operatorWe appreciate everyone being on the line, and we’re glad to have you join us for Aurelia Metals Limited’s report on the quarter ending September 2026. <<operator_script>> At this point, I’ll turn the call over to Steve Badenhorst, our Managing Director and Chief Executive Officer. Steve, the floor is yours.
Stephanus Badenhorst
executiveThanks, Mel, and morning, everyone. Appreciate you being here for Aurelia Metals' first quarterly meeting of the new financial year. Martin Cummings, Andrew Graham and Angus Wyllie are with me today. This is also my first quarterly review, so I'll take just a quick moment to sketch who I am. As was announced at the outset, I'm Steve Badenhorst. I've recently taken the reins as Managing Director and Chief Executive Officer of Aurelia. Before this, I was most recently with Rio Tinto and a few other Tier 1 mining organizations. My career as a mining engineer has mostly been in operational leadership roles spanning bulk commodities through to base metals, in both surface and underground operations across multi-mining jurisdictions. Operational excellence is something I feel strongly about, and we'll get into that later. But that's enough about me — I'd now like to hand over to Martin and the team to share the great news on our first quarterly performance, which he and the team delivered over the period from Bryan's departure to my start a few weeks ago. Martin?
Martin Cummings
executiveThanks, Steve. I'll be walking through the presentation we put out on the ASX this morning. Moving to Slide 3. The main takeaway for this quarter is that as production has grown, we're seeing stronger cash generation. We produced more copper, gold and zinc, while lead output matched the prior quarter. That increased production has once again pushed Cobar Regional cash -- operating cash flow to its best quarterly result since 2018. That in turn lifted our cash and liquidity above $200 million. Our growth projects remain on track, and our leadership is now in place with Steve starting this month. Overall, our operating performance and balance sheet position us well for the next chapter under Steve's leadership. Moving to Slide 4. As I mentioned, it's been a strong start to the year, positioning us well against our production, cost and capital guidance, which we have also reaffirmed. Gold production of 16,200 ounces was supported by continued access to high-grade gold ore from the Peak South mine. After just the first quarter, that figure represents close to 30% of the midpoint of our full year production guidance.
Martin Cummings
executiveCopper output rose to 1,300 tonnes for us, representing 43% of the midpoint in our FY '27 guidance. This quarter we processed a proportionately larger amount of copper ore than we will in later quarters, and grades came in strong, though it positions us favorably for the copper production guidance across the year. Zinc production reached 8,300 tonnes, marking our best quarterly zinc result since FY '22, while lead output of 5,200 tonnes was broadly consistent with the previous quarter and, importantly, stays on track versus guidance. Group operating costs came in lower this quarter, at slightly below $90 million — worth noting that during the prior quarter we reported rehab costs for Dargues, which are now reported separately. The primary reduction in operating costs this quarter came from a larger share of costs being capitalized at Federation for mine development, along with somewhat lower corporate costs. Operating costs will fluctuate from quarter to quarter as the volume of mine development completed changes, but we continue to track in line with our guidance. One quick aside on diesel, since it's of interest to everyone: we encountered no delivery problems this quarter, with shipments arriving without interruption, and we're not aware of any forthcoming issues regarding future supply.
Martin Cummings
executiveOn capital, sustaining capital came to $13.2 million, while growth capital was $11.7 million. On the sustaining side, we do have certain fleet investments in Q2 that should push spending higher next quarter, and that will produce a spend profile that lines up more closely with the full-year guidance. Our exploration expenditure rose by $4 million, driven by acceleration across our regional and underground programs. And yesterday you saw some excellent results that Andrew will speak to later in the pack. So let's move on to Slide 5. The key message here is that our mines keep building the ore availability required to support the production growth we have planned. At Peak, mine development remains on track at above 1,500 meters per quarter, and ore mined came in at 148,000 tonnes. That was down slightly following a very strong June quarter, but it is slightly ahead of our plan year-to-date. The investment in production drilling capacity that I mentioned last quarter has kept benefiting our mining rates. Drill stocks grew from around 25,000 tonnes at the end of June to more than 70,000 tonnes at the end of September, and those additional drilling contractors are now demobilized from site. At Federation, 97,000 tonnes of ore mined.
Martin Cummings
executiveIn July, we encountered certain difficulties involving production drilling, downtime on loaders, and a shortage of operators as well. Happily, though, mining rates came back to plan during August and September. On the development side, we had to actively manage surface water, since our water management dam and the TSF at Hera reached levels that forced us to slow mine dewatering. That meant water had to be stored underground until extra capacity in the dams could be built. We upgraded our water management infrastructure by purchasing 2 large evaporator fans and renting a second reverse osmosis plant. Happily, these efforts brought water levels down in both dams. Even so, mine development came in lower for the quarter at 1,147 meters, with the effect mainly tied to our inability to push the decline deeper. Our focus this quarter is on dewatering what remains of the water in the decline and restoring services, which is on track. We also expect normal development rates starting in Q3 of this year. Importantly, we do not expect this situation to affect our FY '27 metal production guidance. Now, moving to Slide 6, the plant kept performing strongly, processing 226,000 tonnes, close to the record of 230,000 we achieved in the June quarter.
Martin Cummings
executiveOn the production side, what really drove results was grade — we saw better gold grade along with improved copper grade in the copper ore, and for the lead-zinc ore, a larger share of Federation material in the mill feed, which lifted zinc and lead grades. And happily, recoveries kept performing strongly, maximizing the metal we produced. Yet equally significant is the mining performance I discussed on the prior slide, which let us grow our ROM stocks even with strong plant throughput. By the end of September, the combined Peak and Federation ROM stockpile stands at 123,000 tonnes, giving us extra feed once the expanded plant processing capacity comes online through quarter 2 FY '27. Now turning to Slide 7, covering the expansion projects and the tailings water — the tailings and process water management project is finished. Our existing tailings thickener has been given a new role as a second leach feed thickener, and the new tailings thickener was commissioned in June. That project will help us achieve higher copper and zinc recoveries while cutting our cyanide consumption. The tertiary ball mill and the new cyclone cluster are installed and tied in as well. This week, the mill has in fact been operating on both water and slurry as part of the commissioning plan, and we aim to wrap up that commissioning during this quarter, with the expanded plant capacity expected to be fully available starting in quarter 3.
Martin Cummings
executiveAlso, as we said back in August, we now have the regulatory green light to run the plant at the higher rate. Turning to Slide 8 and Great Cobar — that project keeps moving forward according to plan. During the quarter, mine development rose to 506 meters, compared with 438 meters in June, bringing cumulative project development to 2,380 meters out of roughly 4 kilometers still to be finished. Underground work right now is being focused on where the fresh air raise will go, and that's the next big development milestone. At surface, the concrete foundation collar for the raisebore rig is finished. There's a photo of that collar being poured on Slide 3. The raisebore rig is scheduled to mobilize in November, and the pilot hole should start this quarter. Design work is also moving ahead on the electrical and dewatering infrastructure, the grid connection arrangements and the heavy vehicle haul road intersection. As I mentioned, the project is still on budget and on schedule, with first ore expected in financial year '28. Great Cobar, as you're aware, is going to be a significant source of high-grade copper and gold ore and is a core piece of our strategy to boost production via the expanded processing plant at Peak.
Martin Cummings
executiveI'll pass things along to Andrew now, and he'll walk you through exploration.
Andrew Graham
executiveThanks, Martin. Our exploration team has been very active throughout the quarter, as the quarterly summarized. Touching on just a few of those items, there's work at New Cobar and Federation, plus regional targets where we're awaiting assays and processing those results. So our intention really is to bring you updates on the Federation exploration programs and the New Cobar mine exploration programs before Christmas. And then hopefully, an additional Peak South Mine exploration update in due course. But we've also been busy at Peak South Mine. And as Martin alluded to, we did issue a release yesterday on that work. So I thought today, instead of running through everything we've been doing this quarter, where we're still working on the results, I'll run through those Peak South Mine results. So the 4 items to touch on are covered on Slide 9 of the pack that went out today. Firstly, in the Peak Kairos gap, I suppose, so between the Peak Western Lead Zinc Lens and the Kairos Eastern Copper Lens, that was an area poorly constrained by drilling. You'll recall that we tied in that development between Kairos and Peak a little while back.
Andrew Graham
executiveWe now have platforms to drill from, and as we drilled from those, we hit what I'd call nothing short of stellar grades. Yesterday we released a meter at 1,120 grams per tonne gold, which sits within a broader zone of 10 meters grading 113.3 grams per tonne gold and 1.3% copper, and that's in hole 224, which you can see on the image. Even if you strip out the effect of that nuggety hit, it remains a very broad and very good grade intercept of gold and copper between Kairos and Peak. And the view we now hold is that those 2 lenses are in fact joined into a single lens. So that gives us plenty of opportunity to keep targeting it through drilling. The other pieces we put out: we released results from drilling at the Kairos Eastern Copper Lens, which extended mineralization 100 meters to the north and also 80 meters down dip. And then the third item of good news we put out was drilling at Perseverance Zone A. We had a hit there that included 2.8 meters of almost 4% copper within 11 meters at 1.4% copper.
Andrew Graham
executiveMuch like Kairos Eastern Copper, which ran roughly 30 meters along strike. Also worth noting is a hole we didn't call out, 9.7 meters at 2.1% copper. So there are some strong intercepts up there north of Perseverance Zone A. Lastly, whether you're viewing the image or caught it in yesterday's release, you can see a drill hole trace going from surface down beneath Kairos, hole 217. We drilled from surface specifically to avoid problems from acute drilling angles and talc, which had made underground drilling of the Kairos extensions difficult. That hole is now completed. The plan is to drill a set of wedges, meaning daughter holes branching off that parent hole. And those who remember Federation a few years back know that approach worked extremely well, cutting drilling costs substantially. So through this financial year, the plan is to return and put a series of daughter holes off that Kairos hole. So we've been quite busy on the exploration side. It was great to share the Peak South mine results with you yesterday and walk through them just now, and we look forward to bringing you Federation and New Cobar exploration updates shortly.
Andrew Graham
executiveMartin, over to you.
Martin Cummings
executiveThanks, Andrew. Moving to Slide 10, this really illustrates how the quarter's operating performance has driven a substantial lift in cash and liquidity. The chart on the left, as you can see, displays the rise in operating cash flow after sustaining capital for our Cobar region, which now stands at $65.3 million for the quarter — once again the strongest quarterly figure since 2018. The real driver here is the robust production and sales I discussed earlier. Beyond that, this covered our growth capital of $11.7 million, which is tracking in line with spend, mainly for Great Cobar and the Peak plant expansion. We also put a further $4 million toward exploration. One more thing to flag on the cash flow chart on the right: you'll notice a working capital outflow of $23 million for the quarter. Three main items account for that. First, we built up higher concentrate receivables at quarter end. We take receivables through our operating cash flow and then recognize the actual cash receipt in working capital, so those receivables did accumulate at quarter end. We also released some of our trade payables relating to costs from the June quarter, primarily.
Martin Cummings
executiveTrade payables, therefore, come in lower, with cash flowing out. Then lastly, September is the month when our annual incentive gets paid. So costs have been accrued across the year, and in September we paid employees their annual incentive. Following those movements, though, net cash rose to $160.7 million from $143.9 million. And as mentioned earlier, that puts liquidity, together with our undrawn revolver, above $200 million. One further note about cash. Most of you are aware that after the quarter end, we paid the $0.01 fully franked dividend announced in August. It was paid on the 8th of October, totaling $17.2 million. So that covers it. I'll now return things to Steve for closing comments.
Stephanus Badenhorst
executiveThanks, Martin, and thanks as well to Andrew for that update on exploration. I want to turn now to the final slide, Slide 11, and talk about a few key areas of focus, drawing on first impressions and the conversations I've had with lots of you during the weeks since I joined the organization. First, I believe it matters a great deal that we deliver operating performance that is safe and predictable, and that ties into the next point, which is driving gains in productivity and cost. Work that is planned, properly scheduled and properly carried out is much safer. It costs less and is more economical. It is more sustainable. It benefits our customers. It is genuinely good for our investors, and it feels good to be part of a winning team. Importantly, if we are able to bring the cost base down, we gain access to considerably more ore in the Cobar Basin, and that access will shrink if we cannot get the cut-off values low enough. The other item is finishing our growth projects. As Martin mentioned, things are moving along very well with the timing of the Peak Processing Plant. Getting that finished so we reach the full 1.2 million tonnes of operating capacity annually is a really significant commissioning milestone, and over Q2 we hope to take meaningful steps toward it.
Stephanus Badenhorst
executiveThe Cobar development is going great. I got the chance to visit down there a few weeks back, and it's moving along really nicely. Things are going extremely well at the area where we'll be intercepting the new raisebore shaft. There's plenty of enthusiasm around there regarding the copper development that Cobar will bring. One area I'm passionate about is embedding asset management fundamentals. We're an asset-intensive business, with both fixed and mobile assets. Maintained properly, those assets will deliver the performance and reliability the organization needs. That means asset criticality has to be assessed. Work gets planned, resourced and executed correctly, and work management indicators will give us the satisfaction we need that the work is being done right. If we achieve that, our supply chains can be optimized and the cost benefits are significant. Unplanned work costs roughly 4x what unplanned work does. The -- growing our ore body knowledge matters a great deal to us, and that's the term we've used there, we keep advancing our ore body knowledge. We've generated a lot of information in the Cobar Basin over recent years. The more we understand our ore bodies, the better our longer-term decisions can be on investments, growth, optionality, et cetera.
Stephanus Badenhorst
executiveWe hold an appealing set of tenements across the Cobar Basin, and it's set to be a significant copper producer going forward, particularly around the Great Cobar project. Understanding this ore body matters a great deal. And as we're aware, throughout the Cobar region, a lot of the ore bodies within our reach — as Andrew discussed not long ago — remain open at depth. Once we move into the underground workings, that gives us a chance to carry out additional infill drilling and pursue that opportunity. Last, something I'm passionate about too is bringing in, growing and keeping a high-performing workforce. The people I've met over the past few weeks have impressed me. Their knowledge, experience and dedication to delivering our results is genuinely impressive. We have to line up with our key objectives. We have to reach our aspirations, and being part of a winning team is simply a natural passion that I believe most people share — enjoying being on a team where you're getting results. We're looking at options to resolve some of the accommodation difficulties that have existed in Cobar for a long time, and we're working alongside plenty of community members to address that. Last, we need an inclusive culture where everybody shows up to work each day and has the chance to contribute to our aspirations.
Stephanus Badenhorst
executiveMel, I’ll finish on that note and turn it back over to you for questions from the online audience.
Operator
operator<<operator_script>> Our initial question is from Adam Baker at Macquarie.
Adam Baker
analystWelcome, Steve — not a bad quarter to be joining the company. Just maybe starting with strategy: is there anything in the strategy you'd like to change compared to the prior management team? Or do you see the business as being on a pretty even keel at this stage?
Stephanus Badenhorst
executiveYes. I'll take that one fairly quickly. You mentioned the word keel — I don't think that applies. In my view the ship is still afloat, and what this quarter shows is solid operational performance. If anything, what's needed are small tweaks to our direction so that operating gains become more durable. As I mentioned, one opportunity I see is making the asset management basics work properly. The fixed and mobile assets available to us must hit the performance targets we require. That really is essential, and they also need the right functional availability. So I wouldn't call it a strategy change. If anything, it's a course correction — a modest one — aimed at more sustainable improvement. And to link back to my very first point, if we can achieve that and bring down our cost base, I believe there's a chance for us to enhance access to the reserves, or the resources, that we hold in the Cobar Basin.
Adam Baker
analystAlright, and if I could just ask one thing about Federation. You brought up the overlap with additional water. I'm just curious whether that ties to a new aquifer you may have hit as you've been drilling deeper? Or is the water more connected to surface -- surface storage facilities, and I suppose, capacity from that direction? Just trying to get a handle on the problem on that side of things.
Stephanus Badenhorst
executiveThanks. I’ll hand that question over to Angus, since he’s at Cobar and is likely better placed to answer it than I am.
Angus Wyllie
executiveYeah. No, the higher water flow is definitely tied to underground. So what we're seeing is growing water flows underground, and we're also expanding our surface infrastructure capacity along with our ability to handle that water. We saw positive progress during the quarter, with new evaporators installed and additional RO plants, and we can now manage that volume of water and get back on top of it.
Adam Baker
analystOkay, and perhaps just to follow up on the expansion at the new mill or the Peak capacity plant expansion. Obviously, there are a few tie-ins happening this quarter relating to the tertiary ball mill and new cyclone cluster. Do we expect any downtime from this side of things?
Angus Wyllie
executiveAngus speaking. Yes, indeed. We just wrapped up a five-day shutdown recently in order to finish those tie-ins. The new cyclone cluster is now up and operating, and this week the ball mill is turning and has been loaded with balls. So we're actively commissioning the tertiary ball mill at this point.
Operator
operatorThe following question is from Peter Kormendy at Shaw and Partners.
Peter Kormendy
analystMaybe there's one more question for Steve. Liquidity stands comfortably above $200 million. The company funds itself. So this is a fantastic moment to come on board. Could you share some broad thoughts on what your priorities will be, and maybe how you'd divide those among Great Cobar, New Occidental, or perhaps additional exploration at Peak South?
Stephanus Badenhorst
executiveYes. The liquidity position is clearly a fascinating topic. When you consider our working capital, we need about $100 million to handle the normal ups and downs the company experiences regardless. So yes, we're in an excellent liquidity spot, and joining a company at this kind of stage is genuinely appealing. Whether we're prepared to make any significant calls about how we might shift our course right now, I'm not certain. Deviating from this year's planned exploration or the scheduled plant expansion isn't something I expect us to do. Our growth projects are locked in and proceeding on schedule. So using that capital at this point isn't something I anticipate. Over the coming months, I'll be working with our Board, and early next year I'll be strategizing alongside the Board. At that point, we should be better positioned — likely between the end of Q2 and early Q3 — to decide whether any change in direction will occur, though at this moment I can't see that happening.
Peter Kormendy
analystAlright, one more question, this time specifically about the gold-heavy mix. If you annualize the September quarter, it comes out to a rate considerably above what we're currently guiding to. How sustainable do you view that gold mix we saw in the September quarter? Or should we expect a step down in the second half of the year?
Stephanus Badenhorst
executiveAngus, would you mind handling that question?
Angus Wyllie
executiveFor the quarter that's coming up, the plan we have in place right now does include reduced gold output. We benefited last quarter from a number of stopes with very high grades. Gold production will be somewhat lower across this next quarter, but we're still on track and are looking toward the upper end of guidance.
Stephanus Badenhorst
executiveWell Peter, as I mentioned in my remarks, a good chunk of the gold we saw came from the copper ore we put through the mill this quarter. We've actually got quite a bit of Federation ore stockpiled on the ROM, and that material carries a lower gold grade since it's high in zinc and lead. So if you're wondering how we're filling the cup on each of the guidance items, gold and copper are both pretty strong right now. And then as plant capacity grows and we push more of that feed material through, that's the way those metals will kind of top up. So that's roughly how the year is shaping up.
Operator
operatorOur following question is from Paul Kaner at Ord Minnett.
Paul Kaner
analystStarting with the exploration results near Peak and Kairos: does that shift your thinking about the mine plan for the coming 3 years? Does it alter your outlook for Peak?
Stephanus Badenhorst
executiveAndrew, would you mind handling that?
Andrew Graham
executiveYes, absolutely. Paul, it's good to hear from you. Look, no, this doesn't alter our plan. So throughout last year, we discussed a bit the fact that with the gold price in particular, there was more inventory at Peak South Mine. This just adds to that. So effectively, we're getting certainly the material above Kairos, below Peak, in that bridge area. It's great. That additional inventory sits very close to development. All of the extensional drilling where we managed to extend mineralization along strike is again very close to development. So those tonnes will come through. So what it does effectively is what we're already doing, which is to remain in South Mine a little bit longer, and that buys us some optionality, particularly as Great Cobar starts to <<inaudible>> fundamentally change our plan.
Paul Kaner
analystYes. No, that's clear. And then, just to follow up on Peter's question, on guidance—you kind of mentioned tracking at the top end of the range for gold and potentially copper too. But lead production is also running above expectations. I suppose what I'm asking is, did this quarter come in better than planned? Or should we expect some retracement across all the commodity suites to hit the midpoint of guidance, specifically for copper and lead?
Stephanus Badenhorst
executiveMartin, you have the floor.
Martin Cummings
executiveWell, sure, Paul — we're quite pleased without, you know, getting into a budget-versus-actual comparison. The performance has us feeling good. Metal production is solid. And absolutely, we're at ease with the current guidance. That said, I suppose we'll see another quarter through before we think about modifying it. But certainly, on lead — lead is tracking near 25% of midpoint, zinc sits at roughly 28%, 29%. Copper runs high owing to that mix problem. We simply processed far more copper ore than we will across the rest of the year, and the gold came along with it. And then — just to clarify that, as you noted in the report, when those gold-only stopes are being mined at the Peak South mine, we are — they get reported as copper ore. So they go through copper ore in the stats. But — so considerably more copper ore, and then considerably more lead zinc ore with Federation in the second half, or across the balance of the year. So — but I'll just say we feel comfortable regarding metal production.
Stephanus Badenhorst
executivePaul, to revisit that earlier question of yours about how much expansion potential exists and whether it might shift over the coming 3 years — one lesson I picked up quickly at Peak and across all of this is that the further we advance into these operations, the more chance there is to carry out infill drilling deeper down from platforms already in place. These ore bodies, we know, remain open at depth. And the more we can grasp — and it's excellent to see the exploration upside coming through in that update we provided — but the more we grasp from depth, the better, I believe, we'll be positioned to forecast what the Cobar ore bodies are like, and they're probably more clearly defined once infill drilling is done as we reach the top. Drilling of an exploratory kind from surface gives us a really solid signal of where it may sit. Still, we do know the deposits continue deeper. So there is a likelihood of expansion at depth, yet it genuinely depends on us reaching the deeper mining areas and setting up an exploration platform from which that infill drilling can be done.
Paul Kaner
analystAnd then the last thing, more or less, on senior management and personnel. I see Andrew has moved into a different role. Just on that IP departing AMI, so to speak, any thoughts regarding his situation and who will be stepping into it?
Stephanus Badenhorst
executiveYes. One of the situations I've inherited is that Andrew is moving on, which is unfortunate, and I wish him well in the next opportunity he's going to. But it also gives us a chance to look at the organizational structure at this point in our development. And over the coming weeks I'll be doing that. So it's too early to say whether it's a direct replacement or some kind of reorganization at this stage that could come out of that. So I wouldn't speculate right now. I think all options are on the table. But it's -- I haven't arrived at a position where we go with a direct replacement at this point. The team that works for Andrew is very confident that those organizations or parts of the business are doing a great job. So there's a chance to reorganize how that reporting relationship sits, but that will come when we make the decision in the next few weeks.
Operator
operatorDaniel Roden from Jefferies has the next question.
Daniel Roden
analystThanks for the congratulations on the quarter. I’d like a little more detail on a couple of items you’ve already discussed. Let me get into the Peak mining costs. Doing a quick back-of-the-envelope calculation, I come up with roughly $160 per tonne (sic) $161 per tonne, which, again, is what my dataset states and is probably among the highest ever recorded. I note that reducing that unit cost has been a very large focus over the last year or 2. Could you help explain what has driven that cost increase and how much of it, I guess, relates to pursuing higher-grade stopes whose current commodity price gives them a higher NSR? How are you thinking about that internally? And, I guess, given that this has been a pretty major focus over the last 2 years, what strategies can you implement starting now? And what has not worked over the past couple of years?
Stephanus Badenhorst
executiveThanks, Daniel. Like I mentioned, this is genuinely something I care deeply about, and I believe the specialists right now — I'll hand things over to Martin.
Martin Cummings
executiveYes, Dan. I'll start with a few remarks, then pass things to Angus for anything more he wants to add. But yes, I believe we flagged the figure of $161 per tonne in the report — that's Peak mining costs. There are a few elements behind that. I mentioned production drilling capacity, and I raised it back in the June quarter. So we deliberately put extra investment into operators, mainly, and into equipment, to get ahead on production drilling. Those operators were demobilised during September. So we deliberately kept some of those costs running across the June quarter and the September quarter. Diesel, obviously, has cost inflation in it. We don't use a huge amount of diesel, but it does feed into Peak, and probably more into Federation given hauling ore up the road. But I guess the other part — and Angus can give more detail — is that when we're working through our budgets, given the nature of the stopes and how many stopes we're mining at Peak, the stope — the average stope size is getting considerably smaller. So what we're seeing is that we go into these — the same setup and the same development to reach these smaller tonnage stopes, but with higher grade.
Martin Cummings
executiveFrom a margin standpoint, those are definitely worth pursuing. But that does mean the mining cost to access them, measured in dollars per tonne, comes out higher—simply because we don't have those bigger stopes. Once we move over to Great Cobar, though, the stope sizes will be larger on average. So the per-tonne figure should naturally get better as a result, though it's certainly something we're concentrating on heavily as we put together our plans for this year. Angus, maybe I'll hand it over to you in case you have anything else to add on that?
Angus Wyllie
executiveNo. Thanks, Martin. Yeah, as Martin mentioned, that really is the main factor when we worked through the budget. This year we're mining average stope sizes ranging from 6,000 to 7,000 tonnes per stope. So it takes a comparable level of work and effort to prepare those stopes as it does to mine a 20,000 tonne stope. That's where a portion of the cost increases is showing up, and we keep a clear focus this year on improvements in productivity and efficiency. And hopefully we'll see some of those results come through over the coming quarters as we work on improving those unit costs.
Daniel Roden
analystRight, and building on that point — scale has played a major role, perhaps while you’re commissioning and ramping the mill expansion up to 1.1, 1.2 — which areas on the mining side, I suppose, are supporting that? Federation is, obviously, still ramping up and basically in its infancy, so to speak, but there’s still some distance to cover there. For instance, will the stope size at Peak South grow over the coming couple of quarters so it can underwrite and underpin a fully expanded mill?
Stephanus Badenhorst
executiveAngus, over to you?
Angus Wyllie
executiveNo, we aren’t seeing the stope size go up. It’s basically around — we’re working those areas between — around Peak and Kairos, nearer to the crusher and the hoisting infrastructure, and really advancing those stopes. So again, we’re focused on that productivity and efficiency, making sure those stoping fronts are in place. And as Martin mentioned earlier, we have the production drilling, and we’ve kept that drilling going to ensure we have drilled stocks ahead of us, and we have that material — that material available in the quarters to come as we move forward.
Daniel Roden
analystAnd perhaps just one more from me. I realize you've discussed the strategy and your thinking on the business going forward and all of that. But if I factor in that there's some working capital build this quarter that might be reversed — sorry, folded into next quarter's cash flows, your business is in quite good health. How should we think about capital allocation over the next 12 months, beyond project selection? For instance, are you considering shareholder returns? How do you view shareholder returns given that you have, I believe, $40 million or $50 million of franking credits on the balance sheet? Is that a conversation you're having at the management and Board level?
Martin Cummings
executiveYes, Martin here again. Yes, I believe, as we discussed back in August, Steve coming on board genuinely provides us with a chance to take another look at the strategy work he's keen to pursue. You saw our thinking in August regarding the capital management framework. And we really do want to elaborate on that for you — to put a bit more detail around how we're weighing shareholder returns against allocations to exploration, something I know Steve has a real interest in, and also other inorganic growth. So those discussions are definitely taking place, though we're probably not ready yet to take you to the next level on what that means.
Operator
operator<<operator_script>> Our following question is from Ian Hecox, a retail shareholder.
Shareholder
unknownMy apologies, I didn’t actually have a question. I’m sorry if that caused any confusion.
Operator
operatorThat brings us to the end of the question-and-answer session. Mr. Badenhorst, I'll return the floor to you now for any closing comments.
Stephanus Badenhorst
executiveThanks, Mel, and thanks to all of you for being here today. It's genuinely wonderful to become part of an organization delivering the same quarterly performance. And since this quarter marks the start of the first one in our 2027 financial year, being part of the organization is really advantageous. I appreciate the questions. Before we wrap up, I'd like to offer Andrew my very best wishes in his new ventures — he'll be departing the organization in the next few weeks — and to thank him for what he has contributed, especially for leading the exploration portfolio, which was one of his passions as well. So thank you, everyone, for what you contributed to the quarter. Those of you with Aurelia, thank you for your dedication to our results, and I'm looking forward to working alongside all of you over the coming period to see that Q2 turns out even better than Q1 possibly. Thank you.
Operator
operatorThat wraps up today's conference. We appreciate everyone joining in. You're free to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Aurelia Metals Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Aurelia Metals Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Aurelia Metals Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.