Capital Power Corporation (CPX) Earnings Call Transcript & Summary
February 24, 2022
Earnings Call Speaker Segments
Operator
operatorYou're now connected to Capital Power's conference call covering the fourth quarter 2021 results. <<operator_script>> Today, February 24, 2022, this call is being recorded. At this point I'll hand things over to Randy Mah, Director of Investor Relations. Please go ahead.
Randy Mah
executiveGood morning, everyone, and thanks for being with us today as we go over Capital Power's results for the fourth quarter and year-end 2021, which came out earlier this morning. Both our 2021 integrated annual report and the presentation for this conference call can be found on our website at capitalpower.com. With me this morning are Brian Vaasjo, President and CEO, and Sandra Haskins, Senior Vice President, Finance and CFO. We'll begin with some opening comments and then open up the lines for your questions. Before we get started, I'd like to remind everyone that certain statements about future events made on this call are forward-looking in nature and are based on certain assumptions and analysis made by the company. Actual results could differ materially from the company's expectations due to various risks and uncertainties associated with our business. Please refer to the cautionary statement on forward-looking information on Slide 2. In today's discussion, we will be referring to various non-GAAP financial measures and ratios as noted on Slide 3. These measures do not define financial measures according to GAAP and do not have standardized meanings prescribed by GAAP and, therefore, are unlikely to be comparable to similar measures used by other enterprises. These measures are provided to complement the GAAP measures, which are provided in the analysis of the company's results from management's perspective.
Randy Mah
executiveYou can find reconciliations showing how these non-GAAP financial measures compare with their closest GAAP equivalents in our 2021 integrated annual report. At this point, I'll hand the call over to Brian, who will begin his remarks on Slide 4.
Brian Vaasjo
executiveThank you, Randy, and good morning everyone. Capital Power's headquarters in Edmonton sits on the traditional and present-day homeland of numerous Indigenous peoples from the Treaty 6 area and Métis Nation of Alberta Region 4. We recognize the varied Indigenous communities found in these territories, whose ongoing presence keeps enriching the community and our lives as we keep gaining knowledge about the Indigenous history of the lands where we reside and work. 2021 proved to be a superb year for moving forward with our strategy and our pledge to be off coal in 2023, and we achieved substantial headway from a strategic sustainability standpoint as well as a financial one. Broadly speaking, we expanded our renewables and storage footprint. We achieved success in securing long-term contracts for our renewable projects, and we progressed in repositioning Genesee 1 and 2 so they will be the most efficient combined cycle units in Alberta after the repowering project wraps up. Sustainability remains central to our operations, and we have built in wide-ranging compensation tied to our ESG targets. We have likewise pushed ahead with our decarbonization strategy via strategic partnerships, including working alongside Enbridge on a CCUS project. Sandra will share further specifics regarding our financial highlights.
Brian Vaasjo
executiveThe items I just mentioned include record financial results, plus a solid balance sheet and the capital access needed to support our expansion. In addition, we've substantially reduced a number of short-term and medium-term risks facing Capital Power. And given how steady our cash flows are, we've pushed our annual dividend guidance out to 2025. Slide 5 lists our strategic highlights and accomplishments for 2021. We improved the Genesee 1 and 2 repowering project by adding a 210-megawatt battery energy storage system, the biggest such system in Canada. After we reposition Genesee 1 and 2, we will hold the dominant baseload position in the Alberta power market. For Arlington Valley, we signed a 6-year tolling agreement extension, which confirms our approach of putting money into natural gas assets that are strategically positioned. At Decatur, we finished the combustion turbine upgrade, raising our contracted capacity and efficiency and improving the economics in line with the contract extension we signed in 2020. With Phases 2 and 3 finished ahead of schedule in early December and under budget, Whitla became Alberta's largest wind facility at 353 megawatts. We signed 15-year renewable contracts with Labatt's breweries and with Dow Chemical, helping both reach their sustainability goals via customized renewable energy solutions.
Brian Vaasjo
executiveAnd the appetite for renewable contracts on our side keeps looking really strong. Our Alberta renewable portfolio is still expanding, and the newest addition is Halkirk 2 — a 150-megawatt wind farm sitting right next to the Halkirk Wind facility we already run in Central Alberta. On top of that, we grew our solar and storage development pipeline by acquiring a portfolio of solar sites in the United States that carry battery potential, which gives us a platform for meaningful renewable growth. Taken together, these strategic steps underpin growth and our decarbonization road map. Now to Slide 6. This chart lays out how renewables have grown for us between 2016 and 2024. On the basis of current growth projects, we have reached a compound annual growth rate of 18%. As you can see in the chart, we have posted steady yearly growth, with new renewable contracts coming in each year — with the exception of 2023, when the original completion dates for the North Carolina projects slipped to 2024 because of delays in the interconnection process. We hope to announce at least one more renewable project this year. On to Slide 7. We are committed to reaching carbon neutrality by 2050, and we have a clear pathway that involves setting targets along the way.
Brian Vaasjo
executiveCompensation packages for executives and Capital Power leaders include elements tied directly to ESG goals. Among these are objectives for diversity, a 30% carbon reduction by 2024, and employee well-being. During 2021, we met our sustainability targets to create company-wide strategies for water management and sustainable sourcing, built around ESG principles so we contribute positively to society and ensure our environment thrives over the long term. Implementation of those strategies is underway in 2022. Our Genesee 1 and 2 repowering project remains on track, which supports our commitment to be off coal in 2023. Sustainability has also been built into our financing, as we transitioned existing credit facilities into sustainability-linked credit facilities tied to emission intensity targets. We are moving our Genesee 1 and 2 CCS project ahead through collaboration with Enbridge, which I'll elaborate on shortly. Thanks to what we achieved in 2021, we've picked up speed toward our sustainability targets and positioned the company to deliver long-term value for our stakeholders and the environment. Turning to Slide 8. We have made substantial progress on the advancement of CCUS. The CO2 hub development process is moving forward in Alberta with the Enbridge project fitting our needs very well.
Brian Vaasjo
executiveOur pre-FEED study is being wrapped up right now — it's meant to lock down the project definition, technology licensing, scoping, preliminary engineering, deliverables and costing details. We feel good about the odds that the $1.8 billion to $2 billion carbon capture project will secure enough financial backing from both the Federal and Provincial governments. Talks are underway with the Canadian Infrastructure Bank regarding the financing framework. On top of that, we anticipate First Nations' involvement, along with other possible partnerships for this project. Derisking carbon policy stands as one of the crucial issues determining whether this project moves ahead. Governments broadly recognize that long-term policy uncertainty creates unusual risks for CCS investments. In our conversations with government, the focus has been on possible mechanisms and approaches for mitigating adverse impacts should carbon policy-related changes occur. A final investment decision is now anticipated in mid-2023, contingent on satisfactory hub progress, government support and policy risk mitigation. I'll hand the call over to Sandra now.
Sandra Haskins
executiveThanks, Brian. Turning to Slide 9, I’ll go over the 2021 financial highlights. As we noted, we achieved an annual record in 2021 for both adjusted EBITDA and AFFO, and we expect our 2022 financial performance to be comparable. We delivered our eighth consecutive yearly dividend increase and extended our annual dividend guidance of 5% through 2025, supported by predictable cash flows. In 2021, Capital Power produced a total shareholder return of 19%, which aligns with the 5-year average and exceeds our long-term target TSR of 10% to 12%. We have been reducing risk in our cash flows by securing low-cost carbon offsets, expanding commodity hedging, and executing longer-term contracts to manage medium-term risks. In June of last year, we completed a successful $288 million equity offering to prefund our existing growth CapEx. We have just renewed our NCIB program for another year, which provides a capital allocation option during periods of limited growth and when the shares are undervalued. We have also extended our debt maturity profile and lowered refinancing risk. Our investment-grade credit rating remains a top priority, and the strength of our balance sheet and resilient cash flow secures our credit rating.
Sandra Haskins
executiveIn 2021, FFO-to-debt came in at 23%, versus the 17% target from S&P. On the whole, we're in a strong position to fund our growth CapEx from cash flow we generate internally. Slide 10 presents how financial performance compared year over year for the fourth quarter and for the whole of 2021. We posted year-over-year gains across every key financial metric, in the fourth quarter as well as for the full year. That includes revenues and other income of $1.99 billion generated in 2021, up from $1.937 billion in 2020. Adjusted EBITDA and AFFO both came in above the midpoints of the higher guidance we had revised upward. Adjusted EBITDA reached $1.124 billion, which is an 18% increase from $955 million in 2020. AFFO, meanwhile, totaled $605 million in 2021, a 16% increase from $522 million in 2020. Among the positive factors behind this record performance for the year was strong results from the Alberta Commercial segment, driven by high Alberta power prices that averaged $102 per megawatt hour over the year. Whitla 2 started commercial operations one month ahead of schedule in 2021, and we saw full-year contributions from the 2020 additions of Buckthorn Wind and Cardinal Point. We sped up recognition of coal compensation through the Genesee 1 and 2 repowering project, under which we expect to be off coal by the end of 2023, 6 years sooner than required.
Sandra Haskins
executiveWe additionally recorded a lower net finance expense of $23 million, mostly because of reduced interest stemming from fewer loans and borrowings outstanding. Working against those positives were a softer U.S. dollar, diminished wind resources across the majority of our wind facilities, and greater current tax expense, since 2021 marked our first cash taxable year in Canada. Moving to Slide 11, I'll give you a status update on recontracting for our Island Generation facility. For nearly 20 years, Island Generation has delivered reliable power to Vancouver Island in the lower mainland of B.C. Even though the facility operates infrequently, it remains there and available when required to supply reliable generation. During 2019 and 2021, when BC Hydro encountered significant challenges, Island Generation ran at high-capacity factors and assisted in keeping the lights on. As you'll recall, in September of 2021, BC Hydro told BCUC that it required the Island Generation facility to run while transmission repairs took place. In December 2021, BC Hydro issued its final IRP, in which it confirmed its position that a long-term EPA for Island Generation is not needed. Given these developments, and assuming a 4-year contract extension, a $52 million impairment was taken in the fourth quarter.
Sandra Haskins
executiveOur expectation remains that Island Generation will be needed for more than 4 years, and we are taking forceful action within the BCUC IRP process. Turning to Slide 12, I'll discuss the Alberta power market and our hedging position. During 2021, power demand made a complete recovery from the load reductions in 2020 tied to COVID and to oil — to low oil prices. Indeed, the Alberta market recorded new peak demands for both summer and winter. Even though reopening is not yet complete, load is still strong today and should rise modestly compared with a year earlier. Following the expiration of the balancing pool PPAs at the close of 2020, 2021 brought a vigorous power market, with an average price of $102 per megawatt hour versus $47 per megawatt hour in 2020. This slide presents our hedge position for power and natural gas. As you will see, we have raised our hedge positions for 2022 through 2024 since what we disclosed at Investor Day on December 2. For 2022, we began the year 72% hedged in the high $60 per megawatt hour range. For 2023, we are 47% hedged in the low $60 range. And for 2024, we are 32% hedged in the high $50 range.
Sandra Haskins
executiveThat compares with forward prices for 2022 through 2024 of $94, $72 and $61 per megawatt, in that order. Another tool we use for managing price risk and volatility is longer-termed originated contracts within the hedge position. Relative to the forwards, those contracts lock in a lower price for 2022, yet they lessen price risk in later years, when we expect prices to decline. As an example, in 2022 we are 72% hedged overall, and over 40% of that is hedged through contracts with terms exceeding 1 year — many running 3 to 5 years or longer. Those long-term hedges carry an average price in the low $60 per megawatt hour range, consistent with longer-term forwards, while the remaining hedge contracts average a price closer to 2022 forwards. For 2023 and 2024, the hedges presently in price are mostly longer-term contracts. As we move away from coal, natural gas prices play a growing role in our financial results. We have been actively hedging the expected natural gas firm for the Alberta fleet at prices favorable relative to forwards. Of our expected natural gas volumes, we have hedged 100% in 2022, 99% in 2023, and 85% in 2024.
Sandra Haskins
executiveAcross all 3 years, the typical hedge price comes in at $2 to $2.50 per gigajoule — far below the forward gas prices you can see in the table. If you move to Slide 13, I'll wrap up our comments by going over our 2022 targets and speaking to the different sensitivities around them. As we've stressed, 2021 delivered our strongest financial results ever, and 2022 results will carry that strong momentum forward. Our 2022 targets are $1.11 billion to $1.16 billion in adjusted EBITDA and $580 million to $630 million in AFFO. We've examined how rising inflation affects us and found only a modest unmitigated exposure on our operating results. On our growth projects, we're keeping construction exposure in check, and that includes locking in over 84% of procurement costs for the Genesee repowering. In addition, with the North Carolina solar projects' COD pushed to Q4 2024 and Halkirk 2 slated for late 2024, that timing lets us benefit from more normal commodity and shipping costs. To handle the prospect of higher interest rates, we have fixed rate debt in place. We've also been actively hedging the underlying DOC rates for every financing into early 2026, anticipating that rates will rise.
Sandra Haskins
executiveWhen it comes to financing for 2022, we're limiting it to refinancing the preferred shares. The year ahead will include a substantial amount of planned outage work, and that covers outages at Genesee 1 and Genesee 3. Sustaining CapEx should land somewhere between $105 million and $115 million, which is considerably higher than the $55 million to $70 million forecast for the next few years. Our targets for 2022 also take into account our cash taxable position in Canada. With a strong price outlook for Alberta, we anticipate internally generated cash flow will remain strong. And lastly, we're still aiming for $500 million per year of committed capital directed toward growth. We look for 2022 to be another very strong year, financially as well as strategically. At this point I'll hand the call back to Randy.
Randy Mah
executiveOkay, thanks Sandra. Therese, let's go ahead and open it up for questions.
Operator
operator<<operator_script>> Our initial question is from Robert Hope at Scotiabank.
Robert Hope
analystPerhaps this is more of a strategic question for the longer term. Specifically on the natural gas mid-life generation side, what opportunities are you seeing in the market? And when you assess those opportunities, how does the capacity to lower carbon at the sites, or to collocate renewables or batteries, factor into the investment decision?
Brian Vaasjo
executiveRegarding activity around mid-life natural gas assets right now, things have picked up considerably in the past 2 months. We're seeing a decent volume of interest, though not at the level we had before the pandemic, yet certainly stronger than what showed up over the last 2 years. So that looks encouraging. When we're evaluating a specific proposal, clearly there's a contracting-side assurance that, across its economic life, it can be recontracted going forward, or that it holds enough existing and long-term contracts to carry us comfortably into the 2030s — so that's kind of the first hurdle. Looking at it from the standpoint of how optimistic we are about recontracting or not, it would hinge on its strategic positioning. We've examined a number of assets that are, I'll put it this way, purely generation assets and produce energy, but renewables can easily displace those, and they'd have a comparatively shorter history. Assets sitting on the grid in strategic spots — for instance, the facilities at our peaking facilities — would generally carry the most enduring value. Another factor, given where they're positioned, is that adding batteries at those sites is a fairly straightforward transition, and then eventually retiring the natural gas facilities so storage capability gets realized there.
Brian Vaasjo
executiveWe examine a range of factors, and the carbon outlook for every facility gets very close scrutiny, along with how that outlook bears on our targets. We also consider what we see as the long-term viability of the asset and its location. So each case is very much site- and project-specific, but we address all of those points in the evaluation of whether we even proceed with examining an asset.
Robert Hope
analystThanks for that detail—really useful. Maybe shifting to the renewables side now. In the prepared remarks, you noted that several projects in development still have enough time before commissioning to avoid some of the supply chain issues we're seeing at present. For the next batch of renewable projects, is this causing customer discussions to slow down? Or is the pipeline of counterparties ready to backstop EPA still pretty robust?
Brian Vaasjo
executiveWell, it's caused — right now there's something of a lull, and multiple factors are behind it. One, naturally, is the situation with the Biden administration down in the United States. And what will the outlook be for different credits, tax credits, and so forth. So in my view that's producing a meaningful deceleration when it comes to elements getting transacted — though it isn't necessarily putting a damper on some of the discussions. But I think before you see a great many triggers pulled, a bit more certainty will need to arrive in the market. On the pricing side, you can secure or obtain commitments around price stretching out 2 or 3 years, and those tend to run somewhat below current pricing, or today's pricing. We expect that this will ease. And as the market gets clearer and clearer, I think you'll see, once again, a tendency toward more contracting taking place. So I'd say there's a bit of a slowdown for a couple of months, but definitely by midyear and after that, you'll see some acceleration in renewable opportunities in the U.S. In Canada, it's more on a province-by-province basis regarding what the utilities or the provinces are offering when it comes to renewable projects — in Alberta things continue to be the same.
Brian Vaasjo
executiveFrom our standpoint, this is a great area for continued investment. We have done quite well at securing contracts for our renewable projects, even though—as we have repeatedly stated—we are at ease holding them on a merchant basis. Still, getting even the remainder of our renewables position under contract at this stage is a very encouraging development. So the renewable side of things looks quite strong.
Operator
operatorMaurice Choy from RBC Capital Markets has the next question.
Maurice Choy
analystStarting with the CCS discussion — my first question is this: beyond First Nations, what do you expect other prospective partners to contribute? And then, on timing, what might cause an FID to arrive sooner than mid-2023 once more?
Brian Vaasjo
executiveWhen it comes to the partner, what would we be looking for? Well, first off, we'd seek a strategic partner—someone bringing more than just capital to the table. You can see that from a technology standpoint. Mitsubishi, for instance, would be one such candidate, or there are various engineering companies that are strongly dedicated to this area of development. And in fact, they do have capital they would like to put to work. There are also entities that would be quite keen on further investments in CCS. Enbridge, for instance, would be one such organization. But other organizations exist that are very interested in being part of—I'll say—part of the action. And then, naturally, there are financial players who would view it as a favorable investment based on what it's accomplishing. But again, they wouldn't necessarily bring anything beyond capital to the table. And I should be clear, we've had zero discussions with anyone so far. And that perhaps leads us to your second question regarding timing and moving forward. We view a major date, a major milestone for us, as being when the federal budget is released, and what it contains in terms of magnitude and parameters around the investment tax credit.
Brian Vaasjo
executiveFrom what we can tell at this point, nothing has been finalized, committed, or locked in — yet it does appear that, from our side, the result will be favorable. That is also the point when we will begin holding an increasing number of conversations regarding particular partnerships and similar arrangements. As for pulling the date forward on when we proceed with it, the biggest problem we face at present is that the hub process itself is not moving ahead as fast as we had expected. Originally, the expectation — and it was a general one — was that the government would review several different hubs at roughly the same time. What has actually happened is that the response has been overwhelming, and they had anticipated a far larger response than they expected for the first tranche. As a result, they simply lack the capacity to analyze these simultaneously. So they are placing them into an order, and the Enbridge project has not yet come up for assessment — or, to put it more accurately, none of the projects located west of Edmonton has been requested by the government for assessment. That has therefore delayed matters by a few months.
Brian Vaasjo
executiveWe think that could proceed pretty fast. In our view, the — with the — Enbridge is advancing a very clear-cut, very tidy, top-notch, top-notch project. But another factor that comes into play on the hub side is that fairly sizable geological spending has to happen. And it would make sense for that spending to occur only after there's more certainty about how the processes will unfold going forward. So a good deal of that work, as we see it now, is likely sliding into next year and possibly wrapping up by the middle of next year. Now, all of it could be sped up if there were a push behind it. But the way we look at it, and there's still even — even with the plan extended, completion in 2026 is possible, though it starts slipping toward more like finishing in 2027. That said, that lands well ahead of hitting the Provincial and Federal targets before 2030. So we really do have plenty of time on the back end. So we don't want to do anything unwise up front and/or get ahead of ourselves as we move forward. So we're pretty resolute about what we need to see, and things are falling into place, albeit with a modest delay in those items materializing.
Maurice Choy
analystThat ties in pretty well with what I want to ask next, which is about how you're allocating capital. You said earlier, of course, that the activity level in the mid-life gas generation market is encouraging to you. You've got this $2 billion project tied to CCS. And you mentioned as well that one additional renewable project could move ahead this year. Have you thought about taking another look at the possibility of selling part of your renewables to fund all of that? Bearing in mind, as well, that you discontinued the DRIP last quarter?
Brian Vaasjo
executiveOkay, I'll begin, and Sandra will surely add to this. Certainly, regarding new capital requirements, I believe, as Sandra mentioned, we're in a fairly strong position at present when it comes to our capital requirements. Yet at all times, we examine how we might turn over capital. Are there assets we ought to be selling and generating liquidity events and putting those funds to use? So that remains a live option. Much depends on our growth outlook and on deploying that capital versus realizing it versus what other alternatives we have. But that stays on the table, and it's always something under active discussion.
Sandra Haskins
executiveNo, there isn’t much I can really add there. Right now, as we consider how to finance our expansion using cash we generate ourselves along with the strength of the balance sheet, we truly aren’t in a spot where we’re contemplating an equity raise or any kind of sell-down. As you’ll recall, part of our renewable growth involves U.S. solar. That means some of the funding will also come by way of investment tax credits. So at this stage, we don’t find ourselves needing to view that as an option. Still, as Brian said, it always remains on the table.
Brian Vaasjo
executiveThere's one thing worth keeping in mind, I think — and this is where the scale of it matters — the tax credit details that we hope will come out in March could have a really big effect on the net capital cost of that $1.8 billion to $2 billion. And once you factor in partners as well, it doesn't look quite as daunting as the headline number suggests.
Operator
operatorOur next question is from Patrick Kenny at National Bank Financial.
Patrick Kenny
analystSince the Alberta budget is due to be released later today, Brian, could you remind us what further provincial government support you still need to see? Beyond Enbridge receiving the sequestration rights, naturally. But from an economic standpoint more broadly, which provincial clarifications or policy milestones ought we to keep an eye on?
Brian Vaasjo
executiveSure, surprises could come from either the Federal or Provincial governments that end up creating obstacles for us down the road. We don't expect any, and none are on our radar, but that possibility always exists. Still, based on what we observe and what we roughly grasp, purely from a financial standpoint, we expect that with support from the Canadian Infrastructure Bank, the tax credit, and the investment tax credit we think may be accessible to us — we don't believe much else is required from a "financial perspective." What matters, though, at this point, and what we need to witness, is some derisking of the carbon credit environment, whether through contracts with differences or through other kinds of instruments that bring a greater degree of certainty to that cash flow. And as I said, the governments appear to be quite aware of this, they get it. And I think, as the banking community also represents, that's a very, very significant and somewhat extraordinary risk given the magnitude of the investments being made. So I believe the governments are sympathetic.
Brian Vaasjo
executiveSo what does that actually mean, and is it at the federal level or the provincial level — from a federal standpoint or a provincial one, we're in conversations with both governments about the need for something, and we've discussed some mechanisms a bit that we believe could work. And I genuinely think it's a discussion that's having an impact, at least from the federal side. We don't believe it ought to come through regulation. We have somewhat of a difficulty with anything when it's a regulation and you're counting on it holding its course for 20 years — that isn't necessarily going to be the case. What we'd really be after is something contractual rather than regulatory, to give that added measure of reassurance. Very similar to our insistence with the provincial — the Alberta provincial government — when we negotiated the off coal arrangements. We weren't content with it sitting in regulation; it had to be by contract. And from the carbon risk standpoint, we're seeing that same kind of approach for greater assurance.
Patrick Kenny
analystAll right, that’s useful. Perhaps for Sandra: the 72% hedged position for this year in the high $60 range versus, I suppose, a forward price still in the mid-90s — is that comparatively larger share of baseload sold forward mostly because you’re able to lock in your natural gas requirements below market? Or does it instead say more about a view that you believe the forward curve doesn’t reflect reality, and that as we move into the peak summer months, you’d expect spot prices to settle much lower?
Sandra Haskins
executiveIt's a mix of a few factors. First, if you look at that 72% versus the 40% — so more than 40% of the full 100% of baseload sits in long-duration contracts. Some of those extend pretty far out, and that was a deliberate choice once we saw we were in a stretch of very high prices in '21 and '22. But as new supply arrives in a couple of years, we anticipate those prices will decline. So with the additional length we've got from Genesee 1 and 2, it seemed prudent from our standpoint to sign those longer-dated contracts and secure that length. So if you look just at hedging for the 2022-only contracts, we're hedged only 32%, and that's in the low $80 per megawatt hour range. So you have to keep in mind that as we move into hedge positions over time, the forward price has risen to where it stands today in the high 90s. And so we keep evaluating hedges of the book. But what's really behind that comparatively higher hedge position are the longer-duration contracts carrying a lower price, so they'd be contracted at a level more reflective of long-term forwards rather than the current year's forwards.
Patrick Kenny
analystAll right, that's clear. And here's my final question. I'm just wondering whether you're seeing any inflation-related cost pressure when it comes to maintenance work? Or have you managed to offset the risk tied to your sustaining CapEx outlook for this year? And then perhaps you could also weave in a brief remark on how we ought to think about your O&M more broadly, across the rest of your contracted fleet outside Alberta?
Sandra Haskins
executiveSure. So what would be — oh, please continue, Brian.
Brian Vaasjo
executiveNope. Sandra, you have the floor.
Sandra Haskins
executiveWhat I'd add is that where maintenance is concerned, our LTSAs are pretty well shielded from inflation's effects. What we're observing, then, is that we don't face much risk on that front. Taking everything together, our overall exposure to inflation looks fairly contained.
Brian Vaasjo
executiveI wanted to add that our view of the maintenance — the operating and maintenance cost trajectory for this year and beyond — is that, thanks to a lot of the work completed last year plus some of the work we expect to do this year, we're actually positioned for lower spending. So we regard that as a positive. And I believe we covered that at our Investor Day. On inflation: many of the activities tied to outages and routine maintenance work are labor-related. As a result, it's driven more by what the union contracts say and by labor availability in the different regions going forward, so that's a very significant piece of our costs. And while we do see that rising, we don't see it getting too far out of control, and not like what we've seen with steel prices and other items that went up quite a bit — though of course, those are coming down right now as we speak. So we do not expect inflation to have a significant impact on our cost going forward.
Operator
operatorOur following question is from John Mould at TD Securities.
John Mould
analystI suppose it's really just one broad question on the carbon side, since we're going through some fairly large policy reviews over the next few months. I'm just wondering what your current base case assumptions are for Alberta, specifically on the tier review? And how you expect or how you think that might unfold in the context of the Federal backstop as it's currently constituted? And then how you're thinking about the clean electricity standard more broadly? And I appreciate we don't have that policy yet, but I think we've got the contours at least, including in Ontario, outside of the assets for Genesee specifically, I guess, where you're looking at significant carbon abatement. Can you maybe just tackle those 2 bigger picture topics?
Brian Vaasjo
executiveFrom an Alberta standpoint, then, what we observe is a provincial government that is strongly committed to carrying on with the tier system — that is, running its own regime. And as it proceeds to negotiate those agreements with the Federal government, it obviously has to stay mindful of any shifts in federal policy that may come along regarding carbon and assorted standards. Our view is that the Alberta government recognizes the present intensity figure, the 0.37, as the right level and would work to hold it there all the way through 2030. And once more, we'll find out when discussions and negotiations take place. But we see — and this ties back to a question asked earlier — we do expect that Alberta's carbon price is going to stay in lockstep with whatever emerges at the federal level. So that represents one negotiating element and one point of common ground between the Federal backstop and what we'd anticipate in Alberta. The largest question, naturally, concerns what unfolds with respect to the oil and gas sector. From that angle, I can't say what will happen there. And once more, that is, in our view, where the discussions will concentrate. Turning to Ontario, in that province our assets — by and large, the carbon implications tend to fall on the ISO, which holds — which serves as a counterparty on the contract.
Brian Vaasjo
executiveIt isn't flawless, yet where completeness is concerned, it's essentially fully addressed. What's notable regarding a rising carbon price is that, based on an asset's position in the queue and its efficiency level, it typically pushes less efficient assets to run less often, while more efficient ones naturally run more. That's the pattern we observe in Alberta and what we anticipated elsewhere, and as carbon prices may climb, our assets generally get dispatched more rather than less. So going forward, we don't really view escalating carbon prices as a negative.
Operator
operatorOur following question is from Andrew Kuske at Credit Suisse.
Andrew Kuske
analystI think your slide deck included some wording about Island and expressed an intention to intervene forcefully in the BCUC process. So I guess my question is whether there's a broader issue with how BC Hydro has acted regarding Island, where the real problem is actually Powerex's marketing license — because if there isn't a functioning market inside British Columbia, doesn't that pose a larger difficulty? And so is the real question whether, in the end, you'd probably want to reach some fair resolution of this?
Brian Vaasjo
executiveI can't say I have a complete picture of what's driving BC Hydro here, or how significantly Powerex factors into their thinking. As things stand, they clearly require more reliability on the island given the upcoming work on the mounted transmission lines. And to repeat, the work they're undertaking won't actually add capacity — it will only improve reliability. So once more, I'm uncertain whether it will truly resolve the Island's issues. The hardest part for us, I'd say, is that looking back at the last IRP and the one prior to it, there used to be far more information and far more disclosure of the basic data that transmission specialists could examine and assess and then either concur or object. What we've leaned on heavily is the fact that we've been dispatched fairly consistently. Capacity hasn't grown. Demand on the Island has grown. All of it indicates that the need exists historically and will be even greater going forward. And that — the absence of data, the absence of transparency — has been the difficulty up to now.
Brian Vaasjo
executiveAt this point, our expectation is that we'll get past that issue by way of the BCUC proceeding — through information requests and similar steps. We ought to be able to reach that data and then decide whether or not we consider it summed up. To put it plainly, as things stand, our view is that they are planning. On the island, they have a certain level of brownouts that, in their judgment, is acceptable. We don't see any other answer to that situation that makes logical sense. But clearly, they aren't making that public to any significant extent.
Andrew Kuske
analystAll right, that context is quite useful. Then for my second question, it really concerns the fact that your construction know-how has traditionally been a real strength, and you've been able to complete a number of projects on tight schedules and on budget, partly thanks to that construction expertise. How do you view that as a competitive edge going forward? And could you scale it if you wanted to put more capital to work in the market? Or do you feel you're in about the right position at present for building new things?
Brian Vaasjo
executiveIt really hinges on what you mean by those new items. Take, for instance, the repowering work happening at present. We don’t discuss it much, but consider where that project stands after 1 year—it’s usually where other organizations sit at 2 years. We’ve significantly shortened the early phase of that project, and we’re hitting our milestones. I believe that gives us the capacity to move through construction rather fast. On a major project like that, repowering removes a great deal of strain from the organization. Whether it’s a wind farm or a solar facility, we approach and keep approaching things somewhat differently from many others. Whatever we learn or develop at one solar facility or one wind facility, we can apply it simply as part of how we operate. So we definitely have the ability to build a significant number of wind or solar facilities. We can go from a couple of years to a handful, and again, over time, far beyond that. From a renewable standpoint, then, I think we have tremendous capacity to construct several facilities at once.
Operator
operatorMark Jarvi from CIBC Capital Markets has the next question.
Mark Jarvi
analystCircling back to the carbon capture and storage project — you mentioned the Canadian Infrastructure Bank and how First Nations' involvement is strategic, so I was wondering: how low a percentage could you go? Is there a minimum level you want when it comes to economic participation? And at the same time, is there sort of a sweet spot — a specific ownership target you're aiming for?
Brian Vaasjo
executiveUnless something extraordinary comes up, my answer would be that we'd aim to keep no less than 50% of the project. That's roughly the threshold, I think, that we'd begin from when we look at partners, and naturally First Nations would come out of that. If, say, First Nations held a 10% interest, then perhaps the remaining 2 partners — us and another party — would each hold 45%. A great deal will simply hinge on governance and the other matters that shape it, but approximately 50% would likely be the sweet spot.
Mark Jarvi
analystSo when you mention 50%, do you mean that in a scenario where the Canadian Infrastructure Bank is extending something like a loan? And so it's essentially that figure net of the loan from the Canadian Infrastructure Bank? Or what's the way we should think about that piece of Capital Power be ?
Brian Vaasjo
executiveNo. No, I’m putting it more in terms of this: if you look at what our ownership stake in Capital Power would be, it’d be roughly in the area of, let’s say, 50%. As for the Canadian Infrastructure Bank, they’ve got guidelines and direction, and there’s what they might be willing to support or fund, which wouldn’t cover the whole, I’ll call it, debt check for the project. And naturally, any funding tied to First Nations would come from other areas of the Federal or Provincial government. So public debt financing definitely will be needed on the project. It may well be project financing associated with it. Again, depending on partners and approach, you’d probably see a combination of Canadian Infrastructure Bank support plus more traditional debt.
Mark Jarvi
analystSo then, returning to the Enbridge hub — it appears your view is still that it will proceed. But should it not, for whatever reason, what would Plan B be for that piece?
Brian Vaasjo
executiveThe challenge lies in locating a suitable geological site. For instance, let's say at this moment Enbridge made the decision, for some strategic rationale or another, not to proceed. And if there were no technical justification — if the site itself were the problem — we would simply assume control of it. Relative to the CCS investment we are contemplating, it's fairly modest. So we'd just take it over and then either seek out another party, one of the other pipeline companies that would gladly accept it, or once again, handle it ourselves. If the reason were technical, and that technical reason were more geological in nature, we would move quickly to find another geological site situated relatively nearby. Alberta's geology offers abundant potential space. Therefore, I don't think that would necessarily pose a major difficulty.
Mark Jarvi
analystAll right. And then, one final question. Just regarding the gas hedges, you're very heavily hedged for your baseload. If you had something like an unplanned outage, as you saw at Genesee, what risk would there be, or how would you handle that? Could you simply use the gas at other, sort of, just actual facilities? Would you just resell that gas? Just any risk around being so heavily hedged on the gas side?
Sandra Haskins
executiveRight, we could either sell that gas or redeploy it. So there's very, very little risk there, given the contract price we have on those contracts.
Mark Jarvi
analystAnd did you carry that out over the last 12 months, taking into account the Genesee 2 outage?
Sandra Haskins
executiveAt certain points, there would have been a certain structure to it. So yes, there would definitely have been a chance to offset some of that. Yes.
Mark Jarvi
analystOn the whole, are you netting out each of those positives?
Sandra Haskins
executiveThat's right.
Operator
operator<<operator_script>> Our following question is from Naji Baydoun of iA Capital Markets.
Naji Baydoun
analystI have just a couple of questions, and I'll begin with the Genesee CCS project. It certainly looks like the obvious next step in Capital Power's evolution. What I'm wondering is: if that project were not to proceed, or if it had to be changed in a material way, what alternative options are you considering when it comes to other priorities for allocating capital? You mentioned M&A briefly, but some additional color there, along with more specifics on organic growth, would be useful.
Brian Vaasjo
executiveLooking at that project, clearly, were it to proceed, it would somewhat constrain other things Capital Power might pursue. I mean, we could still achieve considerable expansion in renewables plus acquisitions during that period. But it would definitely reduce our overall appetite. So what I would say is that we would keep examining growth in renewables. We would potentially see some extra fill and natural gas acquisitions, even though we're seeing considerable activity right now, and we anticipate considerable activity next year. We do expect that, over time, those opportunities — and when you consider mid-life natural gas assets with substantial contracts tied to them — those will become fewer and farther between. So don't expect to say in the last part of this decade that you'd see considerable activity on that front; more so in the early part of this — early part of this decade. So we would see much of the growth, if not in certain years all of the growth, coming from renewables.
Naji Baydoun
analystAll right, that's quite useful. And perhaps connected to what you said earlier about the competitive advantage from the Genesee repowering — I take it you aren't seriously looking at buying other thermal assets and using that same expertise and know-how to shift them toward more efficient or lower-carbon assets?
Brian Vaasjo
executiveThat is definitely a future consideration, and I'd say that perhaps in a couple of years, if we've had some success with Genesee or at minimum are progressing substantially along that path, it could be worth examining. And in the U.S., recognition of the need for CCUS is certainly increasing. So we believe some opportunities of that type might become available to us, where we could bring our expertise to bear on a relatively new natural gas facility, again in the U.S. Even in Alberta, as we assess things and consider Genesee 3, we'd expect that at some point it would make sense to potentially repower that unit and apply CCUS, especially once the infrastructure exists. So opportunities of that nature may well exist. At this stage, though, apart from Genesee 3, we aren't viewing that as something that's really on the radar screen, but it certainly holds some potential going forward.
Operator
operatorThat brings the Q&A portion to a close. I'll now hand the conference back to Mr. Randy Mah for any closing remarks.
Randy Mah
executiveAll right, with no further questions, that brings this conference call to a close. Thanks for being with us today and for the interest you've shown in Capital Power. Have a good day, everybody.
Operator
operatorThat brings us to the end of today's conference call. You can now disconnect your lines. Thanks for joining us, and have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capital Power Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Capital Power Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capital Power Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.