Balfour Beatty plc (BBY) Earnings Call Transcript & Summary
August 16, 2023
Earnings Call Speaker Segments
Leo Quinn
executiveGood morning, everyone. Looking at how many people are here, it seems you all put off your summer break just to catch these results. I'm Leo Quinn, Chief Executive of Balfour Beatty. With me is Philip Harrison, our Chief Financial Officer. We're going to walk you through the half year performance. Above all, a strong first half, and the progress achieved has come in the areas where you'd want to see it. As you know, earnings rose about 12% overall, but dig deeper and you'll find the UK earnings business climbed roughly 60%. Hong Kong gained 40%. Very encouraging. Cash remains robust at right around GBP 700 million. If you add back the share buyback, which comes to just under GBP 100 million, it's nearly level with last year. Once more, a strong, encouraging first half. What matters most about the business right now is simply where we stand for future growth, and in my view, it has never really been this encouraging or optimistic. Our growth comes from areas such as sustainability, net zero carbon and similar things. Whether you look at demand or supply, we are very, very well positioned.
Leo Quinn
executiveSo what I'm getting at is this: on the supply side — offshore wind farms, nuclear power stations, every kind of clean energy — we're genuinely a big player, and that's a rising tide that stands to benefit us enormously. Then, on returning value to shareholders, an interesting point: we set out our capital allocation model about 3 years back, and over that stretch we've handed back roughly GBP 600 million through cash returns and share buybacks — a third of our market cap. So that's very encouraging, with the earnings-based businesses performing well. The market we sell into is in fact growing, returns to shareholders are substantial, and we envision further shareholder returns down the road as well. I'd like to highlight here what are effectively some of our key national infrastructure projects. These matter a great deal, because our fortunes really do hinge on how well we execute these contracts. It always pays to begin with a solid contract — avoid errors, since they invariably surface later. If I walk you through them: the picture in the top left-hand corner is in fact a National Grid job, where we're handling power transmission and underground cables running from Hinkley power stations through to the grid.
Leo Quinn
executiveThat job came in successfully and was done for a fixed lump-sum price. The reason that matters is that going forward, with an energy market and an energy security market that are expanding, the character of these contracts will shift under the ASTI framework, which gives us inflation protection and a two-step process. You can see that down the road, we'll be taking risk out of these jobs, and that really should be favorable for margin returns. On the upper right, what you see is Old Oak Common, and at some stage we're going to do a showcase on Old Oak Common. It's in London, in the Acton area. What you're looking at is in fact the box section under construction. You can get a sense of the size and scale simply by gauging the 2 engineers standing in the base. This will make up some 6 platforms for the new HS2 rail line, and it will link up with the Elizabeth line and the Great Western Railway, which adds another 8 platforms. This is going to be an enormous station. In fact, it's the biggest station ever built in the United Kingdom. Very exciting projects, and it's where HS2 will currently end for London.
Leo Quinn
executiveThen there's the opposite end, Curzon Street — which is in Birmingham. When you ride the train into Birmingham New Street, the final 3 minutes of the trip will let you watch this project taking shape. Three major structures sit in this zone. What you're looking at here is the Y-shaped piers together with the bridge deck, and that deck gets cast within the next week or two. You can watch it coming together right in front of you. This is an amazing project. And it's amazing for a single reason: I began my career at Balfour Beatty building a bridge roughly 40-odd years back. That one bridge alone counts as a major project. Three of them are underway, all within the same area. One project office oversees the whole thing. It's a lean operation — very, very impressive. Last, looking at Hong Kong to show the international capability we have: this is the T2 airport, and here is one of the roof structures. It measures approximately 70 by about 36 meters, and it is in fact assembled on the ground before being jacked up into position. Major projects like these are what we do. This is a capability that's unique to us. It isn't only the engineering — it's the contract and the commercial terms needed to manage it.
Leo Quinn
executiveRight now, our projection puts us on track for full-year earnings in the neighborhood of these projects. So here's what I'll do: I'll pass things to Phil, and he'll walk you through some facts, and then I'll return and walk you through the future.
Philip Harrison
executiveThank you, Leo. Yes, I can. Good morning, all. I'll begin with the key figures. In the first half, revenue rose 9% to GBP 4.5 billion, an increase of 6% once currency fluctuations are excluded. Profit at the earnings-based businesses climbed 12%, helped by robust profit growth in UK construction. Group operating profit, though, fell 6%, reflecting weaker profits in the investments business, partly because of disposal timing. The boost to net finance income from higher interest rates was offset by a larger tax charge, since no further deferred tax assets were recognized for UK tax losses. Taken together, that produced an 8% decline in profit for the period. Earnings per share nevertheless edged up to 13 pence, thanks to the group's share buybacks. Our order book of GBP 16.4 billion is down 6% over the period, or 3% excluding currency movements. The directors' valuation of the infrastructure portfolio held steady at GBP 1.3 billion. Cash flowed out as expected, with period and net cash of GBP 710 million, and average net cash of GBP 695 million. Consistent with the policy of setting the interim dividend at roughly one-third of the prior year's total dividend, the board is today declaring an interim dividend per share of 3.5 pence.
Philip Harrison
executiveAs we look toward the end of the year, we're still on course to meet our full-year earnings expectations. Now turning to the business units, beginning with construction services. Profit from operations rose 33% to GBP 65 million, with UK construction and Gammon driving that. In the UK, revenue went up. A 23% increase in revenue came from higher HS2 volumes, which, together with better delivery across the portfolio, lifted the profit margin to 2%, versus 1.5% a year earlier. Consequently, profit rose 67% to GBP 30 million. On HS2, earlier this year the client asked us to rephase work on our Area North contract. Having now worked through the change order and rebalanced the workload, those adjustments have had no material impact on our forecasts. We expect UK construction to come in ahead of the 2.1% profit margin achieved in 2022. Beyond the U.K., U.S. construction delivered GBP 21 million of profit, in line with the first half of 2022. Gammon increased revenue and profit by roughly 40%, driven by the major Hong Kong Airport projects. The construction services order book fell 8% in the first half, or 5% at constant exchange rates. In the U.K.
Philip Harrison
executiveAnd Gammon — the pickup in activity at HS2 and Hong Kong Airport, which is what pushed revenue higher, has consequently brought the order book down. In the U.S., delays persisted in commercial office projects moving to contract, especially in Texas, as customers held off awaiting better economic news. As U.S. inflation has eased to roughly 3%, we're beginning to see some early indicators of awarded work advancing to contract. We also secured additional U.S. awards during the first half that have not yet reached contract stage, among them a $650 million project at Raleigh-Durham Airport in North Carolina, where awards will be made in stages, phased across the multi-year project. Let me briefly address our GBP 5.9 billion U.K. construction order book, since its contract mix is a strong indicator of the shifts the business has undergone. The volume of future orders doesn't just give visibility for the short and medium term — the weighting of orders by contract type also mirrors the improved risk profile. Target cost and cost-plus contracts account for 84% of the order book, shielding the group from inflation risk, and most of the fixed price work is priced across 2 stages, which allows for added risk mitigation.
Philip Harrison
executiveWe also keep working nearly entirely with public and regulated clients, and that further lowers risk. We'll go on prioritizing projects whose contract terms carry less risk and give the group stability and predictability. Turning to support services, made up of our power, road, and rail maintenance operations. Revenue fell 7% in the first half, driven by the timing of power projects. Support services PFO dropped by GBP 6 million to GBP 30 million, largely because of lower revenue in power and higher costs in the road maintenance business, where 2 new long-term contracts were launched. As we bring those new contracts onto our systems and align them with our ways of working, extra costs come up front, but that is already built into our expectations when we plan the projects. With these two new contracts now in place, revenue from the road maintenance business should be higher going forward. Looking to the second half, we still expect the full year PFO margin to be towards the top end of our 6%-8% targeted range, with all three businesses performing well. Over the medium term, the power business is set for significant growth as the industry responds to the government's need to invest heavily in the grid.
Philip Harrison
executiveWe were named last week to SSE's GBP 10 billion ASTI framework, and we are also in the running for National Grid's comparable Great Grid Upgrade framework, where project delivery is expected to start in 2025. Turning to infrastructure investments. Within our infrastructure investment business, pre-tax profit has fallen to GBP 14 million from GBP 24 million, for two principal reasons. We completed no disposals during the period, versus GBP 7 million last year. Disposals are inherently lumpy, and for 2023 we still aim for gains on investment disposals within the GBP 15 million-GBP 30 million range. In the U.S., military housing costs have risen in connection with the first year of work by the independent compliance, compliance Monitor. Pre-tax profit also reflects an offset of GBP 3 million between operating profit and interest receivable, caused by higher interest rates on the subordinated debt that the group provides to certain joint ventures. It matters to note that this has no effect on the cash distributions the group receives, but it does mean the returns must be presented differently in the accounts. As for the second half and our planned disposals, we are presently marketing a number of assets that we intend to close out by year-end.
Philip Harrison
executiveOur approach will stay disciplined, and maximizing value continues to be what we prioritize. Now let me walk you through how we valued the portfolio. As a reminder, our year-end valuation was independently verified by a third-party expert, and the methodology applied to the half-year valuation is unchanged. In the first half of 2023, we invested GBP 24 million in new and existing projects, including adding one student accommodation project in Florida. We expect further investments in the second half, since we keep seeing opportunities to invest at our target return rates. Over the period, we received GBP 33 million of distributions from the projects, and reducing the discount by 6 months raised the valuation by GBP 42 million. Changes in foreign exchange rates had a negative impact. 58% of our portfolio's value was in North American investments, and the dollar's weakening drove a GBP 39 million decrease. Lastly, operational performance lowered the valuation by GBP 16 million, as higher U.S. insurance premiums and an increase to our estimates of costs related to the monitor's work were reflected in the period.
Philip Harrison
executiveU.K. student accommodation rent hikes have helped offset part of those costs. As a result, the valuation has come down slightly, though it still sits at roughly GBP 1.3 billion. Cash flow in the period matched what we had anticipated, and the closing balance fell by approximately GBP 100 million. Operating cash flow stayed robust and came in just above the prior year, while the two biggest outflows — working capital and the share buyback program — were each highlighted at year-end. We anticipate a further working capital unwind in the second half and still expect the full year unwind to land between GBP 75 million-GBP 125 million. We've also issued guidance today for 2023 average net cash, which we expect to fall in the range of GBP 650 million-GBP 700 million. Another item worth mentioning is the GBP 13 million in pension deficit payments, which are down from GBP 29 million after an agreement reached earlier in the year with the trustees of our largest pension fund. Contributions should stay at this lower level over the medium term, and self-sufficiency is expected to be reached in 2027. I'll wrap up with our capital allocation framework.
Philip Harrison
executiveWe keep putting money into organic growth opportunities—not just by adding more to our investment portfolio, but also by building capability throughout the earnings-based businesses, which Leo will discuss shortly. As mentioned, we also expect to capture value from the investments portfolio, and we're planning disposals for the second half of 2023. During the first half, we took active steps to strengthen our balance sheet further, refinancing our revolving credit facility: the old GBP 375 million facility, which was set to expire next year, has been replaced with a new GBP 475 million facility running to 2027, plus an option to extend by another year. The board has declared an interim dividend of 3.5 pence per share, in line with the policy of paying roughly one third of the prior year's full dividend. Lastly, we remain on track to complete 2023's GBP 150 million share buyback program during the fourth quarter, and we still expect the capital allocation framework to be in place for years to come. With that, I'll hand you back to Leo.
Leo Quinn
executiveThank you. Thanks. I'll begin here, though I want to pick up on a point Phil made. If you consider how we allocate capital, the top use of our cash is reinvesting into the business we already have. With the tide rising and the opportunity as large as it is, this is an ideal moment to put money into selling expense so we can handle the bid demand emerging in the marketplace. That spending on selling, we expect, will go up. If I direct you to the slide, on the left-hand side — I showed it to you last time — it's worth walking around it to grasp, as I said previously, that we're somewhat like the Intel inside. We are the enabler allowing many of these things to happen. From submersible and semi-submersible platforms, together with the likes of Arcadis, regarding where offshore wind farms are headed, we rank among the biggest suppliers of pylons and transmission cables for the grid, which helps de-risk it. On small modular reactors, we aim to work with Holtec, though a great many players are appearing in the market, and the whole space is quite interesting.
Leo Quinn
executiveWhether it's fusion or conventional energy, nuclear power, things like Hinkley, we're seeing growth with Sizewell, so that area is exciting as well. We put a modest investment into EV charging to capture the demand in that market, and we're running active FEED studies and similar work around carbon capture and hydrogen. This space is genuinely very exciting. Since we discussed this six months ago, what we've observed is what I'd term the mobilization risk — these markets are so large and the opportunities so big that it's too costly for any single company to pursue them alone. The government is launching the ASTI framework, which is aimed at de-risking the grid. It's examining carbon capture, it's examining small nuclear reactors, and it's putting up a sum of money to make these things happen. Right now, we're working on FEED studies and enabling work to turn these into reality. We're actively engaged in setting the stage and laying the foundation to make these things possible. It's very exciting, and I'll touch on it in the next few Slides.
Leo Quinn
executiveThis is a growth market, and we're uniquely positioned to actually capitalize on it. In our support services business, which also feeds into that same market, and in our power T&D, we're off to a very good start. I'd point you again to SSE's ASTI framework. That's already been put out in bid. National Grid will probably make some decisions around the first quarter of next year. I would anticipate between 25 and 30, and maybe even towards the end of 2024, that there'll be an additional GBP 2 billion-3 billion worth of business over that 5-year period, which is substantial growth. In terms of that power T&D, you're looking to the upper end of doubling that business by 2027, 2028. In terms of road and road maintenance, again, a nice business that we seem to manage very successfully. We won two contracts in the first half of the year with East Sussex and Buckinghamshire, and we're mobilizing those. We're targeting one more local authority next year. Again, what we're seeing is good double-digit returns, and we're seeing good growth in that area. In terms of the rail, the CRSA contract is performing very well. Also, the London Underground, in terms of the upgrade of the Piccadilly line with our power traction, is doing well.
Leo Quinn
executiveIn the Midland Main Line area we're seeing growth, along with electrification—and there's also the track slab work from HS2. All of these, again, in the investing line, require considerable resources when it comes to actually investing. Right now the difficulty is that it's rather like London buses: 3 of them arrive at once, and we have to figure out how we deal with that peak loading. What we do here is quite traditional. You know, we run cables across the Highlands, we operate central monitoring stations for road maintenance, and we genuinely repair railways. This is the Nuneaton repair, where the line was closed for 10 weeks. We brought in a small team and in fact restored the bridge and the foundations in record time, handing it back to the client early. I want to highlight this in light of the slide I showed you with the pictures of what we're doing. What's interesting on that first slide was that, if you look at the transmission job in the top left, the old framework was a fixed-price lump sum. If I look at HS2, those particular contracts had inflation de-risked, and they were an incentivized cost plus an incentivized fee.
Leo Quinn
executiveThe goal here is to shift every one of these frameworks into situations where inflation risk belongs to the customer rather than to us — which is fair, since ultimately that's where the returns sit — and where we know how the contract has been de-risked so that such de-risking leads to better margins. With cabling in this instance, we've discussed the ASTI framework along with the size and scale of this opportunity, but what you see is the pylon and the wiring. What isn't visible is the work we carry out beneath it. We possess specialist design capability. We handle the piling itself, we do the pile cap, we install the roads so these items can be reached. Contracting and bidding on this will happen through a two-step process. In effect, our team will be combined with the client's team. We'll examine the DCOs, we'll examine the engineering, and after that we'll examine how the job is actually executed. Once that phase one concludes, we'll then determine the basis on which we perform through to the final contract. That's two-stage distribution — most of the risk will be designed out during phase one before we actually sign a final contract in phase two.
Leo Quinn
executiveIt's a very different situation from where we stand now. When I think about nuclear power stations, what matters most regarding Sizewell is that it represents an intelligent replication of Hinkley. The lessons learned at Hinkley are going to be carried over to this project. All of the marine works in the tunnels were completed by us, and we'll do the same thing here. We're aiming to add the enabling works along with the earthworks. As a point of interest, the earthworks at Sizewell are considerable, but they amount to roughly 20% of the earthworks we've completed on N1, N2, and HS2. That shows you we are uniquely qualified for this kind of work. Within the enabling works, we'll handle items related to pre-construction design. We'll be examining the ground engineering. The largest element will in fact be the diaphragm wall, which will enclose the entire site. Interestingly, the last diaphragm wall we constructed at Sizewell was for Sizewell B, 40 years ago. We're repeating what we did for Sizewell B, now for Sizewell C. Once again, this unique capability underpins everything and contributes to success. Why does this matter? Because in the end, it provides the client with greater assurance. It brings our safety standards with it, and it brings our quality workmanship.
Leo Quinn
executiveSo what you observe in, say, the power business is that this element gets delivered right here. What isn't visible is the way all of it gets delivered across our remaining businesses, plant and fleet included. That's a substantial opportunity, though it's also been substantially de-risked through how the order book has been handled previously. Yeah, very, very exciting. In the United States, honestly not much different from my report six months ago. Two challenging areas. We have the Northwest, which is funded really by the tech sector — the Facebooks, the Amazon, the Microsoft, and that crowd. That market we've seen slowing. In Texas, largely a developer market shaped by interest rates, we've seen that slow as well. What's interesting in Texas is that the work keeps piling up. You know, our largest order book of awards hasn't been contracted. The challenge is that until the developers get certainty, they won't move it into contract, so we have a lot of pent-up demand here. What we're still seeing is strong growth in California in schools. The federal market in Washington, D.C., is going well. Of course, in Florida, with Mickey Mouse and Universal, we've got great growth in hotels, leisure, and that sort of thing, so exciting.
Leo Quinn
executiveWe aren't just sitting back hoping growth will show up. We're putting money to work. What we did was invest in Jacksonville and Sacramento as two new branches. As you know, ours is a local business, since building and construction runs on a local supply chain. With that in mind, both of those are showing really solid activity, Sacramento especially. When it comes to our smaller branches, we're in fact doubling down and putting investment into the Raleighs, the Austins, and the Phoenix so we can grow those, and that comes on top of the base business you've already seen. For 2024 and 2025, we expect some really good revenue growth in those new areas. We're also putting focus on the airport market. We just bought — won a contract in Sacramento for bridge connectors, effectively, which is something we took from the LAX. We just won another contract in Raleigh, and we won one in Jacksonville. Those three come in at just under $1 billion, and delivery will happen over the next 2 years or so. Again, there's a lot going on there. Lastly, on the infrastructure and civil market side, that market is growing. Of course, you have the Biden Inflation Reduction Act, but the US market is still fixed price lump sum, so the risk actually sits largely with us.
Leo Quinn
executiveUntil that matures in line with the UK picture, we're simply going to be more careful when it comes to the big projects we look to take on in that region. Once more, the US is a solid performer — we're just waiting for the dam to break so we can feel more optimistic regarding the outlook for next year and the year after. Turning to Gammon, our joint venture with Jardine Matheson, in their market they're a substantial player, very high profile, a very, very strong brand, a very good business. It almost replicates what we do in the UK when it comes to capability. All those things around piling, concrete delivery, design, temporary works — all of this goes on in Gammon, and it is a GBP 2 billion business, so it's not far off the size of the UK business, about half. Basically, this is a very, very strong market. It's centrally planned, and, you know, since the change of, or the formalization of government, what we've actually seen is that the market's moved forward very, very positively. Historically, we've seen a very strong building market and residential. With interest rates higher, we've now seen that starting to fall off.
Leo Quinn
executiveInfrastructure is really ramping up, and again, in a big way in terms of the infrastructure they're putting in place, which backs the key markets across the region — tech, IT, data centers, R&D centers — and much of that is going to be underpinned by the delivery of 5 new MTR stations plus the rail tracks that go with them. We've just tendered for 1 station with MTR, and that's around GBP 1 billion. Once it's finished, it will include the deck platform, and then what they'll do is build commercially on top of it — commercial and residential. You can see that by actually putting the station in, it puts you in a good position for the next phase of building above it. We're seeing, again, strong growth with MTR. Every customer we work with in this region — those are long-established relationships. And that matters because when problems arise, we know how they act and how they react. MTR has been a customer for a very, very long time, as have many of our buildings customers. We're very selective about what we bid for. There isn't any growth, by the way, in Hong Kong and the area around it. There is the Northern Metropolis, which we've discussed before.
Leo Quinn
executiveThen there are the Macau casinos, and those are expanding too. It's a lively market. The thing holding us back isn't opportunity — it's really capability and the people we're able to hire. Funnily enough, Hong Kong's government has just revised the rules on importing expert labor, and that's going to ease the strain on headcount and capability, which should actually help drive growth down the road. Turning to our investment business, Phil has discussed this ad nauseam. In the second half, we're looking at divestments in that business. As we've said all along, if those investments aren't delivering the right return, we're not going to rush out and sell them just for the sake of selling, because these are actually performing yielding assets. The real question is: do we simply want to keep the yield, or do we actually want to take the capital gain? We keep making investments. As you know, we put money into EV charging, a company we named Urban Fox. That was a small investment; the premise of the strategy was around us having good relationships with local authorities, really good demand for EV charging at the moment, and it's not outside London, the satisfaction levels are really low.
Leo Quinn
executiveWe feel pretty good about that over the long term. GBP 24 million has gone into assets. Tallahassee, Florida was the biggest one, and that was student accommodation. We finished building the Vanderbilt student accommodation in Nashville as well, and we also secured William & Mary College in Virginia. Once again, plenty is happening beneath the surface here. Student accommodation in the UK and the US is something we're strongly dedicated to. In the U.K. we have 2 major projects that we're working to close during the second half of the year. When it comes to U.S. multifamily housing, we keep putting money into it. The biggest opportunity here is P3. As you'll recall, the L.A.X. People Mover — this P3 right here — is a P3 worth roughly GBP 2.6 billion, and we intend to take advantage of that. Our next bid will be for Prince George's County Schools in Washington, D.C. That one, again, is the largest opportunity currently on our plate. What's unfortunate with P3 is that getting these things to fruition just seems to take years, so a heavy upfront investment is required before the returns come in. Naturally, you know, we're looking to be active players in the UK energy transition market.
Leo Quinn
executiveWhen I look at building new futures, there's nothing new here regarding carbon, materials, and communities, since we've kept our 2030 strategy and targets in place. Under the leadership for sustainability, we've made fantastic progress. Our work on the pathway to decarbonizing for Scopes one, two, and three is complete. In the second half of the year, we'll be submitting to the body of the Science Based Targets so that we don't exceed the 1.5 degrees temperature rise globally. We're confident this will go through very well. It's interesting, between Scopes one and two, which is what we do internally around carbon and energy, versus Scope 3. Scopes one and two actually only equal 3% of our overall carbon footprint. You can see that it means we've got an awful lot to do with the supply chain to represent the other 97%. Although we've made great inroads in terms of reducing idling, changing out diesel to electric, and the likes of that, it's still just a small microcosm on the scale. Areas where we've made great progress is, and this, the area I'm focused on the most, is really around how do we drive more social value?
Leo Quinn
executiveBecause we can put things back into communities so those communities become better places to live. Through placing work with local suppliers, we spent GBP 125 million in locally generated economic value. For people coming into the business, we've delivered over 2,000 days of training. On this particular point, interestingly, we've trained or taken on more than 300 people who had been long-term unemployed and placed them into jobs. We're equipping people with the basic skills that let them become productive members of the community. The social benefit that flows from what we do in our ordinary, day-to-day business, I think, is fantastic. This is 1 job. We have 600 other jobs, and right across the group, we're trying to do these things all the time. Naturally, we still run The 5% Club, which focuses on bringing young people — apprentices or graduates — into the workplace early and giving them skills for life. Lastly, for the full year, we're on track. We're positioned really well to capitalize on growth, whether that comes on the demand side or the supply side. Over the last three years, you know, we've delivered GBP 600 million return to shareholders.
Leo Quinn
executiveWe feel good about the returns ahead. The business is positioned well for the entire year, and we have confidence that we will meet expectations. There's a really strong future for growth in this business. With that said, I'll turn things back to Phil for the questions.
Arnaud Lehmann
analystThanks a lot for the presentation. This is Arnaud Lehmann from Bank of America. Two questions from me, both about the US, if I may. First, we've seen some companies — mostly in building products — relist in the US, and they said there was an advantage to being US-listed with a US head office when operating in the country, because, you know, the US is, America is buying America. Have you felt, in the private or the public sectors, that being a British company listed here was ever a problem when you bid for contracts relative to the locals, and is there a way to address it? My second question on the US... is your positioning. I think you're positioned more in the commercial sector, which is suffering a little bit at the moment. There are more opportunities coming up in the infrastructure space. You mentioned that there was more lump sum fixed contract, so that was probably a bit more risky on your side. When do you expect that to evolve, if ever? How easy would it be for Balfour Beatty to progressively transition from the private sector to the public sector in the U.S.?
Arnaud Lehmann
analystThanks.
Leo Quinn
executiveAll right. Regarding the British angle, and also the relisting question — look, everything moves in cycles. I recall, what, 20 years ago, folks were discussing the Capital Asset Pricing Model and saying you're holding too much cash on your balance sheet, so you ought to return it to shareholders. Naturally, the response is that if the way we manage the balance sheet doesn't suit you, you're free to invest your money somewhere else. What matters a good deal, I think, is that markets rise and fall. Right now, listing things in the U.S. might be in vogue, but I'm confident the U.K. market will return. Once we get some growth in the UK market, which is likely forecast over the next couple of years, I believe everyone will hurry back here. We're quite comfortable with where we're listed, and we don't really view an opportunistic shift to the US as something worth spending time on. Feel free to disagree with me, by the way. As for being a British supplier to the US, I'd say we're treated fairly.
Leo Quinn
executiveUltimately, capability is what matters most. Being able to deliver projects such as residential and commercial theme parks—like we did with Avatar—is significant, since these aren’t items you simply pick off a shelf. That represents genuine capability. In my view, customers purchase based on capability, and that is exactly what we provide; we have been established for a long time across every sector in which we operate. Regarding positioning, we are very clear that our purpose in business is to generate returns and reduce risk across the portfolio. I would gladly accept a business at half the size with double the profit, since what matters is returns—not staying busy for no reason. In the U.S., the commercial market—specifically the infrastructure commercial market—is difficult. Our strengths lie in roads in Texas, roads in the Carolinas, and similar work. We have also performed well in California, on the LAX people mover and comparable projects. These are difficult conditions, and when you are awarded large jobs worth $1 billion on a fixed-price lump sum basis, you must be extremely careful.
Leo Quinn
executiveWe would prefer to maintain a presence in the market and hold out until conditions return to normal—specifically, until bidders stop offering ridiculous prices, at which point the developer or client suddenly must revisit their approach to going to market. We are observing this in the UK; in a particular region there, which I won't identify, located north of Hadrian's Wall, we were examining roads in that area and simply declined to bid since the commercial terms were unsatisfactory. They have since returned and asked: Look, fine, on what basis would you bid? With nobody tendering, you cannot get the work completed, and those authorities need the work done. Would you like to add anything?
Philip Harrison
executiveThe sole issue is that the research quality we’d likely receive in the U.S. probably wouldn’t match.
Arnaud Lehmann
analystThat's a fair point. Thanks.
Leo Quinn
executiveThat's a solid answer for you.
Jonny Coo-bra
analystThank you. This is Jonny Coo-bra from Numis, and I have 3 questions, if I may. First, regarding support services, how fast are you able to scale that business, and what lead time applies when adding capability in that area? Second, in UK highways, given the delays in the market, does any of that affect maintenance contracts? And could your share of the A66 increase? Third, on US construction, when it comes to the contracting model, I would be interested in your views on how it has performed through inflation's emergence, or re-emergence, after COVID. In other words, have subcontractors been caught out by inflation coming back, and do they now want-
Leo Quinn
executiveYeah.
Jonny Coo-bra
analystAre there additional continuation provisions in the contracts?
Leo Quinn
executiveOkay, regarding the power business, let's walk through how this works. Essentially, your bidding takes 6 to 9 months within the framework of how you compete. SSE has finished theirs, and National Grid is still going through it. After that comes the DCOs — consent orders — covering how you'll actually deliver on the ground, your environmental matters and all those items, planning and so forth. That is effectively almost, at a minimum, a 2-year design process. Right now the government is actively consulting, looking at how to cut that down. Because everyone complains that project costs keep climbing, but the main driver behind those increases is that we lack environmental consents, we lack planning consents, and even when a judicial hearing says, you know, "You can proceed and carry out the work," the local authority still gets the final say. The government is consulting on this: how do we shorten the timeline? If that timeline can come down to 1 year instead of 2 years, we'll be putting shovels in the ground, you know, by the middle of 2024. We're working with SSE right now to assemble our teams for the consenting and the design work, and after that you're looking at roughly a 3-year construction period.
Leo Quinn
executiveIt's kind of a moving target, honestly. Right now our thinking is roughly 2 years for design and consents, followed by 3 years of construction. Those businesses do have some seasonality, by the way. On your second question, about U.K. highways maintenance: U.K. roads are, sadly, in a bit of a disaster state at the moment, what with potholes and that sort of thing, so I don't see any pullback from that. It's not really something we can do. On the A66, once the project gets the go-ahead, it's highly likely that our share will increase. But right now, we're still waiting for the actual notice to proceed. As for highways, there are 6 highways out there at the moment that we're very interested in. On the portfolio, if you look at where government money is going, obviously they don't have an endless pool of it. I think over the medium to long term, you'll see highways begin to reduce, but it'll be pumped into other areas. Finally, on U.S. construction and the emergence of inflation, I'll do this one just to be quick.
Leo Quinn
executiveMost of what we do — GBP 4 billion of the GBP 5 billion — is buildings. Here's how the contracting works: we assemble the cost, then, say, apply a 4% fee to it, with 2% plus going to overhead and the rest ending up as profit. That contract then gets built out with all the subcontractors submitting their terms on a fixed-price lump-sum basis. Inflation risk sits with them, and beneath that they have to make sure — whether through a bond or some Subguard — that they can deliver, and essentially their, their own house is at stake there, and it's pretty penal if they get it wrong. In the case of U.S. buildings, that risk is fundamentally passed down to the supply chain, and that's quite important to keep in mind. It's a lower return model, but in fact it's a lower risk model. Do you wanna add anything to that, or?
Philip Harrison
executiveThe one point I'd make is that, on a year-on-year basis, I think the supply market is tighter. Subcontractors are feeling some pressure from the inflation impact. We obviously assess the quality of our subcontractors and watch that very closely. So far, we haven't seen a large number of contractors going bust, but obviously that's something we keep an eye on.
Leo Quinn
executiveLook, letting any subcontractor go under doesn't serve our interests. In the same way we'd engage with our customers — you know, if an inflation risk shows up that nobody factored in when the original contract was signed four or five years back, we'll return to the customer and figure out together how to soften that — we'll do the same with our supply chain, trying to achieve the same result. You know, the fallout from a bankruptcy stretches well past merely the expense of repairing a supplier. Yeah.
Joe Brent
analystGood morning. This is Joe Brent from Liberum. I have three questions, if I may. First, regarding the U.S. margin, I understand the point that it involves low risk and low return, but given that you achieved 1.2% in both halves, could you provide some indication of where you expect that figure to settle? Second, if I recall correctly, at the full year you mentioned risks surrounding possibly Chinese capital controls, and nobody knows how those relationships will develop, but clearly you have a significant amount of capital tied up in Gammon. Is there any method by which you could de-risk that? Third, I believe this question is for Phil. Working capital absorption stands at around 15%, stable at the year-end level of minus 15%, and you have grown sales. Why are we not seeing a working capital inflow rather than an outflow in the first half?
Leo Quinn
executiveI figure we'll hand Phil the first two, and I'll take the third one, okay? Do you want to, do you want to give that a shot — the second-half expectations for U.S. buildings, 1.2% to...
Philip Harrison
executiveSo we expect margin to go up in the second half. That's the usual pattern. That said, on the U.S. side right now, from a revenue standpoint, we figure it'll be fairly flat. We'll see. We will see some margin growth. Our commitment to the 1%-2% range hasn't changed, so driving that margin higher remains our key focus. Clearly, we're at a point where we'll make very small increases in that, you know, tens of %.
Leo Quinn
executiveOn the China piece, that's a fair question. From what I recall — I checked into this roughly six months back — our asset base there comes to around GBP 70 million. That isn't, it isn't a large figure. We do hold a larger cash balance, mind you, though that stems from Hong Kong's regulations. You're required to maintain a specific level of cover, aren't you, in order to operate there, and that's actually rather shrewd, since it stops you from draining all the cash and running the business on negative working capital. Do you want to... Anything else to add on that?
Philip Harrison
executiveOkay, so on that point — regarding the safeguards around Gammon — we pay out the entire annual profit from Gammon. Nothing gets retained beyond what's needed to operate that business. We don't provide any guarantees at the group level for anything, so it's clearly a very standalone operation, and because of that it runs its own banking arrangements. It doesn't draw on our group balance sheet. I think our stance has consistently been that right now we carry a fairly thin cap there. On our books, I believe it sits at roughly GBP 75 million.
Leo Quinn
executiveRight.
Philip Harrison
executiveThe main point is that we need to pull our earnings out on an annual basis.
Leo Quinn
executiveYeah, I think Phil has really nailed the main point here: this is a completely separate balance sheet that stands on its own. It's different from when we had the Middle East — the Middle East drew on our balance sheet, and that was one of the reasons we divested of it. Hong Kong isn't in that kind of position. As for your question about working capital, Phil would be upset if I took that one, so I'll let him answer.
Philip Harrison
executiveNo, go ahead, you take it. It really comes down to the project mix, and like we've mentioned, in the U.S., where we received some quite large mobilization payments a couple of years back — on a major set of roads, actually, and on our P3s — we're now seeing that begin to unwind. In the U.K., things lean more toward project bank accounts, so compared with the U.S., we don't see as much of a working capital benefit there. That's the dynamic at play.
Leo Quinn
executiveThat answer was spot on.
Andrew Nussey
analystMorning, Andrew Nussey from Peel Hunt. I've got a couple of questions. First, on UK construction, Phil, I believe you identified the ramping up of HS2 as the main thing driving revenue growth. Given that the project has been rephased, will it be tougher to deliver revenue growth in UK construction across the next couple of years, or have we now hit a kind of normalized run rate? Second, regarding the US investments and the monitor, what exactly are they monitoring? Do they give you any observations that matter for the wider military portfolio and, in fact, for US multifamily housing more broadly? Thank you.
Leo Quinn
executiveI'll hand things over to you.
Philip Harrison
executiveOkay, so about HS2 — we've finished our analysis on that. In our forecast, we don't view it as a 2023 or 2024 problem. What I think does become the problem is those deferrals and delays. People generally understand, I believe, that in construction, that tends to end up costing more down the line. You could expect revenues might tick up beyond that window, since we still have to complete the work. So that's HS2. Now on the monitor — the monitor has broad access across the entire military housing business. They're reviewing our compliance processes, our ethics, and our culture, and they're going across all 55 bases we operate in the U.S. As you can imagine, that's a very large and wide-ranging exercise. When they report out, we take those findings on board so we can improve the process. They're not — what they're doing is monitoring our plans to improve the process. After that, they'll audit the things we've put in place. That's what they're pushing forward on. We welcome it. We welcome the support, and we want to strengthen the military housing controls and compliance in that business.
Leo Quinn
executiveIt's an interesting one, because we operate in an environment with greater compliance these days. There's considerable focus on Speak Up, and on whether we're actually capturing input from the grassroots of the organization all the way up to the top, and then how we respond to it. Across the entire group — not only in military housing — we've observed that the volume of Speak Ups has in fact gone up, along with how we investigate them and similar matters, which is a positive thing, since it produces a transparent, very clean culture. So we actively encourage it. I believe that's occurring at all corporates in this day and age. I think in some cases we're just a little bit ahead of the trend.
Andrew Nussey
analystThanks.
Stephen Rawlinson
analystStephen Rawlinson here from Applied Value — got a couple of questions. First, on that compliance topic, maybe tied to ESG as well: 2030 is approaching, isn't it. When we began discussing 2030, it seemed far off, yet that's no longer the case. So who actually ends up footing the bill for ESG? Will customers pay? Some of the modern equipment now arriving — hydrogen-powered and the like — presumably carries a much higher cost. Do they expect the margin to build on that, build on you, and how does that unfold across the next year or two? Or is it something customers will fund within a cost-plus arrangement? Second, the capital allocation model — you didn't bring up M&A as a probable flow of funds, and it hasn't featured in anything over the past few years. Given an environment where technology, IT — you attend these meetings and hear about digital and so forth — are there technology areas or skill sets where M&A could fill the gaps? Or are you simply satisfied with what you have today and confident you can build that in-house?
Leo Quinn
executiveOkay, so first off, you're correct that 2030 feels closer than it did when we showed those same results 12 months back. That said, customers aren't exactly raising their hands to say, "Sure, I'll pay a premium for lower carbon," or anything like that. The assumption is that you'll handle that on your own initiative. With certain government contracts, they're willing to finance some innovations and some ideas, but broadly, it's a competitive environment. Even if we announced that we'd raise prices, if a competitor is bidding at a lower figure, you shouldn't be shocked that you lose the job too — so you never even get the opportunity to put those kinds of things in place. Look, everyone undoubtedly wants to reach heaven, but no one wants to die. We're all striving for net zero carbon, yet funding it is also a difficulty. Another issue is that some technologies simply don't function. You can electrify a crane, and it can lift and lower and handle loads, but once you move it beyond 100 meters, the battery is dead.
Leo Quinn
executiveTechnology hurdles and innovation remain, and hydrogen is still quite nascent in this field. We have pilots for all of these initiatives out there. We are subsidizing many of them, and the clients are subsidizing them as well. Look, something will break through, and you don't want to be at the back of the class when that happens. Like any large corporation, we invest in many things, and we hope some of them pay for the loss leaders. Regarding M&A, we don't really do it. We'll acquire capability, but as I've always said, if I want to acquire a big project, or I want to lose money, I'll bid it directly rather than buy an intermediary. There's no point in that. But there are some exciting areas out there where — but it's at the small end. And I think in our industry, this is the most — what's the word? Undercapitalized, digitized business in the economy, because of the way we do things. And we do have some competitive advantages. For example, we've worked with a small company called SiteAssist on digital permitting, which has an inference on the following process — you save lives.
Leo Quinn
executiveWith it, you can digitize and secure permits at any location across the site, plus keep tabs on each individual worker, and that translates into greater productivity. On top of that, it delivers improved assurance. Each individual action and process stage gets recorded and photographed, and that, whether you believe it or not, actually provides stronger assurance—but also enhanced productivity—and it genuinely is safer. There are areas where we're putting money in. On the treasury and financing side as well, we've made some significant investments with... Oh, what's the, the company called? The name escapes me. Clearly, you don't know either. So, where's Andrew? Who's handling the treasury software we're partnering on? He's in the audience somewhere. Richard?
Philip Harrison
executiveBloomberg.
Leo Quinn
executiveBloomberg and the rest. Look, we really do have genuine productivity gains available in the back office. We're leading the way on that, and if we can bring that project out into the field — well, that's where the spending happens. Being able to boost productivity in that area would let us deliver at better margins. Causeway. Yes, Causeway was that other firm I had in mind. Good thing somebody here remembers.
Graham Hunt
analystHi there, Graham Hunt here from Jefferies. I’ve got what amounts to three questions. First, for the first half, UK construction margins came in quite strong. Could you share your latest thinking on where those margins are headed over the mid to long term, and what your ambitions are there? Second, you mentioned that you’re increasing investment in selling expenses. With some of these projects coming online, are you seeing a more competitive bidding environment in the UK? Third, on capital allocation: are you guiding the balance sheet down by roughly GBP 150 million this year? Do you remain comfortable with your shareholder returns framework, and should we expect—assuming you come in line with that guidance—a similar mix of dividends and buyback for this year as well? Thank you.
Leo Quinn
executiveWould you like to take the first one and the third one, and I'll handle the second one?
Philip Harrison
executiveSure, happy to. Honestly, I figured you might take a shot at the UK. That's—
Leo Quinn
executiveWell, I’m
Philip Harrison
executiveIt's a long-term thing, so that's always your—
Leo Quinn
executiveLet me correct that for you.
Philip Harrison
executiveOh, right. That's fine. Look, we do, and we remain committed to pushing our margins higher in the UK. As we've said, we believe the range is 2%-3%. We want to reach the top of the 3%, and I think that's still achievable, and we can still do that. Clearly, Leo has an aspiration as well.
Leo Quinn
executiveWell, look, I think that's fair enough. When you consider our capabilities and what we deliver, and put us up against anyone—EPCs, across the whole industry—the fact that we aren't making 4%-5% is simply absurd. It boils down to having the right contract, it boils down to flawless execution, it boils down to the right delivery mechanisms, and all of that exists within our portfolio. As our market has matured over the past 4 to 5 years, that possibility remains on the table. Whenever I bring up that range—nearly double what Phil's saying—he makes me take a drug test, and I've passed every time. The point is, this business is worth far more than what it's valued at right now. If you look at the cash generation, it's pretty easy to see how we've been returning 10% of our end. We've—what is it? 10, 11% annual return on the business between buyback and dividends. You know, there's an engine in there, and all we've got to do is make sure Phil adds the numbers up correctly and reports it. The investment. Oh, what was it, more.
Philip Harrison
executiveIs that the reason there's more competition in the UK?
Leo Quinn
executiveHonestly, when you really examine it, the pool of individuals capable of performing the type of work we do is, in fact, fairly limited. For the client, ensuring they run a competitive tender serves their own interest, so that each party ends up falling on their sword and puts forward the widest scope, the fastest delivery timelines, and the cheapest price. Ultimately it boils down to this: you must have confidence in what you're doing, so that we are establishing the benchmark for margin return at the appropriate price. Bear in mind, it's genuinely crucial that we do this, since our business isn't simply about extracting cash — our business is about reinvesting. Across many of our businesses, particularly the power business, it takes three to five years to train up the following cadre of people, and that cost really sits with us. Should margins stay low, we're unable to make that investment, and as a result, the industry over the long term suffers, because it simply hasn't got the capacities to supply. My view is that, you know, competitive activity will always exist, but I think in most cases, people know whom they want to choose in order to deliver the job.
Leo Quinn
executiveYou've got to go through this whole song and dance process so that, in their own mind, they can feel confident they're getting the best value.
Philip Harrison
executiveAnd the other point I'd make is that I believe it comes down to how much bidding activity we're seeing.
Leo Quinn
executiveMm-hmm.
Philip Harrison
executiveAs we move forward, that means we're also looking to invest in sales expenses. There's simply a volume issue that we see coming at us over the next few years. On capital allocation, we're committed to a multi-year share buyback. We're not backing away from what we've said on that. We won't make any commitments at the half year regarding that value or its shape relative to dividends and buyback. We'll handle that later in the year, once we know where we're going to land, what excess cash we have, and what we want to do with it.
Leo Quinn
executiveWhen you really think about it, your goal is always to put your capital where it earns the strongest return. I honestly can't imagine a stronger return right now than repurchasing our own stock. Just consider that roughly 18 months back we stood at GBP 2.30 or GBP 2.40, and today we're at GBP 3.40, yet we remain remarkably inexpensive. That makes for a solid deployment of cash, doesn't it?
Operator
operatorLeo, there are a few questions that came in through the webcast, and Jim will pass those along to you.
Analyst
analystWe received three questions from Gregor at UBS. What do you expect for sustainable working capital levels and cash returns as we go into 2024? Is it your ambition to grow earnings in the earnings-based businesses in 2024, following a flat 2023? And third, you mentioned that you'll be investing in overheads to capture the growth opportunities. How much is that amount?
Leo Quinn
executivePhil, you take the first one, and I can handle the second one.
Philip Harrison
executiveYes, we are clearly. Sorry, could you repeat the sustainable one? I'll combine it with the second one.
Analyst
analystWhat we anticipate for sustainable working capital levels and cash returns as we head into 2024.
Philip Harrison
executiveWell, listen, over the medium term we've indicated that we're aiming for a working capital range of 11%-13%. Obviously, we've spent 2 years at 15%. I still think we will see working capital flow out again next year, and that should bring us down toward that target. I suspect we probably won't reach 11% over the medium term, but I do think we'll land in the 13% range. That's where we believe a sustainable level sits — probably at 13% now rather than 11. That is the sustainable figure, with the ambition to grow next year, 2024.
Leo Quinn
executiveI'll tackle that question from a slightly different angle. The difficulty with forecasting timing is, well, the frameworks that are coming through, the Consent Orders being implemented, and so on. Should the government consultation speed these developments up, everyone stands to gain and it would save GBP billions — not GBP millions, GBP billions. As things stand, my projection is that an uptick in earnings will appear in the second half of 2024, followed by a strong uptick in 2025. If some of these developments move forward, then in my view you'd get a far better second half, a considerably larger uptick in the second half of 2024. For us, 2025 is going to be a very positive year. That's what I'm forecasting. I don't know whether you'd like to add anything to that.
Philip Harrison
executiveAll I would say is that I wouldn't expect anyone to be revising their 2024 figures just yet. Obviously, we'll get clearer visibility once we work through the full year.
Leo Quinn
executiveSo then the last item — like everything else here — suppose we raise selling expense by GBP 5 million to handle what you might call this flood of bids. You can't really be sure you'll land every one of them. If all of them were won, that would clearly show up as a sizeable lift as well. It's a bit like what Phil mentioned: once you reach the end of the year, and we know what has actually arrived. We already know how one or two have turned out successfully, and we know those amounts exceed GBP 1 billion. The thing is, it's somewhat too soon, though we're quite hopeful, given our market share and how strong our capability is, that we'll be a major participant across every one of these areas. Again, it's just a little too soon to state, with any real certainty, what that figure will be, but without question it will be very positive.
Philip Harrison
executiveTo be clear, I don't think it'll land in the tens of millions — so it's likely to be in the high, high millions.
Operator
operatorThanks. That’s all the questions we have.
Leo Quinn
executivePhil was feeling optimistic there. Great. Well, thanks to everyone for joining us. I hope you get to enjoy your summer break once this event wraps up, and we'll see you in 6 months for the next checkup. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Balfour Beatty plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Balfour Beatty plc earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Balfour Beatty plc or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.