Boralex Inc. (BLX) Earnings Call Transcript & Summary

February 23, 2022

Toronto Stock Exchange CA Utilities Independent Power and Renewable Electricity Producers earnings 74 min

Earnings Call Speaker Segments

Operator

operator
#1

Good morning, everyone, and welcome to Boralex's conference call on financial results for the fourth quarter and year end 2021. Please be aware that this conference is being recorded. At this point, I'd like to hand the conference over to Mr. Stephane Milot, Senior Director of Investor Relations at Boralex. Please go ahead.

Stéphane Milot

executive
#2

Thank you, Operator. Good morning, everyone. Welcome to Boralex's conference call on fourth quarter results. Joining me today from our Montreal head office are Patrick Decostre, our President and Chief Executive Officer, Bruno Guilmette, our Vice President and Chief Financial Officer, and other members of our management and finance team. Decostre will start with remarks on market conditions and the quarter's highlights. After that, Mr. Guilmette will be — well, sorry — will continue with financial highlights and then will be available to answer your questions. As you know, during this call, we will discuss forward-looking and historical information. When talking about the future, there are a variety of risk factors that have been listed in our different filings with securities, regulators, which can materially change our estimated results. So these documents are available for consultation at sedar.com. In our webcast presentation document, the disclosed results are presented both on a consolidated and on a combined basis. Unless otherwise stated, all comments made in this presentation will refer to combined basis figures. Please note that combined is non-GAAP financial measures and do not have standardized meaning under IFRS. Accordingly combined may not be comparable to similarly named measures used by other companies.

Stéphane Milot

executive
#3

For further specifics, please refer to the non-IFRS and other financial measures section within the MD&A. The press release, the MD&A, the consolidated financial statement, and a copy of today's presentation are each available on the Boralex website at boralex.com in the Investor's section. Should you want a copy of these documents, you may reach out to me as well. Mr. Decostre will now begin with his comments. So please go ahead, Decostre.

Patrick Decostre

executive
#4

Yes, Stephane, thank you, and good morning to everyone. I'm happy to walk you through our fourth quarter results today. With the acquisition integrated, new wind and solar farms coming online, and the favorable impact of sharp market price increases in France, we closed the quarter with combined EBITDA of $163 million — up 5% from the fourth quarter of last year. Output came in below the fourth quarter of last year and also under what we had anticipated, because wind conditions were soft in France and Canada. Our development teams stayed very busy during the quarter, adding 137 megawatt of project to the pipeline and moving three projects totaling 41 megawatt forward into construction or the ready-to-build stage along our growth path. On market conditions, delays in approving certain portion of the build back better plan in the U.S. pushed back the announcement of results for the 800 megawatt of project we submitted with NYSERDA in September. We now expect those results in March for this bid. In Quebec, as announced, a 300 megawatt request for proposal for wind energy and a 480 megawatt RFP for renewable energy are planned for this year.

Patrick Decostre

executive
#5

The approval process for the Hydro-Québec transmission line running to New York City is likewise moving forward. As I noted earlier, that project, taken together with Quebec's green plan, ought to benefit the general expansion of renewable energy across Quebec over the next several years. Indeed, our Apuiat project of 200 megawatts stands as a solid indicator that wind power growth in Quebec has picked up again. Turning to France: we continue to feel very confident about renewable energy's development going forward. As I said previously, RTE, which operates France's transmission system, has just put out six distinct scenarios for the 2050 production mix, and every one of them looks highly favorable for renewables. The least aggressive scenario calls for solar output seven times greater than it is now, along with onshore wind output that is 2.5 times greater. The most ambitious one points to solar output 21 times what it is today and onshore wind output four times larger. France confronts serious problems tied to the aging of its nuclear fleet, and in particular the corrosion issues found recently in certain reactors, which have led to temporary shutdowns. Take, for the moment, the recent statement from the head of the French Nuclear Safety Authority — the Autorité de sûreté nucléaire, or ASN — concerning the insufficient margin available to cover contingencies, and the trouble the nuclear sector will face in meeting even RTE's least ambitious scenario of 50% nuclear and 50% renewable energy.

Patrick Decostre

executive
#6

The ASN Chairman further emphasized that margins must be preserved so we don't end up trading off security of supply against facility safety. Back in February 2022, President Macron expressed his hope of doubling the nation's renewable energy output by 2030, boosting solar production ten-fold, and also doubling onshore wind capacity by 2050. As you can see, the French market offers plenty of potential — but let's not lose sight of the fact that this market is not an easy one to develop, with strong barriers to entry, which gives an important competitive edge to an established player such as us. I'll now go over the main variances in our project portfolio. We added six wind projects and five solar projects in France to the preliminary phase, representing a total of 137 megawatts, plus 23 megawatts for wind project optimization. Projects in the pipeline keep progressing, with 124 megawatts moving to mid-stage and 101 megawatts moving to advanced stage. Altogether, we are now developing a portfolio of 3.2 gigawatts of wind and solar projects and 190 megawatts of storage projects. Let's now turn to the review of changes to the growth path.

Patrick Decostre

executive
#7

As I mentioned earlier, two wind projects and one solar project in France, totaling 41 megawatts, have moved into construction or reached the ready-to-build stage. We know of 647 megawatts in the growth path, 493 megawatts in the secured stage, and 154 megawatts in the under-construction or ready-to-build phase. We also have a three-megawatt storage project under construction in France. Altogether, adding the growth path to our existing production capacity gives a potential capacity of 3.1 gigawatts. To conclude, as you can see on Slide 12, we are continuing to execute our strategic plan and making solid progress across all four strategic orientations. I have discussed growth and diversification, but we also recently announced the signing of two corporate PPAs. A 20-year contract with METRO France and a three-year contract with L'Oréal in France. Market conditions are extremely favorable for corporate PPAs, and we keep seeing very strong interest from corporations. On the optimization side, I would like to point out that we began the repair work at our Mont de Bézard 2 project and optimized maintenance for wind operations totaling 161 megawatts in Canada. One final point from me.

Patrick Decostre

executive
#8

Earlier today, our 2021 CSR report was released. I encourage everyone to go through it, because you'll see that in 2021 we achieved very meaningful advances on CSR, and we have a clear roadmap going forward. I'd like to use this moment to express appreciation to Mihaela Stefanov, our CSR Director. Mihaela quickly assumed responsibility for the CSR strategy and got our whole organization engaged around CSR and ESG criteria. CSR has always been embedded in Boralex's DNA, but over the last year we have drastically picked up the pace of change and accountability. That wraps up my portion, and I'll now let Bruno walk you through the financial section in greater detail. We'll return afterward for the question period.

Bruno Guilmette

executive
#9

Thanks, Patrick. Morning, everyone. I'll begin by reviewing how we've done against our 2025 corporate objectives. Fourth-quarter capacity went up as we commissioned the La Grande Borne wind farm on December 1, 2021, the Peyrolles floating solar farm on December 14, and our solar farm <<inaudible>> on December 23, bringing total capacity to 2.5 gigawatt. EBITDA over our last 12 months kept rising, though AFFO dipped a little because wind volumes were lower for comparable assets. Our reinvestment ratio is at 48%, a bit under our 50% to 70% target, reflecting that decrease in AFFO I just mentioned. On our CSR strategy, we kept making solid headway across environment, society and governance. We finished assessing our carbon footprint and have set a 2025 target for CO2 avoided. We set up a working group to analyze and integrate TCFD recommendations, and we ran voluntary training sessions on the impacts and conclusions of COP26. We wrapped up our training on indigenous culture with strong participation — 96% in Canada and 93% for North America. Last, we finished the revised version of our procurement policy. Now let's look at our debt objective.

Bruno Guilmette

executive
#10

Relative to where we finished 2020, our ratio of corporate debt to total debt moved up a bit. We're continuing to work toward the goal of securing an investment grade rating, which would widen the range of financing choices available to us and give us more flexibility. Now I'll walk through the quarter's financial results, beginning with production. The fourth quarter proved difficult because of poor wind conditions in Canada and in France as well. Canadian wind output came in 11% below what we had anticipated and 10% below the same quarter a year earlier. In France, wind production landed 17% under our anticipated level and 14% under the same quarter last year. Taken together, total wind production for the quarter across Canada and France was 13% below anticipation and 12% below last year. Now turning to hydro. Our U.S. hydro assets delivered another strong quarter, with output 23% above anticipated production and 85% above the same quarter last year. That more than offset weakness in Canadian hydro, producing total hydro sector production that was 8% above anticipation and 20% above the same quarter a year ago. Lastly, solar production came in 11% under anticipation, reflecting minor delays in commissioning new solar plants in France as well as lower-than-expected output from our U.S.

Bruno Guilmette

executive
#11

Turning to solar assets. To sum up, quarterly output came in 12% below what we expected and 6% under the prior year. For the full year overall, production ran 6% short of expectations yet 7% above an earlier year, with gains driven by our U.S. hydro operations, U.S. solar acquisitions and Canadian wind acquisition. Fourth quarter revenues fell 6% versus last year, largely because of the drop coming from the wind and thermal segments. In the fourth quarter of 2021, operating income rose 8% to 82 million, and EBITDA reached 163 million against 155 million in the same quarter of 2020, a 5% increase. We produced 81 million of net cash flows related to operating activities, versus 59 million in the same quarter last year. Cash flows from operations totaled 116 million in the fourth quarter, a 15 million increase over the same quarter of the previous year. AFFO came to 58 million against 67 million. That decrease stems mainly from lower volumes for comparable assets in the wind power segment. Our financial position stays solid, with our net debt to total market capital ratio at 48% on December 31, 2021, compared to 41% on December 31, 2020.

Bruno Guilmette

executive
#12

To wrap up, fourth-quarter EBITDA came in above the prior-year quarter, driven by acquisitions, newly commissioned assets, higher electricity prices, and our optimization efforts. During 2021, we put money into our development resources and refreshed our corporate targets. The coming year, 2022, will focus on delivering against our four strategic orientations, and a good number of projects now in progress should come to fruition. Finally, our balance sheet is still strong, and we'll keep working to optimize our capital structure and boost our financial flexibility. Thanks for listening. We're ready to take your questions now.

Operator

operator
#13

Thanks. <<operator_script>> Our first question comes from Rupert Merer at National Bank. Go ahead with your question.

Rupert Merer

analyst
#14

Morning, everyone — good to have you here.

Patrick Decostre

executive
#15

Morning, Rupert — hello there.

Rupert Merer

analyst
#16

Could you shed a bit more light on the way the contracts in France are set up that made the realized power price higher this quarter? And can you also say how many of your contracts are arranged so that you can capture the upside from spot prices?

Patrick Decostre

executive
#17

Right, absolutely. In France during the quarter, market prices sat at roughly €200 per megawatt hour, and because several of our feed-in premium contracts are tied to elevated market prices, we end up paying money back to EDF whenever the price exceeds the strike price — which at €200 per megawatt hour is clearly what's happening. Our installed capacity is exactly 201 megawatts, and under this type of contract, once the total amount received from EDF since the contract began equals the total amount we've paid to EDF, we reach a sort of break-even point where we no longer need to keep reimbursing EDF. At that stage we get to take advantage of the high price and gain from expensive electricity. So that covers 201 megawatts, and it also applies to 125 megawatts of projects currently under construction.

Rupert Merer

analyst
#18

All right, then — projects that came in more recently than the newer ones carrying that contract.

Patrick Decostre

executive
#19

Right, exactly. There's a bit of CR 16, CR 17, and the CR that come out of RFP periods one through five in France. That adds up to 201 megawatts. Then, as I said, the under-construction project is 125, and 58 megawatts of that is CR 17, since you need to be careful and count the full capacity when it refers to RFP periods one to five — 867 megawatts. So put simply, within the under-construction projects, the sole one left out of this type of asymmetric contract for difference is <<inaudible>> megawatts, while every other project gets the benefit of disclose.

Rupert Merer

analyst
#20

Regarding upcoming government RFPs, do you expect they’ll use this same contract structure, and would that create a chance for you to earn better returns on bids down the road?

Patrick Decostre

executive
#21

No, regarding what lies ahead — the RFP from last November didn't have disclosure in it. So that's not something we're gaining from. What matters going forward comes down to two points. First, in Q4 there was that break-even point, that tipping point, where the cumulative amount received matches the cumulative amount paid. So you can run the numbers yourself for Q1, say — check today's price, the first month plus 23 days into February, work out where things land, and disclosure applies roughly from the first of January 4 for the contract. That's the first thing. The second thing is, looking ahead — I'll leave the math to you — but you can visit the European Energy Exchange, the exchange market for forward contracts in Europe, and see how the market is pricing the next quarter, then assess what that means for Boralex. And clearly there are interesting factors here, given our strong wind exposure in France — despite last quarter, seasonality works in our favor, because both production seasonality and price seasonality favor Boralex. And the second interesting point is that the significant interest in corporate PPAs, combined with the market price signal, creates opportunities we're digging into, or hunting for, to capitalize on these high European prices.

Rupert Merer

analyst
#22

If I could, that was going to be my next question—when it comes to those corporate PPAs, are you noticing inflation in the potential pricing on them, and in those cases should the corporate PPA be more attractive than the government PPA?

Bruno Guilmette

executive
#23

Yes. So obviously there’s interest when the market price sits at roughly €200. I’m not claiming it’s going to remain at that level, but my view is that we won’t see it drop back to something like €40 to €50 down the road, since the elevated price in Europe isn’t driven solely by the Russia situation and the gas price alone. It’s also the nuclear fleet issue I just referred to. EDF’s output has fallen from an average of 400 Terawatt-hour per year to 300 Terawatt-hour this year and next year. EDF has already made that public. So that places substantial strain on the overall system. Germany shut 4 gigawatt on the December 31, and will shut another 4 gigawatt of nuclear on the next December 31. So all of that pressure, together with the CO2 price, is creating a situation where — in which companies aren’t only pursuing corporate PPA for ESG and marketing as they did before, but they want it in order to lock in their electricity price over the long term. And that gives us a great deal of optionality.

Rupert Merer

analyst
#24

Perfect. Appreciate the context. That's all from me.

Patrick Decostre

executive
#25

Perhaps just one remark for Robert, to make sure you’ve modeled it correctly—the effect on the contracts is that you’ve accounted for seasonality, meaning Q1 and Q4 tend to be stronger, which means more production and higher prices, while for Q2 and Q3 you need to model lower prices going forward. If you look at this, it’s simply the seasonality of the business that makes it function that way. You’ll see that regardless, if you look at the forward prices or forward contracts.

Rupert Merer

analyst
#26

That’s excellent—thanks so much.

Patrick Decostre

executive
#27

Appreciate it.

Operator

operator
#28

Our following set of questions comes from David Quezada at Raymond James — go ahead and ask.

David Quezada

analyst
#29

Thanks. Hello everybody. For my first question, it's about wind speeds — is there anything you can share on that? What I mean is, it seems as though conditions in France have improved during this period so far. Could you speak to your entire fleet and tell us if wind speeds have recovered in some way, or how they've come in versus what was expected for 1Q?

Stéphane Milot

executive
#30

Bruno's question concerned wind speed in Q1. At this point it appears to be relative to Q4.

Bruno Guilmette

executive
#31

Hi, David. So, as you're aware, when it comes to these wind forecasts, we rely on our long-term averages, and commenting on wind forecasts over a shorter-term horizon isn't really something we like to do. So, I suppose, as we've mentioned before, hopefully there's some data out there that you can look at, but we don't provide our forecast on a quarterly basis or before the quarter has ended.

David Quezada

analyst
#32

All right, got it, and thanks for that. Perhaps just one more from my side. I'm curious whether you have any views on the French election that's coming up — from what I can tell, the results look quite favorable in practically every scenario. The current platform is strongly behind renewables; do you anticipate any shifts that could emerge from the election, depending on how it plays out?

Patrick Decostre

executive
#33

The short answer is no across the board, though with elections you can never be certain, particularly since 2016. So I won't make any prediction about the outcome, but one thing does appear evident: should President Macron win a second term, he will proceed, since the industry's circumstances dictate it rather than politics. Owing to its aging fleet, France must refurbish facilities somewhere and add further nuclear capacity. France also requires a great deal of renewable energy. And under any scenario, when you consult specialists such as RTE — which operates independently of politics — they examine scenarios, as I noted, featuring strong potential for solar, wind, and offshore wind, and President Macron has affirmed this. That, then, is what I expect to happen, and I am confident it also fits the European framework, in which France has made commitments for 2030 and 2035. This will carry on. The European — I can't recall the name, but it's the 55% cut in CO2 relative to 1990, the 2030 target, and that stands as a French commitment.

David Quezada

analyst
#34

That’s really helpful context. Thanks a lot, Patrick.

Patrick Decostre

executive
#35

And maybe one more thing — I know there's been some chatter in the market regarding nuclear — the fact that nuclear has been classified alongside highly efficient natural gas in the European taxonomy as a transition energy rather than green energy. That matters, but at the same time there are plenty of difficulties facing the nuclear fleet, difficulties when it comes to cost and delay. If someone decided in September to actually place an order for a new nuclear plant, it would probably come online in 2035, assuming all goes well, and I wouldn't wager a penny on the cost and the budget. So that's one point. There will also be difficulties bringing HR into this business — lots of engineers, lots of specialized technicians such as welders. And so, I think, for us it isn't a problem. And if you look at natural gas, it's a specific case for Germany, because the Germans want to shut their coal down by 2030 rather than 2038 during the Merkel period. But to accomplish that, they require natural gas and they require highly efficient natural gas, and at some point they'll have to convert their new plants from gas to high nitrogen, and it ought to be green nitrogen.

Patrick Decostre

executive
#36

All of that taken together means there’s a great deal of opportunity for renewable energy across Europe.

David Quezada

analyst
#37

Great, and thanks once more for that, Patrick.

Operator

operator
#38

Our following question arrives from Nick Boychuk of Cormark Securities. Go ahead with your question.

Nicholas Boychuk

analyst
#39

Morning, gentlemen, and thanks for taking my question. I was hoping you could give us a bit more detail on bringing the service and maintenance work for the Quebec wind assets back in-house.

Patrick Decostre

executive
#40

Apologies, Nick — I’m not certain I follow. We do get what you’re asking; would you mind saying it again?

Nicholas Boychuk

analyst
#41

Sure. It was interesting to observe that you have brought the service and maintenance contracts back in-house at a few Quebec wind facilities — I believe that was roughly 160 megawatts. I'm curious whether you could share a bit more detail about what drove that choice, how it could affect costs and margins, and whether other comparable assets exist where you might make a similar switch?

Patrick Decostre

executive
#42

Yes — yes, absolutely, Nick. It really comes down to the optimization focus within our strategic plan. Back in 2019 we began this in Quebec with Le Plateau 2020, and then at the close of 2020 for Seigneurie de Beaupré, and things are going very well. So wherever possible we keep advancing that plan with Enercon under the agreement we hold with them. We're nearly out of that contract, and we're taking over their service, and that's going really well. Costs are coming down and energy availability is going up, since we're more flexible. We have staff at the site whose incentives are tied to production rather than simply time-based availability. And over recent months I've been very pleased, because the Enercon contract carries a lot of inflation, much like any O&M contract. We're somewhat shielded from that — not entirely, but we are protected against certain indexes, say the German industry index, which is climbing by 20 — around 20%, which is high. But because the cost sits lower on our side and is internal, that also gives us protection against inflation.

Patrick Decostre

executive
#43

Things are progressing nicely, and on this front we're actually ahead of the budget. That's part of why global EBITDA isn't tracking the top line precisely, and there's also some cost optimization at play.

Nicholas Boychuk

analyst
#44

Okay, that’s helpful context. Thanks. Regarding development costs, could you give us a bit more detail on whether you’re encountering higher costs when partnering, acquiring, or sourcing even early-stage development opportunities? Some industry participants have mentioned or suggested that valuations and costs at that earliest stage are rising. Are you seeing any of that?

Patrick Decostre

executive
#45

Yes, this is obviously a market trend, since investors — more strategic ones — are taking on more risk with early-stage pipeline. That's why we need to put a lot into our own people. And as you've seen, we're currently developing 3.1 gigawatt, which is genuinely higher than it was if you look back three years ago — back then it was less. And we're watching closely to make sure that each quarter we're adding a new, real project, not just IDs, and that we have the right people on the ground to build the project. We've also really grown the size of the greenfield development team in the U.S. — I don't think I mentioned that three months ago — but we have begun real development negotiations with landowners and are applying for grid connection in two other new states, outside the state of New York, when we will reach some milestone that will, I would say where, where it is, but it's a similar place. So we are genuinely investing in order to avoid having to pay the premium on the project when you have to buy it from local, small developers.

Nicholas Boychuk

analyst
#46

All right, understood, that's clear. Then my final question, regarding that organic growth engine, I'd like to ask whether you could provide a bit more detail about how projects are progressing through the pipeline phases. Clearly, one project this quarter moved through what I believe are the usual stages quite rapidly. I'm simply asking whether you could update us on how long it takes for these projects to reach operation, and whether there are additional projects we haven't yet heard about that might reach that construction-to-build base somewhat soon.

Patrick Decostre

executive
#47

Yeah, so basically, on the pipeline side, we’re waiting on a couple of key things. The first one is the outcome of the NYSERDA 2021 tender. Like I said, we expect that in March, so that could be a meaningful piece. And the second piece is — as I also mentioned — we’re getting ourselves ready for the RFP in Quebec. The government made it clear that after the 300 and the 418 megawatts RFP for 2022, more tenders will come down the road, because Quebec will need about a 12% rise in electricity demand — that’s 20 terawatt hours, which is a big deal for Quebec. And they’ve revisited their 2019 target. In November, from the 29 — no, sorry, they revisited the 2029 target versus what they had two years back, and they raised it by 6.5 terawatt hours because of biofuel demand, hydrogen demand, the battery factories, data centers, blockchain, and all the new demand in Quebec. So that gives us an environment where, in our view, there will be additional RFPs. So that planning is separate from us, but we believe this will be an important development in the pipeline.

Patrick Decostre

executive
#48

And in France, it's more a matter of — as you can see, I think each quarter we're announcing one or two projects that are heading in the right direction.

Nicholas Boychuk

analyst
#49

Alright, Patrick — that's really helpful context. Thanks a lot.

Patrick Decostre

executive
#50

I appreciate that.

Operator

operator
#51

Our following question comes from Sean Steuart at TD Securities. Go ahead with your question.

Sean Steuart

analyst
#52

Thanks, and good morning to all of you. Patrick, I'd like to ask a follow-up question about the New York RFP. My understanding of what you indicated is that the hold-ups in the build back better legislation are acting as a gating factor for pushing that forward. You're still saying you expect to have results by the close of the first quarter. How do you square those two things if we have no visibility into the legislation advancing? Can we still feel confident about that timeframe?

Patrick Decostre

executive
#53

Yes. That is a fair question. First, on timing: the announcement was shifted and then communicated to the bidders in December because both the administration and the government felt hopeful about build back better. And you don’t necessarily get the favorable effect, and some would call it a windfall profit, arising from that. So then where does build back better stand? The situation as of today is that we anticipate the State of the Union Speech next week, on the 1st of March, will shed some light on this; clearly, the U.S. Administration is more focused on Eastern Europe right now. So that remains the latest information I have from the team — that we are waiting for something in March, but it could shift; the situation today is that the U.S. administration is what it is. And that is how we can square the planning.

Bruno Guilmette

executive
#54

To add to Patrick's comments, the connection we're drawing comes from what Patrick mentioned regarding Build Back Better and the bids — Nicer could choose to separate those. What I mean is, they might determine that if Build Back Better gets pushed back even more, they would still announce the results, or again, split the two elements.

Patrick Decostre

executive
#55

Yeah. And regarding politics, the question about build back better dealt more with the social side and certain elements that don’t involve support for renewable energy. So as we understand it, they’ll also divide build back better into separate pieces of legislation, moving forward with the portion that’s accepted broadly by the public and by the political world, and hold off to negotiate the other portion, which was the difficulty in December.

Sean Steuart

analyst
#56

Appreciate the detail there. For my second question, I want to ask about the French organic development portfolio. You said every RTE scenario is moving more in the direction of solar growth—or at least quicker solar growth—and wind across all scenarios. I'm just wondering whether you could give us a sense of this: for the projects sitting in your early-to-mid-stage solar pipeline in France, is there a bias toward advancing those more quickly than the wind projects, or are you agnostic and confident in the overall portfolio you have there?

Patrick Decostre

executive
#57

No, and as you've likely observed, we've begun shifting—not fully to solar, but toward boosting our development spending and concentrating on solar development in France, which started before June of last year, ahead of the new strategic plan. So we've brought on various new people. Solar presents a distinct challenge in France. With wind, the difficulty is chiefly social acceptability along with managing visible and landscape effects and biodiversity impacts. That's what's hard about wind. For solar, the difficulty is more about gaining access to land. So different personnel are needed, and they should be devoted to this development effort. We're therefore investing to speed up this segment, and broadly speaking, developing a solar project in France takes less time than developing a wind project. So that's what we're working on. Just to remind you, yes, if you consider, for instance, President Macron's February 9 speech in Belfort at the GE facility, he said—well, he didn't phrase it this way, but ultimately he lowered the onshore wind target from 50 to 40 gigawatt, yet that still means onshore wind in France is doubling, and he sharply raised the solar portion from 50 to 100 gigawatt, which is a positive signal.

Patrick Decostre

executive
#58

And that's something we've planned for, both in our strategy and within our team.

Bruno Guilmette

executive
#59

And actually, Patrick, that's also true of what we saw in the latest request for proposals: the offer still can't satisfy demand for onshore wind. So that remains the case. Land in France is still scarce, and that's going to stay that way. That's why we feel very good about our pipeline, and we plan to keep growing it and moving it forward into construction phases.

Sean Steuart

analyst
#60

Thanks — that's really helpful context, and I appreciate the thoroughness.

Patrick Decostre

executive
#61

I appreciate that.

Operator

operator
#62

Our next set of questions comes from Andrew Kuske at Credit Suisse. Go ahead with your question.

Andrew Kuske

analyst
#63

Thanks. Morning, everyone. So my first questions are really for Patrick, and they center on what it takes to reach critical mass in a market. When you're entering a new market area and working to build it out, what level of resourcing do you figure is required there for it to genuinely gain traction, to truly begin developing assets, and to earn credibility with corporate buyers, local utilities, and really off-take in general.

Patrick Decostre

executive
#64

Yes. That's a fair question. But there are separate pieces to it. To launch a genuine Greenfield development, five people over three years is a solid beginning. If you start — when we started New York, we didn't assign more than five people. When we — we're beginning in another state, as I said, it's no more than that. In the UK, we've begun via a partnership, and we will certainly speed that up given the pricing environment I mentioned. So we are — but the developer's team is about 10 people doing the developing. So that's for Greenfield development for — to build credibility, that's a separate situation. To — first to gain the ability to have a team and some operations, I think we have an organization today. I clearly saw the difference in France between 200 and 300 megawatt when you're in that position, you can have specialist land people, but I was on my own in France at that time. And but typically if we wish to go into Spain or the UK, it will be the French team providing the service, like we do in the U.S. out of Ontario and Quebec.

Patrick Decostre

executive
#65

That’s likely still acceptable. Then building the brand in the market is a separate matter. In Quebec we have a clear brand. In France we have a clear brand. In New York — I think in Greenfield we have a good brand, but we need to keep developing our branding and reputation in order to sign corporate TPO or to sign a contract if needed. So these are different stages.

Andrew Kuske

analyst
#66

All right, that's really useful color and context, and with everything you have going on, you've gotten quite disciplined about it. So maybe I could direct the question to Bruno, just on securing that investment grade credit rating, and on how you view the gating items on the balance sheet, given that you have a fairly large opportunity set. And does that investment grade credit rating strengthen your credibility in the market and your capacity to develop on a more accelerated basis going forward?

Bruno Guilmette

executive
#67

Thanks for asking that. For sure, we see it as a significant milestone that we need to hit, and we're putting things in place so we can get there as fast as possible. As I believe I mentioned earlier, the goal here is also to strike a balance between flexibility on the corporate debt side and long-term non-recourse debt tied to projects. So hitting that balance matters to us — achieving that flexibility and arranging things so we actually arrive there. We have to keep refining the various financing sources we use, and we think we're getting close, though there's still work ahead before we arrive — for instance, with regard to some of our project depth, what that will mean going forward is that we'll probably dial it back somewhat on particular projects while making certain we bring in more corporate inflows. There are additional steps we need to take as well in order to optimize our corporate debt the way it's currently structured. So those are milestones we're watching, including in terms of securing cash flows from future assets now under construction, like the pipeline you brought up. That's where we've discussed the extra revenues coming our way in Europe, for instance.

Bruno Guilmette

executive
#68

I'd say when you put all of those pieces together, it points to a solid setup for us in the near term to reach that outcome.

Andrew Kuske

analyst
#69

All right, that’s excellent. Thanks so much.

Operator

operator
#70

Our next questions come from Ben Pham, a private investor, on the line. Please go ahead with your question.

Ben Pham

analyst
#71

Hello, thank you. This is Ben calling in from BMO Capital Markets. I have a couple of questions regarding France — is there any news on the possible paper recycling?

Patrick Decostre

executive
#72

Yes. As we've said previously, we're moving through a structured process aimed at securing a partnership with an investor in France for our French operations, covering both assets and the pipeline. That process is quite far along, and we're pleased to see strong interest in this partnership with Boralex in France. So we'll return with more details in due course, but this process is clearly showing the interest that our French operations have drawn from private investors.

Ben Pham

analyst
#73

Okay. So from those discussions with the prospective investors, has anything else come up — maybe additional opportunities coming in that could let you recycle other pieces of your portfolio?

Bruno Guilmette

executive
#74

Sure, and really from the very beginning our strategy has been to create value through developing our assets and developing our teams. We're taking a similar approach — as Patrick mentioned — in the U.S. We think that's a solid way for Boralex to create value. Obviously we're also creating value through our operations and so forth. But it comes down to sequencing. It comes down to how mature the assets and the markets are. So for us, the French market and our operations there were at the right moment and the right stage for us to enter that partnership. We think we can generate additional value by waiting a bit in certain other regions, for instance. But clearly, we have partnered before, this is — the process is going well and we expect more partnerships going forward.

Ben Pham

analyst
#75

All right, thanks. Turning to France, I had another question. With EDF these days, how are you weighing counterparty risk — given the share price and the financial implications? Does that shift how you approach where capital gets allocated and France going forward? And do they have any influence over future RFPs in France, or is that entirely government driven?

Patrick Decostre

executive
#76

Yes, Ben, that's a key point — EDF isn't operating in its capacity as a corporation; when it serves as Boralex's offtaker, it's functioning as an instrument of the French government. In other words, the offtaker here is the French state. That role belongs to EDF chiefly owing to its public service obligation dating back to, I believe, 1999 — is that right? Yes, 1999, lower something along those lines. So quite some time has passed since the French market was liberalized, and EDF enjoys certain advantages as a public service entity and carries certain obligations as one whenever it genuinely acts as the state's instrument. That's precisely how the other banks view the matter. And if you'd like, I can add a penny on that, because the situation is that following the election, the so-called project — a possible split of EDF into the public service portion and the nuclear portion on one side, and on the other side the hydro, the renewable, the service, and I don't know where the grid will land — will keep moving forward. So it's something that will make it possible for the French government to finance new nuclear, and on the other side, and pay for it, and the part of — EDF's role would be clearly defined, and under the law we are protected.

Patrick Decostre

executive
#77

There's no exposure on that front.

Ben Pham

analyst
#78

Alright, that's a helpful reminder. OK. Thanks to all of you.

Patrick Decostre

executive
#79

I appreciate it.

Operator

operator
#80

Our next set of questions comes from Naji Baydoun at IA Capital Markets. Go ahead with your question.

Naji Baydoun

analyst
#81

Hello there, and good morning. I just had a question regarding your strategy in the U.S. It has now been more than a year since that portfolio of solar assets came under your umbrella. Could you perhaps share a little additional detail about what comes next for Boralex and the markets in which you picked up those assets? Also, are there any lessons from the corporate PPA advances you achieved in France that could be brought over to the U.S.?

Patrick Decostre

executive
#82

Yes. Regarding our U.S. approach, we keep advancing a greenfield project in New York State, since we're aware that an annual RFP typically happens over the summer — one, I believe, is set for August. As I said, we're pursuing the same in two additional states, where large-scale development and participation in a public RFP are also possible. On the existing contract — the 2019 contract — we're working hard to align the plants and finalize development on one front, meaning the grid connection plus all the permits needed to build, and also to align the plants in terms of return, factoring in the new costs and the new financing situation, and hopefully as well the Build Back Better direct pay situation and similar items. So everything has to be factored in, and then we take a final investment decision on this project. And last but not least, we're examining some disciplined M&A in the U.S. to speed up our penetration of the American market and/or to diversify into solar as well.

Naji Baydoun

analyst
#83

All right, that's excellent. So it seems like perhaps FID this year on the projects already in place, and then looking into a couple of additional states beyond New York. My follow-up question concerns M&A. Do you sense any pressure to pursue acquisitions in order to meet your 2025 capacity targets, and more broadly speaking, would that require a corporate debt raise, or would you rather wait at least until the minority stake in France is settled before committing to an acquisition?

Bruno Guilmette

executive
#84

You brought up the word pressure, so let me address that directly. To begin with, there isn’t any pressure — we have a strategy in place to reach our numbers. We have a strategy, a plan, and a timeline for getting there, though with M&A in particular, timing is somewhat hard to predict. As Patrick said, M&A forms part of that strategy. So it isn’t the case that we do no M&A — we are able to generate value through M&A. But of course, we cannot forecast when those M&A opportunities will arise; they have to meet our criteria, our return criteria, et cetera, and they must align with our strategy. So these are assets through which we can generate value, where our teams and our skill sets let us add value — it’s about pipeline, and it could involve teams or partnerships with other teams that are present in, say, certain regions, or, as Patrick mentioned, greater diversification in that solar. So this really comes down to a strategy. So, I mean, it will happen when it happens. And if we get through our process on the French process, then we’ll have some money available for that. And if not, there are other sources of financing we can tap, depending on how large the transaction is. Financing, as I said in my presentation, is not really a problem for us at Boralex in this instance — we have, we are also well funded for a plan.

Naji Baydoun

analyst
#85

All right, thank you. Appreciate it, Bruno. This is my final quick question. When I look at your development pipeline, there are roughly 60 megawatts of advanced-stage projects in Canada, plus another 500 megawatts at mid-stage. Would you say that's essentially the majority of the projects you might potentially bid into the upcoming RFP in Quebec?

Patrick Decostre

executive
#86

Yeah, that's the project we're building to meet Quebec's needs — as I said, 20 terawatt-hours to come online over the next seven years. So this RFP could turn out to be a different one, or it might be another opportunity we're pursuing. Still, we're quite confident we've got the right land access and solid interconnection access on some of these projects, and that gives us a competitive edge.

Naji Baydoun

analyst
#87

All right, I appreciate the specifics.

Patrick Decostre

executive
#88

It's a pleasure, and thanks to everyone.

Operator

operator
#89

Our following set of questions comes from Mark Jarvi at CIBC Capital Markets. Go ahead with your question.

Mark Jarvi

analyst
#90

Thanks. Good morning, everyone. I just wanted to return to the higher spot prices in France and clear up a couple of points. First, it wasn't clear whether there was some element of merchant exposure, or whether all of it, or the vast majority, came from the contract for differences?

Patrick Decostre

executive
#91

No, it does — the key point is that our merchant exposure is quite limited. I believe it's 8 megawatts from the first Avignonet site that we retained in this arrangement, and there are some others as well; in one of our corporate PPA contracts we also have potential merchant exposure, though we likewise have the option to lock in the price — to set it — whenever that works in our favor. So that's the only genuinely pure merchant exposure we carry. Regarding the contract, I mentioned 201 megawatts — you need to refer to this slide — there's a floor price; the strike price is effectively a floor. And once reimbursement has happened, we have — sorry, not you — we have repaid EDF the same amount that we received from EDF starting on day one of the contract. So the floor price truly functions as a floor, and there is no longer a set price; instead we gain the benefit of the market price at that moment. So it isn't pure merchant exposure — it's an asymmetric merchant exposure, a sort of floor.

Bruno Guilmette

executive
#92

One more thing on that, Mark — I just wanted to add it, and we've never really discussed it, since we weren't in this sort of pricing environment, but the odds of capturing that upside were pretty low. Now, however, given the kind of pricing environment we're in, this class for the 201 megawatt contracts that Patrick mentioned applies. So this is genuinely something quite new, driven by the pricing environment.

Patrick Decostre

executive
#93

Once that subsidy has been paid back to you, the upside is basically yours.

Mark Jarvi

analyst
#94

Understood. So on that cumulative basis, and reaching that breakeven point—does the prior underperformance, such as the weak results for existing assets over the last 2 years, come into play? I suppose what I'm asking is whether the upside on the existing assets matches the upside on newly commissioned assets, or whether there's somewhat of a gap between the two.

Patrick Decostre

executive
#95

The upside—does it apply to the first asset? On CR16 we have 87 megawatts, 33 on CR17, and 81 across one through five of the request-for-proposal CR contract. So CR16—we began placing that kind of asset into service in 2019, I believe, since in 2018, maybe some—one went in during 2018, I think—so it isn't an old asset, and on those assets, through the period up to Q3 2021, we received money from EDF. So that asset must recover all the money they got from EDF, with a market price of, say, between €45 and €50 and a strike price that, for CR16 roughly, was €82 per megawatt hour, or roughly €82. So you see the gap, and in my example it's €30. Then during the quarter, the price rose to €200 per megawatt hour. So the gap is no longer €30—the gap is €120. So with the same output it takes four times less to get back to breakeven. You follow my example. And on a new asset—on a new asset, the one we'll commission in the coming months under the good contract I mentioned is 125 megawatts; since we have not—we will not get any money from EDF from day one, we will enjoy and benefit from the market price from day one.

Mark Jarvi

analyst
#96

Understood. All right. So returning to that point about moving projects into the construction-ready, build-ready stage — you mentioned possible success with the RFPs, but what about the projects sitting in your secured pipeline? For instance, this quarter you moved some secured items into build-ready. Is there anything that, given certain final permits or authorizations, could shift into that phase and be set for construction, and then commissioning in 2023? Or is everything else in that secured pipeline somewhat longer-dated?

Patrick Decostre

executive
#97

Regarding the secured stage, how many projects do you estimate there are, and what is the timeline for those secured-stage projects — is that right?

Mark Jarvi

analyst
#98

That's right, precisely.

Patrick Decostre

executive
#99

Alright. So for the secured-stage project, basically we're only including the portion of the project that aligns with our 2025 target. For instance, Apuiat is a project running from 2024 to 2025. If you look at the older solar project in the U.S., it's entirely projects that are either 2023 and perhaps 2024 for green corners. And there's no cliff date on this project — that's also important. As for the French project, I don't have the details memorized. It essentially depends on the French project that falls within this portion; it hinges on final authorization or clearing challenges from third parties, and on one or two of these projects like <<inaudible>>. And last but not least, speaking of Limekiln in Scotland, we're currently at the late stage of authorization for expanding the project in terms of turbine count and also increasing turbine size. This is something every single developer in Scotland has to go through. So we're in that process, and as soon as we have a fully permitted project, we'll really begin marketing for corporate PPAs. And in the current environment, I think we'll be able to — I'm confident we'll be able to find enough data for this project.

Patrick Decostre

executive
#100

Following that, we're looking at a contraction period lasting two years.

Mark Jarvi

analyst
#101

Alright. Maybe one last thing for Bruno, specifically regarding what your France wind operations cost. My understanding is those are lower versus a year ago when measured in euros on a constant currency basis. Is that a one-time item, or is it simply the advantage from the Vestas contract you signed a couple of quarters back?

Bruno Guilmette

executive
#102

I'd say this is really a broad strategy for us — a broad way we go about trying to get our costs as efficient as possible. So Vestas is one of those, one of the reasons behind it, but for sure we're going through the whole process on the operations side and on administrative costs. So that's partly — it's a piece of our optimization strategy there. And also, Mark, we did quite a bit of optimization in Canada as well, with our wind assets.

Mark Jarvi

analyst
#103

Absolutely. That’s great. All right, thank you all.

Patrick Decostre

executive
#104

I appreciate that.

Stéphane Milot

executive
#105

All right, then — is there one final question left, or, okay.

Operator

operator
#106

Yes. Our final question comes from Matt Taylor at Tudor, Pickering. Go ahead.

Matt Taylor

analyst
#107

Yeah, thanks guys, and sorry — squeaking in right at the last minute here, stepped on. Just wanted to circle back to the potential. Hey, how are you doing, guys? I just wanted to return to the sale — I understand it's still ongoing — but I'm wondering about funding, and I think it'd be helpful to refresh our memory on funding needs. Because looking at your disclosure, you've got roughly $287 million of capital invest that you'd still need to put in on what's under construction. And then if 20% of that is only about 60 million bucks, it looks like relatively modest needs just for what's in the project under construction. But if you could just refresh your view on whether or not this sale is looking to cash up and fund those needs, plus the other projects that Patrick was walking through there and the secured growth — or do you have other plans for the proceeds?

Bruno Guilmette

executive
#108

Okay, so the proceeds would obviously be allocated somewhere; I think it's all connected, right? We brought up the investment grade rating. We discussed various topics today, including organic growth and M&A. So those proceeds would probably be used for some debt rebalancing involving some debt that's more costly, which we could pay down. And of course, we anticipate having funds left over for growth, whether that means financing the pipeline. Previously, I've mentioned that we're covered until late — 2022 for funding. So that serves as a starting point. And if we receive the extra money, or once we do get it, then yes, we can direct it toward what I've just described.

Matt Taylor

analyst
#109

Alright, that's great. Yeah, the approach really is a blend of all those things, and that's one way to look at it. Correct. Some of it is organic — what's already reflected in the price — and possibly a bit of M&A as well?

Bruno Guilmette

executive
#110

Yeah, and that would obviously help us cut down on how much equity issuance we need.

Matt Taylor

analyst
#111

Great, and I really appreciate you giving me the chance to ask something.

Bruno Guilmette

executive
#112

I appreciate that.

Patrick Decostre

executive
#113

I appreciate it.

Operator

operator
#114

That brings us to the end of the Q&A, so I'll return the conference to you for any closing remarks.

Stéphane Milot

executive
#115

Okay, thanks very much. And thank you all for tuning in. I believe this has been our longest call ever, running an hour and 15 minutes, so we really appreciate the quality questions and the interest shown in Boralex. If anything else comes to mind, just give me a call. The number is unchanged: 514-213-1045. I'll make sure we get back to you quickly with answers. Our next call, where we'll report first quarter results, is set for Wednesday, May 11. I hope everyone stays healthy. Have a great rest of your day, and enjoy the spring vacations coming up as much as we plan to. Thank you.

Patrick Decostre

executive
#116

Thanks to all of you.

Operator

operator
#117

Everyone, that brings today’s conference to an end. We appreciate your participation. You can go ahead and disconnect your lines now. Thanks.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Boralex Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Boralex Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Boralex Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.