Cameco Corporation (CCO) Earnings Call Transcript & Summary
February 8, 2024
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone being on the line. I'm the conference operator, and I'd like to welcome you to Cameco Corporation's Q4 2023 Results Conference Call. Please note that everyone attending is in listen-only mode and that this call is being recorded. Once the introductory remarks are finished, there will be a chance for you to ask questions. If you'd like to enter the questioning queue, press Star followed by one on your phone's keypad. If you require help at any point during this call, you can alert an operator by pressing Star and zero. Those of you joining via webcast, please hold your questions until the Q&A session, since what you're seeking may be covered during the presentation. The Q&A session will wrap up at 9:00 A.M. Eastern Time. At this point, I'll hand the conference over to Rachelle Girard, Vice President, Investor Relations. Please go ahead.
Rachelle Girard
executiveThanks, operator, and good morning to all of you. I'd like to welcome everyone to Cameco's Q4 conference call. I want to begin by acknowledging that we're joining from our corporate office, situated on Treaty Six territory — the traditional territory of Cree peoples and the homeland of the Métis. Joining us on the line today are Tim Gitzel, our President and CEO; Grant Isaac, our Executive VP and CFO; Heidi Shockey, Senior VP and Deputy CFO; Brian Reilly, Senior VP and Chief Operating Officer; Sean Quinn, Senior VP, Chief Legal Officer, and Corporate Secretary; Alice Wong, Senior VP and Chief Corporate Officer; and Dominic Kieran, Global Managing Director of Cameco UK Limited. In just a moment, I'll turn things over to Tim, who will talk briefly about the current environment in the nuclear market, how we performed in 2023, and the way that performance underpins Cameco's plans and outlook for 2024. Following that, we'll open the lines for your questions. Today's call should run roughly one hour, wrapping up at 9:00 A.M. Eastern Time. As always, we aim to communicate openly and transparently. That said, we do want to respect everyone's time and finish the call on schedule. So if we don't get to your questions during the call, or if you have detailed questions regarding our quarterly financial results, we'll be glad to follow up with you once the call is done.
Rachelle Girard
executiveIf you have further questions, there are several ways to get in touch with us. You could contact the people listed in our news release, send a question via the Contact tab on our website, or fill out the Ask a Question form located at the bottom of the webcast screen — and we'll gladly follow up once this call concludes. Should you have joined the conference call via our website event page, slides are available that will be shown during the call. Also, for your reference, a PDF of our quarterly investor handout can be downloaded from our website at cameco.com. All members of the investment community, including the media, are welcome on today's conference call. When the Q&A session begins, kindly keep to two questions and then rejoin the queue. Be advised that forward-looking information will be included in this conference call, which rests on a number of assumptions, and actual results could differ materially. Undue reliance should not be placed on forward-looking statements. These forward-looking statements may differ materially from actual results, and no obligation is undertaken by us to update any forward-looking statements made today, except as required by law. For further detail on the factors that could cause these differing results and the assumptions we have made, please refer to our most recent annual information form and MD&A.
Rachelle Girard
executiveHaving said that, I'll now hand things over to Tim.
Tim Gitzel
executiveWell, thank you, Rachelle, and good morning to all of you. We're grateful you could join us on today's call, and a belated Happy New Year to everyone. Our fourth-quarter conference calls always give us a great chance to talk over how the uranium and nuclear fuel markets developed over the past year. It's also a good moment to mention a few annual highlights showing how strongly our strategy is working and to share some thoughts on what we currently expect for the year ahead. That's the outline I'll be following today. Over this past year, we've spoken consistently about the positive momentum in the market, so I think I can keep that part fairly brief. We devoted a great deal of time on our calls, in our presentations, and on our webcasts to expressing our optimism and our positive view of the constructive market conditions we've witnessed throughout 2023, and we are absolutely carrying that enthusiasm forward into 2024. Those of you listening today who tuned in for a few of our calls and presentations before 2020 would be very familiar with the phrase, positive long-term fundamentals. I say somewhat tongue in cheek that we relied on that message more than just a few times to reinforce our optimism through the lowest points of the market cycle.
Tim Gitzel
executiveWhen we first issued that statement, the timing of a market turnaround was obviously beyond anything we could predict, yet our conviction held that the industry would bounce back once the surplus, uncommitted primary supply and mobile inventories had been absorbed by the market and demand kept expanding—and that our company would emerge stronger than it had ever been. So today, with the uranium contracting cycle moving nearer to a replacement rate level, I can state confidently that we are in the early portion of that long-term window we have long discussed. And the fundamentals we pointed to are actually more favorable than we had expected. On the demand front, we invoke the word durable at every chance, since we think it precisely captures and clearly sets apart the fundamental demand picture of today from earlier cycles. Historically, the peaks in our market have generally persisted for weeks, whereas the valleys have persisted for years... That is what happened when enthusiasm for uranium and nuclear came from one or two isolated events: a mine shaft failure, the conclusion of the Megatons to Megawatts program, a flooded mine under development, Chinese contracting that took up substantial supply. Every one of those kinds of events introduced speculative, shorter-term, fleeting pressure on supply and demand.
Tim Gitzel
executiveBut in the current climate, the uranium market is definitely doing more than simply having a moment. What we're witnessing instead is growth across the full cycle—near, mid, and long term—with interest in nuclear energy at a breadth we've never seen. And the forces behind it are global in scale and are widely anticipated to last for many years ahead. Geopolitical friction is pushing governments worldwide to rethink energy security and put policies in place that lower risk and end dependence on unstable jurisdictions. While doing that, they're keeping climate change and electron accountability front and center, which really shines a spotlight on nuclear. A growing consensus holds that net zero is impossible without nuclear, and 28 countries have now signed an international declaration calling for nuclear energy capacity to triple by 2050. The EU, U.S., U.K., Canada, France and Japan are only some of the jurisdictions where bipartisan backing is turning into political action, and a few have already rolled out financial incentives supporting nuclear development. Thanks to that support, we're seeing life extensions, reactor refurbishments, and demands for new builds that deliver secure, reliable, and clean baseload power. On top of that, a technological evolution is approaching, with SMRs and advanced reactors broadening nuclear's use case past electricity alone, which further bolsters the outlook for rising demand.
Tim Gitzel
executiveDemand is durable and expanding, with more backing than we've ever had. So how does that compare with the fundamentals on the supply side? That is precisely where a great deal of uncertainty persists. Geopolitical tensions, which are driving a reassessment of energy security, are simultaneously exerting adverse pressure on supply. The consequent effect on mining operations, fuel cycle services, supply chains, and worldwide transportation keeps generating substantial difficulties. Last week brought a concrete supply impact from those difficulties, as our partner in Kazakhstan, Kazatomprom, cut its anticipated 2024 production volumes in reaction to restricted acid access and development delays. We are now collaborating with Kazatomprom to establish how our portion of 2024 output from JV Inkai will be affected. Supply chain difficulties, together with continuing mine depletion, falling and finite secondary supplies, and ten years of insufficient investment in exploration and mine capacity during low market prices, have produced the very tight market we see today — something anticipated to last into the next decade. Taking demand and supply together, I believe we can confidently restate that strong long-term fundamentals remain a message that keeps resonating, generating the full cycle growth we've discussed. Reflecting on the highly challenging supply discipline decisions we were forced to make and the strategy we established against that persistent, positive, long-term outlook, I can now state that all of it was meant to prepare us for the current market and for the second half of this decade and beyond.
Tim Gitzel
executiveDuring that difficult period, Cameco kept a disciplined approach across the financial, contracting, and operational sides of our strategy. We followed through on our commitments, and that left us well placed to capture full-cycle demand with a supply pipeline that would only respond to genuine end-user demand as it developed. Looking ahead to customer fuel requirements, we understood that attention had to shift back to the long-term market, since the overall volume of requirements is always much larger than what the near-term spot market can offer. It unfolded rapidly, exactly as we had anticipated, and our patience and experience are now delivering positive results. Our financial performance metrics improved significantly in 2023, supported by greater sales volumes and higher realized prices in our uranium and fuel services segments. That produced better net earnings, adjusted net earnings, and cash from operations, all of which more than doubled in 2023 versus the prior year, along with a substantial rise in adjusted EBITDA. Our ongoing discipline and our proven long-term contracting strategy helped reduce risks tied to our capital decisions and mining plans.
Tim Gitzel
executiveOur strategy is built so that production decisions line up with what customers need and with the commitments in our contract portfolio, and it makes sure we aren't adding surplus supply and capacity at times when the market shows no demand. We recognize that full cycle value can't come from mining on spec. Years ahead of time, before we pull pounds out of the ground, we have to build a home for them, so we avoid selling material into a spot market that is thinly traded and discretionary. That means in the contracting cycle we're in today, we can link pounds we previously left in the ground to long-term contractual commitments now being negotiated. And those contracts are being executed against a market environment that has improved significantly, which generates value for Cameco as we deliver into them now and in the years ahead. We closed 2023 with a healthy contract book and total long-term commitments of 205 million pounds of uranium, with 37 customers worldwide. That total commitment level of over 200 million pounds accounts for only about 20% of our current reserve and resource base, which gives us plenty of exposure to improving demand from our customers as they seek to secure their long-term needs.
Tim Gitzel
executiveTo meet those commitments, we need to keep planning well in advance for where the uranium we require will come from. For the near and midterm, the first place we look is always the output we anticipate from McArthur River/Key Lake, Cigar Lake, and Inkai. After that, we're able to take material out of inventory, and thanks to the licensed storage facilities we run, we've locked in the capacity to borrow product under certain of our storage agreements. On top of that, we can accelerate long-term purchase arrangements that were established when prices were far lower. Our marketing team is likewise capable of obtaining material through purchases in the market. Those purchases would cost more than what we produce and our other available supply, yet our strategy and long-term portfolio leave us positioned to gain when near-term demand rises for scarce nuclear fuel supplies and services. When it comes to the longer-term picture, though, given the contract portfolio we already hold and the contracting momentum gathering in the market, we do anticipate requiring volumes beyond what we currently produce each year. That figure includes the over 130 million Tier One pounds remaining in the ground after we moved into supply discipline between 2016 and 2022.
Tim Gitzel
executiveAs a large-scale producer, we rarely talk about our reserves and resources pipeline. If we look at that pipeline alongside the over 200 million pounds we've locked in through long-term agreements featuring escalating prices plus escalating floors and ceilings, our exposure rate comes to roughly 80%. This means roughly 800 million pounds of in-ground inventory today remains neither contracted nor priced, and that represents potential value down the road. This forms part of a highly deliberate strategy. Cameco, as a proven and diversified producer, is well positioned to deliver long-term value. And because we continually build a contract portfolio offering upside participation alongside downside protection, we anticipate that future production development from that in-ground inventory will be financed through cash flow from product sales rather than through dilutive equity raises or meaningful debt leverage. Given our discipline and our strengthening financial performance, we can now weigh the next steps in our strategy and begin investing in our Tier One capacity. We have an updated Cigar Lake technical report that we expect to publish at some point in March, and it includes converting more than 40 million pounds of our share of indicated resources into probable reserves, which extends mine life at Cigar through 2036.
Tim Gitzel
executiveWe are carrying out a study to assess the work, the timelines, and the investment needed so that the McArthur River Mine and the Key Lake Mill can go from 18 million pounds of annual production today up to the licensed capacity of 25 million pounds, with our share being 70%. If we were to capture every Tier One growth opportunity, our yearly share of Tier One uranium supply might come to roughly 32 million pounds. Past our Tier One assets, we keep evaluating what future need and economic potential our fully licensed and permitted Tier Two assets hold. Those assets sit on care and maintenance at present, yet they offer one more layer of optionality for sourcing material to meet long-term commitments. Keep in mind that, unlike a declared or untested asset held by a developer making promises, our Tier Two assets are demonstrated assets that have an operational history and known costs, and a proven producer holds them, which places them in a much lower risk category. As one of the largest producers globally, we gain no benefit from voluntarily disclosing publicly our advanced project work at Millennium, Yeelirrie, and Kintyre, nor from our ongoing exploration successes. Even so, we keep making progress there as well and continue to evaluate future prospects that fit with market demand and with our long-term contract sourcing requirements.
Tim Gitzel
executiveThis year's MD&A includes additional detail on how we approach exploration, since many people don't realize how many greenfield prospects and deposits we've found over time. Those finds form the basis for a highly attractive land package along the most promising trends, located right in our home region of Northern Saskatchewan, where solid industrial and mine support infrastructure exists and where we keep exploring. In addition to uranium mining, our contracting wins and balance sheet strength let us expand and boost the worth of our fuel cycle assets and other investments. As with our mining assets, we will hold off on raising fuel services output or capacity until customers make commitments. That disciplined stance gives us room to grow precisely when buyers are steering clear of Russian supply and services, and the market sees a substantial need in the conversion and enrichment phases of the fuel cycle. To fulfill those expanding commitments in our fuel services segment, we're lifting 2024 UF6 output at Port Hope to 12,000 tons — a record level for the facility, above the records we achieved in 2022 and once more in 2023.
Tim Gitzel
executiveTo date, we have signed contracts for 75,000 tons of UF6 conversion with 33 customers around the globe, and we anticipate that this will support running our Port Hope conversion facility for many years ahead. In addition, we hold a 49% stake in Global Laser Enrichment, which possesses the sole license to commercialize a third-generation uranium enrichment technology. Assuming it keeps advancing toward commercialization, GLE, if things go well, might be positioned to assist in addressing the industry's changing enrichment requirements. Whether that means re-enriching depleted uranium tails, generating commercial low-enriched uranium for the global reactor fleet operating today, or supplying high-assay low-enriched uranium for tomorrow's SMRs and advanced reactors, GLE offers Cameco a meaningful chance to take part across every stage of the fuel cycle. We are likewise pleased to have brought a 49% ownership position in Westinghouse into our investment portfolio during 2023. Westinghouse is a firmly established business that is vital to the nuclear power sector, giving us greater exposure to the light water portion of the nuclear fuel cycle while introducing potential growth prospects tied to its sales of conventional and advanced reactors. For 2024, we anticipate our portion of adjusted EBITDA from Westinghouse will land somewhere between $445 million and $510 million.
Tim Gitzel
executiveWe think the business stands in a strong position for growth over the long term, and the expected rise in worldwide demand for nuclear power is what drives that view. Across the coming 5 years, we expect adjusted EBITDA at Westinghouse to increase at a compound annual growth rate of 6%-10%. Despite the major Westinghouse acquisition, we have kept room for additional investments if opportunities that add value should arise. Our balance sheet is still solid, with CAD 567 million in cash, roughly CAD 1.8 billion of total debt, and a CAD 1 billion credit facility that remains undrawn. Within our uranium segment, we expect the strong financial results of this past year to carry on in 2024. We will keep moving toward our Tier One cost structure and put to work the capital and other expenditures that we believe are needed so we can meet our commitments and place the company for ongoing sustainable growth. That growth will be pursued just as we approach every part of our business: strategic, deliberate, disciplined, and focused on generating full-cycle value. We also maintain a continued focus on the environmental, social, and governance side of our business, where our track record makes us very proud. ESG principles and practices are integrated into every aspect of our business, from our corporate objectives and how we approach compensation to our overall corporate strategy, risk management, and day-to-day operations.
Tim Gitzel
executiveUnder our plan for lowering carbon emissions, during 2023 we established decarbonization routes tailored to every site in our portfolio, helping us reach the greenhouse gas reduction goals we have set for 2030. In addition, we carried out a climate change scenario analysis covering our Northern Saskatchewan and Ontario operations, so we can better grasp how shifting climate conditions might affect our workforce and our assets over the long term. I would encourage everyone to look through the annual MD&A, since there we move past performance highlights alone. Inside it, you will find a far more detailed view of our strategy and the way we operate, and, importantly, insight into the uranium and nuclear fuel market — a market that is unlike any other. Thank you for your interest today, and we would be glad to take any questions.
Operator
operatorWe're going to open things up for questions now. Given the time constraints, please keep it to one question plus one follow-up. Should you have more to ask, feel free to get back in the queue. Pressing star then one on your phone's keypad will add you to the question queue. A tone will sound to confirm your request. On a speakerphone? Please lift the handset before hitting any keys. To drop out of the queue, press star then two. Those joining via webcast can send questions using the box at the bottom of the webcast frame. After the call, the Cameco Investor Relations team will reach out to you by email. Once more, anyone on the conference call who wants to pose a question may press star and one at this time. Our first question is from Ralph Profiti of Eight Capital. Please go ahead.
Ralph Profiti
analystMorning, Cameco team, and thanks for taking my questions. Tim, regarding the McArthur River evaluation covering as much as 25 million pounds, when do you expect that work to wrap up? And assuming the factors under review include matters from September 2023 — supply chain, skilled labor, plus certain special technical considerations — do you see a possible scenario in which Tier Two, whether US ISR or Rabbit Lake, could be more attractive than output from McArthur River? That's because those production centers might face fewer constraints.
Tim Gitzel
executiveMorning, Ralph — good to hear from you. We've just begun the evaluation work at McArthur River/Key Lake. In the market we're looking at, those pounds may well be needed down the road. As far as pounds not yet being produced, those are likely the finest on the planet. So we're getting started on what has to be done to debottleneck the Key Lake mill. The mine is performing well at present, and we're confident it can deliver at that level. Work is therefore underway. Clearly, we won't produce on spec — Grant has made that point 100 times. We produce within the contracts we hold, so we'll get that effort moving, and as I said, we're pursuing that ahead of any Tier Two project we still have sitting in care and maintenance. That said, don't count those out either, Ralph, since they remain on our batting lineup, further down the list. But first, as we noted in our quarter, we're going to examine debottlenecking McArthur and Key so we can bring those to 25. And then there's that extension — don't underestimate extending Cigar Lake to 2036. That's a massive move, and it positions us really well for the future.
Ralph Profiti
analystAll right, got it. Yeah, appreciate the added detail. I also saw on that uranium sensitivity table that the exposure to a 5% shift in uranium affecting revenue looks pretty small this year. I'm just curious what's happening between the contract book and the realized price guidance, and why the leverage seems reduced compared with earlier years. And it looks as though this stems from the contract books, maybe reaching more of those upper limits, or possibly even customers choosing to flex upward.
Tim Gitzel
executiveRalph, Grant is honestly the top person we have on this subject. Grant, would you like to handle that?
Grant Isaac
executiveSure, that's a really good question, Ralph. Let me be very clear that we established a strategy which supports price discovery in the short term so that we can create value over the long term. What I mean by that is this: it is absolutely the wrong approach to think of a uranium producer as holding back production for the spot market so as to maximize near-term leverage to that market. We've repeated this many times, and people truly need to grasp it: the spot market is small, it is discretionary, it is non-fundamental, and its demand is low-quality. If Cameco produced and turned up trying to sell pounds into the spot market, we would not be discovering higher prices. What would happen is the reverse. The market would come to realize that we were appearing with uncommitted primary production, and the market would back up. Don't just take my word for it. Consider what took place in the days when Paladin, for instance, was a seller into the spot market, or when Kazatomprom was a seller into the spot market. That strategy has been shown to be a colossal failure time and time again. What counts is the non-discretionary, fundamental, high-quality demand of the term market. But make no mistake, Ralph, we do not miss these market moves.
Grant Isaac
executiveWe simply take those and incorporate them into the forward contract book. You've heard me repeat many times that at present we favor contracts tied to the market. A shift of this kind in the spot market — which we do not sell into, since undermining that spot market move is not something we want — lets us subsequently price market-linked contracts forward on a far more appealing basis than was possible before the spot market shifted. Let me offer an illustration. When uranium climbed past $100 per pound, Cameco does not instantly ask, "How do we sell into the spot market?" Instead we ask, "How do we turn that sort of rapid spot market move into forward value?" So a market-related contract we might write today and hand to a utility likely carries a floor set essentially at today's long-term price, escalated, and likely carries a ceiling somewhere in the $120s, escalated. That is the way we capture the value from a spot market move. Those wanting to play the spot market turn up with uncommitted primary production, they apply pressure to it. In a market that trades thinly, it declines, and they ride it back down. Our approach is to take those moves and build them into the contract portfolio going forward.
Grant Isaac
executiveThis approach keeps near-term price discovery intact and assists in lifting that longer-term price toward a level that's economically sustainable for production. Given all of that context, it comes as no surprise that deals we signed several years back—ones that, say, carried a $70 ceiling a few years ago—would have looked like a genuinely appealing ceiling at the time. In a related market, we may now be reaching those ceilings. Take today, for instance, or situations involving some base-escalated component—this development is welcome news. It signals that the market is entering a security-of-supply contracting cycle. It shows our supply discipline strategy is delivering results. It demonstrates that forward value capture keeps expanding. And then, naturally, I want to bring up what Tim said: folks, 20% of our reserves and resources portfolio is under contract. The other 80% is not. That amounts to 800 million pounds of uranium that will now be priced in a far better environment. So we never let these moves pass us by. We incorporate these moves into long-term contracts, into long-term cash flow and earnings. That's what is taking place.
Ralph Profiti
analystOh, that helps a lot, Tim and Grant. Many thanks. That's really useful background on the strategy. Appreciate it once more.
Tim Gitzel
executiveMuch appreciated, Ralph.
Operator
operatorOur following question is from Andrew Wong at RBC Capital Markets. You have the floor.
Andrew Wong
analystHello, and good morning. Thanks for taking my questions. Could you share how confident you are that production will return to nameplate in 2024? Also, regarding the longer-term projects at Cigar and McArthur, I believe the earlier message was that those projects might not be examined until volumes begin to be contracted and demand was present. So now that work is beginning on those projects, does that mean those volumes are starting to see some contracting activity?
Tim Gitzel
executiveThanks, Andrew, for that question. So, how confident are we, really, about production this year? For each of those sites, we've issued a forecast of 18 million pounds, and we're extremely confident we'll hit it. At McArthur and Key, we've gained additional operating experience. With each passing month, we get another perspective on how things are progressing, and I would say the past two or three months have been quite good. If you look at Brian Reilly, our production there has been quite good and very steady. We're ironing out some of the bottlenecks, or kinks, that come along with a restart. So we're really pleased with how things are going there. The same applies at Cigar. You know, it's a well-established mine. We've operated there for years. We've moved into that new ore zone. We're bringing that under control. The mill experienced some hiccups, and they've brought that under control. So yes, we're very confident in our forecast for 2024. And going forward, yes, as I mentioned earlier, we won't produce on spec, but we will get those assets ready to go at McArthur Key. And once Grant and his team have contracts in front of us that call for that production, we will move those forward.
Tim Gitzel
executiveWe're going to increase output at McArthur Key. And so, you know, timing plays a role here, and nothing comes together instantly. We want to be prepared for when that moment arrives, and the agreements we enter into — those long-term deals that Grant mentioned before — you know, deliveries under them won't begin for several years. So there's time for us to prepare, and, well, we have dry powder, and once the moment comes, we'll be set to move. So our positioning is something we really feel good about.
Andrew Wong
analystAll right, thanks. And perhaps for Grant — the contracting approach, you know, really does make a lot of sense. Would you be able to just discuss what the contract book and the price sensitivity table might look like past the years shown in that table, say into the late 2020s and early 2030s, where you could capture more of that leverage to the rising price environment we're seeing today?
Grant Isaac
executiveYes, absolutely—it's structured to take advantage of that higher-price setting. I really want to stress that supply discipline remains in place for us. We're not declaring the market has topped out. Uranium demand hasn't reached its peak at this point. We're at the beginning of this contracting cycle. Being at that early stage is a signal that staying very disciplined on supply is the correct approach. We're considering taking Tier One up to full capacity, as Tim mentioned, but no decision has been made yet regarding McArthur River/Key Lake, and we haven't even begun discussing the Tier Twos. If we combined all of that and asked what our yearly capability would be, it comes to roughly 38 million pounds of annual production. In our guidance table, you'll see 22.4. So Cameco isn't declaring peak demand here, nor peak price discovery in the uranium business. Supply discipline is still our stance. Supply discipline remains our stance because we believe that when we examine the uncovered requirements wedge, a substantial amount of demand—non-discretionary fundamental demand—needs to arrive in the market. We want exposure to that. So the goal isn't to sell out volumes; it's about placing volumes under terms and conditions that make sense to us today.
Grant Isaac
executiveSo that's the market-related exposure I mentioned, and it's really sharply improving the floors and ceilings—both of which are escalated, by the way—and naturally, a long-term price that now stands at $72 U.S. per pound, and that in itself is base escalated if you sign on to any of those contracts. So as you can see looking ahead, we'd aim to move past that contract table, which represents only about 20% of our volume. As a matter of fact, that committed sales table is even less than that. It's just about 13% of our volumes, since it only covers the next 5 years. So 80% of those volumes remain unsold as of yet. That's a positive. Prices are rising. We want that exposure to future prices, and when you consider our reserves and resources that aren't priced yet, which carry that pure exposure to the uranium price, those are reserves and resources held by a proven, proven producer with, and many of those reserves and resources sit adjacent to existing infrastructure and can benefit from all those incumbencies. So this is precisely where a responsible uranium producer wants to be, ought to be, in a market that is entering a security of supply contracting cycle.
Grant Isaac
executiveSure, we really like where we stand. We're big fans of that exposure going forward. It would be silly to claim, "Well, we ought to just force all of our material through a $103 spot market," since the spot market wouldn't be at $103 if we attempted that. That would be a truly foolish strategy. So as for that exposure going forward, no one is positioned better than we are.
Andrew Wong
analystExcellent. I appreciate it very much.
Tim Gitzel
executiveAppreciate it, Andrew.
Operator
operatorWe'll now take a question from Orest Wowkodaw at Scotiabank. Go right ahead.
Orest Wowkodaw
analystMorning, and thanks — I’ve got a couple of questions, if that’s alright. To start, could you give us a sense of how much capital would be needed to take McArthur up to 25 and to extend Cigar?
Tim Gitzel
executiveSo, Brian, would you like to handle that one?
Brian Reilly
executiveAbsolutely, happy to.
Tim Gitzel
executiveOkay, thank you.
Brian Reilly
executiveThat's a good question. On the Cigar Lake extension, we're certainly well along. A pre-feasibility study has been completed, and it confirmed the extension's economic viability. Resources have been converted into reserves, so we're quite far down that path. Next month we'll issue a technical report, as Tim said, containing all the specifics. As for our share of capital at Cigar Lake Extension at this point, it sits somewhere between CAD 250 million and CAD 300 million to carry it through to 2036. So Cigar Lake Extension is shaping up nicely, and a technical report with full details will follow. Turning to McArthur River/Key Lake expansion — early days, really very early days, as Tim noted. We've only just started assessing what the mine will need, along with an end-to-end study at the mill. So my advice would be to bear with us. Later in the year we'll be in a better position, though it remains early days for McArthur River/Key Lake expansion.
Orest Wowkodaw
analystAll right, but would it be fair to characterize that as under $1 billion — so, in other words, we're talking hundreds of millions?
Brian Reilly
executiveOh, wow. Yeah. Absolutely.
Orest Wowkodaw
analystPerfect.
Brian Reilly
executiveYes. That's right.
Orest Wowkodaw
analystThen a quick one for Grant, if I may. On the committed purchases — I think you have £4.7 million committed to acquire this year. Could you give us some sense of how the cost works, like how the pricing mechanism operates on those contracts? Does it track market pricing? Is it fixed? How should we think about that?
Grant Isaac
executiveYeah, thanks, Orest. So if you’re following along, on page 51 of the MD&A, we actually do have some new disclosure on our purchase commitments. In earlier markets where the spot was oversupplied and we were exercising extreme supply discipline and wanted to be heavily over-contracted, we would put out a big purchase number because we wanted the market to know demand was coming, so it would start cleaning up the front end of the market and discovering better prices. But at this phase of our transition, restoring our Tier One costs and bringing production back, we wanted to bring a bit more granularity between what purchases we are already committed to make and which ones might we go into the market to buy. When we cut it that way, what you see is very small exposure to the market. We said up to 2 million pounds that we might buy in the market, but we might — we don’t have to. We have other options in order to source our committed sales. Some of those other options include purchases that we make under a long-term purchase commitment, and I think that’s what you’re referring to.
Grant Isaac
executiveTypically, with those long-term purchase commitments, here's what happens: we'll look at a market where, you know, we may believe the uranium price is low. When that's the case, we might locate a seller prepared to lock in a price for us, you know, under a carry trade arrangement for delivery at some point down the road. For a lot of those contracts, though, we have the option to take delivery whenever it suits us. So we lock in the price during a lower pricing environment. We accept delivery at the moment that makes sense for fulfilling our committed sales volumes. That's the strongest trading margin in the business. So a great many of those long-term contracting, long-term purchase commitments were entered into, you know, in that $30 uranium market. They've risen somewhat, you know, certain ones in more recent years, but still well below today's market prices. So this is simply part of how we approach sourcing material over the long run. So there's very small market exposure to be deployed if we choose to, and then subject to the purchases that come in from Inkai, the purchases that come in from the long-term purchase program. The last thing on Inkai is always keep in mind, we're never afraid of rising uranium prices, and Inkai is a perfect example.
Grant Isaac
executiveCorrect — the material we purchase from Inkai comes to us below the spot price. Those purchases will carry a very high cost, but when they do, the dividend flowing back from Inkai is even larger. The economic worth of those Tier One assets therefore remains ours at all times, and rising prices don't worry us. Rather than letting these markets pass us by, we capture that value over the long term. It's a highly attractive source of supply that genuinely lowers how much we must go into the market to buy. Still, should a buying opportunity appear, we'll take a look. So if someone chooses to try selling material into the spot market, we could end up as a buyer.
Orest Wowkodaw
analystThanks, Grant. So in the end, I think if I'm reading your new disclosure correctly, the amount you intend to purchase from the market at market pricing comes to no more than 2 million pounds?
Grant Isaac
executiveCorrect. In the past, we noticed certain people were entirely misinterpreting the outlook table. They looked at total purchases and assumed all of them would be executed in the spot market, then used that to push a false story about financial distress. Naturally, we would never operate the company in that manner. Were that the situation, the outlook table would look quite different. So we decided to provide some granularity — many sophisticated people grasp how we operate, but others do not. We simply wanted to ensure that granularity was available and to remind people that it is actually as much as 2 million pounds. We have the option to source it directly through the spot market for immediate delivery. We have the option to draw down inventory, to access loans, to access additional long-term purchases should that suit us. We have the option to talk with a customer about shifting deliveries within a year to align with when production arrives. At the end of the day, that is what a responsible uranium producer does.
Orest Wowkodaw
analystThat’s great. I appreciate it.
Brian Reilly
executiveThanks, Orest.
Operator
operatorGreg Barnes from TD Securities has the next question. Go right ahead.
Greg Barnes
analystYeah, thanks. I’ve got a couple of questions. Going back to the Cigar Lake extension, would that stay around 18 million pounds per year, or would it fall off by 2036? And does it go past 2036?
Tim Gitzel
executiveGreg, I appreciate the question. Our intention would be to stay at 18 million pounds annually through 2036. Might there be an extension? At the moment we're focused solely on this one, so once we get in there... And, you know, we're heading west on that front. So as we get out there, who can say? We'll be drilling all over the place down there, so we're hopeful, but there's nothing to report yet, Greg.
Greg Barnes
analystOkay. And regarding the Westinghouse guidance, that 6%-10% yearly CAGR — is it counting only AP1000 sales that have been signed or are signed right now? Or does that figure also factor in a projection of possible AP1000 sales?
Grant Isaac
executiveYeah, Greg, here's the good news. Those are only the ones you're aware of — the ones Westinghouse has announced. So there's more upside ahead, since we think there could be a huge opportunity in other markets that are evaluating that stable, proven AP1000 technology. But this only captures the early contracts needed to move AP1000s forward in the markets that have already made their announcements.
Greg Barnes
analystGrant, just a quick one on Springfields — has any decision been made yet about restarting that conversion plant, or is there any backing from the U.K. government to make that happen?
Grant Isaac
executiveThere's still a great deal of interest in the natural conversion line at the Springfields conversion plant. But Springfields also matters as critical infrastructure for many other ambitions too. We keep working our way through that process. Clearly, conversion prices in the market are very attractive at the moment. That gives a bit of tailwind toward a restart, though it has to be handled responsibly. It's the same situation as in the uranium market. You don't get a conversion plant going and then begin knocking on doors asking whether people would like to purchase a conversion service, since doing so will only drive the conversion price lower. This has to be done responsibly and with discipline, and right now we are simply working through that process.
Greg Barnes
analystGreat, thank you, Grant.
Tim Gitzel
executiveThanks, Greg.
Operator
operatorOur following question is from Lawson Winder at Bank of America Securities. You have the floor.
Lawson Winder
analystMuch appreciated, operator, and good morning to everyone at Cameco. Thanks for fielding my question. My inquiry concerns Westinghouse, and it's great that the notes include such thorough disclosure. The SG&A figure — meaning selling, general, and administrative costs, essentially marketing and admin — comes in somewhat bigger than I had anticipated. Could you share some detail on what's included in that? Or perhaps what the major components are, or how that number breaks down?
Grant Isaac
executiveGrant —
Lawson Winder
analystAnd any guidance on that for what comes next too. Thanks.
Tim Gitzel
executiveI’ll have Grant take that one.
Grant Isaac
executiveRight, so some parts of the Westinghouse business are quite high touch, you know. When we think about the core of that business — which we define as nuclear fuel and operating plant systems — as well as the new build, there are a lot of offices, a lot of engagement, and a fairly high touch involved in moving those kinds of contracts forward. And so right now, when they're at the stage of developing new markets like they are for VVER fuel, or developing new markets, like expanding into BWR fuel, or examining LEU+ fuel. And even the question that Greg asked earlier about Springfields, you know, this is all captured in increased activity running through that line, and of course, the support required to advance new builds, whether that's AP1000s, AP300s or eVinci. So, you know, a bit of a higher touch business than what Cameco is accustomed to, but totally appropriate, given the position that Westinghouse is in and their ability to capture the tailwinds in the nuclear industry as well.
Lawson Winder
analystAnd from here on out, is that 2023 level — well, at least for the share of 2023 that you've reported so far — a reasonable level to expect for 2024 and 2025?
Heidi Shockey
executiveYeah, this is Heidi. I'd describe them as a fairly steady business, and perhaps I'd just build on Grant's comments regarding the other elements — that it's really about acknowledging the fixed costs. I mean, that covers all expenses not tied directly to operations. So it's possibly wider in scope than simply G&A.
Lawson Winder
analystThanks so much. For my follow-up, I’d actually been hoping to ask about the conversion market too. And Grant, back in December, on the investor call during Investor Day, you shared a view that maybe prices were, you know, getting close to a peak. But since then, prices have kept climbing. So have you revised your thinking at all? Do you believe prices could keep going higher? Or are we actually reaching a point where prices are about as high as they can get?
Grant Isaac
executiveSure. Lawson, when I made that earlier remark about Cameco not calling peak demand or peak pricing, I was talking about uranium, though it may apply to conversion too. What I mean is that this market hasn't yet fully priced in a couple of significant risks, and one of them is clearly the possibility that legislative moves to limit Russian supply in Western markets don't just get written into law, but also that Russia retaliates in a way that would create a very favorable setup for conversion, because keep in mind that Russian enrichment services arrive attached to something. They come in a cylinder that already contains the uranium and already contains the conversion. So that's going to keep adding pressure on the conversion side of the business. And then, naturally, I don't believe this market truly grasps how hard it can be to bring production back online, whether that's a uranium asset or a conversion asset. You know, I think many people simply assume these things are easy and they price in a perfection scenario. So between those two really significant risks — that a ban on Russian material prompts the Russians to actually respond by saying, "Okay, well, you can't have it today," and the reality that will sink in, that all these big promises about new supply, whether on the uranium side or the conversion side, are simply going to take longer.
Grant Isaac
executiveThere is still more price formation that has to happen in this industry. That's the reason we don't want to declare a top, and it's the reason we don't want to hurry and, you know, lock in every conversion contract that would sell out Port Hope or push Westinghouse to do the same for Springfields. This market has more ahead of it. We've witnessed this story in the past. Right now is when you stay patient and allow that price discovery to play out.
Lawson Winder
analystI appreciate everyone joining us today.
Grant Isaac
executiveThanks, Lawson.
Operator
operatorJust a heads-up that we have under 10 minutes left for questions, and if we don't get to yours, feel free to contact the IR team. Thanks. Our next question is from Alexander Pearce at BMO. Please go ahead.
Alexander Pearce
analystThanks. Morning, everyone. I wanted to ask if you could expand a bit on the market commentary you've given, especially the shifts you've observed so far this year, and in particular what has changed in your conversations with utilities since Kazatomprom's updates came out last week?
Operator
operatorGrant?
Grant Isaac
executiveSure — we’ve observed a market doing precisely what we said it would do, Alex. Once the market starts moving into a security-of-supply cycle, the spot market actually becomes less important, while the term market becomes more important. And just look at the numbers: the spot market was smaller in 2023 than in 2022. That means utilities are paying less attention to spot and more to term. This ties back to what I said earlier about why we don’t attempt to sell material into the spot market. It’s thinly traded, and it’s non-fundamental discretionary demand. So as utilities shift, what we’re seeing is a market that reached roughly 160 million pounds of term contracting. It might be easy to conclude that we’re at replacement rate, Alex, but I’d say we’re not quite there yet, because two very, very large contracts moved through the market. One was Cameco’s with Ukraine, and the other was Kazatomprom’s with the Chinese. If you take those out and ask whether, on a distributed basis across all markets, we are at replacement rate, the answer is no. And so the good news is that we’re in the early innings of a security-of-supply contracting cycle.
Grant Isaac
executiveWe haven't reached a distributed replacement rate as of yet, and at these price levels we've never occupied this point in the cycle before — that's the reason we'd like to keep that exposure in place going forward. That said, a few shared traits stand out: tenors keep rising. Utilities that come to market seeking security of supply want their requirements covered over a longer horizon. Tenors are stretching out, volumes are climbing — not merely because additional years get added, but because utilities are taking a larger bite from every one of their requirements contracts. And then, naturally, time frames are extending. Some utilities, Alex, are covered really well through the remainder of this decade. Their worry now is the following decade, and they're beginning to look at contracting into that window too. So all of this is very constructive for the view that long-term demand is building rather than peaking — building — and that what we want is to stay very disciplined so we capture as much of that price discovery as we can.
Alexander Pearce
analystThanks, Grant. And Tim, you noted in your remarks that you can pull forward some of those purchase agreements if needed. Could you quantify whether that actually happened for this year’s guidance, and how much you’ve pulled forward from future years into this year in these purchases?
Grant Isaac
executiveApologies—Alex, this is Grant speaking.
Tim Gitzel
executiveWe’re simply leaning on one another.
Grant Isaac
executiveYes, this is Grant once more. That figure of 4.7 million was always part of the plan shown in the outlook table. So we hold it as an option to exercise additional long-term purchase requirements should we choose to. That is the reason the market purchases disclosure runs to as much as 2 million pounds. It would be one of the levers explaining why that 2 million pounds is not a hard figure, since buying in the spot market may not happen. There is no obligation for us to do so, but when it makes sense on our side, we will.
Tim Gitzel
executiveRight.
Alexander Pearce
analystAll right, thanks.
Tim Gitzel
executiveAppreciate it, Alex.
Operator
operatorBrian MacArthur from Raymond James has the next question. You're up.
Brian MacArthur
analystGood morning, and thanks for taking my question. It relates back to the previous question. So in this table — and I appreciate that you've now provided the breakout — two things: do you assume that you receive your Inkai purchases each year? Because again, you also state at present that we're not sure what we're going to get, and again, those are, as you said, profitable pounds once the equity component is included. If not, how do you account for that? Because, again, the question is that you could be getting 4 to 5 million profitable pounds from Inkai. And my third question on that is: I can't recall — under that agreement, are you getting 50% or 40% of the joint venture now? Thanks.
Tim Gitzel
executiveBrian, to begin with, yes — the table does assume that the volumes we expect from Inkai in 2024 will show up. But naturally, as 2023 demonstrated, timing can sometimes differ. Roughly two-thirds of Inkai's 2023 volumes reached us during 2023, with the rest coming in early 2024. Cameco is able to handle that, since we have alternative supply sources. There are other mines, there's our inventory, and there are all the levers we've been discussing already. For the front end of the nuclear fuel cycle, this is in fact a far, far larger issue, because nearly 50% of worldwide uranium production isn't arriving at Western markets at the moment it's needed. So from Cameco's standpoint, it's something we can plan around and something we can manage. Those pounds do eventually reach us, and we can address the timing problem tied to them. The core assumption is, yes, we will receive them. Should that not happen, we'll find a way.
Sean Quinn
executiveGrant, let me just add one point: the split becomes 60/40 as soon as you get to the 4,000 tons per year nameplate capacity, which works out to a bit more than 10 million pounds. That peak has never been reached so far, and across the past several years, what we've essentially gotten as our production share is what 40% of 10 million would give us — roughly 3.3 million pounds.
Brian MacArthur
analystGreat, thanks. Just so I’m really clear, as you said, you also received two-thirds of last year’s shipments from Inkai. So presumably those pounds are in inventory and the rest are at the Canadian port. So wouldn’t you feel fairly comfortable that you’ll have plenty of Inkai pounds to sell this year, since they’ve already arrived and that’s embedded in those numbers?
Tim Gitzel
executiveYeah, sorry about that. I hope what I said didn't come across as lacking confidence. We have a lot of confidence that this supply is going to arrive, and if timing issues come up, we'll handle them through our inventory and our other supply sources. So, extremely confident.
Brian MacArthur
analystRight, yeah… great, that covers everything. It's only that these pounds bring in a lot of profit, so the timing of when they arrive shifts the financial picture.
Sean Quinn
executiveYeah. Absolutely. That's right.
Brian MacArthur
analystAlright, thanks a lot. Sorry, just one final quick question. Regarding CRA, I really don't want to revisit this at all, since I'd sort of assumed it was hopefully resolved, but I do notice you have to set aside some additional money once again. So we've handled 2017. Does that mean they can do 2018 and 2019, and you might have to put money aside this year or later?
Tim Gitzel
executiveAppreciate the question, Brian — well, I was about to say that, anyway.
Grant Isaac
executiveNo, I’m sure that isn’t the case.
Tim Gitzel
executiveI’ll hand it off… Oh, Brian, let me give it to Sean. Sean.
Brian Reilly
executiveAbsolutely. Yes, we did need to revisit things starting from 2017, and I believe we set aside CAD 70 million, which we anticipate having to provide as a letter of credit. The issue does get smaller. The CRA matter is still ongoing, but the scale of it shrinks across 2018, 2019, and 2020 as the pounds sold via our offshore trading structure decline. So I don't have the precise magnitude of that reduction in front of me, but it does become smaller as we look ahead. Great. Thanks. That's really helpful. Thank you, Sean.
Sean Quinn
executiveThanks, Brian.
Operator
operatorThat brings the Q&A portion to an end. I'd now like to hand the conference back to Tim Gitzel, who may offer some closing remarks.
Tim Gitzel
executiveThank you, operator, and thanks to all of you for joining us today. As Rachelle mentioned, if you have detailed follow-up questions about the 2023 results, or anything we didn't get to today, please send them our way and we'll be glad to answer them directly. We still firmly believe that Cameco is the finest avenue for investing in the nuclear fuel cycle's recovery and in the positive momentum building behind nuclear energy. Having spent 35 years in this market, we've earned a solid reputation as a dependable, proven supplier with a diversified production portfolio — one that gives us the flexibility to collaborate with our customers so they keep access to our reliable supplies and can meet their ongoing fuel requirements. The world has made reaching net zero carbon emissions in the decades ahead a priority, and it has become evident that without nuclear there is no net zero. I'd take that a step further: in fact, without Cameco and Westinghouse there is no nuclear, so it is likewise becoming evident that without Cameco there is no net zero. We believe our strategy is the right one for achieving our vision of energizing a cleaner world, and we'll pursue it in a way that reflects our values.
Tim Gitzel
executiveOnce more, thank you all for being with us today. Please keep yourselves safe and in good health throughout 2024. Appreciate it.
Operator
operatorThat brings us to the end of today's conference call. Your lines can now be disconnected. Thanks for joining us, and enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Cameco Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Cameco Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Cameco Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.