Aya Gold & Silver Inc. (AYA) Earnings Call Transcript & Summary
November 14, 2024
Earnings Call Speaker Segments
Operator
operatorGood day, and thanks for staying on the line. You're welcome to Aya Gold & Silver's conference call covering the third quarter 2024 results. Right now, everyone attending is in listen-only mode. Once the speakers finish their presentation, a question-and-answer session will follow. <<operator_script>>. At this point I'd like to pass the conference to Ruth Hanna. Please go ahead.
Ruth Hanna
analystThanks, Operator. Good morning, everyone, and welcome to Aya's earnings call for the third quarter of 2024. With us today are Benoit La Salle, President and CEO; Ugo Landry-Tolszczuk, CFO; Raphaël Beaudoin, Vice President, Operations; and David Lalonde, Vice President, Exploration; all joining from Marrakesh. We'll wrap up today's event with a Q&A session featuring the team. As always, if any follow-up questions aren't addressed during the call, please reach out to our IR team directly. Before we begin, I'd like to remind listeners that today's event will include forward-looking statements involving risks and uncertainties that could cause actual results to differ materially from those in the forward-looking statements. Details of the forward-looking statements are contained in our November 14 news release as well as on SEDAR+ and on www.ayagoldsilver.com. With that, I'd like to turn the conference over to Aya's President and CEO, Benoit La Salle. Benoit, please go ahead.
Benoit La Salle
executiveThanks, Ruth. Morning, everyone. Appreciate you joining us today. Q3 2024 is a quarter of transition, yet it brings a key strategic achievement. We keep moving Zgounder mine forward — it remains on budget, and as we said, we ran a couple of weeks behind the original plan, but we've recovered part of that lost time and commissioning is now underway on an ongoing basis. Our target is commercial production in late Q4 2024. To support that, at the close of this quarter we hold a stockpile of 347,000 tonne of ore, ready for commissioning of the new plant. The expansion stands at 99 point something completed. You saw the video last week. You saw the press release. So we're nearly there, and further development will come in the very, very short-term. On production, this is a transitional quarter. We produced 355,927 ounces, and the reason we came in under budget and below expectation is that we were developing new stopes, but those weren't ready for this quarter. They are ready for the Q4 quarter, so between the delay in reaching the new stopes and the fact that we now follow a very disciplined mining method, we remained in stopes with lower grade and less tonnage — that's why production was lower.
Benoit La Salle
executiveWe're already seeing that get fixed during October. In the quarter, we brought in $11 million of revenue at an average realized selling price of $27 per ounce, and that's quite strong given the broader market over the last few months. The net loss for the period isn't significant — it's $300,000 — and the adjusted cash cost stands at $19.93. As you can see, we're also reporting a total cash cost of $23.47. But we need to point out that this cash cost figure includes non-recurring expenses. Developing the six stopes that are now ready wasn't capitalized; it was run through as an expense in Q3, and that pushed the cash cost up by nearly $3.50. So these are non-recurring expenses. A contract was awarded to an outside contractor to develop those six stopes, and clearly, when a contractor is used, it costs a lot more than our own team. But we chose to do it this way because we're getting ready for the plant to be up and running by Q4 2024. And as you know, by then, we'll be mining underground 1,600 tonne per day. So when we talk about commissioning, very often people think of commissioning of a plant.
Benoit La Salle
executiveOn top of that, you've got the ramp-up and commissioning phase at the underground mine, which involves a great deal of equipment and many new personnel. Keep in mind that this operation was formerly a 700 tonne per day mine, and going forward it will be a 2,700 tonne per day mine. So the plant is ramping up, but the mine is ramping up as well — chiefly the underground operation. Things are progressing very smoothly at the open pit. We're currently mining 500 tonne per day, and we'll be moving to 1,000 tonne per day. Just so you can grasp the cost picture, during Q3 we processed 42,000 tonne, and mining costs underground came to $85, which took in development of the six stopes. Mining cost on our stockpile is $35. So as you can tell, that quarter was truly highly unusual, with non-recurring expenses. As I mentioned, we're already witnessing significant changes coming through in Q4. Because we ran a couple of weeks behind and because commissioning is now getting underway more in Q4 — and then in Q3 — we will revise this year's guidance to 1.6 million up to 1.8 million ounces for the year 2024.
Benoit La Salle
executiveAlso during the quarter, we completed a spinout. We formed that spinout in order to get better value for our gold assets. We signed a term sheet with Mx2, which is a brand-new company, covering the Amizmiz asset and the Tijirit asset. The spinout has been a very strong success. The new team began with $7.5 million in financing and finished with $15 million in financing. So it's been a great success, and everything is being assembled right now as we speak. On the exploration program, as you know, Aya is a really fascinating exploration story. We've confirmed high-grade mineralization at depth and along lateral extension at Zgounder, and we'll go through some of those drill results. We extended the Boumadine main trend up to 5.4 kilometers. You'll remember that last year we stood at 4.2 kilometers. We've also demonstrated potential for new styles of mineralization in one drill hole where we got close to 2% copper and 2,000 grams per ton of silver. Also in the quarter, we are getting ourselves ready for new drilling, which has now begun in Q4. To the West, we have new anomalies to the East and to the South; we are currently drilling the new anomalies to the West.
Benoit La Salle
executiveOkay, so just a really fast rundown of the spinout. For now, Mx2 is a privately held company. It covers North Africa and West Africa, since it holds an asset in Mauritania. Amizmiz is a mining permit located in Morocco. It carries a resource — not 42 to 101, that dates back many years — of more than 300,000 ounces at 13 grams per tonne. And at the moment, a 2,400 meter drill program is underway to examine the extension and to begin building an understanding of the geology. The new team at Mx2 is on site right now alongside our team, the Aya team. And the drilling is in progress. There's also the Tijirit asset, on which we've completed a feasibility study. It holds a resource slightly above 500,000 ounces. It runs between 2 grams per tonne and 1.6 grams per tonne, depending on which deposits you look at. Mx2 holds an option to purchase this from Aya across the coming three years. They'll be evaluating fast-tracking it toward development, or else more drilling plus development and construction, hopefully in the very near future. Our position in Mx2 following the financing will be 42% ownership for Aya. The company will hold $15 million in cash, and Aya will have two Board members seated on a Board of roughly seven individuals.
Benoit La Salle
executiveMoving to Slide 5 in the deck, this is basically a brief snapshot of where things stand as Q3 wraps up. So silver output came in somewhat below our target. That's partly because stopes weren't ready, and partly, as I've said, because we're quite disciplined now — in the past, the practice was to open stopes, leave them open forever, move on to the next, and perhaps return at some point. That's no longer how we operate. We complete the stopes, then we backfill them — we have a cement backfill plant — and by backfilling we can then access the stopes sitting between two mineralized stopes. That disciplined method sometimes pushes us to keep going into stopes holding lower-grade material. Still, for the company overall and for the project, being disciplined — taking all the ore that's there, doing the cement backfill, then advancing to the next phase — is the right path. So on Page 5, you can see production set against the remainder of the year.
Benoit La Salle
executiveYou've got the grade. Once more, since we remained in a few older stopes, our average grade came in at roughly 161 grams per tonne, and for this deposit that is definitely too low. But the truth is, we don't want to leave that material sitting there and simply not extract it. So as of October, we're already back at 190, and we expect that figure to keep climbing. Mill recovery always lands between 82 and 85, again running smoothly. The truly key chart here, though, is quarterly tonnes processed. We're at 83,000, an increase of 19% year-over-year. Both of the plants we operate perform very well. They're older, yet they'll continue running even after the third plant is commissioned. On Page 6, you have a few financial tableau — in French, I said charts — a few financial charts. There's your cash flow from operating activity, negative $6 million this quarter, because we invested heavily in developing the six stopes. Then you have gross profit, which is again somewhat lower since the grade was lower, and profit and cost of goods sold move together.
Benoit La Salle
executiveAnd with somewhat reduced output during the quarter, along with somewhat diminished grade, you end up with an elevated cash cost, which came in at $23, as shown on the following slide. So because of that, you get a quarter in which, at the close, when you review the financial statement, we're at breakeven — something I consider not too shabby for a transitional quarter while we're ramping up the plant and ramping up the mine. And this week we did reach 1,600 tonnes per day from the underground mine. So we've arrived there. We're positioned exactly where we want to be for this project to truly gain momentum. So you have that on the construction side. You can see it on Slide number 8 — this Zgounder expansion — plus you watched the video last week, which is quite revealing. But the processing plant is 99% complete. Both the underground and the open pit are running very well. Tailings water management — very good news on water management. We're at the start of the rainy season and every one of our water reservoirs is full. So that again is quite unique. This is the period of the year when we've had excellent rainfall, and we — our water management system and the way we capture the water is performing extremely well.
Benoit La Salle
executiveSo I'm happy to report that where water is concerned, things are going really well. The electrical infrastructure is in place, as it should be. You've seen a few of those photos. Green energy is arriving at the site. As you're aware, we hold a 20 year PPA. It's on its way, it's running very smoothly, and we're happy about that. On the Zgounder expansion, you saw that decommissioning has begun. You saw the ball mill — the lubrication system that caused a delay of a few weeks is now fully restored and running. Every problem we had has been resolved. All the testing is done. The oil is clean. The ball mill turns. And you saw the conveyor. So everything is functioning very nicely. We've also finished our lab. So at Zgounder we now have a very large lab where all our samples and our preparation can be handled, so that too is complete. Moving to the exploration side of our business. As you know, our drill program ranks among the biggest in Africa. This year we are drilling 160,000 meters, and we have three principal zones: the Zgounder mine, the Boumadine project, and the Zgounder Regional. So at the Zgounder mine, by the close of Q3, we had completed 25,000 meters out of a 30,000 meter program.
Benoit La Salle
executiveAs always, David, David, if additional drilling is needed since you keep discovering and keep discovering extensions, just reach out to us. And at the Zgounder mine there's no restriction on the drilling we wish to carry out there, since it's on site, it can be trucked, and that's something extremely important. At Boumadine, 69,000 — nearly 70,000 — meters have been completed out of the 120,000 meter project program. We ought to reach close to 120,000 by the end of the year. Right now we're operating 11 rigs plus one RC, and we'll likely add a second RC for the deeper holes, so that we don't core the entire way. That will cost less and be quicker. So — but we're running 11 rigs at present. So the initial 60,000 meters was completed on the expansion of the main zone, and it extended the main zone to 5.4 kilometers of strike. The remaining 60,000 meters is being carried out on targets. And as I mentioned at the start, we're presently drilling the West target, which is a very strong geophysical anomaly. At Zgounder Regional, we're nearly finished. We had 10,000 meters in the program. At quarter's end we're at 9,800.
Benoit La Salle
executiveWe're actually locating mineralization. What we need is to locate a pocket where it has built up and that we can mine. The area, as you're aware, is extremely large. All the geological work has been completed by us — spectral imaging, satellite, geochem. Stream sediment has been done, and we're examining numerous targets, and we are drilling every target we identify. And at the same time, we hold the Tijirit asset, acquired last year. So the geophysics program has been completed by us, since Tijirit also carries a copper component alongside the gold and silver. And that is being analyzed by us right now. On Amizmiz, which previously belonged to us directly and now belongs to us indirectly via Mx2 — well, this year, mapping was done by us and a bit of geology too. But drilling, as I told you, has begun being managed by the Mx2 team and by our team. At Zgounder, on Page 11 of the presentation, we continue to hit some beautiful mineralization zones. To date, 8,000 meters have been drilled by us in Q3 within a 30,000 meter program. Look at some of those results again: 1,000 gram per tonne over 13 meters, 322 over 17 to 2,800 over 8 meters.
Benoit La Salle
executiveSo it's basically what we were expecting — a really good loaf of bread, 1.4 kilometers long and 20 meters thick, extending all the way down to the granite, which sits between 600 and 700 meters. Once we reach the granite, just as anticipated, we find a sort of silver enrichment at the bottom. And that's what we're observing. So this work is continuing. The program totals 30,000 meters. We completed 8,000 of that this quarter. And as I said, we'll keep drilling as long as we continue finding extensions at depth and toward the East and West. Turning to Page 12, you'll see the original geophysics for Boumadine. Boumadine is our primary exploration asset, given how much potential it holds. And last year, with 94,000 meters of drilling, it delivered to us globally across all categories more than 300 million ounces of silver equivalent at a very good grade, or 4.1 million ounces of gold equivalent at 5 grams per tonne. So it's a beautiful project. As I mentioned, we drilled 27,000 meters during the quarter. So you can tell things are very, very busy. To date we've drilled 69,000 meters. Results keep coming in continuously, and you'll keep seeing more, since we have 11 drills turning and the work goes on.
Benoit La Salle
executiveOver the course of this year, 18 additional permits have been secured, and that stems from our ability to see the structures at surface, since we carried out geophysics across the entire region. We flew 13,000 line kilometers of mobile airborne geophysics — actually it was empty geophysics — but the whole district has now been covered, and we hold a great many geophysical anomalies, all of which are under review. Geochemistry gets done. Ground is walked. Sampling is carried out. Once things are ready, we will — we drill those targets. So at present, as I mentioned to you, drilling is underway in the West, an important system. Turning to Page 13, just a handful of results from the quarter at Boumadine: 1,000 grams over 13.5 meters, and 322 grams over 17.6. So as you can see, continuous resolution exists along this 5.4 kilometer slab, which in geophysics we actually observe across 6 kilometers. It is continuous, it is present. Into that, 60,000 meters have been drilled. A resource update is planned for Q1 of next year. The real highlight, though, sits on Page 14 — the high conductivity anomaly. So what appears at the top, sitting above the two potatoes or cherries, is the surface. The drill results are visible on Page 14.
Benoit La Salle
executiveWe have been drilling at Boumadine, the target located on the right-hand side. On the left-hand side, as you can see, there is a comparable anomaly, and the top portion is mineralized. The reason we know the top of Boumadine is mineralized is that we have already discovered 352 million ounces of silver equivalent. What is really interesting at this moment, though — and you can see it in the bottom picture — is that we are drilling that long hole, which goes straight into the eye of the anomaly. So as of now, we are only just touching the green. That means we are roughly 900 meters into this drill hole, and we are just starting to enter what we hope to see, the mineralized zone, which carries the same signature as what we have at surface. But this is geophysical. So is it exactly there? This is the start of a program. Now, the reason we are drilling this is that we want to understand whether this is a pore-free system, whether this is mineralization at depth. Because look — if you look at the surface and how small it appears from where we stand now, and we know that this is 5.4 kilometers long and 300 — more than 350, because 352 million ounces was on a strike of 4.2 kilometers and now we are at 5.4.
Benoit La Salle
executiveNow let's examine the system beneath the surface. We'll be moving into that zone in roughly a week to 10 days, I'd say, naturally. And we're monitoring it, with the geologists feeding back to us on the type of rock they're encountering and where we're headed. So this is Boumadine. You have lateral extension westward, eastward, and southward; the north side remains open. And there's this structure at depth that appears extremely, extremely intriguing. Turning to ESG, to wrap up this presentation on Page 15 — look, health and safety matters enormously to us. During the quarter we recorded just 3 lost time injuries, and none of them were very, very serious. They were merely minor injuries. We delivered 5,000 hours of training this quarter, representing a 90% rise year-over-year. And we treat this seriously. If you follow us on LinkedIn, you'll indeed see plenty of photos of some of our employees posting pictures from the training, which covers health and safety. It can be education. It can be emergency. You can see all of that. I'm also delighted to report that we've obtained the ISO 9001 certification.
Benoit La Salle
executiveThe mine site effort was a team one. So from geology through to health and safety production, we've been awarded the ISO 9001 certification. All of our data has also been submitted for the carbon disclosure project. That the, our ESG loan with the EBRD is an ESG-driven facility. We received all of the money in 2024, since we've satisfied every one of our ESG requirements. So that's something we take extremely, extremely seriously. Things are also going very well with the communities. I'm pleased to say that our program in first school showed a 68% increase year-over-year in the percentage of students opting for science projects or science streams. So this is really extremely, extremely interesting. And we are now taking our program to second middle school. So primary school, high school, in Morocco, they call this first school and second school, middle school. But it's — we are very much involved on with education, online education, health and safety, health for the communities. We are now starting a mobile clinic, pediatric. You remember last year, we added for the eyes. We've had diabetes, we've had many, many clinics and livelihood with the saffron project, with agriculture, we have water pumps and we are really very much involved.
Benoit La Salle
executiveWe've put in some signals at the saffron and vegetable farms — that's purely for health and safety. So on a global basis, it has been a really, really strong quarter for certain milestones. Production has come in a bit low, and we acknowledge that, but we are building for the future. We're not simply out to maximize any single quarter. And if it becomes necessary — and we don't want to compromise the mine — so when we must remain in one phase and complete it so that cement backfill can follow, we do exactly that, knowing better times lie ahead. So the takeaway, again, is that at Boumadine 120,000 meters of drilling are underway, with interpretation ongoing, a major, major exploration program on the West and at depth, which is very interesting. Meanwhile the major strike, the main strike, keeps on expanding. At Zgounder, 40,000 meters of drilling — you'll recall 10,000 regional and 30,000 at the mine — are ongoing and again on track. We will probably go beyond the 40,000 meters, and at the Zgounder silver mine the expansion, well, as indicated, is on track and on budget. That budget was prepared in 2022 and saw some inflation in transport. And today we are within 1%, not even less than 1%, of budget — we reviewed that this week and it's — we can still say today that we are on budget.
Benoit La Salle
executiveWe can't claim to be on schedule, since that brief hold-up with the lubrication system plumbing set us back. Still, in another 3 to 4 weeks we'll be nearly back on schedule — though we have stayed on budget. So thanks so much for your time. I'll now hand things over to the operator for the Q&A portion.
Operator
operatorThanks. <<operator_script>>. We’ll begin with a question from Puneet Singh of Eight Capital. Your line is open.
Puneet Singh
analystHello, and thanks. Hi Benoit and everyone. To dig into the finer details of this quarter's modeling, could you say more about the underground problems you encountered at those stopes and the rework that's required? I'm simply trying to grasp the bigger picture here. Regarding those 4 stopes undergoing rehabilitation, do they differ from the 6 stopes currently in development? What's the reasoning behind that?
Benoit La Salle
executiveThanks, Puneet. The entire team is here with me in Morocco — we've just returned from the mine. So we're as well prepared as we could possibly be to address your question, since everyone is with me, and over the last three days we have, of course, gone through Q3's operations with the Board. I'll now hand things over to Raphaël, who, as you know, serves as our VP, Operations, leads the team, and oversees both construction and operations. I'd like Raphaël to share his perspective and some feedback on what we observed, along with the plan moving forward.
Raphaël Beaudoin
executiveMorning, everyone. Yes. So for this quarter, I wouldn’t characterize it as having problems. We’re ramping up. The mine is ramping up. There are three people in rehab. That’s simply because we’re learning more about the geology and refining our geological process. That’s fine. I’d say the lower grade in Q3 came from our access drive <<inaudible>>. We’re developing new stopes, and as we do the drives, we get ore, and when we drive the ore through the body, that tends to be the lowest grade of the stope. And as we move to higher cuts, to higher ranges on the stope, we get higher grades on the stope. We also have at least three stopes where we did the ore access, we did the ore drive, we got the primary reserve, and we’re ramping up our cement plant to backfill them. So we have three stopes that are awaiting. Just as we commission the cement plant, we’re integrating the cemented rock fill into our mining sequence, and we need to do that correctly. So it’s going well. And as we commission the cement plants, we’ll be able to backfill those primaries, mine the secondaries, and go to the upper cut.
Raphaël Beaudoin
executiveThe third quarter matters a great deal, and the fourth does as well. We have to prepare ourselves for the first quarter. Our services are in place. We have carried out substantial stope development in the East, where the grade is good, but we must mine it the right way, and that relies mostly on cement backfill. Once our cement field is fully integrated into the operation, we will be in a position to keep mining the first trench and to carry out the drilling.
Puneet Singh
analystAlright, understood. That sounds positive. It seems as though you're making your way through it during Q4, and hopefully things improve beginning next year. My second question, I suppose, was that open pit appears to be performing better at the moment, correct? And could you perhaps consider sequencing more open pit ore in order to achieve better grades over the upcoming quarters, or will you simply proceed as things stand?
Raphaël Beaudoin
executiveAbsolutely, glad to discuss the open pit. The open pit is actually performing quite well, and we're continuing to ramp it up. We've also discovered some extension slightly to the north that wasn't part of the original pit shell, and the whole team is pretty enthusiastic about it. The open pit has always served two purposes. The first, obviously, is to recover all the top ore that can't be accessed from the ground—that's clear—but also to ensure we have the flexibility required for this mill and for my ramp-up. So with those small extensions to the north and south, are we still working on it? Absolutely. We're now above 500 tonnes in the open pit. Our target is 1,000 before year end. We even hit 1,000 depending on the strip of processed <<inaudible>> each month. And we've started a second shift at the open pit, and it's going—again, going quite well. I mean, in October, at the open pit, we had roughly 200 gram per tonne. The strip is as expected. So yes, we'll sequence it to extract as much as possible from it, particularly to give us more flexibility.
Raphaël Beaudoin
executiveIt's also going to help bring costs lower, particularly during Q4 and Q1, as we proceed with commissioning the mill and continuing to ramp it up.
Puneet Singh
analystAll right, understood. That all sounds fine. So I suppose my last question concerns that anomaly, Benoit — when do you think you might expect results on it before year-end, or is it more likely Q1?
Benoit La Salle
executiveAre you asking about that large potato located beneath the Boumadine trend — is that the one you mean?
Puneet Singh
analystCorrect, that's 5 kilometers. That's right, westward, indeed.
Benoit La Salle
executiveThat call happens 5x a day. And we're tracking the drilling. All of us are tracking the drilling. As of this morning, David reported that we had reached 1,000 meters. So we're getting into the zone. The rock sequence we were hoping for is present. And we're a couple of days out — a couple of days, maybe 10 days, 15 days out. Clearly, this will be the lab's top priority, because turnaround time at the lab, when you're doing 160,000 meters of drilling — we account for 80% of the country's capacity — but this will get top priority so that it's there, the team is there. As you understand, it's like a new theory we're testing because of this massive geophysical anomaly. So yes, we're hoping for results before year-end. You understand, it's not one drill hole that will make it or break it, but the anomaly is strong. And also, when you look at the math, that same anomaly, or the same strength, is also to the West. So when you look at the West and we walk the West, you have the surface anomaly, but you also have the anomaly at depth, which is identical, but even bigger than the one beneath Boumadine main trend.
Benoit La Salle
executiveSo yes, that's a priority. Drilling out to the West is a priority as well, since that surface — and again, the geochem, when we walked around — showed us rocks of a similar type. So yes, we're quite pleased with the 1,000 meters completed to date, and we're expecting results.
Puneet Singh
analystAll right. Sounds good — we’re looking forward to those. Appreciate it, everyone.
Benoit La Salle
executiveThanks, Puneet.
Operator
operatorThanks. Please hold for the following question. We now have a question from Kevin O'Halloran at BMO Capital Markets. Your line is open.
Kevin O'Halloran
analystHi Benoit and the rest of the team — appreciate you taking my question. I was just hoping you could shed a little more light on those backfill problems that came up in the press release. And have they all been sorted out at this point?
Benoit La Salle
executiveOf course, and I appreciate the question. Once more, I'll hand things over to Raphaël so he can explain a little about our current position and why the commissioning process ended up taking somewhat longer.
Raphaël Beaudoin
executiveYes. So we began commissioning, and it went well. And I mean, this is really just a small leak on the cement tank in the field. So we took care of that. We swapped out a couple of elbows in the piping that tend to get somewhat clogged while we're running the testing, and we failed the first stope. We're getting the parts via FedEx and we're starting back up. So I mean, that's just part of commissioning. You commission things, they work, you have to change a few parts, and we're back in business. So essentially this is already fair.
Kevin O'Halloran
analystThanks. Appreciate it. You brought up that grades are improving. I was hoping you could provide a bit more detail on what grade profile we ought to anticipate across the coming few quarters as you ramp up.
Benoit La Salle
executiveWe're not providing guidance for next year at this point, but Raphaël, perhaps you could share what we're currently observing.
Raphaël Beaudoin
executiveYes. I mean, we talked about this in the MD&A back in October — in the open pit we had over 200 grams per tonne, so 209, which is in line with what we expected and also consistent with our mine plan. There are some large benches that might carry a bit more dilution, and a small one depending on it, but we're quite pleased with that grade. As for underground, we're also seeing a pretty good increase in October. And again, Kevin, it's always the stope drive and the first ore drive before we do the raises — those are always somewhat lower grade, and it's normal that as we develop more stopes, initially the grade is over. So to answer your question, it would be what we've historically mined, and some stopes are higher, some stopes are lower, and right now we have stopes above 200 and we'll keep having some.
Kevin O'Halloran
analystAlright. That's great. I appreciate it. That's everything from my side, everyone. Many thanks.
Benoit La Salle
executiveAppreciate it, Kevin.
Operator
operatorThanks. <<operator_script>>. Eleanor from SCP Resource Finance is our next caller, and your line is now open.
Eleanor Magdzinski
analystHello there, and thanks. Hi Benoit, and hello to the whole team. I’ve got a few questions that dig a bit into some of the operational specifics for today. A number of them have already been touched on, more or less. The first one, though, concerns the rehabilitation work. You brought it up earlier, but I think I may have missed part of what you said in response. Is this essentially about restoring the browse and access points to the long haul stopes among the four that are currently being rehabilitated, or does some portion of it involve fine tuning things like blasting and timing so that hang-ups and similar issues are avoided?
Benoit La Salle
executiveMuch appreciated. Once more, this one is really meant for Raphaël.
Raphaël Beaudoin
executiveSo over at Zgounder, there are a lot of high-grade stopes sitting nearer to historical stopes, and as we approach those, the design has to be right so we mine the whole wall. We also have to watch out for the historical back in that area. So whenever we reach a stope, we reassess the design each time, and then we have to ensure the right filler is in place to boost recovery and keep things safe. That's why sometimes, when we do the first hard dryer in a stope, we always check whether we have backfill size from a historical stope, particularly where these three stopes are located. So it's simply a question of taking the time to assess wall thickness before we can take on the other task. And if it's a bit too small, sometimes the access needs to be pushed a bit East or a bit West so we make sure to leave it there.
Eleanor Magdzinski
analystAll right, that helps a lot. So out of every stope you've already developed, plus those under development and being rehabilitated, do all of them use long-haul access, or are they intended to be long-haul stopes? For these first stopes, is any cut and fill being planned, I think?
Raphaël Beaudoin
executiveAt this point, at Zgounder, we aren’t doing long-haul stopping. Next year we have a trial planned, and on the subject of long-haul I consistently give the same answer. Long-haul is a method we at Zgounder want to pursue. It would lower the cost, yet it isn’t something we require. So right now our production cost sits only in cotton field, and introducing long-haul next year would certainly be nice. We are actively working on that as part of our long-term plan. But we don’t need it, and when we do it, we’ll make sure to success.
Eleanor Magdzinski
analystAlright, great. So out of those existing stopes you have — around 19 of them — the ones that have been rehabbed are more or less operational at this point. Broadly speaking, what mucking rates are you expecting from these zones? I'm just trying to get a sense of roughly how many stopes you need to have open in order to hit that projected steady-state production, basically.
Raphaël Beaudoin
executiveOkay, first thing to mention: we're on schedule with the stockpile we have. And we're also on schedule with the open pit mining rate, which has a fair amount of flexibility to increase. So the underground mining rate isn't something we're too worried about. Don't get me wrong — we need to do better than we did in Q3, and that's what I'll be focused on in October and November. Now, if you ask me, the ultimate mining rate — what we're aiming for underground — is somewhere between 1,500 and 2,000 tonnes per day that we have to hit underground, and we'll get there in 2025, depending on how things sequence with the open pit. So we'll stay flexible on both the open pit as we learn more about the opportunities there. And we'll take a reminder underground to make sure that for both open pit and underground, we have the funds we need.
Eleanor Magdzinski
analystAlright. And I suppose I have one more thing to ask about the backfill. You mentioned a backfill station that is presently in progress. Is it the case that all boreholes have been drilled, inserts are set, and the trunk lines and piping are in place? Is this merely a portion of the commissioning you were just describing as we move along, or is it a new backfill station serving another area that hasn't been reached yet? I'm just trying to get a bit more detail on that remark from the MD&A.
Raphaël Beaudoin
executiveAlright, perhaps I didn’t explain that well enough. What I mean is that the backfill plant has been fully installed. On each level, we have service holes and access points for cement. We also have a mixing base so we can combine the waste rock with the cement. So it’s all in place. What we’re discussing here is commissioning. At Aya, we’re pushing hard. We expected to finish in two days, but it turns out it’s taking longer than two days — closer to a month-and-a-half, since we need to swap out a couple of parts, and everything is already installed. We just have to get it running again. And that’s happening right now.
Eleanor Magdzinski
analystAlright, great. So it's only the primary backhaul station. I wasn't certain — at times, when there are small underground substations, folks may refer to those as stations. So I didn't know whether that was a separate item you meant, but that clears it up a lot. That's quite useful. And then, I suppose, my final question — apologies for taking up the line with all these specifics — but regarding ventilation, for the latest 1925, raising to the upper levels. So that's scheduled for commissioning by year-end, with stopping planned essentially immediately after. So those vent trays will sort of open up the upper levels to a somewhat higher grade, and things like that as well. I just wanted to sort of verify that this remains the situation. Is anything else delaying it? Not delaying it, but is there a sequencing element regarding the stopping that's needed before you can access those upper levels, or once the vent trays are installed, can you commence some of your access drives and start stopping basically right after?
Raphaël Beaudoin
executiveAll right. So regarding ventilation, the bulk of that work was completed during 2023 and the early part of 2024. We have two ventilation trays: one running from surface to main level 2000, and another going all the way down to 1925 that exhausts directly at surface. So both of our main vent trays are finished, and we also have our entire secondary vent system in place down to 1925. As we move down toward 1900, we'll need the inter-level tray, which gets done very quickly, and we also have the secondary ventilation. So any — we've never encountered any issues with ventilation, because we're on a mountain and most of the upper levels vent directly outside. But for levels below 2000, we've finished the secondary shaft all the way to 1925, and we can rely on secondary ventilation at 1900 until the other trays are ready. And all the engineering for the ramp moving down is complete. So all of the engineering for sub-level 1925 is finished all the way down to granite, including electrical, pumping, vents, and service. So that's actually progressing very well. And no, it isn't a problem. It isn't something we figured out a long time ago.
Raphaël Beaudoin
executiveThat's fine.
Eleanor Magdzinski
analystAlright. Great. And then, yes, I suppose, the final question is on the — I think I noticed it in the press release. I just want to verify, what is the processing rate at present from the new plant? Like, things appear to be going quite well there since the ball mill adjustments and the re-commissioning of that whole spot. But yes, I just wanted to check what the current processing rate is.
Raphaël Beaudoin
executiveSure, I appreciate the question, Eleanor. Honestly, we’ve been putting out information on the mill ramp-up and no one had been asking, so I was eager to discuss it. So yes, let’s get into it. The crushing plant is running at full capacity. It has been performing as expected for some time now. Our milling rate is excellent. Commissioning is still underway, so I’m only referring to the milling rate here—the rest of the circuit still has to be worked through. We’ve hit 100 tonnes per hour. Availability keeps getting better each day. On milling rate, we’re actually above the main plant. So, we’ve been leaching for roughly a week now; a couple of weeks back, we commissioned the Merrill Crow, and we’ve been turning out our first silver cake for several days now. Last week we hosted the Boumadine site. The mill was operating and we ran silver ore. We’re very pleased with how commissioning is progressing and with the commissioning team. The whole team is working around the clock to get this going, and we’re very excited that we’ve begun producing silver cake. And there isn’t any real bottleneck. It’s simply minor tweaking and tuning and programming each day, and we’re very excited.
Raphaël Beaudoin
executiveAnd so we began manufacturing silver cake, and that week turned out to be enjoyable for everyone on the team.
Eleanor Magdzinski
analystThat's wonderful to hear. Yes, I'm glad I posed that question. No, since it was such a fast turnaround from, I suppose, the first announcement that some edits were needed — let's put it that way — to the whole mill circuit, and yes, that's really great to hear. It sounds like things are going quite well there, so. Yes, those were all the questions I had today, but thanks so much again for your time and for answering everything I asked, and all the best. Looking forward to speaking with you all next quarter.
Benoit La Salle
executiveI appreciate it.
Operator
operatorThank you. Ladies and gentlemen, at this point there are no more questions in the queue. I'd like to hand the call back over to Benoit for some closing remarks.
Benoit La Salle
executiveThank you. I really appreciate everyone joining, and thanks for the questions. Eleanor, thank you for asking about how the new plant is progressing, since ultimately that matters a great deal. And it is — we completed this construction on schedule, apart from, as I noted at the start, apart from the minor issue with the lubrication system. We finished it within budget. Overall, building a facility of this type in Morocco is remarkable. The expense is lower than anywhere else globally. And the plant is very sturdy. We have observed it. We visited this week and it is very sturdy. I think the ramp-up is continuing and it will be quite fascinating to see the capacity this plant will deliver. Now, one point Raphaël presented is that we have flexibility. We have three oil sources. We have the open pit, which is also delivering some very encouraging surprises. We took great care in building a stockpile. Our initial plan was 200,000 tonnes. By the close of the quarter, we stood at 357,000 tonnes. So we have roughly half a year, or a hundred and some days, of ore available that has already been mined and sits in inventory.
Benoit La Salle
executiveNext is the underground mine, and yes, it has to ramp up much like a plant does. But that work is underway. Capacity keeps increasing. I noted earlier that during Q4, in this quarter, we did achieve a single day of 1,600 tonnes per day. That isn't where we stand today, but we accomplished it. The teams are in place now. At present we have 1,300 employees on site. Those teams will still expand slightly. We talked about this this morning. We intend to grow the team, particularly for the underground mine. So flexibility in mining matters most. And the open pit is performing above expectations. Now, some of you who have visited site, we've been calling it an open pit. It isn't an open pit. What we mean is that mountain. The initial 200 meters sits above the base camp. So there is a mountain of 200 meters where the mineralization lies within the mountain. So right now we're meaning our way up that mountain gradually. We're only at the very, very first level, and the grade is good. We see extension. The contractor is performing very well, and we will raise the rate from 500 to 1,000 tonnes a day.
Benoit La Salle
executiveWe've got the stockpile, and underground is progressing upward—it keeps improving. As Raphaël mentioned, we intend to stay disciplined when it comes to mining, since that discipline matters enormously. And should we encounter lower-grade material, we'll remove it. We won't rush off to another stope just to chase a better grade—discipline in mining is essential, and we are highly disciplined. We're equally disciplined about health and safety. So when something appears slightly weak, or when we must pause briefly to secure the stope, we do so. Our health and safety record is very strong. We intend to keep it that way. Zero casualties. Our LTI is excellent, and we want that to continue. So here's a company that's well capitalized, with a plan that is 99.999 built, now coming to fruition—watch the latest video. It's beautiful. It's wide, it's open, it has room to grow, and it's nearly complete. Also—and the major story for Aya is exploration at site. We have somewhere between 16 and 17 drills turning.
Benoit La Salle
executiveAt times that small RC rig isn't rotating, meaning it lacks the power needed at Boumadine, yet it is an extremely — this is a really large program. Raphaël mentioned to us this morning that his team has 80 people carrying out exploration across Boumadine, Zgounder, and Zgounder Regional. So with 160,000 meters of drilling across numerous targets and structures, you truly end up with very, very strong results. Thus, as you watch the new Zgounder plan take shape, as you observe drilling carry on, exploration results carry on, and the stability of the nation where we operate — as you're aware, jurisdiction matters enormously in mining today, and we sit in what is likely one of the finest mining traditions worldwide. The team is highly driven to demonstrate to you and to the world just how robust that project is and will keep being. And regarding corporate social responsibility, we keep enjoying tremendous success. We'll release a video most likely next week about the saffron farms we sponsor. You'll see it's very, very pleasant, extremely fascinating, and that forms part of our social license offering. So that brings this Q3 call to a close.
Benoit La Salle
executiveThis isn't a quarter we're happy with, and we saw some of the notes this morning saying there's a miss on cost, a miss on production, and a miss on grade. But when you get right down to it, grade is the only real miss, because if you did miss on grade — look at throughput at the two plants, it's better than last quarter. Look at availability at the two plants: 96%. And on cost, we've capitalized development. So I agree this isn't a quarter we like, and we know it was a great issue, and we addressed that, and Raphaël explained why. And we believe that going forward, things are coming back to where they should be. Thank you very much. We'll see you in Q1 for the year-end call, where we'll have a full year of operation. Keep watching our little video. There will be more to come on corporate social responsibility and on the plant as well. And we look forward to keeping you informed. Thank you very much.
Operator
operatorThat wraps up today’s conference call, everyone. We appreciate your participation. You’re welcome to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Aya Gold & Silver Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Aya Gold & Silver Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Aya Gold & Silver Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.