Capstone Copper Corp. (CS) Earnings Call Transcript & Summary
August 2, 2023
Earnings Call Speaker Segments
Operator
operatorHello everyone, and welcome to Capstone Copper's Q2 2023 Results Conference Call. Right now, all lines are listen-only. After the presentation, we'll hold a question-and-answer session. <<operator_script>> Today is Wednesday, August 02, 2023, and this call is being recorded. I'll now hand the conference over to Jerrold Annett. Please go ahead.
Jerrold Annett
executiveMorning, everyone, and welcome to the Capstone Copper Q2 2023 conference call. I want to point out that the news release and regulatory filings announcing Capstone Copper's 2023 second quarter financial and operational results can be found on our website and on SEDAR. For those of you logged in to the webcast, we'll be advancing the slides of today's presentation, which is also available in the Investors section of our website. Joining me today are our CEO, John MacKenzie; our President and COO, Cashel Meagher; our Chief Financial Officer, Raman Randhawa; and our Senior Vice President, Risk, ESG and General Counsel, Wendy King. After our brief remarks, there will be an opportunity for questions. I'd like to note that comments made on the call today will contain forward-looking information within the meaning of applicable securities laws. By its nature, this information is subject to risks and uncertainties, and actual results may differ materially from the views expressed today. For more information on the risks and uncertainties pertaining to our business, please see Capstone's most recent filings, which are available on our website and on SEDAR. And finally, I'll just note that all amounts we will discuss today are in U.S. dollars unless otherwise specified. Now, I'll turn the call over to John MacKenzie.
John MacKenzie
executiveThanks, Jerrold, and good morning everyone. We're happy to share the results and accomplishments from our second quarter of 2023. Moving to Slide 5, we're glad to say that construction at our transformative Mantoverde Development Project, or MVDP, is still on schedule and within budget. At this point we've got more than 4 million tons of sulfide ore stockpiled, with an average copper grade of 0.63%, all set for the ramp up that gets underway by the end of this year. The photo on this slide gives you a broad view of the new sulfide concentrator, with the primary crusher visible in the back left. You can see the covered coarse ore stockpile dome in the middle, along with the grinding, flotation and filtration in the center. This year is a pivotal one for Capstone, since we anticipate finishing MVDP construction by year end, which sets the stage for consolidated cash flow to double and puts us in a strong position for our organic growth pipeline. Now on Slide 6, operationally speaking, Q2 was a challenging quarter for us, characterized by unplanned downtime at our Pinto Valley mine in Arizona and ongoing debottlenecking at Mantos Blancos in Chile. Because of that, we turned out a total of 39,300 tons of copper, at consolidated C1 cash costs of $3.01 per payable pound of copper produced.
John MacKenzie
executiveBeyond those difficulties at Pinto Valley and Mantos Blancos, output at Mantoverde took a hit from a scheduled plant shutdown tied to electrical tie-ins for the MVDP. On a brighter side, Cozamin delivered a very strong quarter, since the operation has now reached full production with the new cut-and-fill mining approach. Even though our costs rose in Q2, much of that reflects weaker output rather than fundamental cost pressure. We take encouragement from certain input costs that are moving downward, and we'll cover that in greater detail a few slides later. Moving to Slide 7, we laid out H2 2023 guidance to give clearer visibility into our operations after the sluggish beginning to the year. At Pinto Valley, we anticipate better grades and no planned major maintenance during H2, which should lift output and bring costs down. At Cozamin, we expect the strong run to carry on through the second half. At Mantos Blancos, we have trimmed our expectations, and we believe less downtime will deliver steadier, higher throughput in H2. Finally, at Mantoverde, we look for increased oxide output in H2 thanks to greater irrigation rates from the expanded desalination plant serving the MVDP.
John MacKenzie
executiveOur earlier capital guidance for 2023 has been restated. At this point I’ll hand things over to Raman for the financial results.
Raman Randhawa
executiveThanks, John. Turning to Slide 8. During Q2, copper sales came to 40,800 tons, and that figure includes a catch-up from the previous quarter tied to shipment timing in Chile. The LME copper price averaged $3.84 per pound in Q2, a 5% decline from $4.05 in Q1 2023. Timing of QP hedges — which give month-after-shipment average prices — meant our realized copper price of $3.71 per pound landed a bit under the LME quarterly average. Given how our off-take contracts are currently structured, that mechanism suits us best. Consequently, we booked revenues of $334 million for the quarter. Once copper hedges are factored in, realized copper prices come out to $3.61 a pound. As John noted, our higher per-pound costs in Q2 were denominator-driven. We've gotten some relief on key inputs, among them sulfuric acid, diesel, and power costs, which are <<inaudible>> in Chile. Sulfuric acid is our biggest input cost; it peaked in 2022 above $250 a ton and averaged $158 a ton across the first half of 2023. Looking ahead, we anticipate a $20 a ton reduction in H2, and that softer trend is carrying into early 2024, where we've locked in contracts below $100 a ton.
Raman Randhawa
executiveWith Mantoverde sulfides ramping up in 2024, oxide output—and therefore asset consumption—will make up a smaller share of our overall cost base. Lower spot prices for sulfuric acid should still be favorable for our business. Ocean freight rates for copper concentrates moving from West Coast Mexico to Asia have fallen from a peak above $80 a ton in 2022 to slightly below $40 a ton in June. In addition, U.S. slot diesel prices have dropped from above $5 a gallon last year to the mid $3 per gallon range. What's more, labor agreements are now secured at every one of our operations for the coming three years, which gives us added cost certainty. Turning to adjusted EBITDA, the Q2 figure of $43.4 million was affected by reduced production and elevated maintenance costs stemming from unplanned downtime at Pinto Valley and Mantos Blancos. The gap between the LME price of $3.84 per pound and our realized price, including hedges, of $3.61 per pound works out to roughly $15 million impact after tax, or $0.02 per adjusted EPS. Moving on to Slide 9. On the left hand side, we summarize our available liquidity, which as at June 30th stood at approximately $420 million, comprising $118 million of cash and short-term investments plus $302 million of undrawn amounts on our $600 million corporate revolving credit facility.
Raman Randhawa
executiveWe closed Q2 with consolidated net debt of $760 million, along with an attributable net debt balance of $609 million. Our balance sheet is in great shape and is well positioned to finish construction of the Mantoverde Development Project by year end. With Mantoverde spent to date of $706 million, the remaining balances are approximately $120 million. The chart on the right hand side of the page illustrates our EBITDA sensitivity of various copper prices. You can see that 2023 is overshadowed by the EBITDA generation with Mantoverde sulfides at full run rate production. At $4 copper, we expect to generate approximately $330 million of EBITDA in 2023 and over $1 billion of annual EBITDA when Mantoverde Development Project is online. Although the Santo Domingo project is currently unsanctioned, the project has potential to further increase our EBITDA generation to about $2 billion per annum with the metal prices at current levels. The EBITDA generation associated with Mantoverde will enable accelerated opportunity to delever our balance sheet and be below one times net leverage at copper prices between $3.50 and $4 per pound, which provides additional liquidity to advance our future growth pipeline. Turning to Slide 10. During recent months, we have received some level of clarity with a respect to the new tax regime in Chile.
Raman Randhawa
executiveChile's Constitutional Court gave its approval to the new Mining Royalty Bill back in July. We anticipate that it will be enacted during Q3 2023, taking effect on Jan 1, 2024. Adjusted mining operational income — not net income — is subject to a cap of 46.5% for the overall effective tax rate. That said, we believe we will sit comfortably under that threshold in the near term, and three key factors drive this. First, we don't anticipate paying the 8% cash withholding tax for the coming several years, since we are reinvesting in Chile through our growth pipeline, which includes Santo Domingo as well as expansions at both the Mantoverde and Mantos Blancos. Second, taxable income will be substantially shielded by historic tax loss pools along with an accelerated depreciation allowance tied to our project capital spend and future spend. Thanks to these two items, we foresee a tax rate in Chile of under 20% across the next three to four years. Finally, at Santo Domingo — our Fully Permitted and Shovel Ready project — we have the protection of the DL 600 tax stability agreement. With that, I'll pass things to Cashel for the operations review.
Cashel Meagher
executiveThanks, Raman. Moving to Slide 11 now. Pinto Valley turned out 12,600 tonnes of copper in Q2, with a C1 cash cost of $2.98 per payable pound — that came in under what we had expected, mainly because of unplanned downtime in the primary crushing circuit, which cost us roughly 12 days of production. The operation came back online in mid-June and has run well right through the end of July. For the second half of the year, we're expecting better copper grades, and with no major maintenance on the schedule, that should drive a solid lift in copper output along with lower costs. On top of that, we're putting a strong focus on operational discipline through key performance indicators. We're carrying out component and asset assessments prioritized by downtime, and we're bringing in condition monitoring to lift our performance. As for growth at Pinto Valley, we kept engaging with local stakeholders over the quarter. Our work stays centered on finding ways to transform the district. Now on to Slide 12. Cozamin had a standout quarter, producing 6,700 tonnes of copper at a C1 cost of $1.63 per payable pound. The mine has ramped up mining rates successfully with the new cut-and-fill mining method. For the rest of the year, we anticipate Cozamin will keep performing strongly.
Cashel Meagher
executiveSlide 13 puts a spotlight on our Mantos Blancos asset. Combined sulfide and cathode output came to 11,700 tonnes of copper, with a blended C1 cash cost of $3.15 per payable pound. That fell short of what we had anticipated, and the reasons were preventative maintenance downtime at the mill along with debottlenecking work. The key components — crushing, grinding and flotation circuits among them — are still more than able to handle throughput rates above 20,000 tons per day, yet the connections linking these systems, pumps and pipes included, have shown bottlenecks. Our H2 production guidance for Mantos Blancos incorporates a plan aimed at plant stability, covering better maintenance and optimization of the concentrator. We anticipate more consistently high operating rates during the fourth quarter. Moving now to Mantoverde on Slide 14. Oxide production for Q2 2023 reached 8,300 tonnes of copper in cathode, at an elevated C1 cash cost of $3.92 per payable pound. As noted earlier, the plant shutdown for the electrical tie-in of the Mantoverde Development Project affected both production and costs. Over the second half of the year, we look for oxide production to gain from higher irrigation levels thanks to the expanded desalination plant, and we expect costs to come down as production rises and sulfuric acid input prices fall.
Cashel Meagher
executiveThe biggest meaningful strides happened at the MVDP in Q2. As of June 30th, the project is 88% complete, with $706 million invested so far. Since a lot of the traditional major escalator risks are now behind us and/or notably fading, the project's overall spend is still $825 million, and we remain on track for wet commissioning before the year is out. Blended C1 costs under $2 per pound will come from the Mantoverde Development Project, along with roughly 120,000 tonnes annually of combined cathode and copper and concentrate, plus more than 30,000 ounces of gold each year. Construction progress across several key MVDP areas appears on slides 15 through 20. Slide 15 features the primary crusher, where the retaining wall and conveyances are moving ahead nicely. The ore stockpile dome appears on slide 16 — it is now completely enclosed and can hold roughly two days of coarse ore mill feed. Slide 17 presents, at bottom left, a bird's eye view of the processing flow sheet. Every major component has been procured and is onsite, and these are now in the last tie-in phases. In the quarter, the internal rubber lining for the SAG mills went in, as did the liners for the ball mills. Slide 18 displays the new truck shop, which is mostly finished and will support the project's expanded mining fleet.
Cashel Meagher
executiveSlide 19 focuses on the tailings storage facility. Dredging is essentially finished, and liner installation is now in its closing phase. Then on Slide 20, there's the desalination plant. Capacity has been increased to 380 liters per second in support of the MVDP, and flow rates are presently being raised toward that level. Moving to Slide 21, we present a case study covering earlier ramp ups that Ausenco carried out at comparable copper concentrators. As a reminder, MVDP is off the shelf and has a conventional flow sheet. It is also a completely new plant, with no pre-existing components. Across the four latest Ausenco projects shown, reaching 100% of design capacity took under six months from ramp up. We anticipate wrapping up construction before year end and then starting the ramp up. I'll now hand things to Wendy King for the sustainability review.
Wendy King
executiveThanks, Cashel. We're turning to Slide 22 now, where we'll go over the sustainability highlights from Q2. At Mantos Blancos and Mantoverde, the independent assessment stage of the Copper Mark Assurance process is finished, and we anticipate receiving the Copper Mark for both sites soon. At Cozamin, the gap assessment stage is now complete. Cozamin and Pinto Valley are putting together project plans aimed at closing the gaps identified so they can take part in the Copper Mark process. During this quarter, a working group was set up to help carry out our sustainable development strategy, which we laid out in Q1. Pillar leads have been named, and executive accountability has been assigned. Our first sustainability report for the combined Capstone Copper Company — covering our Pinto Valley, Cozamin, Mantos Blancos, Mantoverde and Santo Domingo site — is scheduled for publication in Q3. Titled Growing Responsibly, this report will expand on our sustainable development strategy, including our specific greenhouse gas emissions targets. We're delighted that the paste fill and dry stack tailings facility at Cozamin hit its design capacity in Q2. That marks a significant step forward for sustainability at the Cozamin mine. We can now send tailings underground to fill voids, giving the mine greater stability, and we're able to recover additional water from the dry stack tailings deposition process, which lowers our overall makeup fresh water production requirements.
Wendy King
executivePutting in this facility cuts down on the area that traditional tailings would usually need. And at Pinto Valley, we're proud to have launched a Women in Mining Chapter aimed at encouraging the hiring and career growth of women. We've also put Women in Mining logos on 5 new trucks. Women remain underrepresented in mining, and we need to build an inclusive, diverse environment so we can keep and draw in a more diverse workforce. With that, I'll hand things back to John.
John MacKenzie
executiveThanks. Thank you, Wendy. If we go to Slide 23, we've laid out the growth plans that lead our sector as well as some extra upside inside our portfolio. As you can see, we anticipate that MVDP, at its run rate production level, will take us to a consolidated level of roughly 260,000 tons of copper at substantially lower costs. From that point, we have a clear pathway to more than 400,000 tons of copper production. We have brownfield expansions at both Mantoverde and Mantos Blancos with attractive capital intensity, and our portfolio includes a Santo Domingo project that is fully permitted and Shovel Ready. Additional upside exists with oxides at Santo Domingo, using our SX/EW plant at Mantoverde. Mantoverde Phase 2, growth in our Pinto Valley District and cobalt optionality in our Mantoverde Santo Domingo district. On Slide 24, we've laid out a potential development timeline for our portfolio. Even so, we're fortunate to have considerable flexibility in this regard, and we intend to advance our pipeline in a prudent manner. In addition, our capital allocation decisions will be shaped by the eventual results of the studies we are working through with respect to each of these projects. However, this timeline does represent a feasible opportunity for us and would let our project team transition from MVDP to our brownfield optimization projects, followed by Santo Domingo.
John MacKenzie
executiveOur emphasis is on execution so that the value contained in our portfolio can be realized. Slide 25 sets out the schedules for the studies and catalysts mentioned earlier that we have over the coming two years, which underpin our growth plans, with additional upside across our portfolio beyond that. We have kept building a skilled technical team and are collaborating with robust engineering companies to carry out these studies. Before I wrap up, I want to announce several key management appointments taking effect August 1st. Jim Whittaker is coming to Capstone Copper as our SVP, Head of Chile. Jim brings more than 30 years of experience, most recently at BHP Chile, where he served as President of Escondida Copper Mine. I also want to express thanks to Giancarlo Bruno, our previous Head of Chile, who retires in mid-August and who played a crucial role in the development projects at Mantos Blancos and Mantoverde. In addition, we have strengthened our operational and technical depth with Hayden Halsted joining us as Vice President, Mining and Maintenance. Hayden likewise brings over 30 years of experience in the mining and civil construction sectors, mainly in South America. And finally, Edgar Rocha is coming aboard as the Project Director for Santo Domingo. Edgar arrives at an exciting moment, as we are advancing the feasibility study before a possible project sanctioning decision late next year.
John MacKenzie
executiveTo wrap up, let me restate that Capstone is having a year of major transformation. It's genuinely exciting that wet commissioning at MVDP remains on schedule for year end, which will bring a step change up to 260,000 tonnes of copper per year at substantially reduced costs. With that said, we're ready to open the floor to questions.
Operator
operatorThank you. Ladies and gentlemen, we are now starting the question-and-answer portion. <<operator_script>> Our first question is from Orest Wowkodaw at Scotiabank. Please go ahead.
Orest Wowkodaw
analystMorning, and thanks — good to see the real progress on the MVDP. I was hoping, though, for a bit more detail on the operations we already have. By now we've had a couple of quarters running where performance at both Pinto Valley and Mantos Blancos has, in my view, been difficult. I understand the planned downtime is finished. But, Cashel, could you shed some light on just why unplanned downtime is showing up to this degree? And perhaps what steps would need to be taken so we can keep that to a minimum going forward?
Cashel Meagher
executiveYeah, hi Orest. Sure — Mantos Blancos definitely had a tough first half of the year. Looking back at the ramp up, the quick version is that the big components went in, but some of the connections between them, from a maintainability and operability standpoint, weren't properly thought through. That was one problem we were working on. The other problem we were working on was probably how intensely and how well we applied our resources. Initially, once we hit commercial production, we may have gotten a mistaken impression that the systems and the linkages among the major components were functioning as they should, and we hadn't put enough crew on the outstanding issues as opposed to a crew handling preventative maintenance. So since then we've split the crews, with one taking care of preventative maintenance — making sure our major components get proper attention and upkeep — while also tackling the design weaknesses in the linkages. That's now in progress. We've also brought in additional resources and more seasoned management to deal with these specific problems. So we're now treating the rollout of preventative maintenance and reliability as a separate focus from dealing with the interlinkage component issues we had. Just to give you a bit of color, maybe I'll offer one example.
Cashel Meagher
executiveTake one case: our Hydrocyclone classification units had rubber linings during the project's early stages. At first, that performed very well indeed. Manos Planos, however, contains quite coarse material, and the wear from that material exceeded what the rubber was designed to withstand. As a result, we have since relined those hydrocyclones using ceramic liners. That illustrates how the intervals now between liner replacements have grown, which means less downtime. So, when you stack up many such improvements, you get reduced downtime, and that is essential to the ramp-up at Mantels Blanco. And that is the direction we are working toward.
Orest Wowkodaw
analystNothing to share regarding Pinto Valley?
Cashel Meagher
executiveYes. So during Q1, as we mentioned previously, Pinto Valley saw a lot of rain, and part of our ore distribution circuit wasn't built for that kind of weather, so we dealt with sticky muck inside the crushing plants, which was something of a headache. Then in Q2, what we've run into now — again in the crushing circuit — was a few failures involving key structural components and some motor alignment problems on certain conveyances, and those were the main difficulties. These are one-off failures on infrastructure that's getting old. That's led us to revisit how we think about asset integrity. It's a current priority, and we've also restructured our maintenance approach so that, alongside our usual preventative maintenance work, we now cover electrical, structural and non-destructive testing. And we think the biggest problems at Pinto Valley have been dealt with. So, given what's happened over the past month, we're feeling quite confident that through to year-end we can average roughly 54,000 tonnes per day. And on top of that, we have no major scheduled maintenance shutdowns.
Cashel Meagher
executiveWhat we’re doing, then, is turning our attention once more toward asset integrity and non-destructive testing of major components.
Orest Wowkodaw
analystAppreciate it, Cashel. If I could squeeze in one last question, it's about Slide 24, the one covering your organic development pipeline. Am I understanding this correctly — you intend to carry out the Mantoverde optimization project along with Montoss Blancos Phase 2 and kick off Santo Domingo simultaneously, with all of them overlapping in 2025?
Cashel Meagher
executiveYes, Orest, what that reflects is an idealized program for each one of those projects. And our view of Santo Domingo is quite similar to the Mantoverde development project Phase 1, which is a major capital project. We already have a very strong owners' project team, along with the Ausenco team that we would intend to see move over to Santo Domingo. The MVDP optimized in the Mantos Blancos Phase 2 are what you could describe as more debottlenecking projects on existing processes. So those obviously have fairly straightforward implementation — for example, in both cases a major proportion of them is really just additional mine fleet when it comes to expanding the mine. So we do believe that we can start each of those two projects with what I would call the mine project teams that we have, independently of our decision making around the commencement of Santo Domingo. I think we've also said before that for Santo Domingo, we will look at a full notice to proceed once we are confident of, I would say, a number of different factors. I think the first is the completed and successful ramp up of Mantoverde and seeing the cash flow coming in from Mantoverde and the de-leveraging of our balance sheet.
Cashel Meagher
executiveI think second, we'd also want to take a look at the broader economic backdrop and feel confident about where things stand regarding capital escalation, where we stand on order lead times and copper pricing, and what makes the most sense regarding the moment we pull the trigger on Santo Domingo. As of now, we don't see any reason that shouldn't be around the end of next year. But with each of these projects, we keep complete flexibility on when we actually get these projects started. So we'll take a look at conditions at the time and see whether it's prudent to kick off that particular project at a given point, whether there's any justification to pause for a while and make sure we're comfortable that whether it's our balance sheet or the macro environment is in the right shape to move forward.
Orest Wowkodaw
analystAppreciate it.
Operator
operatorThanks. We'll take the next question from Dalton Baretto at Canaccord. Go ahead, please.
Dalton Baretto
analystThank you. Morning, John, and hello to everyone on the team. First thing I'd like to do is ask about MVDP. You're in the final stretch at this point, after all. As we look toward the actual ramp-up, could you walk us through the main risks on your radar and the way you're handling them?
John MacKenzie
executiveYeah, thanks Dalton. And look, I'll hand things over to Cashel in a moment so he can go into more detail. But just as a starting point, this is a project where we haven't brought in any kind of new technology. These are established concentrator flow sheets. A lot of the de-risking happens during the early stages of project preparation. And just as an example, it obviously begins with the ore body, and for the sulfide ore body at the Mantoverde project, across the full life of the mine, 70% of the reserves sit in the proven category and 30% in the probable category. That's a high level of geological confidence. And most mines actually have that only for the next couple of years, never for the full life of the mine. We've carried out very, very extensive metallurgical test work and designed the process plants accordingly. And I think you probably saw — so we've actually — our contract with Ausenco covers the commissioning and the ramp up process. And with pretty much identical plants to the ones Ausenco is building for us, they've achieved, well, better than industry average ramp up rates at the previous four copper concentrators they have built.
John MacKenzie
executiveI think the next piece of de-risking, obviously, revolves around being operationally ready. And before I hand things over to Cashel, let me just mention that we have a very thorough operational readiness plan in place. As of right now, we're ahead of schedule when it comes to implementing it. The mine itself is running at full capacity. We're already producing sulfide ore. So the trucks are on site, the shovels are on site, the operators are all on site, and everything is running. So really, it comes down to getting the processing plants, the operating procedures, the processes, and the team in place. That's very much where we are. We're ramping up very quickly with the team we have. And I think when it comes to the ore side of progress — whether that's critical spares, whether that's service contracts, suppliers, consumables — all of that is now very well advanced. But maybe with that, if I could pass over to Cashel just for any additional color.
Cashel Meagher
executiveYes, absolutely. A handful of important pieces come into play toward the close of every project, and one of them is that finishing the project really means getting everything fitted out. As with any project, certain areas lag, and we deal with that by adding resources. So during the past month we added a night shift, something we hadn't needed to do previously, and that's to assist with pulling electrical cables, small bore piping and cable termination, which lets fewer people work within the same footprint, which in turn enables better inspection and, obviously, over a 24-hour period, additional production. And as a matter of fact, productivity has been really strong. They've been pulling more than 2000 meters of cable per day. So that part is going quite well. And so that was one mitigating step that keeps us on schedule. Another is at our tailings facility, where we have two contractors, and we divide the responsibilities between earth moving and liner placement. And so that has really accelerated productivity at the tailings facility. And again, that was addressing something we observed a couple of months ago, when productivity at the tailings facility was dropping off somewhat, so that's something you deal with. So those are the steps you take so you can hit your completion date.
Cashel Meagher
executiveJohn is right on the money that operational readiness comes next. More than half of the staffing complement has already been hired by our team, and over the coming month we'll wrap that up, reaching 126 new employees in total — supervisors, managers, and so forth. So that effort is going very well, as are the implementation and build-out of the maintenance program, our SAP program, and the assorted procedures and operating processes. Another distinctive feature of this contract with Ausenco is that they actually remain involved all the way through ramp-up. Normally they stay only until commissioning wraps up, after which the operational readiness group — largely the operating crew — takes over. In this contract, negotiated with Ausenco to secure the better-than-industry-benchmark ramp-ups shown in our presentation — the kind they achieved at their last four copper concentrators — we want to assure ourselves that we too have a shot at matching that. Through commercial production, they are staying on with their A team for operational readiness. In fact, their commissioning team is already on site working on it and getting ready.
Cashel Meagher
executiveWe’re genuinely confident about it. And to build on what John mentioned, having 4 million tonnes of stockpile in place matters a great deal, and it matters that the mine has already completed its ramp-up, with three of the four shovels fully operational and the better part of 80% of the fleet running. We’re simply adding to the future incremental stripping that the mine plan calls for later in January, when the fourth shovel shows up. So among all the projects I’ve been involved with, this one is exceptionally well organized and approaches that operational period with considerable forethought. That’s exactly why we feel very confident in where we stand today.
Dalton Baretto
analystAppreciate the thorough response. And then, perhaps peering ahead a bit, what's the newest on where you stand regarding MVDP optimization?
John MacKenzie
executiveYeah, Cashel, honestly we're really enthusiastic about the MVDP optimization. To give you a fast overview of what it involves: the MVDP was built by us to handle 32,000 tonnes of ore per day. That said, we've more or less overbuilt the primary crusher along with the grinding circuit, and we figure those can manage roughly 40,000 to 45,000 tonnes on a daily basis. So the MV optimized is essentially a study that's — the detailed engineering on it is happening right now — aimed at removing bottlenecks on the backend of the plant so it can handle that 45,000 tonnes a day too. So that work is ongoing. We'll be filing the permit for it quite soon, and that's a DIA, which is a fairly simple permit. As for what we currently estimate the capital cost at, it's likely somewhere near $150 million. That ought to deliver an additional 25,000 tons or so of copper each year. And looking at it purely through capital intensity, that works out to roughly $6,000 per annualized tonne of copper production, which is about half of what MVDP itself comes in at — and MVDP itself, in turn, is roughly half of the capital intensity numbers you see for the industry.
John MacKenzie
executiveSo it's a highly appealing project. We think it's fairly uncomplicated. Really, it sits in that flotation and filtration space, where some extra equipment is going to be needed, but we do think it will be a very, very solid returning project and one that, I think, keeps — together with our other catalysts — really delivering another exciting year in the year ahead. At the close of this year we start commissioning and ramping up Mantoverde. We also finish the feasibility study for Santo Domingo. And then over the first half of next year we'll finish that optimization study at Mantoverde and obviously finish the — the ramp up. So alongside that, we keep examining Mantoverde Phase 2, which would then amount to a full second line at Mantoverde. The resource base is big enough to support another 45,000 tonne a day line. And that's a study we ought to be releasing during the first part of next year as well. So, plenty of different catalysts that keep this — what I'd describe as — low risk growth profile going forward.
John MacKenzie
executiveCashel, is there anything you would like to add to that?
Cashel Meagher
executiveYes. I think one thing that stands out — and this came up in the earlier question as well — is that we can overlap MB to MV, or optimized MB, and Santo Domingo. But I think what's distinctive about Mantoverde optimize and the jump from 32,000 tonnes a day to what we expect will be nearer 45,000 tonnes a day is that Ausenco-designed plants have hit that kind of performance before. I was fortunate enough to work on one of their earlier plants, which was designed for 76,000 tonnes a day, and in the end, even though it wasn't labeled an optimized process, it wound up capable of running consistently at 90,000 tonnes a day. So we know the overall engineering design is sound, and Ausenco has confirmed this with us, which is why this rests on the engineering study coming out in the first quarter. And we have strong confidence in the ability of the major components of the grinding circuit and the tailing circuit to handle this tonnage. And it's something I've seen before and certainly Ausenco has seen before. So we have great confidence that this is a very straightforward in-house expansion of The Mantoverde Development Project to reach 45,000.
Cashel Meagher
executiveThis addition is fairly complex, I'd say. I'd also note that, as John said, the Mantoverde Development Project has strong project metrics in terms of capital intensity, and we believe this one is even better. So we're really looking forward to releasing this study in Q1 of next year.
Analyst
analystThanks, guys. Perhaps we could fit in just one more. Regarding Pinto Valley, I was just wondering what the current status of discussions is between BHP and Freeport. And how did you arrive at that figure of 80,000 tons of copper per annum in your presentation? Thank you.
John MacKenzie
executiveYes. Thank you, Dalton. We've been pretty excited about the engagement we've had in that district with the players there, and those conversations are ongoing. Obviously, we were doing quite a bit of work behind the scenes, looking at what an optimal district might look like. I'd say it's still early stage. There's plenty of work ahead — both on the district discussions side and on our own efforts to determine the optimized configuration for that district. What we do know is that it's a district with a very, very large resource base, plenty of infrastructure already in place, and the capacity to handle very, very large throughput rates at what we think could be highly competitive costs. So when we look at where that might take us, today we have the capability of doing roughly 60,000 tons a day at Pinto Valley with the district resource base that exists there. You could certainly see that potentially tripling in terms of processing throughput rates, and just based on average resource grades in the area, that's how we arrive at the kind of numbers you're referring to.
John MacKenzie
executiveAnd of course, that comes on top of what Pinto Valley is already turning out today. So as I mentioned, this is early-stage work. Plenty remains to be done. That setup suits us well, I'd say. When we look at our pipeline, we still need to finish the Mantoverde Development Project. Santo Domingo comes as the next phase after that. And clearly, running alongside, we potentially have Mantoverde optimized plus Mantos Blancos Phase 2. That, I think, gives us room in terms of time to genuinely figure out the best way to develop this into a world-class district.
Analyst
analystAppreciate it, John. I’ll get back into the queue now.
John MacKenzie
executiveAppreciate that, Dalton.
Operator
operatorThanks. Our following question is from Ralph Profiti at Eight Capital. Go right ahead.
Ralph Profiti
analystThank you, operator. Good morning, everyone. I’d like to return to a few points that John and Cashel raised. Cashel, you mentioned the comprehensive component and infrastructure assessment at Pinto Valley, along with the testing that will be taking place — I’m curious how that fits into the district growth plan that was just discussed, since that plan itself calls for investments in mill expansion. And I’m wondering whether you’ll be stress testing some of those scenarios within the study, so we can get a line of sight into that?
Cashel Meagher
executiveYes, absolutely, Ralph. So the study we're undertaking is a joint task force effort, and we do collaborate with the partner property owners in the region, chiefly BHP, to figure out what's available to us. Put simply, we're in the middle of trade-off studies right now, evaluating the outer bounds of what's achievable. One of those end members, for instance, that we'd be stress testing is what the Pinto Valley processing facility itself can expand to today, obviously with the ongoing maintenance focus and upgrading. And the thinking there would be: if you optimized the resources available to you across the district in terms of Old Dominion, including Copper Cities, is there a way to high grade the district so that the grade going through our current facility rises, and by how much could we incrementally boost our current facilities' production rate per day to accommodate that? So that's one end member. John, I thought, described the other end member quite well — which is, what if we added processing facilities at strategic locations near where those resources sit, to raise the district product per day, and it could be as much as 150,000 ton a day with the sum of all two — two processing facilities, and then utilizing all the resource in an optimized mine fashion so we can determine what the output is.
Cashel Meagher
executiveSo that work is currently in progress. It's essential for figuring out what type of partnership we'd ultimately reach, and that's essentially what our technical services group, together with partners such as BHP, is doing to grasp what the art of the possible holds, given that the resource exists. At Copper Cities, we've confirmed the resource. We're aware that important underground deposits in the area also present high-grade possibilities as sweeteners for the feed. So we're genuinely enthusiastic about this being Capstone Copper's next growth phase following Santo Domingo.
Ralph Profiti
analystAll right, that's useful. Thank you. Thanks, Cashel. I had a second question, really as a follow-up on Ausenco and in particular that slide covering the case studies. Just to clarify, is Ausenco's benchmark the industry standard? Or are they providing a somewhat more aggressive timeline grounded in their own precedent? Because you sound fairly confident that the right incentives are in place when it comes to execution, which would place commissioning at some point around Q3 of 2024?
Cashel Meagher
executiveYeah. I'm fairly confident about this — they've got a Chief Technical Officer by the name of Greg Lane, who is well known across the industry for copper flotation circuits, and he has demonstrated it works. He's the — well, the proof is in the pudding now. Do they ramp up better than industry standards? We all know, and we all hear about other ramp-ups that take considerable time and considerable pains, and Ausenco is one of the engineers that has found a niche, and their niche and their expertise is in copper plant ramp-up; so that gives me confidence. What I will tell you is, for budgeting purposes, we've assumed industry standard, and ambitiously and confidently I think we will exceed that standard.
Ralph Profiti
analystAppreciate that, Cashel — really useful.
Operator
operatorThanks. We'll take our next question from Craig Hutchison at TD Securities. Go right ahead.
Craig Hutchison
analystMorning, everyone — thanks for the time. I’ve got a couple of quick questions. John, you were quite clear about the capital cost for the optimized MVDP expansion being $150 million. Could someone give us a rough idea of what the cost would be for the Mantos Blancos Phase 2 optimization?
John MacKenzie
executiveYes. Thank you, Craig. This is still a work in progress, and I think the way we intend to handle Mantos Blancos Phase 2 is likewise still developing. The short answer to your question, I would say, is probably somewhere in the sub-$100 million range to bring us up to 27,000 tons per day. Regarding the approach we are considering, we have been drawing considerable lessons from how the plant is currently being commissioned and ramped up. And I think one of those lessons is that instead of carrying out a project that lifts us from 20,000 to 27,000 in one go, we may very well choose to proceed in stages — a kind of progressive debottlenecking across each item of the plant that will move us in steps up to that 27,000 tons a day. As for that capital figure I mentioned, there actually isn't that much required inside the plant itself. I would say at least half of that amount is in fact additional mine equipment, needed to deliver the extra throughput. So really it comes down more to fine-tuning what is already in place to get us up to that throughput rate.
John MacKenzie
executiveAnd work is underway on that front. For instance, we’ve got several of those smaller, older mills available that could be brought in to help us reach 27,000 tons a day. But what we’re actually seeing is that the two mills currently running for the current project may on their own have the potential to get us all the way up to that tonnage, without even requiring those smaller mills. So this is really the point where we’re examining what the most efficient project configuration would be to lift us to that throughput rate. And that throughput rate essentially reflects the optimal pillar value throughput rate for the resource space as we currently understand it.
Craig Hutchison
analystAlright, that's great, thank you. I just have one more question about the choice to approve Santo Domingo — you noted that it clearly hinges on several factors, including the macro environment. You also brought up the capacity to leverage your balance sheet. Which financial metrics would you feel comfortable with before moving forward and approving that project?
John MacKenzie
executiveI'll hand that question over to Raman, our CFO, as well.
Raman Randhawa
executiveRight, Craig, we've consistently said our target is to stay under two times net debt-to-EBITDA, and then we'll lever up somewhat through the build phase. So ensuring the figures land below that level would serve as a decent proxy. And, well, when you look at MVDP, it moves our net debt toward one time pretty quickly. So I'd say somewhere in that one-to-two range before we layer it back on, though we see that happening at the back end of 2024.
Craig Hutchison
analystOkay, that's great — thanks everyone.
Operator
operatorThanks. Our following question is from Stefan Ioannou at Cormark Securities. Go right ahead.
Stefan Ioannou
analystYes. Great. Thanks a lot for all those thorough responses. I’m just a bit curious — obviously it’s really good to see Mantos Blancos and Mantoverde moving from oxides over to sulfides? Given that we’re seeing a pretty compelling copper macro ahead, I’m just wondering whether there are any plans perhaps behind the scenes to still try to add more oxide production at those mines down the road?
John MacKenzie
executiveYes. Thanks. Thanks for that question, Stefan. And once more, the brief response is affirmative. We are considering a wide range of possibilities, since both — both the SX/EW plants, Mantoverde and Mantos Blancos, each have a capacity of 60,000 to 65,000 tons of cathode annually. At Mantos Blancos, we are turning out roughly 15,000 tons or thereabouts. Each year at Mantoverde over the coming 15 years or so, it sits at approximately 30,000, so roughly half of capacity. Therefore we have somewhere between half and three quarters of that SX/EW plant capacity that is free. So beginning with Mantoverde, we have plenty of different alternatives. We are aware there are 90 million tons of oxide ore at Santo Domingo, which was never part of the project. It was they could not justify building their own SX/EW with that tonnage. So at present it plainly makes greater sense to leach that material and to utilize piping the <<inaudible>> to Mantoverde and to utilize that capacity. That is because it was never included in the earlier project. Some drilling work and some network are required before we can confidently include that, but that — that work is underway and we are very optimistic about it.
John MacKenzie
executiveAt both operations, I'd say there are clearly opportunities with sulfide leaching. At Mantos Blancos and Mantoverde alike, we have low-grade sulfides, and those could definitely serve as a source of supplemental feed for the SX/EW plant. Something we're examining at Mantos Blancos: it's an old mine, dating back to roughly the late-50s, early-60s, so we have extremely large coarse tailings — that's the term — and those tailings are quite high grade where oxide grade is concerned. We're therefore studying whether we might leach a portion of that material. That could deliver a fairly substantial feed stream to our SX/EW plants. On our property, we have certain known areas showing oxide mineralization, and we'll be proceeding to investigate whether those justify development. And then, clearly, we always assess the straightforward opportunities that could likewise feed into either one of those SX/EW plants. From our standpoint, any capacity sitting unused represents, in a sense, a dollar thrown away. So we're scrutinizing very, very closely how, over time, we can put that infrastructure to the absolute best possible use.
Stefan Ioannou
analystPerfect. Perfect. Understood. Well, I really appreciate that.
Operator
operatorThanks. We'll take the next question from Alex Terentiew at Stifel. Go right ahead.
Alex Terentiew
analystHey folks, good morning. So I have two quick questions for you. First, I'd like to revisit Mantoverde and 2024, when you get that mine up and running — one of the main benefits you've mentioned repeatedly is the expectation that costs will come down. Could you give me a sense of those costs, based — I'm assuming that's based on past studies and such, obviously — but have those costs been updated to reflect the current cost environment? In other words, I guess, or I'm asking, is that sub-$2 cost still something you feel pretty confident about achieving? So I'll stop there with my first one. I'll ask my second one afterward.
John MacKenzie
executiveYes, Alex. We are right in the middle of our yearly budget cycle at the moment, but those figures did not come from an outdated technology report. For instance, a few of them get updated each year, and what we have observed is that a key factor will be the cost of energy, which is set to stop being cold indexed. That means we should see meaningful savings once the plant is running. So yes, the numbers are quite current, though we will still work through the yearly budget cycle to refresh them. Even so, regarding input costs, power — which is among the biggest — will no longer be subject to that cold index.
Alex Terentiew
analystAlright, that's great. My follow-up question is about the surety bond tied to Minto Mine. I should say up front that I don't really know the accounting treatment for bonds like this. But put simply, that $54 million liability — is it a cash obligation Capstone is expected to settle over the next few years? Any clarity on that would be appreciated.
John MacKenzie
executiveRight, so we got indemnified for the surety bond on Minto at the time we divested it. That came to CAD 72, or USD 54. From an accounting standpoint, we booked that USD 54 as a liability on the balance sheet. Which means, as you pointed out, it gets paid down gradually in cash as reclamation work is carried out at the mine.
Alex Terentiew
analystAll right. And I’m sort of working on the assumption that this happens across the coming 5 to 10 years, roughly?
John MacKenzie
executiveYeah, it's likely weighted toward the early part, so a big portion of it will probably come during the next 5 years.
Alex Terentiew
analystAlright, I’m finished. Thanks.
Operator
operatorThanks. <<operator_script>> Our following question is from Bendik Nyttingnes at Clarksons Securities. You have the floor.
Bendik Nyttingnes
analystThanks. When I look at the guidance for Mantos Blancos in the second half, it's <<inaudible>> noticeably stronger than what we've seen so far this year. I'm no geologist, so how gradual is the process of ramping up that throughput — just in terms of the timing across the second half? And what potential exists for the sulphide operations at Mantos Blancos in 2024, assuming the concentrator optimization works?
John MacKenzie
executiveYes. So with Mantoverde, we expect to be through wet commissioning by year-end. And the worst case, in my view, is late H1. At the Mantoverde Development Project we'd be fully ramped up, but as we've been indicating in the presentation — and in the presentation we're quite confident about beating industry standards, and our setup is going well. So we're optimistic that full ramp-up at Mantoverde will come more in Q1. Mantos Blancos — sorry, go ahead.
Bendik Nyttingnes
analystNo, my apologies. Yeah, what I kept coming back to more and more was the concentrator optimization at Mantos Blancos.
John MacKenzie
executiveRight, so our expectation is that we will reach full design capacity by the time this year wraps up.
Bendik Nyttingnes
analystAlright, thanks.
Operator
operatorThank you. That brings us to the end of the question period. Now I'll hand things over to John MacKenzie, who'll offer some closing comments.
John MacKenzie
executiveThanks. We’re eager to speak with you again when we report Q3 results in November. In the meantime, stay well, and please don’t hesitate to contact Jerrold or Daniel with any additional questions. We appreciate your ongoing support, and have a good day.
Operator
operatorEveryone, that brings today's conference call to a close. We appreciate your taking part, and we ask that you kindly disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.