Bannerman Energy Ltd (BMN) Earnings Call Transcript & Summary
April 29, 2026
Earnings Call Speaker Segments
Emma Culver
executiveGood afternoon, everyone, and welcome to Bannerman Energy's webinar covering the quarterly update for March 2026. A handful of attendees are still coming in, but we want to thank all of you for being with us today. Our MD and CEO, Gavin Chamberlain, is here with us for this webinar and update, covering what has been a very transformational quarter for the company. I'll share my screen now and pass things to Gavin so we can walk through all the quarter's highlights. Great. I assume everyone can see that, Gavin? Is it coming through for you?
Gavin Chamberlain
executiveAbsolutely, thanks Emma. Good morning, everyone, and welcome to this quarterly update. As Emma mentioned, it has truly been a quarter of transformation for us. We have witnessed the successful close of a highly significant transaction for the company. Over the past two years, we have been working through a strategic funding process, and this year we reached the successful conclusion of a strategic financing deal. Through the agreement with CNNC Overseas Limited, they are investing as much as $321.5 million, which splits into two separate figures. The first is a direct payment of $294.5 million, which covers their purchase of the 45% stake, and on top of that they will reimburse the capital work currently underway on-site from the 1st of July through to completion of the transaction. Combining those two elements brings us to the $321.5 million. In return, they receive a 45% interest in the Bannerman UK subsidiary, which itself holds 95% of the Etango Project. Completion is essentially targeted for mid-2026, with the FID coming shortly after that. Throughout all of this, capital work on-site continues in line with the project schedule, which keeps us on the path toward final completion and commissioning of the plant in September of 2028.
Gavin Chamberlain
executiveThere are a few things to note about this deal, and the reason it appealed to us so strongly is that it essentially allows us to build the Etango mine without carrying debt. That clearly is the route that provides the greatest financial and offtake flexibility along with lower risk. Since we know construction is fully funded, we have the luxury of examining our offtake contracting very carefully going forward. The second element of the transaction — really the icing on the cake — was the offtake agreement to be entered into with CNNCOL, under which they will buy 60% of Etango's production, giving us considerable flexibility, as I mentioned, to place the remaining 40%, which stays ring-fenced and entirely within Bannerman Energy's control. Beyond that, the long-term strategic partnership with CNNC, I believe, carries value that isn't yet visible, not only for the Etango Project but also for expanding Bannerman Energy's footprint around the world. Turning to quarterly highlights on our financial position, we have maintained our financial discipline and control over capital expenditure, which let us finish the quarter with a cash balance in the bank of $69.9 million Australian and, on top of that, liquid assets of $12.7 million.
Gavin Chamberlain
executiveWe have committed only an extra AUD 31.1 million, and the cash we hold in the bank covers that comfortably. Just as a point of interest, our expenditure on this project so far comes to $53.6 million, and during the quarter we spent just about $16 million on executing the project. Most significantly, prior to this quarter, we have observed a $6 rise in the long-term uranium price. I think this matters a great deal, since the long-term price tends to be the finest gauge of the direction the market is heading, and a $6 gain within one quarter is meaningful. It backs up our view that we will definitely be seeing a better uranium price going forward. On the project front, we have kept up our momentum. We have been very pleased with how the projects and the contracts have advanced. We are now at just about 560 people on-site, and we have in fact reached 500,000 LTI hours on this project by itself since construction began. That clearly adds to the fact that we have already recorded 16 years LTI-free, and the four Namibian contractors are carrying out work on-site. The standard of work and the safety control they have implemented is extraordinary and truly a first-world effort from the Namibian contractors and the team overseeing them.
Gavin Chamberlain
executiveI want to thank the team personally, one more time, for turning in a great quarter — done safely, on-line, at least on schedule and within budget. What I'm referring to is the bulk earthworks contract, which stands at roughly 66% complete as of today. In front of you, what you see is the start of the platform for building the wet plant. Over on the left-hand side, you can just make out the edge of the HDPE leach pad itself. The other contract, and it's moving along very well, involves us drilling and blasting our own drainage material at the site, then crushing it and building up the stockpile. When the heap leach pad is finished, we'll be in a position to put the drainage layer over the top of the leach pad and wrap up the construction. This is staying on track and sits at about 27% complete to date. Probably the most pleasing thing is having the concrete contractor on-site. We're now into serious construction work, and as you can see, the concrete work moved ahead considerably during the quarter. I was on-site myself yesterday, and this construction is now above ground level. We're very happy with how the contractor is performing.
Gavin Chamberlain
executiveHe's really laid out and split his site into genuinely secure work zones, and the progress on the primary crushing building—the largest concrete structure there—has been outstanding. The secondary and tertiary screening building has likewise risen above ground, with the columns finished up to the first level, and that too is tracking to plan. Lastly, the stockpile tunnel represents the other major piece of concrete work; its walls are finished, and preparation is underway for the roof pour—set to be the largest pour ever done by a Namibian contractor in Namibia, at just over 1,600 cubic meters of concrete in a single pour. They're currently getting ready for that pour. Then the final contractor is handling installation of the permanent water supply pipeline, which sits at 70% complete and is progressing on schedule. It essentially runs from the base station at Swakopmund across the national road to the first pump station. That, ladies and gentlemen, basically wraps up the quarterly highlights, and I'm quite happy to take questions. Emma, if you have any, please.
Emma Culver
executiveThanks, Gavin. Just a note for everybody joining: you'll find a Q&A button down at the bottom of Zoom. Go ahead and enter your questions there, and we'll work through them. Gavin, I suppose my first question — and I think plenty of folks will be keen to hear about this — is the big diesel question. That's not something we're entirely shielded from. Obviously, we've got a bulk earthworks contract running on-site, with plenty of trucks moving around. Could you talk us through diesel — how it impacts us during these early works, how it will impact us once we're into full-blown construction, and where things stand on that front?
Gavin Chamberlain
executiveYes, thank you, Emma. Diesel is clearly something we’re focused on right now. What we did was, as soon as we became aware of what was going on in the Middle East, we immediately put a strategy in place aimed at lowering the risk that we would actually have to halt work physically. That essentially meant we sent instructions to our contractors to make sure diesel tanks were filled right away, and we also assessed the overall cost risk to the project every month. Since we are only in construction and the main use of diesel right now, as you mentioned, is the bulk earthworks, the total monthly impact from diesel comes to less than $60,000 Australian. On top of that, the Namibian government has reassured us that they hold three months worth of storage for diesel. The price risk is minimal. As for the risk that the project could be slowed down because of a lack of diesel, the government has also reassured us that, effectively, they have sufficient supply at present and that they are not panicking and are not considering rationing diesel in any way. Right now, we are keeping an eye on it.
Gavin Chamberlain
executiveWe’re still watching that closely. We’re still in contact with the diesel suppliers, yet we aren’t running into issues, and right now the on-site tanks are full.
Emma Culver
executiveThanks, Gavin. Picking up on that same line of thinking about the conflict, over the longer term, with the conflict affecting supply chains for sulfuric acid, does that lead us to rethink either the cost or the benefit of an acid plant at Etango? Where do we stand on that, and what is the team thinking regarding sulfuric acid?
Gavin Chamberlain
executiveAcid is getting quite a bit of focus at the moment, and what I really want to highlight is this: regardless of whether we bring acid in from outside or whether we all pull together to back a Namibian producer of acid located locally, the exposure is comparable, since you still must import the sulfur that such a producer would have to burn in order to make the acid. The future supply risks for acid look much the same whether you are importing the acid or actually backing the building of an acid plant. Seen from that angle, our acid supply is needed toward the end of 2028. In 2 years' time the world may look completely different. We aren't devoting a great deal of effort to fretting about it, though we have clearly held discussions with acid suppliers. Another thing we are noticing is the reality that, with acid supply shrinking, prices are clearly rising. And then what you observe is that the biggest consumer of acid globally is likely agriculture and fertilizers. What we see is that when prices climb in that area, demand has a tendency to fall away. You get a kind of natural levelling out of acid pricing.
Gavin Chamberlain
executiveEven so, we can't predict the state of the world 2 years from now, but we'll guarantee a solution is ready well ahead of that point. With luck, the Middle East crisis will be over well before that time.
Emma Culver
executiveThere's a question about the selldown. Are there any warning signs? Regarding the plant's commissioning in September 2028 — that end of construction and cold commissioning — what do we need to see in order to finish that FID and finish the selldown? I think that likely flows naturally into where things stand with the CPs, since that's clearly part of completing the final transaction. Yeah.
Gavin Chamberlain
executiveOn the CPs, the only thing I can say is that things are progressing well and that fits with what we're aiming for — trying to get the deal done by mid-year, with FID coming soon after. Since our partner completing the deal is effectively their sign-off for the project to go into construction, reaching FID would be a Bannerman Energy process. We're already working on finalizing the documentation that matches that requirement from our board.
Emma Culver
executiveThere's a question that's come in. Beyond Etango, what kinds of potential cooperation opportunities might exist with CNNC? Their presence in the country is obviously strong. Are any of those collaborations showing up yet? What should we expect on that front, Gavin?
Gavin Chamberlain
executiveLooking at it from that angle, in the local area, Rössing Uranium, 68% of which CNNC owns, clearly is now also facing an acid situation. They are bringing their acid in through the port as well. We're in the middle of designing our acid storage facility, and we're talking with them about how we might potentially share some of those costs, especially for the pipes that have to be laid from the wharf to the various storage facilities. Those kinds of synergies are worth exploring. That said, we're competing companies, so we have to be really careful about what we do and don't share. Wherever working together serves mutual benefit, we'd consider doing that. The acid storage facility is a good example.
Emma Culver
executiveHow are you thinking about the Etango expansion at this point? And what is the soonest that expansion could take place?
Gavin Chamberlain
executiveOur approach on that front remains the same. In practice, within five years of Etango-8 starting operations, our aim would be to have Etango-16 producing. That gives us roughly two years to complete the study work, followed by three years for funding and construction of the project. What matters most regarding Etango-16, however, is that it would be constructed at the same time as operations are running. As designed at present, there would be no need to halt any mining at Etango-8. We could keep producing at Etango-8 while Etango-16 is being built. Another key point is that the infrastructure—power, water, and roads—requires no upgrading. They were already sized properly to accommodate Etango-16. There should be no shutdowns as we connect into the existing infrastructure.
Emma Culver
executiveGreat. Going back to the discussion about closing the transaction, how soon after that closing will the final payments from CNNC come through to us? I suppose at what stage would that then extend the project schedule — say, if there are any delays on it? At what point would we see the project timeline pushed out?
Gavin Chamberlain
executiveOur goal is to reach FID around the middle of the year, though the contract's long-stop date falls in September. As things stand, we're on track with the plan, and we don't foresee any risk of it slipping. That said, should it extend well beyond mid-year, the overall timeline could see one or two postponements. Even so, there are parts of the schedule we think we can still streamline and thereby make up for any time we might lose.
Emma Culver
executiveConsidering the $70 million in cash and $31 million in commitments, if that selldown takes longer and we encounter a delay, what's our thinking around liquidity, working capital, and overruns?
Gavin Chamberlain
executiveWe've been extremely strict about preserving a cash flow level that satisfies both us and the board, and we'll keep doing that. Our approach will be to weigh spending against the balance at every point. Ultimately, building up the war chest so you avoid landing in a spot where cash flow runs too low is very realistic. Alongside that, we're construction funded. We still have to secure working capital funding too, and that's something we're working on right now.
Emma Culver
executiveWe have noticed a few sizable RFPs coming from US utilities lately. Are we putting in bids for them, and could the fact that CNNC holds offtake ownership in any way hurt our chances when we bid on those US RFPs?
Gavin Chamberlain
executiveNo, actually I'd say the result has been quite favorable — in fact, our ties with US utilities remain solid and healthy, and several of them have sent us notes of congratulations about getting this deal done and moving ahead into construction. We're still reviewing RFPs and we continue to respond to them. But as I mentioned, we now have some added flexibility thanks to the 60% at market rates, with neither a floor nor a ceiling, which lets us be somewhat more choosy — right now there's no pressure on us to sign RFPs or to win them. It's more about making sure the pricing message reaches the utilities. We're sticking with our approach of being patient and being prepared, and this situation is one that falls under being patient.
Emma Culver
executiveThanks, Gavin. So, look, that covers the bulk of what's come in. Should anybody have anything they want to ask at the last minute, they can put it in. If not, we'll wrap things up there. Gavin, what should we be expecting over the coming quarter? Clearly, the CPs will be finished, and at that stage we're hoping to declare that FID, along with an updated construction schedule and the costs to go with it. Is there anything else on tap for this next quarter?
Gavin Chamberlain
executiveMy expectation is that it will largely be a continuation of what we've seen. The contractors, I'd anticipate, will keep delivering in line with what we expected, and at this moment we're also in the market with a tender out for the structural, mechanical, piping, and platework contract. There could be some news on that front too, since that's the next major contract we'd be awarding. Really, it's more of the same. Our approach to executing this project has been quite conservative, and we plan to keep going in that direction. The exciting part, I think, is that we genuinely could see an announcement about the deal being completed. For all of us, that would be the ultimate first prize — if we're able to get this deal done in the next quarter.
Emma Culver
executiveThere's one final question that came in, which is that we're noticing nearby African nations raising their corporate tax rates, and countries introducing free carry. Has anything shifted in Namibia? Where does the government stand at this point?
Gavin Chamberlain
executiveOver the past two months or so, our conversations with the government have been quite constructive, especially regarding the deal. We were able to sit down with the mining minister as well as the deputy mining minister, and the feedback we've received has been positive throughout. Nothing is pushing back against the conditions we already have when it comes to tax rates, and our 5% ownership via One Economy Foundation has been regarded as adequate for the requirements of our mining license. At this moment, we aren't facing any pressure.
Emma Culver
executiveThat’s great. Thank you so much, Gavin. Thanks to all of you for being here. Should anyone have additional questions about the quarter or about the project at any time, please get in touch with me. I believe most of you already have my email. You can contact me, and I’m always glad to answer any questions. Many thanks to everyone for taking part. Gavin, thank you. Enjoy your time in Namibia, and we’ll see all of you again next quarter.
Gavin Chamberlain
executiveMuch appreciated. Thanks. Thank you, everyone.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Bannerman Energy Ltd transcript — plus 133,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Bannerman Energy Ltd earnings transcripts and 133,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Bannerman Energy Ltd or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.