Bannerman Energy Ltd ($BMN)

Earnings Call Transcript · April 29, 2026

ASX AU Energy Oil, Gas and Consumable Fuels Earnings Calls 21 min

Earnings Call Speaker Segments

Emma Culver

Executives
#1

Good afternoon, everyone, and welcome to the Bannerman Energy March 2026 Quarterly Update Webinar. We've just got a few people dropping in, but I would like to thank you all for joining us today. We are joined by our MD and CEO, Gavin Chamberlain, today for the webinar and for this update in what has been a very transformational quarter for us at the company. So I'm going to share my screen and hand over to Gavin, so we can go through all of the highlights for the quarter. I assume you can all see that, Gavin, you've got that coming through?

Gavin Chamberlain

Executives
#2

Yes, no problem. Thanks, Emma. Good morning all, and welcome to this quarterly update. It really has been a transformational quarter for us, as Emma said. So we've seen the successful conclusion of a really important deal for ourselves. We've spent the last 2 years going through a strategic funding process. And this year, we saw the successful conclusion of a strategic financing deal. The deal with CNNC Overseas Limited sees them putting in an investment of up to $321.5 million, and that's broken up into 2 different numbers. The one number is a straight payment of $294.5 million, which is for them to buy their 45% share. And then they will also reimburse the current capital work that is ongoing on site from the 1st of July until the completion of the deal. And the combination of those 2 aspects gives us the $321.5 million. For that, they will get a 45% interest in Bannerman U.K. subsidiary, which in turn owns 95% of the Etango project. The completion is basically targeted for mid-2026 with the FID following shortly thereafter. And while this is all going on, the capital work on site is continuing in terms in line with the project schedule and allows us to continue along the track of actually getting to final completion and commissioning of the plant in September of 2028. A couple of points around the deal and the reason why we found the deal so attractive is it effectively puts us into a debt-free construction for the Etango mine. This is obviously a pathway that delivers the best financial and offtake flexibility at reduced risk. So knowing that our construction is funded, it allows us the luxury of being able to look at our offtake contracting very carefully in the future. And the second part of the deal and almost the cherry on top was the aspect of the offtake contract that we signed with CNOL, which is effectively, they will purchase 60% of the Etango production, granting us significant flexibility, as I said, in terms of being able to place the remaining 40%, which remains ring-fenced and totally under the control of Bannerman Energy. But over and above that is the long-term strategic partnership with CNNC, I think, has unseen value in terms of just the Etango project, but the growing of Bannerman Energy's footprint worldwide. Just in terms of quarterly highlights around our financial situation, we've continued with our financial rigor and control of capital expenditure, which has allowed us to have a cash balance in the bank at the end of the quarter of AUD 69.9 million and liquid assets in addition to that of AUD 12.7 million. We've only committed an additional AUD 31.1 million, and that is well covered by the cash in the bank. As a matter of interest, our spend to date on the project is AUD 53.6 million. And in the quarter, we spent just on AUD 16 million on project execution. Most importantly, for this quarter, we've seen a $6 increase in terms of the long-term price for uranium. This is significant, I think, in terms of the long-term price being generally the best reflection of where the market is tending to move to and a $6 increase in a quarter is significant. So this supports our theory that we certainly will be seeing an improved uranium price moving forward. On the project side, we've continued with our progress. We've been extremely happy with the way the project and the contract has moved forward. We're now sitting at just on 560 people on site, and we've actually achieved 500,000 LTI hours on the project alone since we started construction. And this obviously adds to the fact that we've already achieved 16 years LTI [Technical Difficulty] the 4 Namibian contractors are performing on site. The quality of work and the safety control that they've put into place is phenomenal and really a first world exercise by the Namibian contractors and the team supervising them. So I would like to personally thank the team once again for delivering an excellent quarter safely, at least on time and on budget. So what am I talking about is we have the bulk earthworks contract, which is about 66% complete to date. And what you're seeing in front of you is the commencement of the platform for the wet plant construction. And to the left-hand side, you can just see the edge of the actual HDPE leach pad. The other contract, which is progressing really well is we are drilling blasting our own drainage material on site, and we're crushing that and forming the stockpile. So once the heap leach pad is completed, we will be able to place the drainage layer on top of the leach pad and complete the construction. This is going -- is running on track and is about 27% complete to date. I think most pleasingly, it's been the concrete contractor on site. We're now getting into serious construction work. And as you can see, the concrete work has progressed significantly over the quarter. And I was actually on site yesterday, and this construction is now above ground level. So we're really pleased with the way that the contractor is working. He has really designated and divided the site into really safe working areas and has made exceptional progress on the primary crushing building, which is the biggest concrete structure on the site. The secondary and tertiary screening building is also now out of the ground and the columns are completed to the first level and also once again tracking according to schedule. And finally, the other big bit of concrete work is the stockpile tunnel, where the walls have now been completed, and they're in preparation now for the roof pour, which will be the biggest pour by any Namibian contractor in Namibia ever, which is just over 1,600 cubic meters of concrete in one pour. So they're busy preparing for that pour at the moment. And then the last contractor is the installation of the permanent water supply pipeline, which is 70% complete and moving ahead according to schedule. And this effectively runs from the base station at Swakopmund across the national road to the first pump station. And that, ladies and gentlemen, is basically the completion of the quarterly highlights and quite happy to take questions. And Emma, if you have any, please take us through.

Emma Culver

Executives
#3

[Operator Instructions]. Gavin, my first question, I guess, and I think that there will be a lot of people wanting to know about this is, is the big question of diesel. It's not something that we're completely immune to. Obviously, we have a bulk earthworks contract happening on site with a lot of trucks going around. Can you just speak to diesel, how it affects us in these early works, how it's going to affect us going into full-blown construction and where we're at with that?

Gavin Chamberlain

Executives
#4

Yes. Thanks, Emma. Obviously, diesel is at the front of our minds at the moment. So what we did is when we heard around what was happening in the Middle East, we actually implemented immediately a strategy to try and reduce the risk for us actually physically having to stop work. And that basically entailed us issuing instructions to our contractors to ensure that the diesel tanks are filled immediately. And then we also evaluated the overall cost risk to the project on a monthly basis. And given that we're only in construction and the predominant use of diesel at the moment, as you said, is the bulk earthworks, the overall impact of diesel on a monthly basis is less than AUD 60,000. And over and above that is we have been reassured by the Namibian government that they do have 3 months' worth of storage for diesel. And so the price risk is minimal. The risk of the project potentially being slowed down due to lack of diesel, we've also been reassured by the government that effectively, they have sufficient supply at the moment and that they're not panicking and they're not looking at rationing diesel in any way. So at the moment, we're keeping an eye on it. We keep monitoring it. We keep talking to the diesel suppliers, but we do not have problems and the tanks on site at the moment are full.

Emma Culver

Executives
#5

Thanks, Gavin. And I think to continue on that train of thought around the conflict, longer term, the conflict impacting sulfuric acid supply chains. Does this make us reconsider the cost or the benefit of an acid plant for Etango? Where are we sitting and where is the team's thoughts on sulfuric acid?

Gavin Chamberlain

Executives
#6

Yes. Acid is receiving a fair amount of attention right now. And I just need to point out is whether we import acid or whether we get together and support a local Namibian acid producer, the risks are similar because you still have to import the sulfur that they would need to burn to create the acid. So the risks around the acid supply in the future are similar for whether you're bringing in acid or whether you're actually supporting the construction of an acid plant. But from that perspective is, our acid supply is required at the back end of 2028. The world could be a totally different place in 2 years' time. So we're not spending a huge amount of time worrying about it, but we have obviously been talking to suppliers of acid. And what we are seeing as well is we are seeing the fact that as the acid supply is reducing, the prices obviously are going up. But then what you're seeing, the predominant acid user in the world is probably the agricultural sector and fertilizers. And what we're seeing is when the prices go high there, the demand tends to drop. So you are getting a sort of a natural leveling off of acid pricing. However, in 2 years' time, we do not know what the world will look like, but we will make sure that we have a solution in place long before then. And hopefully, the Middle East crisis has come to an end long before then.

Emma Culver

Executives
#7

And we have a question here on the sell-down. Any red flags, the commissioning of the plant, September 2028 end of construction, coal commissioning. What do we need to see to complete that FID, complete the sell-down. And I think that probably naturally progresses into where we're at with the CPs as that is obviously part of that final transaction completion?

Gavin Chamberlain

Executives
#8

Yes. So the progress on the CPs, all I can say is that it's moving along positively and is aligned with our intention to try and complete the deal by midyear and FID would follow shortly thereafter. Given that the completion of the deal in terms of our partner is seen as effectively the approval for the project to move into construction. So it would be abandonment energy process to achieve the FID. And we're already looking at finalizing documentation aligned with that requirement from our Board.

Emma Culver

Executives
#9

And what -- we've got a question here. What could the potential cooperation opportunities be with CNNC beyond Etango? Obviously, their presence in the country is strong. Are we seeing any of those collaborations? What will we see there, Gavin?

Gavin Chamberlain

Executives
#10

Yes. So from that perspective is in the local environment, Rossing Uranium, which is 68% owned by CNOL, obviously is now also dealing with an acid situation. So they're also importing the acid into the port. We're busy designing our acid storage facility. And we are in discussion with them around how we can potentially look at sharing some of the costs, particularly of the pipes we have to install from the wharf to the different storage facilities. So those sort of synergies we can look at. However, we are competitive companies. So we need to actually be very careful around what we do and don't share. But where we can work together for mutual benefit, we would look at doing that. So the acid storage facility is a good casing point.

Emma Culver

Executives
#11

And what are the current thoughts on the Etango expansion? What's the earliest the expansion could occur?

Gavin Chamberlain

Executives
#12

Still our strategy around that hasn't changed. So effectively, 5 years from the commencement of operations of Etango-8, we would want to have Etango-16 in production. So that allows us around about 2 years to finalize study work and then 3 years to do the funding and build the projects. The important point around Etango-16, though, is that it would be built concurrently with operations. So the way it's been designed at this point is not to have to shut down any mining of Etango-8. So we would be able to continue production in Etango-8 while we build Etango-16. And the other important point is that the infrastructure, the power, the water and the roads do not need any upgrading. So they've already been sized correctly to be able to cater for Etango-16. So we shouldn't have any shutdowns while we tie into existing infrastructure.

Emma Culver

Executives
#13

Fantastic. And just back to, obviously, the conversation around the transaction completion. How soon after that completion will we receive those final payments like the payments from CNOL? And I guess at what point is the -- does it then push out the project time line? Like any delays on that? At what point do we see a pushout of project time line?

Gavin Chamberlain

Executives
#14

Yes. So we would like to get FID midyear, but the long stop date on the contract is September. So potentially, at this point in time, we're aligned with the schedule, and we see no risk around the schedule moving out. However if it does push too far past midyear, then there may be 1 or 2 delays to the ultimate schedule. However, there are aspects in the schedule that we still believe we can optimize and actually catch up any time that we may lose.

Emma Culver

Executives
#15

And with the $70 million in cash, $31 million in commitments, if that sell-down drags on and if we see a push out, how are we thinking about liquidity, working capital and overruns?

Gavin Chamberlain

Executives
#16

Yes. So -- I mean, we've been very, very disciplined in terms of keeping and maintaining a cash flow level that is satisfactory to us and the Board and we will continue to do that. So what we would need to do is we will assess the spend versus the balance at all points. And at the end of the day is building up a war chest to make sure that you don't get into a situation where your cash flow is too low is very realistic. And on the back of that as well is we still need to -- we are construction funded. We still need to get working capital funding in as well, and that's something that we're working on at the moment.

Emma Culver

Executives
#17

We've seen some large RFPs from U.S. utilities recently. Are we bidding into those? And is there any reason that the CNNC offtake ownership could just detract from our bidding on those RFPs in the U.S.?

Gavin Chamberlain

Executives
#18

No, I think that's actually been a very positive outcome. In fact, our relationships with the U.S. utilities are still strong and sound, and we have received congratulating notes from a number of them on the fact that we've managed to achieve this deal and are moving forward into construction. And we are still looking at RFPs. We're still responding to RFPs. However, as I said, we have got a little bit of flexibility now with the 60% at market rates with no floor ceiling that allows us to actually be a little more selective in terms of -- we're under no pressure at the moment to sign RFPs and to win RFPs. So it's more around making sure that the message around the pricing is getting through to utilities. So we are continuing with our be patient, be prepared, and this is one of those that falls into be patient.

Emma Culver

Executives
#19

Thanks, Gavin. Now look, most of the questions came through. If anyone has got any last minute questions, they can pop them in. Otherwise, we will round out there. Gavin, what can we look forward to in this next quarter? Obviously, we've got the completion of the CPs. At that point, hopefully announcing that FID, an updated construction schedule to come out with that and costs. Anything else in this next quarter?

Gavin Chamberlain

Executives
#20

No, I think more of the same. I would expect that the contractors will continue to perform the way we expected. And right now as well, we are out in the market on tender for the structural, mechanical, pipe and plate work contract. So we could see some information around that as well, which is the next significant contract that we would place. But really more of the same. We've been very considered in the way we approach the execution on this project, and we intend to continue along those lines. But I think the exciting bit is that we really could see an announcement around the completion of the deal. That would be the ultimate first prize for all of us if we can complete this deal in the next quarter.

Emma Culver

Executives
#21

And one last question that's come through is that we're seeing neighboring African countries adjust company tax rates higher and nations bringing in like free carry. Is there any changes in Namibia? How is the government at this point?

Gavin Chamberlain

Executives
#22

So we've had some very positive interactions with the government over the last couple of months. So -- particularly around the deal. We managed to meet with the Mining Minister, the Deputy Mining Minister and we've only had positive feedback. We're not seeing any pushing around our existing conditions in terms of tax rates. And our 5% ownership through One Economy Foundation has been seen as sufficient in terms of our mining license requirements. So we're not seeing any pressure on us at this point in time.

Emma Culver

Executives
#23

Great. Well, thank you very much, Gavin. Thank you, everyone, for joining us. If anyone has any further questions on the quarterly -- on the project at any point, please reach out to me. I think most of you have my e-mail. You can reach me and always happy to take any questions. So thank you all very much for joining us. Gavin, thank you. Enjoy your day in Namibia, and we will see you all in the next quarter.

Gavin Chamberlain

Executives
#24

Thank you very much. Great. Thank you all.

For developers and AI pipelines

Programmatic access to Bannerman Energy Ltd earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.