operatorGood day, everyone, and thanks for holding. I’m the conference operator, and I’d like to welcome you to the Barrick 2022 second quarter results conference call. For the presentation portion, everyone will be in listen-only mode, and this conference is being recorded. After the presentation, there will be a question-and-answer session. Right now, if you have a question, please press star then one on your telephone keypad. If at any point during the call you need operator assistance, please press star then zero. As a reminder, this conference call is being recorded, and a replay will be available on Barrick’s website later today, August 8th, 2022. I’d now like to turn the conference over to Mark Bristow, Chief Executive Officer. Please go ahead, sir.
Mark Bristow
executiveThanks so much, and good morning and good afternoon, ladies and gentlemen, and welcome to our Quarter Two results update. At the halfway point of the year, Barrick's performance and prospects continue to demonstrate the steady progress we envisioned at the time of the strategic merger, when we radically altered its trajectory and began the journey toward a future-forward business. We have assembled a team and a structure capable of handling a range of global economic, social, and political challenges that are growing increasingly complex. We drove ownership of our ore bodies at the mine site and rationalized our portfolio to focus on world-class assets. We've shed the debt burden, strengthened the balance sheet, and introduced a dividend policy backed by our sustainably profitable strategy. Our exploration teams continue to replenish reserves depleted by mining and to pursue our new Tier 1 discoveries and our growth opportunities. We've expanded our footprint across nearly all the world's major gold and copper regions. On every front, we're closing in on our goal of becoming the world's most valued mining company. At this point, I draw your attention to the usual cautionary statement shown here and also available on our website.
Mark Bristow
executiveNow we can move on to the quarter's results. In a challenging operating environment, the team delivered a stronger performance across the portfolio, keeping us on track to meet our production guidance for the year. At the same time, we've made significant progress in advancing our major capital projects, notably the massive expansion of Pueblo Viejo in the Dominican Republic and the start of the public comment stage on the Goldrush development in Nevada. The prospectivity of our copper portfolio is growing, and our energized brownfields and greenfields exploration continues to deliver results. Earnings were ahead of market consensus, and we maintained the quarterly dividend. Operationally, there were improvements across the board, and particularly at Carlin and Turquoise Ridge in Nevada, Veladero in Argentina, Bulyanhulu and North Mara in Tanzania, and Lumwana in Zambia. With strong gold production expected from Cortez in quarter four and copper production likely to be slightly up in the second half, we are still forecasting to be within annual production guidance. Due to higher energy prices which flowed through to the cost of consumables and global supply challenges, both provoked by the crisis in Ukraine, costs are expected to be at or above the top end of our guidance, depending on how energy prices play out in the second half of the year.
Mark Bristow
executiveWe also expect a few project development hold-ups now — as much as three months at Pueblo Viejo and as much as six months at Goldrush, compared with earlier market guidance — and I'll go into that later in my presentation. Those are the figures, and as you can see, healthy cash flows along with a solid net cash position keep supporting a robust return of capital to shareholders. Under our $1 billion share buyback program, we've repurchased $182 million worth of shares, and we paid out Kibali's remaining cash surplus from the Democratic Republic of Congo. It's worth noting that Q2 is traditionally our highest tax payment quarter as well as when we make most of our semi-annual interest payments on our bonds. Sustainability remains a key focus in every aspect of our business. To support our drive to net zero emissions, we have quantified our Scope 3 emissions, those produced by our value chain to get a full picture of our carbon footprint. This exercise has shown that Scope 3 emissions from our Tier 1 assets accounts for some 40% of the group's total greenhouse gas emissions, mainly from purchased goods and services, capital goods, fuel and energy use, and transport and distribution. We are now engaging with all our suppliers to help them set and achieve their own reduction targets.
Mark Bristow
executiveWhen it comes to health and safety, Latin America and Asia Pacific have kept up their strong track record — cutting the total recordable injury rate by 41% year to date versus the same stretch of 2021. And I should note, that's happening while we've brought 3,500 contractors onto the Pueblo Viejo site alongside a permanent workforce of 2,700 employees as part of the expansion project. Africa and the Middle East posted a similar reduction, though North America still has room to improve, and we'll keep working at it. Even with the delay in energizing the Veladero power line — which will connect the mine to neighboring Chile's greener grid — we held carbon dioxide equivalent emissions at the quarter one level. Water use efficiency averaged 83% once again, above the 80% target. Through the mine's community development committees, we put $7.5 million into community projects, which brings our year-to-date spend to nearly $12.5 million. We also finished the public hearing engagements for Pueblo Viejo's new tailings storage facility, and Nevada Gold Mines renewed its partnership with Discovery Education and the Nevada Department of Education. Turning to operations, we begin our operational review in North America, where the management team has been strengthened by the appointments of Christine Keener as the region's Chief Operating Officer and Peter Richardson as the incoming Executive Managing Director of Nevada Gold Mines.
Mark Bristow
executiveWe've designed a new North American organizational structure that brings Nevada Gold Mines into the fold, and the aim is to unite operational and project leadership so we can keep driving performance gains and regional growth past Nevada and Hemlo. Nevada Gold Mines turned in a solid second quarter and is positioned to improve further in quarter three and quarter four. This complex sits at the heart of our portfolio, and since it was formed three years ago it has yielded 10.1 million ounces of gold and extended its pre-merger life considerably by deepening our knowledge of the ore bodies. It has also paid out $6.5 billion to its JV partners. During the quarter, Nevada Gold Mines delivered stronger operational results at every site except Cortez, which is moving from Pipeline — that's the open cast Pipeline project — to the next phase at Crossroads and should begin contributing its high-grade oxide ore in quarter four. As I said earlier, the notice of availability for the Gold Rush project came out at the end of the quarter, and that started the public comment period. Because of the delay, our expectation now is a Record of Decision in the first half of 2023. We're assessing what this delay means and will bring you up to date when we issue our 2023 guidance.
Mark Bristow
executiveBrownfields exploration is quickly taking the place of reserves that mining has depleted, and it's also pinpointing new targets. As this map shows, we hold a wealth of quality prospects in Nevada, so let's examine just two of them as examples. At North Leeville, a maiden inferred resource of 700,000 ounces has been identified, and at both that site and the nearby North Turf, there's strong potential for adding further resources. North Turf keeps growing toward North Leeville, with multiple high-grade intercepts. Underground drilling launched from exploration declines is anticipated to arrive at North Leeville late this year, at which point the two projects ought to be combinable. Remaining on the Carlin Trend: the Rain project is also demonstrating resource growth, and there we've identified a new western mineralized corridor, Corona, only 250 m away from existing infrastructure. That new corridor, along with the JB corridor, will drive additions to Rain's maiden inferred resource of 1.2 million ounces, which lets us move this particular project forward to feasibility. I've said before that we want to grow our presence in both the United States and especially Canada. Canada, besides being Barrick's home, is a highly prospective region with a mining-friendly jurisdiction.
Mark Bristow
executiveWe have built up a solid team focused on new business in that region, and they have been reviewing a number of M&A and earn-in exploration possibilities aimed at growing our portfolio. Options are already in place on four projects. Hemlo — our Canadian operation, which the pandemic hit hard — has drawn considerable focus as we work on rescoping it. We have been fully remodeling that mine, and as part of that effort we are looking at restarting the open pit. Down south, the Latin America and Asia Pacific region had a very busy quarter, with Pueblo Viejo expanding and a more intense exploration push, led by a new team, around our existing sites and well beyond them in new destinations. There is Reko Diq in Pakistan, a very exciting project I will tell you more about later. In Papua New Guinea, the country's election has delayed Porgera's progress toward reopening. Even so, we are optimistic that operations can be restarted by the end of this year. Pueblo Viejo had a good quarter and is well-positioned to achieve its production guidance. At the same time, its conversion into a long life mine is progressing, and a site for a new tailings facility has now been settled. Detailed engineering and updated costing of the new TSF should be completed in the second half of the year.
Mark Bristow
executiveAs you might remember, the mine was slated to shut down since its enormous resources couldn't be turned into reserves because of constraints on tailings storage capacity. Its life will be extended to 2040 and beyond thanks to the plant expansion and the new tailings facility, with average yearly output projected at more than 800,000 ounces. Operating a large mine while building out this huge expansion project shows once again how Barrick management can take on complicated challenges. Having said that, delays in delivery of certain key components caused by global supply chain constraints are placing pressure on the completion date. Our current expectation is to be substantially complete by the end of this year, with commissioning starting early in the new year. Meanwhile, Barrick's exploration team is pursuing growth opportunities inside the permit and the surrounding concessions, as well as a full reevaluation of the district. Drilling programs designed to test the Oro del Rey and Zambrano Norte targets are in the final stages of planning and will assess their potential to deliver high-grade ore to the mine plan. As you are aware, Argentina has been experiencing some difficult times, but Veladero nonetheless keeps enhancing its performance. With its fourth quarter traditionally a strong one, the mine remains positioned to meet its annual production guidance, though risks exist.
Mark Bristow
executiveWe’ve finished building the first stage of the phase VII heap leach treatment facility, and we expect to begin construction on phase VII’s final stage near the end of this year. One of the group’s three new exploration managers is now leading exploration work throughout the LATAM region, collaborating closely with a dedicated growth manager to assess opportunities. As the LATAM exploration programs and priorities undergo refreshing, activity carried on across the continent, and this quarter produced encouraging results from Veladero, where the team is advancing a number of early-stage near-mine targets. The LATAM region holds promise for world-class copper and gold discoveries, and we clearly have teams possessing the necessary skills and experience to deliver them. Moving to Reko Diq, one of the largest undeveloped copper-gold deposits anywhere in the world. Under the framework agreement involving Barrick and the government of Pakistan, the project—suspended since 2011—will be reconstituted and restarted. Barrick will operate the mine, and consistent with our approach of partnering with host countries, ownership will be split as follows: 50% Barrick, 25% the Balochistan provincial government, and 25% Pakistan state-owned enterprises.
Mark Bristow
executiveFor Barrick this represents a thrilling prospect, and it's just as much one for the nation and the province. Local stakeholders across the board have welcomed us with tremendous enthusiasm and backing. Here is the timeline we anticipate for Reko Diq. Pakistan's administration is an efficient one, and at present we're collaborating with every party involved to wrap up the definitive agreements that underpin the project. A legislative process must also be seen through. After all of that concludes, we'll revise the current feasibility study, which is presently slated for completion in 2024. First production might arrive in 2027 or 2028. Thanks to its rare blend of large scale, low strip, and good grades, Reko Diq is set to be a multigenerational mine boasting a life of at least 40 years. Moving on now to Africa and the Middle East. The region keeps excelling across every front, with a standout showing from the Tanzanian mines. All but halted when we assumed their management three years ago, they've been entirely redesigned and re-engineered, producing what amount to two wholly new mines with the potential, as a combined complex, to reach Tier 1 status within the Barrick portfolio. In Mali, Loulo-Gounkoto turned in its customary strong performance and remains firmly on track toward hitting its annual production guidance.
Mark Bristow
executiveAmong all the sites we run, this complex has the greatest exposure to elevated fuel costs, yet we are currently working to triple the capacity of its solar power facility, and that will enhance the makeup of its energy supply. Turning to exploration, the Loulo district in Mali and the area across the river in Senegal is a gift that keeps on giving. Brownfield exploration at Loulo-Gounkoto will likely replace the ounces depleted this year. Right across the border in Senegal, our Bambadji and Diéma permits contain multiple targets that carry standalone potential. In Central Africa, Kibali lifted output in quarter two, with throughput climbing following the planned mill maintenance of quarter one. We now anticipate the shaft winder replacement in quarter four, which could have a slight effect on production, though the mine remains on course to deliver production within guidance. Thanks to its three hydropower stations, Kibali leads Barrick in renewable energy, which is protecting it from the full impact of higher fuel prices. Exploration keeps replenishing the reserve base while also searching for new discoveries. In Tanzania, as I noted in the introduction to our Africa/Middle East section, both mines reached their steady state run rate in quarter two, with North Mara raising production by 18% and Bulyanhulu delivering a 20% improvement.
Mark Bristow
executiveBulyanhulu's life is now beyond 20 years, and it keeps producing meaningful reserve growth. Work on the new Deep West Extension is set to begin this quarter. At North Mara, the Rama open pit has been ramped up successfully, and the new Gena pushback is planned for the second half of this year. As we keep replacing resources that mining depletes, we're also pursuing new opportunities in the North Mara district. We've grown our footprint around Bulyanhulu by acquiring six highly prospective licenses, and we're also updating geological models and generating targets, as I noted, in the North Mara region. Moving on to copper operations. In Zambia, Lumwana lifted Q2 production by 32%, helped by higher grades and better mill availability. Jabal Sayid in Saudi Arabia delivered consistent production performance and, consistent with Barrick's policy of recruiting host country nationals, has appointed its first Saudi general manager. Output at Zaldivar in Chile was consistent as well. Strong exploration results at Jabal Sayid have identified multiple growth opportunities with ore body expansion potential, both at depth and along strike, adding significantly to the life of mine. Major intersects shown here include one with an eye-watering 54 meters at over 15% copper.
Mark Bristow
executiveOver in Zambia, at Lumwana, we've been focused on near-surface satellite orebodies to underpin the conceptual pushback of the Chimiwungo Super Pit, and that pushback is what will release the site's full potential while stretching its life past 2060. Work on this is underway, and we anticipate kicking off a pre-feasibility study next year. Ladies and gentlemen, that wraps up my operational review. Now I'd like to return to the dividend, because it shows how Barrick is committed to returning capital to shareholders. That $0.20 dividend is made up of a $0.10 base component and a $0.10 performance component, which is determined by the cash on our balance sheet, net of debt, at the close of each quarter. Annualized, that works out to a dividend yield of roughly 5%, which leads our peers. Our dividend framework doesn't just give shareholders enhanced returns — it also gives them predictability and flexibility right through the financial cycle. And so that we can act opportunistically when our shares fail to reflect the value of our assets and prospects, we introduced, as I mentioned earlier, a $1 billion share buyback program, and we used it for the first time this past quarter. To close out my presentation, I thought it would be worthwhile to pull together the earlier slides and summarize how all of this is building value for our investors.
Mark Bristow
executiveOur portfolio of world-class gold and copper assets is the biggest in the industry, and it keeps expanding. Every mine we own has a realistic 10-year business plan — in certain cases stretched out to 15 years and beyond — without any meaningful drops in production. To keep those 10-year plans on track, we have no need to rely on new projects. New projects, by contrast, are built on top of the solid production base that already exists. Indeed, our growth projects, including Pueblo Viejo and Reko Diq, will strengthen the long-term sustainability we have today. Barrick's sizeable project portfolio supports future growth, and it contains Donlin and Pascua Lama, the expanding near mine opportunities I mentioned during this presentation, plus a strong track record in exploration success and reserve replenishment. Our sustainability policies and practices — embedded at Barrick long before ESG became a thing — produce measurable results that benefit every one of our stakeholders. Disciplined shareholder returns underpin all of this. Let me close with a question: where could you find a better investment case? Thank you for your attention, and we are ready to take answers.
Operator
operatorThanks. We’ll start the question-and-answer portion now. To get into the question queue, press star and then one on your phone’s keypad. A tone will confirm your request. If you’re on a speakerphone, lift your handset before you press any keys. If you want to take back your question, press star and then two. We’ll wait briefly while callers enter the queue. Our first question is from Greg Barnes at TD Securities. Go ahead, please.
Greg Barnes
analystYes, thanks. Mark, I’ve got a couple of questions. First, regarding what Goldrush will contribute to Cortez over the next several years: I guess we only have consolidated guidance for Cortez, and we don’t know how much Goldrush adds to that in 2023 and 2024. Could you give us some sense of what that amount is?
Mark Bristow
executiveGreg, we haven’t provided a lot of specifics on that guidance, other than that it truly treats Cortez as a complex exceeding 1 million ounces. That will come once we define the project and finish the feasibility study, and at that point we’ll be able to update it. We did give you an early indication last year, and I believe that still holds at this stage. You have a five-year and 10-year profile. That is an essential part of the Cortez project.
Greg Barnes
analystThere's another thing I wanted to ask about Pueblo Viejo. You've chosen a different TSF location for that project. Has the government also approved that? Do you have their support for that new location?
Mark Bristow
executiveYes, absolutely. Greg, there's a press release the government has put out that confirms it. Of course, everything depends on our environmental license being granted. We feel comfortable. The terms of reference have been agreed with the government, and we're working away at that. We expect to file that application near the end of this quarter.
Greg Barnes
analystI think, Mark, that the government brought in independent experts to conduct a third-party review of these sites. As I understand it, given what you just mentioned, they have approved both of the two.
Mark Bristow
executiveYes. We've collaborated intensively with the government. As you're aware, things got off to a somewhat difficult start, yet we have definitely arrived at a workable path ahead—one that's acceptable. In fact, you should notice in today's releases that, as part of that effort, we've finished the public participation and consultation process.
Greg Barnes
analystAll right.
Mark Bristow
executiveThe group was
Greg Barnes
analystAlright.
Mark Bristow
executiveOne more thing I'd mention, Greg: those came through without a hitch.
Greg Barnes
analystAlright, thank you very much.
Operator
operatorAnita Soni from CIBC World Markets has the next question — please proceed.
Anita Soni
analystHello there. Good morning to all of you. I appreciate you taking the time to answer my question. Regarding a few of the operations that you discussed—some of those expected to get better during the second half of the year—I just wanted to ask about Turquoise Ridge and also about which one is the weaker performer? It was that one, I believe.
Mark Bristow
executiveCortez.
Anita Soni
analystLet's begin with Turquoise Ridge.
Mark Bristow
executiveCortez.
Anita Soni
analystApologies — let's begin with.
Mark Bristow
executiveCortez, that's right.
Anita Soni
analystLet's begin with Turquoise Ridge.
Mark Bristow
executiveAnita, that's correct. The two major gains come from better performance at Turquoise Ridge. I should mention that Turquoise Ridge is performing quite strongly at present, specifically the underground operation there. The issues lie in throughput and the processing plant, plus Twin Creeks and the grade of certain open pit material. We feel confident that Turquoise Ridge is ramping up according to plan, especially the key component of that asset, namely the Turquoise Ridge underground. As shaft three comes into production, we also have a development heading toward the target we refer to as BBT, which sits close to the former Getchell pit, though it is an underground target. Once more, we anticipate continued ramp-up of our underground operations at that site. The major boost comes from Cortez. We have been processing considerably lower grade open pit ore from Pipeline, and we are actively moving to the next phase at Crossroads. A very high-grade oxide section of Crossroads features in this year's mining plan, and we reach it only at the start of the fourth quarter, which represents a significant increase. Throughput and similar metrics remain unchanged. We utilize the oxide mill.
Mark Bristow
executiveThe capacity is there. Grade is the issue. We've devoted considerable effort to the reserve model and its grade, and we're comfortable that, provided we can hold the mining rate at today's level, we'll get access to that, and you'll see it come through late in the year. Those are the two.
Anita Soni
analystAlright, thank you very much.
Mark Bristow
executiveLooking year over year, those represent the two major gains. As I mentioned, PV remains pretty much where we expected. We're maintaining a run rate similar to quarter two. It's the same story at Veladero. At Loulo-Gounkoto, the run rate is right on target. At Kibali, which I highlighted during my presentation, production is rising somewhat more strongly in both quarter three and quarter four. North Mara is tracking at the run rate, and Bulyanhulu is the same.
Anita Soni
analystRight, so my follow-up was going to touch on Veladero, since it’s operating a bit better than what you described as a modest gain throughout the year?
Mark Bristow
executiveYeah. What I mean is, we’re genuinely beginning to.
Anita Soni
analystSure.
Mark Bristow
executiveWe need to grasp how leaching behaves at Veladero, since, you know, nobody has really zeroed in on what that behavior actually is. We’ve been, you know, putting in place the next leaching infrastructure. Now that this infrastructure is operational, phase VI, and we’re progressing to phase VII, the major priority at this point is grasping the leaching behavior, how we handle the winter months, and we expect there ought to be better leach kinetics as we move into the summer. So again, we’re projecting a better back, you know, final quarter of this year as we head into summer.
Anita Soni
analystAlright, my second-to-last question has to do with CapEx. I believe you're tracking a bit above 50% for the year, and I'm curious whether what you said about cost landing at or above the top of the guidance range would hold true for the CapEx figures as well. Should we be expecting somewhat higher CapEx numbers?
Mark Bristow
executiveThat's right.
Anita Soni
analystTaking into account the oil prices that haven't been factored in there as well.
Mark Bristow
executiveThey're linked together, as you're aware. Some of it—you know, it's a heavy stripping year. With fuel prices higher, there's a chance that, if we complete the full stripping program, depending on where fuel sits, that feeds into our total cost structure. But as you noted, that capital—sustaining capital—does affect all-in sustaining costs. We're keeping it under control. The thing I'd say to everybody is that these matters count. We don't attempt to—and we hold assets that will work at whatever gold price you assume. We are—and certain assets are generating solid cash flow, while others need sustaining capital investments, yet every one of our assets holds up under any—you know, essentially any gold and copper price you can picture. They're built to get through the cycles profitably.
Anita Soni
analystAlright, thanks so much.
Mark Bristow
executiveHappy to be here.
Operator
operatorJackie Przybylowski from BMO Capital Markets is our next questioner. You have the floor.
Jackie Przybylowski
analystThank you so much for taking my questions. Perhaps I'll pose my first one just to return to something you brought up during the introductory remarks regarding Canada. Could you provide us with a bit more detail? I'm aware that quite a few transactions have, you know, appeared and disappeared in Canada, both in terms of M&A and exploration. What are your present views, or what are you seeing right now in the landscape out there in Canada today? Thanks.
Mark Bristow
executiveOkay, Jackie — two points on that. To begin with, as I've mentioned repeatedly, our approach to expansion is highly disciplined. If opportunities arise but fail to satisfy our investment standards, we simply don't do the deal — and that is exactly what took place in Canada not long ago. That is not to suggest we've lost our commitment to continuing to grow there. A phrase I use often: if we can't buy it, we'll find it. That has genuinely been the thrust of our overall strategy, since otherwise — merely reshuffling the assets within our industry — no value gets created, which is what the years have shown us. That is precisely where we concentrate. Our Canadian team is excellent. Bit by bit, we're assembling portfolios. Right now, 4 separate projects are receiving our attention. In due course, you will see it. Simultaneously, during periods such as this, when the industry — and the market in particular — comes under abrupt strain, the junior market feels the pressure. Once more, that gives us a sensible opening to capitalize on, and capitalize we do. I'd probably close by noting that we have never acquired any exploration project at full value, and we have no plans to begin doing so.
Jackie Przybylowski
analystOkay, that's a reasonable point, and you have certainly shown discipline on that front. For my second question, perhaps I could get an update from you on where things stand at Porgera. It sounds as though an agreement has been reached and you are now simply working through a public notice process. Could you speak a bit about how long you anticipate that will take, and when you might be in a position to fold Porgera back into your guidance, if you have any sense of that? Thanks.
Mark Bristow
executiveYeah. You know, we were moving along. We've had this dispute involving a structure that previously held 5% equity in Porgera. Again, it held that stake for the benefit of the key SML landowners. Those landowners have now signed on to the new transaction, and the management of that particular vehicle is resisting heeding the direction of its own shareholders. That's a matter we're working through. At the same time, the elections, as you know, have been quite complicated. We expect — and we have a process in place. The electioneering process is now at a stage that should lead to the person, or the party, being designated to form a government. That individual will be invited by the governor general. We're right in the middle of that process as we speak today. We expect over the course of this week to have a good sense of who will be leading the next government. Once that's done, we believe we'll be able to move forward and close this out, because that's all we require — we require a shareholders agreement. We have agreement among the key stakeholders, the landowners, the provincial government of Enga and the other landowners, and everyone included in the framework agreement as beneficiaries.
Mark Bristow
executiveThe focus is on completing the shareholder agreement for the new Porgera and putting in the application for the SML, the Special Mining License, which would then let us head toward reopening that mine. That is the sequence. I was over there a couple of weeks back. We had a meeting with the prime minister serving at that point. At the moment we're in a stretch where there's no prime minister for a couple of days, and after that we'll see the appointment of the new prime minister this week, and then we can get back to pushing this project forward.
Jackie Przybylowski
analystMy apologies. It does sound like a lot is happening, but would it be fair to expect a restart in 2023?
Mark Bristow
executiveJust one thing.
Jackie Przybylowski
analystWe closed out 2023.
Mark Bristow
executiveOne thing I've grown accustomed to is that Papua New Guinea isn't always functioning as a sensible state.
Jackie Przybylowski
analystAbsolutely.
Mark Bristow
executiveWe’ll continue to push on it. I believe our ties and our conviction that everyone who matters in that process has reached a point where we know where we want to end up, and it is moving through the process. Naturally, as you’re aware, we have always shown respect for the different stakeholders in any of our businesses, and this is another of those pioneering deals. The gold remains underground, and we are quite confident that once we get the rules correct and the agreements settled, we will be able to run comfortably again in Porgera.
Jackie Przybylowski
analystThank you. Appreciate it, Mark.
Mark Bristow
executiveIt’s a pleasure.
Operator
operatorLawson Winder from Bank of America Securities has our next question. The floor is yours.
Lawson Winder
analystHey Mark, good to hear from you, and thanks for the update. I'd like to circle back to Pueblo Viejo and the CapEx. In the MD&A, you noted there could be a significant rise in CapEx, depending on a range of factors. Could you walk us through some of the factors behind that possible increase, and how much the delay plays into it? Thanks.
Mark Bristow
executiveRight. We have to complete the feasibility study. As you know, an initial site was the source of all that controversy. That site has been relocated, and the new one — as we indicated when we made the move, and we had various options — really hinges on volumes. The volume of the key for the dam walls, plus the overall volume required to construct those walls. If you recall, early on we discussed the two separate sites and the differences in terms of whether those tailings facilities could be built. At the same time, the new site brings greater volume as well. That is what we are working on right now. We are considerably ahead of schedule on drilling out the foundations to determine how much excavation is needed and what the size and components of the key for the wall must be, and after that we can share it with you. What I can say is that the economics remain very robust, Lawson.
Lawson Winder
analystAll right, that helps. Just so we’re clear, if I understand you right, it sounds like the $1.4 billion estimate is going to rise somewhat, and you folks simply need time to determine how big that increase will be.
Mark Bristow
executiveRight.
Lawson Winder
analystJust how material would that be? Does that seem fair?
Mark Bristow
executiveExactly right, yes. It’s a complete package. We want that finalized. We want to submit the permit application. We have to file for that permit. By the close of this quarter, we’ll have a pre-feasibility-type estimate, and after that we’ll share it with the market.
Lawson Winder
analystThanks. I’d also like to ask about the new Asia Pacific team you’ve set up. That team — which I understand is located in Perth — could it be read as a sign that Barrick wants to go back into Australia after leaving a few years ago? And if that’s the case, might M&A form part of that reentry approach? Thanks.
Mark Bristow
executiveSo, just so you know, that team's main priority is — and by the way, that team isn't operating Porgera, since there was a bit of a rumor going around that we'd be running Porgera remotely. That's not what we're going to do. What we intend to do, and we already have a complete Porgera team based in Port Moresby. We still have some infrastructure in Cairns, and we will relocate all the significant leadership roles for Porgera to Porgera and Port Moresby, consistent with our commitment to being host country-based. Perth — the team in Perth is really tasked with — right now it's working alongside the team in Pakistan, so that leadership structure will back our Pakistan project as we build up capacity, and we've already begun hiring people for that project. It's about looking at the whole part stretching from Pakistan south and east, right through to Papua New Guinea. In theory, nothing prevents us from going back into Australia, as long as we can find things that meet our criteria. As you know, Australia is a fairly mature destination for exploration. M&A — you know, from my experience in Australia, it isn't the place to go hunting bargains.
Operator
operatorJosh Wolfson from RBC Capital Markets has the next question. Go ahead, please.
Josh Wolfson
analystThanks a lot. To build on what Lawson asked regarding Pueblo Viejo capital, I get that there are various possible options for the tailings dam, along with the volumes and energy prices tied to them. But if you had to give us some kind of goalpost to frame what a material change in the capital would look like, is there a percentage we ought to have in mind? Or is there any information you could share on that?
Mark Bristow
executiveJosh, power isn't the issue at all here. I just walked Lawson through this — what matters is how much material we need to move. We're in the middle of working through the design and calculation work on that, and I think that's the right approach for us. To start with, once we reach that stage we have to present it to the government, and after that we'll take it to the market. You know, I think we're — it is substantial, but even so, it still produces very robust economics. This project extends well past 2040 and, you know, by every account it will deliver production of more than 800,000 ounces per year. That feasibility study is underway right now. Once we're finished, we'll tell you what it shows.
Josh Wolfson
analystRegarding the schedules for that project or the expansion at that site, at what point do you anticipate reaching a steady-state run rate of 800,000 ounces or above? Considering how the commissioning timelines have shifted, what impact does that have on the 2023 production figures?
Mark Bristow
executiveLook, the expansion guidance and that situation aren't directly connected. With the tailings facility, what we had to handle was this: without getting it, operations would have been hit hard. Our entire profile would have shifted. Mining would have had to halt, so we had to stay on top of it—otherwise there'd be no location left for the waste, and that waste generates acid. That's settled now, so we can proceed. Meanwhile, backed by the government's endorsement, we carried on with the expansion program once we had certainty about securing a footprint to construct the new tailings facility. That expansion program is what we describe as delayed. Initially it was projected for quarter three, and now we're indicating it will be substantially complete by the end of the year, with commissioning beginning in the new year. Just to remind you, this essentially transforms the front end of the plant from a feed of 9 million tons a year to 14 million tons. The effect is that we reduce it in a flotation circuit, so the back end of the plant retains capacity of roughly 9 million tons.
Mark Bristow
executiveThrough that approach, we maintain the gold output run rate we've had historically and improve it a little if possible. We hold costs down. That's how it works. Since we now have the ability to store material, and since we know we can keep ramping up the new expansion, next year will naturally be a better one. After that, we ought to reach the planned run rate around late next year, or in the back half of next year. In 2024, we'll return to those high production profiles.
Josh Wolfson
analystAll right, so if we consider how these measures will affect the rest of the year and the finishing of the project, is there anything that could disrupt things—perhaps near the end of the year, either during commissioning or while construction work is going on?
Mark Bristow
executiveAs I highlighted during the presentation, we have several construction workstreams running alongside the operation. If you look at how this mine is performing, the results are spectacular — truly spectacular. There are 3,500 additional people on site. I'm not sure whether you've ever visited, Josh, but the footprint there is fairly small. Beyond that, it's also our strongest site on safety. Overall, things are going well. Some tie-ins are already complete, and more will follow. Tie-ins have had our close attention. We feel very confident that the team knows precisely what must be done in order to deliver. As with many of our businesses, this is about creating value over the long term. What we're focused on is making sure we establish that solid foundation allowing us to operate across the coming 20 to 30 years. Experience has definitely taught me to concentrate on getting it done properly, and the rest will follow.
Josh Wolfson
analystThanks a lot — that's great.
Operator
operatorTanya Jakusconek from Scotiabank has the next question. Go right ahead.
Tanya Jakusconek
analystOh, fantastic. Good morning to all of you, or good afternoon. Thanks for taking my questions. Perhaps it's just regarding a few of the development projects. I'm just going to return to and wrap up on Pueblo Viejo so I can get the timeline clear, Mark, from you. We're working on a pre-feasibility study that will be finished in Q3. Will we receive an update along with the Q3 results on what you've found in that pre-feasibility study at that point?
Mark Bristow
executiveTanya, that figure is purely the expense associated with the tailings facility. We'll put that out once we have a solid handle on what the number looks like. We also have to submit it to the government, since as you'll recall, this forms part of the arrangement we have with them regarding a major expansion. It doesn't truly affect the schedule for ramping up the expansion. The expansion is separate from the tailings facility.
Tanya Jakusconek
analystYeah. No, I appreciate that. It’ll probably be sometime in Q3, or maybe Q4.
Mark Bristow
executiveSure.
Tanya Jakusconek
analystWe’re going to receive that.
Mark Bristow
executiveCorrect.
Tanya Jakusconek
analystThere's a fresh cost figure for the tailings. Is that right?
Mark Bristow
executiveThat is a reasonable assumption. Naturally, getting it to the market as quickly as we possibly can is in our interest.
Tanya Jakusconek
analystAlright. That permit you're filing in Q3 2022 — when do you expect it to be granted to you?
Mark Bristow
executiveYeah, that’s a project that has been running alongside, with consultation involving the government. You know, I mean, Grant is on the call. Grant Beringer, do you want to take a shot at that? Do you know how long it takes?
Grant Beringer
executiveThat depends on how the government's review goes. Our plan is to file the ESIA near the end of this month, at the start of September. Naturally, they have to carry out their review — the government, I mean. We're looking for that in the first half of next year.
Tanya Jakusconek
analystOkay. Is it at the point when this permit is granted that we'd examine that resource for reserve conversion in your reserve statements?
Mark Bristow
executiveNo. Rob, do you want to say something about that? Once we're clear and feel confident that we'll deliver.
Rob Krcmarov
unknownYeah, you know, once we’re
Mark Bristow
executiveGo ahead. Yeah. As soon as it's clear that we're going to receive the permit, we'll be glad to approve the reserve increase. Having the terms in hand isn't strictly necessary. We simply need confidence that nothing will stand in the way of that permit being granted. Once that matter is settled, we're happy, and we engage with the government, you know, and then we're glad to declare the reserve increase. We still expect that reserve increase this year, Tanya.
Tanya Jakusconek
analystThere's a chance we land it during this year, particularly alongside your year-end financials.
Mark Bristow
executiveSure.
Tanya Jakusconek
analystJust to be clear, given the plant expansion and all the tie-ins we might have to handle, at the end of this year, can we safely assume Q4 could be a bit weaker than Q3 as a result of those tie-ins?
Mark Bristow
executiveRoughly in line with the plan. It'll be around that level, Tanya. No, we aren't anticipating any meaningful deviation. Naturally, we would prefer to shift some output into Q3 so that we retain the flexibility you mentioned. As things stand, we aren't aiming to exceed the run rate for quarter four — the run rate we achieved in the first two quarters of this year remains attainable.
Tanya Jakusconek
analystAlright, regarding that CapEx figure for the tailings, Mark — as I recall, and I believe this came up on the last conference call, out of the $1.4 billion, roughly $500 million to $600 million related to the earlier tailings facility. Can we safely assume that any CapEx increases would apply to that $500 million-$600 million rather than the other $1.4 billion-plus, and obviously with the three-month delay there's some additional costing tied to that.
Mark Bristow
executiveAbsolutely.
Tanya Jakusconek
analystCan we take that as a safe assumption?
Mark Bristow
executiveYes. As we indicate in the expansion project, there are certain increases. That falls inside the guidance. Then, you know, we'll rework the capital estimates for the tailings facility together with the new plan, after the drilling is complete. Tanya, it really comes down to the drilling and the volume estimates. You know, what depth must we excavate at the key in order to tie it in? Because keep in mind, this mine lies within a seismically active zone. Today our existing El Llagal tailings facility is arguably the finest-built tailings facility anywhere in the world. We are fully committed to making sure this tailings dam gets designed like that one, or even better, so that the facility's safety and integrity are assured.
Tanya Jakusconek
analystNot at all — I really appreciate that.
Mark Bristow
executiveOn the other hand,
Tanya Jakusconek
analystThanks for that.
Mark Bristow
executiveThat’s what you’re assuming.
Tanya Jakusconek
analystOh, please, go right ahead.
Mark Bristow
executiveThat's right, your assumption holds up.
Tanya Jakusconek
analystSo if we do see any CapEx increase, should I basically be thinking about it in terms of that $500 million to $600 million range?
Mark Bristow
executiveYes, that would come on top of it.
Tanya Jakusconek
analystMeasured against that.
Mark Bristow
executiveMoving on to that point.
Tanya Jakusconek
analystWhen it comes to tailings.
Mark Bristow
executiveYeah, that would come on top of it.
Grant Beringer
executiveYou've got that right.
Tanya Jakusconek
analystAll right, perhaps I'll set Pueblo Viejo aside if I may, and return to Nevada alone. Just a couple of points regarding Nevada. About the holdups on the Goldrush, you know. You've begun the public hearings. Perhaps you could give an update on how those are proceeding. Is the six-month slip happening because we're running into problems on the public hearing front? Maybe a bit more detail on that slippage would help.
Mark Bristow
executiveNo. There are no delays whatsoever. As you're aware, in the US, the permitting process is time-consuming, and consultation is required. That consulting phase is where we currently stand. I should also mention that slippage occurred with the Notice of Availability. The BLM and the Department of the Interior put in tremendous effort, and following some slippage, we managed to pull that forward. That is encouraging. Our teams are fully engaged, together with the BLM and the outside consultants assisting the BLM, to move the permitting of this asset ahead. Tanya, that's the — once more, the long-term effect on Cortez from this is enormous. You know, it genuinely lifts Cortez as a complex past 1 million ounces. Carlin sits at 1.5 million-1.6 million ounces. Cortez will be above a million ounces, and then Turquoise Ridge comes in around the 600,000-ounce mark. Those three world-class assets truly form the foundation of Barrick's production profile. I'd argue it matters just as much to our partners at Newmont that we get that foundation built correctly. You know, this will continue for a very long time. Goldrush, and after that Fourmile. We have some highly exciting projects. We mentioned North Leeville, along with the Wren Project.
Mark Bristow
executiveThere are plenty of additional projects throughout the Carlin portfolio that could keep generating opportunities as we move increasingly to underground mining. We have those greenfields projects we mentioned in earlier quarters, and we'll bring you another update near the end of the year — these are the ones that removing the fence has opened up. Specifically, I mean the gap between Turquoise Ridge and Twin Creeks, then South Carlin, and naturally more opportunities around the Cortez complex too. I'm really enthusiastic about what's possible from both the brownfields side, in terms of extending mine life, and the greenfields side that our exploration teams are beginning to pinpoint.
Tanya Jakusconek
analystWhat I'm really attempting to get at is whether the local side ran into any problems at all.
Mark Bristow
executiveNo, not right now. Sure, we’ll have plenty of critics, and we’ll need to push back firmly so this project keeps advancing. As things stand, we aren’t worried at all about the process or about the points being made on either side.
Tanya Jakusconek
analystAlright. If I may, my final question relates to Long Canyon. I notice it isn't listed for sale anymore — you've removed it. I'm curious about what shifted there. Do you view this asset differently now? Perhaps regarding the underground potential, maybe. What has changed in that respect?
Mark Bristow
executiveThis asset was one where, you know, the market didn’t value some of the assets correctly. Keep in mind, when we struck the deal with Newmont, that was a hostile deal. We had to place our trust in the market. The next phase of Long Canyon had not been permitted. It has been a great asset so far. It has resources. Our view was that it didn’t really fit. It is an outlier within our Nevada portfolio. We felt that represented a chance to see whether anyone else might want to take this project on. The interest that was shown on that project, just like, by the way, Tanya, remember Lumwana, when we put it up for sale and then, you know, people felt this was some way, you know, you could bargain hunt? Well, we aren’t prepared to do that. We couldn’t find anyone we felt had the capacity to ensure that our model of responsible mining would be respected at Long Canyon. It still has some residual leach potential. Our team is now refreshing the process of continuing to license the project, and we’re comfortable that we will manage that. On top of that, the sale process got caught up with a sudden drop in the gold price, sentiment turned, lots of things.
Mark Bristow
executiveLook, we're certainly not thinking about any kind of fire sale where Long Canyon is concerned. That asset is back in our portfolio.
Tanya Jakusconek
analystAt this point you're returning to the subject of permitting, and possibly.
Mark Bristow
executiveSure.
Tanya Jakusconek
analystExamining what’s underneath.
Mark Bristow
executiveAbsolutely, that's right.
Tanya Jakusconek
analystAlright, thanks a lot for giving me the chance to ask.
Mark Bristow
executiveIt's a pleasure.
Operator
operatorJatinder Goel from BNP Paribas Exane is up next with a question. The floor is yours.
Jatinder Goel
analystThanks, operator. Good morning, and good afternoon to everyone. My first question is about the Cortez and Fourmile royalty that Rio Tinto sold to Royal Gold. From your point of view, Mark, was there any interest in buying that royalty stream, either on your side or at the NGM joint-venture level, or simply didn't it make financial sense?
Mark Bristow
executiveJatinder, as everybody acknowledged, that royalty carried a pretty hefty price tag. Naturally, we're always paying attention. I think it wouldn't be right for me to reveal our corporate thinking and strategy on that matter. One point worth stressing is that it represents a genuine vote of confidence in the capability of Nevada Gold Mines management and in its ability to expand that resource. What's baked into the price, I believe, is that conviction that we can keep growing the resource. From where Nevada Gold Mines sits, our emphasis is on expanding our resources. We would prefer to put money—especially at a level like that—back into our own ore bodies. I hope that answers your question well enough, Jatinder.
Jatinder Goel
analystYes, thank you, Mark. Just to add to that point — I mean, you're the one operating those assets, so nobody else can have better knowledge of the reserve resource, the potential production, and the cost situation than you do, particularly anyone on the outside who happens to be evaluating it. So from that angle, would a different gold price assumption be what produces a different valuation, or was it more a matter of you wanting to direct your money toward better places, as you put it, on exploration, instead of buying back the royalty stream?
Mark Bristow
executiveYes, Jatinder, I believe the answer you just gave covers it.
Jatinder Goel
analystAll right, that clears things up nicely. I just have one more question, this time from the standpoint of modeling cash flow. As far as Kibali goes, will the cash repatriation come in once per quarter, with roughly a one-quarter lag, so we can gauge how steady that inflow is? Or might the timing still vary in terms of how it reaches Barrick?
Mark Bristow
executiveWe're actively moving that forward. Under our arrangement with the government, the cash flow gets divided roughly 50% toward paying down the outstanding debt and 50% toward dividends. That way, everybody gets a piece of the pie, especially our partners, SOKIMO. Dividends go to them, the government collects the withholding tax on those dividends, and we see the outstanding debt steadily decline. That's the plan. Whether we do this quarterly or twice a year is a decision we'll make down the road. We'll be sure to let the market know.
Jatinder Goel
analystGot it. Thanks so much, Mark, and to the whole team. Wishing you all the best.
Mark Bristow
executiveCorrect.
Operator
operatorBrian MacArthur from Raymond James has the next question. The floor is yours.
Brian MacArthur
analystGood morning. At this point, most of what I had has already been covered, though I did want to circle back to something you said, Mark, regarding Bulyanhulu. You mentioned that over 20 years now, the entire mine has essentially been rebuilt. Several years back, there was discussion suggesting it might become a considerably larger operation than it is today. Given that you've now sorted it out — this new mine with a lengthy reserve life — could there be any chance of moving toward those 500,000 ounces per year figures that were discussed around 15 years ago?
Mark Bristow
executiveBrian, the clearest way to put that is there is zero chance—and likely no second opportunity either.
Brian MacArthur
analystAlright, it's worth verifying that.
Mark Bristow
executiveLet me walk you through it, since that was the piece that kept breaking down — Bulyanhulu.
Brian MacArthur
analystSure.
Mark Bristow
executiveYou know, this ore body can produce roughly 250,000 ounces — somewhere between 200,000 and 250,000 ounces annually. It's a narrow, high-grade ore body. Whenever you try to push the tonnage up, the feed grade drops, and it simply doesn't work. The sole route to achieving that increase is to develop new working fronts — new faces. For that, you need additional ore bodies. That's the reason we did the deal and expanded the footprint around Bulyanhulu, since our geologists believe there's definitely potential for more ore bodies and that there may be somewhat more folding than people previously understood. If we were able to open up extra working areas and not depend on, one, the existing infrastructure by itself, and two, you know, attempting to mine, you know, at a faster rate given how large the ore body is, then we could add to it. That's why at this point, the life of the mine just keeps getting bigger and bigger. North Mara is around 300 — a little more perhaps, depending on grade, producer — and Bulyanhulu is just above the 200,000, maybe as much as 230, 240 thousand ounces a year. Add them together, and there's the 500,000 ounces.
Mark Bristow
executiveBoth of those are solid, low-cost mining operations. Bulyanhulu has a longer lifespan compared with North Mara, but these days North Mara holds more untested prospectivity than Bulyanhulu does.
Graham Shuttleworth
executiveCorrect. That matches my expectation — I simply wanted to confirm it with you. Many thanks.
Operator
operatorWe'll take our next question now — if you'd like to ask something, just press star followed by one again. Adam Josephson from KeyBank is on the line. Go right ahead.
Adam Josephson
analystThank you, operator. Mark and Graham, good afternoon — hope both of you are doing well. This is sort of a two-part question on costs, for either of you. Could you describe the assumptions built into your thinking that gold cash costs will land at the high end, or maybe a bit above your full-year range, keeping in mind that global commodity prices, as you know, have been dropping quite sharply over recent weeks? If you do in fact finish at that level — the high end or slightly above it — what do you consider a reasonable expectation for next year when it comes to cash cost per ounce? I know you've said you expect production to rise to some degree next year. With that in mind, again, at this early stage, what do you think is the most reasonable expectation for what the year-over-year change might be, if any?
Mark Bristow
executiveI'll do my best to speak directly about operations, and Graham can step in to cover anything I miss.
Adam Josephson
analystAppreciate that, Mark.
Mark Bristow
executiveAdam, the thing is, one moment we’re discussing elevated gold prices and how that will transform the world, and the next everyone is panicking about expenses. Ultimately, those costs are what they are, and you have to handle them. One reality we’re definitely facing is inflation, and we can hope it disappears, but that won’t occur until someone takes action. We’re contending with expenses, and beyond that, there’s the Eastern European crisis—the Europe crisis—which has introduced a severely strained fuel market. That applies to both oil or diesel and gas. Gas markets are fluctuating. Consider how much gas is being shipped out of the U.S., for example, where we are, where we depend on and are expanding our capacity to add more gas-fired power generation. All of those are complicated circumstances. You can’t simply examine the commodity price and claim that’s going to be what it—that’s going to be capable of being passed directly into cost. Beyond that, Barrick right now has several major sustaining capital programs, especially stripping in our pits.
Mark Bristow
executiveAnd once more, that carries an added expense, and higher fuel prices are going to hit those areas as well. All we're doing is providing you with the figures. This doesn't expose us to risk. What I mean is, the nice part about owning world-class assets is that it doesn't expose us to risk, and it definitely has no bearing on how we allocate capital. Managing that impact is part of what we do as managers. Right now, without question, we don't want to compromise any of our commitments when it comes to capital, whether that's growth capital or sustaining capital, because, as you know, we're likely the sole gold company and copper business that doesn't depend on a new project to deliver our five-year plan and our ten-year plan. We feel entirely confident in our capacity to handle the cyclicality of the commodities we mine. As you know, naturally, we've removed roughly $500 million from Barrick's logistics, supply chain, and procurement. In fact, we have budgeted improvements once again this year that will offset the inflationary pressure, whichever inflation it happens to be. You know, the matter of Eastern Europe or simply general embedded inflation, which, as you know, is something visible everywhere right now. Everybody continues to deny that it's a genuine problem for our global economy.
Mark Bristow
executiveHaving said that, I'll hand things over to Graham. He's able to provide a bit more perspective on the way we view the capital. I mean, the way we view the costs.
Graham Shuttleworth
executiveYeah. Thanks, Mark. I mean, I think you've really addressed the question quite well, and it is very tricky to be forecasting costs in the current environment. I'll just say that the current guidance for 2022 in terms of this, you know, at or slightly above our previous guidance is a function of an expectation of $110 oil. As you would have seen, you know, a few weeks ago, we were trading over $120, and then we dropped below $100. It's moving around all over the place. It's difficult to predict, and that's why we're reluctant to be drawn on a particular number. As we look to 2023, as Mark has indicated, it's, you know, so much depends on the global economic environment when we get there. I think that's something we'll give you guidance on at the end of the year, as we always do.
Adam Josephson
analystYeah. No, thank you. Mark, I just want to return to what you were saying. Yeah, we see some of these commodity prices dropping sharply, and like you mentioned, some folks are quick to jump to the conclusion that inflation will fade, disappear, whatever the situation might be. Your point is that it isn't, that this just isn't how things appear at all, that supply chains remain quite troubled. Could you elaborate, Mark, on what you're observing regarding supply chains, et cetera, and how that is impacting the inflation you're contending with and presumably impacting what you believe will be the persistence of that inflation?
Mark Bristow
executiveRight. Supply chains — one aspect is cost, and the other is the capacity to manage them. On the second one, I'd say we've got a handle on it. The team handled COVID really well. I frequently give the illustration that our purchasing of steel balls went from China to Europe, then back to China, then back to Europe. We benefit from having several suppliers, which gives us flexibility. We've increased inventory levels past 3 months, and somewhat beyond that for certain core assets that are under pressure owing to the Ukraine crisis. Several crises are emerging right now. We're not certain exactly. The U.S.A.-China matter has lately been aggravated by events surrounding Taiwan. Multiple problems have arisen. Our approach to handling this is to make sure, first, that we hold partnership relationships. We're heavily contracted, and at this point we possess outstanding supply infrastructure and procurement capability. Here's an illustration: in PV, we faced serious pressure on certain key components for the expansion, and what we've managed to do is bring steel into the country, and we're establishing a manufacturing sector there.
Mark Bristow
executiveA lot of the equipment for Pueblo Viejo, we’ve managed to build it ourselves, and you know, that hasn’t really set us back too badly in terms of the delay—because otherwise we’d have been in a spot where delivery was out of our hands. My own take is that in every crisis, and especially during any major inflationary stretch or global economic downturn I’ve been through, things are always worse than they appear, and recovery takes longer than you expect. In the global economy, very few people are around who really understand inflation. I definitely lived through the last major inflation period, and again, it takes diligence. It absolutely takes world-class assets, and you will come through it. It comes down to agility, innovation, and above all the skill profile of your employees, and then we’ll come through it. Barrick, I think, has all of those components needed to handle this situation. And just to wrap up, Adam, if I may.
Adam Josephson
analystYeah.
Mark Bristow
executiveAs you’re aware, I frequently.
Adam Josephson
analystSure.
Mark Bristow
executiveMake the point that the world is, you know, incredibly muddled. From COP26, where everything was going to be green and clean, we moved to a situation in which all of that got thrown out the window, and now look at where we are. We're burning coal and every other bit of fuel, fossil fuel we can. Just like COVID, there's no global coordination. There's a lot of sort of disengagement. What I, you know, refer to the issues we dealt with in COVID as COVID nationalism, and you're seeing the same again. On top of that, no one's caring about the emerging markets. Then when you look at the drive behind some of these ESG strategies, none of them seem to be sustainable. Sustainable is the real focus when you talk ESG, is how do you build sustainable industry, a sustainable global economy? You can't do that without investing in the developing world, which has largely been neglected. Even last night in the United States Senate, they passed this big bill, but no one even mentioned the emerging markets and the developing world and what is needed there to bring them along. You know, we all know that this world. There's no island on this world.
Mark Bristow
executiveYou can't accomplish things alone. We're seeing more and more proof of that taking place. At the same time, all of this demands more and more mining—and more responsible mining, if we're going to get it right. What we and Barrick are very clear on is that sustainability sits at the center of our focus. We examine high quality assets. We seek to develop them wherever they may be across the world, and we benefit the stakeholders in our host countries to the same degree that we benefit our own shareholders.
Adam Josephson
analystThanks for that, Mark. I’ll ask just one question about the buyback, if I can. Clearly, in the prior quarter, inflation was ramping up and gold went from $2,050 all the way down to $1,700, and my assumption is that this is what created the dislocation in your stock that you had in mind. In your thinking, was the dislocation mainly about gold having reached $1,700? Or what exactly did you mean by the dislocation? On a related note, do you expect these buybacks to continue, or should they? For whatever reason, should we not assume or expect that level of buybacks in later quarters? Thank you.
Mark Bristow
executiveWe made it quite clear that we're going to use this facility for repurchasing our stock whenever we believe it's trading below what we consider fair value, and to tighten up the market when possible. That is exactly what took place last quarter. As you noted, there was considerable weakness in the share price, and we entered the market in a deliberate manner. We don't intend to repurchase all of our shares. In a deliberate manner, we were active in the market. Again, as of today, we believe the same conditions apply, and we will carry on with this buyback strategy that we shared with the market. Again, in a deliberate manner, whenever we believe it serves the interests of our genuine long-term shareholders to remove some of the softness in the market when we can.
Adam Josephson
analystMark, thanks for that.
Operator
operatorThat brings us to the end of the Q&A portion of this conference call.
Mark Bristow
executiveAlright, once more, everyone, we really appreciate the time you’ve given us. I’m certain it was a productive use of it. Thanks again for the questions, and as always, if anyone out there couldn’t come up with something to say or ask, or preferred not to raise it in this public setting, we as a management team are always open to taking your questions. You all know us, so simply get in touch with us, or contact Lois or Kathy, or anyone on our investor team, and we’ll make sure you receive the answer. Once again, many thanks, and for those in the Northern Hemisphere, enjoy the summer, and we’ll talk with you soon.
Operator
operatorThat brings us to the end of today's conference call. If any further questions come up, you can reach out to the Barrick Investor Relations Department. You're welcome to disconnect your lines at this point. Thanks for joining us, and we hope the rest of your day goes well.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Barrick Mining Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Barrick Mining Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Barrick Mining Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.