Barrick Mining Corporation (ABX) Earnings Call Transcript & Summary
May 6, 2020
Earnings Call Speaker Segments
Operator
operatorGood day, everyone, and thanks for remaining on the line. I'm the conference operator, and I'd like to welcome all of you to the Barrick conference call covering first quarter 2020 results <<operator_script>>. Just a quick note that we are recording this call, and a replay is going to be posted on Barrick's Web site later today, May 06, 2020. At this point I'll hand things over to the room, where Mark Bristow, Chief Executive Officer, is standing by. Sir, the floor is yours.
Mark Bristow
executiveThank you so much. And a very good morning and good afternoon to everyone. Welcome to this presentation of our Q1 2020 results. When I addressed you roughly a year ago at this time, I could say that we had achieved excellent progress toward the goals of the merger. The company's structure had been shaped to suit its purpose of becoming a model of a modern mining business. Strong regional management teams were in place, ownership of the orebodies had been returned to the mines, costs had come down, and the balance sheet had been made stronger. Over the last year, we have worked to further enhance how well we operate. And alongside all of this activity, we completed formal transactions that create value: the historic Nevada Goldmine’s merger, which brought six Tier 1 mines into our portfolio; the sale of our stake in KCGM and the buyout of the Acacia minorities, which let us resolve that company's dispute with the Tanzanian Government and assume control of its assets. In quarter one, we combined our Massawa project with Teranga's nearby Sabadola mine, in a deal that has already delivered significant value to all of our stakeholders. The past quarter's results, published earlier today, demonstrate that we are actively building on the solid foundation established in 2019, as we look toward the next phase of value creation.
Mark Bristow
executiveI want to draw your attention to the cautionary statement. Anyone wanting to read a bit more can find it on our website. The very fact that we're holding this presentation virtually today captures the harshest reality of our era. The COVID-19 pandemic has confined a great many of us — at home, at our operations, or in other places. History will sit in judgment on how our governments handled this black swan event, which arrived with no warning, set off an extreme crisis, and will carry unforeseeable consequences that will probably transform the world permanently. Speaking for Barrick, though, I can report that our team reacted right away to the first signals of the crisis, and as a result, we were ready to handle its effects on our people and on our business. Detailed action plans were rolled out quickly across every site and office we operate, within an overall strategy we refer to as the four Ps approach. Those Ps are pro-activity, preparedness, prevention and perspective. Although our top priorities have been protecting the health and safety of our workforce and communities, and keeping our logistics and supply chain secure, Barrick has also been working with our host governments since mid-February to assist their own campaigns against the pandemic. Some of the community assistance measures we've taken appear on screen.
Mark Bristow
executiveSo as you're able to see, up to now we've given over $20 million to host governments so they can fund buying medical supplies and facilities. A lot of these nations face economic hardship, and poverty, as we discovered, is a worldwide issue stretching from Nevada all the way to Tanzania. At Barrick, we're hopeful that what we're doing will assist not just those who are sick but also people hurt in other ways by COVID-19. The reality that sustainability sits at the heart of Barrick's management philosophy without a doubt made us ready to soften the pandemic's blow. Last month we released our Annual Sustainability Report, and you'll find it online. In it is what we consider an industry first: an ESG scorecard that measures how we perform against 18 key indicators and lifts accountability to a new level. We awarded ourselves a B rating, reflecting better overall sustainability performance and headway on many of our KPIs. It likewise recognizes that more work remains. We intend to refresh the scorecard at the close of the second quarter, after some of our peers have put out additional 2019 information. Our employees' health and safety is vital to our business succeeding. When I addressed you last year, I stated that I wasn't comfortable with Barrick's record in this area.
Mark Bristow
executiveHowever, as this slide shows, things have improved consistently from that point onward. Our goal is for every operational mine to hold ISO health and safety certification by the close of next year. Every Barrick mine ought to have obtained its environmental ISO certification by later this year as well — specifically, before 2020 ends. During the quarter just passed, we had no significant environmental incidents. Stewardship of the environment is something Barrick treats with real seriousness. Our clean power strategy is cutting our carbon footprint meaningfully, and we've committed to a target of at least a 10% further reduction in emissions over the next 10 years. Water matters too — it's a precious resource, and conserving it ranks high on our environmental priorities. Once again in the first quarter, we raised our water reuse and recycling rate, reaching 77%. At Barrick, responsibly closing a mine counts just as much as discovering new ones through exploration. Approval of the tailings retreatment project at Golden Sunlight, our Montana mine, speaks directly to that principle. It will lower long-term water treatment needs and stabilize the old open pit, while generating revenues that help offset rehabilitation costs.
Mark Bristow
executiveI should say that following the manager, we had to address several significant legacy problems, and Tanzania has made things harder, yet we are tackling these issues methodically. Barrick likewise keeps investing in the communities where it operates. During the previous quarter, we devoted $4.2 million to development projects, on top of COVID-19 assistance. Moving on to the results: this table illustrates how our performance in the first quarter measured up against our KPIs. The bullets are self-explanatory, though I will address the main points during this presentation. Despite COVID-19 and the lockdowns, Barrick got off to a strong start this year, with gold output and costs in line with guidance for the quarter. Copper costs per pound came in significantly lower, which shows how resilient the business is to lower process. As you know, we moved Porgera into temporary care and maintenance in late April after the government responded to our request for an SML extension. I will go into more detail later in the presentation, but this step has obliged us to pull our 2020 guidance for Porgera for the time being. Our updated Group guidance, excluding Porgera, now stands at 4.625 million ounces, and group cost guidance remains the same.
Mark Bristow
executiveEven with all that going on, we're still in a strong position to hit the updated guidance we've set for the year, thanks to the solid start we've made. As you can imagine, things at Porgera are changing fast. So we'll share more on where we stand when the time is right. As we said before, gold output for the second quarter should come in below the first, reflecting mine sequencing and scheduled maintenance. On top of that, bringing the Veladero workforce back safely and steadily after Argentina lifted its quarantine restrictions will also weigh on results. Going forward, we expect production to pick up in the back half of the year, consistent with our plans and guidance. Strong results across every operation meant the upside from higher gold prices was captured and flowed through to the bottom line. Free cash flow rose to $438 million, and net debt fell another 17% to $1.85 billion, with nothing significant maturing before 2033. Adjusted net earnings came in at $0.16 per share, and the quarterly dividend — supported by the strong balance sheet and the free cash flow outlook — was kept at $0.07 per share. I've always said that to be a world class business, you need a global presence.
Mark Bristow
executiveSo, as you can see here, Barrick has a strong presence in every major gold district globally, with the exception of Russia and Eastern Europe. Last year, brownfield exploration around our existing assets more than compensated for the reserves we depleted through mining — and, I should note, at a higher grade. We expect similar results this year. At the same time, our generative teams are searching farther out for the next tier one and tier two discoveries. We're also expanding your horizons into Saudi Arabia, Japan, and Asia along with the Pacific Rim. So we'll begin our tour of the operations in Nevada, which we consider our value foundation. Carlin ranks as the biggest of our Nevada operations, and with a strong management team at the helm, this mine would stand as an impressive standalone mining company. Output at Carlin came in slightly below quarter four because of scheduled autoclave maintenance and reduced roaster throughput of Carlin ore, as higher grade Cortez ore took the place of the comparatively lower grade Carlin ore in the roasters' feed mix. Total cash costs matched the prior quarter. And I should add, the Carlin trend is the busiest exploration area within Barrick's portfolio and holds genuine potential for continuing to replace the gold we mine far into the future.
Mark Bristow
executiveGoldrush is now folded into the Cortez mining complex, and the deep south underground development remains on schedule to begin adding to production near the end of the third quarter of this year. Feed grade overall came in a bit below the prior quarter, but our cost-control work produced a 10% reduction in total cash cost per ounce versus the quarter before. And naturally, Fourmile still holds additional potential for extending mine life, though it is not yet part of the Nevada gold mine’s portfolio. At the Turquoise Ridge complex, bringing the two teams together, along with the geological models from both legacy operations, is essential to realizing the full potential of this tier one facility. That effort is still underway, though I would note it is heading in the right direction. Meanwhile, building of the Turquoise Ridge third shaft is proceeding on schedule and within budget. It is another important project that will unlock value from the higher grade underground resources. Among the smaller Nevada mines, Phoenix delivered a particularly strong quarter, with production up and costs down. Long Canyon, where permitting for the pit expansion is ongoing, reported lower output, but costs stayed well contained.
Mark Bristow
executiveNevada is arguably the planet’s richest gold district, so the opportunity inside Nevada Gold Mines’ portfolio is huge. I’ve already brought up Cortez deep south and the Turquoise Ridge third shaft. Beyond those, though, the final feasibility study for the Goldrush project remains on schedule, and drilling at Fourmile keeps growing the mineralization. Over at Carlin, our attention is on Greater Leeville — the region north of the existing Leeville underground operations, plus the surrounding area. At Turquoise Ridge, the integrated geological model reveals that in the space between and beneath the Turquoise region and Twin Creeks ore bodies, our favourable host drops, which are surprisingly under explored and where tier one potential still exists at depth. Mineral resource management and exploration at the operating mines concentrate on optimizing their mining plans and extending their ore bodies, while the exploration teams are searching for additional tier one assets. So let me stay on Fourmile a little longer: we already hold a substantial mineral inventory there and we see potential for much more. As this slide shows, an oscillated hole 900 meters north of Dorothy indicates further extensions to what is already a significant mineral system.
Mark Bristow
executiveThere are also some really encouraging results from drilling waste at Fourmile. Our aim is to keep going with the drilling program while pinning down the area's full potential and establishing a framework at district scale. Meanwhile, our mineral resource teams are drilling continuously to prove continuity and achieve improved stope definition. We're likewise working through permitting to convert Nevada gold mine's coal-fired TSF power plants into a dual fuel system, letting the facility generate power from natural gas. Approval of that permit is anticipated later this year, with commissioning targeted for the second quarter of 2022. Thanks to the conversion, the facility can cut carbon emissions by up to 50%, which works out to about 650,000 tonnes of CO2 saved annually. A new solar project at the TSF power plant is moving ahead as well. Our intent is to permit a 200 megawatt facility, even though phase one will be 400 megawatts. We anticipate receiving permits somewhere between quarter three of this year and the first quarter of next year, and the first 100 megawatts of power would lower our greenhouse gas emissions by another 130,000 tonnes of CO2 each year.
Mark Bristow
executiveNow heading north into Canada. After installing a fresh management team and altering how it ran last year, Hemlo keeps progressing toward possibly reaching tier two status. It has, among other changes, adopted an underground contract mining model, and the open pit operation is set to finish in the second half of this year. As you can see here, Hemlo's results have improved markedly since we restructured it. Even so, on the operational side there is more work ahead before it achieves the efficiencies and throughput needed to be a genuine tier two operation. By bringing a new, disciplined lens to comprehending the orebody and the controls on mineralization, we are now examining an extension of its life past 10 years, and also reassessing what the entire Hemlo district could offer. Here is a summary of our North American assets. The figures make the point on their own. Also worth highlighting is that Goldrush and Fourmile will guarantee Cortez, Carlin and Turquoise Ridge hold on to tier one status far into the future. A major effort has gone into reviewing regional geology, and as a result multiple framework drilling programs are now running to close gaps in what we know, unlock usage areas and set the stage for targeting and defining mineral inventories.
Mark Bristow
executiveWe’ve also been revisiting our closure portfolio with fresh eyes. I already mentioned a different strategy for Golden Sunlight involving tailings retreatment, and another illustration of value being revealed comes from our partners at Eskay Creek up in British Columbia. Now shifting south to the Dominican Republic, where the Pueblo Viejo management team is performing exceptionally well as the mine gets ready for the expansion project. Output during the quarter came in below the previous quarter because of the planned mine and processing sequence. Even with that production level, costs stayed very well contained. We anticipate lower production in the second quarter owing to annual maintenance schedules, after which it should rise to within guidance by year-end. As an aside, PV became the first of our mines to work with the government on COVID-19 rapid screening tests. Engineering design and costing for the plant expansion were finished during the quarter. The existing El Llagal tailings storage facility can support expanded production through 2028. That means the plant expansion program is now able to move forward independently from the TSF 3 program. A mix of COVID-19 and the postponement of the Dominican Republic’s presidential election to July has slowed the TSF 3 permitting process, and we are collaborating with the government as well as the political opposition to get the program back on track.
Mark Bristow
executiveWhat you're seeing in this slide is the Quisqueya power plant, which has been successfully switched over to natural gas — one more significant step toward cutting our greenhouse gas emissions. Veladero faced considerable difficulty as it entered the quarter, largely owing to how the Argentine government handled COVID-19: first it halted the mining industry, then it permitted operations to resume, though this time with social distancing restrictions in place. Two additional difficult quarters lie ahead, in our view, and full-year production at this operation will probably land at the low end of guidance. At Veladero, projects such as the power transmission line, the Phase 6 pad expansion and construction of the air strip were wound down because the government's limits on camp occupancy during the COVID-19 outbreak made work impossible. Commissioning of the power line has been pushed back from mid 2020 to the close of this year, while Phase 6 commissioning slips by three months. Still in South America: the El Indio trend, running along the Andes and encompassing Veladero plus our Pascua-Lama project, holds abundant potential for major gold and copper discoveries. With a full exploration team now in place for that region, we have begun an extensive compilation of legacy data in order to generate new ideas.
Mark Bristow
executiveWhen it comes to Veladero itself, the signs suggest satellite deposits might stretch its lifespan past the tenures it holds today. Here's a look at our footprint across Latin America, where you can see a mineral inventory nearing 100 million ounces of gold as well as ownership of several of the biggest undeveloped assets in the region. Our belief in how prospective this ground is remains strong, which explains our concentrated expiration work in this area. Turning to Papua New Guinea, the government's recent reaction to our engagement over extending the SML was, as you know, a surprise. As a result, we had no choice but to put the mine on care and maintenance. Last week we filed a lawsuit in the PNG court seeking to quash that government decision. A preliminary order came back directing the government to cooperate with our efforts to secure and protect the mine, and it also directed the government to enter negotiations with us in an attempt to settle the matter. So now let me turn to my old hunting grounds in Africa. Beginning at Loulo-Gounkoto, where throughput and recovery rose and production, though a bit behind the prior quarter, remained ahead of plan. Development of the complex's third underground mine at Gounkoto is set to begin in the fourth quarter of this year.
Mark Bristow
executiveAt the same time, five megawatts—the first installment of capacity from Barrick's inaugural solar facility in Africa—are now in place. Commissioning, though, must wait until contractors who are presently locked down can arrive, and the rest of the 20-megawatt capacity is still slated for completion by the close of September this year. Kibali in the DRC got off to a strong start, lifting output while bringing costs down, and it is on course for yet another solid year. The optimal battery storage required to cut down on the diesel generators kept as spinning reserve has now been installed and commissioned. Brownfields and greenfields exploration prospects that continue are also a promising sign that the mine will once more offset its reserve depletion this year. Production at Tongon and Kalgoorlie stayed on plan with lower unit costs, and this mine is on track to hit its guidance for the year. The mine keeps making a substantial cash contribution to all of its stakeholders, and exploration aimed at extending its life past the present two years is ongoing. West Africa remains another thrilling region in which to search for gold. New Loulo-Gounkoto keeps proving able to deliver fresh opportunities for adding resources and reserves, and a target of interest has been pinpointed in the far north.
Mark Bristow
executiveAt the Bambadji joint venture, our modeling work has brought to light fresh mineralization styles, which points toward what could be a new prospective corridor running along the prolific Senegal Mali shear zone. And over in Tanzania, we have achieved tremendous progress ever since we set up the Twiga joint venture in January, which has strengthened the partnership we share with the government. North Mara has made a successful shift from contractor mining to owner mining. Concentrate exports that the government had suspended earlier, during its dispute with Acacia, have now resumed and will be recorded in net income as of quarter two. In Tanzania, we have by now put most of the key issues between Acacia and the government to rest. Even so, some legacy issues remain that the company left behind in its wake, and those still need addressing. I have confidence that we will get these resolved. Meanwhile, what we have observed so far has left us feeling quite bullish regarding resource extensions and new targets in the area around the mine. Elsewhere in Tanzania, Bulyanhulu holds enough tailings material to keep the plant operating as we move forward with restarting underground mining there, on plan, later this year. Buzwagi, too, is processing stockpiles. And it is interesting that we have found some potential new resource opportunities at Buzwagi, which are being evaluated at present. After the incorporation of Tanzania, we have ramped up exploration across the highly prospective Central and East African regions, where we now maintain a strong presence.
Mark Bristow
executiveEven though it's still early, we've spotted some promising opportunities, and the only thing I can say is keep watching that space. Randgold's history demonstrated that Africa is somewhere you can find major gold deposits and turn them into world-class mines, and at the same time make a positive difference in countries held back by underdevelopment. Our asset base is strong, and we have two tier one mines on the continent. And although Africa itself still holds enormous potential, we're also searching further north for growth. We already have a foothold in Saudi Arabia, and we're taking a close look at the Nubian-Arabian shield, which, despite its prospectivity, has so far produced just one significant gold mine — the Sukari gold mine in Egypt. In our copper portfolio, Lumwana and Jabal Sayid both raised output and cut costs. Notably, at Jabal, exploration has been highly encouraging, and step-out drilling has intersected very high-grade mineralization that suggests extensions to mine life. Production at Zaldivar was affected by lower grades and recoveries. The development of Zaldivar's secondary sulphide leaching project, which our partner Antofagasta operates, has been temporarily delayed because of COVID-19 movement restrictions. While keeping operational performance very strong matters to us throughout the Barrick Group, we keep asking how we can bring more value to our operations, and innovation and technology are central to that.
Mark Bristow
executiveEfforts have carried on with the enterprise resource planning system we implemented, along with its worldwide deployment, and the initial rollout is set to start across the Nevada gold mining group in quarter three, just as scheduled. Even with the difficulties brought by COVID-19, we are still on course to finish this extensive rollout project before the year is out, and after that we intend for remaining regions to follow in 2021. This global design, which is more streamlined and standardized, will strengthen further our capacity to report cost and efficiency data in real time and, even more importantly, to manage using real-time information. We likewise pressed ahead with digital innovation at our underground mines, including projects that let us now remotely track, in real time, machines, their location, productivity and health, plus that of operators, which boosts our efficiencies and predictive maintenance capabilities. Since we are already fairly advanced in underground automation, our focus has now shifted to surface mining, with haulage drilling projects moving forward through the quarter. Our surface haulage proof of concept, which permits both manned and unmanned operations inside the same zone, was brought to a successful conclusion this quarter. During the quarter, we also began our first trials of battery powered electric underground equipment, which we think could potentially reduce operating costs and raise efficiencies.
Mark Bristow
executiveIn a similar vein, the team at Yalea underground was involved in creating a system that switches secondary fans on and off automatically through the use of personal RFID tracking systems, and that should help lower power consumption. That project is now being rolled out at underground mines across Africa. We've mentioned micro grid stabilization at Kibali, and we are seeing meaningful gains from our advanced process control systems in the milling and processing circuits. Through the use of these real time data and model predictive control to optimize the circuits quickly, we can raise throughput and cut reagent usage. As promised, together with this year's annual report, we published what we believe is an industry first 10 year gold production plan, which you can see here. I will note that Porgera remains in the forecast, though its contributions are shaded a different color because that asset is currently in care and maintenance. What sets us apart from our peers is that our 10 year plan is built both on our portfolio of tier one strategic and embedded projects, all of which have post plus 10 year life of mine plans except for Tongon. As a result, our business has an outstanding value foundation that does not need new Greenfields builds or discoveries to underpin our 10 year plan, which gives our investors the comfort they require to invest for the long term.
Mark Bristow
executiveNaturally, any finds or purchases will strengthen what we offer. True to our mission, we possess the quality, the management, and the financial depth needed to keep creating value for every stakeholder, and to give Barrick the free cash flow to put into its own future. Ladies and gentlemen, as always I'll close with the comparison of share price performance. Barrick's guiding principle holds that the finest assets paired with the finest people produce the finest returns, and this is one way to gauge that. So far this year, Barrick's share price is up 45%. And measured from when the Randgold merger was announced, the gain is considerably larger, beating both the industry and the gold price. Thank you for listening. Most of our senior executives are on the call with me. With that, we'd be glad to take whatever questions you may post.
Operator
operatorThanks. At this point we're opening things up for questions <<operator_script>>. Chris Terry at Deutsche Bank has the first one. Go ahead.
Chris Terry
analystHi Mark and team, I have a couple of questions, and I'll separate them one by one. Starting with the first, which concerns cash flow and CapEx for the coming year. I suppose quite a few companies have been reducing their CapEx, citing fewer essential workers being present on site. And in the context of Porgera as well as the power plant — I believe you mentioned something around Veladero — I was just wondering whether you could say a bit more about where CapEx is likely to land. Then maybe one more regarding working capital: since you've built up sites ahead of COVID and so on, are there any considerations for 2Q and then the back half of the year on that front? That's my first question. Thanks.
Mark Bristow
executiveTo begin, I’ll hand things over to Graham in case I overlook something. As you mentioned, Veladero has certain rescheduling needs. Our whole focus has been on trying to complete all the capital spending we have across the group. And even though we’ve pushed back both the number six expansion and the power line, we’ll still get a great deal of that finished—if not all of it—during this year. On the airstrip, we are right now working to try to mobilize that team so that we can make sure the strip is in place before winter begins. The reason is that it has to give us our capacity to re-mobilize and get those other capital projects up and running as quickly as possible, and make things more efficient once spring comes. Nevada is pretty much on track with its key projects. For Porgera, there wasn’t a big capital spend forecast, because everyone was waiting for the SML extension outcome. And the rest of Africa is on track with all its key projects—as I said, the shaft at Turquoise Ridge and the development at Goldrush are all on track. At Hemlo, we are currently busy working with the authorities to ensure the new underground contract can be mobilized and take over the previous contract as agreed, so that work continues.
Mark Bristow
executiveSo we're handling the arrival of some of those key Australian supervisors and skilled people so that transition can happen. As a result, we still expect to keep our capital guidance as it is. That said, some of that spending will likely be scheduled in a way that takes us nearer the lower end of the guidance rather than the upper end. But you can be sure we're all putting in a great deal of effort to keep our investments on schedule. Graham, would you like to add anything?
Graham Shuttleworth
executiveMy sense is that it covers things pretty thoroughly. The one thing I'd add is that in Nevada our capital has gone up somewhat. One of the projects involved is the solar power that Mark mentioned during the presentation. So that's a new element we've brought into the mix. But as Mark says, looking at the big picture, we remain quite comfortable with the guidance we issued at the beginning of the year. And as things develop, we'll fine-tune that figure over the course of the year.
Mark Bristow
executiveRegarding cash flow, Chris — let me address that specifically. As you're aware, there are considerable upward pressures on cash flow stemming from the gold price, and that's a major area of focus for us. The dividend was maintained at its existing level. We feel good about our current position. Our liquidity and our forecasts leave us quite confident. So I believe we're well positioned to make sure we can deliver on our plans. And beyond that, to seize any opportunities we may be able to unlock during this period to grow our business further.
Graham Shuttleworth
executiveYes, regarding working capital — I'll just build on that point. It's somewhat elevated relative to the prior quarter. We typically do see working capital rise during the first quarter. And if you look back at the same quarter a year ago, you'll notice a comparable uptick in working capital. That's partly driven by the timing of payments we accrue over the year and then disburse in Q1 — employee incentives, for instance. We also made an installment payment to EPRA in Argentina, related to the power line. So a handful of unusual items nudged it up somewhat, but this is typical for this point in the year.
Mark Bristow
executiveAnd lastly, Chris, regarding inventory build-up, you've asked plenty of questions about that. But on the inventory side, as you're aware, Riaan and his team throughout the group acted very quickly to raise our stock of consumables and fast moving items to 3 months and beyond. Yet he also has a plan in place to reduce that by year-end. So that's one piece of our working capital that we will manage actively.
Chris Terry
analystAnd if I could just ask one more thing as a follow-up, regarding Pueblo Viejo, you covered several of the specifics there with the election and so on. Could you remind us about the present plans for the expansion and the kind of timeline you would potentially foresee for the mill expansion? Thanks.
Mark Bristow
executiveAlright, so the mill expansion is moving forward as we planned. We're currently focused on placing orders for the long lead items. The feasibility study for the actual plant expansion has been finished. And as I mentioned, at this point a gap is opening up between that and the TSF permitting process. But once again, we have support — bipartisan support — for this project. What we need to do is get out into the field and finish the initial work along with the consultation, community involvement, and engagement, which has been somewhat held back up to this stage. We still have a bit more engineering work to do on the fatal flaw investigations. We're fairly comfortable with the answer, but that work needs to be done. Beyond that, we're in good shape to make sure that storage facility is in place when we need it, which is after 2024, I believe. John Steele, are you on the call?
John Steele
executiveCommissioning of the expanded plant is currently scheduled for early 2022. Also, as Mark noted, the TSF capacity we have at El Llagal carries us all the way into 2028. So ahead of the project moving forward, that isn't a bottleneck for us.
Mark Bristow
executiveOur original plan was to bring TSF 3 into service starting in 2024 if that proved workable under the existing program. Even so, should that program slip, the broader expansion would not be affected.
Operator
operatorBarclays' Matthew Murphy is up next with a question. The floor is yours.
Matthew Murphy
analystMy questions concern mainly how sensitive your guidance is to the oil price—and, I suppose, to 4x as well—though $65 oil is still assumed in it. I'm just wondering whether you have a sense of that sensitivity, or of sensitivity to diesel prices, or any metrics of that kind you could share?
Mark Bristow
executiveMatt, to go back to your point, there are pluses and minuses here. The way we see it is this: the COVID challenge has definitely brought some extra costs into our business. At the same time, lower oil prices have worked in our favor. A few of those effects get softened, especially in Africa, where oil pricing is far more structured and doesn't reach consumers as fast as it does in parts of North America. But as a rough figure, $10 on oil comes to roughly $8 per ounce, just as a broad number. Keep in mind that our hydrocarbon mix is quite different — some natural gas, some diesel, some heavy fuel. But as a rule of thumb, that's roughly the number.
Matthew Murphy
analystAnd then, just a quick point regarding what was disclosed about that tax claim. I'm curious whether you view this as having any connection at all to the mine's requirements for new ore, or is it an entirely separate matter?
Mark Bristow
executiveMatt, this is a really complicated situation. I’m not sure whether you’ve seen the judge’s order that came down last Friday, but one thing in it was a very explicit directive that we avoid making comments about this process while we concentrate on trying to reach a solution that works for both sides going forward. So it wouldn’t be appropriate for me to comment on that question, if you don’t mind.
Matthew Murphy
analystSo maybe I could just ask about that court matter. I believe your next hearing is on May 8th. Could you say anything about whether there's a chance a resolution might come at that point, or is it more of a preliminary hearing just to check how things are progressing?
Mark Bristow
executiveWell, all I can say is that, as you know, I’m very committed to finding solutions and have spent my entire career working toward ensuring we have constructive partnerships with our stakeholders. And that commitment is no different when it comes to Papua New Guinea. And the order was very clear that we engage in a committed way to working to find a solution. And he also indicated that should it not be possible for us to do so, he would be minded to appoint a court-appointed arbitrator to ensure that we do come to a solution.
Operator
operatorGreg Barnes from TD Securities has the next question. Go right ahead.
Greg Barnes
analystMark, I was going to ask whether you’ve actually engaged with the government, but I suppose we’ll set that aside for PNG. On capital allocation, you’re producing a lot of free cash flow now, and I expect you will going forward. One of your competitors suggested that, in their view on free cash flow, 50% would go back into the business and 50% would be returned to shareholders. Is that a framework you’d agree with, or something Barrack would pursue?
Mark Bristow
executiveGreg, as you're aware, copying anyone else has never been my style, and I don't plan on beginning now. We steer clear of putting out work that isn't distinctive and dependable. Barrick's journey to this point has been remarkable. Going back to 2015 versus $12 billion today, we can claim the strongest balance sheet across the industry—the mining industry. Accordingly, our dividend policy has been set against the 1,200 long-term gold process. In light of the circumstances we confront now and the unprecedented scenario lying ahead, it's sound practice. We believe—and our Board shares this view—that we keep our dividends in place, since we know we can afford them. We also make sure we hold the financial muscle to come through this challenge and to chase other opportunities, value opportunities, if they should emerge in this very dynamic environment. Then, as I've said previously, our objective is very clear: to reach a point where we shift from a dividend policy supported by the robustness of our P&L to a more standard style dividend policy—perhaps along the lines we used at Randgold, where we agree to pay out a certain portion of our cash flow, falling provisions for our long-term business investment, and always balancing whether we are able to at perform the market on value creation.
Mark Bristow
executiveAnd certainly, all signs suggest a stronger gold price, with certainly more upside than downside. And on top of that, the sort of full cost reduction and new gold supply, every indication is that maybe we have to review that policy earlier rather than later going forward. But I think right now we're all clear that a strong balance sheet independence of capital markets financially is a good place to be in the situation we find ourselves today.
Operator
operatorThe following question is from Josh Wolfson at RBC Capital Markets. You have the floor.
Josh Wolfson
analystI just have a question about Tanzania, regarding the final resolution to sell the inventory and pay off the outstanding amounts. What deliverables are still needed, and what timelines should we add? Then, from an accounting standpoint, how are you going to see that flow through the statements?
Mark Bristow
executiveSo Josh, as we speak, everything is finished and wrapped up. Shipments are moving, and we have a substantial amount of concentrate to send out. Some payments have already come in. That's the current status. As we've said, you'll see the bulk of that revenue show up in quarter two. Depending on how the final logistics play out, a portion could land in early quarter three. But all that remains is making sure that concentrate gets to the port and reaches the processing facilities via our agents. So that's genuinely where things stand, and nothing else is outstanding. It's fully done.
Graham Shuttleworth
executiveJust to build on that, Josh, regarding the accounting treatment. Those ounces, of course, were produced back in 2017. So when it flows through in the second quarter, you'll clearly see a mismatch between sales and production, since sales will exceed production. That inventory's cost is still carried on our balance sheet, so as we sell that gold, we'll apply that cost. And the proceeds from those sales will, of course, go to the individual operations. Those proceeds will then be divided among the shareholders under the 84%, 16% split. That said, we do of course have our 50 to 50 sharing arrangement. So ultimately, everything will be trued up on the basis of that 50 to 50 sharing going forward.
Mark Bristow
executiveAnd I’d just add one thing there. Josh, that initial $100 million is going to be the first payment under the $300 million settlement agreement.
Graham Shuttleworth
executiveJust to reiterate, that $300 million has already been accrued for, so it won't affect our earnings — it will only affect our cash flow.
Josh Wolfson
analystJust to be clear, that falls under operating related item.
Graham Shuttleworth
executiveWhat exactly does the operating-related option include?
Josh Wolfson
analystIs the cash flow from operations line just the amount paid to the government for taxes?
Graham Shuttleworth
executiveThat's a tax payment.
Operator
operatorCarrie Smith from Haywood Securities has our next question. The floor is yours.
Carrie Smith
unknownMark, can you explain what approach you're taking for COVID testing at the sites when it comes to asymptomatic employees who aren't showing any signs?
Mark Bristow
executiveSo we're not there yet. What we've accomplished so far, Carrie, is—I'd say this is the key piece, and it's something folks didn't quite grasp early on—education, being prepared, and screening. By screening I mean temperature checks, confirming everyone completes a self-assessment form before they head off to work each morning. Then reacting right away to any risk factors—a high temperature or any kind of symptoms—by isolating them, tracing immediately, isolating further, and then testing. That's how we've handled it. To this point, we've had no confirmed transmissions inside our operations. We've definitely had staff test positive. At the same time, we've launched a major initiative involving rapid test kits. The Dominican Republic was the first country to partner with us on this. And we've definitely built out our protocol for using it and are refining it all the time. In the end, that kit will be a crucial test for gauging the kind of immunity, herd immunity, as we move forward. We've also carried out, together with the rest of the industry, a large project that's currently being rolled out in Argentina.
Mark Bristow
executivePeru has also begun distributing the test kits. In Africa, Riaan and his team are collaborating with the countries hosting us on that effort. In North America, we have an abundant supply of proper DMA or PMR tests. And once more, I believe we will continue to improve how we manage our employees at the sites. But that is the approach we have chosen. I think we have been considerably more successful at handling the pandemic and at keeping both our people and the disease visible, instead of giving in to the temptation to lock everything away, so that you then cannot see its real impacts. And the team — I have to say — the Barrick teams have performed remarkably well. And perhaps I could ask Catherine to walk you through some of the steps and the way she and the team handled the situation in Nevada, which is truly a strong example, on a large scale, of how the rest of Barrick has tackled this crisis. Catherine?
Catherine Raw
executiveOkay, addressing Carrie's questions straight on — the screening approach we've been running has served to reduce risk regardless of whether someone shows symptoms or not. To give a picture of how big this is, Nevada gold mines has 7,000 employees, and quite a few more once contractors and anyone else arriving at site are counted. To begin with, entry now happens at one point only, and screening happens there. The screen is a questionnaire asking about symptoms, about contact with anyone showing symptoms, and about travel — specifically, at the outset, whether they've been to any place where COVID posed a significant risk. That gave us the ability to isolate the people flagged by the questionnaire, symptoms or no symptoms. What we've seen, then, is that across roughly the past month and a half — eight weeks now — 593 employees in total have been away from work for an average of seven days, whether because screening sent them home, with 113 of those having self-selected because they identified their own risk — immunodeficient, some other reason — or because symptoms appeared or they'd been caring for someone symptomatic.
Catherine Raw
executiveAnd then the other group, of course, is a quite small minority whose situation was impacted because their children aren't attending school. Altogether, that's 593 people, averaging seven days each. What matters more, though — and I believe this is significant — is that out of those 593, 495 have gone back to their jobs; 83% have come back to work. What we observed, then, is that the actual effect landed in roughly the initial three or four weeks, essentially across late March and during April. And at this point we're starting to shift toward what I'd call — well, not a normal environment, but a normalized one. That means whenever a positive case arises — we've recorded seven confirmed positive cases in NGM to-date — we can contact trace everyone with whom that person has been in contact. We've reduced batch sizes as much as we can in order to lower risk. After that we have those individuals self isolate. Next they either get tested or remain in quarantine until the 14 days finish, or they get tested and come back negative, after which they can go back to work. That's the procedure enabling us to account for those asymptomatic people along with those showing symptoms.
Operator
operatorCarrie Macquarie from Canaccord Genuity has the next question. Go right ahead.
Carrie Macquarie
unknownI'll step back and ask a broader question about your 10-year plan. That plan calls for 5 million ounces over 10 years. I believe a peer of yours has a comparable flat output profile across 10 years. I'm just curious what you think about why this business can't scale. For instance, could production grow in an accretive way, or once a company reaches that size, is a flat profile essentially the new normal?
Mark Bristow
executiveCarrie, if you take a look at that graph, a few points stand out immediately. First, over the initial five years, we reduce costs, which boosts cash flow — and I assume you've factored that into your model, both as capital turning into proper sustaining capital, since what you're describing is a steady-state business rather than one that's growing, and then those costs decline. Then, on the margin side, we expect that to carry through the latter five years. And again, if you're trying to benchmark us, there's simply no comparison, because we don't have to spend big on anything. So there's no huge capital spike. As a matter of fact, the capital we discussed in today's presentation truly positions us for the remaining 10 years. The major items are PV and Dominican Republic, the shaft, and Turquoise Ridge. The rest, though, are all truly sustaining capital — even Goldrush is merely a continuation of development to produce additional ounces. And I believe that's the highlight of the Barrick 10-year plan, founded of course on tier one assets, which means you have substantial production for over 10 years in your business plan grounded in a $1,200 long-term gold price.
Mark Bristow
executiveSo if you look at this business, it's a real business where the growth then shows up in financial delivery, in profits depending on the gold price that you received. Beyond that, we're spending $170 odd million a year on exploration. And as you've seen just in the last 15 months, we're not shy about creating M&A opportunities that deliver real value. So that's the difference — this isn't a sustaining business, or a business you'd refer to as consistent production. It's a solid foundation on which to keep going after value-creating opportunities for our owners. And I think that's — hopefully you get it now, because you're definitely missing something. And again, there's nothing in this plan that we can't take you to and show you. So there are no soon-to-be-discovered ounces. There might be some ounces where we need to change the definition, take out some of the risks. But it's already in the plan and accessible from current infrastructure, or infrastructure that we're all committed to invest in during the next four or five years.
Carrie Macquarie
unknownSo what I’m getting at is this: Randgold, you managed to expand output across a lengthy stretch. There’s apparently a belief out there in the industry that after you reach 5 million ounces, that’s the ceiling — 5 million ounces is all it will ever be. It can’t become 6 or 7. I realize it isn’t solely a matter of production; it’s about whether growth is possible…
Mark Bristow
executiveWhat I'm giving you is grounded in what we have in hand right now. It isn't grounded in anything else. Therefore no benefit is recognized for the $1.6 billion that we will put into exploration over the next 10 years. And so as a foundation on which to build a business, this is an outstanding business. This is precisely the point we reached at Randgold, where you and others — when we hit a plateau and said we're now at a stage where we can generate returns and replace the gold we mine in a long-term sustainable way — everyone asked where's your growth. Until we struck the deal with Barrick, and then all at once everyone understood, when you look back at how Randgold produced that value, that the first part was of course growth in reserves and growth in production, but at the same time that arrived with capital spending to deliver it. And then you reach a point where you truly begin delivering real value for the shareholders, and Randgold, at a time when the industry was destroying value, kept growing its dividends for 13 years in a row and performed in the market despite the ups and downs of the gold price at a total shareholder return level that ranked it among the top 100 value creators of all listed stocks globally.
Mark Bristow
executiveSo that's what we're doing — rebuilding a world-class business, one that can compete in the public markets and deliver the returns and value people would expect, plus offering the insurance that all of us have witnessed over the last nine, 10 weeks. And I might add, since 2008 — it's just that some management teams didn't deliver that big opportunity back to shareholders after the 2012 peak. But certainly, at this point we have an industry that's far more disciplined, and we've seen that industry ready to live up to that gold insurance that mine is in times of crisis like the one we're experiencing.
Operator
operatorWe move on to our following question, which is from Tanya Jakusconek at ScotiaBank. You have the floor.
Tanya Jakusconek
analystMark, Graham, could you perhaps discuss a few of the cost effects that the business is experiencing as a result of this COVID, and maybe also some of the opportunities on the other side?
Mark Bristow
executiveOkay, Tanya, I'll start us off. You heard earlier, naturally, that the oil price stands out as one of the largest opportunities. Meanwhile, our costs truly are — a portion of those costs are working capital costs, since we've grown our inventory so that we can handle any disruptions in the supply chain. We clearly have chances to tighten up our contracts on some of that supply, because common consumables are shared across the mining industry, and not the entire mining industry — the global mine industry — sits in the same spot right now when it comes to robust performance. So many things exist that, for us at Barrick, are just the normal course of business. We constantly focus on reining in our costs and on making sure our contracts are fair and appropriate given market conditions. We still hold substantial opportunities to keep enhancing our operational efficiency, simply because we began with a fairly lazy organization back last year. We've demonstrated a lot of progress, yet there's more ahead. Consider the work Graham and his team are doing to ensure we have a fully integrated data system — a financial business system — that lets our managers make real-time decisions within the shift.
Mark Bristow
executiveAll of those factors will keep making us increasingly competitive when it comes to improving our EBITDA margin. And if you compare today's results with what we delivered in quarter one last year, our EBITDA margin is markedly better than 12 months ago. So efficiency is something we're obsessed with, along with cost discipline, and making sure our businesses stay focused on profitability and cash flow. What the COVID situation has given us is this: as you know, there was some hesitation about whether we could bring in the Randgold flat integrated management model. We went ahead and did it. We've put in hard work on it together with the regional executive teams. And this corona challenge has certainly sharpened our management skills and pushed us, and accelerated our capacity, to be agile and integrated in how we operate. And it has demonstrated that this model — this modern approach of not having a corporate tower of authority located far from your operations — is the correct path. So if there's one thing I'd say this has done, it has helped us or taught us precisely that: refining our ability to manage in a way that's more modern and agile.
Mark Bristow
executiveBeyond that, our HR group is concentrating hard on ensuring that the way we approach hiring tilts toward younger individuals and a more diverse workforce drawn from the nations where we do business. And once more, given enough time, that effect will become visible.
Tanya Jakusconek
analystBut if I've got that right, when you mentioned improving productivity, that's one part of it, and the second might be reducing costs on the contractor side. Would that be a fair way to put it?
Mark Bristow
executiveRight, precisely. What I mean is that plenty of opportunities exist. As I recall, Riaan and his group have already removed roughly $115 million in Nevada alone, purely through contract efficiencies — simply by renegotiating contracts. And there is far more we can accomplish. In South America, we've already done a great deal, yet more remains to be done. And I think as we develop relationships with our contractors — well, that's another major aspect of this COVID challenge: you quickly see who your partners truly are. And we will certainly focus on strengthening those positive partnerships while changing the less committed ones within our organization.
Tanya Jakusconek
analystMaybe this one's just for Graham. Would it be fair to think that any extra expense tied to COVID — from social distancing and tasks that might take longer, plus the added costs involved — gets more than offset by the $25 per ounce gain coming from your fuel price?
Graham Shuttleworth
executiveOkay, Tanya, I believe—as you heard Mark mention at the start of their discussion—we hesitated to commit to that large reduction, since we're conscious that we're simultaneously facing inefficiencies tied to COVID, and those inefficiencies are far from trivial. Like you mentioned, social distancing and the inability to relocate staff the way you once could. So you might end up with inefficiency in your workforce, unable to ship goods the way you previously did, meaning you have to arrange various kinds of freight. There are numerous multiple touch points that hurt your efficiency. So even though we've managed to get past the restrictions that were imposed, those restrictions carry a cost. That's the reason we're hesitant to throw that figure out there and declare, this is what you ought to anticipate. I mean, that figure is a theoretical computation. And once more, as Mark pointed out, quite frequently when you witness such a steep decline in the dollar oil price, it doesn't necessarily flow through to the per-litre diesel price. So getting overly theoretical about it isn't particularly helpful. What we'd prefer to highlight is that we've experienced some swings and roundabouts.
Graham Shuttleworth
executiveOverall, the guidance we laid out at the beginning of the year is something we feel good about.
Tanya Jakusconek
analystAnd is it tough to say — just looking at it from a currency angle, Graham — that roughly 70% of your costs are denominated in U.S. dollars, so only 30% carries exposure to Canadian, euro and others, and that would have a smaller impact on $1 per ounce than your fuel?
Graham Shuttleworth
executiveI wouldn't put it at 30% — honestly, we're mainly an organization built around the dollar. And even where we do take on costs in local currency — fuel, for instance — the core driver behind it is dollar-based; the underlying product itself is dollar-based. So, you know, I wouldn't frame it as being that high. I'd say it's lower than that — probably under 20% would be FX.
Operator
operatorThe following question is from Kip Keen at S&P Global. Go right ahead. And our next question is from Helen Reid with Reuters News. Please go ahead.
Helen Reid
unknownMark, a quick question regarding Grasberg. Are you still actively examining that mine? In what ways does COVID-19 alter the M&A landscape? And second, I don't know if you noticed, but the Trump administration is preparing a legal framework for lunar mining. Is that a possibility for Barrick?
Mark Bristow
executiveHelen, at this point we have no intention of heading to the Moon, and certainly not in the way gold miners and copper miners would. Regarding Grasberg, I believe my prior statements on it have been quite plain. Let me also say that in today's world, our mining sector requires reshaping, reinvention, revitalization, and without question modernization. So, as I see it, this is an excellent chance for us to reposition ourselves as miners. What the COVID challenge has shown us, I think, is the genuine contribution mining makes to the countries that host it. And taken as a whole, the work and the outreach mining has delivered have been truly impressive in what was otherwise — miners, managing prices and challenges is our business each day. I have seen and witnessed the impact miners have had around the globe, especially in the emerging markets. So I believe the time has come for us, as a mining industry, to stand up and share and advertise the partnerships we enter into boldly, along with the difference we make and the value we create worldwide, and I think that can be done better. And so, we have seen the first — I mean, since the Barrack brand gold deal, quite a few deals have come along that have really consolidated the industry, particularly in the gold space.
Mark Bristow
executiveWe have observed deals lately — during the early phase of this COVID period — that are now reaching completion, and these tend to be transactions driven by necessity. I have absolutely no doubt that we will keep seeing deals that are sensible given these conditions, since the consequences of this situation are genuine. From these kinds of black swan occurrences, a paradigm shift invariably emerges. So, from where I sit, what you have witnessed is an abrupt push toward the E component of ESG, following the onset of democratic engagement in the U. S. presidential elections, which has now somewhat settled given that you have one candidate. Yet right after that — and this COVID has brought into focus the gap within this global business family of ours, reflected in how we attend to social engagement and responsibility, to governance matters, and most importantly, to something I have consistently discussed, namely poverty. And, you know, there is certainly every justification for believing that the world will look different going forward, and we in mining must ensure we remain relevant in this highly dynamic environment. And with that, I am convinced it will deliver meaningful opportunities.
Mark Bristow
executiveAs I mentioned during my presentation, I genuinely think Barrick possesses an exceptional leadership group and operations crew—one that can create genuine worth. They also have an extremely solid financial base from which to pursue acquisitions and go after opportunities. Built into that is a tier one quality portfolio, which guarantees we remain a long-term enterprise and lets our shareholders put money in with visibility—runway visibility, really—into our future capacity to keep delivering value. So all of these factors will, in my view, fuel a vigorous M&A landscape, and it falls to us as managers to decide whether we keep rising to these challenges, consolidating this industry, and delivering genuine worth to our owners—just as we did in 2012—or fail to do the right things and wind up looking back on a missed chance and a great deal of value destruction.
Operator
operatorThat appears to be all the questions from the conference call. I'd now like to return the call to Mr. Bristow so he can offer his closing remarks.
Mark Bristow
executiveWell, ladies and gentlemen, we really appreciate you taking the time to be with us today. I can't tell you how much I'm looking forward to seeing all of you once again, and we're putting in hard work toward that. Until then, please know that every one of us remains sharply focused on carrying forward the very solid groundwork we established in 2019. I encourage each of you to stay safe and keep up that social distancing. And I look forward to the next occasion when we get together. Thank you so much.
Operator
operatorThat brings us to the end of today's call. If anything further comes up that you'd like to ask about, the Barrick Investor Relations team is the group to reach out to. At this point you're welcome to hang up your lines. We appreciate you joining us, and we hope the rest of your day goes well.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Barrick Mining Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Barrick Mining Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Barrick Mining Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.