Capital Power Corporation (CPX) Earnings Call Transcript & Summary

November 2, 2020

Toronto Stock Exchange CA Utilities Independent Power and Renewable Electricity Producers earnings 58 min

Earnings Call Speaker Segments

Operator

operator
#1

Good morning, everyone, and thanks for joining Capital Power's conference call covering our Third Quarter 2020 results. Right now, everyone attending is in listen-only mode. After the presentation wraps up, we'll open the line for questions. Today is November 2, 2020, and this call is being recorded. At this point I'll hand things over to Mr. Randy Mah, our Director of Investor Relations. Please go ahead, sir.

Randy Mah

executive
#2

Good morning, everyone, and thanks for being with us today as we go over Capital Power's results for the third quarter of 2020, which came out earlier this morning. You can find our Q3 report along with the presentation for this conference call on our website, capitalpower.com. With me today are Brian Vaasjo, our President and CEO, and Sandra Haskins, Senior Vice President Finance and CFO. We'll begin with some opening remarks, and after that we'll open the lines so you can ask your questions. Before we get started, I want to remind everyone that certain statements made on this call about future events are forward-looking in nature and rest on certain assumptions and analysis made by the company. Actual results could differ materially from what the company expects because of various risks and uncertainties associated with our business. Please refer to the cautionary statement on forward-looking information on Slide number 2. In today's discussion, we will be referring to various non-GAAP financial measures as noted on Slide 3. These measures are not defined financial measures according to GAAP and do not have standardized meanings prescribed by GAAP and therefore are unlikely to be comparable to similar measures used by other enterprises. These measures are provided to complement the GAAP measures which are provided in the analysis of the company's results from management's perspective.

Randy Mah

executive
#3

You can find reconciliations showing how these non-GAAP financial measures compare to their closest GAAP counterparts in the MD&A for the second quarter of 2020. At this point I'll hand things over to Brian Vaasjo, who will begin his remarks on Slide 4.

Brian Vaasjo

executive
#4

Thanks, Randy, and good morning. I'll begin with the quarter's highlights. First, I want to acknowledge the work of our employees at our facilities and those still working remotely through the COVID-19 pandemic, whose efforts helped deliver strong operating performance and financial results consistent with management's expectations. Our outlook hasn't materially changed, so we're keeping the 2020 financial guidance we announced at our Investor Day last December. We're continuing to carry out our growth strategy, with ongoing progress in renewables and sustainability. In October, we signed a 20-year PPA covering three new solar projects in North Carolina, supporting our goal of achieving net carbon neutrality before 2050, which I'll cover shortly. We've raised our investment in C2CNT from 9% to 25% after our due diligence showed that C2CNT technology consistently produces quality carbon nanotubes and can be scaled. C2CNT is a strategic investment that generates environmental benefits consistent with our sustainability strategy. We hold an equity option to raise our equity investment further, to 40%, at the end of 2020. Three initiatives were completed that give the company financial stability. We completed the Canadian market's longest-dated, lowest-coupon transaction when we raised 350 million through a highly successful 12-year medium term note offering at very attractive interest rates of 3.147%.

Brian Vaasjo

executive
#5

This MTN deal, which went through successfully, shows the market has faith in the quality of our credit and in our strategy for the long haul. Back in August, we signed a 10-year tolling agreement covering Decatur Energy Centre in Alabama — something that backs both our strategy for gas assets in mid-life and our belief that natural gas generation, together with carbon capture, utilization and storage technologies, will keep playing an essential role. We also brought down our wind service and maintenance costs by an estimated 26% relative to our current agreements by finishing the shift to 10-year long term service agreements with Vestas covering maintenance of our Vestas equipped wind facilities, which add up to over 1200 megawatts of capacity. Moving to Slide 5, as I mentioned, we have extended the tolling agreement at our Decatur facility by an additional 10 years, so it now runs out in December 2032. Since we bought Decatur in 2017, we began upgrading the combustion turbines so as to boost capacity, cut emissions, enhance the heat rate and keep reliability up. Through the upgrades on two of the three combustion turbines, we have added 60 megawatts of capacity. Next year the third combustion turbine gets upgraded, which will add another 30 megawatts of capacity. Under the tolling agreement extension, we are paid for 34 megawatts of additional capacity right away and for up to an additional 79 megawatts of capacity in 2021.

Brian Vaasjo

executive
#6

The added financial benefit we anticipate from extending this contract is going to deliver meaningful value both across the remaining portion of the existing agreement, which runs out in 2022, and throughout the 10-year extension period. At the time we bought Decatur, our view was that the likelihood of re-contracting was high, given how often it had been re-contracted previously and the region's requirement for that facility. This 10-year PPA expansion confirms that our acquisition approach — buying mid-life contracted natural gas assets with an improving contracting outlook and worth past the current contract term — is the right one. Our focus is on the correct assets, in the correct markets, delivering the correct service. Moving to Slide 6, growing our renewable assets is a central element of our strategy and of achieving our objective of net carbon neutrality before 2050. We keep proving how competitive we are in renewable development projects, and in October we executed 20-year PPAs for three new solar development projects in North Carolina with Duke Energy Carolinas. Those projects are Hornet Solar, Hunter's Cove Solar and Bear Branch solar, totaling 160 megawatts of combined capacity. Construction on all three is expected to get underway in late 2021 or early 2022, at an estimated capital cost of 260 million, with commercial operations beginning in the fourth quarter of 2022.

Brian Vaasjo

executive
#7

Taken together, those 3 solar projects should produce, on average across the first 5 years, 23 million in adjusted EBITDA each year along with 5 million of AFFO annually. Our contracted cash flows are made stronger by these 20-year contracts, and the average remaining life of the facilities we have under contract will rise overall. At present, 6 renewable projects are either in advanced development or being built, amounting to roughly 350 megawatts. Renewables will account for 23% of our capacity by the end of 2022, up from 16% at the close of 2019. Sandra, I'll hand the call to you now.

Sandra Haskins

executive
#8

Thanks Brian. I'll walk through the financial results for our third quarter, beginning on Slide 7. For the third quarter, revenues and other income came in at 453 million, a decline of 12% versus the third quarter of 2019, driven primarily by unrealized changes in the fair value of commodity derivatives and emission credits, along with the lower Arlington Valley total contract. Adjusted EBITDA stood at 284 million, unchanged from a year earlier. The contributions from Cardinal Point, Whitla Wind 1, and Buckthorn Wind, together with strong trading performance, were offset by the Arlington Valley toll decrease. Normalized earnings came to $0.66 per share, a rise of 10% from $0.60 per share in the third quarter of 2019. AFFO generated was $221 million, a touch below the $225 million recorded in last year's third quarter, and AFFO per share of $2.10 was unchanged year-over-year. On Slide 8, you can see how our financial performance compares on a year-to-date basis with the same period in 2019. Revenues and other income reached 1.4 billion, up 11% year-over-year, largely on stronger portfolio optimization performance, contributions from renewable additions, and additional months of operations at Goreway. Adjusted EBITDA was 735 million, up 9% versus 2019, mainly reflecting the Goreway acquisition and renewable additions, partly offset by the Arlington Valley toll decrease.

Sandra Haskins

executive
#9

Adjusted earnings came in at $1.09 per share, which represents a 4% increase versus the prior year. We're still producing robust AFFO, with 436 million generated during the first nine months of the year, marking a 2% rise year-over-year. On a per-share basis, AFFO stood at $4.14, 1% above the comparable stretch in 2019. If you'll move to Side 9, broadly speaking, our third quarter financial performance matched what we had anticipated. The trading desk keeps delivering value by securing real-life power prices that exceed spot power prices. During the third quarter, the average realized power price came in at $59 per megawatt hour, which was 34% above the average spot price of $44 per megawatt hour. The softer spot price in Q3 mirrored weaker market demand stemming from declines in oil and gas output along with the effects of COVID-19, plus gentler pricing driven by a steady baseload supply, robust hydro and wind generation, and mild temperatures. Regarding the Line Loss Rule proceeding, we've booked a provision of 18 million so far. We have now gotten the first of three invoices, and that initial invoice must be paid by the close of 2020 and will affect AFFO by $6 million. Payment on the second and third invoices falls due during the first half of 2021.

Sandra Haskins

executive
#10

I'll go into more detail on the Alberta power market in relation to the COVID-19 pandemic, as you can see on Slide 10. This chart presents a year-over-year comparison of internal load demand, calculated using actual 30-day rolling averages, so it has not been adjusted for weather or other factors. For instance, extreme cold temperatures in Alberta drove the higher demand seen in February 2019. As the chart illustrates, COVID-19 was declared a pandemic on March 11. After that, Alberta power demand began falling in early April, in the wake of various shutdowns across the province, and kept falling through the month of May. Power demand's biggest year-over-year drop came in at roughly 7%. As the economy reopened, demand began to recover in June and narrowed the gap toward a year-over-year decline of approximately 2% in October. Assuming the current pace of recovery holds, we anticipate demand returning to pre-COVID-19 levels late in 2021, and any additional demand disruptions would be met with a disciplined supply response. Moving to Slide 11, I'll give an update on where our commercial portfolio stands. For the rest of 2020, our baseload generation is substantially hedged. As of the end of September, we are 13% hedged for 2021, at an average contract price in the high $50 per megawatt hour range.

Sandra Haskins

executive
#11

Our hedge position for 2021 being smaller stems from liquidity that is below normal, plus the disconnect between how we fundamentally see pricing and where forwards sit. The thin liquidity for next year ties to uncertainty caused by the Alberta Balancing Pool PPAs expiring and the related shift of market share offer control over to commercial entities. Also at play are the ongoing effects of COVID-19 and the drop in oil prices on demand, along with carbon pricing. Given weak liquidity, forward prices have been sluggish to react. That said, after the quarter closed, liquidity has begun to pick up and forwards are getting stronger. Board prices right now for 2021 sit near $55 per megawatt hour versus $51 across Q3. So should forwards keep climbing, we'd step up hedging in the fourth quarter, though the share hedged as we go into next year is expected to be below where it has sat in recent years. For 2022 and 2023 the figures were 18% and 12%, hedged at an average contract price in the low $50 per megawatt hour range for each of those years. Forward prices today are in the low $50 per megawatt hour for 2022 and 2023 alike. I'll hand the call back to Brian now.

Brian Vaasjo

executive
#12

Thanks, Sandra. On Slide 12, we show how our committed growth capital is progressing. So far this year, six renewable projects have been announced, and together they'll contribute 355 megawatts. That figure covers our purchase of Buckthorn Wind in Texas, completed in April, along with two renewable development projects we're constructing in Alberta — Whitla 3 and Strathmore Solar — plus the three solar projects in North Carolina that I referenced earlier. In total, we've allocated $592 million of growth capital to the renewable sector this year — strong growth and a step toward our objective of achieving net carbon neutrality ahead of 2050. I'll wrap up with how we're tracking against our 2020 annual targets, which appear on Slide 13. Facility availability has averaged 94% over the first nine months, against an annual target of 93%, and since major planned outages are already behind us and the Genesee 2 planned outage has been deferred into 2021, we anticipate average availability will come in a bit above the annual target. Sustaining CapEx stands at 50 million year-to-date. Given the deferral of the Genesee 2 outage, we expect sustaining CapEx to land under the $90 million to $100 million annual target. Adjusted EBITDA is 735 million year-to-date. On our present forecast, 2020 adjusted EBITDA should exceed the midpoint of the 935 million to 985 million target range.

Brian Vaasjo

executive
#13

Through today's date, we produced $436 million of AFFO, versus the target range of $500 million to $550 million. Barring effects from the Line Loss Rule proceeding, we remain positioned to land close to the midpoint of that AFFO range. As we noted earlier, growth this year has been outstanding: $592 million of committed capital, which is above our yearly growth capital target of $500 million. Lastly, we have set construction targets for the Cardinal Point and Whitla 2 projects. The Cardinal wind project was finished on schedule in March and came in within the US dollar budget range. As for Whitla 2, it is presently on budget and on schedule for commercial operation in Q4 2021. To sum up, it was a robust quarter for operations and financial results, thanks to the Decatur Centre 10-year PPA extension, along with excellent strategic growth in renewable development projects. I will now hand the call back to Randy.

Randy Mah

executive
#14

Okay, thank you Bryan. And Felicia, we can begin taking questions now.

Operator

operator
#15

We're moving into the Q&A portion now. <<operator_script>> Our initial question is from David Quezada at Raymond James. You have the floor.

David Quezada

analyst
#16

Thanks. Morning, all. My first question is about that Decatur contract extension. I was just wondering whether you could give us a little perspective on how the terms came out relative to what you'd anticipated when the acquisition happened back in 2017. And any thoughts, I suppose, specifically on what has influenced the returns you expected from that acquisition at the time.

Brian Vaasjo

executive
#17

When we bought the Decatur facility, we definitely anticipated re-contracting it, and from that standpoint, it worked out as expected. And on that particular point, even though we had anticipated and observed a chance to grow the facility's capacity and possibly raise the — or lower the heat rate, we weren't exactly certain what result to expect. So it was flagged as a possibility. As you can imagine, we've invested a substantial amount of capital in that facility. And what I can tell you is that, on the whole, the return on our current investment, together with the added facilities, aligns with our usual expectation for project returns. But its nature and form differ from what we would have anticipated when we made the acquisition.

David Quezada

analyst
#18

All right, thanks for that. Then it would be helpful to get your wider perspective on additional natural gas, mid-contract-life M&A. I know you've noted during the last couple of quarters that activity in that market has been softer — has any of that returned, and I'm curious what you think about where things stand there.

Brian Vaasjo

executive
#19

Relative to earlier years and to what we had anticipated, the market is still fairly sluggish, but we keep hearing about quite a few opportunities that have not yet reached the market. So we will see how things develop. As for our perspective, as I mentioned earlier in the presentation, the question comes down to whether an asset opportunity exists that makes sense in markets that work for us and where one can take a view on long-term contracted capability. Another very important factor is whether that specific power facility has characteristics that are either unique within the market or very deep, in the sense of whether there is a stack of facilities delivering that same service, since we do expect natural gas generation as it stands today, from the State Energy perspective to the client, to shift somewhat over time. And certainly, we do not want to own one of those facilities that is merely producing electrons, because at some point it will not be re-contracted. So we keep examining a number of markets and expect various opportunities to come forward. So do expect further mid-life natural gas acquisitions going forward.

David Quezada

analyst
#20

Thanks a lot for that context. I'll rejoin the queue.

Operator

operator
#21

Patrick Kenny from National Bank Financial has the next question. Go right ahead.

Patrick Kenny

analyst
#22

Morning, everyone. Brian, I noticed the release didn’t mention your application to repower Genesee 1 and 2, so perhaps you could share your thinking on how you plan to proceed with construction by next summer. And on adding another cold 600 megawatts of supply into the market, particularly given that Cascade is expected to come on by 2023 as well. Not to mention some course cogent, possibly a couple of years later. And any preliminary capital cost estimates for the project would be great.

Brian Vaasjo

executive
#23

As you're aware, the initial thing we need to do to advance a project of this kind is proceed with permitting, and that's already been completed. We keep working on the project and refining the capital costs. That said, we're getting substantially nearer to having every piece required for a project so we can do things such as request Board approval and publicly announce that it's going ahead. When we consider the market outlook, capacity is entering the market, though we anticipate a meaningful supply response tied to new natural gas units being added. Regarding the assets we're examining, what I can tell you is that they are highly efficient. We anticipate they will rank as the most efficient available in the market, and their capital cost is quite low because we're using existing facilities. So I'd say you should expect that both units would definitely come in under $1 billion to put in place. Things are going well so far in developing the project, and once more, we truly do expect a supply response in the market, and we'll keep watching closely, and at some point we may very well announce that these two repower ends are proceeding.

Patrick Kenny

analyst
#24

All right, that's quite useful. And what part do you see Genesee playing over the longer term in the province's aim of turning into a top blue hydrogen producer? I realize it's still early days. But perhaps you could simply confirm whether you'll be seeking the 12% capital cost grants that were announced on Friday.

Brian Vaasjo

executive
#25

We're still examining that, along with how it ties to Genesee and what options might exist there. In a repowering scenario, it can definitely make a great deal of sense much sooner. The 2 units we're considering repowering right out of the gate will be 30% carbon ready, and with a fairly small investment of under $10 million per unit, they can reach as much as 95% hydrogen ready. That way we'll be prepared for the moment when the economics and the value support shifting to blue hydrogen or green hydrogen, whichever one happens to be obtainable at competitive pricing.

Patrick Kenny

analyst
#26

Okay, that's great — seems like there's a lot happening at Genesee. So for Sandra, following your recent successful bond refinancing: how do you view accessing the green bond market from here, especially considering some of the recent and, I suppose, planned investments in new renewables? Would you consider green bonds, say, to refinance your 2021s next year?

Sandra Haskins

executive
#27

Appreciate that, Pat. So we're still evaluating green bonds alongside sustainability linked bonds, and we're giving thought to both. And I think as our integrated reporting and our ESG targets keep taking shape, that aligns quite well with our ability to execute on a sustainability linked bond pretty seamlessly. We've had a few conversations about next year's refinancing and whether that might present an opportunity to do it. So we'll keep watching that. We do expect that to be part of our future — whether that's a green bond at the project level or financing through sustainability linked metrics.

Patrick Kenny

analyst
#28

All right, that's helpful. And I recall that in the past you worked through the calculations around realizing the worth of those off-coal payments. Have you revisited that analysis lately, simply to determine whether it could be worthwhile and let you perhaps shut the drip off once more?

Sandra Haskins

executive
#29

That isn't something we've reviewed lately, though I believe our perspective would be the same: there isn't much benefit in crystallizing it. Through the drip, we have substantial internal spending on our existing assets, plus certain development projects. So that simply appeared to be an efficient means of raising equity to finance that. I think we'll keep going with it for the foreseeable future.

Patrick Kenny

analyst
#30

Alright, that's great. I really appreciate all the feedback. So I'll stop there.

Operator

operator
#31

Robert Hope from Scotiabank has the next question. Go right ahead.

Robert Hope

analyst
#32

Morning, everyone. The first question is just about the outlook for the Alberta power market. And we did just see that you raised your overall hedge position there. As we've gone through October with the volatility and the pricing we've seen, are we getting close to your kind of notional view of what 2021 looks like? And overall, is the market behaving the way you'd expect? And is it just the view that the forward markets aren't reflecting the fundamentals?

Sandra Haskins

executive
#33

Yeah, I think our expectation in Q3 was that with the RRO options beginning in September, we'd start seeing liquidity and pricing increase. But through the end of the quarter, that didn't happen. But as you mentioned, in the last couple of weeks we are starting to see prices move forward or upwards. So right now at $55 a megawatt hour, market participants are starting to take a price view. But yeah, we continue to see — we would expect to keep seeing forward movement come more in line with our expectations. So we still think there's a bit of a gap even at 55, but starting to see some momentum in the right direction in Q4.

Robert Hope

analyst
#34

So it sort of seems like your basic take on 2021 is essentially this high 50s figure, is that right?

Sandra Haskins

executive
#35

Broadly speaking, yes, that falls within the range.

Robert Hope

analyst
#36

All right. Then, just below the border, do you have any thoughts on the possibility of extending Southport’s life, given some of the permanent challenges there, or what the strategy is for that unit?

Brian Vaasjo

executive
#37

Looking ahead, for a couple of years we had been examining re-contracting those facilities — both Southport and Roxboro — and there were also other entities in the market potentially looking to buy those assets and use a different kind of fuel, and so on. Unfortunately, neither re-contracting nor selling those assets came to fruition. So our expectation is that next year, those facilities will likely cease operations.

Robert Hope

analyst
#38

Okay, so that covers Roxboro as well, not only Southport?

Brian Vaasjo

executive
#39

You've got that right.

Robert Hope

analyst
#40

Okay, thanks a lot.

Operator

operator
#41

Mark Jarvi from CIBC has the next question. Go right ahead.

Mark Jarvi

analyst
#42

Thanks, and good morning, everyone. For my first question, on the portfolio optimization revenue, could you break out for us how much of that comes from power sales versus how much money in a quarter like this one, with lower generation — did you resell gas at a profit?

Sandra Haskins

executive
#43

So I'd say natural gas optimization came in at roughly $9 million for the quarter, and power optimization would account for the remainder.

Mark Jarvi

analyst
#44

Alright. Turning to gas costs — and I suppose from what you disclosed, you’re substantially hedged, or mostly hedged, on fuel expenses for 2021. Could you offer some sense of where you stand compared with gas prices for 2021 — specifically, how large a cushion you’ve built relative to where the spot market has moved? Then, over the longer term, are you considering lengthening the duration of any gas hedges or procurement?

Sandra Haskins

executive
#45

Our gas purchasing depends on when we convert fuel to gas and on overall gas consumption. For natural gas, we have secured prices for the majority of next year at a level under current forwards, so it remains in that range of about $2 per gigajoule.

Mark Jarvi

analyst
#46

All right, that’s quite useful. Next, I’d like to ask about the solar projects located in the Carolinas. Could you provide a bit of context on how you came to be involved with those projects? At what point did you get in, and, given that competition for renewable projects in the US is obviously intense, when you evaluate these assets, do you intend to hold your equity stakes through to the end of their operating life, or would you consider a partial sell-down in order to improve returns?

Brian Vaasjo

executive
#47

The story with those three solar projects is that Duke Carolina's put out an RFP for 600 megawatts of renewables as a competition. Through some relationships — we're in North Carolina and actually have a solar farm there, so we have some profile at this stage — we partnered with a junior developer who had some projects, and after going through due diligence we concluded that these two projects had a very good probability of moving forward. So starting almost nine months ago, we began working to prepare a bit and put our best foot forward, and we were successful on the three projects that we put forward. Regarding sell down, in our view of the renewables portfolio we have on both sides of the borders, there's significant value there. And at times, whether it's looking for a source of capital, or when we look at optimizing the returns we get from assets, we would certainly consider selling down projects to a lower level of interest. In all likelihood, if we were going in that direction, we'd bundle one or two projects together and have those as a package, because we would again look for more of a strategic purchaser — somebody who obviously, a financial entity that would work with us on a couple of projects and, as we move forward, would be somebody who would be a natural buyer of other interests with low bar.

Brian Vaasjo

executive
#48

I do think that at some point down the road, we'll consider divesting some of our stakes. Again, that would be when capital is needed, or, as you put it, to maximize the returns tied to a specific project.

Mark Jarvi

analyst
#49

Alright, thank you very much, Brian. Moving on to my final question, which returns to what Pat asked regarding Genesee and re-powering: could you remind us of the useful life, or the end-of-life assumption, for conversion as opposed to repowering, and also tell us how much clarity you currently have on useful life?

Brian Vaasjo

executive
#50

When you consider the useful life in connection with repowering, we’re viewing it through a particular lens—perhaps another 20 years, in terms of the economics for that type of facility. That said, I’d want to stress that shifting to hydrogen or carbon capture in the utilization would lengthen that life considerably past the 20 years. So again, in what you might call a status quo world, a 20-year life would be a reasonable economic expectation for us. With dual-fuel, we’d view it as potentially somewhat shorter. But as we’ve noted over the last couple of years, our view is that eventually those units would become repowered facilities at some point, and the question was simply when.

Mark Jarvi

analyst
#51

All right, I appreciate that.

Operator

operator
#52

Our following question is from Andrew Kuske at Credit Suisse. You have the floor.

Andrew Kuske

analyst
#53

Thanks. Good morning. So I’ll start with what’s probably a two-part question, and it really just has to do with natural gas prices going up. How do you see that altering market dynamics as the market transition happens on Jan 1, and then tied to that is simply your capacity to enter into longer-term contracts inside the province?

Sandra Haskins

executive
#54

Regarding the first part of your question, on natural gas prices and the dynamics there: what we've observed through this year as gas has gone higher is simply reduced utilization at our gas facilities. Even so, we expect that at some point price increases will emerge, restoring those spreads and letting us run our plants in a manner closer to how we historically have. As for longer-term natural gas hedging, I'm not sure — Brian, would you like to take that one?

Brian Vaasjo

executive
#55

We have examined longer-dated hedging tied to natural gas. And of course, in a dual-fuel environment, that can complicate things somewhat, since the last thing we want is to simply speculate outright on natural gas prices rather than hedge the gas for what we anticipate our own consumption to be. And we have revisited, periodically, whether there might be some share we could lock in through a long-term hedge arrangement. And our conclusion has been that, at least for now, given market volatility, that strategy does not really work to our advantage. That said, we have extended out two and three years and have been able to hedge meaningful portions of the natural gas demand we expect, and we will keep doing that.

Andrew Kuske

analyst
#56

Alright, that helps. My follow-up really has to do with the renewable valuations we've been seeing in the market. Obviously, it's a very topical subject, and you have a fairly sizable renewable portfolio yourselves. I suppose the question is really aimed at Sandra: do you consider changing how you present your financials so that the embedded value in the company gets highlighted to a much greater degree?

Sandra Haskins

executive
#57

Yeah, that’s a discussion we’ve genuinely had — about whether we begin presenting things in precisely that format. In a few of our presentation decks, we actually do separate EBITDA according to fuel type. So that’s something we’re kind of moving toward, and we’ll give it more thought in our MD&A and other reporting materials as we go forward.

Andrew Kuske

analyst
#58

That's wonderful. I appreciate it.

Operator

operator
#59

Ben Pham from BMO has the next question. You're up.

Ben Pham

analyst
#60

Good morning, and thanks. I had a follow-up question about the repowering of Gen 1 and 2. Obviously, you're working through the public stakeholder process. You're filing an application late this year. I'm wondering, is the plan similar to peers, where you look to layer on some contracts on the powering as reopen to spot and then the second part of it is, is the CapEx you quoted aims at — or is dramatically lower than — with one of your peers and it's almost 30%, 40% lower. So there — it's really just the age of the facility or it your relationships with the suppliers that's driving or is it something else?

Brian Vaasjo

executive
#61

So first off, Ben, when it comes to contracting the facilities, if an opportunity existed to contract them up to some portion, we would definitely look at that. That said, that wouldn't be the foundation on which we'll proceed. On the capital cost side, I think the only thing I can really say is that combining very well-maintained Genesee units with the newest technology produces a unit that's actually very low cost and extremely efficient, and it's kind of some of the pieces we've actually completed. <<inaudible>>, but some very, very creative engineering has gone into our ability to achieve such a low capital cost and to have, I'd say, when all is said and done, outstanding performing units.

Ben Pham

analyst
#62

All right. My next question is probably for Brian or Sandra regarding capital recycling, and please correct me if I'm mistaken — I believe that for the longest time, you perhaps haven't been opposed to recycling, but it may have been more about growing and acquiring in order to evolve. So is it — particularly on the renewables side — is this a subtle shift in high yield capital allocation involving asset sales, is it that the renewable portfolio is now getting larger so you're able to consider that, or is there simply perhaps the need for CapEx such as Gen 1 and 2 as another opportunity that is emerging in the years ahead.

Brian Vaasjo

executive
#63

I'd just like to say that historically, recycling capital by divesting assets has always been something we've examined. We've actually done that a couple of times over the years. And of course, looking ahead, selling assets is definitely something that would be taken into account whenever we're evaluating particular capital requirements. What has served as somewhat of a hurdle during the last couple of years is that when we consider forward EBITDA expectations or expectations regarding AFFO, AFFO per share, selling an asset generally produces a decline as we move forward. So that modest dilution is among the factors that have influenced our choices about recycling capital. But once again, it remains always an option, and certainly with a portfolio of renewable assets that is broadening and deeper, it does make — it does raise the likelihood that at some point we might divest all or a portion of an interest in a facility.

Ben Pham

analyst
#64

And you still hold the view that splitting the renewables business off into a public entity isn't sensible.

Brian Vaasjo

executive
#65

My view is that it's simply too small right now. Market traction would be insufficient, and if you consider how the organization's balance would look, it would be considerably smaller as well, so I believe both would face real difficulty in the market at this stage — you'd definitely require substantial scale before that becomes viable.

Ben Pham

analyst
#66

All right, that's great — thank you. Over to you, Brian.

Operator

operator
#67

The upcoming question is from John Mould at TD Securities. You may proceed.

John Mould

analyst
#68

Good morning. Perhaps to revisit those solar projects in North Carolina — they run roughly 260 million, yet deliver neutral AFFO accretion across the first five years, and plainly carry other advantages, such as 20-year PPAs and expansion of your renewables platform. In choosing whether to move ahead with investments like these, how do you weigh the trade-off between pursuing growth and per-share measures — say, AFFO returns against your hurdle rates, which I recognize you do satisfy on this particular investment — alongside other benefits, for instance lengthening the contract life of your overall portfolio and growing renewables?

Sandra Haskins

executive
#69

Right, so all of those factors definitely get weighed, but as far as the economics go, you're looking at something neutral to slightly positive, and it's still a couple years away — we've got to finish construction and lock in the actual financing on it. So expect roughly 40% tax equity with the full ITCs at 30%, but for the rest of the financing, this is the type of project where bringing in a partner is possible, and that would affect our economics too. So probably the target right now is that it's most likely a few cents accretive on average in the first few years, but neutral at worst — I think we've framed it conservatively in what we've communicated, but we'd weigh the ESG impacts along with the average contract life and the economics of it all as part of that decision.

John Mould

analyst
#70

Alright, thank you for that. Turning to C2CNT, could you give us an update on how the nano-to-production work is progressing, along with Shepard? Also, any news on the concrete testing, and how is the possible start date for building the Carbon Conversion Centre at Genesee taking shape?

Brian Vaasjo

executive
#71

Regarding the situation at the Shepard site, as I mentioned during earlier quarters, COVID and various other factors have generally slowed progress there—not only for us but also for XPRIZE and others. As things stand currently, the facility is ramping up. By ramping up, I mean that physically, components are being installed so it can reach the full production level anticipated. That process is proceeding well. On the cement side, there have been a couple of distinct nanotube developments—specific nanotube advancements—along with methods for dispersing nanotubes in concrete, which have been created and are going through additional testing before a batch is assembled and sent to Lehigh for their testing. So some intermediate testing is occurring at present, and from that standpoint things are going well. Looking ahead again, since everything has been somewhat delayed, I'm not certain when we would actually break ground. However, we expect that at some point during the fourth quarter of next year, we would begin production from the Genesee Carbon Conversion Centre.

John Mould

analyst
#72

All right, thanks. And maybe one final item on geothermal — Alberta's government is working toward establishing a geothermal policy. I'm just curious about your view on what the prospects look like for geothermal power in the province, and whether you'd consider dipping your toe in if the right opportunity came along?

Brian Vaasjo

executive
#73

Geothermal is something we've examined a few times over the past several years, and we recognize that southern Saskatchewan has a fairly solid geothermal regime, and British Columbia definitely holds some promising geothermal prospects. As we understand it, Alberta may have less potential, and much depends on geology, depth, and similar factors. And I suppose, again, having reviewed it a couple of times, we don't see a high probability, though that judgment rested on the technology available at those points, and yes, it is somewhat outdated now. Would we take a look? We would definitely give it consideration. If it proved to be a workable technology and one capable of producing, clearly, renewable energy in substantial volume, then investing in that technology would be worthwhile. You might remember that we were engaged in small hydro several years back and owned a number of them, but we reached the conclusion that in fact — to adopt a technology, you must hold some expectation that it will represent a substantial volume of that technology, since operating and managing those facilities and developing them requires that you truly know what you're doing.

Brian Vaasjo

executive
#74

And it would be more than just us looking at one or two sites. We would need to believe that it is actually resulting in the building of a business.

John Mould

analyst
#75

All right, thanks for that context. That covers what I wanted to ask.

Operator

operator
#76

Maurice Choy from RBC Capital Markets has the next question — please go ahead.

Maurice Choy

analyst
#77

Thanks, and good morning. I'd like to start with something from the reports: they mention that Genesee 1 and 2 were dispatched less by the balancing pool this year, despite there having been no planned outages. Do you have any thoughts on why that's the case? Is this the balancing pool behaving in a more commercial way, is it their view on stock spreads, or is there some other reason?

Sandra Haskins

executive
#78

Right, my sense is that those units simply carry the carbon tax obligation. So when spot prices in the province turned out fairly low, as we observed, it reached a point where they were examining it on a commercial basis, and dispatching it down would be our assumption regarding what they were up to there.

Maurice Choy

analyst
#79

And I suppose, following up on that, if those carbon tax costs end up being yours next year, does that mean that production level is a good indication of what you're expecting for yourselves?

Sandra Haskins

executive
#80

Regarding pricing as we move into next year, our view is that it will be somewhat elevated compared with the forwards we have this year. So would you expect those units to be economic at the prices we're seeing today, even taking into account the carbon tax obligation?

Maurice Choy

analyst
#81

That makes sense, and for my second question, I'd like to look ahead to December, I suppose, when you traditionally issue your full-year guidance, and potentially also — so your dividend, objectively speaking, for 2022? On Slide 11, you've highlighted quite a few uncertainties for next year. Could you, I guess, speak in broad terms about where you see clarity improving over the coming four to five weeks, before early December, or should we be expecting a different kind of guidance next year — sorry, next month?

Sandra Haskins

executive
#82

Could you give us some guidance specifically on the dividend increases?

Maurice Choy

analyst
#83

With respect to earnings for 2021, and also dividend guidance past 2022.

Sandra Haskins

executive
#84

At this point, I'd say our stance is that we won't extend dividend guidance past what we've already provided for '21 and '22 until we begin to see growth that can support incremental increases, and until we take a look at some of the other uncertainties ahead. So regarding the uncertainties we mention for 2021, I think this past month we're starting to get some clarity on power prices, so we'll keep monitoring that over the next number of weeks, and carbon taxes as well. So whether carbon tax rises or remains at 30, we'll be examining the financial impacts of both scenarios going forward. But I'd say those are kind of the two biggest uncertainties around next year, and of course demand in the province too. So just regarding the pandemic and where it's headed and what it means for demand in the province, some of those will begin to clear, and some will be throughout 2021 before we get a better indication as things unfold.

Maurice Choy

analyst
#85

And I suppose, just as a last follow-up on that remark that we aren't anticipating — or at least there's no expectation of — any increase past 2022 until growth appears that would justify such an increase: could you at minimum reaffirm that the dividend won't be reduced? And given that, should all of us assume it will stay at that level for the time being?

Sandra Haskins

executive
#86

No, nothing points to any reason for reducing the dividend. That's definitely not something we'd be announcing in any way. We still stand by the guidance we've provided; what's needed is simply growth that supports raises past that level. Previously, we issued guidance fairly far ahead regarding dividend increases. That was done only to show the market we didn't view this as a one-and-done, and that we did anticipate continued increases. I believe that message has now been received. So you'll likely see us signal dividend increases nearer to the expected time. Right now, we're still a couple years out, so expect that timeline of advance signaling to compress in the years ahead.

Maurice Choy

analyst
#87

Thanks so much — that's really appreciated.

Operator

operator
#88

Our following question is from Naji Baydoun at Industrial Alliance Securities. You have the floor.

Naji Baydoun

analyst
#89

Hello, and good morning. Regarding how quickly renewable projects have been expanding, that certainly sped up during this year. Do you believe that pace is repeatable as we move into 2021 and past that? And on that same topic, how would you describe the renewable project pipeline at present?

Brian Vaasjo

executive
#90

As we think about what lies ahead and acknowledge — and I believe, as we've talked about previously, renewable projects reach us through two channels. One involves the pipeline already in place that reaches completion, while the other consists of collaborating with additional developers, usually junior ones, examining sites and pushing ahead. So considering both of those, certainly, and considering what's currently in progress, it's essentially a combination of the two, and we would anticipate that continuing in the future. So we've enjoyed a very strong year and it isn't finished yet, but we do expect further success as we progress through the coming couple of years in developing and constructing renewable projects.

Naji Baydoun

analyst
#91

All right, and I imagine you've also considered whether to speed that up through M&A — or are you presently evaluating any purchases of junior developers or late-stage renewable projects to give the renewables side a real boost, or does the M&A emphasis remain on natural gas at this point?

Brian Vaasjo

executive
#92

We certainly examine M&A possibilities in the renewables space. What we usually discover is that, purely given how these acquisitions are structured and the considerable financial interest involved, we generally aren't competitive. Still, we absolutely review M&A opportunities tied to renewables, and in fact there have been some this year. The Buckthorn acquisition is one such example, so you can always expect that we're evaluating acquisition opportunities in both natural gas and renewables.

Naji Baydoun

analyst
#93

All right, thank you. The other questions have already been addressed, so that's everything from me.

Operator

operator
#94

That wraps up the question-and-answer portion. I'd now like to hand the conference back to the presenters for any closing remarks.

Randy Mah

executive
#95

Okay, thank you. On the morning of December 3, we'll be holding our Annual Investor Day event, conducted as a conference call and webcast. Further particulars are going to be shared over the next few weeks. Thanks once more for being with us today and for the interest you've shown in Capital Power. Have a good day, everyone.

Operator

operator
#96

That brings us to the end of today's conference call. Your lines can be disconnected now. Thanks for joining us, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Capital Power Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Capital Power Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capital Power Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.