Cardoso
executiveWe can check the specific numbers.
Rodrigo Barbosa
executiveYes; on the contractor side at the mine, it comes to roughly a 10% decrease in price. And once things settle down, we anticipate some productivity improvement versus the other one. That's because the equipment and the trucks are bigger and better able to handle too much rain, really. Correct? When conditions are wetter, that equipment performs very well.
Caio Greiner
analystOkay, thanks a lot, everyone.
Gabriel Sapucaia
executiveThe next person in the queue is Román Rossi with Canaccord.
Román Rossi
analystMorning, everybody, and I appreciate you taking my questions. There are two, if I could ask them one after the other. The first concerns how Matupá and Borborema get built. According to what you've disclosed, you're assuming construction on both mines begins next year. I simply wanted to find out whether you have any CapEx guidance, and in particular, whether you anticipate taking on additional debt in order to build these mines.
Rodrigo Barbosa
executiveI did not understand the last question. Particularly if we are?
Román Rossi
analystTrying to take new debt. For the construction of the mines.
Rodrigo Barbosa
executiveWe're aiming to kick off building at both sites next year, but not at the same time. One will happen in the first half of the year, and the other in the second half. The final call hasn't been made yet, but we're leaning toward doing Borborema first, followed by Matupá. There's still plenty of analysis and modeling underway. The plan is for the one beginning in the first semester to reach production by the second semester of 2024. For the one we start in the latter half of next year, production should begin by 2025. That's the reason we're now able to give the market updated 2025 projections. On the CapEx side, we don't have figures for Borborema yet. What we do have is the number they generated, and we're currently revising it, looking at ways to improve the return on that project. As for Matupá, the investment is $104 million; Román, our usual approach is to fund at least 50% of CapEx through debt, with the rest coming from equity. Naturally, if there's a chance to improve that ratio, we'll take it, but typically in our projections, it's 50% debt and 50% equity for these projects.
Román Rossi
analystGreat. Turning to the second question about EPP guidance: through the year's first 9 months, output has been roughly 44,000 ounces, and hitting the midpoint of your guidance means roughly 26,000 ounces still need to come. Could you give us some detail on how you plan to get to that level of production during Q4? Should we expect better grades? More feed going into the mill? Any detail along those lines would be useful.
Rodrigo Barbosa
executiveCorrect, it's mainly better grades. In the past, we'd recover 1 gram, 1.2 grams per ton. Today we're sitting at 3 grams per ton, 2.80 grams per ton. Naturally, that's going to blend with the other zones, the ones with the lower grades. We'll find out. I'm aware you've already noticed a big jump in grades that's pushing our output past 10,000 ounces per month during certain months.
Román Rossi
analystOkay. Fantastic. Thank you very much.
Rodrigo Barbosa
executiveThank you.
Gabriel Sapucaia
executiveThat wraps things up for now.
Rodrigo Barbosa
executiveAll right. Thanks to everyone for joining. Once more, I'd like to extend an invitation to all of you to take part in Aura Day, happening next week on Thursday at 8:00 A.M. Eastern Time, which is 10:00 A.M. Brazil Time. The company's strategic agenda has plenty in motion, and there are numerous operational enhancements too, which we'll be happy to share with you. Appreciate it.
Kleber Cardoso
executiveThanks, everyone. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Aura Minerals Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Aura Minerals Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Aura Minerals Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.