Operator
operatorHello and good morning. Joelle here, and I'll be your conference operator for today. Right now, I'd like to welcome all of you to Capstone Copper's conference call covering the Q1 2023 results. Every line has been muted so that background noise stays out. Once the speakers finish their remarks, we'll open things up for a question-and-answer session. <<operator_script>>. Thank you. Mr. MacKenzie, the conference is now yours to begin.
John MacKenzie
executiveThanks. I'll hand things over to Jerrold Annett, who has a few opening remarks for us.
Jerrold Annett
executiveGood morning, everyone, and welcome to Capstone Copper's Q1 2023 conference call. I want to point out that the news release and regulatory filings announcing Capstone Copper's 2023 first quarter financial and operational results can be found on our website and on SEDAR. For those of you logged in to the webcast, we will be advancing the slides for today's presentation, which you can also find in the Investors section of our website. With me today are our CEO, John MacKenzie; our President and COO, Cashel Meagher; our Chief Financial Officer, Raman Randhawa; and our Senior Vice President, Risk ESG and General Counsel, Wendy King. After our brief remarks, we'll open things up for questions. I should note that comments made on the call today will contain forward-looking information within the meaning of applicable securities laws. By its nature, this information is subject to risks and uncertainties, and actual results may differ materially from the views expressed today. For more information on the risks and uncertainties pertaining to our business, please see Capstone's most recent filings, which are available on our website and on SEDAR. And finally, I'll just note that all amounts we will discuss today are in U.S. unless otherwise specified. Now, I'll turn the call over to John MacKenzie.
John MacKenzie
executiveThanks, Jerrold, and good morning, everyone. We're happy to share the results and achievements from our first quarter of 2023. Most importantly — and we're now on Slide 5 — we're glad to say that building at our transformational Mantoverde Development Project, or MVDP, is still on schedule and within budget, and close to 3 million tons of sulphide ore have been stockpiled so far, ahead of the ramp-up that begins late this year. On the left, the photo shows part of the overall progress of construction at the processing plant, and on the right you can see sulphide ore being mined at Mantoverde for the first time. This year is a pivotal one for Capstone, since we expect MVDP construction to be finished in Q4, which sets the stage for consolidated cash flow to double and puts us in a good position for future growth. I'd also like to point out that last week we arrived at a new collective agreement with the two labor unions at Mantos Blancos. That comes after successful agreements with our labor unions at Mantoverde and Pinto Valley during the past 12 months. So across all of these operations, we now have agreements in place covering the next three years. Moving to Slide 6, operationally we had a challenging Q1 2023, which was marked by heavy rainfall at our Pinto Valley mine in Arizona.
John MacKenzie
executiveSo in total, we turned out 40.7 thousand tonnes of copper, with consolidated C1 cash costs sitting at $2.96 for each payable pound of copper we produced. Beyond the weather-driven difficulties at Pinto Valley, over at Mantos Blancos in Chile, our push on preventative maintenance led to greater downtime and reduced throughput. That said, very strong recoveries and continued strong grades gave us encouragement. At Mantoverde, we mined lower grade oxides during the quarter, and those carried higher acid consumption. On top of that, carryover inventory of sulfuric acid came with elevated prices. Even so, for the rest of this year we are locked in for roughly 80% of sulfuric acid consumption at Mantoverde at $140 per ton. Spot prices have come down recently to under $100 per ton, compared with prices above $280 in 2022. If prices stay at today's levels of $100 per ton, our C1 cost for oxides could fall by as much as $0.40 per pound next year. Finally, at Cozamin our attention was on development and on ramping up the paste backfill plant. Despite that slow start — and moving to Slide 7 now — we are reaffirming our 2023 consolidated guidance for production, cost and capital. We expect output to rise sequentially, quarter over quarter, through the rest of the year, with costs coming down in step.
John MacKenzie
executiveMarch brought a big step up in how things are running at Pinto Valley, and that site is now in good shape, since we have no major shutdowns on the schedule for the remainder of 2023. Along with that, we expect both grades and throughput to rise, and the same holds true for Cozamin. Finally, throughput at Mantos Blancos should be higher through the balance of the year. With that, I'll hand things over to Raman for our financial results.
Raman Randhawa
executiveThanks, John. Turning to Slide 8 now. Copper sales in Q1 came to 37.5 thousand tons, and that figure includes a sales lag of roughly 2.4 thousand tons stemming from shipment timing in Chile. Those sales should be made up during Q2. LME copper prices averaged $4.05 per pound in Q1, a 12% increase from $3.63 per pound in Q4 2022. Because our 2p <<inaudible>> hedging program hedges 0M+ 1<<inaudible>>tied to our commercial contracts, the copper price we realized, $4.17 a pound, came in a bit above the quarterly LME average. Consequently, we recognized revenues of $336 million for the quarter. Adjusted EBITDA for Q1 was $65.2 million, and that number was affected by the sales lag, reduced production, and elevated costs caused by heavy rainfall in Arizona, along with higher Q4, 2022 sulfuric acid inventory carried over into Q1, 2023. The adjusted EBITDA figure also takes in realized foreign exchange losses of about $9 million and derivative losses of $8 million. Excluding the FX and derivative losses and the sales lag, EBITDA would have come to roughly $85 million. Now to Slide 9. On the left-hand side we summarized the liquidity available to us, which as at March 31 stood at approximately $529 million, comprising $101 million of cash and short-term investments plus $428 million of undrawn amounts under our $600 million corporate revolving credit facility.
Raman Randhawa
executiveWe've completely drawn down the $520 million project debt facility, along with the $60 million cost overrun facility, together with our Mantoverde partner Mitsubishi Materials Corp. As John said earlier, we're still on track and on budget to finish the Mantoverde development project by the end of the year. Q1 closed with a consolidated net debt balance of $651 million and an attributable net debt balance of $492 million. The chart on the right-hand side of the page shows our EBITDA sensitivity at different copper prices. As you can see, 2023 is overshadowed by the EBITDA generation once Mantoverde sulfides are at full run rate production. At $4 per pound copper, we expect to generate approximately $400 million of EBITDA in 2023 and over $1 billion of annual EBITDA when the Mantoverde Development Project is online. Although the Santo Domingo project is currently unsanctioned, it has the potential to further increase our EBITDA generation to about $2 billion per annum with metal prices at current levels. The EBITDA generation associated with Mantoverde will enable an accelerated opportunity to delever our balance sheet and be below one times net leverage at copper prices between $3.50 and $4 per pound, which provides additional liquidity to advance our future growth pipeline.
Raman Randhawa
executiveAt this point, I'll pass things along to Cashel, who will walk us through the operations review.
Cashel Meagher
executiveThanks Raman. We're now on slide 10. During Q1, Pinto Valley turned out 12.8 thousand tonnes of copper at a C1 cash cost of $3.09 per payable pound, which came in under what we had expected. The main reason was weather-related difficulties — in particular, heavy rainfall in February created stickier wet ore, which is harder to process and hurt throughput. More importantly, it also kept us from reaching some of the lower benches in the pit that carry higher grades. Going forward, we're encouraged by solid production through April, and we are reiterating our guidance, since we expect sequential improvements quarter-over-quarter. As John noted, we also have no significant maintenance planned for the rest of 2023. On growth at Pinto Valley, we're increasingly enthusiastic about the potential for district consolidation. Because of that, our efforts are now focused on analyzing the impacts of potential district opportunities, and we have deferred our PV4 study. Moving to Slide 11. Cozamin had a transitionary production quarter, producing 5,200 tonnes of copper at a C1 cost of $1.72 per payable pound. For the rest of the year, we expect throughput and grades at Cozamin to rise. Today we also released an updated technical report at Cozamin to reflect changes in the mining method that we disclosed last quarter.
Cashel Meagher
executiveThe technical report shows average copper output of 20,000 tonnes with a C1 cash cost of $1.51 per pound, plus a higher average of 24,000 tonnes at a C1 of $1.46 per pound during the first five years. The new mine sequencing combines long-hole stoping with cut and fill. We made this shift drawing on what we've learned about the ore body so far, and we think it will deliver better mining recovery than sticking solely with long-hole mining methods. We also see several chances to enhance the life-of-mine plan, such as exploration, refinements to cut-and-fill that reduce dilution, and the potential for drift and fill methods to boost pillar and post recovery. Regarding exploration, the Mala Noche Footwall Zone deposit remains open toward the Northwest, Southeast, and down dip. Our Mantos Blancos asset is featured on Slide 12. Combined sulfide and cathode production came to 14.1 thousand tonnes of copper, at a blended C1 cash cost of $2.68 per payable pound. The sulfide operation achieved its strongest quarter to-date, driven by better grades and recoveries. Current efforts are aimed at raising overall reliability and lifting production uptime. On that point, unplanned maintenance and process improvement initiatives affected production and costs during the quarter.
Cashel Meagher
executiveOn the growth side, design work for Mantos Blancos Phase 2 continues. Turning to Mantoverde on Slide 13: first-quarter 2023 oxide output came to 8.5 thousand tonnes of copper in cathode, with elevated C1 cash costs of $4.02 per payable pound. As John noted, those costs reflected reduced production along with the carryover of high-cost sulfuric acid held in inventory. Above all, Q1 brought substantial advancement at MVDP. Project progress is now at 83%, and $654 million had been spent as of March 31. With a good number of the classic major escalator risks now behind us or significantly receding, the project's overall expenditure stays at $825 million, on track for wet commissioning by year-end 2023. The Mantoverde development project is set to deliver blended C1 costs under $2 per pound and to produce 120,000 tonnes of combined cathode and copper and concentrate, together with more than 30,000 ounces of gold annually. Slides 14 through 18 illustrate construction progress across several key areas of the Mantoverde Development Project. Slide 14 depicts the primary crusher, where the retaining wall and conveyances are coming along nicely. Structural steel erection is progressing well too, as the copper filtration building, column cells, and rougher cells demonstrate; every major component has been procured and delivered on-site and is now in the final tie-in stages.
Cashel Meagher
executiveSlide 15 gives you a look at the copper concentrate thickener, plus another angle on the copper filtration and load-out facility. In the right-hand image, you can clearly see how far assembly of the SAG and Ball mills has progressed. Moving to Slide 16, this is the truck shop, and the photo on the right shows the core seller stockpile along with the reclaimed tunnels, which are being readied for construction of the geodesic dome for dust control. Slide 17 highlights the interior of the desalination plant on the left, where the expansion to 380 litres per second remains on track for completion in Q2. The tailings facility appears on the right. I'll now hand things over to Wendy King for the sustainability review.
Wendy King
executiveThanks, Cashel. Moving to Slide 18 now. Back in March, we were delighted to share news of our fresh Sustainability Development Strategy, which contains concrete targets for greenhouse gas emissions. Putting that strategy together took a structured 12-month effort involving stakeholders from across the whole company, and it lines up with our purpose and values. Oversight and execution of the strategy sit within a strong governance process. This strategy mirrors our strong dedication to sustainability and lays out the priorities, actions, and targets we will pursue across the coming seven years, centering on five initial priorities: Climate, water, tailings, biodiversity and communities. Within the climate priority, we aim to cut greenhouse gas emissions from fuel and power by 30% by 2030 against 2021 baseline levels. On tailings, our goal is for 100% of our tailings storage facilities to receive independent assurance of conformance with the global industry standard for tailings management by year-end 2026. If we turn to Slide 19, let's go through our quarterly sustainability highlights. At Mantos Blancos and Mantoverde, the self-assessment states for the Copper Mark assurance process are now complete, which lets us proceed to the independent review in Q2. We have finished the human rights assessment update as well as our annual review of the grievance mechanism.
Wendy King
executiveThe Copper Mark gap assessment is now finished, and we've started planning projects aimed at formally addressing whatever gaps were identified so we can move ahead with the Copper Mark assurance process at Pinto Valley. Over at Mantoverde, we've brought in rotainers for shipping concentrate, and these are viewed as an industry best practice. Rotainers count as an ESG-friendly transport option because they allow for dust-free operation. Each concentrate container comes fitted with ISG's pathogen <<inaudible>> removable hard lid and is sealed. The design additionally guarantees that no contaminants are able to build up and accumulate on the containers' exterior. At Pinto Valley, we run a donation program together with a Navajo Reservation in which a portion of our non-sellable copper goes toward making jewelry and other craft items. A photo we received recently, shown at the bottom right, highlights some of the crafts that students at the reserve created. Our first combined sustainability report, Growing Responsibly, is progressing well and is set to be published in early Q3. We're working to bring more climate discussions into our mainstream disclosure documents, going beyond the sustainability report, so as to deepen our disclosure across the four TCFD areas: governance, strategy, risk management, and metrics and targets. With that, I'll hand it back over to John.
John MacKenzie
executiveThanks, Wendy. Slide 20 highlights the major catalysts we have coming up over the next two years that back our sector-leading growth plans, with additional upside beyond that throughout our portfolio. We've got a skilled technical group in place and we're collaborating with solid engineering companies to carry out these studies, and we look forward to sharing the results within the timelines the slide shows. To be specific, before the year ends we intend to publish our optimized MVDP study, which aims to raise throughput from 32,000 tons per day to as much as 45,000 tons per day without needing major capital equipment upgrades. We're also considering a possible additional expansion that might involve installing a second processing line. In the meantime, we're active at Mantos Blancos assessing whether we can lift throughput from the installed 7.3 million tons per annum to 10 million tons by using the existing Ball mills and processing equipment that are underutilized. Then, to wrap up the year, we intend to publish an updated feasibility study for Santo Domingo in December. And to finish on Slide 21, we restate that Capstone is in the middle of a transformational year. We stay laser focused on delivering our near-term growth profile, lifting copper production by 45% to roughly 260,000 tons, after the ramp-up at the Mantoverde Development Project.
John MacKenzie
executiveFollowing that, we turn to the Santo Domingo Project, which is fully permitted, creates synergies across the district, and adds another 45% of copper output, bringing us to 380,000 tons annually, along with more upside and expansions throughout our portfolio. With that said, we're ready to take questions now.
Operator
operatorThanks. <<operator_script>>. Orest Wowkodaw from Scotiabank has the first question. Please go ahead.
Orest Wowkodaw
analystHello, and good morning. It's great to see how far the Mantoverde Sulfide project has come. Since you're roughly nine months away from finishing, could you perhaps take us through what the critical path looks like and tell us where you think the greatest risk sits right now to that year-end startup timeline?
John MacKenzie
executiveAppreciate that, Orest. Maybe I'll begin by restating that the bulk of the traditional risks are now behind us. The infrastructure exists, the big equipment sits on-site, and that big equipment has in fact already been installed. At this point we're moving into pipe installation, the electrical work, and all those components. Still, what we're seeing right now is nothing that raises concern about the schedule. Projects can certainly throw surprises at you, but we believe every one of those elements is under control, and we've essentially removed risk across all the contingencies we could foresee coming up. Let me hand it over to Cashel and see whether he wants to add anything more.
Cashel Meagher
executiveJohn, I believe you've captured it nicely. The biggest dangers we observe in projects carried out over recent years tend to be — the primary one is typically a geotechnical risk, and we've achieved fairly substantial headway on the significant material movement needed at that site. So although we can continue to monitor and assess it, we consider ourselves to be in a strong position, with the tailings dam and the related geotechnical works advancing very nicely. And then the other one we classically encountered throughout the pandemic era was electrical and instrumentation, and I'm glad to report the electrical e-rooms have shown up, the majority of them, and they're underway and being delivered. So what I'd say is the main risks we've witnessed on projects over the past few years are more or less behind us, so now they are the classic or the more basic man-hours, pulling cable, placing pipe and bore in place, and items of that kind, which are simply the effective man-hours and the efficiency of those man-hours on a project. So I'd say at present we're down to the boring risks on a project, and it's simply about getting the work done.
John MacKenzie
executiveAnd I suppose one last point to add is that, clearly, the other thing people always watch is how the mine itself is ramping up, and the last batches of extra mining equipment arrived a few months back. At this stage we're essentially at full ramp-up, and in fact we're now building a stockpile of sulphide ore in front of the plant, and as we mentioned earlier, roughly 3 million tons of sulphide ore is already stockpiled. So I think that gives us considerable confidence as well when it comes to the ramp-up that follows.
Orest Wowkodaw
analystThanks. As a quick follow-up — and honestly, boring is a positive on a project like this — what are your plans for the construction crew once work wraps up at Mantoverde? My assumption is there'll be a pause before Santo Domingo gets underway, but do you stand the team down and then bring them back later? How are you thinking about that at this point?
John MacKenzie
executiveYeah, I think that's a really good question, Orest, and obviously there are kind of two parts to it. One is our owners’ team, and we certainly plan to keep that owners team of ours intact. For us, I think this is the next step as we move to Santo Domingo — obviously ensuring Mantoverde is fully ramped up. We obviously want to get the Santo Domingo financing completed, and we want to kind of take a look at the macro environments at that time, and those three items will kind of guide our timing on decision-making to kind of take a full notice to proceed on Santo Domingo. But I think we can certainly keep our full project team well occupied during that period. I think while we might not make a decision for full notice to proceed, that certainly doesn't stop us from progressing the engineering work, which in any event is kind of the first stage of a project. So really advancing the engineering work and increasing confidence in all the parameters within the project. I think the other element is our key contractor, and I don't know if you're aware, but recently we've changed contractors at Santo Domingo.
John MacKenzie
executiveWe switched from Posco to Ausenco, using the same contractor we have at Mantoverde, and the goal there is likewise to make sure that experience and those people carry over from Mantoverde to Santo Domingo. So I think certainly, for the key members of both teams, the plan is to keep them on for the Santo Domingo project.
Orest Wowkodaw
analystAppreciate it, John.
Operator
operatorThe following question is from Dalton Baretto at Canaccord. Go ahead. Bryce Adams from CIBC has the next question. Please proceed.
Bryce Adams
analystHi there, and thanks to John and the team for fielding my question. I’ve just got the one. I wanted to ask about Ausenco and the lump-sum contract at Mantoverde. During our site visit last November, there was some discussion about inflation—specifically that a capstone of that kind carried less <<inaudible>> inflation exposure thanks to the lump-sum arrangement, and that Ausenco would bear more of that exposure, though they were preserving margin because of favorable FX rates. FX rates have moved since November, so I was wondering whether that dynamic with Ausenco has shifted as well, and whether the change in FX has raised any counterparty risk. Naturally, the ideal contract is one that benefits both sides, so does that still hold true with your partner?
John MacKenzie
executiveYes, this is Bryce, and I believe it was quite fortunate that Ausenco had already secured a great deal of its essentially foundational expenses—so basically all of its equipment, subcontracts, and so on. Much of the, I suppose, primary foreign-exchange exposure, I think, came earlier in the project. So at this point we certainly—I completely concur with what you said, that even though it's a lump sum turnkey contract, it always matters that everyone is earning a profit, and certainly based on what our conversations with Ausenco indicate, the project continues to work well for them.
Bryce Adams
analystUnderstood. Thank you very much.
Operator
operatorCraig Hutchison from TD Securities has the next question. Go right ahead.
Craig Hutchison
analystMorning, everyone. I’ve just got a single question too. Regarding Mantos Blancos, you’ve been hovering around 15,000 to 16,000 tons per day across the past few quarters. I realize in your MD&A it was disclosed that you had, I believe, 18 days at that point, or 20,000 tons per day, and some preventive maintenance took place during the quarter. Could you provide a bit of context on what that preventive maintenance involves, and do you feel confident that we can reach 20,000 tons per day in Q2 or the following quarter or so? Thanks.
John MacKenzie
executiveAppreciate that, Craig. I'll hand that question over to Cashel.
Cashel Meagher
executiveThanks, Craig. Yeah, I think we've mentioned this before — often it's simpler to begin from a blank page than to kick things off with a kind of combined brownfield development, where you're pairing aging equipment with new machinery. At the outset of this project, while it sat within the private equity world, there were particular constraints, and I believe those are issues we're addressing and have been addressing. How I'd frame the project is this: the key components exist and have existed from day one. They were engineered soundly. They can handle the throughput, but a few of the interconnections may not have been designed all that well, and we've been grinding through those on a trial-and-error footing. That said, I think we've adjusted our approach on those, so my confidence is considerably higher now that we've gotten past a lot of the critical problems, where certain smaller bottlenecks disrupted our steady output because of maintenance stoppages. We can observe that and monitor it by comparing how much preventive maintenance we perform against breakdown maintenance, and on all those metrics we're now on the favorable side and following them through, and it's progressing — where perhaps a pump got missed or perhaps a pipe got missed — and now performance is beginning to look more consistent.
Cashel Meagher
executiveThe target for nameplate capacity remains 20,000 tons, and we expect to hit that quite soon and far more consistently. So this ramp-up has differed from what a brand-new construction would involve, since that kind of project gets a different degree of engineering and evaluation applied. On this one, there’s a larger learning curve.
Craig Hutchison
analystSo I suppose at this stage, boosting some of those efficiencies wouldn't really call for any significant capital, right — is that accurate?
Cashel Meagher
executiveNo, and here's the crucial part: the first project took care of the big capital items, so at this point it comes down to the finer details, and we're steadily making our way through those, and I believe we have an excellent plan going forward from here.
Craig Hutchison
analystAppreciate it, everyone.
Operator
operatorDalton Baretto from Canaccord has the next question. You may proceed.
Dalton Baretto
analystApologies — I lost the connection somehow. Let me begin by returning to Mantoverde, and I'm sorry if some of these questions have already come up, since I only just rejoined the call. But you're mining the sulphide ore at this point. You have 3 million tons sitting on the surface. How does that stack up against your block model and what you had expected? Any surprises there?
John MacKenzie
executiveI'll start off with a response, and after that hand things over to Cashel. One benefit we had, I believe, is that we did a thorough job of drilling out the sulphide ore body well in advance. So when you consider the whole life-of-mine plan for the Mantoverde project as it stands, 70% of the reserves fall in the proven category, while 30% sit in probable across the entire mine life. That represents a greater level of confidence than most mining companies can claim even for just the coming couple of years. As a result, we have an enormous degree of geological confidence in the reserve, and what we've encountered so far aligns precisely with our model. What I'd also note is that we're finding things in areas where no reserve or resource has been shown, though that sits somewhat interconnected between the existing pits. We're likewise encountering some very encouraging holes that are being drilled into those areas too. So over time we do anticipate adding to those reserves and resources, and I think that will certainly prove accretive. Cashel, is there anything you would like to add to that?
Cashel Meagher
executiveSure — the sole reconciliation available to us on a stockpile is blast hole data versus diamond drill hole data, and those two broadly line up. So things look good, and that has given us confidence. We have several different stockpiles: transition material, high-grade sulphide material, and then run of the mill materials. That setup is meant to help optimize our ramp-up, so that while we're at lower recoveries, we can feed through material where we aren't exposed to losing copper through those lower recoveries. But then again, we have the high-grade material to feed through once the plant has ramped up, and we can capture the revenues as soon as possible. So they've planned it out really well, and as John said, you might actually call the deposit over-drilled for a measured reserve. It's down to 25 or 35 meters in some places on the diamond drilling, and that has greatly reduced the risk of surprises in grade or in material quality.
Dalton Baretto
analystAlright, thank you for that detail. Then, regarding the Mantoverde studies — or rather the Mantoverde study due later this year — I just want to confirm: will that study cover both the optimization and the expected Phase 2 expansion involving a second line, or will it only address the optimization?
John MacKenzie
executiveDalton, right now our main focus is clearly on the MV optimization, since that's the opportunity sitting closest at hand. We over-designed the crushers and mills, and we believe those key equipment pieces can handle roughly 40,000 to 45,000 tons a day, compared with the 32,000 tons a day in the current project design. Our expectation is to wrap up that feasibility study by the end of this year, and we don't see this as a major CapEx project, though it clearly delivers very, very meaningful extra returns. So we'd aim to permit and implement it about as soon as possible. As for Mantoverde Phase 2, where we'd be considering a full second line, those studies are ongoing, but I'd say it's clearly at an earlier stage, and ultimately we want to be sure we optimize that project in line with the ore body's ultimate capability. So while our near-term focus will be on Mantoverde optimized, at the same time we'll also begin drilling out some of the further portions of the ore body, or rather the concession area, just to ensure that second line represents the optimal, ultimate capacity to move toward.
Dalton Baretto
analystUnderstood, alright. Then a somewhat comparable question regarding Santo Domingo — Ausanco is carrying out the study at present. Will they take into account the wider district along with all the synergies, or will Santo Domingo be optimized by itself?
John MacKenzie
executiveRight, so the Santo Domingo feasibility study is really being — the initial feasibility was completed back in 2018, and what we're doing now is an update covering three elements. The first is sort of relation, the second is exactly what you're asking about, namely the synergies between Mantoverde and Santo Domingo, and then the third is actually some design optimizations. The footprint, for example, at Mantoverde is sort of much smaller in terms of layout and more efficient than the earlier design at Santo Domingo. So we think we can eliminate roughly 35% of the footprint simply through a more efficient layout and design. Now, going back to those synergies, this study will incorporate some of the synergies we identified in November last year. There are others that sit more on the revenue side, and those are, for instance, the processing of the Santo Domingo oxides and the processing of cobalt at Santo Domingo. Those are studies in their own right that are being run in parallel, and I think from recollection we're actually due to present those sort of more like in sort of 2024.
Dalton Baretto
analystOkay, great. And then maybe I could fit one more question in. Regarding the deferral of the PV4 study, could you say anything at all about what you have in mind when it comes to the broader scope and the opportunities, as well as the timing and when all of that might come together?
John MacKenzie
executiveSure — to take your second question first, on timing, the immediate priority for us is getting the Mantoverde development project finished. After that, we'll shift our attention to Santo Domingo, and we'll likely run the optimization work at Mantoverde at the same time. That gives us the time to really examine the Pinto Valley area and figure out the best development plan for it as a district. There are enormous resources there — roughly 1.5 billion tons in total at Pinto Valley. We've also been doing work on BHP's Copper Cities site next door. We think there's another roughly 1 billion tons or so of resource there. It all sits at a grade of, I think we're talking about 0.33% copper. Ultimately, our view is that by building a large-scale processing plant, you can actually achieve highly, highly competitive costs. Obviously, since these are porphyries, we believe you could get decades and decades of flat-lining production there, without any grade decline, at highly competitive costs, by working out the most sensible scale and how to fit it all together in the best, most efficient possible way in that district.
John MacKenzie
executiveThere's a great deal of work ahead of us there, but I believe time is somewhat on our side to get it done. And I think finally this is an area that has been mined for at least the past hundred years, so we see a lot of benefits in the plans we have to develop this district, which would also deliver very, very significant environmental benefits by mitigating some of the environmental issues that past operations in that district have created. So for that district, we think it's truly a kind of win-win solution.
Dalton Baretto
analystAppreciate the context, John. Nothing further from my side.
Operator
operatorStefan Ioannou from Cormark Securities is up next; please proceed. Thanks a lot, everyone.
Stefan Ioannou
analystThanks a lot, everyone. Most of what I wanted to ask has already been covered. I’m mainly curious about Cozamin — I’m looking at the updated mine plan, and it’s good to see. Just reading between the lines when I look at the sort of annualized mill throughput that’s in it: can I assume there’s still a bit of untapped capacity there? And is that simply because you may be being a little conservative about how much ore you can pull from the underground?
John MacKenzie
executiveYes, thank you, Stephan. That question is one I’ll hand over to Cashel.
Cashel Meagher
executiveYes, Stephan, hi! You're completely correct. The plant itself — the processing plant — has a capacity of 4,500 tons a day, and the paste plant dry stack facility we have is equally capable. So really, the underground is where the production bottleneck lies, and we certainly felt that continuing with the prior mining methodology was constraining our chances to boost output there. As you pointed out, the technical report keeps the current production profile in place, but I believe that as we build up our competencies in the cut-and-fill methodology, it opens up a few other opportunities for us there in drift-and-fill, which will strengthen our ability in the high grade areas to achieve greater mineral recovery than the sort of 80% to 90% we would get in a normal cut-and-fill environment. And that potentially gives us the ability to extract some higher-grade pillars, which would allow us to increase our mineral recovery and slow down some of our capital development. The other one, of course, is the transverse mining method that we're including. We previously had solely a long-hole retreating method, sub-level retreat, and the transverse mining method will give us a higher — a greater opportunity as well to recover those pillars in a sequential fashion. So we could carry out pillar-less mining in some of the areas so as to be able to sequence with the paste-fill plant.
Cashel Meagher
executiveI'd say we were somewhat conservative—that's your phrasing. What we actually did, though, was act prudently by releasing a life-of-mine plan that can be achieved, can be delivered, and has been carried out previously. And the task now falls to the mine to expand the opportunities available to it through the paste plant infrastructure and the new underground mining methods, so as to raise output from there, since we definitely have enough capacity on surface to mill more.
Stefan Ioannou
analystAlright, understood. Many thanks for that.
Operator
operatorThat brings us to the end of the question-and-answer portion. You may go ahead.
John MacKenzie
executiveOkay, so thanks a lot, and we’re looking forward to bringing you another update in August when we report Q2 results. In the meantime, take care, and if anything else comes up, don’t hesitate to get in touch with Jerrold or Daniel. Thanks for sticking with us, and have a great day! Bye-bye!
Operator
operatorThat brings today’s conference call to an end, everyone. We appreciate your participation, and we ask that you disconnect your lines at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.