operatorGood afternoon, everyone, and thank you for joining the Capstone Copper Q4 2023 Results Conference Call. Right now, every line is in listen-only mode. After the presentation, we'll hold a question-and-answer session. Should you need immediate assistance at any point during this call, just press star zero to reach the operator. Today is Thursday, February 22nd, 2024, and this call is being recorded. I'll now hand the conference over to Jerrold Annett — please go ahead.
Jerrold Annett
executiveGood day, everyone, and welcome to the Capstone Copper conference call for Q4 2023. I want to point out that the news release and regulatory filings that announce Capstone Copper's financial and operational results for the fourth quarter of 2023 are posted on our website as well as on SEDAR+. If you are logged into the webcast, we will call out or move forward the slides for today's presentation, and those are also accessible in the investor section of our website. With me today are our CEO, John MacKenzie, our President and COO, Cashel Meagher, our Chief Financial Officer, Raman Randhawa, and our Senior Vice President, Risk, ESG, and General Counsel, Wendy King. After a few brief remarks from us, you will have a chance to ask questions. I'd like to note that what is said on the call today will include forward-looking information as that term is defined under applicable securities laws. By its very nature, such information carries risks and uncertainties, and actual results could differ materially from the views expressed today. To learn more about the risks and uncertainties that relate to our business, please refer to Capstone's most recent filings, which can be found on our website and on SEDAR+. Lastly, let me just mention that every amount we discuss today is in U.S. dollars, unless stated otherwise. I'll now hand the call over to John MacKenzie.
John MacKenzie
executiveThanks, Jerrold. Good afternoon to everyone across North America, and good morning to those of you joining us from Australia. We're happy to share our results for the fourth quarter of 2023 along with what we achieved over the year. Beginning on slide five, we turned out slightly more than 44,000 tons of copper in Q4, with consolidated C1 cash costs of $2.67 per pound. On both production and costs, that made it our best quarter of the year, and from a financial standpoint it was also our strongest quarter of the year. With 2023 finishing on such a strong note, our operations are well positioned for 2024. Across the whole of 2023, we produced 164,000 tons of copper, consistent with the guidance we gave for the second half. Lower production levels early in the year, together with our higher cost cap at production, weighed on our consolidated C1 cash costs. Even so, we anticipate that our consolidated unit costs will come down as the Mantoverde Development Project in Chile ramps up. Completing the construction phase of MVDP and now concentrating on commissioning and ramping up the project was a major accomplishment for our team. Our previously announced total capital budget for the project of $870 million is unchanged, and the commissioning timeline set out in our January guidance release is unchanged as well.
John MacKenzie
executiveGetting to first production has taken years of hard work from our whole team — exploration, studies, permitting, engineering, and actually constructing the mine — and it's incredibly exciting that we're almost there. MVDP is a game changer for Capstone Copper, driving a step change in our consolidated unit costs and opening a path toward record operating cash flow. Building on what we achieved in 2023, I'm also really proud that our Mantoverde and Mantos Blancos mines in Chile both earned the Copper Mark. Operating responsibly is essential to what we owe the environment, our employees, local communities, and governments, and it has to stay front of mind in all that we do. The Copper Mark gives strong assurance of transparency and accountability and underscores our values around responsible, sustainable production. We're proud of what our Chilean operations have accomplished, and we're working hard to repeat that success at Pinto Valley in Cozamin. We also strengthened our senior management bench considerably this year. Three of our mines now have new general managers, and we brought in several key people to our corporate technical team over the course of the year.
John MacKenzie
executiveWe have managed to bring in highly skilled and seasoned people to our team, and I think we are set up to succeed. Finally, I'd also like to point out that during 2023, we broadened our investor base by way of a secondary share placement made by Orion Mine Finance, our biggest shareholder. We kept strengthening our shareholder register earlier this year through an additional sell down from Orion, along with a primary equity raise completed by Capstone. On February 2nd, we announced that our shares had begun trading on the Australian Securities Exchange under the ticker symbol CSC. We expanded our investor base across the Asia-Pacific region considerably last year. The ASX is a top-tier market with a lengthy history as a platform for mining companies. We are dedicated to enhancing liquidity in our shares on the ASX as time goes on. With that, I'll hand things over to Raman for our financial results.
Raman Randhawa
executiveThanks, John. Turning to slide six now. During Q4, copper output came to 44,100 tons, while copper sales totaled 43,300 tons. The LME copper price averaged $3.70 per pound in the quarter, a 2% decline from $3.79 per pound in Q3 2023. Realized copper prices for us were $3.74 per pound, essentially matching the LME average. Consequently, we booked net revenues of $354 million for the quarter. Consolidated C1 cash costs came in at $2.67 per payable pound in Q4, falling inside our second half guidance range and marking the lowest quarterly C1 cost we saw all year. We anticipate costs will follow a similar path in the first half of this year, ranging from $0.265-$0.285 per pound, ahead of a significant step change in our consolidated unit cost during the second half brought about by our Mantoverde Development Project, bringing it down to $2.10-$2.30 per pound. Adjusted EBITDA for Q4 reached $88.3 million, up 41% from Q3, reflecting a stronger operational quarter with production results 10% higher. Adjusted net income to shareholders came to $10.8 million, or $0.02 per share, and excludes $21 million of unrealized derivative and FX losses. Now let's move to slide seven. On the left side, we summarize the liquidity available to us, which stood at roughly $353 million as at year-end 2023, comprising $127 million in cash and short-term investments plus $226 million of undrawn amounts under our $700 million corporate revolving credit facility.
Raman Randhawa
executiveEarlier this month, we completed a $356 million primary equity raise that formed part of a bigger CAD 431 million bought deal; that deal also featured a secondary sale from Orion Mine Finance, our biggest shareholder. This equity raise strengthens our liquidity and gives us more financial flexibility. Pro-form liquidity, once the net proceeds from the primary offering are included, now stands at $606 million. Taking the offering into account on a pro-forma basis, consolidated net debt comes to $674 million, while the attributable net debt balance is $523 million. Our balance sheet is in excellent shape. The chart on the right-hand side shows how our EBITDA responds at different copper prices. The first two bars make clear that we anticipate substantial near-term EBITDA growth once Mantoverde sulfides reach full run rate production. In the near term — this year, 2024 — our EBITDA will double compared with 2023 levels as MVDP ramps up. Once MVDP is at full capacity, we expect to produce roughly $1 billion of annual EBITDA, assuming a $4 copper price. The EBITDA that Mantoverde generates will let us concentrate on producing free cash flow so we can delever our balance sheet and sit below one-times net leverage at spot copper prices, which gives us extra liquidity to move our future growth pipeline forward — Mantoverde Optimized, expansion, and Santo Domingo — depending on market conditions.
Raman Randhawa
executiveAt this point, I'll pass things along to Cashel, who will walk us through the operations review.
Cashel Meagher
executiveThanks, Raman. Moving to slide eight now. During Q4, Pinto Valley turned out 15,933 tons of copper, with a C1 cash cost of $2.36 per payable pound. That was the strongest quarter of the year for Pinto Valley, as we began seeing the benefits of our new asset integrity program, and from where I sit, the mine is well positioned for this year. For Pinto Valley in 2024, we've guided to 58,000 to 64,000 tons of copper production at a C1 cash cost of $2.50-$2.70 per payable pound. We expect copper output to be weighted toward the second half of the year, driven by grades. Our guidance implies throughput of roughly 52,000 tons of ore per day, versus mill capacity of 60,000 tons per day. As we keep executing on our asset integrity program, we believe we'll be able to extend the meantime between failures and lift our overall availability so we can deliver more consistently higher throughput. Also worth noting, last year Pinto Valley completed a third-party gap assessment for the Copper Mark. In 2024, our capital expenditure guidance also reflects our efforts to improve tailings stewardship as we work toward implementing the Global Industry Standards for Tailings management by year-end 2028.
Cashel Meagher
executiveTurning to slide 9. Cozamin Mine put up a strong fourth quarter, with output of 6,564 tons of copper and a C1 cash cost of $1.76 per payable pound. Following the switch to the new cut-and-fill mining method earlier last year, the operation posted yet another quarter at nameplate mining rates. For 2024, our guidance for Cozamin production is 22,000 to 24,000 tons of copper. Costs for 2024 are above those in our most recently published technical report, reflecting a stronger Mexican peso and greater reliance on the new cut-and-fill mining method. We see opportunities to bring unit costs down going forward as the workforce becomes more proficient with cut-and-fill. Our Mantos Blancos asset is featured on slide 10. Combined sulfide and cathode output came to 11,587 tons of copper at a blended C1 cash cost of $2.71 per payable pound. This year, sulfide operations have not run consistently at nameplate levels. Although the major components, including the crushing, grinding, and floating circuits, are still capable of throughput rates above 20,000 tons per day, the linkages between these systems, including pumps and pipes, have shown bottlenecks. In Q4, we kept executing our plan to address plant stability, which includes better maintenance and optimization of the concentrator and tailings system.
Cashel Meagher
executiveWe’ve also taken on board what we’ve learned so far from running the plant since the expansion finished. During the quarter we worked through a number of areas, and we’ve resolved several bottlenecks in the mine’s crushing and grinding circuit. So far in 2024, operating rates have been closer to our plan. For sulfide production, we’ve guided to 43,000 to 49,000 tons of copper, weighted more heavily toward the second half because of greater throughput. In the first half of the year, we’re focused on receiving and installing the engineering and infrastructure upgrades needed in the plant’s tailings dewatering area. We expect to receive and install the required equipment in Q2, and after that we expect Mantos Blancos to run at nameplate throughput rates. Our sustaining capital guidance for Mantos Blancos in 2024 includes roughly $35 million tied to reaching sustainable run rate production. We’re confident that we have both the team and the asset in place to support full run rates. Our efforts are concentrated on getting there, and once that is achieved, we will restart our studies related to Mantos Blancos Phase II, since we believe the ore body can support a further expansion.
Cashel Meagher
executiveTurning to Mantoverde, slide 11. Oxide output for Q4 2023 came in at 10,019 tons of copper cathode, with a C1 cash cost of $3.68 per payable pound. In the first quarter of 2024, Mantoverde welcomed Óscar Flores as its new general manager; he brings considerable experience ramping up and running sulfide concentrators from earlier positions at Kinross, Antofagasta, Anglo American, and Codelco in Chile, along with time at New Gold in Mexico, Australia, and Canada. Pablo Asiain, our prior GM, remains with us until the close of Q1 before he retires. We appreciate his stewardship at Mantoverde and wish him the very best. Importantly, Q4 saw substantial progress at the MVDP. Construction is essentially finished. Our project capital estimate of $870 million stands unchanged, and at this point we do not expect any additional increases to the project's capital budget. Key commissioning milestones appear on the right side of the screen: first ore to the mill is expected in Q1, first saleable concentrate in Q2, and the mine reaching nameplate operating rates in the third quarter. Once fully ramped up, Mantoverde will produce roughly 120,000 tons of combined cathode and copper concentrate, plus more than 30,000 oz of gold annually.
Cashel Meagher
executiveIn this ramp-up year, our plan is to generate 61,000 to 75,000 tons of combined copper at Mantoverde. We intend to publish a study around mid-2024 for Mantoverde Optimized, a brownfield expansion designed to boost ore throughput by roughly 40%. Given a resource exceeding 1 billion tons of material that isn't in reserves at present, we would keep assessing whether to add a second concentrator line at Mantoverde. Slides 12 through 16 illustrate how construction and commissioning are progressing across several key areas of the MVDP. On Slide 12, the primary crusher appears on the left, with the covered coarse ore stockpile on the right. First ore went into the primary crusher in the fourth quarter, and the covered coarse ore stockpile is now roughly one-third full as we head into the ramp-up. As you'll remember, mining took place across all of 2023, and we've stockpiled approximately 6 million tons of sulfide ore that awaits feeding to the primary crusher in the mills. Another six months of sulfide ore is exposed in the pit as well, which further reduces ramp-up risk. Slide 13 offers a close-up view of the SAG and ball mills. That represents the next big step in our systematic commissioning process.
Cashel Meagher
executiveAusenco, the engineering contractor we use, has been brought on to handle commissioning and ramp-up work for the mill operations. Beyond that, we've brought in a full crew of sulfide operators, along with our new plant manager, and they're all working side by side with the Ausenco ramp-up team. The mills were energized last week and have been spinning with no ore in them. We're collaborating with FLSmidth, the manufacturer of our equipment, while they carry out their final instrumentation and calibration runs before the first ore goes into the mills — something we anticipate happening later this quarter. Slide 14 gives you a bird's-eye view of the processing flow sheet. We'll keep commissioning the plant in a systematic way, moving through the flotation, filtration, and tailings areas across the coming few months. Slide 15 shows the tailing storage facility. Mantoverde is located roughly 900 m above sea level and ranks among the driest locations on the planet. As we see it, it's one of the finest sites on Earth on which to have built a copper concentrator and to be ramping one up. Finally, slide 16 shows our desalination plant on the coast, approximately 30 km from the mine. It has now been expanded so it can support the MVDP. I'm eager to keep commissioning and ramping up the Mantoverde Development Project over the next few months.
Cashel Meagher
executiveWe’ll now hand things to Wendy King for the sustainability review.
Wendy King
executiveThanks, Cashel. We're moving to slide 17 now, where we'll go over the highlights of our sustainability work. In November, Capstone Copper released its first combined sustainability report, titled Growing Responsibly. That report gives expanded detail on our sustainability policies worldwide, along with deeper information about how we engage communities and manage biodiversity. We also disclosed emissions intensity figures both per unit of ore processed and per unit of copper produced, so our emissions picture is clear and transparent. During 2024, we'll keep building on this improved reporting by sharing the findings of our climate-related risk and opportunity assessment and scenario analysis, work that began in 2023. Those efforts will further shape our business strategy and our decarbonization plan. Together with other Canadian mining companies, we will publish our first modern slavery report covering responsible sourcing practices in our supply chain. We're happy to share that Mantoverde was named 2023 Company of the Year by CORPROA at its annual general meeting. Cozamin received three separate awards: the Socially Responsible Company Distinction Award from the Mexican Center for Philanthropy, the Ethics and Values Award for its corporate social responsibility practices from the Confederation of Industrial Chambers of Mexico, and the Company Committed to Human Rights Awards from the Zacatecas State Human Rights Commission.
Wendy King
executiveThese awards really reflect what our sites have accomplished in becoming leaders — both corporate and industry-wide — in the communities where we work. Over at Mantoverde, we're partnering with Econssa Chile and the Atacama Regional Government to supply desalinated water to Flamenco and Las Piscinas, covering all the water needs those towns have. That stands as a meaningful illustration of the way mining companies are able to give back and make life better for people in the communities where we operate. At Pinto Valley, the water supply wells have been switched over from diesel power to electric, and within our mine fleet we're working to swap diesel equipment for electric or lower emission equipment whenever replacements come due. We've brought in a new dust suppression system, and it saved roughly 17 million gallons of water last year. Steps such as these will shrink our carbon footprint and strengthen our sustainability. In 2023, Cozamin published a biodiversity handbook built on a two-year flora and fauna monitoring program, and it gives us the foundation for estimating net losses and gains at the site. That handbook went out to universities and schools through our environmental education program, and it helps show the delicate balance between human activity and wildlife preservation — and how mining can coexist with nature.
Wendy King
executiveDuring 2024, Capstone is going to create a worldwide biodiversity standard that lays out our biodiversity-related commitments. Throughout the fourth quarter, every one of our sites kept backing the priorities of nearby communities — notable examples being the removal of an abandoned water pipe measuring 8,000 ft from National Forest land in Arizona, and Mantos Blancos ran an idea fair in Antofagasta together with children and youth aimed at advancing the themes of innovation, development, and entrepreneurship, which are important skills to encourage in our young people. On that note, I'd like to hand things back to John.
John MacKenzie
executiveThanks, Wendy. If you go to slide 18, we've laid out the growth plans that lead our sector plus a few extra sources of upside in the portfolio. You can see that we anticipate MVDP, once running at full production rates, will take us to a consolidated annual figure of roughly 260,000 tons of copper, with costs coming in near $2 per pound. As Cashel said, we intend to publish a feasibility study for our Mantoverde Optimized project later this year — a brownfield expansion carrying low risk that we believe will free up a further 20,000 tons of copper each year, at a very appealing capital efficiency of $7,500 per ton of annual production. From that point, we have a route to more than 380,000 tons of copper output through the fully permitted Santo Domingo project, situated 35 km from Mantoverde, which we expect to establish a world-class mining district in Chile. Past that lies additional upside throughout our portfolio: underused SX-EW capacity in Chile, one more low-risk brownfield expansion chance at Mantos Blancos, the potential to unlock cobalts in our MV-SD district, and finally, we think we can build a world-class mining district at our Pinto Valley mine in Arizona as well. Slide 19 sets out the timelines for several of the studies mentioned above and other milestones as we carry out our growth plans.
John MacKenzie
executiveTo wrap up, I want to emphasize that Capstone stands right at the edge of a major transformation, as we ramp up Mantoverde and at the same time complete the studies that will shape our next phase of growth. With that said, we're ready to take your questions now.
Operator
operatorThanks, everyone. We're moving into the Q&A portion now. Whenever you'd like to ask something, just hit star one on your touch-tone phone. Should you need to withdraw your request, press star two instead. Orest Wowkodaw from Scotiabank is up first. Your line is open.
Orest Wowkodaw
analystGood afternoon, and congratulations on getting the Mantoverde sulfide construction finished. This question is for Cashel—I suppose you're now in your second month of commissioning. If you had to choose a single part of the startup, where would you say the greatest risk lies to hitting the ramp-up timeline you've published?
Cashel Meagher
executiveRight. So clearly, what we're doing is commissioning in sequence. It's not as though a single area carries the risk. The point is that risk is present in every ramp-up I've ever been part of or seen in this industry — you may hit issues that were locked in years earlier, back in fabrication. That's the reason you get vendor affirmation across all these processes: they confirm their warranties are solid and valid because their products work the way they were designed to. With that process, whatever risk it carries usually means an extra week here or an extra week there on the individual items that get flagged. Beyond that, there isn't really a big risk. And one reason I say so is that this is a fairly straightforward process line. It has been demonstrated repeatedly at some six mines Ausenco has commissioned before, including Carrapateena most recently, Mina Justa, Constancia, Cadia East, Lumwana, and I may be forgetting a couple. But this is a single line. They've done it before. Their highly experienced ramp-up team leads it, and that team is separate from their construction team, which most recently handled this at Carrapateena and Mina Justa, as I mentioned.
Cashel Meagher
executiveWe believe we're in really capable hands. Another advantage is that our operators are also on site, helping to facilitate, monitor, and learn the process. A total of 127 people have been hired, and that includes the plant manager, his supervisors, the operators, and the maintenance personnel. We think we have a solid group of people in place there to review any of the usual commissioning risks and processes that exist, so that we achieve a very efficient and robust commissioning process throughout this ramp-up.
Orest Wowkodaw
analystSo right now, there's nothing you're seeing that has you especially worried?
Cashel Meagher
executiveNo, no, absolutely not. As I mentioned when I discussed this earlier, regarding the project and the update, we are at this moment simply rotating the two mills under FLSmidth's oversight. Consequently, we expect to be able to begin charging them with ball charges quite soon. That is a very encouraging indicator for us, since that piece of equipment is truly the most essential one across the entire area. As for everything else, we have completed all of the hydro testing, circulating water throughout the full process and plant site. So after that, the question becomes whether it will cope with slurry. Those items are pumps and pipes, and given the design Ausenco has provided to us, we are fairly confident.
Orest Wowkodaw
analystAlright, and let me just squeeze in one quick follow-up if I may. For the optimization study—or the optimization work—and that expansion at Mantoverde up to 45,000 tons a day, do you still picture the CapEx for that coming in at roughly $150 million?
Cashel Meagher
executiveI'd put it roughly in that same range, yes.
Orest Wowkodaw
analystI appreciate it.
Cashel Meagher
executiveSure, that's not an issue.
Operator
operatorRalph Profiti of Eight Capital has the next question. Your line is open.
Ralph Profiti
analystThank you, operator. Good afternoon. My question concerns the difficulties you believe you might encounter in hitting that cash cost guidance for the second half of 2024 — the $1.45 to $1.75 range. I'm wondering whether, in these early days, you are observing any deviations, such as concentrate logistics, energy costs, or other cost pressures, compared with the time those guidance expectations were established?
John MacKenzie
executiveYes. Thanks for that question, Ralph. As things stand right now, we aren't seeing anything that would lead us to think differently from what we've already laid out in the guidance. I'd like to stress that the main thing driving the cost reduction we expect in the second half is the ramp-up of Mantoverde. And the cost comes down because it simply lifts the share of high-grade sulfide ore we're processing throughout our business. As we bring Mantoverde on, we're nearly doubling the grade across our average portfolio, going from 0.35% last year to around 0.6% across the portfolio this year. Along with that comes improved recovery. The concentrators give us better recoveries than the leach plants do. So there are a few other factors too. Obviously, there's scale, and there's throughput. But those are the fundamental drivers behind the cost reduction we forecast. And I'd also note that it's really a matter of grade and recovery. We already have 6 million tons of sulfide ore stockpiled at Mantoverde. I'd say reconciliation between our block model and what we've actually mined has been excellent.
John MacKenzie
executiveAt this point, then, we see no cause for moving away from the guidance we've provided.
Ralph Profiti
analystThanks, John. Perhaps there's something for Raman here. In 2024, there's $75 million of capitalized stripping at Mantoverde. And presumably a good deal of that ties to the sulfide ramp-up. But I'm just wondering, how much does that drop off, if at all? Does the falloff beginning in 2025 carry any significance? And specifically for Mantoverde, what would be a good run rate for cap stripping?
Raman Randhawa
executiveYes, Ralph, that mostly comes down to how the accounting works. It reflects the straightforward ore-to-waste ratios. The accounting method we use differs from the technical reports, since those assume no capitalization of deferred stripping. So that figure will fluctuate year to year, but going forward it should land in roughly the 50 to 70 range. And the capitalization actually happens pit by pit. So it isn't simply what we move across the whole mine during the year — it's per pit. And we're operating in several pits. So while we're currently mining sulfides in one particular pit, we're also stripping two additional pits at the same time, and we'll be mining sulfides from those three years from now. That's the reason you tend to see that run rate carry on in your model.
Ralph Profiti
analystThat's really useful. Yeah, genuinely useful. Thanks to all of you.
Operator
operatorDalton Baretto from Canaccord has the next question. Your line is open now.
Dalton Baretto
analystThanks a lot. Good afternoon, everyone. I’d like to ask about the Santo Domingo study that’s coming up. Presumably, you’re nearing completion at this point. And I’m wondering: beyond presenting the CapEx and the OpEx to the market, what material differences should we expect, I suppose, compared with the feasibility study that already exists?
John MacKenzie
executiveYes, and thanks for raising that, Dalton. I'll likely hand most of it over to Cashel to answer. That said, I would note that things appear to be in very solid shape. We're genuinely enthusiastic about where it's going. Naturally, the initial feasibility study was completed back in 2018, so we've now built in six years' worth of capital inflation since then. Two additional factors have also entered the picture, though. First, we're factoring in synergies with Mantoverde, including a range of infrastructure-related ones. Second, we took another look at the design as such, examining ways to optimize it. Thanks to a more efficient design than what existed before, we've managed to reduce the footprint by roughly 40%. And with our technical team having gained more experience processing ores in that region, we've tweaked the process flow sheet, which I'd say gives us greater confidence in the flow sheet as such, and while it may not reduce CapEx, it should deliver meaningful operating cost benefits going forward.
John MacKenzie
executiveSo perhaps with that, I'll just hand things over to Cashel to see if there's anything to add.
Cashel Meagher
executiveYes. The design has undergone a full overhaul while keeping the same essential footprint the permit calls for. Naturally, this includes its DL 600, and it is a permitted facility. We see a chance here to boost throughput. There's a change in the flow sheet, and John brought up the lower steel and concrete needs tied to the footprint. So we're achieving greater capital efficiency. And that simply draws on the work Ausenco has completed for us at Mantoverde along with certain other plants of theirs here at Santo Domingo. That said, we aim to add more tons and a bit more life-of-mine potential. We also pointed out that, with the resource itself re-evaluated, the copper there is in fact somewhat higher grade than we previously believed, thanks to density weighting. Iron ore, as you're aware, has greater density, and we hadn't been weighting it correctly. So that's a small adjustment that we think will deliver more copper sooner and for longer — across an extended stretch, I should say, where the copper grade previously fell off around year six or seven. We may gain a couple of extra years from it. So that's yet another kind of improvement area.
Cashel Meagher
executiveAnd then I think this will do more to flesh out the opportunity section in the feasibility study, where we'll get a clearer picture and assessment of what some of that strip material could potentially do. John mentioned the synergies — some of the oxide available to us in that strip material would never justify an SX-EW plant on its own. But Mantoverde has capacity, as we know. And we believe there's a genuine opportunity there going forward to process that material. And the other one, of course, is our emerging cobalt business. We're running some pilot testing at Mantoverde right now. And we believe Santo Domingo could supply a substantial amount of feed to that processing plant that we may build at Mantoverde down the road. So it will lay out, among other things, all of those items. And I think one of the key things for the analyst community is that it will include a refreshed capital cost estimate that is present and achievable, along with the returns we expect from that project. So it's a good moment to bring all of that up to date. So we're very much looking forward to getting it completed.
Dalton Baretto
analystThanks, Cashel. As a follow-up: I realize the cobalt study is arriving somewhat later. Still, regarding the JV process you’re running, will this study suffice to advance it, or will you hold off until the cobalt study is finished?
John MacKenzie
executiveApologies, Dalton — regarding the joint venture process you mentioned?
Dalton Baretto
analystCorrect — it’s only the Santo Domingo partnership.
John MacKenzie
executiveOh, so a partner is being brought in for Santo Domingo. Yeah. Look, in the end, I think the partnering process will more or less need a completed feasibility study from us. Within that study, as Cashel mentioned, there's the base case, which I think he described well. And then on top of that come the opportunity sections. So I think work on those areas began a bit later than the feasibility work that's been done across the rest of Santo Domingo. So bringing those up to the same level of study and confidence takes a somewhat longer timeline. But we're already fairly far along the track. So I think those will definitely be opportunities we'd be discussing with potential partners for Santo Domingo.
Dalton Baretto
analystUnderstood. Thanks, John. Perhaps I could fit in just one more. John, would you mind explaining a bit about why the company recently decided to raise equity?
John MacKenzie
executiveSure, absolutely. So I'd say first off, what we observed in the markets was, in a sense, a fairly appealing kind of window to raise certain amounts of funding at what looked like a sensible valuation. And our approach has been — we're comparatively conservative in how we handle our balance sheet. And really, what we've been doing is restraining a great deal of expenditure that would otherwise generate some genuinely interesting value down the road. The main reason for that is that although we are fully funded for the Mantoverde project, I really don't want to be committing money before we've actually witnessed the ramp-up and seen the project produce the cash flow we anticipate. That said, it does mean we've been reining things in somewhat on a few genuinely exciting opportunities. To give you a quick list of some of them: in the northern part of Mantoverde, we hold highly, highly prospective exploration targets that we think could substantially expand the resource base at Mantoverde. We clearly also have Mantoverde Optimized. And Cashel mentioned earlier a CapEx figure of roughly $150 million.
John MacKenzie
executiveThat project has a very short payback period. So the sooner we can get it done, the better. And then as we move toward Santo Domingo after that, in my view, it's best practice to actually push forward the detailed engineering work on the project before you give full notice to proceed on the construction itself. That simply gives you a much tighter level of confidence regarding where your CapEx will land for the project. So this raise helps make it possible for us to execute on each of those items, and if we hadn't done the raise, we would probably have been keeping the brakes on for certainly a bit longer. On the other hand, I'd say part of it was also the secondary sale by Orion. I think through both the primary and the secondary, we improved the liquidity in our stock. I think that's clearly one of our objectives. And then finally, I think, when we looked at our shareholder register, there were quite a number of blue-chip shareholders, blue-chip funds that we saw on some of our competitors' registers and who were not on ours.
John MacKenzie
executiveSo one goal involved making it easier for a number of those funds to get onto our register. And honestly, we were quite happy with how those funds took it up. And when we look at our share register today, it seems to be in a solid position.
Dalton Baretto
analystAppreciate it, John—that was helpful. I have nothing further to add.
Operator
operatorWe’ll now take a question from Stefan Ioannou at Cormark Securities. Your line is open.
Stefan Ioannou
analystOkay, that's great—thanks, guys. This is maybe more just curiosity on my part regarding MVDP. I'm just wondering: you said you now have a substantial amount of material stockpiled, and you've also opened up in the open pit. Is the grade fairly variable, or is it mostly all low-grade material? I'm just curious—as you ramp up, do you have any flexibility on grade as you go through that process to play with?
Cashel Meagher
executiveYes, Stefan. Under the stockpiling approach, they included both high-grade and low-grade material, so those are kept apart. With the usual ramp-up, at the very start, when only a handful of tons are moving, clearly very little grade is passing through, since I'm tuning the flotation cells and similar equipment. Once the process was running, though, we intend to feed the high-grade material, and we have that on hand.
Stefan Ioannou
analystAll right. So both of those are available to you. Excellent. Okay. Many thanks, everyone.
Cashel Meagher
executiveCorrect.
Operator
operatorLadies and gentlemen, just a quick reminder — if you'd like to ask a question, press star and then the number one. At this point, we have no more questions. Mr. John MacKenzie, the floor is yours.
John MacKenzie
executiveThank you. We’re eager to reconnect with all of you in early May, when we’ll share our Q1 results. In the meantime, please take care, and don’t hesitate to contact Jerrold or Daniel with any additional questions. We appreciate your ongoing support, and have a great day.
Operator
operatorThat brings us to the end of today's conference call, everyone. We appreciate your participation. You're welcome to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.