Balfour Beatty plc (BBY) Earnings Call Transcript & Summary

March 11, 2020

London Stock Exchange GB Industrials Construction and Engineering earnings 57 min

Earnings Call Speaker Segments

Leo Quinn

executive
#1

Morning, everyone. This is Leo Quinn, Chief Executive of Balfour Beatty. We're here to present our full year results for 2019. First, though, there's a 2-minute video, since I believe it truly matters to grasp that this company undertakes a great deal of work — genuinely complex, inherently valuable work — and it's worth being reminded of that, and then seeing that it is this very work which delivers the figures we'll be discussing in a few minutes. <<presentation>>

Leo Quinn

executive
#2

Genuinely inspiring when you stop to think about it, and that's a wonderful thing. If you consider what lies ahead for Balfour Beatty, your mind goes to infrastructure investment around the world — this is a wonderful spot you ought to be considering, where your children can build their careers, since we undertake plenty of inspiring work, among it showing folks how to perform the Mexican wave. So, Leo Quinn, Balfour Beatty, Chief Executive. These are the 2019 full year results, and our Build to Last program is now beginning to pick up speed and produce the gains we have described. Over this year, we've seen some tremendous financial performance. And to my mind the real gauge of our business and our sector centres on cash generation, and our average cash across the past year has in fact risen by roughly 68% to GBP 325 million. We ended the year holding GBP 0.5 billion of cash on the balance sheet. Profits from our earnings-based businesses climbed by around 22%. And in total, we delivered roughly GBP 221 million, which takes in the asset sales on top of our earnings-based businesses. So broadly speaking, an extremely, extremely strong performance. We're also genuinely heartened by growth in our order book, which rose by around 13%.

Leo Quinn

executive
#3

Phil will walk you through that. For us, the U.S. was the market that grew the most this particular year. But when we actually add on HS2 next year, the U.K. backlog will actually double. So a very strong booking performance. And again, the strength of our balance sheet is very encouraging to us. It gives us confidence in actually increasing the dividend by some 33%. And we have lots of headroom within the balance sheet now, so that's encouraging for the future. Moving on and looking at the indicators behind Build to Last, we've always talked about Lean, Expert, Trusted and Safe. And for us, Lean is about cash in, cost out, but more importantly, investing in the platform for the future. And I'll take you through that in great detail later on in the presentation. We've used the measure of cash. And you can see back in 2014, the peak of the cash outflow was minus GBP 600 million. You can see this year in 2019 for the first time, the actual cash flow has been sinusoidal around the 0 mark. So we're now starting to generate cash, which backs our profits from our earnings-based businesses. So generally speaking, really encouraged.

Leo Quinn

executive
#4

This is consistently the real gauge of how the business is doing. When we turn to Expert — our definition being that we create a great place to work along with employee satisfaction — once again, the trend in that area has carried on, and we've seen another improvement. It's interesting that, looking at everything we're doing across the organization, we are in fact putting a lot into recruiting, bringing in new graduates and new apprentices, and training and retaining our people. And again, I believe this particular measure will speed up next year, because I sense the overall atmosphere inside the company keeps getting better. Trusted means no surprises when it comes to doing what we said we would do. I think we assume there should be no surprises, but it's quite interesting that in this industry over the last 3 years, surprises have outnumbered good news. We gauge this through our customer satisfaction. We set 95% as our goal. So being at 94% doesn't surprise us. So good performance there. And then finally, Safety for us is our license to operate. And as you can see, we've cut our safety statistics in half over the last 5 years.

Leo Quinn

executive
#5

We've been able to keep those gains through 2019. That matters a great deal to us, since it isn't just about our people — it's also about members of the public and the customers we serve. So Safety is the number one measure for the business right now, and it will be going forward too. What I find interesting about this chart is that we can look at 2019, but really, when you examine the 5-year trend, it's a genuinely impressive trend, and these are truly the leading indicators. That gives me confidence that as we look toward '20 and '21, we'll keep seeing further improvement. Then, if I turn to what I think of as the lagging indicators — and this is essentially what you can check on our balance sheet, where you can see these numbers and see this performance — we have a 5-year record of year-on-year improvement. So looking at our average net cash, back in 2014 we were overdrawn to the tune of GBP 371 million. Today we're actually sitting in net cash in our bank of GBP 325 million. That's a difference of nearly GBP 700 million, which lines up with the Lean graph you saw. As for our earnings-based businesses, we were at a loss in '14.

Leo Quinn

executive
#6

We've reached a profit of GBP 172 million now. And once more, I believe this is going to begin speeding up. If I look at overhead — that's corporate overhead for the worldwide operation, the whole of it — we cut it effectively by GBP 200 million, taking it from GBP 465 million down to GBP 267 million. That's interesting on its own. But what's genuinely interesting is what has taken place beneath that. This GBP 267 million is arguably the most productive resource the company has today. And I'll go into this in somewhat more detail, since it truly is a source of competitive advantage for us and is the future lever that will actually cause our returns to accelerate. And then in the end, we employ people, and we want to retain them in the business. Attrition stood at 16% back in '14. It's down at 11% now. We track this monthly, and through this year we're now below 10% on a monthly basis. So in essence, Build to Last has delivered 5 years of progress, and we see it accelerating into the future. Phil will now walk you through some of the financial facts, and then I'll return and tell you a bit more about how the business has performed.

Philip Harrison

executive
#7

Thanks, Leo. Good morning, everyone. Let's turn to the headline numbers. As Leo mentioned, these results show the financial strength that Build to Last is delivering. We'll go through all of these figures over the next few slides, but as Leo said, I'm especially pleased with average net cash, which is up 68% to GBP 325 million. In this industry, you have to operate with average net cash, and this result supports the strong financial position we've built. The order book, excluding HS2 orders, has risen 13% to GBP 14.3 billion, and every profit metric shows improvement: profit from operations is up 8%, profit before tax up 10%, and earnings up 4%. Earnings were affected by a higher tax charge. The tax increase was driven by geographic profit mix and U.S. investment disposals. Looking ahead, the effective tax rate you should apply for the U.S. is around 27%, and for the U.K., half the statutory rate. Given this performance, the Board has recommended a full year dividend of 6.4p, a 33% increase on prior year. We're now operating from a position of strength, with the financial flexibility to seize the market opportunities we see ahead, which Leo will discuss later.

Philip Harrison

executive
#8

Let's turn to the detailed results now. Within the earnings-based businesses, underlying profit from operations rose 22% to GBP 172 million, and that fed into an 8% rise in the group's overall underlying profit, which reached GBP 221 million. Breaking that down, construction services stood out, climbing 32% to GBP 125 million, with a 68% improvement in U.K. construction to GBP 47 million providing support. Support Services, as we had anticipated, came in level with the prior year. Meanwhile, after the sizable disposals made in 2018, infrastructure investments saw profit from operations fall to GBP 82 million. Turning to the order book, it grew 13% across the year overall, and a strong order rate in U.S. construction drove that result. The most noteworthy award came in the U.S. — a $1.7 billion road project, LBJ East in Dallas, in which Balfour Beatty Civils holds a 45% share of the joint venture. The buildings business order book also grew, as the Northwest division booked additional high-tech office work and the Florida division secured a contract to expand the Broward County Convention Center. Crucially, the quality of these bookings matches our policy of bidding selectively for projects that align best with our capabilities.

Philip Harrison

executive
#9

In the U.K., the HS2 main civil works and Old Oak Common station contracts are still outside the order book at this point. They'll be added only when the main civils works contracts are finally signed, and after the recent U.K. government approval, that's now expected during the first half of 2020. The group anticipates booking more than GBP 3 billion of orders tied to these HS2 awards, and once included, the U.K. order book will more than double. Over at Support Services, the order book rose 14% to GBP 3.2 billion, driven by growth in transportation — specifically the Central Track Alliance award from Network Rail, where we've booked GBP 0.2 billion so far, and the RIIO award of the London underground maintenance contract. Let's now go through each segment in more detail, beginning with Construction. In the U.K., revenue was up 16%. For the first time, it has grown under Build to Last. Profit from operations rose to GBP 47 million, with a related PFO margin of 2.1%. In the U.S., revenue was up 13%, or 8% at constant exchange rate, reflecting the order book increase during 2018. Profit from operations rose to GBP 52 million, with a related PFO margin of 1.4%.

Philip Harrison

executive
#10

Revenue at Gammon held roughly steady, and more significantly, operating profit rose to GBP 26 million. Moving on now to Support Services. As anticipated, Support Services revenue fell 7%, reflecting reduced volumes in the power transmission and distribution business along with the completion of the area 10 highways maintenance contract. Crucially, profit from operations held steady at GBP 47 million, and the PFO margin for the year climbed to 4.6%. Let me break the constituent parts down in somewhat greater detail. In power, the business is now picking up speed after a substantial restructure and cost removal, and it secured notable new contracts during the year, among them Hinkley Point overhead lines and the Viking Link interconnector project. In gas, the group is still managing long-term gas contracts in the RIIO-1 period, which have historically underperformed. The gas market is no longer viewed as viable for the group, given the unfavorable working capital and onerous terms and conditions. On that basis, Balfour Beatty will not rebid these contracts under RIIO-2, and the decision produces a noncash, nonunderlying goodwill impairment of GBP 58 million in 2019. The water business is now approaching the end of the current U.K. water regulatory cycle, with bidding under the new AMP7 regulatory period underway.

Philip Harrison

executive
#11

Once more, the group will bid for work only when the terms and conditions satisfy what the group regards as its minimum expectations. In transportation, the highways market underneath is performing well, and several local authority contracts are arriving on the market. As for rail, as was said earlier, our track partnership contract with London underground was renewed at the beginning of 2019. And in March, the group was chosen for the 10-year GBP 1.2 billion Central Track Alliance contract. Turning to infrastructure investments. This business carries on with its strategy of optimizing value by disposing of operational assets, while it also keeps investing in fresh opportunities. After significant disposals in 2018, underlying profit from operations fell to GBP 82 million, with both predisposal operating profit and profit from disposals below the prior year. Notwithstanding that decrease, I want to draw attention to the GBP 69 million of profit on disposals, which were sold at or above directors' valuation. The timing of asset sales is invariably uncertain, and the outperformance in the last month of the year gave 2019 results a boost. Completing more deals in 2019 could potentially have a knock-on impact on 2020. We stay focused on maximizing shareholder value across the full investment portfolio life cycle rather than on when individual transactions occur.

Philip Harrison

executive
#12

We’ll have a clearer picture of the disposals we expect in 2020 when we report half-year results in August. It’s worth keeping in mind that the investment portfolio sits at the heart of the group — an asset base that keeps regenerating and connects with our construction and support services operations. The group still sees chances to put money into high-quality projects that deliver good returns. In the U.S., the emphasis is on student accommodation, multifamily housing and public-private partnerships. In the U.K., student accommodation is the main focus. Turning to the directors’ valuation: looking at what moved, we put GBP 64 million into new and existing projects, while cash yield from distributions came to GBP 65 million. Proceeds of GBP 102 million from 10 asset sales were largely offset by the discount unwind, so the factor behind the fall in the directors’ valuation overall to GBP 1.1 billion was operational performance in the group’s military housing portfolio. Let’s look now specifically at U.S. military housing. We recognize that operational challenges have arisen within the portfolio. Together with the Air Force, we have agreed a Performance Improvement Plan for Tinker Air Force Base and the wider portfolio, and we are making headway in resolving those operational issues.

Philip Harrison

executive
#13

Several initiatives laid out in the plan are now finished, among them a substantial management and restructuring effort to better align technical support with resident services, plus the appointment of a Transformation Director. An investigation was opened last year by the Department of Justice, and it remains ongoing. As a result, the group cannot indicate what the outcome will be, whether in terms of timing or any quantum. Turning to the directors' valuation of the military housing portfolio, assumptions such as future rental income, project costs and incentive fees were reviewed project by project. Two items have affected that valuation. The first is operating costs. Higher costs were agreed with the military, in part to improve the housing experience for military families and in part to cover increased insurance costs. When costs rise, the equity cash flow splits and the renovation and development fees for the group come down. The second is incentive fees. Compared with the historical agreements, the prospective incentive fee metrics carry a larger discretionary portion. Given no clear track record in the current environment, the group has adopted a conservative stance on the assumptions for the discretionary element of incentive fees. Together, these 2 items produced a GBP 69 million reduction in operational performance, which helped drive an overall year-on-year decrease of GBP 79 million in the valuation of the military housing portfolio.

Philip Harrison

executive
#14

Now let's go to the slide after this one. Here we're showing how disposals have gone since 2015. You've seen this presentation before. It's an updated version of that slide, simply to refresh everyone's memory. Every bubble stands for 1 disposal. How big the bubble is reflects the sale proceeds we received. The bubble's color tells you if the asset went out above the directors' valuation or not. Dark blue means it went out above directors' valuation. Over on the left-hand side of the graphic, we show the end-to-end multiple for each project when it was disposed of. What the graph tells us is that the group keeps finding a strong secondary market for its investment assets. We'll keep investing so as to generate future asset sales wherever we spot the chance to hit the multiples this portfolio has historically delivered. As you can see on the following slide, the portfolio stays a long-term source of value. That slide displays the expected annual cash flow from our investment portfolio. The left-hand axis in fact displays, in blue, the forecast cash distributions to the group across the next 20 years, and in orange, the committed equity investments across the next 5 years. The right-hand axis displays the projected directors' valuation of the portfolio at each point in time.

Philip Harrison

executive
#15

Two things stand out to me about this graph. First, the lengthy lifespan of the assets in the portfolio, with cash distributed back to group of over GBP 70 million for the next 20 years. And should we do nothing — meaning no new projects, but no disposals either — the directors' valuation is expected to stay above GBP 1 billion for the next 20 years. As I said earlier, we will keep managing this business with a view to investing so as to maximize group return. In 2020, we'll invest circa GBP 50 million, and we will continue to make the appropriate timings on disposals through 2020 and beyond to maximize value. Now if we move to cash flow. As I mentioned in my opening remarks, I'm particularly pleased with our cash performance in 2019. As you can see from the waterfall, in 2019, we have generated a total cash flow of GBP 175 million, increasing the group's net cash position to GBP 512 million. The increase is driven by GBP 213 million of operating cash flows with working capital as expected broadly neutral. I said previously that working capital would be plus or minus GBP 20 million to GBP 30 million in 2019, and I'd expect a similar outcome in 2020.

Philip Harrison

executive
#16

Given the uncertainty we're facing right now, having a robust cash position and balance sheet gives us some reassurance that we possess the financial flexibility needed to navigate through this. Thank you. I'll now turn things back over to Leo.

Leo Quinn

executive
#17

Thanks, Phil. As everyone knows, we started Build to Last roughly 5 years ago. What Build to Last is really about is building a platform for what I describe as the coming 100 years. This isn't a sprint — it's a marathon — and it comes down to how we get better each day inside the company. That is genuinely the foundation on which we're constructing what I see as a scalable platform for the business's future. I mentioned that we spend GBP 260 million on corporate overhead, and I spoke to the efficiency and effectiveness of that spend. The sorts of things we count within that, and what we've delivered over the last 5 years to make it possible, include, for instance, running our U.S. and U.K. organizations on a single instance of Oracle -- or JD Edwards in the U.S., Oracle in the U.K. We implemented what is effectively a standard risk and estimate review process that we call a GTIC, and that ultimately results in a project on a page. And as of today, we have 1,200 projects across the company, which are managed with the touch of a screen, and you're able to see the financial performance of that.

Leo Quinn

executive
#18

Frequently, through data analytics, I'm aware a job is heading off track even before I sit down and go over it with the crew assigned to it. On the supply chain side, we've started making some aggressive cuts to our supplier base. We're also rolling out platforms such as Jaeger, which gives us software procurement at a highly sophisticated level. And once again, that's generating efficiencies throughout the organization. Earlier I mentioned our IT organization. Right now, roughly GBP 48 million goes toward keeping it running. If I go back -- we had no figures for 2015, but we estimated around GBP 110 million in cash was being spent each year. And everyone was firmly in agreement on one thing: it didn't work. These days it works seamlessly and very effectively. All of this means we have a platform where, as the business expands, our revenue will increasingly drop through to the bottom line at a faster rate than is the case today. That's going to be crucial as I begin to lay out where our growth opportunities lie. Looking at U.K. performance, the U.K. has enjoyed a good year.

Leo Quinn

executive
#19

As you can tell from the profit, it nearly doubled over the past 12 months. Still, our focus remains on what are effectively some very strong clients, and on building and deepening those relationships. Take clients such as the Scape platform, which enables a single action tender, so the client can carry out an ECI and work directly with us in negotiating the final outcome of the job. Highways England remains one of our biggest customers, and we won 2 areas in the RIS, meaning the Road Investment Scheme program — the north and the south — and that will produce a number of road projects over the coming few years. Every one of these customers is very enlightened. Another thing we are noticing is that, beyond continuing to win major contracts with very stable, reliable clients, we are also seeing that the industry has shifted slightly over the last few years. In particular, with the loss of Carillion — or the demise of Carillion — what we are seeing is that the whole industry effectively lost a competitor that was in fact a low price bidder but also had a very weak balance sheet. We are now seeing prices normalize and the terms and conditions improve.

Leo Quinn

executive
#20

Regarding Balfour Beatty, we've gained directly from Carillion's collapse 2 years ago. Their joint venture stake in the A14 was taken over by us. We've secured road contracts in Leeds — the Orbital Road. We just closed on the Midland Met hospital, a Carillion PPP worth GBP 267 million. We're not delivering it as a PPP. And our contract is far more sensible. So broadly, the orders we keep investing in and winning come from clients we have tremendous confidence in — strong, dependable brands. Looking at future prospects and at Heathrow, there's considerable debate around the third runway. Let's set that aside for now, since it will be settled over the coming months or years, but Heathrow will spend another couple of billion over the next few years on Terminal 4 and Terminal 2 upgrades. So they are a very, very large client. We've held a framework agreement with them for some 16 years. So we're deeply embedded and supportive of what they're trying to do. And we're regarded as a really good supplier.

Leo Quinn

executive
#21

On other infrastructure efforts, like the Lower Thames Crossing, ground investigation work is underway right now, and that scheme will probably move forward over the coming 2 years or so. So our position there is solid. But the real centrepiece for us is largely HS2, and what I'll do is walk you through it in somewhat more depth and lay out what I see as the upside as well as a few of the risks. HS2, as you're aware, we've mentioned previously, we've been awarded 2 sections on the program so far. Those are the Birmingham sections N1 and N2 plus the Old Oak Common section located just outside London, or in London. N1 and N2 come to roughly GBP 6 billion, and there we serve as the construction deliverer. In other words, we're the construction company carrying out the work. It's a joint venture with VINCI on a 50-50 basis. And for Old Oak Common, we're in fact the construction manager. That means a fee-for-service arrangement, a somewhat different contractual setup, a somewhat smaller fee, yet also far less risk. When we consider these particular contracts, one very important thing has to be watched carefully, and I believe it is a risk, namely that we operate an GBP 8 billion organization today, and what we're going to do is stand up a GBP 6 billion contract alongside a joint venture partner.

Leo Quinn

executive
#22

It isn't accomplished without significant effort. This is really the point where the scalable platform we've deployed throughout the organization will demonstrate substantial advantages, since it will essentially take our current operations and replicate them inside an entirely distinct instance, establishing that as an independent company. As we proceed, caution is essential. A few weeks back we held a meeting, and it was fascinating — 9 of my direct reports were seated around the table. We were examining how to support the mobilization of N1 and N2. What struck me was that everyone's attention was on the new growth opportunity, the shiny object right in front of us. Yet those 9 individuals currently run a GBP 8 billion company very effectively. So we must be careful, because the finest business we have is the one we have today, and our focus needs to remain there. And we need to establish this in a separate manner. The excellent news is that, thanks to standardized processes, systems and governance, I believe we can accomplish that with relatively strong confidence in that area.

Leo Quinn

executive
#23

Looking ahead, our rail division has expertise in track, catenary, and electrification work that's likely worth an additional GBP 300 million to GBP 500 million, and we'll be actively bidding for that. Beyond that, you can see the route up to Leeds by road or rail and onward to Manchester — we'll definitely have an interest there. That said, I think the immediate priority is getting delivery underway on the projects we've secured today. This will be transformative not just for the U.K., but for Balfour Beatty as well, and for our industry too. So there will be some very interesting challenges ahead, and it isn't without risk. What matters, I think, is being aware of those risks and anticipating them. But I believe we're well placed to clear that first hurdle effectively. Turning to our U.K. support services, Phil has given you much of the detail there. What I'd say — and I think this is really important to note — is that the work we've won here is largely with customers we've had relationships with for a long time: Network Rail, London Underground, National Grid. Our relationships with those customers, and how we work and deliver, are very effective.

Leo Quinn

executive
#24

And I think they'd likely see us as one of their top suppliers — maybe even the top one. So the future here genuinely lifts my spirits. What we have to focus on is getting out of the gas market. Phil mentioned this, but that contract was effectively won by us 6 years ago. And we've had GBP 30 million to GBP 50 million of working capital tied up in it. And our economic value-added after the cost of money has been 0. So in effect, from day 1 it's been a bad contract for us. And so we won't be carrying on with it. The good news is that once we get past 2020 into 2021, we're talking about average industry standard margins of 3% to 5%. I see this business moving above the upper level of those limits. And I think it will contribute very strongly to the group. So what we're doing in this business encourages me. If I look at the U.S., this is a real transformation story. The U.S. is about GBP 4.5 billion of revenue, and about GBP 4 billion of that is actually in our buildings business. And our buildings business this year has probably had its best year since 2013.

Leo Quinn

executive
#25

And it has basically delivered on every single measure. It's grown the business substantially. Revenue is higher. Profitability is higher. Cash flow has gotten better. So broadly speaking, we are definitely picking up market share and doing so very effectively. Every one of the branches — whether that's Seattle in the Northeast and Portland, whether that's San Diego, Dallas, Florida, the Carolinas or Washington — each of those branches has come in at or above budget. So a very encouraging picture. Now it's a tale of 2 cities here, because on one hand our buildings business has done very well, while our civils construction business has gone the other way — a very poor year, I'd say. The difficulty we've faced in that business is that we have a number of contracts, roughly 18. They're large in nature, and we've kind of failed to deliver against the job schedule. Because we're behind on schedule, we're then behind on profitability and on profit recognition. So our civils business has had a very challenging year. We've taken a number of corrective actions, and those will see it improve next year. We shut down our local rail support business, which was a small business but a big distraction for management.

Leo Quinn

executive
#26

Our attention now is on the six jobs that will matter most when it comes to producing future profit. Still, taken as a whole, the net result in the U.S. is a highly encouraging year, with an outlook that is equally encouraging. Turning to Hong Kong, as you're aware, this is the joint venture we hold with Jardine Matheson. It's a 50-50 split. This business defines itself around big infrastructure projects. The mix is 60-40 between buildings and infrastructure. A great deal of building is taking place here. Links through to China. A major hospital program is underway right now. And the airport is continually being developed. There are 2 terminals we are bidding for over the coming year or 2. So we are very eager to keep up our presence and the returns we earn from China. We've been successful in winning the advanced manufacturing center, and then the 10-year residential program development in the new territories. Broadly speaking, this is a well-run business that keeps producing returns of 3% after tax, yet it genuinely takes on very large projects. And clearly, handling a few large projects rather than a lots of small ones always brings a challenge.

Leo Quinn

executive
#27

Let me just remind everyone that we do have what I'd call a risk-adjusted portfolio, and we're diversified both operationally and geographically. As far as our construction business goes, right now slightly less than half comes from the U.K., yet more than half is actually denominated in dollars. That's going to shift over the coming year or 2, with HS2 here in the U.K., and we'll see the balance swing back to favor the U.K. more. Turning to our investment portfolio, once again more than half of it is dollar denominated across the group. So basically, we're strong in 3 markets: Hong Kong, the U.K. and the U.S.A., and that gives us a degree of comfort that our portfolio really is diversified geographically and operationally. Finally, a look at where we stand. Build to Last has been a program alongside us for the last 5 years. It will remain with us for the next 5 years, and it keeps delivering the returns. The scalable platform we've put in place has still to accelerate those returns, but given the top line revenue, we're confident we're going to see that a greater proportion of profit will now drop through to the bottom line.

Leo Quinn

executive
#28

Our culture is built around handling risk in commercial terms. That means we won't initially accept a contract we believe we can't deliver while earning the returns we need from it. A rising tide is what I see ahead of us, with a strong infrastructure market across every geography where we operate. So what happens with the top line encourages me a great deal. Cash is the only thing we really watch. Nothing else in the business tells the truth the way it does. And we've actually been delivering what I consider improving cash returns, which gives us confidence about our dividends. It also leaves us enough headroom on the balance sheet to review what future cash distributions we'll make as a company. So Build to Last has been extremely successful to date, in my view, and we're now beginning to see those returns accelerate. So a good year result, and I'll hand over to you for questions.

Leo Quinn

executive
#29

Howard, a microphone is on its way to you. Joe?

Joe Brent

analyst
#30

Sorry about that. I have 3 questions, if that's alright. First, regarding today's budget — I realize nobody has seen its contents yet, but what would you be hoping to see in it? And what ought we to keep an eye out for? Second, on High Speed 2, you mentioned some of the risks briefly. Is there anything further you can tell us about the contract terms and how the structure is likely to work regarding working capital and risk sharing? And third, could you just provide the sales figures for the gas business, please?

Leo Quinn

executive
#31

Alright, that's done. Yeah, what we'd hope to see in the budget — I mean, above all else, the one thing that matters most to us is a 10-year runway that lets us put money into assets, capability, and people. So if we could get some reassurance about how much will be spent and what kind of spend it is, that would be very, very reassuring. Honestly, that's really all I'd ask of the budget, and I'm optimistic it will be delivered. On HS2, I'm glad that question came up, because I'd meant to bring it up. I have to say that HS2, in my view, is a fairly enlightened customer. What they've come to realize is that the budget they're working with to build HS2 means they can't simply push down the risk — or all the risks tied to it — because if you ask the contractor to price risk, the price goes up considerably. So I think their approach to where risk gets assigned is very balanced. From where we sit, the contract for N1, N2 is effectively a guaranteed fee. And if we perform early, deliver early or on budget, that fee can rise by a couple of points.

Leo Quinn

executive
#32

If we're actually running late or over budget, that figure can drop by 1 point. So there really is a cap on the guaranteed return that we have. From where we sit, we see it as a well-balanced contract. I'd call it quite mature. And it's going to depend heavily on the client and the contractor working closely together. So I'd say that's a positive for the industry.

Joe Brent

analyst
#33

Just to clarify that — when you mention a decline of 1 point, do you mean 1 percentage point?

Leo Quinn

executive
#34

One percentage point. So if you're talking about a fee that was, say, a large figure of 20%, it isn't — but if it was 20%, you could go down to 19% and up to 22%.

Joe Brent

analyst
#35

That sounds good.

Philip Harrison

executive
#36

Yeah, you're dreaming once more about <<inaudible>>.

Leo Quinn

executive
#37

However, if it were 8%, then it would move up to 10% and fall to 7%, roughly along those lines. That's right. As for the fee itself, I believe we haven't disclosed that figure.

Executive

executive
#38

That isn't something we intend to do.

Leo Quinn

executive
#39

Understood.

Joe Brent

analyst
#40

And then the third one, about gas sales?

Leo Quinn

executive
#41

Yeah, on gas revenues...

Philip Harrison

executive
#42

Roughly GBP 100 million — around GBP 100 million to GBP 120 million.

Leo Quinn

executive
#43

One quick clarification: this applies only to the U.K. gas business. We're strongly behind what's happening with G&I, the Irish gas business. Howard?

Howard Seymour

analyst
#44

Howard Seymour from Numis here. I have 3 questions, if I may. First, I just want to note that you mention the central costs, which have come out fantastically in terms of where we stand at the moment. But since we're now beginning to see revenue increase, should we expect to see some element of increase in that area as well? You clearly said you expect the drop-through to be good, but would you expect to be able to contain those costs against what is now a growing company as opposed to a shrinking company?

Leo Quinn

executive
#45

There are two additional ones.

Howard Seymour

analyst
#46

Turning to the second item, the DV valuation, you referenced the 2 factors affecting military housing. Regarding the first, you stated that, in effect, discussions are underway with the military. On the second, incentive fees, I wanted to ask whether that is likewise what you expect will occur with incentive fees, or whether it too has been part of talks with the client? And then thirdly, just to clarify, Leo: you said the civils corrective actions would deliver an improvement next year. Does next year mean 2020 or 2021?

Leo Quinn

executive
#47

Understood. I’ll take 1 and 3. You’ll handle 2?

Philip Harrison

executive
#48

Correct.

Leo Quinn

executive
#49

First, this isn't a fluke — we've genuinely stripped roughly GBP 200 million out of overhead, one step after another. You can't save your way to success. But what I'd stress is that as revenue grows, we don't feel any need to grow corporate overhead along with it. So in effect, more of each extra pound will drop through to the bottom line. Obviously, if you're actually going to deliver a GBP 6 billion joint venture job, there will be some increase. But from where I sit, it stays at a marginal level — not substantial. So I think that puts us in a very, very strong position. And the reason we're able to do this, incidentally, is that we've automated a great many of the systems. Because of that automation, pushing through another 1,000 invoices or handling another 500, 600 people doesn't cost you much extra. On the civils side, I think some of those gains will clearly show up in 2020, with even more arriving in 2022. And they'll stem from the fact that we'll have caught up on our schedule and will be in a position to recognize the profitability tied to those points.

Leo Quinn

executive
#50

Additionally, the disputed items should get worked out during 2020. So I expect that to show up marginally in 2020 and more substantially in 2021.

Philip Harrison

executive
#51

Regarding item three — or item two, the DV valuation incentive fees — we've held talks with the service branches. Each is at a different point in finalizing their incentive metrics. A few are further along, and in fact, we've already settled those with them. Others lag a bit. So we've booked what we expect those conversations to produce. That said, yes, there has been dialogue with the military.

Andrew Nussey

analyst
#52

Andrew Nussey here from Peel Hunt. I have a couple of questions. To start with, regarding the U.K. construction margin: as it moves ahead from this point, how much depends on truly expanding that cost base you mentioned — that is, growing the top line — versus what can still be gained through improved bidding and sharper operational focus? And second, on capital allocation, which external events are shaping your thinking as you move forward? That applies both to what could go into the investments portfolio and to what could be returned to shareholders.

Leo Quinn

executive
#53

We’ll defend those. I’ll take the first one, and Phil can handle the second. Why don’t you start with the second one — it’s the more interesting one?

Philip Harrison

executive
#54

No, you take the first one. I want to give me a chance to get me answer right.

Leo Quinn

executive
#55

On the U.K. construction side, if you look at bookings, we’ve actually increased them this year except in highways. The sole cause we haven’t increased highways is that the awards fell in the previous year. So they’ll flow through a thin year in ’19 and then a stronger year in ’20. Revenue has gone up across the whole business. And what disappoints me is — I’m very focused on this — I would rather run a small profitable business than a large medium-profit business. So the emphasis we want is really on lifting our returns, and that boils down to signing better contracts, securing better pricing and actually delivering better. So what I see is that the improvement in our U.K. construction business, across the board, stems from those 3 factors. As for the cost base supporting it, I think some gains can be made there, but I think that shows up more in the margin. So I think we’re sort of — we’re getting to — you’ll recall, we had 89 distressed projects, a number — 85 distressed projects. I think we have 2 or 3 lying around, which hopefully will disappear — and I think it’s 4, which will disappear over the next 12 months.

Leo Quinn

executive
#56

And that's really where you'll begin to notice better returns coming through. It's going to show up on the margin side. As for growth — I mean, growth isn't a constraint for us at all. We could bring in plenty of business; what matters is bringing in the right business.

Philip Harrison

executive
#57

Let's talk about capital allocation.

Leo Quinn

executive
#58

You can take the lead on this one, and I’ll follow along correctly.

Philip Harrison

executive
#59

All right, I'll take the lead on this, and you can jump in if I get anything wrong. Regarding capital allocation, it's clear that if you look at how we've performed over the past couple of years, we've now sorted out the balance sheet where debt is concerned. We have some preps to remove at the half year in July. So we're happy with how we've done on cash and with the position of the balance sheet. Obviously, we've stated that we intend to keep investing, and we will keep investing in our investments business. We view that as an excellent method of boosting our returns and boosting returns for shareholders. So that will remain a component of the allocation toward it. And then, as we said in our press release, the Board intends to review the capital structure once we're past this short period of uncertainty caused by COVID and examine it as a whole — how much capital do we require, and how much capital might we consider it possible to redistribute. So that's where our thinking stands right now.

Leo Quinn

executive
#60

On the flip side, I want to bring up the Aberdeen peripheral road for everyone. That was a PPP, sold for GBP 533 million, and I believe it delivered GBP 1.2 billion. Picking up back contracts isn't difficult. That's why we've taken an extremely careful approach when it comes to entering PFIs and PPPs. And plenty of those exist out there. So you can appreciate that. Right now in the U.S., I believe we have LAWA, the LAX people mover. We also have the student accommodation in Raleigh, North Carolina. So there are a handful where we believe we can genuinely collaborate with the client effectively to produce a good result for both sides. All the capital required to invest in those, we have it, and we're putting it to use, but we won't deploy our capital to charge in and snap something up just for the sake of growing the business. What I mean is, if the terms aren't right and we can't see the right return, we won't proceed. And we have a few selective projects in the U.K. where we're executing them very successfully.

Leo Quinn

executive
#61

Looking back over 5 years, I could show you a list of PFIs and PPPs that delivered fantastic investment returns, yet those were simply awful construction projects. These days, we ensure the rule applied to all of them is that they're profitable for us. Because naturally, if you're losing money on the construction of the PPP, all you're doing is injecting additional equity, right? So your equity ends up being whatever you believe it to be. And therefore, I think you'll have to characterize us as tending to err on the side of caution. I'm sure we'll make mistakes. But ultimately, we'll simply make fewer of them, which will place us ahead of the rest of the competition.

Executive

executive
#62

A few questions have come in via the webcast. The first comes from Gregor at UBS. There are 4 questions. The first one: what's the run rate for your annual revenues from HS2? And within that 2% to 3% range, what margin do you expect? Second, how would you quantify your excess capital position? In your view, what average cash do you need to hold? Third, what do you expect your average net cash position to be in 2020? And finally, he asked what your worst-case outcome is regarding the U.S. military housing situation?

Leo Quinn

executive
#63

Well, that's difficult enough...

Philip Harrison

executive
#64

We aren't going to keep accepting webcast questions — practically speaking, I'm not willing to do that.

Leo Quinn

executive
#65

I was just going to say those are easy enough that Phil can take them. As for the HS...

Philip Harrison

executive
#66

You can start us off.

Leo Quinn

executive
#67

Yes, and unfortunately those are lengthy questions. On the HS2 item, I’d put it this way: if you’re considering average revenue, my expectation is that we begin in year one at roughly GBP 500 million. By year 3, we would move up to GBP 1 billion, and then stay at GBP 1.4 billion for 2 or 3 years. So that’s approximately where we’ll be with HS2. That figure is at the joint venture level, actually. So we account for about half of it. As for returns, I believe margins of 2% to 3% are the industry standard. What I’d call the bottom line range would sit at the 3% to 4% level, assuming we can capture the advantages of our scalable platform, and we are confident that we will.

Philip Harrison

executive
#68

I apologize for the <<inaudible>> every time.

Executive

executive
#69

Yeah. We did discuss excess capital, but to get specific, what amount of average net cash do you think you need to keep on hand? And in 2020, where do you expect your average net cash position to land?

Philip Harrison

executive
#70

Well, look, it's too early to do the first question. Obviously, the Board is going to make that determination through the capital structure review, which will factor in the average net cash we'll need to hold. As I keep saying, we will always hold a level of average net cash. That's how this business needs to be run with average net cash, so we'll get that appropriate thing. But that will be reviewed with the capital review. On average, net cash this year with the press coming out, clearly, that will have an impact because that's not in our average net cash numbers. So I would say we're currently thinking GBP 300 million, GBP 330 million is the range.

Leo Quinn

executive
#71

Yeah. And I think another point worth keeping in mind is that as infrastructure expands — and that's mostly treasury-funded money — there's a tendency to shift toward project bank accounts. Once you go down the project bank account route, your free cash flow really amounts to just the profit on the job, since the cash essentially flows in and straight back out. So I'd say it's somewhat of a moving piece. We simply have to be cautious, because you do need that headroom — these days, if you look at most players in our sector, you'll see a cash flow figure or a net cash number, but then there's the net cash you can actually spend, and that's probably around 65-35, meaning nearly 2/3 of it is locked up — sitting in project bank accounts, joint ventures and the like. So your cash flow is a bit more complicated than it first appears. But being aware of that means you just find a way to handle it.

Executive

executive
#72

And then the last item—what would the worst-case result be for U.S. military housing?

Philip Harrison

executive
#73

It's not possible for us to put a number on that statement — we just don't know.

Executive

executive
#74

Alright, thanks. Here's another one from Marcin Wojtal at Bank of America. He has 3 questions. The first one, you might have already addressed it, but I'll go ahead and ask it regardless. Are you expecting the HS2 contract to be accretive to margins in U.K. construction?

Leo Quinn

executive
#75

Yes, that’s correct.

Executive

executive
#76

All right. Moving on to the next question. Did the U.S. civil construction business turn a profit in 2019?

Leo Quinn

executive
#77

No.

Executive

executive
#78

Third question: what steps are you taking so that business continuity is ensured if COVID-19 causes potential disruption?

Leo Quinn

executive
#79

Yeah, we’ve gone over this one for roughly a week, so I’m glad someone raised it. Yes — above all, we take the virus — the COVID virus — very seriously. And we — I have to give the Board credit, because we had a really, really interesting discussion about the company’s capital structure and what was happening in the markets and that sort of thing. We have a standing committee that meets on Tuesdays and Thursdays, and its purpose is really to watch everything going on with the coronavirus, any effect on the supply chain and similar matters. We’re watching for any shortage of supply. Right now, every one of our sites is open. They’re all operating. We see no shortage of supply, except — this is quite interesting — in 2 cases at the moment. One is actually on a power job where the pylons are coming in from China, but that’s fairly far out ahead of us, so we’re not worried about that. And the other is actually shipping testing engineers from India — not, from Italy to — in order to test a cable that we’re connecting to France. So it’s quite interesting that we’ve got it down to a level of granular detail where we actually know where some of the risks are.

Leo Quinn

executive
#80

Additional risks are going to show up sooner instead of later. Much of the supply chain we have in the U.K. is fairly local, since when you're working on roads, concrete, and earthmoving, you don't bring in most of those materials from abroad. That said, when it comes to Hong Kong, aggregate imports are giving us problems right now. So that's a difficulty. And to make Phil look truly great, Phil can tell you the count of contracts we hold across the U.K. and U.S.A. where force majeure applies. In the U.K., force majeure covers 76% of our contracts. If we're compelled to shut them down, we'll be granted time, though not money. In the United States, I believe the figure is 85%, and there we'd receive time rather than money. So we've reviewed all of this. Yet despite everything we've done, I'm confident that what actually comes up will be something we didn't plan for — but we're nimble and we'll react the right way.

Executive

executive
#81

Thanks. I don't see any further new questions coming in over the webcast. Does anyone else in the room have one?

Leo Quinn

executive
#82

Thank you, everyone, for the time you've given us and for sticking with us. We appreciate it.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Balfour Beatty plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Balfour Beatty plc earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Balfour Beatty plc or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.