Capstone Copper Corp. (CS) Earnings Call Transcript & Summary
November 3, 2023
Earnings Call Speaker Segments
Operator
operatorGood morning, everyone, and thanks for joining us for Capstone Copper's Q3 2023 Results Conference Call. <<operator_script>> Today is Friday, 3rd of November 2023, and this call is being recorded. At this point I'll hand things over to Jerrold Annett. Go ahead, please.
Jerrold Annett
executiveGood morning, everyone, and welcome to Capstone Copper's Q3 2023 Conference Call. I want to point out that the news release and regulatory filings announcing Capstone Copper's 2023 third quarter financial and operational results can be found on our website and on SEDAR. If you're logged into the webcast, we'll be advancing the slides of today's presentation, which are also available in the Investors section of our website. Joining me today are our CEO, John MacKenzie; our President and COO, Cashel Meagher; our Chief Financial Officer, Raman Randhawa; and our Senior Vice President, Risk ESG and General Counsel, Wendy King. After our brief remarks, there will be an opportunity for questions. Please be aware that comments made on the call today will contain forward-looking information within the meaning of applicable securities laws. By its nature, this information is subject to risks and uncertainties, and actual results may differ materially from the views expressed today. For further information on the risks and uncertainties pertaining to our business, please see Capstone's most recent filings, which are available on our website and on SEDAR. And finally, I'll just note that all amounts we will discuss today are in U.S. dollars unless otherwise specified. Now I'll turn the call over to John MacKenzie.
John MacKenzie
executiveThanks, Jerrold, and good morning, everyone. We're happy to share the results and achievements from our third quarter of 2023. Beginning on slide 5: last week I was in Chile, and it was a thrill to see how near we are now to wrapping up construction at the Mantoverde Development Project. That project represents the culmination of many years of dedicated work by our team, from permitting and engineering through to the mine build, and we're now approaching commissioning and first production. MVDP is transformational for Capstone copper and will drive step change improvements in our consolidated unit costs as well as a pathway to record operating cash flow generation. During the quarter, we advanced the project in line with our schedule. As at September 30, we had stockpiled approximately 5 million tonnes of sulfide ore, which puts us in an extremely strong position for the project ramp-up. We also began commissioning of the primary crusher and carried out the first rotations of the SAG and ball mills. Meanwhile, at our tailings storage facility, mass excavation was finished, and both the Starting Wall and the Cut-off Trench are close to completion. The project remains on time, with construction completion to occur by year-end. Following that, we expect a 6-month commissioning and ramp-up to the MVDP's nameplate capacity of 32,000 tonnes of oil per day.
John MacKenzie
executiveWith completion nearly upon us, our total capital cost estimate for the project has been revised to $870 million. That represents a 5% rise over the $825 million we initially estimated in March 2022, and three factors largely explain it. First, inflation, chiefly tied to elevated diesel prices affecting pre-stripping and tailings earthworks, accounted for $20 million of the increase. Second, we've implemented several project improvements, among them buying extra retainers for best practice and concentrate transport and storage, a water reservoir, plus additional camp and warehouse infrastructure. Those project improvements added a further $20 million to the increase. The remainder relates to additional forecast ramp-up and commissioning costs. Through a video update of the project from early October, we've provided a link along with our news release and presentation materials. We're excited to be in the final stages of construction. Moving to slide 6; in Q3 we produced 40,300 tonnes of copper at consolidated C1 cash costs of $2.88 per pound. Production and costs took a hit from 8 days of unplanned downtime in the crushing circuits at Pinto Valley, our Arizona operation, as well as from our ongoing debottlenecking work at Mantos Blancos in Chile. Cozamin turned in another solid quarter, with the mine now having ramped up to full production levels using the new cut and fill mining method.
John MacKenzie
executiveOn the whole, output came in a bit better than Q2, and we feel we're in a strong position as we head into Q4. If you turn to slide 7, we're reaffirming our consolidated guidance. To be specific, we still expect second half production of 83,000 tonnes to 93,000 tonnes of copper. As for our C1 cash costs, we've said they're trending toward the upper end of our second half guidance range of $2.55 to $2.75 per payable pound of copper produced. We've also reaffirmed our consolidated capital expenditure guidance for 2023, though we've reclassified certain expenditures by operation, as shown on the slide. I think we're well set up for our strongest quarter of the year in Q4. With that, I'll hand things over to Raman for our financial results.
Raman Randhawa
executiveThanks, John. Moving to slide 8 now. During Q3, copper production came in at 40,300 tonnes, while copper sales totaled 38,700 tonnes. LME copper prices averaged $3.79 per pound over the quarter, a 1% decline from $3.84 per pound in Q2 2023. Our realized copper price was $3.77 per pound, essentially matching the LME average. Consequently, we booked revenues of $322 million for the quarter. Once copper hedges are factored in, the realized copper price came to $3.69 per pound. That gap between LME and our realized price works out to roughly $6 million after tax, or $0.01 per share against our adjusted EPS. Consolidated C1 cash costs for Q3 were $2.88 per pound, pressured by reduced production levels and extra maintenance spending. As we mentioned last quarter, the production denominator remains a major driver of our elevated C1 cash costs. We anticipate lifting output in Q4, which should produce a meaningful reduction in our C1 cash cost. Adjusted EBITDA for Q3 reached $62.8 million, an improvement over Q2, though it was held back by the unplanned downtime at Pinto Valley and the debottlenecking work at Mantos Blancos.
Raman Randhawa
executiveAdjusted net loss attributable to shareholders came in at $15.8 million, and that figure excluded a onetime deferred income tax expense of $24.3 million tied to the Chilean Tax Reform, which includes a modest increase in taxes effective January 1, 2024. My view is that the uncertainty around the new taxation regime in Chile has now been resolved, and any impact to us is somewhat mitigated by the ongoing level of reinvestment we have in the country. Turning to slide 9; on the left-hand slide, we summarize our available liquidity, which as at September 30 was approximately $425 million, including $130 million of cash and short-term investments and $295 million of undrawn amounts on our $700 million corporate revolving credit facility. During Q3, we increased the size of our revolving credit facility by $100 million, and we extended the maturity by one year to September 2027. We ended Q3 with a consolidated net debt balance of $855 million and attributable net debt balance of $705 million. Our balance sheet is in good shape. With Mantoverde <<inaudible>> September 30 of $763 million, the remaining balance is approximately $107 million. We expect roughly $50 million to be incurred in Q4 2023 and the remaining balance of $57 million in 2024.
Raman Randhawa
executiveThe chart on the right side of the page shows how our EBITDA responds to different copper prices. In the first two bars, it’s clear we anticipate meaningful near-term EBITDA growth once Mantoverde sulfides reach full run rate production. At full capacity for MVDP, we expect to produce roughly $1 billion in annual EBITDA, assuming copper at $4. The EBITDA that Mantoverde generates will let us concentrate on producing free cash flow to delever our balance sheet and stay below 1x net leverage at copper prices ranging from $3.75 to $4 per pound, giving us extra liquidity to move our future growth pipeline forward — whether through incremental brownfield expansions or Santo Domingo, depending on market conditions. Moving to slide 10, we lay out our copper hedging program, which offers downside protection for our balance sheet during MVDP construction and ramp-up. In late July, we took the opportunity to add 20,000 tonnes of copper hedges for H1 2024 at an average floor price of $3.74 per pound. In total, our hedge book, excluding QP hedges, contains 54,000 tonnes of copper across the next three quarters, with a weighted average protective lower copper price of $3.54 per pound. At the same time, we hold 21,000 tonnes of <<inaudible>> in our portfolio at a weighted average ceiling price of $4.27 per pound.
Raman Randhawa
executiveOnce the Mantoverde development project has finished ramping up, we won't have any copper hedges remaining, so our exposure to the copper price will be complete. At this point I'll pass things to Cashel for the operations review.
Cashel Meagher
executiveThanks, Raman. At Pinto Valley, we turned out 13,700 tonnes of copper in Q3, with a C1 cash cost of $2.83 per payable pound. Unplanned downtime at the secondary crushing circuit affected operations and cost us roughly 8 days of production. As we talked about last quarter, we're stressing operational discipline and key performance indicators so that online time and reliability improve. We're putting asset integrity assessments first, prioritized by downtime, and we're bringing in condition monitoring to lift our performance. Pinto Valley did well in October and is positioned for its strongest quarter of the year in Q4, helped by higher grades and steadier throughput. During the quarter we kept engaging with our neighbors in the Pinto Valley District as we look into value creation opportunities. Turning to slide 12; Cozamin Mine had a solid Q3, generating 5,900 tonnes of copper at a C1 cash cost of $1.85 per payable pound. Following the switch to the new cut and fill mining method earlier this year, the mine posted another quarter at nameplate mining rates. Crusher availability and unfavorable foreign exchange rates weighed on cash costs in the quarter. Our Mantos Blancos asset is featured on slide 13.
Cashel Meagher
executiveAll told, sulfide and cathode output came to 12,100 tonnes of copper, with a blended C1 cash cost of $2.82 for each payable pound. This year, the sulfide side hasn't run steadily at nameplate levels, even though the key equipment — crushing, grinding and flotation circuits — is still more than able to handle throughput above 20,000 tonnes per day. Bottlenecks have shown up in the links connecting those systems, such as pumps and pipes. We're carrying out our revised plan to fix plant stability, which covers better maintenance plus optimization of the concentrator and tailings system. That plan takes in input from Jim Whittaker, our new SVP, Head of Chile, and Jaime Rivera, our new General Manager. We've likewise folded in what we've learned from running the plant since the expansion wrapped up. During the quarter we worked through a number of areas and dealt with several of the bottlenecks in the mine's crushing and grinding section. To reach a sustainable 20,000 tonnes per day throughput rate, we've pinpointed extra tailings handling and pumping infrastructure that should arrive and be installed in early 2024, and after that we expect to run at nameplate throughput rates. We're confident that we have both the team in place and the asset to support full run rates.
Cashel Meagher
executiveWhat we're working toward is making that happen. Once that's done, we'll restart the studies for Mantos Blancos Phase 2, since we think the ore body is capable of supporting a bigger operation. Moving to Mantoverde on slide 14: oxide output for Q3 2023 came in at 8,600 tonnes of copper in cathode, with a C1 cash cost of $3.74 per payable pound. A temporary shortfall in sulfuric acid supply weighed on oxide production and costs during the quarter, and that issue has now been resolved. The most important thing is that significant progress was made at the MVDP in Q3. It now sits at 93% complete, with $763 million spent as of September 30. As John mentioned earlier, we've raised the project's total capital estimate by 5% compared with the original 2022 estimate. Even so, we're still on track to finish the project by year-end, with ramp-up following in 2024. The Mantoverde Development Project will yield roughly 120,000 tonnes of combined cathode and copper and concentrate, plus more than 30,000 ounces of gold annually. Slides 15 through 18 illustrate construction progress across several key areas of the MVDP. Slide 15 shows the primary crusher in the background, with the covered coarse ore stockpile in the foreground.
Cashel Meagher
executiveIn Q3, we began commissioning tests on the primary crusher. Slide 16 gives a bird's-eye close-up of the processing flow sheet. On the right-hand side, you can see the ball and SAG mills. Over the quarter, we put in the lubrication and cooling systems, finished the first round of testing on those components, and carried out the initial rotation of these mills. Slide 17 highlights the tailings storage facility. Mass excavation is done, and the starter wall and cutoff trench are almost finished. Liner installation is also in its final stages. Finally, slide 18 shows the desalination plant, which has now been expanded to support the MVDP, and we're currently ramping up flow rates to that capacity. I'm excited to wrap up construction of the MVDP by year-end and move into the project's ramp-up stage. Now I'll hand things over to Wendy King for the sustainability review.
Wendy King
executiveThanks, Cashel. Moving to slide 19, we'll go over the sustainability highlights for Q3. As we disclosed before, we're delighted that Mantoverde and Mantos Blancos both received the Copper Mark. Responsible operating practices are an essential part of what we've committed to for the environment, our employees, local communities and governments, and they need to stay top of mind in all that we do. The Copper Mark is a strong champion of transparency and accountability and it strengthens our values around responsible, sustainable production. We're proud of what our Chilean operations have achieved, and we're working hard to repeat that success at Pinto Valley and Cozamin. Also in Chile, we were recognized recently by Corpora Ataccama for Achievements and Advances in Sustainability, for what we contribute to sustainable development in the region. John MacKenzie received the award from the Chilean Minister of Mines, and it's one more testament to the excellent work our teams at Mantoverde and Mantos Blancos are doing. At Cozamin in the quarter, we improved our biodiversity monitoring with camera traps, which automatically take photos triggered by a change in activity nearby. Five of these cameras have been placed across the site, and they'll make a significant difference in how we monitor local species.
Wendy King
executiveAt Pinto Valley, we added more air quality monitoring stations, which helps us better understand how air quality differs from place to place locally, so we can keep protecting the health of workers and our communities. Over the quarter, we kept backing local community initiatives, with a focus on community safety, education, fundraising for local schools, technical training and community celebrations. Pinto Valley put on a local community event that brought in over 50,000 for three schools in the area. Cozamin held a full-day community Safety Fair for families, teaching safety skills in a fun and interactive way. In Chile, roughly 90 local community members graduated from Mantoverde's Learning for Development Program, receiving certificates that boost their employability in food handling, security, forklift crane operations, warehousing and mine equipment maintenance. This backs our strategy of developing technical skills in local communities. In Chile, we have kept up our efforts of teaming with some of our partners to put money into community projects so that community programs have a bigger impact. We are also working on building these initiatives in the other jurisdictions where we operate. Finally, we expect to release our first combined sustainability report for Capstone Copper, Growing Responsibly. It will come out in the coming weeks.
Wendy King
executiveThis report is something we're really proud of — it gives you richer detail on our worldwide sustainability policies, and it presents emissions figures on a per-unit basis, both for ore processed and for copper produced, so that our emissions come through clearly and transparently and stakeholders can track how we're doing. On the diversity and inclusion front, the report also calls out the advancement of a number of women into key management positions in Chile and at Pinto Valley. Having women in leadership is an essential factor in drawing more women into mining and into our operations, and in keeping them there. With that, I'll hand things back over to John.
John MacKenzie
executiveThanks, Wendy. If you go to slide 20, we've laid out the growth plans that lead our sector plus a few additional sources of upside inside our portfolio. As you can see, we expect MVDP, once at its run rate production level, to take us to a consolidated annual level of roughly 260,000 tonnes of copper at significantly lower costs. From that point, we have a pathway to more than 380,000 tonnes of copper production with the fully permitted Santo Domingo project. We have high returning brownfield expansions at both Mantoverde and Mantos Blancos with low capital intensity that are not pictured on the slide. And then further upside exists with oxides at Santo Domingo utilizing our SX-EW plant at Mantoverde, Mantoverde Phase 2, growth in our Pinto Valley district and cobalt optionality in our MV-SD district. On slide 21, we show more detail around what is driving the significant near-term cost reduction at MVDP. As can be seen in the graph on the left, 70% of our copper production today is from sulfides with the remaining 30% from higher-cost oxides. The oxide production has both lower grades and lower recoveries as the highest grade oxides have previously been mined and processed at Mantoverde and Mantos Blancos. With MVDP at full run rate, our copper production will be split roughly 85% sulfides and 15% oxides.
John MacKenzie
executiveThe middle graph illustrates how this affects our weighted average grades and recoveries. This year's blended grade processed stands at 0.35% copper, and with MVDP operating, that will rise to a blended copper grade of just over 0.6%. In a similar way, average recoveries across our portfolio will climb from 80% to closer to 90%. The chart on the right displays the overall impact: a substantial rise in copper production alongside a substantial drop in our unit costs, which together produce an overall gain in margin. Slide 22 highlights the timelines for those catalysts and studies coming over the next year that underpin our growth plans, with additional upside beyond that throughout our portfolio. We have kept building a highly talented technical team and are collaborating with strong engineering firms to carry out these studies. We now expect to deliver the updated Santo Domingo Feasibility Study during the first half of 2024. As the study has progressed, our view is that it does not yet capture the optimal project configuration and design, especially when we factor in the synergies with Mantoverde and the flow sheet improvements we have identified.
John MacKenzie
executiveSo because of that, we've chosen to put in extra time to make sure the project is designed and configured in a manner that maximizes the value created for Capstone Copper before we move ahead to the detailed engineering phase. We feel this approach aligns with best practice in large project development. To conclude, we restate that we are in the middle of a transformational period for Capstone. I'm very excited that we remain on track for project completion at MVDP by year-end, which will lead to a step change to 260,000 tonnes of copper per year at significantly lower costs. That will expand margins and drive record operating cash flow generation for the company. With that, we're now ready to take questions.
Operator
operator<<operator_script>> The initial question is from Orest Wowkodaw of Scotiabank.
Orest Wowkodaw
analystOn the Mantoverde question — capital expenditure went up to $870 million, I believe, plus 5%. Could you shed a bit more light on what's behind that rise? And perhaps even more significantly, how confident are you that this represents the final bump and that $870 million will end up being the definitive figure? We've seen a different project that is in its ramp-up stage announce yet another CapEx overrun. So I suppose we're trying to get somewhat more detail on the reasons for this, or on whether you expect $870 million to be the last number.
John MacKenzie
executiveYes, thanks, Orest. So regarding that cost increase from $825 million to $870 million, it essentially breaks down into two pieces of $20 million apiece. The first piece relates to certain inflationary effects. At Mantoverde we've already taken delivery of three of the large electric shovels. The fourth shovel has in fact arrived and is being put together right now. But that one carried an escalation clause, and given somewhat higher inflation rates, that adds a further amount that hadn't been factored into the $825 million figure. And then I think as well — although our contract with Osisko is fixed-price, the tailings facility operated on a unit rate basis. So I think the effect of elevated diesel prices in particular hit all the earthmoving work we required to develop the trench and the start-up wall at the tailings facility. And some of the pre-stripping activity was similarly affected by somewhat higher diesel prices. The remaining $20 million came from areas we identified that would genuinely improve and enhance the projects. So we'll be moving all of our concentrate to port with a comparatively new technology known as retainers.
John MacKenzie
executiveThese are basically containers, though the ones loaded at the site get completely sealed and can then be moved to the ports. At the port they effectively serve as storage, and from there they are tipped straight into the vessel. So this is what we'd consider a form of leading practice when it comes to transporting and storing concentrate. And when we took a look at — we had already placed orders for these retainers, we already essentially own what we first thought would be enough retainers, but we chose to order additional ones so as to factor in any possible fluctuations in — you encounter things such as swells at the ports, which are capable of delaying shipments. And we simply wanted to ensure we had sufficient capacity available. We also made the decision to install a water reservoir, and that really was just on the basis of — we are aware that we have more than enough water for the MVDP. However, throughout the ramp-up, you invariably have a water balance, and a portion of that water comes from the tailings facility and from recovery out of tailings, but it takes a while before that is actually accessible to you.
John MacKenzie
executiveSo we basically felt that, to reduce any water-related problems, we'd construct one more reservoir for this project. And then we've added a modest amount of extra camp space plus more warehouse space, just to, I think, serve the business better as we move ahead. We've been bringing quite a few functions in-house that used to go to external contractors — things like maintenance, now done by ourselves. And so we decided to install some additional facilities. That's the context for the increase. We have a fairly clear view of where construction ends. We're truly at the point of final piping — now it's cabling and instrumentation. Everything this project needs is already at the site. So it comes down to finishing these last stages of work. So we're fairly at ease regarding the capital figure we've published. We see no reason to expect difficulties while the project ramps up. Obviously, should problems arise, they can affect matters by requiring extra CapEx, but at this point we definitely don't foresee that.
John MacKenzie
executiveAnd I think a key way we reduced that exposure was — the main reason we brought Osisko in as our EPC contractor on this contract was that they have constructed four of these — essentially near-identical concentrators previously, and three of those are located in South America. So they have done this before. In our situation, they will be ramping it up just as they have with each of those other concentrators they have constructed. And so I think we take a good deal of confidence from that experience they bring. And on our side as well, we have been devoting a fairly large portion of the past year to operational readiness. Our own operating team is now in place. I think we have recruited top-notch people at essentially every level. And so I think all of that gives us a strong degree of confidence that the project will ramp up successfully. We have budgeted for a ramp-up period of 6 months. We obviously hope to do somewhat better than that. But our present assumption is 6 months. And that aligns very closely with how Osisko has performed previously in ramping up concentrators that are very similar to this one.
John MacKenzie
executiveWhat also bolsters our confidence, I believe, is that the mine stands ready — in fact, more than ready. We have now built up a stockpile of 5 million tonnes of sulfide ore positioned ahead of the crushers. So from a mining standpoint, we have actually exposed roughly a year's worth of sulfide ore. As a result, the mine is essentially just waiting at this point for the plant to be prepared to accept the ore.
Orest Wowkodaw
analystOne quick follow-up for Raman. As things ramp up—say in Q1 and Q2 of next year—do you expect every cost tied to that ramp to be expensed, or might we see some capitalization of costs, similar to what happened with QB2? I'm just trying to figure out how to model Q1 and Q2.
Raman Randhawa
executiveYes. We’re examining what technology is accomplishing in that area. So we’re analyzing that a bit more deeply. But really, under the IFRS standard, once production begins, you start expensing those costs. So that lasts until the concentrate is on your books. But once it is on your books and you produce it, you expense it. So for a certain period, we can capitalize the ramp-up commissioning costs, which are included in this $870 million. But past that point, we expect to expense it.
Operator
operatorRalph Profiti with Eight Capital has the next question.
Ralph Profiti
analystThanks, operator. Good morning, everyone. John and Cashel, when you discuss the Pinto Valley Asset Integrity Program, right, and you raised those KPIs, I'm just wondering: is there some kind of strategic management of the grade and the mine plan being considered, or is this mostly about costs and continuous improvement, or does it have any effect on the mine plan itself, including stripping? And along with that, might we be looking at some cost improvements going forward?
Cashel Meagher
executiveThanks, Ralph. The mining isn't the issue, nor is the mine itself—both are doing what they should be doing. Grades are coming out, and reconciliation is happening the way it ought to. Let me begin by saying our efforts so far, and what we accomplished in October, have left us genuinely pleased. We've gotten off to a solid start as we work toward catching up in Q4. So we've begun on the right foot. That gives us a measure of confidence that certain initiatives we've launched in asset integrity and maintenance are beginning to deliver results. One step we took involved changing the structural design. We're moving toward putting in place a maintenance program along with a maintenance manager. That's a different arrangement from what Pinto Valley had previously, when maintenance sat within the purview of either the Mine Manager or the Plant Manager. What we're doing, then, is raising expectations for our maintenance department and making those processes better. And in the last quarter we brought on a VP of Mine and Maintenance who excels in this area, Hayden Halsted, and he in turn has a fixed plant person, a Director of Asset Integrity, Rob Taylor.
Cashel Meagher
executiveThey've played a key role in assisting us to boost uptime and cut downtime on our critical components, which typically revolve around the crusher infrastructure and the conveyance infrastructure feeding our mills. So we've already observed gains there. And to be specific, those are the spots where performance is shifting, and those are the spots where we were generating bottlenecks in our production during Q3 and somewhat in Q2. So I'm glad to report that we're seeing improvement. And it also helps that our schedule, our budget, our plan for year-end involved a somewhat higher grade. It's in fact the highest grade in the sequence as we enter Pinto Valley, and we're seeing that advance as well.
Ralph Profiti
analystAlright, that's good to hear. And regarding Mantos Blancos, it seems like reaching cash flow of 20,000 tonnes per day is roughly a target for the end of Q1 '24 as a reasonable expectation, with perhaps some of it slipping into Q2 of 2024. I'm just wondering whether that's something we ought to be assuming, and do you see any chance that some CapEx carries over into 2024, simply in order to smooth things out as you ramp up to full capacity?
Cashel Meagher
executiveYes, we're moving forward with that plan. Bringing the plant up to the needed condition will call for roughly $20 million in additional spending. As I believe we've explained previously, the key components are already in place and have the capacity. What we're upgrading is some of the piping, cabling, and instrumentation so we can get there. One area we've really homed in on is the back end of the plant — the dewatering and tailings infrastructure. On paper it appeared able to handle the 20,000-tonne design, but we'll need to upgrade that section. That's where some of the longer lead items sit, and those will carry us into the window you referenced — close to the end of Q1, the beginning of Q2 — before we can get this plant running consistently and sustainably at 20,000 tonnes. We have hit above 20,000 tonnes on a sporadic basis, but what we're after is steady output. So the back end of the plant is our focus, along with some upgrades to instrumentation and piping in certain other areas. But from where we stand today, it will take that much time to get these installed.
Cashel Meagher
executiveOnce more, there's a fresh General Manager in place for Chile—sorry, for Mantos Blancos—and several members of the team have been swapped out. These people are genuinely capable, bringing substantial experience in this kind of operation. So our confidence in the path ahead is high. The plans are laid out in considerable detail at this point. We've moved past fixing bottlenecks one by one, and we're now addressing the issues that remain, and that's the amount of time we'll need in order to get the necessary equipment purchased and put in place.
Operator
operator<<operator_script>> That brings the Q&A to a close, as no more questions remain. John, go ahead with your closing remarks.
John MacKenzie
executiveOkay. We’re eager to speak with you again in February when we report Q4 results. In the meantime, stay well, and don’t hesitate to contact Jerrold or Daniel with any additional questions. Thanks for your ongoing support, and have a good day.
Operator
operatorEveryone, that brings us to the end of today’s conference call. Thanks for being with us. You can go ahead and disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.