Capstone Copper Corp. (CS) Earnings Call Transcript & Summary
October 31, 2024
Earnings Call Speaker Segments
Operator
operatorGood afternoon, everyone, and thank you for joining Capstone Copper's conference call on our Q3 2024 results. Right now, every line is muted so that everyone can listen only. <<operator_script>> Today is Thursday, October 31, 2024, and this call is being recorded. I'll now hand things over to Mr. Daniel Sampieri. Thank you, and please go ahead.
Daniel Sampieri
executiveThank you, operator. I want to extend a welcome to everybody joining Capstone Copper's Q3 2024 conference call. Just a note that the news release along with regulatory filings that announce the 2024 third quarter financial and operational results for Capstone Copper can be found on our website as well as on SEDAR plus. Should you be logged into the webcast, we'll be advancing the slides for today's presentation, and those are also accessible in the Investor Section of our website. Joining me today are our CEO, John MacKenzie; our President and COO, Cashel Meagher; our SVP and Chief Financial Officer, Raman Randhawa; our SVP, Risk, ESG, and General Counsel, Wendy King; and our SVP, Technical Services, Peter Amelunxen is also available at the end of the call. After our brief remarks, there will be a chance to ask questions. Please be aware that comments made on the call today will contain forward-looking information within the meaning of applicable securities laws. By its nature, this information is subject to risks and uncertainties, and actual results may differ materially from the views expressed today. For more information on the risks and uncertainties pertaining to our business, please see Capstone's most recent filings, which are available on our website and on SEDAR plus. And finally, I'll just note that all amounts we will discuss today are in U.S.
Daniel Sampieri
executiveAll figures are in dollars, except where noted otherwise. At this point, I'll hand things over to John MacKenzie.
John MacKenzie
executiveThanks, Daniel. Good afternoon to everyone in North America and Europe, and good morning to those of you dialing in from Australia. We're pleased to share our third quarter 2024 results and achievements. Beginning with Slide 5. In Q3, our operations delivered consolidated copper production of 47,500 tonnes at consolidated C1 cash costs of $2.83 per pound. Very importantly, during the quarter we had several major achievements at our mines in Chile. At our flagship Mantoverde Development Project, we achieved commercial production levels in September. This is a tremendous accomplishment within 3 months of producing first concentrate from the plant. We also completed our first two concentrate shipments with a copper concentrate meeting all required specifications. At Mantos Blancos, we undertook a two-week shutdown to install the new equipment that will allow us to unlock the design capacity of the plant. Following these milestones and the Q3 results, we've noted that we expected to finish at the low end of our 2024 production guidance. We revised our C1 cash cost guidance to $2.60 to $2.80 per pound, mainly as a consequence of the ramp ups at Mantoverde video and Mantos Blancos commencing later in the year than we had expected. On the corporate side, our net debt was largely unchanged at $751 million as at September 30.
John MacKenzie
executiveOur balance sheet is in great shape as we ramp up Mantoverde ahead of the next phase of growth. We also shared our leadership succession plan during the quarter, which takes effect at our AGM in May next year. That announcement came after a thorough and orderly succession process aimed at ensuring continuity of leadership and the company's continued success. Serving as Chief Executive Officer of Capstone Copper since March 2022 has been a privilege, and I'm thrilled to be nominated for the role of Board Chair at our next AGM. I was also very pleased to announce that Cashel will be appointed as our next CEO. I have every confidence that Cashel will lead the execution of our next stage of growth at Capstone, including our Mantoverde Optimized and Santo Domingo projects. Jim Whittaker will succeed Cashel as COO, and this will also let us flatten our organizational structure, with all my general managers reporting directly to the COO. We also announced today that Jerrold Annett has retired after 5 years with Capstone to spend more time with his family. Jerrold has been an important contributor to Capstone's success over the past 5 years, and we thank him for all of his contributions and wish him all the best in retirement.
John MacKenzie
executiveMoving on to Slide 6. Back in October, we put out a feasibility study for the Mantoverde Optimized Project. MV Optimized is a brownfield debottlenecking effort that's capital efficient, and it will grow the sulphide concentrator that already exists at Mantoverde from 32,000 to 45,000 tonnes per day, making use of spare capacity in the infrastructure already in place. This project adds another 20,000 tonnes of copper each year for an initial capital figure of slightly under $150 million, which works out to a super low capital intensity of 7,500 dollars per tonne of copper equivalent production. That puts us in position to generate over 120,000 tonnes of copper annually at Mantoverde over the next 10 years, at cash costs of $1.80 per pound. Importantly, together with the updated Santo Domingo feasibility study we released earlier in July, we've now mapped out the next transformational growth phase for Capstone and for our world-class Mantoverde-Santo Domingo district in Chile's Atacama region. We expect to be producing copper through these two processing centers in this well-endowed district for many decades ahead. Only 35 kilometers lie between Mantoverde and Santo Domingo, and we've identified multiple options for delivering significant additional value in the years to come. With that, I'll hand things over to Raman for our financial results.
Raman Randhawa
executiveThanks, John. Moving to Slide 7 now. During Q3, copper output came in at 47,500 tonnes, which was up 16% from the prior quarter, thanks to the first production from the MVDP ramp up. Because of that ramp up, as we had expected, we began accumulating some concentrate inventory as well as some accounts receivable, and that left copper sales trailing payable production by 1,500 tonnes for the quarter. The gap between payable production and sales works out to roughly $5 million to $6 million in EBITDA. Average LME copper prices for the quarter were 4.18 per pound, an 8% decline from 4.42 per pound in Q2. Our realized copper price came in at 4.24 per pound, a touch above the LME average, thanks to our QP hedging program. We achieved solid gross margins of $1.41 per pound, or 33%. C1 cash cost was $2.83 per pound, and that figure included made in unit cost of $2.52 per pound from Mantoverde Development Project. At the MVD sulfide operation, posted cash cost in September was $1.83 per pound. Combined with higher production volumes from MVDP, that should bring a meaningful drop in our consolidated unit cost during Q4 and afterward. As John noted, we have raised our consolidated C1 cash cost guidance for 2024 to $2.60 to $2.80 per payable pound of copper produced.
Raman Randhawa
executiveThe higher cost is mostly due to the effect of production volume from the MVDP and Mantos Blancos ramp ups beginning later in the year than we had initially anticipated, along with a related knock-on impact on our unit cost. At Mantos Blancos, we have additionally seen year-to-date spending above what we expected, caused by more maintenance as well as additional materials and labor needed to finish the debottlenecking work that will unlock the plant's nameplate capacity. For the remainder of the portfolio, our underlying costs have come in fairly close to what we had anticipated. Moving to EBITDA, adjusted EBITDA for Q3 came to $120.8 million, nearly double the prior year and only 2% lower quarter-over-quarter, even with copper prices falling 8%. Looking ahead, our financial results will be affected by reaching commercial production at MVDP <<inaudible>>. Reaching commercial production sets off a few items for Q4 financials, including additional finance charges being expensed rather than capitalized, and the start of depreciation and depletion on the MVDP capitalized cost. We anticipate finance expenses rising by $25 million each quarter, which covers interest on shareholder loans. That includes both cash finance expenses such as interest on our debt facilities and other non-cash finance charges.
Raman Randhawa
executiveIn a similar vein, we anticipate that annualized depreciation will rise by roughly $80 million, primarily figured on a units-of-production method along with a portion of straight-line amortization. Turning to Slide 8. On the left side, we lay out our available liquidity, which stood at $516 million as of September 30, 2024 — comprising $139 million in cash and short-term investments plus $377 million of undrawn capacity under our $700 million corporate revolving credit facility. Notably, during the quarter we began making repayments on the project finance and cost overrun facilities at Mantoverde as operations ramped up. Net debt of $751 million is essentially flat versus the prior quarter, and with MVDP ramping to full production rates we are now moving into the next stage of deleveraging. The chart on the right shows how sensitive our EBITDA is at different copper prices. We sit right at the edge of the light blue bar, which reflects EBITDA of nearly $1 billion to $1.3 billion at copper prices ranging from 4 to 4.50 per pound with MVDP running at full rates. The EBITDA that Mantoverde generates will let us concentrate on producing free cash flow to pay down our balance sheet, with a path to under 1x net leverage at spot copper prices.
Raman Randhawa
executiveThat gives us a solid foundation for pushing ahead with our upcoming growth pipeline, including Mantoverde Optimized and Santo Domingo. At this point, I'll pass things along to Cashel for the operations review.
Cashel Meagher
executiveThanks, Raman. We're now on Slide 9. During Q3, Pinto Valley turned out 13,980 tonnes of copper, with C1 cash costs of $2.92 per payable pound. In the quarter, throughput came in at an average of 45,000 tonnes per day, which fell short of what we had expected, and the reason was unplanned maintenance. Over the past few quarters, following the launch of an asset integrity program, we had been seeing encouraging progress and better throughput. What the third quarter demonstrated is that this initiative is necessary if we are to make the plant more reliable, and implementation of it is ongoing. Even with those unplanned interruptions, Pinto Valley remains on track relative to the guidance we gave at the start of the year. Now to Slide 10. Cozamin Mine turned in another strong quarter, with production of 6,025 tonnes of copper and C1 cash costs of $1.82 per payable pound. Cozamin has stayed remarkably consistent even as we rolled out a larger volume of cut and fill mining methods this year, along with running the paste backfill plant. Our Mantos Blancos asset is the focus of Slide 11. Combined sulfide and cathode production came to 9,974 tonnes of copper, at a C1 cash cost of $3.41 per payable pound. Although output and costs were comparable to what we saw in the prior couple of quarters, that doesn't capture the full picture of what was a highly significant quarter at Mantos Blancos.
Cashel Meagher
executiveBack in July, we wrapped up a shutdown lasting 2 weeks, during which we connected critical equipment pieces that we had determined were needed so that throughput at the tailings handling area at the back end of the plant would be more consistent. Over on the right-hand side of the slide, you can see the new surge tank along with the fourth positive displacement pump. During August, the plant ramped back up, and beginning in the middle of that month, we averaged more than 18,000 tonnes per day, a meaningful improvement compared with the past few quarters. With these modifications now finished, plant utilization is increasing as designed. We anticipate carrying on with higher output in Q4, which will boost copper production and bring our unit costs down significantly. Also worth noting in Q3, recoveries rose to a more normal 82% from a low of 73% in Q2. That followed a short-term localized geotechnical issue in Q2 that affected mine plan sequencing of grades and recoveries. Grades are likewise expected to improve in the fourth quarter, returning to the 0.8 to 0.9 range from sub 0.8 across the last two quarters. On the whole for the year, production and costs at Mantos Blancos are trending unfavorably compared with the guidance ranges we gave in January.
Cashel Meagher
executiveThat said, at Mantos Blancos our confidence is now far greater than at any time in the past 2 years, and we will keep raising daily output levels through the year's end. Turning to Mantoverde on Slide 12, which was a quarter of transformation. Combined sulfide and cathode output came to 17,481 tonnes of copper, a substantial gain powered by a meaningful 8,139 tonnes from the Mantoverde Development Project. Having generated first concentrate close to the finish of Q2 in June, we increased throughput swiftly and efficiently during July and reached facility practical completion together with Ausenco, our construction partner. That came after we hit 7 days of running close to the 32,000 tonnes per day nameplate capacity. This led to a 2-week shutdown at the start of August. Over that period, we assumed operation of the plant, and every OEM was onsite to give final sign-off on warranties covering all the equipment. Following the shutdown, beginning mid-August, we once more ramped up efficiently and reached commercial production in September. Our quarterly average throughput naturally takes in the downtime and ramp-up periods, yet during September we averaged 26,200 tonnes per day.
Cashel Meagher
executiveThe grades matched up nicely with both the mine plan and the block model, with 0.71% copper during the quarter. The recoveries we've observed thus far have also been exciting for us. Once we normalized for work in process inventory builds, we arrived at implied metallurgical recoveries of roughly 78.2% for the quarter and higher than 80% in August and September. On top of that, we completed our first two concentrate shipments, and they satisfied all the required saleable specifications. That marked a significant milestone. The project and operating teams have accomplished a great deal to date, and we are very proud of it. Mantoverde is positioned to produce with greater consistency and reliability throughout the fourth quarter. Moving to Slide 13. Roughly a month ago, we published the results of a feasibility study covering our Mantoverde Optimized Project. At capstone, this is a capital efficient, near-term brownfield growth opportunity that takes advantage of available excess capacity in the crushing and grinding circuits at our Mantoverde concentrator plant, giving us the option to raise throughput from 32,000 to 45,000 tonnes per day of plant feed at a capital efficient cost of $146 million. On Slide 14, the plant presented for MV Optimized represents the next major growth step in the evolution of a world-class Mantoverde-Santo Domingo district. Over its first 10 years, MV Optimized will lift production to an average of more than 120,000 tonnes of copper and 40,000 ounces of gold per year.
Cashel Meagher
executiveAt the bottom right of the page, the study shows an NPV at an 8% discount ranging from $2.9 billion at $4.10 per pound copper to almost $4.5 billion on a 100% basis at a bit above $5 per pound copper. Moving to Slide 15, we've called out several of the main differences between the new MV Optimized study and the prior technical report release for the Mantoverde Development Project. To begin with, mine life now extends to 25 years, and it's worth noting that this was achieved with no extra drilling, since Mantoverde has not had a comprehensive exploration program since before 2019. This longer mine life and higher throughput are made possible by a 67% increase in the total sulfide reserve, which now stands at 394 million tonnes classified as reserve. The resulting life of mine produces a modest decline in head grade along with greater stripping requirements. There is still opportunity — sorry, opportunity still exists through exploration drilling in what we at Capstone regard as outstanding exploration prospectivity along the Atacama Fault for higher grades and potential mineral that could be accessed with less stripping. And as mentioned earlier, plant throughput is set to rise from 32,000 to 45,000 tonnes of ore per day.
Cashel Meagher
executiveAt the bottom of this slide, we show the bigger production profile — covering both the initial 10 years and the extended mine life. In the center, we point out the appealing cash costs: $1.82 per pound of copper for the first 10 years, and roughly $2 per pound across the life of mine. The higher sustaining and deferred stripping CapEx compared with the prior plan reflects the larger operation, with more tonnes moved and greater throughput, and it has also been updated for the inflation observed since the 2021 technical report came out. Moving to Slide 16, the MV-O study sets out an initial expansionary cost of $146 million. That works out to a very low capital intensity of 7,500 per tonne of annual copper equivalent production, and naturally it stacks up very favorably against the other projects profiled. Santo Domingo, which appears on the slide as well, also stacks up very favorably. There is no better location for us to build another mine than 35 kilometers down the road from where we just finished construction successfully at the Mantoverde Development Project. Moving to Slide 17, on the left-hand side we present the combined MVSD district production potential, with the first 3 years of combined output averaging about 250,000 tonnes of copper at a very appealing cash cost.
Cashel Meagher
executiveLooking ahead, we intend to build on those base case figures by adding further opportunities — among them processing Santo Domingo oxides at Mantoverde, carrying on district exploration so we gain a better grasp of the long-term potential, and evaluating whether by-product cobalt production is viable. On the right-hand side, you can see the different copper occurrences that have been identified in the district so far. The potential for future exploration across our own properties has us very excited, and so does the chance that other sterilized deposits could one day serve as future feeds for our processing centers in the district. I'll now hand things over to Wendy King for the sustainability review.
Wendy King
executiveThanks, Cashel. We're turning to Slide 18 now, where we look at sustainability highlights from Q3. In Santo Domingo, we set up a community engagement office so residents stay informed and involved in developments as the project ramps up. In Mantos Blancos, we marked 20 years of partnership with the Delta UCN program. Each year, that education program reaches close to 500 elementary and high school students across the Antofagasta region. This year it was broadened to offer mental health support for over 100 university students. We take real pride in the positive impact this collaboration has delivered over the years for young people's education in the region. Also in Chile, Capstone Copper earned the 2024 best Midsized Company of the Year Award from Sonami, the Chile Mining Association. Recognition of Capstone's ESG practices and community engagement is a key part of that award. At Cozamin in Mexico, we released a biodiversity handbook. It drew on a site monitoring program in which we teamed up with six biologists to collect and classify data across 2 years. In the quarter, Cozamin also worked with its contractors to replant two hectares of land using native species.
Wendy King
executiveAlso, out at Pinto Valley in Arizona, three diesel-powered engines have been swapped for electric ones, and we intend to swap out another two units during Q4 under our PV electrification project. Carbon emission Scope 1 reductions will come from this initiative. With that said, I'll hand things back over to John.
John MacKenzie
executiveThanks, Wendy. If you look at Slide 19, we've laid out the growth plans that lead our sector, along with some extra upside that exists in our portfolio. As you can see, once MVDP reaches its full run rate, we expect it to take us to a consolidated annual production level of more than 250,000 tonnes of copper, with costs in the low $2 per pound range. From that point, the Mantoverde Optimized and Santo Domingo projects together would bring us to roughly 400,000 tonnes of copper production per annum, at cash costs that are even lower. Our intention is to move ahead with Mantoverde Optimized once we receive a DIA permit amendment. We filed for the DIA permit earlier this year, and we expect to receive it in the first half of 2025. Our plan is to fund this project using cash flows generated internally. At Santo Domingo, we're continuing to work through the assessment of the best financing structure for the project. We're approaching this in much the same way as what we managed to achieve at Mantoverde. As part of this, we've recently started a process aimed at bringing in a partner at the minority level. We're also pushing ahead with discussions regarding a project finance facility, which we see as forming part of the financing package for Santo Domingo.
John MacKenzie
executiveBefore we make a possible sanctioning decision at Santo Domingo, we also want to see every one of our assets running at or close to full production levels, along with consolidated net debt to EBITDA below 1x. And naturally, we'll keep the broader macroeconomic environment in mind as well. Because of that, we expect to reach a sanctioning window for Santo Domingo sometime later in the second half of 2025. Past these projects, we see further upside throughout our portfolio: another low-risk brownfield expansion opportunity at Mantos Blancos, added flexibility in the MVSD district to unlock more copper and potentially by-product cobalt production, and the possible development of another major copper district around our Pinto Valley mine in Arizona. Moving to Slide 20. We lay out the timelines for several of the studies I've mentioned, plus other milestones as we carry out our growth plans. This is a big year for Capstone, and the third quarter represents an important step in transforming our business, with tangible delivery on our peer leading growth. During the past few months, our Chilean operations hit meaningful milestones at both our flagship Mantoverde Development Project, where we achieved commercial production, and at Mantos Blancos, which is now enabled to deliver its nameplate capacity.
John MacKenzie
executiveWe anticipate that the fourth quarter will be the strongest one for us this year, giving a preview of what Capstone will look like going forward, with a bigger production base and reduced operating costs per unit. At Capstone, we are now in an extremely strong position to grow into a leading copper producer with long-life assets and low costs, and to play a significant part in backing global decarbonization efforts. With that said, we are ready now to take your questions.
Operator
operatorThanks. <<operator_script>> Our first question is from Orest Wowkodaw at Scotiabank. Go ahead, please.
Orest Wowkodaw
analystThanks, and good evening. Perhaps I could begin by congratulating John and Jerrold on their retirements. Congratulations also to Cashel on the new role. I wanted to focus on the Mantoverde sulphide project. You've been operating now for a couple of months. Can you give us — are you seeing any area of the operation, whether it's mining, crushing, grinding, flotation, et cetera., where you are seeing any concerns that could limit your ability to ramp up or achieve a consistent, call it, 32,000 tonnes a day by the end of the fourth quarter? I'm just wondering if there's any area where you see some risk right now.
John MacKenzie
executiveYes. Hi, Orest, and thank you for asking that, and I appreciate the congratulations — though I'd note that my plan for retirement is to stay fairly deeply engaged with the business. So …
Orest Wowkodaw
analystPerfect.
John MacKenzie
executive… you'll be hearing a lot more about this. So I'll hand it over to Cashel, who can give you a more detailed answer on that point. From where I sit, though, I've been through a good number of mine ramp-ups. What I've seen at Mantoverde so far has made me very happy. In just about every area, the equipment has been, I'd say, over-designed. We've managed to run the plant at rates above the design capacity <<inaudible>> for many continuous days, and no bottlenecks have shown up. So obviously, there's still work to do to make sure we achieve ultimate operational continuity and to get our operators trained up so they run the equipment well. But looking at it from the mine side, the mine is operating really well. The reconciliation between the block model and what we're actually mining is spot on. The performance of each piece of equipment, whether it's crushers or mulls or flotation — I was just talking to Peter Amelunxen earlier today. He was just amazed at how we haven't had any issues downstream with things like filtration and thickening, et cetera. Tailing dams in place, the desal plant is ramped up really nicely. So at this point, certainly from my perspective, I'm really pleased with what I see.
John MacKenzie
executiveI see this from two angles: one is the ramp-up we're doing right now, and the other is the Mantoverde Optimized Project that comes after, where we aim to push this equipment further so it handles 45,000 tonnes a day instead of 32,000 tonnes a day. And I have to say, I'm quite encouraged on that front too. Nothing we're seeing gives us reason to hesitate about whether the plant can eventually reach that level. But, Cashel, could I ask you to build on that?
Cashel Meagher
executiveYes, absolutely. Everything John mentioned is accurate, and it's quite encouraging to hear. No ramp-up ever happens without hiccups, and we've certainly had some, though luckily they were issues we could work around. At the start, a motor failed on us, but we happened to have a spare on hand. That spare motor is being repaired right now and should be coming back to us shortly. We also ran into some limitations with our cleaner circuits, and we accepted a small amount of downtime in order to fix that by boosting pumping capacity and enlarging pipe diameters. That constraint had actually been limiting the grade we were able to feed through. So as things stand, we're fortunately now able to process the higher grade that Mantoverde offers. I'd characterize these as ordinary problems. And at this point we're handling smaller items — reagent optimization, establishing control parameters for the operators, and adjusting operator procedures so they align more closely with Mantoverde specifically. For instance, the desalination plant has now undergone stress testing and is capable of supplying all the water we need. Sand production is proceeding nicely at the tailings dam. So, touch wood <<inaudible>>, things have gone very well, and we believe we've been eliminating the variability in the process, and with that small modification to the cleaners I mentioned, we feel fully capable of reaching consistent full nameplate production before this year is over.
Orest Wowkodaw
analystThat's great. And since today happens to be Halloween, could you offer us an early glimpse of how October may have shaped up on that front, specifically regarding average throughput and perhaps recoveries?
John MacKenzie
executiveCashel, would you like to take that one?
Cashel Meagher
executiveYeah, I won’t give you exact figures. As of today, they’re still pending completion. But things are progressing quite well. We’re in the high 20s on recoveries? So that’s moving along nicely. Yes, recoveries are also performing well. So there was — we had what we refer to as the buildup. We needed to accumulate inventory inside the bedding of the thickener as well as in the cracks and crevices. We also encountered those problems, as I mentioned, with the cleaners. So on site we actually have a storage pond that must be reprocessed and concentrated. As a result, our metallurgical recovery has been in the low 80s this month, and before that we were at just about 80. So it’s going really well. And as I said, there’s some optimization work on the cleaner and rougher circuits, some reagent optimization, and all of that is underway now. So it’s good to be in a position where we don’t have to concentrate on throughput and can instead focus on metallurgical characterization, so to speak, and optimize that as we move into Q4.
Orest Wowkodaw
analystGreat. Let me ask just one more quick thing, if that's all right. I noticed the release didn't mention any CapEx guidance for this year. Does the earlier figure — 470 million — still hold at this point, or is it different now?
John MacKenzie
executiveYeah, it's pretty much the same. We had — yes, sorry, John. Or it says pretty much the same. We had allowed for a bit of expiration that we'd sort of flagged earlier in the year.
Orest Wowkodaw
analystI appreciate that.
John MacKenzie
executiveMuch appreciated, Orest.
Operator
operatorThanks. The next question is from Ralph Profiti at Eight Capital. Go ahead, please.
Ralph Profiti
analystThanks, operator, and thanks for taking my questions. I’d like to get a bit more specific about recoveries, Cashel, at Mantoverde. Have you now worked through the in-process inventories and moved into the run of mine ore? And just thinking about how we get from 80% to the 88% design rate — would that 88% be something like a year-end ’24 target? Is that conceivable?
Cashel Meagher
executiveYeah, I’d say it’s possible. From what I’ve seen — and Peter is on the line with us here — I’d put it this way: ramping up always follows a sequence. First mechanical, then warranty, then throughput, and after that optimization on recovery. We’re really close to the end of the throughput stage now. Obviously, we reached facility practical completion, where we had consecutive days at nameplate throughput. At this point we’re focused on operational controls. But since Peter is on the line, perhaps he can speak to the process of reaching the desired recovery.
Peter Amelunxen
executiveAbsolutely, and thanks, Cashel. Right before I get into it, I want to second what John and Cashel said — I'm really pleased with how the plant has performed so far, on both tonnage and recovery. The roughly 80% to 82% recoveries we're getting at the moment come from a mix of losses in the roughing circuit and losses in the cleaning circuit. For a plant that's well designed and well run, the cleaning circuit ought to be sitting near 98%, with the bulk of the losses occurring in roughing. In our situation, though, the cleaning circuit had constraints, so operators ended up running it slower, which produced higher-grade concentrates and pushed more copper into the cleaner tails. Consequently, cleaning circuit recoveries have typically landed around 90% — in the 88% to 92% band — far below what we'd anticipate once that bottleneck is removed. Those modifications went in roughly late last week. We installed the new pumps earlier this week, so the final results aren't in yet. The operators will also need some time to learn how to run the circuit at higher throughput rates, but overall, my point is this: if we had a recovery problem tied to the design, we'd normally spot signs of it in the roughing stage, and we aren't seeing any of that.
Peter Amelunxen
executiveThose recoveries in the rougher circuit are above 90%, and there's plenty of residence time available. In the roughers we're at roughly 34 minutes, while the Cleaner Scavenger gives us about 35 minutes. Taking it all together, what the metallurgical data show me day in and day out leaves me very, very encouraged.
Ralph Profiti
analystAppreciate the commentary, Peter. Turning to Pinto Valley — it took a bit of a step back in Q3, and I noticed from the presentation that it's now in its 50th year. If Raman would like to jump in here: how are you viewing sustaining CapEx going forward? Historically, I see a run rate of $50 million to $60 million each year. I'm just curious, as that operation gets older, how should we be thinking about that piece of the equation?
John MacKenzie
executiveYes, Ralph, good question. What I'd probably propose is this — Cashel, perhaps you could kick things off by explaining our approach where the asset management framework is concerned, since I think, Raman, once that's done, I'd like you to address the sustaining CapEx itself. To my mind, though, the bigger point is genuinely having the proper preventative maintenance program plus the proper asset management framework in place, so that the equipment runs at or above design. So maybe I could just have Cashel say a few words on that, and then we'll move over to Raman.
Cashel Meagher
executiveYes, Ralph, what we're putting in place is an asset management framework. The reason for that is two of our mines have what you'd call aging infrastructure — things like electrical components that are past their prime, conduits, steel that's wearing out, fatigue, and it even comes down to pipes and the brackets holding them needing to be swapped out. And what we noticed over the past few years is that at Pinto Valley, we kept getting unplanned breakdown events involving some of these structural, electrical, and mechanical components that are essential for steady throughput. So when those unplanned events happen, they're really what's working against Pinto Valley and causing it to miss targets from time to time. So we began last year. We brought in a team that is rolling out an asset management framework across all our mine sites. It contains 15 components that cover all the various pieces of asset integrity, asset management, and maintenance. Everything from the procurement chain all the way through to inspection, repair, time to repair — all of those kinds of systems and processes. And we've begun implementing it, and we got some really quick wins, which was great early in the year at Pinto Valley, and we were getting much higher production with fewer unplanned events, but we had a couple of events in the last quarter that we'd describe as one-off events.
Cashel Meagher
executiveA key conveyor transporting ore between our primary crusher and the tertiary crusher system failed on us. The belt split apart, and it turned out a splice installed a year earlier had been vulcanized poorly. So essentially, we want a system in place that gives us solid evaluation of these systems and processes. It wasn't catastrophic in the sense that it broke anything, but bringing it back online took a long time — more than a week — and we lost those production days. So what we're trying to drive out of the system now are those unique events, by having regular proper inspections and bringing more modern techniques and systems to bear on assets that ostensibly are 50 years old, as you mentioned. So those are the things we are doing to improve it. And with that, I will hand it off to Raman for your original question around the CapEx.
Raman Randhawa
executiveYeah. Ralph, that CapEx figure you brought up falls roughly in that band—we'll be looking at 70 to 80 across the coming few years, since we keep putting money back into the facility and upgrading various parts of it as time goes on.
Ralph Profiti
analystAlright, that's great, and I appreciate it. I want to thank the team for the answers they gave. Let me also add my congratulations regarding the leadership change. It's very encouraging to see the strategy continuing. Many thanks to everyone.
John MacKenzie
executiveAppreciate that, Ralph.
Operator
operatorThanks. The next question is from Craig Hutchison at TD Cowen. Go ahead, please.
Craig Hutchison
analystHello there, and good afternoon, everyone. I'd like to pose something along the lines of what Orest raised regarding Mantoverde, except I'd direct it toward Mantos Blancos. How are things moving along there in October when it comes to throughput levels and the improvement in grades that we had anticipated? Thank you.
John MacKenzie
executiveThanks, Craig. I’ll hand it right over to Cashel so he can speak to that.
Cashel Meagher
executiveYes. It's a comparable situation to Pinto Valley, Craig, in that a number of the components are getting older, and we're likewise putting an asset management framework in place, and we've already started to see the benefits from that. I noted in my script that we just went through that we exceeded 18,000 tonnes a day for August and September, and I'd add that October is going better for us than August and September were. So that's really encouraging. Another really encouraging item is obviously that recoveries are getting better. So that's really encouraging. And then the other one is, we had a sort of, at the beginning of the year, we had a minor geotechnical problem in the mine that made us re-sequence the mine and pushed us to somewhat lower grades, and that's been resolved as well. So the work we did with the two-week shutdown to be able to fix the back end by installing an additional positive displacement pump, because really the three pumps needed to be online 100% of the time. So we needed one in rotation to maintain one of the other three. So now we have four pumps, so three can be online at all times.
Cashel Meagher
executiveSo the <<inaudible>> restriction is gone now. What we observe, naturally, is that once you fix a single constraint, another one pops up as the following constraint. We've therefore achieved certain gains in our hydro screens and cyclones on the coarse fraction of the tailings, yet we can see where we stand today: we'll reach several consecutive days at the nameplate capacity we refer to for that specific mine. So what we're seeing, roughly, is incremental gains week by week and month by month, and right now we're nearing the high teens. As I mentioned, we're holding steady at 18,000. We therefore think we have a very solid plan that takes us to that nameplate capacity by the beginning of the year, the new year. So we're quite happy with the progress achieved. I believe a number of the modifications we've made have had a real impact and been transformational there. And at this point the team can focus on some of the smaller items, such as recovery, to lift that and make improvements on that side of things.
Craig Hutchison
analystAll right, that's helpful. Perhaps I could just ask one more follow-up. <<inaudible>> brought up a goal of getting leverage under 1x prior to, I suppose, your making a call on Santo Domingo. Do those same leverage goals extend to the Mantoverde Optimization Project as well?
John MacKenzie
executiveYes, I’ll have Raman go into that in more detail. But overall, Craig, I’d say our approach to managing the balance sheet and how we finance is relatively conservative. We don’t want to put the company at risk by moving quickly on capital projects that could place any stress on our balance sheet. Mantoverde Optimized is a fairly specific case, because to some degree that operation is somewhat ring-fenced by the project financing facility we have in place. What I can tell you is that in our discussions with our project financing banks, they are actually very enthusiastic about us proceeding with Mantoverde Optimized. Some elements in our current covenants, such as cash sweeps, they appear quite willing to review with a view to reinvesting some of that cash flow into Mantoverde Optimized instead of cash sweeps. But overall, when we look at our leverage levels, I think we’re going to reach that one-times net debt to EBITDA pretty quickly during the course of next year. So I think regardless, by the time we move forward with Mantoverde Optimized, we should be in a position where we’re certainly on a leading basis at that ratio.
John MacKenzie
executiveRaman likely has a clearer read on that when we look at it on a lagging basis. Raman?
Raman Randhawa
executiveYeah, I mean, Craig, I’m on board with everything John just said. And I mean, when you consider MV optimizers, we’ll work alongside you with the banks regarding amendments on the PF and the ability to reinvest. But when you look at Mantoverde in 2025 on a full run rate basis, like, I mean, you’re talking operating cash flow of 450 million, 500 million, less than stripping. So you can tell just from the cash flows at the site level that that would be enough to kind of spend that $146 million over a 12-month period. And obviously, it comes with a very quick payback. So — and look, doing that in step while we’re doing the financing for Santo Domingo obviously just improves our EBITDA and helps actually get lower — get to that one times even faster if you think about it that way.
Craig Hutchison
analystExcellent. Appreciate it, everyone.
Operator
operatorThanks. Our following question is from Adam Baker of Macquarie, on the line. Please proceed.
Adam Baker
analystHey John, appreciate the call. I was just wondering whether we might get an update on where things stand with the Santo Domingo minority sell-down process, and when we should expect to hear something on that. And perhaps you could give us a sense of what kinds of parties are in the data room there. Thanks.
John MacKenzie
executiveYes, absolutely. So we put out the full technical report for Santo Domingo fairly recently—the actual technical report. And obviously, we couldn't really move the process forward until parties had that in hand to review. So that's now been completed. I've been quite pleased with the level of interest and enthusiasm shown. At this point we have many parties in the data room. Last week I was over in Japan along with our head of corporate development. We held meetings with a good number of Japanese parties that are currently in the data room. Those discussions, I'd say, were very constructive. Another thing that's interesting is the emergence of interest from a lot of sovereign wealth funds in the Middle East. Once again, we have quite a number of parties from that region in the data room, plus a bunch of others, I would say. So interest has been wide ranging. Ultimately, we need to look at all of these parties. We need to consider what gets put on the table, but we also need to consider that this will be a partnership lasting 30 or 40 or 50 years, and that we need to make sure there is good strategic alignment between ourselves and whichever party is finally selected to move forward with us.
John MacKenzie
executiveI'd say we're making solid headway, though it will likely take a couple of rounds. My guess is we'll be in a position to give you some kind of meaningful update around some point in the first half of next year.
Adam Baker
analystGot it — that's clear, thanks. Maybe just one question about the <<inaudible>> project: if I remember right, the latest update said the exploration agreement ran through September 2024. Could you remind us what happens next on that?
John MacKenzie
executiveYes, absolutely. As I remember it, we've pushed that out through July 2025, so it continues. Right now we're working together on some studies regarding what the ideal district would look like. Those studies have to wrap up before we're able to shift from that point into talks on the commercial side. Still, I'd say things are going quite well for us at this stage.
Adam Baker
analystAppreciate that, John. I'll take it from here. Thanks.
John MacKenzie
executiveAppreciate that, Adam.
Operator
operatorMuch appreciated. The following question is from Dalton Baretto of Canaccord Genuity. You have the floor.
Dalton Baretto
analystThanks, operator. Good evening, everyone. And Jerrold, Cashel — sorry, John, Cashel, congratulations. And to Dan as well for filling Jerrold's very big shoes. Most of my questions have been answered, just one for me, maybe for Cashel. There was some talk a while back about the new tailings facility at Pinto Valley and how the water reclaim system there would unlock debottlenecking up to 70,000 tonnes per day. I'm just wondering where that stands right now. Thanks.
John MacKenzie
executiveCashel, the floor is yours.
Cashel Meagher
executiveYes, absolutely, John. We're currently going through the design work on that. My sense is it'll likely be sometime in the early part of the first half of next year when we'll be able to share a base case for the new life of mine plans at Pinto Valley. And that would also let us bring into line some of the optionality we have at Pinto Valley. So you're absolutely right that a new tailings stand could create the chance to use reclaimed water. It could also open up the ability to boost the horsepower in the milling system as it stands today. If we do that, the circuit would then be able to handle more throughput. We already know the crushers have the capacity as currently installed. So all of that opportunity exists, and these are the kinds of things we're working through. It's actually tied to the work being done for the Copper Cities opportunity as well, since to really unlock the larger district, what's needed is additional capacity. That's because the majority of the ore in the region carries the same grade, between 0.3 and 0.35. There's close to perhaps 2 billion or 3 billion tons of resource available in the district.
Cashel Meagher
executiveWe’re reviewing quite a few alternative versions with BHP, and our base case is to make Pinto Valley itself as efficient as possible.
Dalton Baretto
analystThanks, Cashel. That actually leads nicely into my follow-up question. So when you consider the wider district and move toward the asset reliability program, do you feel comfortable with the existing Pinto Valley mill ultimately serving as the base case, or do you believe a new mill will be needed at some point?
Cashel Meagher
executiveThat's an excellent question, and it comes up often in our discussions. Owning a mill represents the greatest asset, and getting that mill repaired represents the greatest asset. Therefore, in every scenario I can envision, that mill will be put to use in some form or another. The possible configurations are numerous. Which option ultimately prevails is unclear to me, but you could imagine, for instance, if the goal were to raise capacity beyond 100,000 tonnes, simply installing a sag mill ahead of the existing ball mills and then perhaps drawing on some of that surplus crushing capacity to sustain a portion of our sulfide leaching. So there are quite a few — I believe the team had somewhere between 10 and 15 distinct alternatives that they were evaluating. Another possibility involves constructing an entirely new complex nearer to the Copper Cities resource. So the range of options is simply enormous, and the effort underway sits at the trade-off study stage, at PA scoping stage, so that we select the optimal path against multiple criteria: execution, risk matters greatly as well, permitting risk matters greatly, water matters greatly, as you noted, and new tailings facilities matter greatly.
Cashel Meagher
executiveSo all of that is being weighed in there, but every one of those options is under evaluation by us.
Dalton Baretto
analystUnderstood — thank you, Cashel. That covers everything on my end.
John MacKenzie
executiveAppreciate that, Dalton.
Operator
operatorThanks. Our final question is from David Radclyffe at Global Mining Research. Go ahead, please.
David Radclyffe
analystHello, and good morning — good afternoon to all of you as well. My question follows up on Mantos Blancos. I’m wondering whether the delays you’ve had in the learnings from those affect your thinking about a Phase 2 project in the current study. So, I mean, at this point it sounds like you remain confident that you can reach capacity with the recent works, but do you believe that Phase 2 requires any extra works beyond the original scope in order to improve performance redundancies going forward?
John MacKenzie
executiveYes. David, I’ll make a quick remark, then hand things over to Cashel. In the end, moving from 20 to a range of 27,000 to 30,000 tonnes per day requires us to determine precisely where the constraints sit, since we already have an existing plant. What we do know at this point is that we have substantial excess crushing capacity. We clearly have enough milling capacity to reach 27,000 to 30,000. So the real issue is downstream of that, where we need to pin down exactly where the bottlenecks are. And until the operation is actually running at steady state, at current nameplate capacity, it isn’t optimal to try to specify precisely what the best engineering approach is for taking it to that next stage. So we know the resource base is there to support this growth. As a matter of fact, the optimal throughput rate today is likely in the 27,000 to 30,000 tonnes per day range. But I think at this point, what we really want is to be operating at steady state at design, and from there we can then push the different parts of the system so we can see exactly where the bottlenecks are and what the most efficient way is to spend capital to get us to that next step up, and whether it is best done in a single step or in multiple steps.
John MacKenzie
executiveCashel, is there anything you’d like to add on that?
Cashel Meagher
executiveNo, John, I believe you got everything. Appreciate it.
John MacKenzie
executiveOkay, that's all from me.
David Radclyffe
analystWell, thanks for that. I'll make sure to share it.
John MacKenzie
executiveAppreciate it, David.
Operator
operatorThank you. There — thank you, and at this point we have no more questions. I'll hand things back over to Mr. John MacKenzie now for any closing remarks.
John MacKenzie
executiveThanks, operator. We’re eager to welcome some of you to our Chile operations in just a few weeks for the analyst and investor site tour. Following that, we’ll bring you another update in February when we report Q4 results. In the meantime, please stay safe, and don’t hesitate to contact Daniel or Michael with any additional questions. We appreciate your ongoing support, and have a good day.
Operator
operatorAppreciate it, and that brings us to the end of today's session. Thanks for joining us. Everyone is free to drop off now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.