Barrick Mining Corporation (ABX) Earnings Call Transcript & Summary
August 11, 2025
Earnings Call Speaker Segments
Operator
operatorGood morning, everyone, and thanks for joining Barrick's presentation of our second-quarter 2025 results. Right now, everyone is in listen-only mode. Once the formal remarks wrap up, we'll hold a Q&A session for analysts. Just a reminder that this event is being recorded, and a replay will be posted on Barrick's website later today. I'll hand things over now to Mark Bristow, Barrick's President and CEO. Mark, please go ahead.
Mark Bristow
executiveThanks so much, and a good morning and good afternoon to all of you, and I appreciate everyone being with us today. It's great to be back here in London, where the weather has been wonderful, and to walk you through our second quarter results and talk about the progress we're making throughout the business. Quarter two was a productive one for Barrick, a quarter in which we carried forward the positive momentum from quarter one with stronger production, Tier one assets, and solid advancement on our growth projects. We kept performing within a global environment that is still uncertain and at times even uneven, which underscores the worth of a diversified portfolio, disciplined capital allocation, and the capacity to operate effectively across a range of settings. The results this quarter speak for themselves. The portfolio is delivering, our balance sheet remains strong, and the second half is shaping up to be even better. We're growing real value through delivery, and although the market hasn't fully recognized this yet, we view it as a clear opportunity. Before we begin, I'll just remind everyone that today's presentation contains forward-looking statements and financial measures that are subject to a number of risks and assumptions. The full cautionary language is in the appendix to this presentation and on our website, which you can read at your leisure.
Mark Bristow
executiveTurning to the group highlights: this was yet another quarter that came in according to plan, as we kept taking advantage of the elevated gold price. Output stayed on track with our guidance, and the back half of the year should bring more, consistent with the guidance we set out at the beginning of the year. EPS was more than double the prior year, and adjusted earnings per share came to $0.47 — the best level since 2013. We ended the quarter holding net cash, which let us keep repurchasing shares while also reinforcing the balance sheet. Consistent with our performance dividend policy, the board approved a total dividend of $0.15 per share, including a $0.05 performance top-up. On operations, we're happy with how the portfolio is progressing. Nevada Gold Mines and Pueblo Viejo turned in solid results. Lumwana is beginning to reveal its true potential, the Goldrush ramp-up is building momentum, and naturally Fourmile continues to grow, as we'll cover later. Operationally speaking, this was another quarter where everything was moving in the right direction. Production rose across the portfolio, with solid contributions from Nevada Gold Mines, Pueblo Viejo, Kibali, and Lumwana. Those assets are performing as planned, which positions us for a stronger second half.
Mark Bristow
executiveWhen it comes to copper, we recorded an obvious gain both versus a year earlier and versus the prior quarter. Output rose while unit costs declined. Attributable gold production went up, and importantly, all-in sustaining costs remain a major priority for us, and that discipline is beginning to show up in the figures. With our continued emphasis on Tier one assets, we finished divesting our stake in the Donlin Gold project for $1 billion. That transaction shows how disciplined we are about capital allocation and makes our growth pipeline even sharper. Moving to the group's financial results, better operating performance combined with a stronger gold price produced the best quarterly adjusted earnings per share in more than a decade. We observe a substantial gain in revenue, net earnings, and adjusted net earnings, with all three moving higher against quarter one and against the same quarter a year ago. Our attributable EBITDA growth mirrors stronger margins, and net cash provided by operating activities reached $1.33 billion, a rise of 35% from last quarter excluding interest and income taxes. Free cash flow got better, helped by the gold price and disciplined capital allocation, and as I noted, earnings per share climbed to $0.47, in line with the operational and market tailwinds we've discussed.
Mark Bristow
executiveThe direction we're seeing is unmistakable. Barrick is moving forward positively, and there's still more ahead. This slide really brings out what our clear, consistent capital return framework produces. It shows the disciplined way we allocate capital, making sure we achieve long-term profitability throughout our portfolio while creating value via Tier one assets and new projects. During the first half of the year, we've already given back $753 million to shareholders via dividends and share buybacks combined. That's before the performance dividend we declared, which gets paid in quarter three, consistent with our capital return framework. Importantly, this covers only the first half of the year. Every indicator suggests a stronger second half still, as we keep delivering against our plans. As all of us remind one another daily, at Barrick health and safety stays a core priority, and this quarter brought further gains on both leading and lagging indicators. Year to date, we've recorded a 50% decrease in lost time injuries and a 37% decrease in total injuries versus the same period last year. Those improvements reflect stronger frontline engagement as well as the effectiveness of our critical control verification program, which stays central to the way we manage risk and embed a safety culture throughout all our sites.
Mark Bristow
executiveNow let's move on to operations, beginning with North America. This quarter marked the first time Nevada Gold Mines topped the group's results, powered both by output and by advances on major growth projects. As we've noted previously, the complex is moving toward being mostly an underground operation. To facilitate development, we originally engaged contractors, but we are now returning to self-perform as our in-house teams' capacity grows. At Goldrush, ramp-up is proceeding according to plan as we progress toward main plate capacity. Meanwhile, we're very excited about what Fourmile could deliver — a Barrick asset that is 100% owned and essentially an extension of the Goldrush ore body, only better. I'll cover that in more detail shortly. At Nevada Gold Mines, gold production rose this quarter, underscoring the portfolio's financial strength All-in sustaining costs. that pattern should persist, with additional cost gains expected before year-end. Output improvements came mainly from greater volumes at Carlin, and a decrease in sustaining capital helped bring the overall all-in sustaining cost down. Now that every major planned maintenance shutdown is completed, we're positioned well to deliver a still stronger second half.
Mark Bristow
executiveNow moving on to Fourmile — this asset is quickly emerging as a contender for the biggest and highest-grade gold discovery our industry has seen this century. The potential of the ore body has expanded considerably since we last presented this picture to you, and the grade keeps climbing as well. Let me take a moment here to reflect. As you remember, the resource we calculated at the close of 2024, which this table displays, is shown by the red outline in this graphic. For anyone having trouble spotting that outline, it's also that red arrow. The outline with black dots represents what we anticipate converting during this year, and everything we're seeing suggests we will at least double the current resource. What's even more exciting is the green outline on the slide, where we keep defining meaningful extensions of high-grade ore body. Fourmile is without question shaping up as a generational asset. It's worth placing this in context, and I believe Simon did that at our Investor Day. Consider Goldstrike Underground, which — as some of the older folks in this audience will recall — was the making of Barrick at the time. To date, Goldstrike Underground has yielded roughly 13 million ounces at a grade of about 10 grams per ton.
Mark Bristow
executiveWhat we're seeing from the exploration drilling underway right now — which builds on the earlier program, with a portion of it marked by the yellow dots and black dots, the ones carrying grades next to them — is really bringing the potential into focus. It has been a long while since intersections of these grades, with these thicknesses, have shown up in such numbers. So what you've got is an extension of Goldstrike — sorry, correction, Goldrush. We're now tapping into brittle host rock, and these big breccia bodies are what's delivering the grade. Another key point is that these large bodies are competent. When you hit them — for the geologists or mining engineers listening — as you drill through, the core comes out continuous. That isn't typical for Carlin-style ore bodies, where drilling through the ore bodies gives you plenty of breaks in the core. It genuinely does, and on a like-for-like basis, whether you take Goldstrike or Goldrush, unit underground mining costs are going to come in substantially lower. The other piece of this is the geometallurgy. We're now well along in drilling intersections across that purple patch on the screen, since there are signs that a substantial share of this ore body may well be single refractory ore rather than double refractory.
Mark Bristow
executiveThat's truly the heart of it. For the remainder of this year, the goal is really to establish what this ore body could become. We've held back from the temptation to try to bank it, really so we can get our heads around how big this ore body is and what the grade looks like. We'll begin thinking about what comes next. The next logical step is to consider accessing it from underground. There's an opportunity, with minimal permitting, to do exactly that from the old Bullion Hill site. With that approach, we believe we'll save $500 million-$600 million on drilling versus having to try to drill it out from surface, which would involve long, complicated holes. What I think I want to leave you with — and I'm certainly going to be discussing this each quarter from here on — is how significant this resource is. The key distinction that really ought to be considered here is that this is world-class, tens of millions of ounces, and it sits right in the middle of infrastructure, the Nevada infrastructure. It isn't something you have to go and build up in some complicated location in other parts of the world. I'll leave you with that. When you look at the intersections — multiple meters, 10 m, 20 m, 30 m, 50 m at one and two ounces per ton rather than grams per ton — it's very significant.
Mark Bristow
executiveNow let's turn to Latin America and Asia-Pacific, which turned in another strong, well-rounded quarter. It's important to remember that back in 2019, when we began, this was an extremely difficult region. At Pueblo Viejo, we achieved additional headway on the plant expansion, which helped boost throughput and output from one quarter to the next. Veladero kept up its positive trajectory, and at Zaldívar we obtained a new mining permit for the operation, which now takes its life out to at least 2051. We're also continuing to push the permitting work forward at our El Alto exploration project. As you'll see shortly, Reko Diq is still very much on track — a world-class project with outstanding potential over the long term. At Pueblo Viejo, as I mentioned, we achieved a solid gain in gold production this quarter on higher plant throughput, while also bringing unit costs down. The plant modifications finished last quarter are performing well, and we anticipate sustained momentum as throughput increases further in the second half. You'll recall that we shut down not the entire process but portions of it for 35 days in Q1, concentrating squarely on debottlenecking throughput within the operation. Building of the new tailings facility is moving ahead, with access roads now in progress and engineering design optimization continuing.
Mark Bristow
executiveAs I mentioned earlier, our emphasis during this year has been on removing bottlenecks at the plant and raising throughput. You can see that improvement plainly in the production trend shown here. The small dip in the third bar from the top corresponds to the quarter when operations were halted for a period. That is the reason throughput falls on that light blue bar. Throughput keeps climbing, and we expect steady growth throughout the second half. To reiterate, a planned shutdown affected Q1, yet the broader trajectory remains firmly upward. By 2026, we are aiming for throughput of 12.8 million tons per annum. Equally important, we keep optimizing the life of mine. Although the ramp-up has come gradually, we are handling the blend more aggressively by introducing older, higher-grade stockpiles during this phase, and that is being incorporated into the plan. We will provide updates as we proceed and as our test work on the old stockpiles advances. At Pueblo Viejo, we hold a substantial reserve base in stockpiles. As noted earlier, the resettlement action plan at PV is moving forward well. One key milestone in this quarter was the signing of a formal agreement with the affected communities, which settled every outstanding issue through a commission process mediated by the country's public defender and the Catholic Church.
Mark Bristow
executiveSo with that in place, every week families are now moving into the New Horizons housing estate, and we're making steady progress on this important social commitment. It's worth noting that many of these people were living in the jungle, in single houses that they didn't own. This estate includes a pre-school, a primary school, a middle school, and eventually a technical high school. From your home, you can walk to school. It has running water and sewerage. As you can see, it's a modern estate. Everyone receives a title deed. For people in emerging markets, that's a very important part of building a value base. Turning now to Reko Diq, we've achieved further progress in moving this world-class project forward. Fluor has now been formally onboarded as the EPCM engineering partner, and the design of the tailings storage facility is now complete. Early works are underway, and the project remains on track. For Barrick, Reko Diq continues to represent a significant long-term value opportunity — a truly world-class asset with meaningful upside. We've also made good progress on the project financing, and with the bulk of the due diligence complete and documentation well advanced, we continue to work to complete the financing this year.
Mark Bristow
executiveAs I noted, six years back, opportunities in Latin America and Asia-Pacific were constrained. At present, that region offers a substantial exploration presence and considerable potential for value growth. During this stretch, we have reconstructed our exploration crew and built up a collection of concrete near- and medium-term opportunities. Results in Argentina have been encouraging, with prospects capable of prolonging the mine life at Veladero. In Pakistan, drilling that extends our new discovery at Bukit Pasir continues, and we already hold another new discovery within that mining license. One quick note: at this new discovery, we have encountered certain drill intersections that rank among the finest ever drilled in the Reko Diq porphyry complex. We are talking about hundreds of meters of intersections grading a continuous 0.8% copper. We are likewise pushing new targets forward via drilling in the Dominican Republic and Peru, and further reinforcing our future growth pipeline across the region. Moving to Africa and the Middle East, this quarter centered on further releasing the value potential throughout the region as one of the group's primary cash generators. We observed a robust performance across the portfolio, with encouraging gains at Kibali, which I will address in greater detail shortly.
Mark Bristow
executiveRegarding Mali, we keep handling the circumstances there in a prudent, constructive way. Arbitration is ongoing, and we remain dedicated to securing a way ahead that benefits every stakeholder. Anyone following developments closely should check out the microsite that we recently put up on our website. As I mentioned, Kibali turned in yet another robust quarter, with output rising and unit costs improving throughout, helped partly by lower sustaining capital. We also brought the solar power plant and battery energy storage system online, which further cements Kibali's standing as both one of the most automated gold mines globally and one of the greenest. Tanzania posted another quarter that is on track, with North Mara maintaining its consistent performance. At Bulyanhulu, the expansion project work is ongoing, centered on a second access and production area that will underpin future growth. Gold sales in Tanzania lagged production a bit during the quarter, since we are adjusting to new legislation that requires 20% of production be reserved for in-country trading, with a corresponding royalty reduction benefit. Zambia and Lumwana: we are highly enthusiastic about how the Lumwana Super Pit expansion is coming along. The operation maintained its steady upward path, with production up both year-on-year and quarter-on-quarter and a favorable decrease across all key metrics.
Mark Bristow
executiveThe expansion project is progressing nicely. We have fine-tuned the development plan, and so far this year Lumwana has funded the project itself from operating cash flows, and at current spot prices we expect that to continue for the remainder of the year. When finished, the expanded operation should produce 240,000 tons of copper annually, backed by a processing plant of 52 million tons per annum and a mine life beyond 30 years. It's worth taking a look at the right-hand side of those results. Look at last year, quarter two, 2024: copper production came in at 25,000 tons, then quarter one at 25,027; quarter two at 25,044; along with a corresponding reduction in unit All-in sustaining costs. That is very material, and it's where our attention sits. Since Barrick acquired Lumwana, that mine never turned a profit until 2020. It came down to discipline and unit costs, and now we're going to expand it. Our all-in sustaining cost needs to be below $3. That really validates our feasibility model very well. As you're aware, few copper mines can deliver All-in sustaining costs of -$3 a pound.
Mark Bristow
executiveAfrica and the Middle East are still in a strong position to once again offset reserve depletion this year, which has long been a defining feature of the region throughout its many years of operation. During this quarter, we keep moving near-mine exploration forward, with particularly notable advances along the ARK corridor at Kibali, where drilling is extending mineralized lodes and confirming substantial exploration upside. The ARK lies directly adjacent to the main KCD ore body, and that ore body is the true foundation of Kibali's value. Greenfield programs are likewise making headway throughout the region in Tanzania, the DRC, and across the Central African Copper Belt, which stretches across both southern DRC and Zambia. Beyond that, we continue to push our early-stage exploration in Saudi Arabia, further underscoring how deep our pipeline runs across this region. This slide truly reflects the strength and resilience of our portfolio. As we keep working toward a solution for Loulo-Gounkoto, it's important to recognize that even without it, the underlying value of our portfolio still considerably exceeds our market value. Barrick remains an unmatched opportunity to invest in a world-class gold and copper business, and few, if any, companies in the sector can equal the depth or quality of the growth shown here.
Mark Bristow
executiveIn quarter two, we increased output, and as I've mentioned many times, the back half of the year should bring greater volumes along with reduced costs, consistent with the guidance we've given for the full year. Simultaneously, we are replenishing the gold and copper that we extract and expanding organically by 30% come 2029. This portfolio is being assembled to deliver above Tier one assets, world-class people, and a disciplined capital allocation strategy supporting the whole thing. Our view is that Barrick continues to be among the most compelling investment cases in the gold and copper sector right now. This is an enterprise possessing world-class assets, an unambiguous growth strategy, and the balance sheet needed to finance that growth absent diluting shareholder equity. We keep delivering on our commitments, raising production, replenishing reserves, and returning additional capital to shareholders. This company rests on foundations of long-life assets, strong partnerships, financial discipline, exploration excellence, and a sustainable operating model — the pillars supporting all that we do. In a world seeking real assets, strong partners, and responsible growth, Barrick distinguishes itself. Hardly anyone can equal what we provide, and even fewer can achieve it free of debt or dilution. Many thanks for your time, and we would be glad to take questions.
Mark Bristow
executivePerfect.
Daniel Major
analystHello, this is Daniel Major calling from UBS. Good to see you all here in London. I have a handful of questions for you. To start with Loulo-Gounkoto: I understand that the ideal outcome would be a restart and so forth, but could you share any timelines for the important milestones we should anticipate or watch for as the arbitration proceeds? And what ought we to keep an eye on should the parties fail to reach a resolution?
Mark Bristow
executiveI don't think we've reached a point where we've given up on finding a resolution. Dan, I've consistently maintained that as long as you're engaged and talking, an opportunity always exists. Sure, there's been some activity in Mali that makes the process more complicated, but when it comes to the exit process, the tribunal has been appointed. The Malian authorities have put forward their member to the tribunal, and so have we, and we have an independent president. It's constituted. We've already filed our first application for some interim relief measures, really aimed at cautioning everyone against damaging the assets while we attempt to seek a solution. That process will continue to develop. At the same time, we keep engaging through other sorts of treaty programs between Canada and Mali as well. We have representation in-country through our legal counsel, which is an in-country team with real experience, along with some of our executives who remain in the country. We also have third-party mediation underway. A lot of effort is going in, and we still, as I say, communicate. It would be unwise, and you've seen some efforts to try and bring this discussion dispute into the public domain. We're mindful that that's not the case.
Mark Bristow
executiveWe've set up a page on our site that genuinely keeps people current on the facts, and we'll keep adding to it, so that anyone who wants to check how things are advancing and wants the facts can do so. Over all my years in this business, trying to negotiate out in public isn't a good practice.
Daniel Major
analystAlright, thank you. Regarding divestments, the next question: it seems you're proceeding with Hemlo and Tongon. Zaldívar received an extension on its water permit, so we now have visibility into that asset's life of mine. How does it fit within the portfolio? I suppose the same question applies to Pueblo Viejo — as things stand today, is that a core asset?
Mark Bristow
executiveI believe there's plenty on our plate for the near term, so let's complete that work first. We'll return to the remaining items later, Dan. Earlier today I reminded someone that back in 2019, when we completed the Barrick and Randgold merger, Hemlo was on the block at that time. We put substantial capital into Hemlo to rebuild it into a viable operation. As we've observed, there's genuine interest in mines of this kind. Our position is that a moment comes when we must measure our portfolio against our rigorous standard for tier one, long-life assets capable of carrying us through every cycle in the commodity markets. That's sound practice. As you're aware, we're among the few mining companies that have managed to add 110 million ounces of gold equivalent ounces to Barrick's reserves over the past six years. We put capital into our future. We've introduced meaningful new reserves through Reko Diq, and we've upgraded large reserves at Pueblo Viejo and Lumwana. It's sensible to streamline your portfolio periodically. We did exactly that right away in 2019, as you'll remember. Quite a few years have passed since then.
Mark Bristow
executiveThere's still growth in front of us. Tidying up the portfolio makes a lot of sense. And with buyers present in the market right now, this is a good moment to get it done.
Daniel Major
analystAlright, thank you. If I could just ask one more about Fourmile. Those results look really exciting for what's ahead. Given the growing scale, does this shift how you view the scope of the operation going forward, or the timeline? Yeah, how are you seeing that?
Mark Bristow
executiveA lot still has to happen at Fourmile before things are settled. We've compressed the schedule, and our aim is to have something like a scoping-level position on the project by the close of this year. After that, we'll determine the following step — whether that's pre-feasibility or feasibility, and precisely how we move it forward. From my perspective, when you look at Fourmile alongside Nevada Gold Mines — if you were to slot Fourmile into the center of Nevada Gold Mines, which is exactly where it belongs — you'd be substituting some of the roaster feed, our bottleneck, with material at 3x-4x the grade. That lets you lift the profile, extend mine life, and bring costs down. Inside that complex, it's a highly valuable asset. I'd say the tougher part — you know, we've put a great deal of effort into our partnership with Newmont and with Nevada Gold Mines, and we'll keep at it. At the same time, I believe we've demonstrated an ability to permit mines here in the United States. We permitted Goldrush and Robertson not long ago. That happened under a pre-Trump administration. Naturally, the sitting administration has made things considerably easier, or rather has concentrated the permitting process so it can't be taken over by litigation, ensuring it stays focused and nobody is attempting to alter the regulations.
Mark Bristow
executiveThose rules are sensible and consistent with how we see things globally. One more point I’d make: we’re quite active on brownfield and greenfield extensions to the Nevada portfolio. That means the Nevada Gold Mines portfolio — the joint venture portfolio — as well as Barrick itself operating farther out across Nevada. We recognize this opportunity. It’s something we’ve seen consistently. We’ve been putting investment into building that knowledge and making sure we’re able to permit drill platforms, which we’ve gotten quite good at by now. Through the remainder of this year, you’ll see additional opportunities. We’ll highlight further chances to grow our portfolio inside the United States.
Daniel Major
analystThat’s great—thank you.
Maurizio Carulli
analystMaurizio Carulli here, from Quilter Chief Investment Management. It's been a while since I've tracked this company, so please forgive me if my two questions show a lack of familiarity. On Loulo, regarding the balance sheet — has the book value of the assets been partly impaired, or fully impaired? Where does that stand now?
Mark Bristow
executiveI'll hand things over to Graham. Given where we are right now, this is an accounting matter, and he's the right person to walk you through it. Is it on?
Graham Shuttleworth
executiveRight. Yeah, as Mark mentioned, from an accounting standpoint, once the government installed the administrator to assume control of Loulo-Gounkoto, we ceased to have control over that asset. So from an accounting perspective, when control of the asset is lost, consolidation is no longer possible. We took two actions. We deconsolidated the asset and effectively wrote off the assets and liabilities on the balance sheet. We then performed an evaluation of our investment, since we still held 80% of that asset. We can still expect to receive the benefits from our investment in that asset. We carried out a valuation of that asset using a number of different metrics, including risk-adjusted cash flows that we anticipate receiving from the asset over a period of time. The difference between those two came to approximately $1 billion before tax, about $600 million after tax, which is what went through the P&L. I'd just note at this point that we also sold the Donlin Gold asset during the quarter. We recognized a gain on that, which was around $750 million after tax, about $600 million. In effect, we had a loss and a gain that more or less offset each other, which is why, when you look at adjusted earnings and net earnings, they're approximately the same.
Maurizio Carulli
analystAlright, thanks a lot. That's much clearer now. My second question is really just to get a little more detail on your project in Saudi Arabia, Jabal Sayid, if I'm saying that right — both regarding the ownership structure and regarding development, expectations, and so on and so forth.
Mark Bristow
executiveIt's a compact underground mine with high-grade copper. It still has a 10-year life. We've done really well at extending that life and boosting output. This is a producer with very low costs. All of its loans and debt have been repaid, and it makes a major contribution to its partnership. Ma'aden and Barrick each own 50/50 of it. In effect, we're the sole foreign operator, since we run the mine. We're equal partners with Ma'aden, but the operation is ours to run. What it has demonstrated is that operating in Saudi is feasible. Together with Ma'aden, we've grown our partnership in the exploration fund, both in the area around Jabal Sayid. Lately, we're looking past that partnership, because that one is the genuine partnership. Over my career in complicated jurisdictions, I've established plenty of partnerships. Ma'aden, as you're aware, is effectively the state mining company. It has considerable depth and is strongly focused on bulk mining. That's where its main value lies. It holds a portfolio of exploration rights spanning the Arabian Shield, and we regard that as a minerals belt with high prospects, especially prospective for gold as well as copper. We're collaborating with Ma'aden to grow our partnership throughout that region.
Maurizio Carulli
analystMuch appreciated.
Mark Bristow
executiveDoes anyone here have a question?
Justine Barry
unknownJustine Barry from JPMorgan here. I have a brief question regarding Lumwana and the power situation in Zambia. Could you share any update on availability as well as the power plans in that area? Thank you.
Mark Bristow
executiveAnd it's good to see you too, Justine. We invested considerable effort into the fee during the feasibility work for the power expansion. We carried out an extensive survey across the entire Zambian power grid. Two things came out of that—we've handled the power situation. In the near term, given the low water levels in the Zambezi River, what we did was collaborate with the state power utility to wheel electricity through the grid from neighboring countries. That was achievable at a fairly cost-effective level, far cheaper than operating diesel engines. The second discovery was that the grid was losing a substantial amount of power owing to poor synchronization of the feeds entering it from various sources. Through a partnership of First Quantum and Barrick, we set out to tackle that and unlock—by our estimate—roughly 500 MW of power. We've put money into technology to resynchronize that power and unlock a portion of what was being lost. We have a partnership with First Quantum. They're putting capital into what we refer to as statcoms, which are essentially these synchronizers. We are financing some extra redundancy power lines in order to create loops in the feed.
Mark Bristow
executiveIt's once more being done alongside ZESCO. Our view is that — and we now hold the permits for the electricity our expansion needs, and so does First Quantum. Our belief is that jointly we'll be in a position to underpin the greater demand stemming from the power expansions and from their expansions. Simultaneously, quite a few power projects in the Zambian grid require investment yet are certainly capable of delivering inexpensive electricity. That power region is — you know, these days people talk about exporting electricity from Zambia over to DRC. That strikes me as about the oddest thing I've ever come across, since, you know, DRC is the genuine power sink across Central Africa. The Tanzanians are building and have lately completed a sizable hydro facility inside Tanzania. It's genuinely big. Once fully developed, it will carry substantial capacity. Serious negotiations are now underway about connecting that infrastructure into the region. Increasingly, that region — the SADC region — is examining integrating its power infrastructure among the different countries. There's a fair amount of opportunity to enhance the security of electricity supply and also to make it more cost-effective. We're heavily involved in it. We're at ease that we'll manage with the plans now in place, the expansion for Lumwana.
Mark Bristow
executiveAll right, should we get started? Claudia, are you running things there?
Operator
operatorWe’re going to use the raise hand feature for the Q&A portion of today’s session. If you have a question, please click the raise hand button located at the bottom of the screen. When you’re prompted, unmute your line and start with your question. We’ll take a brief pause while the queue forms. Our first question comes from Matthew Murphy at BMO Capital Markets. Your line is open. Please go ahead with your question.
Matthew Murphy
analystHey, Mark and the team. I’ve got a couple of questions about the sequential outlook for the back half of the year. The first is Pueblo Viejo, especially the emphasis on better recoveries. Is 85% recovery in Q4 still the target, or how are you thinking about that? The second is the cost trajectory at Nevada Gold Mines. How do you feel about the path toward lower gold unit costs in the back half of the year?
Mark Bristow
executiveMatthew, if you run the numbers, you'll see output has improved throughout the group, especially at Nevada Gold Mines. At this point, once you account for the higher gold price, we're protecting the expectation that we'll reach that point, definitely on a group basis, by the latter part of the year. At PV, throughput is the main thing we're watching. With the expansion delays, especially on the tailings facility, one factor is that there's a sizable stockpile that we blend with the threshold. Part of that stockpile is high grade, but it's declining. In 2019, we carried out a thorough assessment of those stockpiles going into 2020. We've launched another campaign, and the thinking is that we have to review that blend and also bring in the older stockpiles, which, incidentally, carry higher grade. What this also does in the current gold price setting is boost cash flow, since these stockpiles, as you know, have already been paid for. We'll keep you updated as that progresses. Recoveries and the profile have always been a topic of debate. Over time, we'll let you know how that develops. Graham, would you like to add anything?
Graham Shuttleworth
executiveLet me just add this, Matt: regarding our outlook for the second half of the year, we obviously provided guidance of 46 to 54 for the first half and the second half. We've also said that every quarter improves sequentially. You can work out the numbers on your own, but if it's 54 and the midpoint is 27, perhaps it comes in at 26 to 28 or thereabouts, just to give you some broad parameters for what sort of step-ups you can expect.
Mark Bristow
executiveI think, Matt, just to wrap things up — as you're aware, I brought this up earlier during my presentation — we experienced quite a bit of downtime. At Gold Quarry — or, first off, the Goldstrike roaster, the Gold Quarry roaster, and the autoclaves. There was the winder replacement, plus the motor replacement at Kibali. We weren't down 100%, but we were intermittently down across 35 days at PV. Much of that — some of it retrofitting work, other parts planned maintenance — now sits behind us. We have a reasonably solid stretch ahead through year-end, which backs up Graham's outline of how we expect to perform.
Matthew Murphy
analystAll right, thanks.
Mark Bristow
executiveThere's nothing magical about those figures.
Operator
operatorAnita Soni from CIBC is up next with a question. Your line is open, so go ahead and ask.
Anita Soni
analystHello there, good afternoon, Mark, and to the rest of the team. I have a small follow-up regarding PV, building on what Matt raised. With grades being considerably higher, could you tell us where the stockpile currently sits in millions of tons, or alternatively how many tons you expect to process as you resequence?
Mark Bristow
executiveThat's quite a lot. Simon, have you joined the call? Anita, let's go ahead, but it's like, you know, when you—I'd estimate roughly 10 million ounces sitting in stockpiles. That's 20 million through to the end of the mine life. It's substantial. I can provide you with the—I can pull those figures. They're disclosed in our filings.
Anita Soni
analystCould you give us a sense of — I mean, you're driving throughput up. At PV, that throughput was quite high and quite solid. As we consider the tailings facility, how much headroom do you have in front of you, and how ought we to think about the second phase, and at what point do you need it?
Mark Bristow
executiveOur capacity is secured through 2030, and that includes some room to lengthen how long the existing tailings facility operates. At the moment, our attention is firmly on ensuring we time the building of the tailings facility so it can take tailings toward the latter part of this decade.
Anita Soni
analystOkay, let's turn to Turquoise Ridge.
Mark Bristow
executiveRidge.
Anita Soni
analystYeah, I was just going to bring up Turquoise Ridge. Could you remind me — you're also working through stockpiles there, correct? I mean, the grades you're mining are much higher than what's going through the process plant. When do you think you'll shift back more toward a higher blend, I guess, of underground material versus stockpiles?
Mark Bristow
executiveWhat matters at present, you know, is that a portion of the high-grade material is high in carbon, so blending becomes necessary in order to keep recoveries under control. That blending management is what the life of mine plan is about. As for throughput, you observed it this quarter — there remains some headroom there. Recoveries are holding up well. Turquoise Ridge, you know, is a significant asset for us. Additional opportunities exist in the open pits. Is Simon on the line? Simon? Yeah.
Simon Bottoms
executiveYes, I’m present. Are you able to hear me at this point?
Mark Bristow
executiveSomeone raised a question regarding the tonnage and grades of the stockpile at PV.
Simon Bottoms
executiveSo we have 97 million tons at 2.45 grams per ton, and some parts of that stockpile were operated at grades up to 2.7 grams.
Anita Soni
analystAll right,
Mark Bristow
executiveAll right, here we go. That answers it. If you check the inventories at Turquoise Ridge — sorry, hold on a moment, I need to pull up those figures.
Anita Soni
analystNo problem—I'll make this my final question, then.
Matthew Murphy
analystI’ll return to that point with you.
Anita Soni
analystYeah. And just last thing, sorry, I'm midway through my modeling here, or actually roughly two-thirds done with it. On the, oh, Porgera, that was Porgera, I realize it's a small contribution, but it looks like you've got a pretty meaningful ramp-up there in, you know, getting back to those earlier run rates from before you had all those problems with, well, the country had that landslide issue. What should we expect in the back half of the year, and what does 2026 look like?
Mark Bristow
executiveWe have genuinely optimized Porgera again. When you consider the dividends distributed and the share of those dividends going to the two investors, Zijin and us, that figure is substantial. We are currently working to recover the capital we invested while the operation was under care and maintenance. Every dollar returned to the investors carries a larger cash flow element, and recovering that capital matters to us. At the same time, we remain among the biggest contributors to the Treasury in Papua New Guinea. I am not sure whether you track this, but you would likely have noticed that the Prime Minister issued a press release not long ago commending Porgera for what it contributes to the Treasury. Graham, would you like to add anything?
Graham Shuttleworth
executiveAnita, on the production side, what I was about to say is that the outlook comes in a bit above the first half, though not by much. As for what you asked earlier about Turquoise Ridge, the stockpile stands at 26 million tons grading 2.26 grams per ton.
Anita Soni
analystAll right, I really appreciate it.
Mark Bristow
executiveThere's another point, Anita, and I'd encourage all the analysts to contact our team about this: Barrick's approach is that we don't build mine plans around maximizing NPV. Our mine plans are built for long-term delivery, so the ore body is fully optimized. That has always been our approach, and it is how we will keep doing things. When you build models, you have to understand our philosophy, which differs considerably from others in this industry. You won't see a huge production increase up front followed by a cliff forming at the back end of your mine life.
Anita Soni
analystAll right, thanks.
Operator
operatorJust a quick reminder — if you'd like to ask a question, click the raise hand button located at the bottom of your screen. Josh Wolfson from RBC has our next question. Your line is open, so please go ahead.
Josh Wolfson
analystThanks a lot. If we return to the Fourmile slide, slide 10, and look at a few of these outlines, the resource we already have appears to be considerably under half of the total footprint. That's roughly what's shown in green there. The grade also seems — perhaps 50%, or maybe a bit above that — but the existing resource carries a substantially lower grade than what has been delineated. At least in my view, there are some pretty large updates at this asset. So I guess, first of all, is that the correct way to think about it? The second part is that an initial PEA was issued, I believe late last year, which mentioned more than half a million ounces, yearly production rates, and a throughput rate tied to that. The second part is whether we should still regard those economic criteria as applicable if this resource ultimately proves to be what it looks like on this page.
Mark Bristow
executiveWell, Josh, honestly, I’m not sure where to begin. I mean, what more could you possibly want? We’re fully occupied with this evaluation. As you can see, the figures we gave you at the close of last year appear in that embedded table. Fresh results come in every day. They need to be verified. As you’d expect, these boreholes are long. Drilling them takes considerable time. Those preliminary numbers reflected drilling completed up to that point. The black dots, as you can see, represent boreholes we’ve finished. The yellow dots are ones still awaiting drilling. Some significant numbers have yet to emerge from this ore body, and in our correction, the yellow ones are what we’re drilling in 2025. A portion of them are drilled. That’s the yellow — I mean the white arrows. The rest, which have no grays on them, either still need drilling or have been drilled without results returned yet. My view is this is a modeled interpretation built on the early-stage drilling we’ve completed. Continuity is turning out much better than we expected.
Mark Bristow
executiveThe scale of these breaches is considerable. Later, once we get you out in the field following Denver, those of you attending can see the situation firsthand. It's significant.
Josh Wolfson
analystThanks. I'll see you there. So my second question is, I suppose, when you consider how the stock is valued and also, I guess, in light of the upside here at Fourmile, how are you approaching capital allocation? You know, looking at the results for this quarter, buyback levels came in healthy. They rose versus last quarter. There was also a sizable disposition that bolstered the cash position, but you know, a portion of that went toward the dividend. That inflow from an asset sale may not recur down the road, though it could. The bottom line, I guess, is how would you be allocating cash going forward from here, and how important is the buyback?
Mark Bristow
executiveI believe we're on course for — we're dedicated to that strategy of buying back $1 billion. So far this year we're at $411 million, and that's how we'll handle it under our approach to capital allocation. We're pretty disciplined about how we manage capital allocation. As I've said, you know, Graham and I have operated that way certainly from the time we started working together. Would you like to add anything, Graham?
Graham Shuttleworth
executiveRight, I hear you. As I keep telling Josh, when you put the performance dividend together with the buybacks, that's what gives us the capacity to capitalize on the situation the way we see it. At this moment we have the $1 billion that's earmarked. If it turns out we end up with excess capital, we've got options. Clearly we can boost the buyback if we've used it all up. We're always on the lookout for opportunities, obviously, and we can keep paying a performance dividend. It comes down to capitalizing on our options and preserving our flexibility. Buybacks are definitely something we'll focus on more and more, since the shares are very undervalued.
Mark Bristow
executiveJosh, one more thing on this: if you take a look at Lumwana, when we set out the total capital guidance for Lumwana, the plan was for us to put money in this year. At this point, unless copper prices fall sharply, we'll be funding the full capital spend at Lumwana this year. That materially reduces that $2 billion headline number as we move forward. What we're signaling is that Barrick's five-year plan can easily be financed out of internal resources. As for non-core asset sales, part of the proceeds will go toward — as Graham mentioned — handling that process within our capital allocation guidelines. Part of the proceeds will fund share buybacks, since that makes sense given that you're removing production. Part of the proceeds will be returned to shareholders, because it's an extraordinary benefit. I've always said in business that when you do something you hadn't planned on doing, you ought to share it with your owners. That's our approach. On the capital front, I think we're quite comfortable that we can fund our future. I'd simply note one thing the market hasn't grasped: once we reach the point where we can demonstrate the financing for Reko Diq, that removes the market's fixation on the gearing that people keep writing about.
Mark Bristow
executiveThere are some pretty meaningful catalysts coming, and honestly, they land in nearly every quarter from now through the beginning of 2028.
Josh Wolfson
analystExcellent. I really appreciate it.
Operator
operatorWe'll take our next question from Tanya Jakusconek at Scotiabank. Your line is open. Go ahead with your question. Tanya, your line is open. Please go ahead. It seems Tanya is dealing with some audio problems. We'll proceed to the following question. John Tumazos with John Tumazos Very Independent Research. Your line is open. Please ask your question.
John Tumazos
analystThanks a lot. Could you bring us up to date on where your Canadian tax losses stand, and whether there's a set date when they lapse? The American ones do at some stage, and how does that factor into the choice to sell Hemlo or perhaps acquire something in its place?
Graham Shuttleworth
executiveJohn, this is Graham. We hold roughly $2 billion in ordinary losses, plus a further $2 billion in capital losses. Generally speaking, those carry around a 20-year expiry, though certain ones never expire. There's a considerable amount of headroom and runway available to us on those tax losses. In the context of the Hemlo disposal, to be sure, they'd be quite helpful in shielding a substantial portion of the proceeds from that sale.
John Tumazos
analystI appreciate that.
Operator
operatorFor our final question, we go to Martin Pradier of Veritas Investment Research. Your line is open, so please go ahead with your question.
Martin Pradier
analystYeah, thanks. I'd like to ask about Tanzania. That 20% — at what price do you need to sell it?
Mark Bristow
executiveThe spot price is one that's tied to the market. That's why we held off during this quarter, simply to make sure everything was done properly. We want to — you know, we've put forward proposals for getting the gold back from the Rand Refinery in refined form, or else selling it into Tanzania to other buyers. Our requirement is that it has to pass through the central bank, and the agreement goes along with that. We need to reach consensus on how the check assays are done and the follow-up, plus how we'll handle any disagreements. The upside there is that we gain a 3% advantage, since no duties are payable on that export because it's internal. That's a meaningful benefit for us, at least where gold prices are concerned. As you know, we have a solid engagement with the government of Tanzania, and that's our focus — just making sure everyone agrees on how it works and that we have proper binding agreements in place.
Martin Pradier
analystOkay, just one final question. If you’re able to share, how far along are the discussions regarding Tongon? I’ve seen in the news that some offers were made, and, you know, might we see something by the end of this quarter?
Mark Bristow
executiveThere's one thing I can state with complete confidence, and that's this: don't pay attention to the rumors some of these reporters are spreading. As you're aware, these processes move forward in a very disciplined way, guided by our investment banking partners, and we don't reveal where things stand until the process has concluded. We certainly do involve our host countries throughout the process, but leaking or revealing how far along things are — or even who is taking part — would be unprofessional.
Martin Pradier
analystI appreciate that.
Operator
operatorThat wraps up the question-and-answer portion. Mark Bristow, I'll hand things over to you now for your closing remarks.
Mark Bristow
executiveThank you, ladies and gentlemen. As I mentioned, today hasn't been especially buoyant for gold, what with the chatter about charges on gold bars that surfaced late last week. For our business, it was a strong showing following the opening we had in quarter one, with a very clear goal and a start on delivering across the full year. I think this stands as a fine illustration of how we deploy capital and the enormous value we've built into this organization. Truly, when NAV grows, bringing that to light is always difficult. Doing M&A is far simpler. That expansion — that organic expansion — is where value is genuinely created in mining. We're very well placed to make good on that. Thanks once more to those who attended, especially in this lovely London weather. For everyone else, I hope to see you in Denver. After that, for those coming along with us on the trip, it will be good to catch up. With that, many thanks again and talk to you soon.
Operator
operatorThat wraps up today's event. If any questions come up, please reach out to the Investor Relations Department at Barrick. Thanks for being with us.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Barrick Mining Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Barrick Mining Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Barrick Mining Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.