Capstone Copper Corp. (CS) Earnings Call Transcript & Summary
May 2, 2024
Earnings Call Speaker Segments
Operator
operatorGood afternoon, everyone, and thank you for joining us for Capstone Copper's conference call on our first quarter 2024 results. <<operator_script>> Today is Thursday, May 2, 2024, and this call is being recorded. At this point I'll hand things over to Mr. Jerrold Annett. Please go ahead.
Jerrold Annett
executiveGood day, everyone, and welcome to the Capstone Copper Q1 2024 conference call. I want to point out that the news release and regulatory filings that announce the 2024 first quarter financial and operational results for Capstone Copper can be found on our website and on SEDAR. For those of you logged into the webcast, we will be advancing the slides of today's presentation, and those are also available in the Investors section of our website. With me today are our CEO, John MacKenzie; our President and COO, Cashel Meagher; our Chief Financial Officer, Ramanpreet Randhawa; and our Senior Vice President, Risk, ESG and General Counsel, Wendy King. After our brief remarks, there will be a chance for questions. I should note that comments made on the call today will contain forward-looking information within the meaning of applicable securities laws. By its nature, this information is subject to risks and uncertainties, and actual results may differ materially from the views expressed today. For more information on the risks and uncertainties pertaining to our business, please see Capstone's most recent filings, which are available on our website and on SEDAR. And finally, I'll just note that all amounts we will discuss today are in U.S. dollars unless otherwise specified. Now I'll turn the call over to John MacKenzie.
John MacKenzie
executiveThanks, Jerrold. Good afternoon to everyone in North America and Europe, and good morning to those of you joining us from Australia. We're happy to share our results and achievements for the first quarter of 2024. Beginning on Slide 5. In Q1 we turned out a bit more than 42,000 tons of copper, and consolidated C1 cash costs came in at $2.88 per pound, and we are reaffirming our 2024 guidance. It's been a strong start to the year, with production near the midpoint of our first half guidance range. Our Sulphide cash costs of $2.55 per pound also landed at the midpoint of our guidance, while costs in our smaller cathode business ran above plan. As a reminder, with our transformational development project — now a month old — ramping up this year, Sulphide will account for a significantly larger share of our production base, which contributes to lowering our consolidated cash costs. The MVDP is still on track and on budget. We're on the verge of producing first saleable concentrate, and our team is focused on ramping production up to the design run rate levels. I was in Chile a couple of weeks ago, and I spent some time at site reviewing our progress and meeting with our team. I'm very pleased with the work done so far and believe Mantoverde's future looks extremely positive.
John MacKenzie
executiveDuring my time in Chile for meetings, I went to a CESCO Dinner, where President Gabriel Boric restated the administration's wish to keep building an investor-friendly climate for copper miners, aiming to boost foreign private investment in copper mining. That's a positive signal for Capstone Copper as we move forward with feasibility studies for MVDP optimized and for our Santo Domingo project in the Atacama region, both of which we expect to publish by mid-year. On the corporate front, net debt fell significantly, from $927 million at year-end 2023 to $740 million at the close of the first quarter. Our balance sheet is in great shape as we ramp up Mantoverde ahead of our next phase of growth. Also worth noting this quarter: Orion Mine Finance, formerly our biggest shareholder, cut its ownership stake from 24% to 12% after two secondary share placements. Orion's second sale during the quarter was placed directly into Australia through our secondary listing, which trades on the Australian Securities Exchange under the ticker symbol CSC. We're pleased with how our CDIs have performed so far, and we believe we're on track to be considered for the ASX 300 index rebalance in September.
John MacKenzie
executiveThe ASX stands as a premium marketplace with a lengthy history of serving as a venue for mining firms, and we're eager to keep expanding our investor base across Asia-Pacific. With that said, I'll hand things over to Raman for our financial results.
Ramanpreet Randhawa
executiveThanks, John. Turning to Slide 6 now. During Q1, copper production came in at 42,100 tons, while copper sales were a touch under 41,000 tons. LME copper prices averaged $3.83 per pound over the quarter, roughly 4% higher than the $3.70 per pound seen in Q4 2023. At $3.85 per pound, our realized copper price was broadly aligned with the LME average. As of today, copper is trading nearer $4.50 per pound, and each 10% rise in the copper price during 2024 affects our EBITDA by approximately $125 million. Looking to next year, once MVDP is running at full rates, a 10% shift in copper prices would lift our EBITDA by a bit more than $200 million. Consolidated C1 cash costs for Q1 came in at $2.88 per payable pound, which was $0.03 above the guidance range for the first half. We anticipate a significant step change in our consolidated unit cost during the second half, driven by our Mantoverde development project, bringing it down to between $2.10 and $2.30 per pound. Adjusted EBITDA for Q1 reached $80.1 million, a 21% increase year-over-year versus the first quarter of 2023, mainly reflecting greater copper sales and reduced costs. Let's move to Slide 7. On the left side, we lay out our available liquidity, which stood at roughly $540 million as at March 31, 2024, comprising $132 million in cash and short-term investments along with $400 million of undrawn capacity under our $700 million corporate revolving credit facility.
Ramanpreet Randhawa
executiveOur liquidity position rose considerably compared with year-end, thanks to $253 million in net proceeds from the primary equity raise we completed in February. Consequently, we ended Q1 with a net debt position of $740 million and an attributable net debt balance of $591 million. During the MVDP ramp-up, ahead of our next growth phase, our balance sheet is in very strong shape. The chart on the right-hand side of the page shows how our EBITDA responds at different copper prices. In the first 2 bars, you can see that we anticipate significant near-term EBITDA growth as Mantoverde Sulphide reaches full run rate production. This year, in 2024, with MVDP ramping up, EBITDA will more than double from 2023 levels. And with MVDP at full capacity in 2025, we expect to generate between $1.2 billion to $1.3 billion of EBITDA at copper prices of $4.50 per pound equivalent to today’s pricing levels. The EBITDA generation associated with Mantoverde will let us focus on generating free cash flow to delever our balance sheet and be quickly below 1x net leverage of spot copper prices, which provides additional financing capacity and advance our future growth pipeline in terms of Mantoverde optimize, exploration and Santo Domingo depending on market conditions.
Ramanpreet Randhawa
executiveAt this point, I’ll pass things along to Cashel so he can walk us through the operations review.
Cashel Meagher
executiveThanks, Raman. We are now turning to Slide 8. During Q1, Pinto Valley turned out 15,672 tons of copper at a C1 cash cost of $2.53 per payable pound, and those figures are competitive when set against similar grade copper mines in the U.S.A. Our production performance came in above the high end of the first half guidance range, and our cash costs landed below the guidance range, thanks to grades that came in stronger than expected. We are beginning to realize the advantages of the asset integrity program we recently put in place, and there remains room for us to raise the mean time between failures and enhance our overall availability so we can deliver higher throughput more consistently. Water inventory levels are sitting well ahead of the dry season. Turning to Slide 9. Cozamin Mine posted a solid first quarter, generating 6,006 tons of copper at a C1 cash cost of $1.93 per pound. After moving to the new cut and fill mining method earlier last year, the mine showed another quarter of nameplate mining rates. Costs have risen 12% year-over-year, reflecting a stronger Mexican Peso and additional contractor costs tied to more cut and fill as part of the mining sequence in 2024. Our Mantos Blancos asset is highlighted on Slide 10.
Cashel Meagher
executiveCombined sulphide and cathode output came to 10,967,000 tons of copper, with a C1 cash cost of $3.05 per payable pound. Our sulphide operations performed at a steady rate matching what we saw during the back half of last year — a level under the 20,000 tons of ore per day nameplate capacity, mostly because of constraints in the plant's tailings dewatering area. In the first quarter, we kept carrying out our plan aimed at plant stability, which covers better maintenance and optimization of the concentrator along with retrofitting of the tailings systems. In the second quarter of 2024, we anticipate installing the last equipment pieces, particularly a surge tank and pumps, enabling us to ramp the plant up to nameplate capacity during the second half of this year, which should also bring a corresponding reduction in costs. We have confidence that both the team and the asset are in place to support full run rates. Our efforts are concentrated on getting there. Following that, we will restart our studies tied to Mantos Blancos Phase 2, since we believe the ore body can sustain a further expansion. We will additionally seek to step up exploration work at Mantos Blancos, as we believe we hold highly prospective near mine targets that could let us enhance our grade profile and grow our tonnages over time.
Cashel Meagher
executiveTurning to Mantoverde, Slide 11. In Q4 2023, oxide output came to 9,476 tons of copper in cathode, with C1 cash costs of $3.82 per payable pound. Although those costs sat above the guidance range we had set for the cathode business in Q1, we expect a step change in Mantoverde's cost profile once the MVDP Sulphides ramp-up is complete. The quarter brought significant commissioning advances. In particular, we have now moved further into the grinding circuit, mainly the SAG and Ball Mills, and we remain on schedule for our other key commissioning milestones — first saleable concentrate in the second quarter and nameplate operating rates in the third quarter. With the operation fully ramped up, Mantoverde will turn out roughly 120,000 tons per year of combined cathode and copper concentrate, plus more than 30,000 ounces of gold annually. We progressed the feasibility study for our Mantoverde optimized project during the quarter and intend to publish it by midyear. MVDP optimized is a brownfield expansion designed to raise ore throughput at the Mantoverde development project by approximately 40%, and we anticipate this project being highly capital efficient. Slides 12 through 15 illustrate our construction and commissioning progress across several key areas of the MVDP.
Cashel Meagher
executiveSlide 12 illustrates how the fourth and final Shovel comes together. The 3 electric shovels assembled earlier began mining work last year, and that resulted in more than 5 million tons of Sulphide ore being stockpiled. In addition, we have another 6 months of Sulphide ore exposed within the pit, which further reduces ramp-up risk. Slide 13 gives a close-up view of the SAG and Ball Mills, with the flotation circuit visible in the background on the left side. As I noted, the mills have been turning under power, and material was introduced during the first quarter. To be specific, the SAG and Ball milling circuits were tested at 100% charge load, and we are nearing a 30-day running test. Located behind the mills and on the left are several sections of the flotation circuit. We have commissioned the rougher flotation cells, and they are ready for full throughput testing. The cleaner columns, tower mills, scavenger circuit and filter press are each at various commissioning stages as well, and we remain on track for first saleable concentrate in Q2. On Slide 14, the tailings storage facility is shown, and in the background you can see our water reservoir, which has been filled with desalinated water for site use.
Cashel Meagher
executiveAlso, this slide shows that Mentaverde ranks among the driest locations on the planet and lies roughly 900 meters above sea level. From where we sit, it stands as one of the finest sites anywhere for having constructed a copper concentrator and for ramping one up. Finally, Slide 15 shows our desalination facilities along the coast, around 40 kilometers from the mine. That capacity has since been enlarged and brought up to full operation to serve MVDP. We're eager to keep ramping up the Mantoverde development project through the coming few months. Moving to Slide 16. Our aim was a 2-year, $25 million exploration program at the outset, concentrated on our highly prospective Mantoverde, Santo Domingo land package. In our belief, this effort will show even more clearly how world-class this district is. Since Mantoverde is close to completion, we can turn our attention now to growth opportunities, among them the plan to carry out a $25 million exploration program involving more than 61,500 meters of drilling. There are three initial objectives for this program: first, to target higher copper grades at two locations; second, to explore new areas next to or within the existing Mantoverde pits that could add new reserves and/or resources; and third, to test priority targets in the northern portion of the Mantoverde land package that might support the Mantoverde Santo Domingo district.
Cashel Meagher
executiveThe first phase of work is split between targets near the mine and those in the Northern District. On this slide, the Mantoverde Santo Domingo district appears on the right-hand side. Within the northern portion of our Mantoverde land package, we have identified a number of high-priority targets, showing either copper mineralization at surface or a combination of geological and geophysical characteristics similar to the Mantoverde mineralization style. The existing Mantoverde pits follow the Mantoverde fault. North of there lies roughly 12 kilometers of underexplored ground along the Atacama fault. This fall line hosts a number of historic artisanal mine workings, and in our view, the northern part of the Mantoverde District has strong prospectivity. In the Northern District of Mantoverde, our target is a 200 million to 300 million ton ore deposit, with grades of 0.4% to 0.6% copper. Past this initial program, we are also pinpointing our priority exploration targets at Santo Domingo. Two key areas of focus will be drilling out the oxide resource at Santo Domingo, which could supplement our underutilized SXEW plant at Mantoverde, currently running at two-thirds capacity. The second is to push exploration forward for additional copper-bearing sulphides nearer to the existing pits. Moving to Slide 17.
Cashel Meagher
executiveWe've mapped out the near-mine targets that we think could add to our grade profile and help extend mining at Mantoverde. Our plan is to explore continuity along the Santo Clara corridor and test the areas north of the pit, and we'll also be drilling for Sulphides between the Manto Ruso & Kuroki reserve pits. All told, the team has pinpointed nine targets for near-mine exploration that we believe could have an impact on our grade profile at Mantoverde down the road. This exploration program marks the beginning of what we expect will shape copper mining across the Mantoverde Santo Domingo district for many decades ahead, with a goal of more than 250,000 tons of copper production each year. I'll now hand it over to Wendy King for the sustainability review.
Wendy King
executiveThanks, Cashel. Turning to Slide 18, we'll go over the sustainability highlights from Q1. In 2023, at Mantos Blancos, renewable energy certified sources — as defined under the International Renewable Energy Certificate standard — supplied 100% of electricity use. Under our sustainable development strategy, we're working toward a transition to at least 50% renewable electricity in Chile by 2025, and to more than 90% renewable electricity throughout Capstone by 2030. Also in Chile, ISO 50001 energy efficiency management system certification was awarded to both Mantos Blancos and Mantoverde. ISO 50001 exists for organizations that are committed to tackling their impact, preserving resources, and strengthening their bottom line via efficient energy management. Our organization, we believe, will find it easier with this management system to fold energy management into our broader efforts at improving quality and environmental management. An interim target is also part of our sustainable development strategy: cutting greenhouse gas emissions from fuel and power by 30% by 2030, measured against a 2021 baseline year. To back this up, GHG emissions and energy management teams have been set up at every one of our sites to lead the creation of our operating level greenhouse gas and energy reduction plans. Over the quarter, a climate-related risk and opportunity assessment and scenario analysis were also finished.
Wendy King
executiveDoing this also brings Capstone more in line with the task force on climate-related financial disclosures. During this quarter, we started to add a section focused on ESG inside our management’s discussion and analysis, and we anticipate more extensive disclosure during the second half of 2024. In 2023, Mantoverde and Mantos Blancos each received the Copper Mark. And Pinto Valley and Cozamin are working hard to do the same. In Q1, PV and Cozamin refreshed their self-assessment and GAAP closure projects so they match the newest Copper Mark version 3, and both sites aim to sign commitment letters in 2024. Finally, every one of our sites stays involved in our local communities, backing a range of initiatives and priorities. Among the first-quarter highlights are the Pinto Valley cleanup, the graduation of the third cohort of the Learning for Development Community training program at Mantoverde, and the graduation of the first cohort of all female haul truck operators at Mantoverde. Making a positive difference in the lives of our people and our communities sits at the heart of our purpose at Capstone. We are always glad to talk about our ESG performance and initiatives with analysts and investors and are available for calls to discuss them further. And with that, I’d like to hand it back to John.
John MacKenzie
executiveThanks, Wendy. If we move to Slide 19, we've laid out the growth plans where we lead the sector, along with some extra upside sitting inside our portfolio. As you can see, once MVDP reaches its full run rate, we anticipate that it will take us to a consolidated annual production level of roughly 260,000 tons of copper, at costs of about $2 per pound. As Cashel said, we intend to publish a feasibility study for our Mantoverde optimized project by midyear — a low-risk brownfield expansion that we believe will unlock a further 20,000 tons of copper, with capital efficiency that is highly attractive at roughly $7,500 per ton of annual production. From that point, we have a pathway to more than 400,000 tons of copper production once we add our Santo Domingo project, located 35 kilometers from Mantoverde, and together these will establish a world-class mining district in that part of Chile. On top of that, there is additional upside throughout our portfolio: another low-risk brownfield expansion opportunity at Mantos Blancos, the ability to unlock cobalt in our MVSD districts, and finally, the potential development of world-class districts around our Pinto Valley mine in Arizona. Moving to Slide 20, we highlight the time lines for several of the studies I mentioned, as well as for other milestones as we carry out our growth plans.
John MacKenzie
executiveTurning now to how copper output will increase — what Capstone has in place is not something that comes together quickly. At Mantoverde, the site where first salable concentrate is nearly ready to be produced, the choice to expand output was made almost nine years back. If you look at the sector as a whole, the queue of copper projects stands at its lowest level in two decades. At the same time, demand for copper worldwide is set to rise by a tremendous amount in the years ahead. To illustrate, generating one megawatt of offshore wind power calls for eight times the copper needed for one megawatt from coal or gas. Growing the electricity grid and the distribution systems will likewise demand vastly larger quantities of copper. And more recently, we are gaining greater insight into the data centers needed to power artificial intelligence. From where we sit, the copper market is at the beginning of a new era, and this is an excellent moment for us to be increasing output at Mantoverde, our flagship asset. With that said, we are ready to take your questions.
Operator
operatorThanks. <<operator_script>>. Our first question is from Dalton Baretto at Canaccord Genuity. Go right ahead.
Dalton Baretto
analystThanks. Good afternoon, John and Cashel. I'd like to begin by asking about MVDP. As of March, you've had the mail — or you've started working through it. I'm just curious what your view is on how the circuits have responded up to now, not from a metallurgical standpoint but also from a general operational one. Thank you.
John MacKenzie
executiveThanks, Dalton. I’ll hand that over to Cashel for a fuller response, but I’d note that I was down there about a week ago. From what I saw, the plant is behaving just as intended. I’d say we’re quite happy with how things are going. And certainly, what we’re observing there lines up very closely with what we expected. So perhaps, Cashel, for a somewhat more complete answer?
Cashel Meagher
executiveDiscussing metallurgical characteristics is a little premature at this stage. That said, the crushing circuit and the grinding circuit are performing very well. In the coming weeks, we will just be starting to examine metallurgical responses. Even so, all is proceeding as planned. Fingers crossed — with these ramp-ups and these late commissioning cycles on such operations, what you want is for no major failures to occur. And everything is behaving normally for a ramp-up or commissioning process. So we are genuinely encouraged. We stay on track and on schedule, and we are truly pleased with the progress achieved up to now.
Dalton Baretto
analystOkay, thank you, Cashel. Maybe we can turn now to Santo Domingo. Since you're finishing up the report, and if I recall the November 2022 release that laid out all the synergies, could you remind me, John, which of those are going to be part of this report?
John MacKenzie
executiveYes. So we are definitely folding in quite a few of the synergies that were pinpointed back then, and those synergies fall into different categories. A portion of them come from efficiencies gained by having infrastructure or operations situated near each other. Clearly, several are scale-related synergies that exist between the assets. That said, I would argue the most significant synergies are actually the ones that ultimately drive revenue. Those include, for instance, processing the oxides ore that we have at Santo Domingo at the months of at the SXEW plant, and also, for example, the joint processing of cobalt from both sites. At this point, those studies have not yet reached the same feasibility level as the remainder of the Santo Domingo project. So they will appear in the opportunity section of that feasibility study. And we anticipate being able, within a relatively short period afterward, to bring those opportunities into the base case.
Dalton Baretto
analystThanks, John. And maybe I can just fit in one more. As you look ahead to sanctioning Santo Domingo, and given your former employer, John <<inaudible>>, I'm curious how you weigh the buy versus build question.
John MacKenzie
executiveI think we're in a really, really lucky spot in that the chances we have sit quite high on the capital efficiency curve. So we have just finished building Mantoverde at roughly $11,000 in annualized ton. For Mantoverde optimized, our estimates come in at about $7,500 an annualized ton. And we also think Santo Domingo — it has a mix, I'd say, of somewhat greenfield and brownfield traits — is going to be a bit higher than Mantoverde, though it will still be very competitive. So I think how we see this is that what the world truly requires over the next decade or 2 decades is far more copper. And that has to come from somewhere. And I think we're lucky in that we can bring it online in a highly capital-efficient manner. And that really reflects three things. One is that we have great grades at those deposits. We already possess very, very substantial infrastructure in the district. And then finally, it's simply a great location for building projects, and it's low altitude, it's nearer to the coast, and it's fairly close to some major mining centers. So I think from where we sit, our strategy of pursuing our internal organic growth stays very much intact.
Dalton Baretto
analystAppreciate it — I'll stop right there.
John MacKenzie
executiveThanks, Dalton.
Operator
operatorThanks. The next question is from Orest Wowkodaw at Scotiabank. Go ahead, please.
Orest Wowkodaw
analystGood afternoon. To continue from where Dalton stopped, I'd like to ask how soon you expect to proceed with the Mantoverde optimization project as you ramp up, specifically regarding Phase 1.
John MacKenzie
executiveYes. That's a solid question. The way we see it, we submitted the permit application for that project fairly recently. It's a DIA, and we'd anticipate receiving it probably somewhere in the neighborhood of 10 to 12 months. This isn't a complex project. There really isn't anything we're altering when it comes to the overall footprint of the business. That should put us in a position early next year to actually get the project underway. So, we're looking at advancing the detailed engineering ahead of that. We're looking at putting in some long lead time orders before then. And what we've said on month over is that we're going to be ramping up during the third quarter. We expect steady-state production in the fourth quarter. From that point onward, as we bring on the incremental equipment involved in Monterey optimized, we'd certainly be looking to move up to that 45,000 tons a day as we progress toward the back end of 2025.
Orest Wowkodaw
analystAll right. And for that project, are you still expecting capital expenditures of roughly $150 million?
John MacKenzie
executiveCorrect.
Orest Wowkodaw
analystOkay, and one last thing if I may. I’m just curious whether you could update us on the JV process — the JV sale process for Santo Domingo.
John MacKenzie
executiveSo we can’t really move that process forward in any meaningful way until the updated feasibility has actually been published. We expect that updated feasibility to come out around the middle of the year. And then, during the second part of this year, our intention is to really engage with those parties that we already know have expressed a strong interest in participating in Santo Domingo. So by the end of this year, we would hope to have a lot more clarity on who that partner is going to be.
Orest Wowkodaw
analystAll right, that's great. Thanks a lot.
John MacKenzie
executiveAppreciate that, Orest.
Operator
operatorThanks. Our following question is from Ralph Profiti at Eight Capital. Go ahead, please.
Ralph Profiti
analystThanks, operator. Good afternoon, everyone. Cashel, from a technical standpoint, it sounds like the grinding circuit and flotation were separated by challenges of roughly equal difficulty. I'm just wondering: as you get to the particle separation stage, which key deliverables within the design criteria will you be watching closely?
Cashel Meagher
executiveSure. Thanks. Honestly, from what I’ve seen when bringing copper concentrators up to speed, throughput is the thing you concentrate on first during a ramp-up, and it matters most because, plainly, without the ability to crush or grind the rock, there’s no way to liberate any minerals. And every one of our reagents, our flotation circuits, and all that sort of equipment is simply moving slurry along. And in fact, it floats pretty readily, and we’re aware it floats very readily — the chalcopyrite does so almost right away. So what happens in the latter half of a ramp-up is that you’re optimizing, going from roughly the low-80s up to nearly 90% recovery. And it’s just that 10% you’re dealing with, and you’re tuning, and you’re carrying out that kind of work. So what we’re observing is that at a 100% load charge, we’re hitting the P80 specs we need so the flotation cells can liberate the chalcopyrite and perform the flotation. So we’re just now starting up, in the final sequence of our commissioning, a few of our cleaner circuits, our scavenger circuit, our copper thickener, and our filtration, which will let us begin floating that material.
Cashel Meagher
executiveHowever, with any kind of ramp-up at a copper concentrator, your attention always goes first to crushing and grinding, and after that you turn to flotation. Next you concentrate on the hardening of the crushing, grinding, and tailings circuit. You handle the flotation. And once throughput reaches a consistent, sustainable level, that is when you begin tweaking copper recovery to push it higher. Still, everything is proceeding precisely as planned so far. And again, I'll knock on wood.
Ralph Profiti
analystAll right, thank you. That's pretty encouraging to hear. To follow up, looking at the exploration slide for MVDP, it seems that between the outcropping and what the IP has accomplished, there are opportunities in both oxide and sulphide. I'm just curious whether that same strategy applies at Mantos Blancos, where you also mentioned ramping up exploration efforts, and where oxides and sulphides could both potentially be something we see.
John MacKenzie
executiveI'll offer just a few remarks, and then I'll hand things over to Cashel. As an illustration, though: when Anglo American acquired Mantos Blancos back in 1980, it had a lifespan of 5 years. And each time we drill there, we keep extending the resource and the reserve, more or less. So I think at present we've got roughly 16 years, 17 years of life at Mantos Blancos. I believe it's the longest — Mantos Blancos is in fact out in front when it comes to its life over the last 30 years or 40 years or thereabouts. But what we do know is that substantial prospectivity remains, both at depth in the pit. Historically, we weren't able to drill at depth in the pit because of the old underground workings. Now that we've mined the pit through those, we genuinely do have the capacity to see what's at depth. And in fact, the couple of drill holes we've put into the bottom of the pit keep going through very attractive copper grade beyond that. That said, around the lease area, there are certain other areas we consider very highly prospective for oxides or sulphides.
John MacKenzie
executiveAnd we're really lucky that we've got processing plants for each of those now. So our exploration efforts are, to some degree, aimed at both. We see pretty meaningful opportunity in the oxides as well as the sulphides at Mantos Blancos.
Ralph Profiti
analystThat's encouraging. Thank you, John. And thank you, Cashel.
John MacKenzie
executiveAbsolutely, Ralph — thank you.
Operator
operatorThanks. Our following question is from Bryce Adams of CIBC Capital Markets. Please proceed.
Bryce Adams
analystThanks, Capstone, for the update and the presentation. I just wanted to get some clarity on the milestone for MVDP nameplate capacity. When you guide toward hitting nameplate rates in Q3 of this year, does that mean running reliably and consistently at nameplate, or does it mean doing that across a stretch of x many days? I'm just thinking about it — let's say the first concentrate gets produced here in May, June — that implies a ramp-up, or could imply a ramp-up, to full capacity in roughly four months, and if that happens, I'd view it as a very strong performance. And I just wanted to clarify what the definition is around that milestone.
John MacKenzie
executiveSure, Bryce. After we've run the grinding and crushing circuits hard for a 10-day stretch, we kind of enter what we refer to as a commercial ramp-up phase. That process is starting right now, since we believe we're reaching the point where we can pull it off. For us, that's the technical milestone marking the shift into the formal commercial ramp-up phase. You're absolutely right that reaching sustainable full nameplate throughput production in four months would be a terrific metric to hit. We think we're on track for that kind of timeframe. Looking back at the initial feasibility, at the 43 to 101, I believe it was roughly six months. So if you do it, we're right around that timeline at present. Still, given how things are progressing, we see no reason we can't deliver what we've laid out. And everything has gone extremely well so far.
Bryce Adams
analystThat's wonderful to hear. And does that also mean design recoveries are on the same timeline?
John MacKenzie
executiveYes. The rebound trajectory is somewhat less steep than the ramp. But yes, we do see ourselves approaching that level. It takes slightly more time for the curve to get there. However, our view is that once we've reached 80% to 90% of the design recoveries, that satisfies the definition of commercial ramp-up, and from that point we keep making adjustments.
Bryce Adams
analystAll right, thanks — I appreciate it.
Operator
operatorThanks. We’ll take the next question from Craig Hutchison at TD Bank. Please go ahead.
Craig Hutchison
analystHey everyone, good afternoon. I was hoping you might give us a bit more detail on your concentrate off-take commitments, especially since the market is so tight at the moment. I mean, one of your peers said last night that they're actually getting negative TCRCs — they're being paid to take their concentrate. So I was wondering whether you could shed some light across your operations: do you have commitments in place, and where are you exposed to the spot market in order to secure lower TCRCs? Thanks.
John MacKenzie
executiveI'll hand that question over to Jerrold — he's from Investor Relations and also handles our marketing area — so Jerrold, the floor is yours.
Jerrold Annett
executiveYes. Thanks, Craig. I figured that question was coming, so I went back and took a look at it. We've got a substantial amount of unencumbered tons available to move. Right now we're in talks with a number of traders and smelters. The real impact, I'd say, lands in 2025, and at CESCO in Santiago we're pleased with how those discussions are going. It's also clear to us that the benchmark will probably come down quite a bit next year. Beyond that, we're able to lock in tons right now for 2025, and even for '26 and '27, on terms that are very attractive and haven't been seen in decades. So I'd say a $50.05 reduction in our effective treatment charges would bring Capstone's consolidated C1 cost down by more than $0.11 a pound next year. So when John mentioned that MVDP at full rates would be roughly $2 a pound, then if this plays out, as I said, we'd land in the neighborhood of $1.90.
Craig Hutchison
analystSo it sounds like the exposure is more of a 2025 thing rather than upside, I guess, when it comes to cost in this second half of this year?
Jerrold Annett
executiveAbsolutely — so a handful of cargo lots could come through during this year, and securing negative treatment charges remains a possibility. That said, in my view the major effect lands in ’25.
Craig Hutchison
analystAll right, thanks. Perhaps a final item from my side. Turning to the oxides: I believe those expenses came in above what you had anticipated during the first quarter. Could you explain what caused that, and is it confined to this one quarter, or should we anticipate somewhat elevated oxide costs carrying into Q2 too? Thank you.
John MacKenzie
executiveHi Craig. Yeah, we were probably slightly behind on our ambitions regarding how much cathode we were going to produce. So at this point we’re more or less catching up, and part of that was related to placement and part was related to some irrigation, but those are minor operational issues. Still, we don’t see any reason we won’t catch up and correct that in the second half of the year.
Craig Hutchison
analystAll right, that's wonderful, thanks.
Operator
operatorAnd our following question is from David Radclyffe, who is on the line representing Global Mining Research. You have the floor.
David Radclyffe
analystHello, and good morning, good afternoon to John and the team. My first question concerns Pinto Valley, which is clearly performing in line with guidance and building on a solid Q4. Could you perhaps discuss the grade profile and how it is expected to look across 2024? Do you still anticipate improved grades during the second half? Also, were those high grades in Q1 part of the plan, or did you bring some grades forward? Thank you.
John MacKenzie
executiveCashel…?
Cashel Meagher
executiveAbsolutely. Yes. So, some slight re-sequencing occurred during the first half because of a few minor operational problems. As a result, there was a bit of a surprise in the grade, along with that re-sequencing. Still, on the whole, I think the guidance remains valid and will even out across the year on the grade profile. What I would say is that we have steadily been raising throughput from Q4 into Q1. And now at Pinto Valley we are seeing that again in Q2. So our efforts on the asset integrity program are now paying off, and we are really seeing the benefit in consistent throughput. So I will be glad to see, over the coming quarters, the mine finally being challenged against what the plants can do — hitting nameplate throughput figures more consistently. So yes, I think it is still within guidance. We did make a small change in sequence, but we are back on plan now.
David Radclyffe
analystAll right, thanks. Then perhaps turning to Mantos Blancos and the sulphides, it seems there were, clearly, additional stability problems this quarter. You're running somewhat below what was expected. And I believe you're now indicating that you aim to hit the 20,000 ton per day level during the second half of the year. So that appears to have slipped somewhat. Yet you're keeping guidance unchanged. So how exactly do you make up the shortfall at Mantos Blancos sulphides?
Cashel Meagher
executiveRight, so essentially what happened is that at the time we first issued that guidance, we already had engineering work underway on the section of the plant responsible for our sustainability and maintenance problems — the tailings deposition and transportation part, which I believe we've covered a number of times previously. We've now completed a substantial engineering project, moved into procurement, and are currently doing civil earthworks and pouring foundations for the different positive displacement pumps, pipes, tanks, and infrastructure needed to achieve more sustainable production. A portion of the procurement and some of the engineering work ended up taking somewhat longer, and part of the scope also grew. That's the reason we've effectively deferred reaching nameplate capacity of 20,000 tons to what we believe is roughly the Q3 window. We say H2 — we're still awaiting delivery of certain items, though under the current new schedule every item should be ready for assembly in the middle of this year. Regarding catching up, we'll be looking at what opportunities exist in the mine sequencing. That's being figured out right now, to determine whether we can hold the production guidance from that single plant.
Cashel Meagher
executiveStill, we think that across the whole company, combining all the mines, we'll hit the guidance, since we have chances in other areas.
David Radclyffe
analystMuch appreciated. I'll be sure to share that.
Operator
operatorThanks. At this point there aren't any more questions. I'd like to hand the conference back to Mr. John MacKenzie for his closing remarks.
John MacKenzie
executiveOkay, then. We’re eager to bring you another update in early August when we report Q2 results. In the meantime, please stay safe, and don’t hesitate to contact Jerrold or Daniel with any additional questions. Thanks for your ongoing support, and have a good day.
Operator
operatorThanks, everyone. That brings today’s conference to an end. We appreciate your participation. You’re all free to disconnect now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.