Capstone Copper Corp. (CS) Earnings Call Transcript & Summary

February 19, 2025

Toronto Stock Exchange CA Materials Metals and Mining earnings 54 min

Earnings Call Speaker Segments

Operator

operator
#1

Good afternoon, everyone, and thanks for joining Capstone Copper's conference call on the results for the fourth quarter of 2024. Right now, every line is listen-only. After the presentation, there will be a question-and-answer session. Should you need immediate help at any point during this call, just press *0 to reach the operator. Today is Wednesday, February 19, 2025, and this call is being recorded. I'll now hand the conference over to Daniel Sampieri. Please go ahead.

Daniel Sampieri

executive
#2

Thank you, Operator. I want to extend a welcome to everybody on Capstone Copper's Q4 2024 Conference Call. A quick note that the news release and regulatory filings that announce Capstone Copper's 2024 fourth quarter financial and operational results can be found on our website and on SEDAR+. If you've logged into the webcast, we'll be advancing the slides for today's presentation, and those are likewise accessible in the Investors section of our website. Joining me today are our CEO, John MacKenzie; our President and Chief Operating Officer, Cashel Meagher; our SVP and Chief Financial Officer, Raman Randhawa; and our SVP Risk, ESG, and General Counsel, Wendy King. Our Head of Chile, Jim Whittaker, along with our Head of Technical Services, Peter Amelunxen, will also be on hand at the end of the call for questions. Please be aware that remarks made on the call today will include forward-looking information within the meaning of applicable securities laws. By its nature, this information carries risks and uncertainties, and actual results could differ materially from the views expressed today. For more detail on the risks and uncertainties pertaining to our business, please refer to Capstone's most recent filings, which can be found on our website and on SEDAR+. And finally, I'll just mention that all amounts we discuss today are in U.S.

Daniel Sampieri

executive
#3

Figures are in dollars except where noted. At this point, I'll hand the call to John MacKenzie.

John MacKenzie

executive
#4

Thanks, Daniel, and greetings to everyone joining us from the Americas, Europe, Australia, and across the world. We're happy to share our results and accomplishments for the fourth quarter of 2024. 2024 proved to be a major year for us, since we commissioned and ramped up Mantoverde and hit design throughput rates at Mantos Blancos. The year ahead marks an inflection point, with our recently released 2025 guidance showing greater cash flow generation, robust copper production growth, and reduced costs. Our focus will be on operational execution throughout our portfolio and on further deleveraging of our balance sheet, while we keep advancing our pipeline of organic growth opportunities. Beginning on slide five, during Q4 our operations achieved record consolidated copper production of 53.9 thousand tons at consolidated C1 cash costs of $2.56 per pound. That was our strongest quarter of the year in terms of production and costs, and it translated into our best quarter of the year financially. For the full year 2024, we produced a record 184.5 thousand tons of copper at consolidated C1 cash costs of $2.77 per pound, which represents a 12% increase in output compared to 2023. The past year was marked by several major achievements at our mines in Chile.

John MacKenzie

executive
#5

Following our first copper concentrates at the flagship Mantoverde Development Project in June, we reached commercial production levels during September, and by year-end the mill had ramped up to full rates — all within the $870 million capital budget we had previously announced. That is a significant accomplishment, and I want to thank our team for their commitment and dedication over the past three years in delivering this milestone. Turning to the start of the year, I'm pleased to report that in January we averaged above nameplate throughput capacity at Mantoverde, with mill throughput of 33,409 tons per day. I know our team is eager to show what the new Mantoverde sulfide concentrate can do, and that the team remains hard at work getting ready to execute on our Mantoverde Optimized project. At Mantos Blancos, meanwhile, we unlocked the operation's design mill capacity through a successful debottlenecking at the back end of the plants, finishing the year above design mill throughputs in November and December. That continued in January, marking a third consecutive month above the targeted mill capacity of 20,000 tons per day. Our finish to the year at Pinto Valley was subpar, but we're laser-focused on advancing our asset integrity program so that we consistently achieve the design capacity of the operation.

John MacKenzie

executive
#6

Alongside delivering the growth we have slated for the near term, we have also moved our later stages of expansion forward. That came through the release of feasibility studies for Mantoverde Optimized and the adjacent Santo Domingo project—both attractive and executable—during the second half of 2024. On the corporate front, in 2024 we acted to strengthen the balance sheet and add flexibility, highlighted by a $185 million cut in net debt relative to 2023. Our balance sheet sits in excellent shape, and we remain committed to further deleveraging using cash flows generated internally ahead of our next major growth phase. Moving to slide six, as I mentioned, this year marks an inflection point for Capstone. For 2025, our target is 220 to 255 thousand tons of copper output at cash costs of $2.20-$2.50 per pound. With our attention on operational execution throughout the portfolio, we will push our pipeline of organic growth opportunities ahead so the transformation of our business continues, and with that, I will hand things to Raman for our financial results.

Raman Randhawa

executive
#7

Thanks, John. Moving to slide seven now. During Q4 our copper output came to 53.9 thousand tons, which works out to 14% growth versus the prior quarter, and that was powered by rising volumes as MVDP continued its ramp-up. Because of seasonal swells at the load ports in Chile, copper sales for the quarter landed roughly 2,300 tons under payable production. The hit from sales delayed at Mantoverde comes to about $11 million in EBITDA terms, or roughly one cent per share on earnings. Q4 revenue reached $447 million, supported by a realized copper price of $4.04 per pound. That figure was a touch under the LME copper average for the quarter. Even so, looking at the full year, our realized copper price ended up broadly matching the LME average, which speaks well of our QP hedging program. During Q4 we posted solid gross margins of $1.48 per pound, equal to 37%. C1 cash cost came in at $2.56 per pound, down 10% from the previous quarter. The driver was the ramp-up at our Mantoverde sulfide operation, one of our lowest cost sources of production, where cash costs fell to $1.83 per pound in Q4 from $2.52 per pound in Q3. In addition, at Mantos Blancos, running at nameplate capacity, cash costs went from $3.41 per pound in Q3 to $2.30 per pound in Q4.

Raman Randhawa

executive
#8

At Mantoverde, sulfide cash costs ought to fall even more in 2025 once we're running at full nameplate capacity. Q4 adjusted EBITDA came in at $171.9 million, almost twice what it was a year earlier, thanks to better realized copper prices and more copper output as sulfide production ramps up at Mantoverde and Mantos Blancos. Let's turn to slide eight. The left side gives a summary of the liquidity we had available, which as at December 31, 2024, stood above $500 million, comprising $132 million in cash and short-term investments plus $374 million undrawn under our $700 million corporate revolving credit facility. Net debt of $742 million is a touch lower than the previous quarter, now that the MVDP capital cost is behind us. During 2024, we deleveraged successfully, taking our consolidated net debt to EBITDA ratio from 3.6x at the start of the year down to 1.5x by year-end. The chart on the right of the page shows how sensitive our EBITDA is at different copper prices. With the start of 2025, we moved from the light gray bar—2024 actual EBITDA of $496 million—to the turquoise bar, representing EBITDA in the range of $800 million-$1.3 billion at copper prices between $4-$5 per pound, using the midpoint of our 2025 guidance.

Raman Randhawa

executive
#9

With that amount of EBITDA being generated, we can concentrate on producing cash to pay down debt on our balance sheet, and there is a route to getting net leverage below one times at spot copper prices. That gives us a solid base for pushing ahead with our growth pipeline, namely Mantoverde Optimized and Santo Domingo. Turning to slide nine, we'd like to give you a breakdown of what drives our operating costs for 2025 so we can tackle what tariffs might mean for Capstone. If those threatened tariffs do come into force in the U.S., our estimate is that 90% of our 2025 operating costs would not be directly affected, particularly labor, contractors and services, desal, sulfuric acid, and power. Across the consolidated company, year-to-date, we've had some positive tailwinds from favorable foreign exchange movements and from higher bond, by-product pricing than the assumptions in our guidance, and that leaves us well positioned so far in 2025. I'll now pass things to Cashel for the operations review.

Cashel Meagher

executive
#10

Thanks, Raman. We're turning now to slide 10. During Q4, Pinto Valley turned out 11,626 tons of copper, with a C1 cash cost of $3.30 per payable pound. The first half got the year off to a strong start, but in the third and fourth quarters Pinto Valley ran into setbacks, and as a result the mill was operating—excuse me—beneath the level we'd like to see. In Q4, throughput came in at an average of 45,000 tons per day, and unplanned downtime from electrical and mechanical problems left one of our six ball mills out of service. That carried over into the first quarter, though all mills are now running again as of recently. For 2025 at Pinto Valley, our guidance is 51 to 58 thousand tons of copper production, at C1 cash costs between $2.55 and $2.85 per payable pound. We anticipate that copper output will be weighted toward the second half of the year, driven by grades and throughput, with a weaker first quarter stemming from the maintenance I mentioned earlier. We remain committed to implementing our asset integrity program, aiming to boost plant reliability so we can drive higher production and lower costs. On slide 11, the Cozamin mine posted another solid quarter, producing 6,724 tons of copper at C1 cash costs of $1.55 per payable pound.

Cashel Meagher

executive
#11

During Q4, Cozamin’s cash costs got a lift from stronger silver byproducts and a softer Mexican peso, and that kept serving as a favorable factor for 2025. For Cozamin in 2025, we’ve guided copper output of 23 to 26 thousand tons, with a C1 cash cost between $1.60 and $1.80 per payable pound. Our Mantos Blancos asset wrapped up 2024 very strongly, as shown on slide 12. Combined sulfide and cathode output came to 13,563 tons of copper, with C1 cash costs of $2.45 per payable pound. Both production and cash costs improved substantially versus the prior quarter, thanks to a successful concentrator ramp-up following the July installation of new equipment. Now that we’ve finished the work needed to support average throughput of 20,000 tons per day—a level reached for three months in a row—we’re eager to show the market Mantos Blancos’s full potential. For Mantos Blancos in 2025, we’ve guided copper production of 49 to 59 thousand tons, a bit weighted toward the second half because of planned maintenance. C1 cash costs are guided at $2.35 to $2.66 per payable pound, as shown on slide 13. Average sulfide plant throughput in Q4 was 19,600 tons per day, and nameplate throughput capacity was reached in November and December.

Cashel Meagher

executive
#12

We're still seeing robust results as we move into 2025, and in January average throughput came in at 20.6 thousand tons per day. Even before the July shutdown, throughput had begun improving thanks to our asset integrity program. In terms of plant throughput, Mantos Blancos is one-third the size of Pinto Valley, so we anticipated that this program would deliver results faster at this site. We keep rolling this program out systematically across all of our sites to boost availabilities and drive more consistent performance. Turning now to Mantoverde on slide 14, which saw a transformational quarter and year, powered by the ongoing ramp-up of the Mantoverde development project. Total production came to 22,029 tons of copper at a C1 cash cost of $2.53 per payable pound. Looking at the new sulfide operation, we achieved record quarterly copper production in Q4. Plant throughput averaged almost 25,000 tons per day for the quarter. Throughput rose steadily through the quarter, reaching an average of just over 27,000 tons per day in December. That improvement has carried into 2025, with average mill throughput of over 33,000 tons per day, surpassing the nameplate capacity of 32,000 tons per day in January.

Cashel Meagher

executive
#13

At the same time, grades are still lining up nicely with both the mine plan and the block model. A bit of work remains on the recovery side. December averaged roughly 85%, and that slipped back to about 81% in January. Earlier this month, in February, we finished a planned five-day shutdown that involved changing out liners on our mills. On top of that, we keep making additional small adjustments in the flotation area so recoveries can reach design levels in the upper eighties. Our target is to hit those design recoveries during the first quarter. For 2025, copper production and cash costs are forecast to improve significantly, thanks of course to the new sulfide concentrator. Our guidance for Mantoverde in 2025 is 97 to 112 thousand tons of copper production. With a combined C1 cash cost of $2.10-$2.36 per payable pound, Q1 should be the lightest quarter because of that planned maintenance and rising recoveries. As John mentioned, our team is also eager for the chance to execute on the Mantoverde Optimized project. Detailed engineering is moving forward, and we are getting ready to launch the project as soon as possible once we receive a DIA permit amendment, which is expected around the middle of the year.

Cashel Meagher

executive
#14

What has given us encouragement to this point is the individual peak daily throughputs coming in above 38,000 tons per day, and we're eager to de-bottleneck the plant so that it reaches 45,000 tons per day. At this point I'll hand things over to Wendy King for the sustainability review.

Wendy King

executive
#15

Thank you, Cashel. We are now turning to slide 15, where we review the sustainability highlights for Q4. During the last quarter, we released our 2023 sustainability report, and it also featured a data book on sustainability performance. That document covers four years of consolidated Capstone data, plus data at the site level. In 2023, we began reporting GHG emissions on both a location-based and a market-based basis, and you can see how we started making progress against our 30% reduction target. We carried that progress forward into 2024, where we have put key initiatives in place — among them electrifying four generators and three desal pumps at Pinto Valley, along with commissioning the fourth electric rope shovel and adding two electric buses at Mantoverde. These initiatives are also examples of win-win opportunities, since we believe they will cut our emissions while also producing cost savings. Over the course of 2024, we made significant progress toward our sustainable development strategy goal of implementing the Global Industry Standard for Tailings Management across all our TSFs by year-end 2028. Our internal benchmarking shows 48% confirmation achieved at year-end 2024, which came in above our target for the year. I am personally very pleased that we have published our first Responsible Sourcing Policy, which sets out our commitment to embedding our sustainability expectations and considerations into how we select and manage suppliers and goods and services.

Wendy King

executive
#16

We’re really eager to partner with our suppliers so that we can stay aligned with our aim of making a positive contribution to the lives of workers and communities near our sites as well as worldwide where goods are produced. Then, after the quarter ended, in January, we signed a 35-year water agreement with Econssa to lock in a long-term water supply by reusing treated wastewater from Antofagasta. That will also cut marine discharge and boost water recycling at the Mantos Blancos mine. The project calls for a wastewater treatment plant to be built by a third party, and it is expected to be operational in 2028. With that, I’ll hand it back to John.

John MacKenzie

executive
#17

Thanks, Wendy. If you look at slide 16, we've laid out what our main priorities are for 2025. This year, our emphasis will be on running our portfolio well operationally. During the last two years, we've gone through a stretch of major transformation, constructing mines and ramping them up, and at this point we'll concentrate on extracting the greatest value from that portfolio. Mantoverde Optimized represents another central priority for us. As soon as the permit comes through, we intend to move forward on it with maximum speed, since it delivers very strong returns for us, and finally, our attention is on reducing debt and moving our pipeline of organic opportunities forward. If you turn to slide 17, we've set out those sector-leading growth plans along with some of the extra upside that exists within our portfolio. 2025 will extend last year's solid base of 184,000 tons of copper, and we remain on track with the guidance we issued last month. We intend to move ahead with Mantoverde Optimized once we obtain a DIA permit amendment. We submitted our application for the DIA permit in the middle of last year and anticipate receiving it around the middle of this year. Our plan is to fund this project using cash flows we generate internally. MV Optimized has the potential to lift us to roughly 280,000 tons of copper per annum on a run-rate basis.

John MacKenzie

executive
#18

At Santo Domingo, we keep moving forward on figuring out the best financing structure for that project. Our approach here closely mirrors what we managed to pull off at Mantoverde. As part of that, a process is underway to bring in a minority partner at the asset level, and it is progressing nicely. Ahead of any possible sanctioning decision at Santo Domingo, we also want to see every one of our assets running at or close to full production, along with consolidated net debt to EBITDA under 1 times. And naturally, we will keep the broader macroeconomic backdrop in mind as well. As we see things right now, that creates a possible sanctioning window for Santo Domingo beginning in 2026. Santo Domingo could lift our output to roughly 400,000 tons of copper per annum, with consolidated costs that are even lower. Past these projects, we are working diligently to capture more upside throughout our portfolio — another low-risk brownfield expansion chance at Mantos Blancos, added flexibility in the MV-SD district to unlock additional copper and possibly byproduct cobalt output, and the potential build-out of a further major copper district surrounding our Pinto Valley mine in Arizona.

John MacKenzie

executive
#19

So let's move to slide 18, where I'll give a recap. During 2024, we brought this initial stage of Capstone Copper's transformation to fruition, delivering concretely on growth that leads our peer group. Our position is very strong for becoming a top-tier, long-lasting, low-cost copper producer that plays a meaningful part in backing global decarbonization and electrification efforts — and on that note, we're ready to take your questions.

Operator

operator
#20

Ladies and gentlemen, the question and answer session is starting now. If you have a question, on your touch-tone phone please press star and then the number one. A prompt will sound telling you your hand has been raised. If you would like to decline from the polling process, press star and then the number two. When on a speakerphone, please lift your handset before you press any keys. Our first question is from the line of Orest Wowkodaw at Scotiabank. Please go ahead.

Orest Wowkodaw

analyst
#21

Hello, and good evening. It's great to see the progress at Mantoverde this January. I'm curious about what you expect for reaching sustainable throughput and design recoveries over the coming couple of months. It sounds like we should anticipate some maintenance affecting February and Q1 as a whole, but I'm wondering whether we're aiming to exit Q1 with both of those essentially at steady-state nameplate.

John MacKenzie

executive
#22

Thanks, Orest. The way you’ve laid it out definitely matches how I see things, but I’ll have Cashel give that comment a bit more detail.

Cashel Meagher

executive
#23

I suppose I can't simply say ditto. Still, that is indeed what we expect. Given where we stand today on recoveries, we believe production is stabilizing. As we mentioned, we had a scheduled maintenance effort in place to reline the mills. Yet clearly, judging by how things have progressed—pardon me—with the recoveries achieved so far, we expect that by the quarter's end we will reach standard nameplate operation. So it is going well.

Orest Wowkodaw

analyst
#24

That's really encouraging to see. Perhaps we can change topics a little. Now that Mantoverde is performing so well, Santo Domingo is clearly going to draw more attention. John, I'm wondering whether you have any debt reduction targets in mind before a sanctioning decision, or do you feel the balance sheet is strong enough that you could move ahead with it even in a somewhat uncertain copper market?

John MacKenzie

executive
#25

Sure, that's a fair question. What I'd really like to see is every one of our remaining assets running at full capacity or extremely close to it, with solid confidence that our Asset Management Framework is being executed successfully, and also producing cash and beginning to chip away at the overall debt we carry. As I mentioned a bit earlier, we're aiming for a net debt to EBITDA ratio under one. That target clearly has two components. The first is an absolute cut in our debt, and we've clearly hit that inflection point now that we've begun bringing it down, lowering our debt as of this last quarter. But at the same time, we're also lifting EBITDA considerably. So that ratio keeps looking better and better. Still, I definitely want us to reach a point where, judged by that backward-looking metric, we can feel comfortable that we sit below a one times net debt to EBITDA ratio. After that, we'll of course be watching the macro picture. I don't believe it's simply a matter of saying that if copper prices are elevated, that automatically means we proceed with the project. We also have to examine what's going on in the broader project environments.

John MacKenzie

executive
#26

At times, launching a project actually works out better when others aren’t doing the same, because you can secure favorable contractor rates and improved lead times on assets. That said, I think we see ourselves approaching a sanctioning window probably around the start of next year. That will really mean examining the macro environment, examining our internal environments, and simply ensuring that this is the correct timing for taking the project’s next step.

Orest Wowkodaw

analyst
#27

Appreciate that additional detail.

John MacKenzie

executive
#28

Absolutely.

Operator

operator
#29

The following question is from Kate McCutcheon of Citi. You have the floor.

Kate McCutcheon

analyst
#30

Morning John, thanks. To pick up on Santo Domingo: you said the sanctioning window would come early next year. How are the discussions going on the sell-down stake, and when will you update the market on that?

John MacKenzie

executive
#31

Yeah, thanks, Kate. Things are progressing nicely. We kicked off a process late last year, and a fair number of parties came into the data room. Our intent has always been to narrow that down to a smaller group, because in the end this isn't simply a matter of whoever bids first or highest winning. What we're really talking about here is a partnership that will run for the next 30 or 40 years. So ultimately, it comes down to negotiating with a very small, select set of preferred partners we've identified. As of today, we've reduced that group to six parties we're holding discussions with. I'd expect that around the middle of the year, we should be able to give further updates on where those conversations stand. Alongside that, we're beginning to push ahead with other financing talks on the project financing side. Obviously, the two are linked to some degree. The type of party that comes in would also, to an extent, shape the final financing structure for the project.

John MacKenzie

executive
#32

And I'd add, Kate, that around the same time, several work streams are running in parallel. We're examining quite a few opportunities. I believe we've discussed certain synergies that generate revenue. At Santo Domingo we have 90 million tons of oxides. Right now those aren't part of the base case plan. That represents a significant opportunity ahead. Cerro Norte was acquired by us late last year. Our ultimate intention is to fold that ore into a mine plan for Santo Domingo. So there are multiple parallel streams of work. We're likewise exploring opportunities, instead of constructing all of our standalone infrastructure ourselves, to see where infrastructure sharing might be possible. And all of those, I'd say, are parallel work streams that are actively underway at present. So there's plenty in motion, but I think we're quite encouraged.

Kate McCutcheon

analyst
#33

All right, that helps. Turning to tariffs and the administration — a few of your competitors have brought up possible tax advantages, though those relate more to refining. Is there anything favorable worth flagging, maybe around capturing that COMEX premium, or any tax tailwinds that people have been discussing?

John MacKenzie

executive
#34

Sure, so we do have the Pinto Valley mine in the U.S., and over the longer term, one might see some potential opportunities emerging there. But regarding what the tariffs imply right now, you're seeing a pretty significant premium between COMEX and the LME. For us, ultimately, it's probably a fairly neutral outcome. We're not heavily exposed to tariffs on our input costs. If tariffs were to affect global GDP growth, that could be viewed as a modest negative. On the other hand, should that prompt additional stimulus in China, that would be a positive. So our view at this point, without further information, is that it's really swings and roundabouts right now, and we don't see any real impact on the medium- or long-term very positive fundamentals for copper.

Kate McCutcheon

analyst
#35

Alright, thank you, John.

Operator

operator
#36

Daniel Morgan from Barrenjoey has the next question. Go right ahead.

Dan Morgan

analyst
#37

Hello. My first question relates to the guidance that was issued a few weeks ago—could you perhaps elaborate on the main assumptions built into it, especially at Mantoverde, and essentially what has to happen for us to land at the top end of that guidance, or what could go wrong that would put us at the bottom end? Thank you.

John MacKenzie

executive
#38

Appreciate the question, Daniel. Since our President and Chief Operating Officer, Cashel Meagher, is sitting here alongside me, I'll hand that over to him.

Cashel Meagher

executive
#39

Alright, I'll give it my best shot. So Mantoverde — as you can see in the guidance, we've set the copper tonnage at 68,000 to 80,000 tons for the sulfides, sorry, and 29,000 to 32,000 tons for the cathodes. The reasoning there is that things could turn out favorably. There's upside if we get to the middle of the year and we do secure our permit — it's noted that for one month we ran at 33,000 tons per day and now and then we reached 38,000 tons per day. So that potential isn't really built into the guidance for the second half. That's a positive, since we're a multi-asset portfolio today, and when one asset is having difficulties, another one will compensate. And that's the genuine blessing we have now that Mantos Blancos and Mantoverde are ramping up — we anticipate having four assets running dependably. For Mantoverde on its own, taking the middle of the guidance range, that implies roughly 30,000 to 31,000 tons per day through the sulfide plant, at approximately reserve head grade of 0.77 for the year and recoveries somewhere in the mid-80s%. We believe that's within reach. For sure, we've had a solid start here, and our predictive maintenance is certainly performing very well, plus we completed a successful shutdown and reline.

Cashel Meagher

executive
#40

The way 2025 is taking shape has us genuinely encouraged.

Dan Morgan

analyst
#41

Thanks. Yeah, thanks — that answers it. But to broaden things a little, on the cost part of your guidance, could you say what's baked in there when it comes to treatment charges? Have you factored in what looks like a very favorable settlement, or not?

John MacKenzie

executive
#42

Right, right. Could I just get Raman to weigh in on that?

Raman Randhawa

executive
#43

Yes, well, the cash costs we have do incorporate the present TCRC market. So I would say the cash cost we've budgeted sits at roughly $25-$30 a tonne. If you look at the mix of our concentrate, 56% is benchmark and 44% is spot. That means there's clearly a chance in the spot market, near zero or negative, to come in under some of that cash cost. But taken as a whole, it comes to about $25-$30 a tonne.

Dan Morgan

analyst
#44

Thanks. And the final question concerns the Mantoverde Optimized project—what's the most current target for an FID? What critical path has to happen for that, which I believe was mid-year, if I have that correct?

John MacKenzie

executive
#45

Yes, that's right. So right now we're moving the detailed engineering forward on that. We expect it to wrap up roughly around mid-year. The real critical-path element is getting the permit amendment, the DIA. It isn't a major permit, but clearly we need it in hand before we can move ahead properly. We filed that around the middle of last year. Typically these take about 12 months. We've just finished answering the second round of questions the authorities raised. That's usually a pretty good signal as to whether there are any complicated issues or whether it's fairly straightforward, and I think we felt very, very comfortable with the kind of questions being asked, so I think at this point we remain confident that around the middle of the year we should receive that permit. We aren't seeing any red flags at this stage on that front. But that really is the gating item. It may well be that between now and then we decide to begin ordering a few long lead time items. And obviously, we just need to consider where the market stands in terms of lead times on certain pieces of equipment.

Dan Morgan

analyst
#46

John and Cashel, I really appreciate you both sharing your points of view.

John MacKenzie

executive
#47

I appreciate that.

Operator

operator
#48

Moving on, Adam Baker from Macquarie has the next question — your line is open now.

Adam Baker

analyst
#49

Good morning or good afternoon, John and team. I just want to follow up on that MV Optimized, specifically regarding the CapEx guidance, since we're noting that no CapEx from it is coming through in 2025. Compared with the feasibility study from the end of last year, which, if I remember correctly, did include roughly $100 million in CapEx for the MV Optimized project expansion, how should we be thinking about CapEx from MV Optimized this year, given that, if all goes well, permitting will come through mid-year? Would you expect to greenlight the project as soon as that permit comes through? And if so, could CapEx potentially be re-evaluated? Sorry.

John MacKenzie

executive
#50

Right, so the capital needed for this project is $146 million for MV Optimized. The return is tremendous. So this is the kind of project that makes sense to do as soon as we possibly can. And given that we have that permit in the middle of the year and we're able to commence then, I think our current estimate is that we'll probably spend about $73 million of that budget this year and $73 million in the first half of next year. But as you say, that's not currently in our CapEx budget. It's obviously until we've got a project to an approval stage, and that involves having all the permits required, we'll obviously be taking that to our board, getting approval for it, and obviously we'll then be sort of notifying of that change in CapEx.

Adam Baker

analyst
#51

Right, understood. So that $10 million in expansionary CapEx you have in there now — that could involve a couple of long lead items, potentially. And then, should permitting and board approval come through, that has the potential to rise if everything goes well.

John MacKenzie

executive
#52

Yes, that comes to 10 million. Should we reach that point, another 62 would be added, bringing the total to 72 for the year.

Adam Baker

analyst
#53

Understood. All right, thanks so much. And the Mantoverde ramp-up looks like it's going really well. I just noticed that your throughput is at 32,000 or 33,000 tons a day — should say, above nameplate levels. Is there room to push that further? Do you even need to push it further? And is it just recoveries you're working on now, and are you very comfortable from the front end of the plant perspective?

John MacKenzie

executive
#54

Jim Whittaker is with us, and he leads our Chile operations, so I'd say he's in the best position to field that one.

Jim Whittaker

executive
#55

Yes, hello. As Cashel said earlier, there have been certain days when we were right at the nameplate figure. Naturally, we aim to operate above that level so we can absorb any downtime we run into while continuing to ramp up this plant and learn more about this new facility of ours. We have reached days as high as 36,000 to 38,000 tons per day. So our confidence in the plant's throughput design is very, very strong. Recovery has picked up a bit more slowly. We were in the high 80s in December and the mid-80s through January. So we're quite confident that we're heading in the right direction on that front too. As a result, we don't foresee any major changes to what we've put out regarding the plant.

Adam Baker

analyst
#56

Appreciate it, everyone. I'll pass it along now.

John MacKenzie

executive
#57

Appreciate that, Adam.

Operator

operator
#58

Paul Hissey from Moelis has the next question in the queue. Go right ahead.

Paul Hissey

analyst
#59

Oh, hello everyone. I was just wondering whether you could give us a bit of commentary or an update on any discussions or plans that might be underway with your neighbors near Pinto Valley, please.

John MacKenzie

executive
#60

Sure, I can offer some opening remarks on that, and then I’ll ask Cashel to add a bit. As you know, a couple of years back we signed an agreement with BHP concerning Copper Cities for certain drilling activities. That drilling has now finished, and the resource model has been redone. In essence, it confirmed what had already been identified. Since that point, our focus has really been on a set of option studies examining how a district development might be configured under different alternatives. That effort is ongoing at present. So at this stage we have no conclusions from it. Cashel, is there anything further you’d like to add?

Cashel Meagher

executive
#61

No — we’re still operating under that option agreement John referred to. It’s scheduled to lapse around the middle of this year, though we’ve already extended it once. That said, given how things are moving, our hope is that another extension won’t be necessary. There’s a joint committee looking at what’s possible in that region by linking Copper Cities with Pinto Valley. Of course, Pinto Valley on its own holds 1.4 billion tons, and at Copper Cities there’s a historic resource that comes close to that figure as well. So it’s an enormous resource and an enormous chance to improve the mine plans in that area. We’re therefore working alongside that group. They’re highly collaborative, and the aim is to determine the best route to extract value from both sites. All I can really say is that it’s going very well.

Paul Hissey

analyst
#62

All right, so I’m hoping you can give us a bit more detail on that potential mid-year point, just picking up on what you said about possibly not needing to renew the option agreement once more. So yes, I appreciate the answer. That’s useful.

John MacKenzie

executive
#63

Appreciate it, Paul.

Operator

operator
#64

Dalton Baretto with Canaccord has the next question for you. Go right ahead.

Dalton Baretto

analyst
#65

Thank you. Good afternoon, John, and to the team. A majority of what I wanted to ask has already been covered. However, John, I believe infrastructure sharing came up among the work streams tied to Santo Domingo, and I'd like to know whether you could say a bit more about that — in particular how it connects to the JV process that's underway, and likewise what it might mean for the capital involved in the project. Thanks.

John MacKenzie

executive
#66

Right. And of course, this project was put together and filed as a standalone thing. So permit issues played into some of that as well. We intend to construct a further desalination facility — a second one — simply because to expand the Mantoverde plant we'd need a permit, while through Santo Domingo we already have a desal plant that's fully permitted. It also means we'll be building a port of our own. Now, all of that clearly provides us with a lot of strategic flexibility. But one of the matters in Chile that the government has certainly been concentrating on is that it would make much more sense if mining companies shared infrastructure. Doing so clearly means a smaller environmental impact when it comes to how many sites are affected, but it also helps because generally the cost of these kinds of facilities is largely fixed. And so the greater the throughputs you achieve, the lower unit costs become. So I think the industry broadly shares the view that sharing infrastructure carries plenty of benefits. Now, along that coast there are already quite a few ports and quite a few desal plants in existence.

John MacKenzie

executive
#67

One of the work streams, obviously, it sort of makes sense for us to complete this before we sort of move forward and build our own — and that is the base case — just to evaluate whether an economically more attractive option exists to share infrastructure with another party.

Dalton Baretto

analyst
#68

Understood. All right, thanks. Then perhaps just one final question, and this is pretty much a housekeeping matter. Within your CapEx guidance, there is $80 million allocated toward what I believe you'd describe as ESG-related projects — tailings, dam upgrades, and items of that nature. My question is simply whether that figure will be something of a recurring number as we move forward, or is it a one-off?

John MacKenzie

executive
#69

No, I believe we're currently in the middle of migrating every one of our sites toward GISTM compliance. And a few of our sites — Mantoverde has already reached that point, since we designed and constructed it just recently, and we did so consistent with those standards. For the rest of our tailings facilities that clearly were built before those standards existed, we have plans in place to get them there. And each one has somewhat differing lengths of time required to reach that status. I'd say the one with the furthest-out date is likely Pinto Valley, which will probably need something like two or three years to arrive at that point. Mantos Blancos, I think, is probably two years, roughly that. So that's roughly the horizon across which we'd expect that capital to recur. After we get there, we return to simply the ordinary maintenance expense of keeping those facilities running.

Cashel Meagher

executive
#70

Yeah, I'd say that Dalton is going to come up again for a few years. It might not happen at that same pace, so you could see somewhat of a decline from 80 downward, but there will be some continued interest, as John mentioned.

Dalton Baretto

analyst
#71

Got it. Thanks a lot, everyone.

John MacKenzie

executive
#72

Appreciate that, Dalton.

Operator

operator
#73

Ladies and gentlemen, one quick note before we proceed: to submit a question, just hit star and then the number one on your touch-tone phone. If you'd rather opt out of the polling process, press star and then the number two. Also, for those on a speakerphone, please pick up the handset before you press any keys. Our next question is from Sam Catalano at Wilsons. Your line is now open.

Sam Catalano

analyst
#74

Oh, yeah. Hi there, good morning — or good evening, depending on where you're joining from. I just had a quick question about Pinto Valley. Obviously, you gave us a great update on how well the Chilean assets performed in January, but you also pointed out some of the difficulties Pinto ran into toward the end of last year. I'm just wondering how things are going so far this year, and whether you see any risk to your cost guidance in particular coming from Pinto.

John MacKenzie

executive
#75

Thanks, Sam. I’ll have Cashel address that.

Cashel Meagher

executive
#76

Absolutely, Sam, thank you. We do have a plan in place. That plan involves building out a proactive maintenance process rather than constantly reacting to unplanned maintenance events. And clearly, as that system matures — we call it our asset management framework — we become more predictive, particularly regarding the older components inside a mine. So at Pinto Valley specifically, most of the asset is quite aged, given it was built in the 1970s. We're making very solid progress there. We did experience some unplanned events in Q4, obviously, that you referenced in your question. And the fix for that carried over into January, as we mentioned in the script. But we've worked through that now as of February, and we're back up and running with all 6 ball mills. So we do have planned maintenance scheduled. That is fully factored into the guidance. And so we're meeting the cadence that we believe will get us to the guidance we've provided for Pinto Valley. So we don't expect to fall outside of it. And within that guidance, there is some room for unplanned events. So what we're hoping is that we get ahead of them through this asset management framework and this predictive maintenance model.

Cashel Meagher

executive
#77

A large number of folks are dedicated to this effort. It's the top priority for the general management team there. And we're confident that the work we've invested throughout the past year is going to pay off this year.

Sam Catalano

analyst
#78

Alright, thanks, Cashel. I want to dig into that a bit further. The reason I'm asking is that South America appears to be performing really strongly. And when I look at the company's overall volume guidance of 20 to 255 for the year, it seems that the Chilean assets will come in as expected so far. Would it be fair to say that you feel Pinto is likely the largest risk when you consider that guidance number for the latter part of the year?

Cashel Meagher

executive
#79

You know, the whole thing comes down to forecasting what can't be forecast. So every event we can plan for gets included, whether that's scheduled maintenance, Mantoverde, and/or Pinto Valley. What I'd say is the guidance carries the risk that's inherently part of it. So when you look at Pinto Valley's throughput and at how it performed in the first half of last year, which was 54,000 tons a day with no unplanned interruptions, that's above the midpoint of the guidance we've put out here, which sits at 52. So if you're speaking in terms of risk, that's been adjusted within the guidance. If you're speaking strictly on a comparative or relative basis of whether we anticipate or have factored in more unplanned breakdowns at Pinto Valley than at our brand new plant at Mantoverde, yes, but that too is reflected in guidance. We've put our best foot forward regarding what's achievable and what we believe is reliable from the assets as they stand today, with the goal of improving on them year-over-year.

Sam Catalano

analyst
#80

Thanks, Cashel. That's really useful context, and I appreciate it.

Operator

operator
#81

That brings us to the end of the question-and-answer portion. At this point, I'll hand things over to John MacKenzie, who has some closing remarks. John, the floor is yours.

John MacKenzie

executive
#82

Thanks. So we’re looking forward to giving you an update in early May when we report our Q1 results. In the meantime, please stay safe, and if you have any more questions, don’t hesitate to contact Daniel, Michael, or Claire. Thank you for your ongoing support, and have a good day.

Operator

operator
#83

That brings us to the end of today's conference call. We appreciate everyone joining us. You're free to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.