Operator

operator
#1

Good morning, and thanks for joining Capital Power's conference call covering our first-quarter 2020 results. Right now everyone is connected in a listen-only format. After we finish the presentation, we'll open up the line so you can ask questions. Today is May 4th, 2020, and this call is being recorded. I'll hand things over now to Mr. Randy Mah, our Director of Investor Relations. Randy, over to you.

Randy Mah

executive
#2

Good morning, everyone, and thanks for being with us today as we go over Capital Power’s first quarter 2020 results, which came out earlier this morning. You can find our first quarter report along with the presentation for this conference call posted on our website at capitalpower.com. As a measure to help prevent the spread of COVID-19 through physical distancing, Brian Vaasjo, President and CEO, and Bryan DeNeve, Senior Vice President and CFO, are joining me on the call from their homes. We’ll begin with the opening comments and then open the lines to take your questions. Before we start, I’d like to remind everyone that certain statements about future events made on the call are forward-looking in nature and are based on certain assumptions and analysis made by the company. Actual results could differ materially from the company’s expectations due to various risks and uncertainties associated with our business. Please refer to the cautionary statement on forward-looking information on Slide number 2. In today’s discussion, we will be referring to various non-GAAP financial measures as noted on Slide number 3; these measures are not defined financial measures according to GAAP and do not have standardized meaning prescribed by GAAP and therefore are unlikely to be comparable to similar measures used by other enterprises.

Randy Mah

executive
#3

These figures are meant to supplement the GAAP figures that appear in the review of the company’s results as seen through management’s eyes. You can find reconciliations of these non-GAAP financial measures in the MD&A for our first quarter of 2020. At this point I’ll hand the call over to Brian Vaasjo, who will begin his remarks on Slide 4.

Brian Vaasjo

executive
#4

Thanks, Randy, and good morning. I'll begin with some high-level remarks about our first-quarter results and our 2020 outlook. On the whole, our results for the first quarter came in solid and matched what we had expected. Since there are no material changes to our outlook, we are keeping our financial guidance and dividend guidance for 2020 unchanged. Our financial position and liquidity are very strong, and Bryan will address that shortly. At Capitol Power, we have put in place a range of measures to manage the risks posed by COVID-19. The primary aim is keeping employees safe and healthy, lowering risks, and keeping our plants running. I'll also go over the progress we've made on our renewable and growth strategy, which has been good so far this year. Moving to Slide 5, in response to COVID-19, we have implemented our business continuity and risk management plans to ensure our employees stay safe and healthy. That includes working from home for office staff and all non-essential plant employees. At the plants, we have put in place numerous hygiene and social distancing protocols while still delivering reliable power. All in all, the company is operating very well. We are also managing operational risk by completing planned maintenance and enhancement outages at Southport, Roxboro, Arlington, Decatur and Goreway. With our employees and contractors in mind, we have modified the Decatur outage and have pushed the Genesee to 2021.

Brian Vaasjo

executive
#5

We've also leveraged technology so that our 3 simple cycle plants can be run from a laptop. All in all, we're navigating the COVID-19 pandemic quite effectively. Turning to Slide 6, I'll discuss the recent strides we've made on our growth and renewable strategy. So far this year, we've brought 251 megawatts of renewables into our fleet. That includes finishing the Cardinal Point Wind project in Illinois, which came in on schedule and on budget in US dollars. Back in April, we purchased the 101 megawatt Buckthorn Wind facility in Texas, which is contracted with 15 years of weighted average remaining contract life. We've signed an agreement with Vestas that established terms for a 10-year extension of our long-term service agreements. That extension provides fleet-wide maintenance for all wind facilities using our Vestas equipment, and the LTSA carries an expanded scope of services, with an expected 26% cost reduction versus the current service and maintenance agreements. On an annual basis, once the new LTSAs all take effect between 2021 and 2023, they're expected to boost EBITDA by $8 million and AFFO by $6 million, respectively. An agreement has been reached with Vestas to supply turbines for Whitla 2, which will begin commercial operations next year.

Brian Vaasjo

executive
#6

Bryan DeNeve, over to you now.

Bryan DeNeve

executive
#7

Thanks, Brian. I'll walk through the financial highlights, beginning on Slide 7. On the whole, our first quarter financial results came in as we had expected. Planned outages made the first quarter the busiest such period of the year, which is reflected in the 91% average availability. As a result, we anticipate generating positive net cash flows over the rest of the year. As Brian noted, the major planned outage at Genesee 2 has been pushed to 2021 because of COVID-19. During the first quarter, we held discussions with ENMAX, our JV partner on the Genesee 4 and 5 project, and concluded that we would not be moving forward with that project any longer. As a result, $13 million tied to developing Genesee 4 and 5 was booked in the first quarter as a write-off within depreciation and amortization. Turning now to the Alberta power market. The average spot price came in at $67 a megawatt hour for the first quarter, a bit below the $69 seen in the first quarter of last year. Each quarter had one month of higher pricing driven by cold temperatures and outages at baseload facilities, while the remaining two months settled at moderate pricing with stable baseload supply. During the first quarter, our trading desk achieved an average realized price of $62 a megawatt hour, which was 7% below the average spot price.

Bryan DeNeve

executive
#8

Now on Slide 8, first-quarter revenues and other income came to $533 million. That's a 34% increase over the first quarter of 2019, primarily as a result of acquiring Goreway in the second quarter of 2019. Adjusted EBITDA reached $234 million, a 16% rise year-over-year, which was mostly due to the Goreway acquisition along with the addition of Whitla Wind 1. Normalized earnings came in at $0.27 per share, a slight decline from $0.29 per share in the first quarter of 2019. AFFO generated was $118 million, in line with the $117 million recorded in last year's first quarter. AFFO per share was $1.12, a 3% decrease versus the first quarter of 2019. Moving to Slide 9, I'll give you an update on where our commercial portfolio positions stand. For the rest of 2020, baseload generation is 91% hedged at an average price in the mid $50 per megawatt hour. That compares with forward prices currently at $48 per megawatt hour. As the quarter closed, we sit 7% hedged for 2021 at an average contract price in the low $60 per megawatt hour range. For '22 and '23, we are 15% and 9% hedged, respectively, at an average contract price in the low $50 per megawatt hour range for both years.

Bryan DeNeve

executive
#9

That's against forward prices right now of $53 a megawatt hour for 2021 and 2022, and $51 a megawatt hour for 2023. To wrap up my remarks, I'll talk about our solid financial position and liquidity, which is on Slide 10. Capital Power is producing robust cash flows, including more than $300 million of discretionary cash flow in 2020. The pie chart there shows our adjusted EBITDA forecast for the last nine months of 2020. As you can see, 83% of adjusted EBITDA sits under contracts, with an average PPA term remaining of 10 years. Those PPAs are mostly with investment grade counterparties. The other 17% of adjusted EBITDA comes from the Alberta Merchant business, and 13% of that is hedged, so our merchant exposure is just 4% for the rest of 2020. For our commercial industrial customer base in Alberta, one-third is investment grade, one-third is posted collateral, and the balance carries some default risk that has been recognized in a $200,000 provision. On liquidity, we have $900 billion of available capacity on the $1 billion of committed credit facilities that mature in 2024. At present, we don't expect to need to access the capital markets, other than potentially to refinance the $250 million in debt maturing in November.

Bryan DeNeve

executive
#10

Back in April, DBRS reaffirmed our BBB low credit rating with stable trends, which reflected a fairly steady long-term business risk and financial profile. Since what we expect for 2020 hasn't changed, we're restating our guidance for 2020 financial and dividend growth. At this point I'll hand the call back over to Brian.

Randy Mah

executive
#11

Brian, your line is still muted—please unmute it.

Brian Vaasjo

executive
#12

Yeah. Thanks, Bryan. I'll go over how we performed in the first quarter against our 2020 annual targets, which are laid out on Slide 11. As I said, the first quarter was a busy one for planned outages, and that gave us average facility availability of 91%, versus the 93% annual target. Sustaining CapEx came to $16 million in the first quarter, and with the Genesee 2 planned outage deferred to 2021, we expect sustaining CapEx to come in below that $90 million to $100 million annual target. We posted $234 million in adjusted EBITDA in the first quarter, against the $935 million to $985 million target. And we generated $118 million of AFFO in the first quarter, compared with the $500 million to $550 million target range. On our current forecast, we're on track to land near the midpoint of the AFFO range, while we keep watching the impacts from COVID-19. Slide 12 sets out our development and construction targets for 2020. That includes building 2 wind projects. As I mentioned earlier, we finished our Cardinal Wind project on schedule and within the US dollar budget range. After commercial operations started up, we received $221 million in net tax equity financing from two US financial institutions.

Brian Vaasjo

executive
#13

Cardinal Point is now running under a 12-year PPA covering 85% of what it produces. Our second wind project in construction, Whitla 2, is staying on budget and on track for a 2021 COD. For growth, we aim each year to commit $500 million in capital, and our progress on that measure includes the recent purchase of Buckthorn Wind in Texas, which has a weighted average contract life of 15 years remaining. As I close, I'd like to emphasize Capital Power's investment thesis and restate that the long-term forces driving our business remain resilient. Our young fleet, with an average age of 14 years, forms the base — we keep pushing it to show solid operational results while we keep optimizing assets to improve operations and efficiency. Our portfolio is heavily contracted and diversified across geography and fuel type. The business produces robust cash flows, among them over $300 million of discretionary cash flow for 2020. With our two rating agencies, S&P and DBRS, we are dedicated to preserving our investment grade credit rating. Growth for us centers on putting money into emission-free renewables and essential natural gas generation. On sustainability, our objectives include transitioning Genesee to natural gas and investing in carbon capture and utilization.

Brian Vaasjo

executive
#14

All told, our goal is to reach carbon neutrality by 2050 or sooner. Randy, I'll hand the call back to you now.

Randy Mah

executive
#15

All right, thank you, Brian. Anastasia, we can begin the Q&A portion now.

Operator

operator
#16

Thanks. At this point we're going to open things up for questions. <<operator_script>> The first one is from Maurice Choy at RBC Capital Markets. Your line is open.

Maurice Choy

analyst
#17

Thanks, and good morning. My first question has to do with where the G 4 and G 5 sit. I suppose what I'm asking is, why decide this at this point instead of simply holding off and watching how things develop? To put it another way, what has shifted in your underlying pieces?

Brian Vaasjo

executive
#18

I mean, obviously, you know, G4 and G5 involve two partners — us and ENMAX — and, you know, the way we've described the status is that it's been sitting on the shelf, fully permitted, and if the province ever had a very rapid, immediate need for generation, it would be there and available. And our timeframe for implementing it, you know, kept getting pushed out further and further, you know, with the outlook for power in the province. The other thing that factors in is that, you know, as the fleet has evolved, then the market has evolved, and it's turned out that for Capital Power, a better choice for us right now when it comes to deploying capital in the Alberta market would actually be repowering our existing units rather than building additional units. So, again, lots has happened since, you know, the initiation of Genesee 4 and 5, and it's a solution that no longer fits the market.

Maurice Choy

analyst
#19

And I suppose that connects to the way you're now seeing things and what you're aiming toward, which of course is still a merchant project as it currently stands?

Brian Vaasjo

executive
#20

Nope, nope — that really has nothing to do with that project.

Maurice Choy

analyst
#21

Alright. My second question is about Decatur. Obviously, the most recent update we received was that talks were still continuing — is there any news on that too? Could you go into more detail about the modified outage that took place at the plant?

Brian Vaasjo

executive
#22

Regarding where things stand with Decatur, what has occurred is that COVID-19 has considerably affected how responsive the counterparty has been, given the activity levels they would normally have had. So the process has been slowed, but I'm glad to report that as of today, what remains is minor legal matters being exchanged back and forth—though the pace of those exchanges has clearly diminished—and we remain very hopeful and expect a resolution to arrive in the relatively near future. As for Decatur, owing to the matter of utilizing foreign expertise at times—or expertise not based in North America—along with the fact that we might have needed to relocate the rotor to a facility, a different facility rather than performing the work on site, we ultimately reached the decision that doing so was too risky at this juncture, could readily be postponed, and the bulk of the outage could still proceed. That is what we have done. And the outages have proceeded very well and are nearing completion as we speak.

Maurice Choy

analyst
#23

Thanks — I really appreciate it.

Operator

operator
#24

David Quezada from Raymond James has our next question. You may proceed.

David Quezada

analyst
#25

Thanks. Good morning, all. For my first question, I'd just like maybe some of your thinking on the hedging strategy for 2021. In the past, I know you've said that you're confident in the market's fundamentals, and that's what led to the smaller hedge position. I'm wondering whether your views on that have changed at all?

Bryan DeNeve

executive
#26

Absolutely — with the drop in oil prices, we've updated what we expect for 2021. Before that decline, our projection was that Alberta power prices would exceed $60 per megawatt hour in 2021. Much of that came from the many outages occurring as companies pursue added gas-fired generation capability at their units. Given lower oil demand, plus a solar recovery anticipated across '21 and '22, we see 2021 as roughly 400 megawatts to 500 megawatts of reduced demand in the Alberta market, and that has cut our projections by about $7 per megawatt hour for the year. The effect is that we're now more or less aligned with current forward prices in the Alberta market. So if opportunities come up, we would expect to grow our hedged position in that year.

David Quezada

analyst
#27

All right, thanks a lot. That really helped. Then the one remaining thing I wanted to ask about is the $500 million in committed growth capital you have. Are you still feeling confident that things are on schedule with the Buckthorn investment, and perhaps you could offer a bit of general color — I’m not sure whether you can speak to how the opportunity set looks at present?

Brian Vaasjo

executive
#28

Yeah, of course, we still have prospects we're chasing when it comes to growing the renewables business, and we remain hopeful that some of those will come together over the course of this year. So you'll see additional investment on that front. On the mid-life natural gas side, essentially COVID-19 brought that deal market to a halt almost instantly. We are picking up some signals, though, that opportunities will soon start appearing again, and there will likely be a substantial volume of them available in the market. And once more, we aren't under any obligation to deploy capital, and we'll only commit to those assets and prospects that still make sense for Capital Power.

David Quezada

analyst
#29

All right, that’s helpful context — thanks. I’ll rejoin the queue.

Operator

operator
#30

Patrick Kenny from National Bank Financial has the next question — go ahead, please.

Patrick Kenny

analyst
#31

Morning, everyone — thanks for the financial guidance on the Buckthorn acquisition. I was just hoping you could confirm what your internal IRR expectations are for this deal, perhaps on both an unlevered and a levered basis? And then, how would those returns stack up against, say, Cardinal and Whitla 1?

Bryan DeNeve

executive
#32

So yes, for Buckthorn the levered returns we're expecting would land in that 10% to 11% range on a levered basis. And that aligns with what we're anticipating for Cardinal Point as well as Whitla 1.

Patrick Kenny

analyst
#33

All right, thanks. Now, regarding that Q2 turnaround sliding into 2021, does that affect when we’ll hit 100% dual-fuel capability at all three Genesee units? And does it have any effect on the AFFO increase, which I think was around $20 million for 2021?

Brian Vaasjo

executive
#34

So let me address the — shifting Genesee 2 into 2021 still, you know, aligns with what we've said about having natural gas capability across all three units, you know, by 2021. Now, can Bryan just comment on how that affects AFFO?

Bryan DeNeve

executive
#35

Yes, absolutely — the increase we expected on the AFFO side is a bit smaller at this point. What's behind that is natural gas prices rising in Western Canada. As oil output has fallen, that has had a knock-on effect of pushing April prices higher. So to be clear, we aren't planning to consume as much natural gas in 2021 as we previously expected. On the other hand, those higher natural gas prices work in our favor in other respects, for example by exerting some upward pressure on power prices in Alberta. But getting to what you asked specifically, Pat, there will definitely be some downward pressure on that $20 million figure we mentioned before.

Patrick Kenny

analyst
#36

Understood, thanks. And Bryan, you noted that DBRS reaffirmed the credit rating. I was just wondering whether we could get an update on any discussions you've had with S&P recently? Is the stable outlook currently under review or not, given Alberta's economic condition and in light of your upcoming debt maturity in the fall — and maybe just how you're thinking about keeping some dry powder into the back half of 2020 and into 2021 given the open position there. You know, just maybe a general comment on how you're thinking about allocating free cash flow for the remainder of the year between M&A, debt repayment, and CIB activity and so on?

Bryan DeNeve

executive
#37

Okay, so regarding S&P, we usually get in touch with them around June. We expect to do that again this year. They haven’t given any signal that they’re worried about where we stand financially when it comes to an investment grade credit rating. Pat, I can say that our forecasts for the rest of this year and for next year show we’ll keep hitting those credit measures S&P wants us to maintain for investment grade. So that’s not a concern for us. On capital allocation, like I said, we still expect to produce more than $300 million in discretionary cash flow for 2020. Some of that, naturally, has gone toward growth work we’ve been doing and the continued development of Whitla — sorry, the Cardinal Point project. We’ll soon begin reviewing capital costs for Whitla 2. As usual, we’re looking at the remainder of the year at this point, and we’re not certain we’ll need to tap the debt market given our positive cash flow position — that’s something we’ll keep an eye on and assess as the year goes on. Regarding allocation, M&A activity, if the right opportunity arose and was a strong fit that helped from a casual position, it’s something we’d consider, but certainly we do have development spending still underway here with construction of Whitla 2.

Patrick Kenny

analyst
#38

Thanks, that's great. This is my last one, guys. I didn't really see much of an update on C2CNT. Maybe I missed it, but could you comment on how this pandemic has affected the progress over at C2CNT, if at all? And also, maybe what milestones we could watch for through the back half of 2020 as it relates to the Genesee carbon conversion center?

Brian Vaasjo

executive
#39

Sure. At C2CNT, as you remember, it's involved in the carbon XPRIZE, and it's a collection of stakeholders working with emissions coming from the Shepard facility. One of the earliest closures in the province happened there — and clearly, since a provincial entity operates it, that site was completely shut down. The C2CNT Group managed to relocate a good portion of their operations into a warehouse and keep going with more of the fabrication work and some of the technology development, though this has definitely made it harder for them to keep advancing at the same rate. Along those same lines, the XPRIZE schedule has shifted later too. So what I'd say has basically occurred is something of a pause — even though substantial development is still underway — but looking at the whole timeline, I'd put it this way: ultimately, the pandemic will likely have added roughly a quarter to the timing. Therefore, we should keep expecting that we'll press ahead with the Genesee carbon conversion center, and we do anticipate it being constructed and hitting COD at some point next year.

Brian Vaasjo

executive
#40

That said, the entire timeline has likely shifted by roughly a quarter. And at this point, you shouldn't count on any additional postponements.

Patrick Kenny

analyst
#41

Okay, thanks for that update. I won’t push further on it. Thank you, everyone.

Operator

operator
#42

Mark Jarvi from CIBC World Markets has the next question. The line is yours.

Mark Jarvi

analyst
#43

Morning, everyone. I'd like to return to what we discussed regarding capital allocation and perhaps sharpen a few of the answers about how we use cash—specifically, whether you'd prefer to keep somewhat greater liquidity at present, given the uncertainty that lies ahead, and how willing you are to be active with the buyback at today's levels?

Bryan DeNeve

executive
#44

So at this point, by and large, that surplus cash is going toward debt repayment. And naturally, there's some development spending on Whitla 2. As I said, our credit metrics leave us in good shape, though we certainly want to be careful about keeping them there, so near-term we wouldn't see any share buybacks happening. That positive cash flow, we'd see it going to paying down the credit lines and funding development activity.

Mark Jarvi

analyst
#45

All right, that’s clear. Then just your remarks about the hedges, and even what you expect power prices to settle at in 2021. The fact that you didn’t add much more to the 2021 hedges—is that simply because there isn’t liquidity in the forward market?

Bryan DeNeve

executive
#46

Right now, there really hasn’t been much liquidity in the forward market lately. That said, we do anticipate that liquidity will begin to build up. Specifically, as we move toward roughly the August-September period, at that point the regulated rate option that providers to that service begin entering the market seeking hedging. So that is where we expect liquidity to rise. In addition, I think as we emerge from COVID-19 and the Alberta market reopens, that will likewise give support to liquidity. So since we now see alignment between forward prices and our expectations, we would expect that hedging percentage to go up as we progress through the year.

Mark Jarvi

analyst
#47

Alright. Then you offered your remark about where you felt demand perhaps didn't materialize here. What do you guys believe will ultimately occur regarding other parties' intentions for new supply, such as the Cascade project, which is fairly large, or some of the cogen items? My sense is all of that has been delayed or pushed out, or do you have any concerns that people will keep moving forward with adding new capacity here?

Bryan DeNeve

executive
#48

No, you know, we certainly saw Suncor's announcement, and at a minimum they've pushed that project out by two years, which takes it to at least the end of 2025, if not beyond. You know, we would expect other development projects will definitely get deferred, delayed or if not, outright, just cancelled given the environment. You know, the one thing that we see is a real positive for the Alberta market as we move into the lower demand as compared to what we saw happened in 2015, is the supply side will be a lot more responsive. So yeah, to those growth projects we see those we expect will be deferred, if not cancelled, but also all the PPAs will have expired at the end of this year. So all the output in the Alberta market will be in the hands of commercial entities which will result in supply side response to a much greater degree than what we would have seen in 2015, which will support power prices in the face of the lower demand we're seeing.

Mark Jarvi

analyst
#49

Alright, and one final question about that long-term service agreement covering the Vestas turbines. How does it roll out, you know, from the top through the period between 2021 and 2023? Is that a gradual rollout with incremental pickup each year, and is there any other color you can provide on how those savings come in?

Bryan DeNeve

executive
#50

So a fair way to think about it is that it would taper off at an even pace across those years. Broadly speaking, we've got our renewal dates spread out in a staggered pattern, and the shape of it would come out roughly linear.

Mark Jarvi

analyst
#51

All right, that's excellent. Thank you, everyone.

Operator

operator
#52

The following question is from Robert Hope at Scotiabank. Go ahead, please.

Robert Hope

analyst
#53

Hi, everybody. I’ve got a single question. I’m just hoping to understand how you view the remainder of 2020, given a scenario in which oil sands curtailments might occur. What’s your expectation for how behind the fence generation would react to that? Is it possible that this could serve as one area that helps bring the market there into balance?

Bryan DeNeve

executive
#54

Yeah, that's our view. For sure, a few cogen units have scaled back — part of that reflects maintenance, though we think another portion stems from lower output. So yes, we see that as one more factor underpinning our market pricing going forward.

Robert Hope

analyst
#55

Also, you mentioned your take on 2021 pricing, which is based on the forward curve. How does 2020 shape up for the remainder of the year?

Bryan DeNeve

executive
#56

Right, so 2020 has settled out a bit under $50 per megawatt hour. For us, though, that doesn't move the needle much, since more than 90% of our baseload generation is hedged. One point I'd make — and this ties back to an earlier question — is that when we look past 2021 toward ’22 and ‘23, we do expect Alberta power prices to keep strengthening, and that's of course tied to the Suncor cogen having been pushed out, but we think other supply additions will get deferred as well. So even though power prices have softened for ‘21, we do see a strong outlook for ‘22 and ‘23.

Robert Hope

analyst
#57

Thanks for the extra detail — I appreciate that.

Operator

operator
#58

Ben Pham from BMO Capital Markets has our next question. Go right ahead.

Ben Pham

analyst
#59

Hello, thank you. Good morning. Regarding what you said about how strong power prices were in 2023, could you share your view on where you believe the long-term Alberta power price ought to sit? Has that shifted since what you presented at Investor Day?

Bryan DeNeve

executive
#60

No, it would be about the same, maybe a touch higher. So as natural gas prices strengthen, that creates upward pressure on how we see a long-run price for the Alberta power market. But still not meaningfully different from what we discussed at Investor Day.

Ben Pham

analyst
#61

All right. So if that holds true—and it sounds like part of this is also supply driven, with some of your competition involved—when you look at Genesee 4 and 5, it seems like your burn costs were probably fairly low. So I'm a bit surprised, given your earlier comments to Maurice, that you're not proceeding. So it sounds like FTE <<inaudible>> willing to honor the CapEx and there is no upfront payment near-term, then it sounds like your partner is more the one driving this decision?

Bryan DeNeve

executive
#62

My take is that this is likely more a result of what Brian Vaasjo brought up. A different setup exists that is more logical than separate combined cycle plants, and that was the technology we had been considering for Genesee 4 and 5. As a result, we have put considerably more effort into repowering and what that might involve. So, at that location, repowering one of the units already there — which naturally would make use of the steam turbine already in place and would make use of the generators already in place — that is a setup we now see as more logical than separate combined cycle units.

Ben Pham

analyst
#63

Alright, alright. And do you figure ENMAX might possibly return as a purchaser of that power down the line? Would you feel fine going spot if you were to bring it back in another shape?

Bryan DeNeve

executive
#64

I'll hand that question to Brian.

Brian Vaasjo

executive
#65

So, just so you're aware, if we get to the point of deciding to repower one of the units, we would certainly be seeking off-takers. My sense is that it probably wouldn't be anything beyond what you'd typically see in the market. We don't think ENMAX would necessarily be interested in taking part in the project or heading in that direction. And again, that's perhaps something better directed to ENMAX as a question, but for Capital Power, repowering one of its units is clearly the stronger technical solution and the more market-responsive one today. So it simply became a fact that the answer sitting on the shelf — the no-cost option for carrying it — reached a point where, if it were needed, it wouldn't make sense to pull the trigger on that project regardless.

Ben Pham

analyst
#66

All right. And regarding those long-term service agreements, you're off on that. Did you guys examine any process for bringing some of that work in-house?

Bryan DeNeve

executive
#67

Right. So we put in a fair amount of effort behind the scenes looking at another option where we'd handle things ourselves — self-managing or self-performing — at our renewable facilities. And, you know, we've noticed newcomers to North America who are ready to supply those kinds of services as an alternative to the original equipment manufacturer. So we were examining those other choices closely and had in fact worked out price points that we believed we could shift to and deliver on. What ended up happening was that Vestas was actually capable of hitting those price points while still offering full service. So from our standpoint, it became — we had a solid read on that, but Vestas managed to raise its game, so we're genuinely pleased with where we've ended up with Vestas on that front.

Ben Pham

analyst
#68

Okay, seems like you got a solid deal there. Thanks, everyone.

Operator

operator
#69

The following question is from Andrew Kuske at Credit Suisse. You have the floor.

Andrew Kuske

analyst
#70

Thanks. Morning, everyone. Q1 was clearly a choppy quarter. That said, could you perhaps walk us through how your optimization approaches shifted as the quarter went on, and also explain how you are setting yourselves up for the rest of the year?

Brian Vaasjo

executive
#71

Regarding optimization efforts, much of what we did came through outages — the Genesee 2 outage, the work at Decatur in Arlington — and Arlington has now been completed, and we're very pleased with what was done there. As I said before, we adjusted the Decatur outage purely from a risk-management standpoint. That piece will be picked up later on, so the impact really isn't significant. The biggest item, naturally, is the rescheduling of Genesee 2, given the upfront work that had to happen at the plant and the fact that foreign expertise would need to be brought into Canada, and so forth. At one stage we shifted it, and we were working toward possibly moving it to the fall, and ultimately it went into next year, since it kept being impractical and not a risk worth taking. So as far as the overall program goes, it keeps moving ahead. Nothing has changed — in fact, because of COVID-19 and by examining various parts of the business, we've actually sped up some of the developments we had intended to pursue.

Brian Vaasjo

executive
#72

So for instance, you know, I made the comment that, you know, we're now able to run, you know, our simple cycle units entirely from laptops, which is something we were working toward and we had actually, you know, figured out in the technology and made some choices, but that would have been happening over, you know, a couple of years — we just sped it up. So there are a number of things like that from a development standpoint, that — yeah, and optimization that we simply pushed forward very fast, not only on the facility side, but you know, on the, say, support services side too.

Andrew Kuske

analyst
#73

Alright, that's useful. Then I believe the figure mentioned before was that your expectations and projections pointed to 450 megawatt hours, which basically represents demand destruction under current conditions for 2020. So how do you view coal's role in setting the marginal price in the market, both now and in upcoming years — for instance, what share of time has that actually shifted within your modeling forecasts?

Bryan DeNeve

executive
#74

Yeah, for the rest of this year, we'd see the coal units on the margin — often we weren't in a position to give a specific percentage, but that would certainly hold true. Now, as we get into 2021, of course, those units are going to shift to dual-fuel or be converted 100% to natural gas. So we'll certainly see somewhat of a different dynamic in how those units respond; it will really hinge on, you know, what happens with carbon pricing and natural gas prices.

Andrew Kuske

analyst
#75

And then last from me — at this point you're not seeing any shift in the carbon pricing the federal government has set out, is that right?

Bryan DeNeve

executive
#76

Actually, that isn’t the case.

Andrew Kuske

analyst
#77

All right, that was excellent. I appreciate it.

Operator

operator
#78

The next person to ask a question is John Mould of TD Securities. You have the floor.

John Mould

analyst
#79

Good morning. I have a couple of questions about the timing of dual-fuel work at Genesee. Now that the G 2 outage has shifted to 2021, could you clarify the current planned dates for each outage that enables 100% dual-fuel operations at each of the units? And can you confirm what dual-fuel capability levels you expect for the rest of 2020, given that G 2 had to be deferred, but after the Pembina-Keephills pipeline is finished?

Bryan DeNeve

executive
#80

Yes, so through 2020 we have of course carried on with linking up additional gas capacity at the Genesee site, and that line is now finished. With certain upgrades we have put in place, we in fact expect a somewhat greater share of gas-fired capability over the rest of 2020 — always in the vicinity of 40%, up from 30%. During 2021, every one of those conversions would still be slated to bring the units to the point of running at 100% firing on natural gas.

John Mould

analyst
#81

Okay. And do those get distributed across the rest of the year instead of being concentrated toward the usual Q2-type outage for the season?

Bryan DeNeve

executive
#82

I mean, if you look at the outage plan, that should give you a pretty good sense of it. We’ve got a couple of those units in Q2, and one of them is set for the fall in 2021.

John Mould

analyst
#83

Alright, everything else I wanted to ask has been covered. Thank you very much.

Operator

operator
#84

We now take a question from Naji Baydoun at Industrial Alliance Securities. Your line is open.

Naji Baydoun

analyst
#85

Good morning, hi. I’ve just got a single brief question. Could you share your most recent views and expectations regarding the ISO’s review process in Ontario, and how that could affect your portfolio in the province from here on?

Bryan DeNeve

executive
#86

So the government there has paused its review of how the capacity market is designed, and they're certainly still examining bilateral contracting approaches. But of course, all of our thermal assets in Ontario are hedged through to the end of the next decade. So near-term adjustments to that market generally won't have an impact on our financial position for those units. The longer term, though, is something we'll be involved in and keeping an eye on as the discussion about Ontario market design carries on. But again, that isn't something that really has a financial effect on us until the end of the next decade, or the end of this decade, I suppose.

Naji Baydoun

analyst
#87

I appreciate that.

Operator

operator
#88

That wraps up the question-and-answer portion. I'll now hand the conference back to Mr. Randy Mah for any closing remarks he'd like to make.

Randy Mah

executive
#89

All right, seeing no additional questions, that brings us to the end of the call. Thanks once more for being with us today and for the interest you've shown in Capital Power. Keep well, and have a good day, everyone.

Operator

operator
#90

That brings us to the end of the conference call for today. Your lines can now be disconnected. We appreciate everyone for joining, and we hope the rest of your day is a pleasant one.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Capital Power Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Capital Power Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capital Power Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.