Capstone Copper Corp. (CS) Earnings Call Transcript & Summary
October 31, 2022
Earnings Call Speaker Segments
Jerrold Annett
executiveGood morning, everyone, and welcome to the Q3 2022 conference call for Capstone Copper. I want to point out that the news release and regulatory filings that announce the 2022 third quarter financial and operational results for Capstone Copper can be found on our website and on SEDAR. For those of you logged into the webcast, we'll be advancing the slides for today's presentation, and that presentation is also accessible in the Investors section of our website. Joining me today are our CEO, John MacKenzie; our President and COO, Cashel Meagher; our Chief Financial Officer, Raman Randhawa; and our Senior Vice President, Risk, ESG and General Counsel, Wendy King. After our brief remarks, you'll have an opportunity to ask questions. I should note that comments made on today's call will include forward-looking information within the meaning of applicable securities laws. By its nature, this information carries risks and uncertainties, and actual results could differ materially from the views expressed today; for more information on the risks and uncertainties related to our business, please refer to Capstone's most recent filings, which are available on our website and on SEDAR. And finally, I'll note that unless otherwise specified, all amounts we discuss today are in U.S. dollars. I'll now hand the call over to John MacKenzie.
John MacKenzie
executiveThanks, Jerrold, and good morning to all of you. This marked our second complete quarter since becoming Capstone Copper, and I'm really happy with how our integration work has gone since the Capstone-Mantos deal closed earlier this year. Last week, both management and our Board made visits to Monteverde and Monte Blancos, and we were very encouraged to see how the Monteverde development project is advancing, along with the progress and the potential for more upside at Monte Blancos. During the third quarter, we turned out 45,700 tonnes of copper in total, with consolidated C1 cash costs of $2.76 per pound across our 4 operations. Even though throughput at Monte Blancos fell short of plan, the mine still achieved substantially lower sulfide costs of $2.17 per pound, and that figure ought to get even better once the mill hits its target run rate in the fourth quarter. On the cathode side, the biggest cost driver was sulfuric acid: prices contracted in the second quarter at all-time highs and were delivered in the third quarter. To be specific, Monte Blancos and Monteverde operations paid more than $260 per tonne for acid during the quarter; however, we are right now locking in much lower prices for delivery in the first half of next year, with contract pricing in the $120 to $140 per tonne range. All in all, notwithstanding inflationary pressure, I'm glad we kept operating costs flat quarter-over-quarter on production similar to Q2, and our C1 cash costs ended up lower this quarter. On the right-hand side of the slide, we show the first of 4 Komatsu electric rope shovels, which was commissioned at our Monteverde mine in September. Moving to electric equipment at Monteverde won't just help shrink our environmental footprint; it will also boost the mine's productivity, thanks to the larger loads these new shovels are able to handle. The second shovel is due to be commissioned imminently, and the final third and fourth will follow. Moving to Slide 6, we show our 9-month production and cost guidance covering April 1 through December 31, which is unchanged, and we reiterate our consolidated copper production range of 136,000 to 150,000 tonnes, with C1 cash costs trending toward the upper end of our guided range of $2.55 to $2.70 per pound. We expect better concentrated throughput levels in Q4 at Monte Blancos as well as Pinto Valley. The ramp-up at Monte Blancos is going well. The mill ran above the designed 20,000 tonne per day throughput level on over 20 of 27 planned operating days in October, with copper recoveries in line with expectations; now I'll hand things over to Raman for our financial results.
Raman Randhawa
executiveAppreciate that, John. Let's turn to Slide 7. Copper prices fell sharply beginning late in Q2 and kept sliding through the whole of the third quarter, and that dealt a significant blow to our Q3 financial results, generating unfavorable provisional pricing adjustments that have dragged down earnings across many of our peers in base metals. For the quarter, our realized price was $3.29 per pound — $0.22 per pound under the Q3 LME average and about $1 below this year's Q2 LME average. The quarter's lower realized price came from two things: 29,700 tonnes of copper that carried an average price of $3.75 per pound as of June 30 and eventually settled at weaker average prices in Q3, plus 34,600 tonnes provisionally priced at $3.45 per pound on September 30, a level under the third-quarter average. Q3 adjusted EBITDA of $34.1 million took a hit from a $32.5 million realized provisional pricing loss, and from ongoing inflationary pressure across the portfolio — particularly sulfuric acid in our cathode business, as John noted earlier. That $32.5 million traces back to Q2 provisional pricing. Strip it out, and EBITDA would have been $66.6 million. Our adjusted EPS came in at negative $0.02 per share, and that figure also took a hit from an additional $22.5 million in realized provisional pricing losses. Going forward, we're looking to reduce how much provisional pricing affects us by using the QP hedging strategy we put in place recently, and I'll walk through that in greater detail on the upcoming slide. Turning now to Slide 8. The left side gives an overview of our available liquidity, which was $711 million as of September 30. That total includes $196 million in cash and short-term investments, $405 million in undrawn capacity under our $500 million corporate revolving credit facility, and $110 million in undrawn amounts under our $520 million Monteverde development project facility. We also have more room to work with financially. There's the $100 million accordion, plus the portion of our $60 million cost overrun facility with Mitsubishi Materials Corp., our partner in Monteverde, that hasn't been drawn yet. As of September 30, we had drawn $22.9 million against that cost overrun facility — something we're required by contract to do no matter what our operating cash balance is, given the capital increase we announced earlier, from $785 million to $825 million in Q2, which hasn't changed. On the page's right side, we show the proactive measures taken during Q3 to guard against downside risk by adding 2023 copper hedges as we near the last years of construction at Monteverde; in short, 85,000 tonnes of copper output for next year is hedged at a weighted average price of $3.45 per pound. As noted earlier, late in Q3 we launched a QP hedging program that uses derivative contracts to offset copper sales so revenue is fixed at the time of shipment, thereby removing significant deviations in realized copper prices from the LME average. The QP hedging program we put in place not long ago also allows us to manage liquidity better, particularly when copper prices are falling, so that our business plans and our balance sheet are protected as we move ahead. We're still in a strong position to fund the rest of the CapEx at MVDP, and once that project is commissioned in late 2023 it will transform our portfolio. At this point I'll pass things to Cashel for the operations review.
Cashel Meagher
executiveThanks, Raman. Turning to Slide 9, Pinto Valley turned out 14,100 tonnes of copper in Q3. Average mill throughput came in at roughly 48,000 tonnes per day, and it took a hit from unplanned downtime on the water pumping system at one of our large make-up water sources, along with a thickener rate failure that affected our ability to run at full rates. At present the mill is running at normal throughput levels, since we have restored normal operation in those areas. C1 cash costs came to $2.60 per pound, which sat at the upper end of our 9-month guidance range and was $0.22 per pound below the prior quarter. On PV4, we keep advancing engineering detail and network, aimed at extending the mine life with additional tonnage from 2039 out past 2050. Onto Slide 10. In Q3, Cozamin delivered good grades and throughput levels, producing solid copper output of 6,400 tonnes at a C1 cash cost of $1.20 per pound, with both in line with guidance. The paste backfill and dry stack tailings project keeps progressing well and will support the mine's planned long-term sustainability, with completion of the project expected in Q4 and ramp up during the first half of 2023. So far we have invested $41 million out of the total $55 million budget for this project. Cozamin's exploration program remains focused on testing the Mala Noche Vein West Target from surface and underground. Testing of other targets along the San Roberto mine began in Q3, and results from the ongoing exploration program will feed into an updated mineral resource estimate in the second half of 2023. Onto Slide 11. Throughput at Mantos Blancos is steadily improving, averaging above design levels on over 70% of planned operating days in October. Several sampling and testing programs around the new mill A) show that it is running at better-than-expected grinding efficiency. To be specific, this new mill is operating 15% to 20% above design grinding efficiency and drawing 10 megawatts out of the 13 available of motor power. Our operations team is actively working with the mill vendor to raise mill speed and draw more power, while simultaneously increasing throughput of the fine crushing plant to capitalize on the higher efficiencies. We are very pleased with these results and are confident that the front end of the plant can achieve throughput higher than design. October's production performance bears this out, with the mill averaging above the design throughput level on 20 out of 27 planned operating days. The highest daily mill throughput was just under 25,000 tonnes. In August 2022, we filed for the required environmental permits for Phase 2, which adds a further 35% expansion over Phase 1. The feasibility study for this expansion has shifted to the first half of 2023, as we are incorporating recent operating performance and a fresh understanding of where bottlenecks lie. Now on Slide 12. During Q3, cathode output at Monteverde reached 11,600 tonnes, with a C1 cash cost of $3.87 per pound. As John mentioned before, record-high sulfuric acid costs affected this, but those costs have now peaked, and we've locked in asset supply for Q1 2023 delivery at under half the prices we paid in Q3 2022. I visited Monteverde last week, and the momentum and progress on our MVDP project make me very happy; it's still on schedule for construction, completion, and wet commissioning in late 2023. By September 30, we had achieved 67% overall progress and 37% construction progress, having spent $490 million out of the $825 million capital budget for the project. At this stage, with most major equipment now delivered to site, I believe the potential areas for capital escalation are significantly diminished. Referring to the next 4 slides, 13 through 16, construction activities are ramping up substantially, currently 40% complete, with the main concrete foundation work almost finished. As Slide 13 shows, the primary crusher, the concentrate thickener, and the filter building are well advanced. Slide 14 displays the grinding and flotation areas. Then on the right, you can see the ore stockpile and reclaim infrastructure area. Slide 15 shows work at the tailings thickener plus the trenching and wall construction for the tailings storage facility. On Slide 16, there's a photo of a mill shell. Right now, all major components for the wet and dry circuit have arrived at site. You'll also notice the electric rope shovel. It's #1 of 4 and has been running on the pre-strip for several weeks now, with the second due to be commissioned imminently, and the final third and fourth to follow. Work is advancing on all fronts of the Monteverde development project, and we look forward to hosting our Chile tour in just 2 weeks' time. Lastly, on Slide 17, work continues on the Monteverde Santo Domingo district integration plan. This plan will set out how we use our existing and future plan infrastructure to maximize value creation across the district. Our aim is to build a world-class district able to produce 200,000 tonnes of copper annually at low cost, with the added benefit of a leading cobalt business that would rank among the largest outside the DRC and China; we keep maturing the overall strategy for the district, balancing potential revenue opportunities against cost-saving synergies. We know the desalination plant, the electrical infrastructure, the operating team, and the project delivery team will all greatly benefit Santo Domingo, and conversely, the port, the future cobalt plant, and the potential additional oxide leach production from Santo Domingo will benefit Monteverde. We look forward to discussing this in more detail soon when the plan is released, and we can talk about it during our site tours 2 weeks from now. I'll now hand things to Wendy King for the sustainability review.
Wendy King
executiveThanks, Cashel. We've reached Slide 18 now. Monteverde and Mantos Blancos formerly became participants in the Copper Mark assurance framework in August, and that's something we're proud of. Over the next 12 months, they'll finish a self-assessment along with an independent assessment against the Copper Mark criteria. Work on setting our greenhouse gas emissions targets carried on through Q3. We focused on building the business as usual forecast, which will serve as the base case for our decarbonization pathway. We've also begun reviewing Scope 3 emissions at our Chilean sites, and in 2023 we'll start assessing broadly across Capstone. Our initial ESG priorities have been set, and they appear on the right of Slide 18, and we're developing and rolling out our goals, emissions targets included, very soon. Monteverde inaugurated the first of 4 electric shovels, and during the expansion phase that will help cut the site's Scope 1 greenhouse gas emissions. Pinto Valley hosted its annual Old Dominion's Day event, a celebration of mining history in the region. It offers a valuable chance for broad stakeholder engagement and lets members of the surrounding area take guided tours at the site. Pinto Valley also finished its Peeples Pond construction project, with a liner installation and pump system supporting water conservation and reuse. We're in discussions with some key corporate partners about backing community investment projects in Chile and Mexico, so we can further enhance our social impact in these regions. Cozamin moved the remediation of the historic Chiripa tailings site forward, securing a final permit for the confinement cell. Chiripa stands out as an important example in the industry, since it's one of the few historic remediation projects in Mexico. Lastly, Mantos Blancos successfully submitted its environmental impact statement for raising the concentrator capacity for the Phase 2 expansion. I'll now hand it over to John for final remarks.
John MacKenzie
executiveThanks, Wendy. Last, on Slide 19, we’re reiterating the guidance range for production and costs for the 9 months, and we expect to produce roughly 185,000 tonnes of copper over 12 months in 2022. Our focus is still on executing the near-term growth profile, lifting copper output by 40% to about 260,000 tonnes by 2024 as the Monteverde development project is completed, and that project is still on time and on budget. After that, we have a fully permitted transformational project at Santo Domingo, with the taxability agreements in place to move it forward, and it unlocks another 45% of copper production growth to 380,000 tonnes per year, with more upside and expansions across our portfolio, including an exciting cobalt opportunity at Monteverde and Santo Domingo; with that, we’re ready now to take questions.
Dalton Baretto
analystJohn, to kick things off, could you share your perspective on the proposal from the Boric government regarding the new mining royalty that was achieved last week?
John MacKenzie
executiveDalton, appreciate the question. Perhaps I'll begin by noting that, obviously, 2 processes have been underway. The first is the constitutional referendum, and the second is the new royalty legislation. As we all saw, the draft constitution got rejected by a very significant majority, 62% against 38%, a few weeks back. Yet about a year ago, 80% of Chile voted in favor of changing the constitution. So our belief is that it's most probable the constitution will keep being adjusted, adapted and changed. Still, it appears to be heading toward a process that should end up with a far more measured outcome. That process is right now being discussed in parliament. Regarding the royalty proposal, the new proposal certainly represents a very significant step in the right direction. The previous proposal, I think, would have turned Chile into something of an outlier; this new proposal moves very much back closer to where, I suppose, tax rates sit in other jurisdictions. In our view, it's still work in progress. In its current form, it will still act to make Chile less competitive than it would otherwise be. So we will certainly keep engaging with the government and seek an outcome that is a win-win for both Chile and mining companies.
Dalton Baretto
analystGreat; and then perhaps I could shift direction a little for my second question. That integration study coming out next week — could you tell us how much detail we're going to see?
John MacKenzie
executiveYes. I think, Dalton, for that I might just hand you over to Cashel, who's clearly been very close to that study; so over to you, Cashel.
Cashel Meagher
executiveRight, Dalton. What I think we have to recognize is that ever since those 2 companies were integrated, we've seen an enormous amount of opportunity — and it keeps revealing itself across the different operations, whether that's Mantos Blancos, Cozamin or Pinto Valley, but especially in the integration zone between Santo Domingo and Mantoverde, where the deeper we dig, the more we find. And knowing that the last technical report for Santo Domingo dates to 2018, and that it now stands to gain greatly from the infrastructure already in place at Mantoverde, there's a substantial amount of engineering work needed to bring things up to that standard. So I think you can look at it this way: you'll get a sense of the scope and the benefits of the existing infrastructure, while we'll set out the timeline for some of the more detailed work and more of the feasibility work — meaning what the cobalt flow sheet is, when we expect the oxide at Santo Domingo to be delineated, and that kind of thing. But we can certainly provide more detailed color on what the expectations are, or what the value could be, from adding a port to Mantoverde, or adding the desalination plant, or some of the electrical power infrastructure. The real difficulty is that the technical report is dated and new information keeps coming up, so this isn't a subtraction from the prior CapEx because of inflationary pressures plus some design considerations and optimizations. So what we hope — what we're going to set out is this optimized pathway going forward, and the fact that certain key infrastructure integrations materially affect Santo Domingo's efficiency from here on.
Dalton Baretto
analystAnd perhaps I could fit one more in. Regarding PV4 as you work through that, are you only looking at extending the mine life, or will there also be a production expansion?
John MacKenzie
executiveGo ahead, Cashel.
Cashel Meagher
executiveYeah, we’re constantly looking at the opportunity to expand. Expansion opportunities do exist. At this point, we’ve got them in what we’d describe as an evaluation or trade-off or value engineering process. The base case is obviously a life expansion, bringing in the reserves and developing appropriate tailings options. Alongside that, though, we’re also assessing the chance to grow the operation. So multiple trade-offs of that kind are in progress. Again, I’d say the base case involves additional reserve to mine life, yet there is potential for some expansion that’s being assessed alongside it. But the jury is still out and we don’t yet have the scorecard in.
Orest Wowkodaw
analystI'd like to build on what Dalton asked regarding the Chilean operations. I'm curious where things stand at the moment on Santo Domingo, especially considering how uncertain the market is right now for projects and for copper itself. Do you still see construction at Santo Domingo getting underway soon after Mantoverde wraps up, or should we expect a longer pause, with the balance sheet being rebuilt first, before you commit to another large project?
John MacKenzie
executiveThanks, that's a really good question. As you probably know, we've said before that we don't intend to run 2 major projects at the same time. So our clear priority is to finish Mantoverde and get it ramped up. That project should be done and first ore should come through around the end of next year. That gives us some room, to a degree, to evaluate the macro environment. On top of that, I'd say overall we're fairly conservative in how we manage our balance sheet and how we think about future commitments. So the timing for Santo Domingo will obviously factor in the Mantoverde ramp-up, the cash building up in the business, and today's macro conditions. That covers both copper prices and the inflationary picture. We're using this period to push the studies ahead and move them forward. So we stay flexible and can pull the trigger at what we see as the best moment. Obviously, that decision involves multiple parameters we have to weigh. In an ideal world, clearly, we'd want to pull the trigger on Santo Domingo during a tailwind, perhaps when the market is a bit weaker and capital inflation is a bit lower, rather than waiting until copper prices are really booming. So we'll factor all of that in, but ultimately I think it will come down heavily to how confident we are about keeping a strong balance sheet.
Orest Wowkodaw
analystAll right, and as a follow-up to that, then. So when I consider roughly your projected start-up schedule and then a ramp-up for Mantoverde, that would point me toward roughly the earliest schedule being, say, the second half of '24 for that project to be sanctioned. Is that the correct way to look at it?
John MacKenzie
executiveThat's a fair comment, I think, Orest. I think we — like I said, I think roughly once construction is finished and ore has been put through, I really do think — we're quite hopeful that the Mantoverde ramp-up will go fairly smoothly; it's a tried and tested design that we have, tried and tested equipment, and the team from Ausenco that we're working with has, over the past few years, ramped up in a very impressive form several of these sort of almost identical concentrators before; so I think we're fairly optimistic about the ramp-up schedule. But clearly, then we want to be in a position where we can sort of assess the cash build in the business and the macro environment, and then we'll take into account what represents the optimal point to pull the trigger on Santo Domingo.
Orest Wowkodaw
analystAlright. And then regarding Santo Domingo specifically. Prior to the merger, 2 infrastructure deals were under consideration to lower the upfront capital port rail. Do those remain in the new plan? Could you perhaps update us on where those 2 proposals stand?
John MacKenzie
executiveYes, absolutely. And Orest, on that point, I'll hand over to Cashel; but to be sure, both of those are essentially at the detailed investigation study stage.
Cashel Meagher
executiveOrest, yeah, so now that we're a combined entity, rather than rushing ahead on these — as you pointed out and John articulated nicely — we're basically holding off on Santo Domingo until the economics look right, and we don't want to create extra complexity or workload by juggling two projects at once. That said, we still have a full Santo Domingo office staffed with engineers and business folks who are assessing the various integration options. It becomes more complicated once you bring in the potential for cobalt — not just from Santo Domingo but from Mantoverde as well — and the possibility of oxide from Santo Domingo being used at Mantoverde to fill some of the unused capacity at the SXW. Meanwhile, we're also concentrating on the other big revenue source at Santo Domingo, which of course is iron ore. And iron ore is really the driver behind serious port evaluation — that being the Port of Santo Domingo — or the notion of trade-offs, which is still being worked through: trade-offs between slurry and filtering at the port versus hauling by rail. Those trade-offs remain ongoing, purely because of how the two assets integrate — the return water, water quality, the placement of pumping stations, what the electrical infrastructure looks like; so at first glance they appear quite straightforward. Once you dig into the specifics, though, there’s a correct approach, and that’s what we’re moving toward. So we continue keeping those partners and partnerships involved regarding what those trade-offs involve. They remain in ongoing discussions with us regarding which scenario serves Capstone's shareholders best, and we are keeping our Mantoverde joint venture partner informed and involved concerning the optimal path for that JV as well; and without fail, whatever proves best for Capstone Copper and Santo Domingo likewise proves best for Mantoverde, along with the sharing and all such optimizations; so those conversations, those relationships, and those assessments all continue to form part of this value engineering effort and trade-off process.
Orest Wowkodaw
analystSo is that going to be made clear by the integrated study coming out next week, or do we need to wait for the updated feasibility for that?
Cashel Meagher
executiveWhat I think it does is, over the next couple of weeks, we'll be able to disclose what we're working on specifically and what the merits of each are, but a final evaluation of that we won't have. That will come as engineering gets more detailed and trade-offs mature; so yes, it's about laying out the pathway in the map more clearly, and then in time those evaluations will reveal themselves.
Orest Wowkodaw
analystAll right. If I can fit in one more question. Regarding the Mantoverde sulfide project, what amount of contingency is included within the $825 million CapEx? And how much of that has been used so far?
John MacKenzie
executiveYeah, I believe the key thing is to look at that total number and what it — roughly what it consists of. And I think you heard a bit earlier during Cashel's presentation that it's really composed of a number of categories. So one is the EPC lump sum turnkey project with Ausenco. A very big portion of that is fully fixed price. There's a piece of it that relates to some of the earth moving at the tailings facility. But that portion now has — is very nearly cast in stone. And then the other significant cost items are the mining equipment. Well, all of that mining equipment is in fact priced and the great majority of it has already been delivered. And then the remaining part, roughly speaking, is the pre-strip. And clearly, the prior increment we reported was mainly centered on that. And that came about because of higher diesel and explosive prices and the effect those had on the pre-strip. So we have, I'd say, a modest contingency left within that $825 million figure. That's roughly a handful of million dollars; but at this point, we see relatively limited room for any further cost slippage.
Ralph Profiti
analystPerhaps a couple for Raman, if I may. Raman, regarding the QP program, is the aim to fully hedge out provisional pricing? The MD&A still discloses open pounds for Q4. I'm just curious how long you'd anticipate the QP program staying in place? Might we see it sort of fall away once we reach higher copper prices?
Raman Randhawa
executiveYes. So the QP hedging program will just — it's going to keep rolling. We launched it in the first month of September, which is why there's some open exposure in the MD&A there covering a couple of months of Q3. So you'll see that sort of clear out here in Q4 now, and then that ought to be our final quarter of really carrying provisional prices. Basically, with the concentrate business, you have a 3-month kind of floating price out there. We're essentially swapping that for a 1-month kind of near-term fixed price, so locking in a price closer to it rather than having that exposure out there. And basically, when you shift to this, Ralph, we just stay on it because what we observed, I think we talked with you about it a little, is that when the price drops, it drops hard, and you lose a lot of money. When it rises, it doesn't rise as quickly. So this essentially lets us achieve LME average each quarter, but you'll probably start seeing that in a full quarter in the first quarter Q1.
Ralph Profiti
analystYes, that helps. And for my second question, how solid is the liquidity in the sulfuric acid market for locking in those Q1 '23 prices into later quarters, roughly speaking? Is there a target you have for the share of sulfuric asset exposure you want hedged?
Raman Randhawa
executiveYes, I'd say it's a fluid strategy that actually gets discussed at the Exco every week. But usually the fourth quarter is when you can make a pivotal call on how much you want to fix versus float, let's call it, for the following year; so as we mentioned, we've begun fixing into Q1 for Mantoverde. Those are really good prices at 120%. And then, based on our market intelligence, we can decide whether we want to fix a bit more here in the fourth quarter going into next year or leave a bit more open to spot. So we'll work through that strategy here in the fourth quarter, and that will be baked into our 2023 guidance then.
Stefan Ioannou
analystI just wanted to ask about Pinto Valley, where throughput came in lower last quarter, around the 48,000 tonne mark, versus PV3, which I believe was aiming for roughly 58,000 tonnes a day. It sounds like some capital went toward water retention and water infrastructure. Should we take that to mean there's a seasonal problem here, or is it just something to consider going forward? And with the new infrastructure in place, do you think we'll really be able to sustain that 58,000-tonne a year across the whole calendar year, or will it be a summertime situation where throughput drops simply because of water?
John MacKenzie
executiveI'll hand that question over to Cashel.
Cashel Meagher
executiveYes, Stefan, the seasonal pattern is definitely real. It is no secret that Arizona gets very hot during that period. A large portion of the water we use, or much of what serves as makeup water, actually comes from groundwater sources. That supply is influenced by annual recharge. As a result, it is affected less by immediate growth in recharge and by securing that extra makeup water. The infrastructure items we mentioned, including some of the thickener problems, the rake, and certain water infrastructure, were in fact separate breakdowns that curtailed our capacity to capture some of that recharge water. So in a way that falls on us, in terms of how we manage infrastructure and assets moving forward, to reduce that exposure. That said, reclaim water is certainly one of the main water sources as well. It involves recycling and reusing water, and that takes place within our operations — mainly in the thickeners and our tailings stand, where we recover water. When conditions are dry, we are hurt in the sense that the natural reclaim of water, from wherever the spigotting occurs to where the reclaim pumps are located, declines in those seasonal periods. So at a local level, what we do is plan for the additional production. If you remember — I believe this happened before my time, in Q4 of 2022 — Pinto Valley had very strong production, and that was because reclaim was very high and they could reuse the installed capacity in the mill to reach more than 58,000 tonnes per day. So the likely approach going forward is to structure things that way, though I still think we are examining the details and working through exactly where we will land with our late January guidance, since each year we publish what is expected from Pinto Valley; but on average, it will be in the high 50s. Seasonally, however, we will need to profile that water dependence on reclaim while also gaining much more confidence in our freshwater makeup capability, with a stronger emphasis on asset integrity for 2023.
Bendik Nyttingnes
analystThere isn’t a lot I still have, though I’ll put one question about those premiums we keep hearing about. Over the past couple of weeks, I believe several news stories have come out about premiums for customers in Europe and Asia taking effect in 2022; those are well above where we are seeing them today. Will you be in a position to take advantage of that?
John MacKenzie
executiveAppreciate it, Ben. I’d like to hand things over to Jerrold, who has also recently assumed marketing duties. Jerrold, over to you.
Jerrold Annett
executiveThanks, John. I think you're referring to the cathode premiums, Ben?
Bendik Nyttingnes
analystRight.
Jerrold Annett
executiveAll right. A third party is handling the marketing of our cathodes for us. As I understand it, that arrangement runs through the end of 2025. At present, we aren't getting the benefit of the higher premiums. Once 2025 is behind us, though, we will, and so we're eager for that point when the premium upside can be realized.
Craig Hutchison
analystI've just got one question, and it concerns Mantos Blancos Phase 2, taking it from 7 million tonnes up to 10 million tonnes. There's a note saying you filed the DIA application back in August 2022 for the environmental permitting, I assume. Could you talk about what Phase 2 permitting involves and how burdensome that process is?
John MacKenzie
executiveYes. I'll certainly take a first stab at that, and then I'll hand it over to Cashel. In Chile, though, permitting comes at 3 different levels. There's what they call a pertenencia, which is merely a minor adjustment, generally something within a plant. Then there's a DIA, which means some extra throughput or scale, or more material heading into a tailings facility. And then comes the EIA, the fully fledged environmental permit. Our belief, and the authorities have accepted this, is that this Monteverde expansion falls in the middle category, the DIA. So it's basically a fairly straightforward process. It really just means some additional processing infrastructure inside what is essentially an existing brownfield plant. And clearly, the main reason it triggers a DIA rather than just a pertenencia is that we'll actually be increasing the quantity of reserves to be processed, and that will go into the tailings facility. But what we're doing is doing that within tailings facilities that already have permits, and we believe it should be fairly straightforward. So I think our expectation is that this permitting process will be relatively straightforward. Obviously, though, we do need to make sure we dot the I's and cross all the T's on it. Cashel, is there anything further you'd like to add?
Cashel Meagher
executiveNo. No, I think that explains it well, John.
John Tumazos
analystNice work on that big derivative gain. Are you able to unwind the derivative positions and simply pocket the profit? And if that's possible, would you actually want to?
John MacKenzie
executiveThanks for asking, John. I'll hand things over to Raman so he can answer that.
Raman Randhawa
executiveJohn, that's a fair question. If you look at the mark-to-market on our hedge book, it breaks into 2 parts, roughly. Part of it is corporate hedging that we do up here. So yes, we sit in a profitable position that we could potentially close out if we chose to. And then another portion of the hedge book is tied to the project financing. It was a requirement of the Mantoverde development project facility. So those hedges are in place relative to that debt structure we have put in place; so doing that or unwinding that would require a bit more discussion with lender consent.
John Tumazos
analystIs there a broad principle you follow when it comes to hedging — given that prices can bounce back and move against your position?
Raman Randhawa
executiveJohn, please go ahead.
John MacKenzie
executivePerhaps, before I hand things back to Raman, I could just give a sort of high-level view: our hedging philosophy is really a defensive kind of strategy. Clearly, right now we have considerable capital expenditure on our projects, and we have some high-cost cathode production. From our standpoint, it still seems sensible and prudent — whether we are locking in on the cost side or the revenue side — to do so in order to ensure our balance sheet stays strong through the construction. I think as we move toward lower-cost operations, we will at that point be revisiting our hedging philosophy. But clearly, there are matters such as capital projects where our view is fairly standard — when we move across to Santo Domingo, for instance, if we raise the financing in U.S. dollars, we will look to, for instance, hedge out any peso exposure within that capital and ensure that, at the end of the day, we are able to manage the capital expenditure. Still, I do think that while we are in this particular phase, we are very much focused on a strategy to protect margins during our major construction. So Raman, I don't know whether you would like to add to that?
Raman Randhawa
executiveI believe that point came across nicely. Basically, when it comes to our hedging approach, the goal is to hedge away input costs — namely FX and interest rates — and to lock those in from a guidance cost standpoint. Copper, then, is looked at purely from a risk management angle, or — as John mentioned while MVDP was being built, historically we have typically actually been unhedged on copper. And with the QP hedging we referred to that we've brought in, it will be small, but it is very short-term in its outlook.
John Tumazos
analystWould you rule out alternative risk management approaches, such as issuing equity or bringing in a partner?
John MacKenzie
executiveWell, I wouldn't say — we definitely don't rule those approaches out. What we do, though, is examine what financing options are available to us. We examine our balance sheet. And then we usually rank what our preferred methods of finance tend to be. At this point, I'd say we stay comfortable that such steps are neither desirable nor necessary. Having said that, going forward, when we consider the Santo Domingo project, we'll clearly be evaluating it against both the base case project and possibly the oxides and the cobalt. And at that point, we'll want to determine whether, say, an equity partner in the project would make sense.
John Tumazos
analystLet me just jump in here, because one thing that worries me is that we're in a period of very high inflation. And if you lock in your selling price while leaving your cost unfixed, then unanticipated inflation leaves you exposed — that's basically it; it's a different kind of risk.
John MacKenzie
executiveJohn, you're completely correct. And we attempt to take what I'd call a really considered approach to this. On one hand, we do try — for instance, in our high-cost cathode business — we do try to ensure that we're sort of locking down our biggest cost components, such as the asset price at roughly the moment we're locking in our copper price; but having said that, you're completely correct as well, when — if copper rises to $5 a pound, you'll see cost inflation across a number of other areas. And so what we aim to do is ensure we're not over-hedged on the copper, and we can be confident that the net benefit from that higher copper price will outweigh any other inflationary increase on any unhedged portions of our cost inputs.
John MacKenzie
executiveOkay, as we talked about earlier, we're putting a lot of effort into delivering the integration plan for the Mantoverde and Santo Domingo district, and into hosting our Chile tour in 2 weeks. We're really looking forward to seeing those of you who'll be joining us and to showing off the exciting growth opportunities that are underway and that lie ahead of us. In January, we'll announce the date when our year-end results will be released. So until then, stay safe, and don't hesitate to reach out to Jerrold or Kettina if you have any more questions. Thank you for your continued support, and have a good day.
Operator
operatorThank you. That brings us to the end of today's call, ladies and gentlemen; we appreciate your participation, and please go ahead and disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.