Greetings, everybody, and thanks for joining Avista's call covering results for the fourth quarter and fiscal year 2020. We published our earnings figures along with our 2020 Form 10-K before the market opened today, and you can find both on our website. With me today are Dennis Vermillion, Avista Corp.'s President and CEO; Mark Thies, our Executive Vice President, Treasurer, and CFO; Kevin Christie, Senior Vice President of External Affairs and Chief Customer Officer; and Ryan Krasselt, Vice President, Controller, and Principal Accounting Officer. A reminder to all of you: certain remarks we make today constitute forward-looking statements involving assumptions, risks, and uncertainties, all of which may change. For a look at the various factors that might cause actual outcomes to differ materially from what we discuss on this call, please check our 10-K for 2020, posted on our website. Before diving into this presentation, let me go over the financial results from today's press release. Consolidated earnings for the fourth quarter of 2020 came to $0.85 per diluted share, versus $0.76 in the fourth quarter of 2019. On a full-year basis, consolidated earnings reached $1.90 per diluted share for 2020, against $2.97 last year. At this point I'll hand things over to Dennis.

Dennis Vermillion

executive
#2

Okay, thank you, John, and good morning to all of you. As 2021 gets underway and we keep dealing with the COVID pandemic, we hope that you are safe and healthy. When I think about the past year, I feel such pride in our employees for how they handled the difficulties the pandemic brought, for continuing to deliver energy to our customers the way they always have, and for moving our business plans ahead. I want to express my thanks to every one of our employees for their commitment and resolve over the past year. We keep assisting those in our communities who are struggling and in the greatest need. During 2020, Avista and the Avista Foundation gave over $4 million in charitable contributions to address the growing demand for services that community agencies continue to face in the areas we serve. On the financial side, our 2020 earnings came in above expectations, and Mark will share more specifics in just a few minutes. On the operational side, we completed the installation of almost all of our smart meters, electric smart meters, and natural gas modules throughout Washington, one of the biggest projects in our company's history. Deploying this infrastructure will give customers more real-time data so they can manage their energy usage better. This technology lets us proactively send high energy alerts to let customers know if they might go over their preset energy budgets, which naturally helps remove surprises when the bill shows up at the end of the month. Beyond producing bills, we use smart meter data to operate a more reliable and efficient power grid and to provide a higher level of service to our customers. For instance, we now have greater visibility into our system, which lets us find and fix power outages faster; we also made progress toward our clean energy targets when the Rattlesnake Flat Wind Farm came online last December. While it was being built, the project generated clean energy jobs for our local communities, and now that it is finished, the project's 57 wind turbines, pardon me, will deliver 50 average megawatts of clean renewable energy to our customers at an affordable price. That is enough energy to power 38,000 homes for years ahead. As wildfires keep affecting our region, we put in place a new comprehensive 10-year wildfire resiliency plan aimed at strengthening defense strategies and operating practices for a more resilient system. We expect to invest roughly $330 million to carry out the components of this plan over the plan's life, which, as I mentioned, was 10 years; we were proud to announce yesterday that Avista has again been named one of the 2021 World's Most Ethical Companies by Ethisphere, a global leader in defining and advancing the standards of ethical business practices. This is the second year in a row that Avista has earned this distinction. Based on their assessment, we are just one of nine honorees recognized in the energy and utilities industry. In 2021, 135 honorees in total were recognized, spanning 22 countries and 47 industries. We feel privileged to get this acknowledgment, since it affirms our conviction that folding corporate responsibility into how we run the business creates trust, builds enduring relationships, boosts morale, lowers risk, and produces greater value for our shareholders, and in the end lets us more effectively fulfill our vision of providing better energy for life. Back in January, we posted Avista's 2021 corporate responsibility report on our avistacorp.com site, and I encourage you to take a look when you have a moment. This material offers a wide-ranging view of our operations and of how we are meeting our obligations to our employees, our customers, our communities, and our shareholders. The site also includes links to Avista's reporting on a number of industry and financial ESG disclosures. This refreshed material backs Avista's long-held dedication to corporate responsibility and to sharing such information with our stakeholders. Changing topics, on the subject of regulatory filings, during January we submitted two-year general rate cases in Idaho, and as you're aware, during 2020 we submitted general rate cases in Washington, and we keep working through the regulatory processes in both of those states; we take very seriously our duty to supply safe, reliable energy at a price people can afford, and we strive to make sound financial investments in our infrastructure, control our costs, and find ways to serve our customers as well as possible that help hold energy prices down. As an illustration, our proposed tax customer credit would entirely offset a near-term rise in electric and natural gas bills for our customers in Washington. Over in Oregon, new rates took effect on January 16th of this year, and we anticipate submitting another rate case during the second half of 2021 in Oregon. Going forward, we stay concentrated on operating a excellent utility and keep putting prudent capital to work to maintain and upgrade our infrastructure and deliver dependable energy service to our customers. We are starting our 2021, 2022, and 2023 earnings guidance with consolidated ranges of $1.96-$2.16 per diluted share for 2021, $2.18-$2.38 in 2022, and $2.42-$2.62 per diluted share for 2023. That positions us to earn our allowed return by 2023. Finally, earlier this month, the board lifted our dividend by 4.3% to an annual dividend of $1.69 per share. The dividend increase the board approved represents the 19th consecutive year the board has raised the dividend for our shareholders, and I think it shows the board's dedication to maximizing shareholder value. With that, I'll hand this presentation over to Mark.

Mark Thies

executive
#3

Thanks, Dennis, and good morning to all of you. We came into this year with low expectations. Not the company — the Blackhawks. After a sluggish first four games, the Blackhawks have actually gotten off to a pretty solid start; we've seen five rookies net their first career NHL goals. Exciting times for those of you who follow hockey; as for the company in Q4, Avista Utilities delivered $0.81 per diluted share, versus $0.67 during the same period a year ago. Our earnings rose mainly because of better utility margin and customer growth. In addition, during the fourth quarter, the Oregon and Washington Commissions joined the Idaho Commission in permitting deferral of certain COVID-19-related expenses for possible future recovery. On top of that, Avista Utilities' earnings came in above expectations thanks to higher utility margin and lower income taxes, partly offset by greater operating expenses; regarding COVID-19, as I said before, we've now obtained accounting orders in every one of our jurisdictions to defer the costs and benefits tied to COVID-19, and those will be taken up in future proceedings with each of those commissions; we anticipate a gradual economic recovery that will still involve somewhat depressed load and customer growth in 2021. We expect improvement to begin in the second half of 2021 for our economy. We do have decoupling and other regulatory mechanisms that soften the effects of load changes for our residential and certain commercial customers. Over 90% of our revenue, as you remember, is covered by regulatory mechanisms. As Dennis said, we remain committed to putting the necessary capital into our utility infrastructure. We expect capital expenditures in 2021 to be roughly $415 million. At AEL&P, we expect roughly $7 million, and roughly $15 million in our other businesses; regarding liquidity, as of December 31st, we have $270 million of available liquidity under our committed credit line at Avista Utilities. In 2020, we issued roughly $72 million in stock in 2020. In 2021, we expect to issue roughly $75 million of equity or stock and up to $120 million of long-term debt. As Dennis said, we're initiating guidance not just for 2021, but for 2022 and 2023 as well. As he mentioned those ranges, this is meant to get us back to earning our allowed return by 2023. Our guidance does assume timely and appropriate rate relief in each of our jurisdictions relative to the capital ex- and expenses that we have going forward; we experienced regulatory lag during 2020 and expect this to continue through the end of 2022 due to our continued investment in infrastructure and our delayed filings. We again delayed last year, as we discussed with the, with the pandemic in Washington and Idaho. Dennis mentioned those earlier. We expect our cases in Washington and Idaho, along with new rates, to provide some relief in 2021 and begin reducing that regulatory lag. Moving forward, we'll aim to keep lowering that and bring our returns into close alignment with what was approved for 2023. Once 2023 is behind us, growth of 4%-6% is what we anticipate. Our earnings. Unrecovered structural costs, estimated to cut return on equity by roughly 70 basis points, are reflected in our 2021 guidance. Beyond that, our timing lag — the very thing we're attempting to shrink through rate cases — has brought it down by around 100 basis points. For Avista Utilities in 2021, that leaves an expected return on equity of about 7.7%. Operating cost growth of roughly 3% and customer growth of roughly 1% per year are what we're forecasting, a touch better than earlier figures when it comes to customer growth. For 2021, Avista Utilities should contribute somewhere between $1.93-$2.07 per diluted share, and no expense or benefit under the ERM is baked into the midpoint of our guidance. In our present view, the ERM sits in a benefit position inside the 75% customer, 25% company sharing band, which should add $0.05 per diluted share. For 2021, AEL&P should contribute somewhere between $0.08-$0.11 per diluted share, and normal precipitation and hydroelectric generation for the year are among the variables our outlook for both Avista Utilities and AEL&P assumes. A loss of between $0.05 and $0.02 per diluted share is what we expect from our other businesses. As we keep building opportunities for the future, we'll invest a modest amount over the coming couple of years to keep raising those earnings across the next five years, and we're eager for those opportunities. They're both in our service territory and in funds. Only normal operating conditions are generally included in our guidance, and no unusual or non-recurring items enter the picture until their effects are known and certain. I'll now hand the call back to John.

John Wilcox

executive
#4

Now we would like to open up this call for questions.

Richard Ciciarelli

analyst
#5

Hi there, and good morning. I appreciate your taking my question.

Dennis Vermillion

executive
#6

Good morning, Richie.

Mark Thies

executive
#7

Good morning.

Richard Ciciarelli

analyst
#8

Yes, only the first one. Could you update us on how things are going with the rate case filings in Washington and Idaho? I suppose, to reach the midpoint of your 2021 guidance range, what share of the revenue requirement ask are you counting on?

Kevin Christie

executive
#9

Hi, Richie. This is Kevin Christie. How are you doing?

Richard Ciciarelli

analyst
#10

I'm doing well, thank you.

Kevin Christie

executive
#11

Regarding how the rate case is moving along, we have really only just begun in both of them. Here in Idaho, which is the case we filed most recently, no procedural schedule has been set or seen by us as of yet. That ought to come together within the next few weeks. Over in Washington, the procedural schedule has been set, and so far we have been working through discovery; our first conversation about settlement is scheduled for March 10th. Turning to your second question, what we generally observe as favorable results from a regulatory perspective, comparing what is sought against what is granted, falls within that 55%-65% range. Once again, we believe the capital we have spent has been prudent, and we would anticipate receiving fair recovery from the regulators going forward.

Richard Ciciarelli

analyst
#12

Understood, that's quite useful. Thank you for that detail. I suppose, regarding what you expect looking ahead to 2022 and 2023, your capital expenditures stayed about the same. Clearly, you now have 2 rate cases that appear to be at an early point. So what makes you confident that you can earn nearer to your permitted ROEs across the entire company, and how do you intend to execute in order to reach that? Does the outlook include any multi-year rate plans or similar items?

Mark Thies

executive
#13

A few points on that. We must obtain fair or reasonable outcomes from our commissions and through our filings, yet we also think we submitted suitable cases; we've made prudent investments on behalf of our customers, and our expenses are prudent as we serve them. We are making up for timing lags, so we think we can catch up gradually over the coming 2 years, rather than all at once. We expect that to require a couple of years. In Idaho, we filed a multi-year case. At present we have a 2-year case in Idaho, and as we move ahead, we would consider it, and we'll work through it. We examined it for Washington, but concluded that with everything happening with the pandemic and certain large projects, as Dennis Vermillion mentioned, the AMI project, one of the biggest projects in our history, is being included in this case; a multi-year did not seem sensible, so we filed for a single year. We can file multi-year later; that could bring us to where we need to be. That is essentially our plan: to submit a suitable case reviewed by the staff and the parties, but we believe we can return to earning our permitted return.

Richard Ciciarelli

analyst
#14

Understood. That explanation is quite clear. You're referring to the structural delay that remains at approximately 70 basis points.

Mark Thies

executive
#15

Correct, that is what we anticipate; it has been present for quite some time. We simply highlight it. Indeed, we anticipate that will continue to be the situation.

Kevin Christie

executive
#16

Richie.

Richard Ciciarelli

analyst
#17

Understood. My apologies — please continue.

Kevin Christie

executive
#18

Looking ahead, we're collaborating with the same counterparts in Washington we usually engage with, as well as the commission and the remaining utilities. There's a bill currently before the Senate aimed at steering and in fact mandating multi-year rate plans lasting no less than two years and as many as four years. Should it advance, we view it as a genuinely positive piece of legislation that would give us the ability to have that multi-year rate plan option — pardon me, requirement — and it would assist us in getting the initial year right and the shifts between each year right too. So that's something we'd consider down the road following this specific case in Washington.

Richard Ciciarelli

analyst
#19

Yeah, definitely. That's going to be useful. Okay, great. So the final item I had was, I believe in your press release, you referenced exploring certain strategic opportunities during 2021. Could you explain what exactly you're examining? You also brought up some higher costs in that context. I'm just wondering.

Mark Thies

executive
#20

Richie, it's a small bump in cost. A small bump in cost. What we're doing is, part of that is simply in the University District in Spokane; we keep expanding our five smartest blocks in the Eco-District; we're putting some money into that. We're examining a pilot involving certain possibilities in some regional communities that we believe might hold possibilities for us, and we're also putting money into a couple of different funds where we've had steady dollars. We anticipate those. From a cost standpoint, they're small right now, but we believe they hold possibilities down the road, and they truly relate to the innovative side of our company. Innovation has been part of our history, so we invest those dollars since there are possibilities to assist in the market.

Richard Ciciarelli

analyst
#21

All right, so that falls under the other businesses rather than the utilities.

Mark Thies

executive
#22

That's right.

Richard Ciciarelli

analyst
#23

Alright, thanks. That covers everything I wanted to ask.

Mark Thies

executive
#24

It sits somewhat inside the area we serve, yet it falls beyond the utility segment.

Richard Ciciarelli

analyst
#25

Okay. That's everything I wanted to ask. I appreciate you giving me the time.

Mark Thies

executive
#26

Thank you, Richie.

Brian Russo

analyst
#27

Hi, good morning.

Mark Thies

executive
#28

Morning, Brian.

Dennis Vermillion

executive
#29

Good morning.

Brian Russo

analyst
#30

Hi. You brought up a Washington IRP that's coming in 2021. Does that land in the second half, or in Q4?

Dennis Vermillion

executive
#31

My understanding is April. We need to verify that. Last year we made a filing in Idaho, along with a progress report in Washington. The reason for that progress report was to get the order right with Washington's new Clean Energy Transformation Act. We can confirm it, but my recollection is it's only a couple of months away.

Brian Russo

analyst
#32

Right. Okay. What I wanted to know is, once Colstrip is retired and the Lancaster PPA runs out — which I think happens in 2025 — what should we anticipate from the push for additional PPAs? Going forward, in any competitive RFP, might there be self-build possibilities?

Dennis Vermillion

executive
#33

Yes. That's correct. Clearly, Colstrip is going to exit our portfolio in 2025, and Lancaster follows a year afterward. Acquisition mode is where we'll be. As a matter of fact, a renewables RFP is currently open. What we'd anticipate buying — and this draws on the IRP we submitted in 2020 — I don't think 2021 will look much different. It'll combine generation plant upgrades, more clean energy, renewables, storage, energy efficiency, and demand response. How we'd approach this: in the end, our goal is serving customers' needs in the most cost-effective manner on a risk-adjusted basis, and reliability is going to be a crucial design element in anything we select. This would go through a competitive process. Whether self-build options make the cut for us or don't, we'll simply have to wait and see once we reach that point. In the end, the aim is the lowest cost, risk-adjusted basis for our customers.

Brian Russo

analyst
#34

All right. That 10-year wildfire investment plan — does it sit inside this rate case, or does it need approval through a different docket?

Dennis Vermillion

executive
#35

On the wildfire matter, Kevin, would you like to address that? Does it fall within this case, or is it handled under a separate docket?

Kevin Christie

executive
#36

I'll walk through the situation in each of those two states. Over in Idaho, this was handled as a standalone docket; it's already been submitted and cleared, and what it permits is a deferral approach covering expense, depreciation, and capital. When it comes to Washington, we submitted it under a different docket instead, alongside the most recent GRC there, and it ended up consolidated with that GRC. This is going to unfold across those 11 months, or at least that's what we anticipate happening. Included in that, for 2021, is deferral of O&M, and after that, once we're past the rate effective period tied to the rate case dated October 1, it would cover both expense and capital.

Brian Russo

analyst
#37

All right, that sounds good.

Dennis Vermillion

executive
#38

Brian, we looked just now, and the filing for the upcoming IRP in Washington is going to happen in April of this year. On that one, I was correct.

Brian Russo

analyst
#39

All right, sounds good. So it appears that during the prior year, you brought in $72 million through equity. My understanding is that for 2021, the plan is roughly $75 million. Would you mind discussing how much balance sheet room you have compared with your CapEx? Because of how this rate proposal is uniquely set up, with the tax credits, there could be some near-term strain on cash flows. I'm just curious what your goal is for FFO to debt, or debt to cap, when it comes to credit ratings.

Mark Thies

executive
#40

Sure, once more, what we aim for is to keep the ratings we have right now. We examined that tax customer credit, examined how it affects our FFO, and we feel we ought to be in a position to hold onto our existing credit ratings. This is only for a brief period. It's interim rate relief. That rate relief lasts one year, or as long as two years, based on how each of those cases turns out. Afterward, we go back to typical cash flows; there could be a minor decline in the present year once it takes effect. 2022 is really when that would land. We don't think it ought to alter our ratings, since we bounce back fast to having standard cash flow from it; we don't anticipate our ratings being off, and we keep bringing in capital, the equity, and the debt that we use to support our capital expenditures. What comes out of that is keeping a sensible capital structure for regulatory reasons. We think we will have that. Of course, we'll need to guide the rating agencies through it and go through that process the way we always do. We've taken a look at it, and we've also had an outside review done, and we think it shouldn't affect our ratings.

Brian Russo

analyst
#41

All right, understood. So next, you brought up certain bills sitting with the Senate in Washington that permit rate cases spanning multiple years, and so on. In what way does that line up with the Clean Energy Transformation Act, which grants the commission several instruments, including as much as 48 months of used and useful plant, earning a return on PPAs, and similar items? Would that be an extra thing, or would it substitute for CETA? I just want to get this straight.

Kevin Christie

executive
#42

Yes, fair question, Brian. It comes on top of CETA, which remains in place as we understand it, and every fact and figure we've previously provided still holds. What this does is simply bring added clarity regarding the commission's capacity and its emphasis on a multi-year approach. It's also efficient given that a lot of utilities keep submitting rate cases annually, and this assists the commission in reaching a situation where utilities become somewhat staggered in their cases thanks to the multi-year element. It further brings clarity about what goes into getting that initial year correct and the shifts from one year to the next too. Should this legislation advance, the utility would have the choice to file for anywhere between two and four years. Once more, that would hand the commission the means to reach a determination grounded in those filings.

Brian Russo

analyst
#43

All right, and my understanding is that this bill will either get through or it won't during the current legislative session. What's the closing date for that session?

Kevin Christie

executive
#44

Yes, you've got that right. It could emerge from the Senate at some point in the next several days. After that it would head to the House, and from there the usual Washington procedures would play out. Assuming it keeps advancing, it ought to happen by the time the session wraps up, possibly sooner.

Brian Russo

analyst
#45

Okay. So, following up on something asked earlier — should we expect that you'll submit another Washington rate case so that either the CETA provisions or the provisions in this legislation get folded in, giving you new rates that start closing that regulatory gap in 2023? Or does a favorable outcome in the case that's still pending get you to that point?

Kevin Christie

executive
#46

No, filing will be necessary for us. Most likely, we'll submit it early next year. Should this legislation keep advancing — and even if it stalls — we might still proceed with something spanning multiple years, and that would capture every bit of capital being spent right now that isn't part of the case currently before regulators.

Brian Russo

analyst
#47

All right, understood.

Mark Thies

executive
#48

Brian, the reason is that Idaho is the filing we've got. That case runs 2 years.

Brian Russo

analyst
#49

Yeah, that's right. Regarding only the multi-year guidance and the losses you're taking in the other businesses this year, do you expect those losses to turn around and begin producing positive earnings and/or monetizing some of those investments during the multi-year guidance period?

Mark Thies

executive
#50

Well, within the multi-year, we didn't break out our guidance, and I won't break it out at this moment between Avista Utilities, AEL&P, and other for 2022 and 2023. What we provided was consolidated guidance, but we've stated previously, and we remain committed to this being the reason we're making these investments, that we expect — I believe we began in 2019 saying this — that within three to five years, we expect to start generating earnings from that, $0.05- $0.10 of earnings. We continue to believe we're going to accomplish that. Likely around the 2023, 2024 timeframe, we're aiming to have earnings in those other businesses. Once we release specific guidance on that, we will include it there. We do hold that expectation, and that's why we keep investing dollars in those areas.

Brian Russo

analyst
#51

Okay, that makes sense. So the $15 million being put to work this year — the thinking is that it will produce a return of some kind on that $15 million across the coming years?

Mark Thies

executive
#52

A number of these are new businesses. With what we're putting into the University District, certain ones might not deliver a return for a few years and then come in afterward, while others could deliver returns earlier. It's not like purchasing a bond, where a return arrives annually. These are startup investments, and they require time. Certain ones move faster than others. We've already watched earnings emerge from the fund investments we've made and turn around fairly fast, and we've watched others that will be longer term. There's a balance in that, Brian. It simply requires time. I can't give you specifics on it. Once we release our guidance in those forward years, we'll set it out. As you look at it, we do expect earnings from those businesses to start being generated by 2023 or 2024.

Brian Russo

analyst
#53

All right. So again, you anticipate being in that 75/25 sharing for the ERM, and my understanding is that you've benefited from it annually for at least the past four or five years. What's causing that ERM this year versus last year? That would lead into a second question. Given the weather patterns observed in the Pacific Northwest and what's anticipated over the coming couple of weeks or months, what's your present view regarding hydro concerns?

Dennis Vermillion

executive
#54

Yes. Brian, this is Dennis. I believe what has been pushing the ERM across the last several years is a mix of a couple of factors. One is simply lower gas prices in general compared to what we'd seen previously. Additionally, our team's capacity to optimize or manage our resources efficiently. It's a blend of those factors persisting that I believe places us in a genuinely strong position to receive the benefit in the ERM for this year. Now, clearly, looking ahead, if we witnessed a dramatic run-up in natural gas prices, matters could shift on that. So long as gas remains where it is, we're sitting pretty good. Your second question.

Brian Russo

analyst
#55

Hydro.

Dennis Vermillion

executive
#56

Hydro. Look at where we are — February's nearly over, and there are genuinely still 2 months or so remaining when snow can accumulate up in the mountains. At this moment, we're simply anticipating, when we look ahead, conditions that are normal. The way things stand as of today, the runoff forecast, or the water supply runoff forecast, from the Northwest River Forecast Center covering April through September comes out at essentially average for us, meaning 100%, give or take only a small amount depending on which basins you look at. Broadly speaking, what we anticipate right now is hydro at normal levels as we move forward through this year.

Mark Thies

executive
#57

Keep in mind, Brian, how much temperature matters and the speed at which melting happens. Snow could be sitting up in the mountains. Should it melt very quickly, that's a negative. Should spring stay long and cold, with melting occurring gradually, that's a real positive. Anything between those extremes. As Dennis mentioned, we're anticipating normal since our snowpack is solid, yet you still need to watch the way it comes off.

Brian Russo

analyst
#58

Sure. Naturally, what you're looking for is typical temperatures during April and May.

Mark Thies

executive
#59

Correct. That is the assumption behind our projections.

Brian Russo

analyst
#60

is that the situation currently visible in the market?

Mark Thies

executive
#61

correct.

Dennis Vermillion

executive
#62

Yes.

Brian Russo

analyst
#63

Okay. So, one final thing — I'm just interested. Rates have moved up in recent times, and people are worried about inflation. What kind of effect does that have, first, perhaps on when you plan to carry out your 2021 financing on the debt side? And that 3% growth in O&M expense you brought up before as one of the 2021 assumptions — I'm just wondering what you think about that.

Mark Thies

executive
#64

On the O&M growth side, we're always trying to find ways to keep our costs under control. We give a figure, and then the question is whether we can land below it. We do our best to get there when possible. Our intent was to set out our expectations as they stand, since insurance, pension, and other expenses have climbed. We have to keep working to keep those in check. That's the assumption we have, and we want to state it. As for rates, sure, they've risen somewhat, but not in any major way. We're contemplating 30-year debt, and we've already hedged a portion of it. We aren't attempting to pick the perfect moment down to the final bit. The Fed chair testified before Congress just yesterday and again today, and we anticipate he'll keep saying that low rates are expected — no movement from us. We keep watching it, and should it make sense, we'd consider issuing our debt somewhat sooner. At this point we don't believe that's sensible, and we'd anticipate coming out as we always do and getting it done during the second half of the year.

Brian Russo

analyst
#65

Okay, great. Thank you very much.

Mark Thies

executive
#66

Thanks, Brian.

Chris Ellinghaus

analyst
#67

Sorry. My bad. How are you? Good morning.

Mark Thies

executive
#68

We're not even video, Chris. We couldn't tell you you're on mute.

Chris Ellinghaus

analyst
#69

Right, I mean, I get plenty of things wrong. As for that roughly $75 million run rate you've been running on equity, is it fair to think that's the level you've baked into this guidance window?

Mark Thies

executive
#70

Issuing at that level is something we've done before, and our CapEx isn't being adjusted. Cash flow is the sole thing that will shift.

Chris Ellinghaus

analyst
#71

All right.

Mark Thies

executive
#72

We aren't providing forward guidance on that, though that has been what we've historically expected for issuing.

Chris Ellinghaus

analyst
#73

Okay. You didn't say anything about the dividend payout. Can you just address that?

Mark Thies

executive
#74

Okay, so the dividend payout has remained unchanged ever since we began experiencing some lag; we've stated that our dividend will keep going, and we will reach the guidance we've set out, which is 65%-75%, but that won't happen until we're back to earning our allowed return. Right now we'll be running a bit elevated, and we'll have our earnings growth. As you can see, the guidance ranges for growth exceed the dividend increase, which came in at 4%-5% on the dividend. That was 4.3%, as Dennis pointed out, I believe. Earnings growth is higher than that, which will bring us back in line with our stated 65%-75% payout ratio as we get to earning our allowed return.

Chris Ellinghaus

analyst
#75

Sure. What was the increase in bad debt expense last year?

Mark Thies

executive
#76

I want to say $6 million-$7 million.

Chris Ellinghaus

analyst
#77

All right. You mentioned earlier that you expect the pandemic will keep weighing on things during the first half of the year. Could you share any additional detail about how you anticipate that playing out over this year?

Mark Thies

executive
#78

I'll simply state that this color is factored into our projection. You're going to observe certain load expectations like we have witnessed, but as I noted in my previous remarks, we are largely decoupled. Load that isn't decoupled does have an effect, and then insofar as bad debts exist, yet as we said, we possess deferral mechanisms across every one of our jurisdictions allowing us to postpone that and afterward pursue a recovery via a future proceeding; now, should that proceeding turn out differently, we'll need to deal with it, but what we expect is that those costs ought to be recouped through such future proceedings.

Chris Ellinghaus

analyst
#79

When you factor in both the deferrals and the decoupling, your expectation is essentially that it won't end up being all that large.

Mark Thies

executive
#80

That's our expectation, and it's included in our guidance.

Chris Ellinghaus

analyst
#81

Okay, just one final item. Dennis, what's your take on that electrification legislation up in Washington?

Dennis Vermillion

executive
#82

Appreciate that, Chris. So to start, I'd say our position is that we're in favor of cutting emissions. Clearly, through what we're engaged in on the electricity side, that's what we're doing, and we're making solid headway. The way we go about it has to keep cost burdens on our customers as low as possible and, I suppose I'd put it, safeguard the dependability of the energy systems across the region. My view is we should take a holistic approach so that unintended consequences stay minimal. That said, the bill doesn't truly take into account all of these wide-ranging impacts. I'm glad to be able to say we've been collaborating with other utilities in Washington state and additional stakeholders, genuinely attempting to inform legislators about the significant worries we hold regarding this bill and the major effects we think it would inflict on our customers and the energy system. I'm happy to share that our work resulted in the bill being defeated early on in the legislative session. That's a positive. For this year, it's essentially finished; even so, it's clear we should anticipate that pieces of it, or the whole bill, may return at some future point. All we can do is keep informing legislators about where we stand. Which is, once more, our strong belief that natural gas has a significant part to play as we decarbonize the energy system. I don't mean that as an excuse for natural gas; we're developing plans around renewable natural gas. We're trying out other technologies, or looking into other technologies, and energy efficiency matters as a piece of that too; on the gas side, we'll do our share as well, but our real worry is the impact of electrification — not just what it would mean for our customers when it comes to affordability, but also what it would mean for our electric system. According to our studies, a full electrification of our system would mean electric infrastructure, generation included, would have to double in order to satisfy the added needs, and clearly there are reliability and cost consequences tied to that which worry us. That's roughly our current position on the matter. Going forward, we'll keep working to educate stakeholders on why gas is sensible in the years ahead. Is that useful?

Chris Ellinghaus

analyst
#83

Yeah, that's helpful. Thanks. I appreciate the color.

Dennis Vermillion

executive
#84

Okay.

Chris Ellinghaus

analyst
#85

Be safe.

John Wilcox

executive
#86

Thank you all for being here with us. We truly value the interest you show in our business. Enjoy the rest of your day.

Operator

operator
#87

Thanks so much, everyone, for joining us on today's call. That brings the program to a close. You're welcome to disconnect at this point. Have a great day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Avista Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Avista Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Avista Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.