Bathurst Resources Limited (BRL) Earnings Call Transcript & Summary

August 29, 2025

Australian Securities Exchange AU Materials Metals and Mining earnings 23 min

Earnings Call Speaker Segments

Richard Tacon

executive
#1

Hello, everyone. Many thanks for being with us for the FY '25 full year results release and an update on the company. I'll share my screen now to pull up the presentation that came out earlier today. Thank you. Okay, and disclosures. For anyone new to Bathurst, I'd like to give a quick overview of how we're structured. Obviously, Bathurst is an operating coal mining company. We have 4 operations in New Zealand with different ownership arrangements, some 100% owned, some held through a joint venture with a New Zealand family-based company. We hold 65% of that joint venture, and we serve as the mine operator. Next to our Stockton operations sits the Buller project, which again is 100% owned by Bathurst, and the recently acquired Tenas project, which we've had now for a couple of years, and we'll talk about that as we move further forward, and the joint venture with Jameson Resources on the Crown Mountain project in the Elk Valley, again in British Columbia. So we have a solid base of existing operations, and backing that up are some longer-term projects that we'll certainly discuss as we go further through. Market cap of around $190 million at the end of July, an enterprise value of around AUD 35 million.

Richard Tacon

executive
#2

Right now, we hold roughly NZD 170 million in consolidated funds. Our Board is highly experienced and has been working together since 2015, and we're well placed to move this company forward. So I'd say the central strategy, spanning many years now, has been to run operations that are successful, safe, and profitable. That gives us a mix of operations via the joint venture — Stockton, Maramarua, and Rotowaro — plus Takitimu, which we own 100%. Each serves a different market segment: Takitimu mainly provides process heat energy for value-added New Zealand production, Stockton sends 100% of its output to export for steelmaking, and Maramarua and Rotowaro primarily supply New Zealand's sole steelmaker. Around each of these, and also by bringing in some new greenfields and brownfields sites, we have a range of growth projects that let us carry existing tonnage forward while also lifting our overall exports — in particular the Tenas project, by really 100%. The aim of that strategy is then to begin delivering reliable, repeatable capital returns to shareholders. So essentially, what we're doing is building on the success we've achieved by taking the assets we bought back in 2017 through the joint venture.

Richard Tacon

executive
#3

We have demonstrated the ability to run those operations. A substantial amount of cash has been produced by that business. And what we want now is to move that business ahead, but increasingly around the Bathurst asset, which is 100% owned. So once more, the picture is really the same. There are 2 mines for us in the North Island. That's -- <<inaudible>> apologies. Stockton and Maramarua, plus Rotowaro in the middle of the North Island. Stockton sits on the West Coast, immediately next to the Buller project, which forms part of the development we will discuss as we go further forward, and Takitimu is located right down in the deep south, mainly supplying coal into the south and the southern parts of Canterbury. We also have a head office in Wellington and a suboffice in Christchurch. So turning just to the results for the last financial year, which ended 30 June this year. Revenue fell quite considerably compared with FY '24 but remained very positive, at around $270 million. From that, we generated $44 million of EBITDA at a consolidated level. On revenue, as I said, we have NZD 178 million, all of these in, at the end of the financial year, and we recorded a profit of NZD 4.4 million once again on a consolidated basis.

Richard Tacon

executive
#4

Clearly, that's a fair amount lower than the prior year, though it remains firmly positive. If we go through the primary operating segments individually, beginning with exports: the important point, I'd say, is that we had close to 6 months — for anyone who has tracked this company, there was a — well, we didn't. In our rail supply, a tunnel collapsed within the — one portion of the supply chain. That effectively took out the initial segment of our logistics running from the mine to a place named Reefton, roughly 100 kilometers away, and it was out of action for approximately 6 months. It occurred in late June 2024. We only had it running at full capacity again earlier this year, in the middle of January 2025. It cost us roughly $15 million in direct costs. We did receive some insurance relief from that. But the crucial point was that we did have to reduce tonnage somewhat. We actually recovered almost all of that tonnage by the close of the financial year, which was — we ended up short by one boat, 50,000 tonnes, which moved into the following financial year. But what mattered most, I'd say, for us was that we satisfied the requirements of our major customers.

Richard Tacon

executive
#5

We did miss a business development opportunity, though it wasn't really contracted coal in any case. So, as you can see, there was also a fairly substantial decline in export pricing, and that in turn brought lower revenue along with lower EBITDA. At Rotowaro, we're currently in a significant cutback period. We've completed the coal that remained in the Waipuna extension area — the project we'd been working on over the last 4 years. We've now shifted into the Waipuna west extension, and that one comes with a fairly big stripping requirement. So our stripping rose 50% from '24 to '25, and also — but we did shift into some additional coal sales. So part of that provided an offset. As a result, we finished with a bigger EBITDA, roughly $80 million to $90 million. We're carrying a similar burden this year. We'll move about 10 million bcm this year, and after that it will fall away sharply in the years that follow. So a lot of cash is currently tied up in that cutback, and we'll begin to see that cash come through into the business across the next 3 or 4 years. Maramarua is a similar story. Sales stepped down a little as some of our domestic customers dropped out, but we're raising the volume of coal from that business that goes into steelmaking.

Richard Tacon

executive
#6

EBITDA has been fairly steady, though we did record an extra 600,000 bcm as we transition into the M1 pit — we secured the resource consent for that earlier in the early part of 2025. At Takitimu, we're winding down now, unfortunately. We'd like to extend into another block, but the customer base simply isn't there to support it. So people are either stepping away from coal or leaving the district altogether. This year we'll post a good, strong EBITDA result. Last year we were down slightly, purely because of lower tonnage and a modest rise in the amount of overburden we had to move. We have roughly 12 months of full production remaining, after which we enter a final year of rehabilitation. Regarding our contribution to New Zealand — which matters a great deal now as we head into this next phase of the business — looking at our fast-track application, we have around 700 employees across most of the operating mines, and $90 million paid to employees. Our direct payments to the government come to about $11 million. And obviously, there's also the flow-on from taxes generated through the employees and likewise from suppliers via ordinary GST.

Richard Tacon

executive
#7

That is a fairly big drop versus the prior year, since during that prior year we clearly made some sizable tax payments that arrived as a result of the extraordinary pricing seen in FY '22 and '23. On our health and safety figures, we have put in a great deal of effort. Clearly, a lost time injury frequency rate of 4.5 looks high next to what some of our peers in Australia, and perhaps the U.S. and Canada, report, though we have fallen from a base that was higher still. So substantial effort is going into risk management, and substantial effort is going into training especially. We have brought in a learning management system that standardized, through a database, both our recordkeeping and our competency analysis, and then also takes us into e-learning. We have, in a sense, two different sets of operations. At Stockton and Rotowaro, our 2 bigger operations, we have recorded a number of injuries there. Yet at Takitimu we have now gone over 3,000 days lost time injury free, and Maramarua stands at over 1,500 days lost time injury free. So we need to take those lessons and then apply them at the 2 larger mines -- apologies for that. Going forward, we are looking at consolidated guidance, or consolidated EBITDA guidance, of roughly $45 million, within a range of $35 million to $45 million.

Richard Tacon

executive
#8

The main shift there, clearly, is that export pricing has fallen substantially, and it's even below where the average sat a year ago. What we're observing is a decline in the -- actually, an uptick in EBITDA produced by the North Island, and cash generation from the North Island will also rise a couple of years from now. At the same time, we're taking on extra costs because of shutting Takitimu and Canterbury within the South Island operations. And this business has consistently been profitable. We are -- clearly very reliant on the worldwide coal price. So the graph here shows -- the darker blue represents EBITDA on a consolidated basis coming from the export business. Once more, FY '21 was hit by COVID. FY '20 was hit by COVID. And after that came the big rise in coal price, shown by the red line across the '22, '23 stretch, before it scales off once more going into '24, '25 and then '26. So it's largely a fixed-price kind of business, with fixed costs, yet any rise in that export coking coal price means we'll see profitability in the business jump up quite well. On the curve itself, we're observing a curve in more contango.

Richard Tacon

executive
#9

I believe that the majority of proponents and analysts are indicating the supply-and-demand balance isn't really shifting. We aren't seeing fresh supply entering the industry, and we aren't seeing demand falling away on either side. So pricing is expected to rise well above USD 200 across the next couple of years. What matters most for our business right now is to consolidate where we stand today but also to bring the new projects online so we can benefit from that higher pricing as we go further forward. So let's discuss that now. The Buller project sits directly adjacent to Stockton. What we intend here is to leverage the existing stock and infrastructure that we control. There is coal still remaining in the Stockton holdings, with reserves there sufficient for another 3 years. And after that, we're planning to bring in Buller coal along with some coal that's sort of held between the 2, Denniston and Stockton plateaus, to add up to sustaining roughly 1.1 million tonnes of export out for another 15 to 20 years. The Tenas project is entirely greenfield, with no other mines in the area. As I mentioned, we've been in there since '22. We are working our way toward submitting the final application for environmental certificate through the Environmental Assessment Office, and after that we'll move into the permitting phase.

Richard Tacon

executive
#10

This is a genuinely exciting project — roughly 750,000 tonnes per year across about 20 years. At Buller, we're targeting an average of somewhere around 850,000 tonnes over roughly 13 or 15 years, and that comes on top of the coal that's left at Stockton. If you picture it as a graph, the lighter blue portion represents the tonnes still remaining at Stockton. You can see that beyond '29, the volumes begin falling away quite sharply. The plan, though, is to backfill those tonnes with material from Denniston and the Mount Fred area. That's what lets us hold roughly 1.1 million tonnes well beyond 2040. Our approach is to make use of infrastructure that's already in place, link the 2 plateau areas via a dedicated haul road, and take up any spare capacity at the Stockton CHPP. Then, as the Stockton reserve declines, we'll substitute tonnes from the other development areas. We already have rail and port access in place, we already have customer bases established, the coal seams are exactly the same, and we'll satisfy exactly the same market requirements. On the planning side, we're aiming to lodge the fast-track application at some point later this year. We'd then expect it to be granted later in the following calendar year, in FY '26.

Richard Tacon

executive
#11

Our plan is to put out a pre-feasibility study for that project at the start of September, and after that we'll follow it with the DFS at a later point in the next calendar year. Essentially, there are some early works on the access road that we can begin once we have a reasonable degree of certainty about being accepted into the fast track. This project is already listed under the Fast Track Act, so the referral stage has been met. At this point we simply need to work through completeness, then move on to a panel, and finally come out the other side if we can persuade a panel that our conditions are right for addressing the environmental impacts especially. Naturally, we think it will be economically significant regionally and/or nationally. What we're looking at is a business that puts roughly $300 million of revenue into the New Zealand system annually. So it is certainly significant regionally, and possibly nationally too. As for the fast track, that is a process which was clearly brought in by the current government in December last year, 2024. It genuinely establishes a pathway containing very fixed time frames.

Richard Tacon

executive
#12

But I guess the key point is that we submit a single application, and from there we have a pathway to obtain all the different resource consents, approvals, and permits required to begin operating — and that's genuinely the new element here. So it's labeled fast track, yet in reality it functions as a one-stop shop. That's the heart of it. And there are time limits laid down for the panel as well as for the named parties under the act — those we must consult with beforehand, and then those who will be obliged to provide comments on the project — plus deadlines on us to actually return those comments. So it's very much a first-in, first-out kind of process, and right now we're putting hard work into that application to ensure we can move through that tightly time-constrained process very swiftly. So there's a pathway at the end of it for judicial review and appeal by anyone who is either a statutory partner to the FDA or who has been invited into the FDA. And so, once again, one of the crucial things we're doing at the outset is making certain we've consulted with everyone as much as we can, but also that we've dealt with as many of the issues they might have raised early — and that we know will be raised as part of the project — within our initial application.

Richard Tacon

executive
#13

So we'd like that to be settled if at all possible. And when we can't reach agreement, we make sure to spell out plainly where the boundaries of our disagreement lie. Tenas, this project sits roughly in middle BC, straight north of Vancouver — around a 2-hour flight up, and quite close to the Ridley coal port, which has ample capacity. We also hold a parcel of land right next to the main rail line. So when it comes to infrastructure, the project is in a strong position. As I mentioned, it's entirely greenfields. There is another mine in that area. We have solid local backing. We're progressing with First Nations groups that hold either interest land or a registered interest. As part of that effort, we took a group of people — 16 of them — over to New Zealand to look at our existing operations and also to engage with First Nation groups there that we work with routinely, both on the West Coast and on the North Island. I believe we all gained plenty of learnings from that, and it has built a degree of trust that I think is now beginning to show results.

Richard Tacon

executive
#14

So once more, our aim is to have that last environmental submission filed around October or November of this year. Getting through that process should take roughly 6 months, and after that we'll begin work on the permits. Once the environmental certificate is actually in hand — assuming it all goes smoothly — we can then kick off some of the other preworks needed to bring the project into production. Again, nothing by way of infrastructure exists there. We have to build everything from scratch, and over the coming couple of months we're also aiming to update the PFS so the market gets a sense of where we believe the capital will land and where we believe the costs will land. Same story again: we want to wrap up the remaining information requests that came in from the last phase of the EAO process, get that effect assessment underway, and from there we'll move on to the permit documents. After we clear that stage, we can then move into actually building the project, with our sights set on first coal in FY '28. So what we're really setting out to build is a business that will be predominantly 100% owned Bathurst coal, as much as 2.5 million tonnes a year feeding steelmaking — a mix of international steelmaking in the Asian markets we currently supply, meaning India, South Korea, Japan and a small amount into China, while still keeping, through the joint venture, a supply of coal to the New Zealand steelmaking business as well.

Richard Tacon

executive
#15

As things stand right now, we're holding roughly $170 million in consolidated cash as of the end of July. There's no debt whatsoever on our balance sheet — that applies both to the joint venture and at the Bathurst level. At the Bathurst level, we expect to generate EBITDA somewhere in the range of $35 million to $45 million again this year, with asset backing of $1.75 per share, and right now our cash backing sits at approximately $0.66 per share. So we have — there's a solid path ahead of us, and we're building that path on the strong cash flows we already have. That's really the story of this business. We have profitable operations, both through the joint venture and privately owned, 100% owned. We completed a successful capital raise, which positions us for the next 2 years at the Bathurst level to work through consenting for both Tenas and the Buller project. We hold solid cash reserves inside the joint venture. As a result, the joint venture is fully funded for any development work, including haul roads and the mine developments across an area between the Denniston and the Stockton plateau. We have access to the fast track. Once again, we have a listed project with the Buller project.

Richard Tacon

executive
#16

There's also the Rotowaro extension. That extension, honestly, depends on customer backing. The environmental work underpinning it is complete. At this point we're just aiming to lock in the hub via some local environmental assessment work, so we can move that project ahead if we manage to get an MOU, or at least greater certainty that the customer base will actually want that coal. The Fast Track Bill has been passed, and beyond that, metallurgical coal has been included as a New Zealand critical mineral, since a big chunk of New Zealand's export story is gold and metallurgical coal — which hasn't appeared on many other critical minerals lists worldwide apart from Europe. And we're making progress on the environmental assessment work and the DFS for the Tenas project. So thank you very much for that very quick overview.

Richard Tacon

executive
#17

One item came up through the invitation list concerning the recent protest activity at Stockton. The first thing asked was what the financial impact had been. Roughly $0.5 million went toward extra trucking as well as security. The following question was whether revenue took a hit, and the answer is no. We found a way to truck around the area that was affected. And even at a small rate, the shipping plan won't be affected whatsoever. We're fully stocked, and at this point we're back to full 5-day logistics. Our next step is moving to 7-day logistics. Some of the resilience in that system has been used up. So by Christmas we want to have that resilience restored. The last question was whether more action is coming. According to these opponents, they will attempt to disrupt us further down the road, especially once the application is in. Our security is being strengthened. Security was already fairly significant, but this exercise taught us lessons, and we'll be working to try and ensure we don't see another repeat of this incident. But many thanks for that. Yes, I'm looking forward to updating you further as we enter the exciting next phase with the fast track application.

Richard Tacon

executive
#18

Appreciate it, and best of luck to you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Bathurst Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Bathurst Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Bathurst Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.