Capstone Copper Corp. (CS) Earnings Call Transcript & Summary

May 1, 2025

Toronto Stock Exchange CA Materials Metals and Mining earnings 58 min

Earnings Call Speaker Segments

Operator

operator
#1

Good afternoon, everyone, and thank you for joining us for our first-quarter 2025 results conference call. <<operator_script>> Today is Thursday, May 1, 2025, and this call is being recorded. At this point I'd like to hand the conference over to Daniel Sampieri. Please go ahead.

Daniel Sampieri

executive
#2

Thank you, operator. I want to extend a welcome to each of you on this Capstone Copper Q1 2025 conference call. We appreciate you being with us today. Just a note that the news release and regulatory filings that announce Capstone Copper’s 2025 first quarter financial and operational results can be found on our website and on SEDAR+. For those of you logged into the webcast, we’ll be advancing the slides for today’s presentation, and those are also accessible in the Investors section of our website. With me today are our CEO, John MacKenzie; our President and Chief Operating Officer, Cashel Meagher; our SVP and Chief Financial Officer, Raman Randhawa; and our SVP, Risk, ESG and General Counsel, Wendy King. Our Head of Chile, Jim Whittaker, and our Head of Technical Services, Peter Amelunxen, will also be around at the end of the call for questions. After our brief remarks, we’ll open things up for questions. Please be aware that comments made today on the call will contain forward-looking information within the meaning of applicable securities laws. By its nature, this information is subject to risks and uncertainties, and actual results may differ materially from the views expressed today. For more information on the risks and uncertainties pertaining to our business, please see Capstone’s most recent filings, which are available on our website at www.capstonecopper.com and on SEDAR+.

Daniel Sampieri

executive
#3

Before we go further, one quick note: every figure we mention today is denominated in U.S. dollars unless we say otherwise. At this point, I'm happy to hand things over to John MacKenzie.

John MacKenzie

executive
#4

Thanks, Daniel, and greetings to everyone joining us by phone from the Americas, Europe, Australia, and elsewhere across the world. It's a pleasure to share the results and accomplishments of our first quarter of 2025. During the last 3 years, Capstone has gone through a substantial period of transition, as we built and ramped up mines and put standardized processes and systems in place. At present, with worldwide economic uncertainty running high, we are well placed, since our ramp-ups are finished and we have no major expansionary projects in progress. So far, tariffs have not produced any material direct effect on our business. In today's market, we keep witnessing robust physical demand for copper, and we believe the copper market's medium- and long-term fundamentals stay highly attractive. The short-term uncertainty surrounding the global growth outlook, though, underscores why we remain focused on safety, operational execution, and keeping our financial position strong. Through the rest of this year, we look forward to showing dependable copper production, reduced costs, and greater cash flow generation, while we keep moving our production growth projects forward. Turning to Slide 5. In Q1, our operations achieved consolidated copper production of 53,800 tons, with consolidated C1 cash costs of $2.59 per pound, which matched our expectations given a quarter weighted heavily toward maintenance and an unplanned nationwide power outage in Chile.

John MacKenzie

executive
#5

During Q1, we kept seeing the advantages that come from the ramp-ups at Mantoverde and Mantos Blancos, with sulfide output reaching a record 46,000 tons. That marks a 50% rise versus Q1 of last year. It has been encouraging to watch both assets perform at or above what we expected once ramping up was done. Our teams, I know, are keen to keep showing what these mines can do over time, including at Mantoverde, where we are still working diligently to get ready to carry out our Mantoverde Optimized Project. At Pinto Valley, the difficulties we faced during the latter half of 2024 carried over into the start of Q1. Even so, our team put in serious effort to fix things by the middle of the quarter. We continue to concentrate on rolling out our asset integrity program so that operations stay stable and we reach the design throughput capacity. And at Cozamin, we delivered yet another consistent quarter, with solid production and low unit costs. On the corporate front, we are happy to report that we were added to the ASX 200 Index during the quarter, which reflects the ongoing success of our secondary listing in Australia since trading began last year. We also moved this quarter to strengthen and add flexibility to our balance sheet, finishing an upsized offering of $600 million in senior unsecured notes.

John MacKenzie

executive
#6

Our balance sheet is in great shape, and we're committed to reducing debt further using cash flows we generate internally. Now if we turn to Slide 6. This year marks an inflection point for Capstone, as our reiterated annual guidance confirms. For 2025, we continue to target copper production of 220,000 to 255,000 tons at cash costs of $2.20 to $2.50 per pound. Compared with 2024, that means significantly more production and lower cash costs. The chart on the right-hand side of the page shows our EBITDA sensitivity at various copper prices, based on the midpoint of our 2025 guidance, as well as the upside tied to MVO and Santo Domingo at run rate production. This level of EBITDA generation will let us focus on producing cash to delever our balance sheet, which will strengthen our financial position and gives us a strong platform to weather any macroeconomic volatility. And with that, I'll hand it over to Raman for our financial results.

Raman Randhawa

executive
#7

Thanks, John. Turning to Slide 7 now. During the first quarter, copper output came in at 53,800 tons, which reflected a record for sulfide production, helped along by rising output from the Mantoverde sulfide concentrator. Robust copper sales, combined with a realized copper price that was higher at $4.36 per pound, pushed quarterly revenue to a record $533 million. The LME copper price averaged $4.24 per pound during the quarter, a 2% gain from $4.17 in Q4. Although LME copper prices have been volatile recently, they are currently at a comparable level, slightly under $4.20 per pound. In Q1, we saw a meaningful premium arise for the U.S. COMEX benchmark price. A modest share of our output — PV Pinto Valley cathodes in the U.S. — gains from that premium, whereas the bulk of our copper production is priced off the LME. Cash cost for Q1 was $2.59 per pound, a 10% decline relative to Q1 2024. The drivers were the ramp-up of our Mantoverde sulfide operation, which delivers some of our lowest-cost production, and Mantos Blancos running at nameplate capacity, which brought sulfide cash costs down from $2.55 per pound in Q1 2024 to $2.23 per pound in Q1 2025.

Raman Randhawa

executive
#8

So in Q1, we achieved robust gross margins—$1.77 per pound, or 41%. Adjusted EBITDA for Q1 came in at $179.9 million, which is more than double what it was a year earlier, driven by stronger realized copper prices and greater copper output. And finally, adjusted net income attributable to shareholders was $8.1 million, or $0.01 per share, for Q1 2025. Now that Mantoverde and Mantos Blancos have been ramped up, we recorded depreciation of $120 million this quarter—a more suitable run-rate level than the $68 million booked in Q1 2024. At the same time, since we stopped capitalizing interest expense on the Mantoverde development project, we also recorded finance expenses of $37 million, versus just $10 million a year ago. Within that $37 million, roughly $15 million consists of recurring noncash items such as accretion of liabilities. Turning to Slide 8. A key topic this quarter was, naturally, tariffs and how they might affect different parts of the global economy. Although the situation keeps changing, we first want to emphasize that, to date, tariffs have had no effect on our revenue. At present, meanwhile, the expected direct effect on our consolidated operating cost is minimal.

Raman Randhawa

executive
#9

Pinto Valley is the sole U.S. operation we have. Following the review we carried out to assess how tariffs might affect us, we've laid out a breakdown of the cost drivers at that site. As you can see, a large share of our costs — things like labor, diesel, contractors and services, and power — aren't directly affected by tariffs. Some spare parts and grinding parts are examples of purchase categories that could be exposed. Our estimate is that the tariffs proposed and announced today might raise the cost of goods Pinto Valley buys in the U.S. by roughly 5%, or $0.10 to $0.15 per pound of PV, which reflects suppliers potentially passing through the tariffs they incur. Work is underway to assess alternative options for mitigating these possible impacts. On a consolidated basis, that would imply an impact of under 1%, or $0.02 per pound. We'll keep watching global inflationary effects, but as of now we see ourselves tracking within our 2025 cash cost guidance range. Turning to Slide 9. On the left side, we summarize the liquidity available to us, which as at March 31, 2025, was more than $1 billion, including $345 million of cash and short-term investments and $700 million of undrawn amounts under our corporate revolving credit facility.

Raman Randhawa

executive
#10

We closed the quarter with net debt of $788 million, up modestly from $742 million at year-end. The increase came from a $46 million working capital draw, mostly tied to an accounts receivable buildup, plus nonrecurring payments of $35 million for the final installment tied to the 2021 consolidation of the 100% interest in Santo Domingo de Cores and $10 million to buy back part of the royalty at Santo Domingo. In Q1, we kept seeing our net leverage come down, with a net debt-to-EBITDA ratio of 1.3x at the end of Q1 versus 1.5x at year-end. Turning to Slide 10. Near the end of March, we announced an upsized offering of $600 million of 6.75% senior unsecured notes due 2033. That was part of a debt refinancing transaction that met the goal of swapping our higher cost, amortizing and very restrictive Mantoverde project debt facility for a lower cost, longer-term senior unsecured note while also boosting our pro forma liquidity. The new high-yield bond closed on March 25. We expect the refinancing of the Mantoverde project finance facility to close in Q2. Consequently, at the end of Q1, we repaid our corporate revolving credit facility in full.

Raman Randhawa

executive
#11

During the second quarter, we anticipate refinancing the Mantoverde project facility, and we intend to repay our 70% share using cash along with a redraw under the RCF. At the same time, our partner MMC is expected to refinance its portion of that facility through a new loan at the asset level. Taken as a whole, this refinancing reduces our cost of debt capital and extends the maturity profile of our debt, resulting in a simplified structure. With that, I'll turn things over to Cashel for the operations review.

Cashel Meagher

executive
#12

Thanks, Ron. Moving to Slide 11, we'll begin by covering what's happening in Chile. Broadly speaking, it's encouraging to see the projects we recently brought up to speed performing as we had anticipated. Sadly, February brought a countrywide electricity failure across Chile, and that caused lost operating time at Mantoverde as well as Mantos Blancos. We're lucky the disruption lasted only about 2 days, and that's down to the dedication of our Chilean teams. On top of that, both assets underwent 5 days of scheduled maintenance in February, a month that is already brief. All told, that added up to roughly 7 days of disruption across both mines in the quarter, which accounts for the softer throughput in February. When operations were running, we were glad to observe Mantoverde and Mantos Blancos both delivering to plan, and we expect results to keep strengthening as this year unfolds. Beginning with Mantoverde, we saw steady gains in sulfide output and costs, helped by the ramp-up of the Mantoverde sulfide concentrator. Output reached a record 22,540 tons of copper, at C1 cash costs of $2.46 per payable pound, which includes a lower $1.53 per payable pound contribution from the sulfides. Plant throughput came in at an average above 31,000 tons per day for the quarter, and in January and March rates ran above nameplate capacity, partly offset by weaker rates in February, as I mentioned earlier.

Cashel Meagher

executive
#13

During the quarter, copper grades came in at an average of 0.71%, and sulfide copper recoveries kept climbing, averaging roughly 82.3% in Q1. As noted earlier, in February we carried out a planned 5-day shutdown that involved changing out liners on our mills, and beyond that we're continuing to make additional minor tweaks in the flotation area aimed at boosting recoveries. At present, we're concentrating on training operators so they can respond to varying ore characteristics as the material feeds through the mill. We believe we're beginning to hit our design recoveries during the second quarter. Q1 was anticipated to be the weakest quarter because of maintenance. Accordingly, we anticipate copper production and cash costs improving as the year progresses. As John said, our team is likewise keenly looking forward to the chance to carry out our Mantoverde Optimized Project. We're pushing detailed engineering forward and getting ready to launch the project as soon as we obtain a DIA permit amendment, which we expect around mid-year. Individual peak daily throughputs above 45,000 tons per day have been encouraging us thus far, and we're eager to debottleneck the plant so those rates can be achieved consistently. Our Mantos Blancos asset carried its momentum into 2025, as highlighted on Slide 12.

Cashel Meagher

executive
#14

Combined sulfide and cathode output came to 13,846 tons of copper, with C1 cash costs at $2.43 per payable pound. Both production and cash costs showed significant quarter-over-quarter gains, thanks to the successful 2024 ramp-up of the concentrator. At Mantos Blancos, we've held an average throughput of 20,000 tons per day since November—leaving out February because of maintenance and power outage effects. It's great to see that the overall variability of the milling process at this asset has come down significantly. We also gained from strong grades as 2025 began, averaging 0.89% in Q1. Pinto Valley turned out 10,886 tons of copper at an elevated C1 cash cost of $3.84 per payable pound in Q1, as Slide 13 shows. As we mentioned on our Q4 conference call, Pinto Valley hit setbacks in the latter half of 2024 that carried into the early part of Q1. Consequently, throughput averaged 50,000 tons per day in Q1, with unplanned downtime from electrical and mechanical issues that left 1 of our 6 ball mills down during the first half of the quarter. We managed to fix these problems mid-Q1 and closed the quarter with every mill running, averaging throughput above 53,000 tons per day in March.

Cashel Meagher

executive
#15

Our focus remains on executing the asset integrity program, which is designed to boost plant reliability and thereby support increased output and reduced expenses. We still anticipate that copper production will be weighted toward the latter half of the year, driven by grades and throughput, with a lower first quarter stemming from the maintenance mentioned earlier. Turning to Slide 14. Cozamin turned in another strong quarter, generating 6,524 tons of copper at C1 cash costs of $1.28 per payable pound. During Q1, Cozamin's cash costs gained from better contractor utilization, increased silver byproduct, a weaker Mexican peso, and reduced treatment charges, which remain a favorable factor for the rest of 2025. I'll now hand it to Wendy for the sustainability review.

Wendy King

executive
#16

Thanks, Cashel. Turning to Slide 15, we'll review how we've progressed on our sustainability priorities and targets as we begin 2025. During Q1, we signed a 35-year water agreement with Econssa, which secures long-term water supply through reusing treated wastewater from Antofagasta. That project will also cut marine discharge and boost water recycling, and it's expected to be operational in 2028. We keep refining how we approach sustainability, adopting a water stewardship policy aligned with the ICMM Water Stewardship Framework, along with a tailings leaching and waste rock management policy, which broadens the scope of Capstone's Tailing Management Framework. These policies are a key part of strengthening governance and accountability at all of our sites. This quarter, we kept moving forward on our sustainable development strategy goal of implementing the global industry standard for tailings management at all of our TSFs by year-end 2028. Against our internal forecast, we are tracking well. On climate, I'm especially pleased about the solar array installed at our Pinto Valley mine, which replaces some of our diesel generators with a renewable source of power. Also, at our Chile operations, 100% of our electricity use in 2024 was covered by renewable energy certified sources as defined by the International Renewable Energy Certificate standard.

Wendy King

executive
#17

This quarter gave us plenty of chances to engage with nearby communities and stakeholders—particularly at Mantoverde, Pinto Valley, and Santo Domingo. Those efforts line up with the social performance standard we recently put in place, which sets the rules for how the whole company works with communities. With that said, I'll turn things back over to John.

John MacKenzie

executive
#18

Thanks, Wendy. If you go to Slide 16, you'll see that what we're aiming for in the current year is to capture the value from the work we finished in 2024, with our attention on running operations well and making the balance sheet stronger. That gives us a solid base for carrying out the coming stages of organic growth when the timing is right for our company. On that slide we've laid out the growth plans where we lead the sector, along with some extra upside that sits in our portfolio. Growth priority number one is the Mantoverde Optimized Project — a superb project delivering high returns, fast payback and capital intensity as low as just $7,500 per ton. We intend to fund it from cash flows we generate internally. That's the kind of project we think we can and should carry out in just about any economic climate. Our plan is to move ahead with it once we receive a DIA permit amendment that was filed in mid-2024, and we still expect that around the middle of this year. At Santo Domingo, we're continuing to advance the work of assessing the best financing structure for the project, which includes running a process aimed at bringing in a minority partner at the asset level. The progress we've seen up to now has us very encouraged.

John MacKenzie

executive
#19

Outside of those projects, we have no shortage of options throughout our portfolio of projects that carry low risk and high returns. That covers a further brownfield expansion at Mantos Blancos, the flexibility within the MVSD district to unlock additional copper and possibly byproduct cobalt output, and the potential build-out of another major copper district surrounding our Pinto Valley mine in Arizona. Turning to Slide 17. We wanted to lay out the path forward for Santo Domingo regarding what must be seen before a possible sanctioning decision. With these criteria, our primary aim is to make sure we execute the project at a time that makes sense for Capstone, while preserving optionality and continuing to build the project's value. First, as I noted on the previous slide, we think a minority interest sell-down — potentially comparable to what we managed with our 30% partner in Mantoverde — is an appealing solution that balances the project's risks. We are running a process, and it keeps advancing well, with parties in Phase 2 of that process visiting the sites over the past few months. After this process has concluded, we will then seek to secure the optimal financing structure for the project, and we have already gotten early indications for a project finance facility of $1.1 billion to $1.3 billion.

John MacKenzie

executive
#20

Ahead of any sanctioning choice at Santo Domingo, our goal is making sure the balance sheet stands ready to back a fresh growth project. In practice, that means assets running at or close to full production, solid liquidity, and net debt-to-EBITDA leverage under 1x. During Q1 we moved the balance sheet forward nicely, and through 2025 our focus stays on making it stronger still. Criterion number four is making certain the project's scope is properly defined and optimized. This year we aim to reach a minimum of 40% detailed engineering, and meanwhile we keep progressing several options for optimizing key infrastructure and boosting project value through incremental upside opportunities, among them possible extra copper output from Sierra Norte plus oxide production. And, as noted on earlier conference calls, we remain highly attentive to the broader macroeconomic backdrop, which has drawn greater attention as of today. As we currently read it, that creates a possible sanctioning window for Santo Domingo beginning near the midpoint of 2026. For Capstone, Santo Domingo is a transformative opportunity that could lift output to roughly 400,000 tons of copper annually, at consolidated costs that are even lower and with a capital intensity that stacks up well across our industry.

John MacKenzie

executive
#21

So that brings us to Slide 18, where I'll wrap up today's presentation. During this quarter, the advantages of Capstone Copper's transformation first phase have started to show up, with concrete results delivered on growth that leads our peers. Because we concentrate on running operations well and keeping the balance sheet strong and flexible, we are ready for what lies ahead. Our position is very strong for becoming a top long-life, low-cost copper producer that plays a meaningful part in backing global decarbonization and electrification. With that said, we're ready to open the floor to questions.

Operator

operator
#22

Appreciate it. <<operator_script>> Orest Wowkodaw from Scotiabank has the first question.

Orest Wowkodaw

analyst
#23

Good afternoon, and thanks. Regarding Mantoverde, it's encouraging to see throughput hit nameplate in, I believe, 2 of the 3 months. But what about recoveries? You're running in the low-80s against a design of 87% to 91%. I understand that recoveries typically come last when it comes to debottlenecking and optimization. Still, what timeline do you see for getting to that design recovery on a sustainable basis?

John MacKenzie

executive
#24

Yes. Orest, thank you for raising that. It has clearly become our main priority now. We feel quite confident about the throughput rates. So, as you noted, the following stage involves dialing in the recoveries correctly. We expect to reach design recovery around the middle of this year. That said, maybe I could hand things over to Cashel so he can expand on that a bit.

Cashel Meagher

executive
#25

Yes, that’s a fair point, Orest. It aligns with what John mentioned — we think Q2 looks solid as we move closer to the recoveries. I’d also note that we’ve been processing transition ore, and maybe that came through more smoothly in the original model. As a result, we’re seeing a slightly larger oxide component, which is pulling that figure down, but we’re working through that material right now. So naturally, we think 82.3% may actually be somewhat higher when you consider it relative to sulfide — 100% sulfide-type ores versus a bit of blending in the upper benches at a few of our satellite pits. The team has said they’ve worked through that, and we’re continuing to educate our operators about the various ore types and reagent blends. We’re also still focused on our operational controls in the mill. So improvements are showing up. As John said, we expect to get there around the middle of this year.

Orest Wowkodaw

analyst
#26

Thanks. And as a quick follow-up, I believe John mentioned that you're now aiming for Santo Domingo FID possibly around mid-'26. If I've got that right, that's likely a pushback of 6 months versus what had been expected before. Given the uncertain — well, the copper backdrop and macro uncertainty — might there be more room to delay that? Have you considered simply shelving it for another year and just collecting free cash flow?

John MacKenzie

executive
#27

I think, Orest, the way we see it is that we don't want several projects going on simultaneously. So Mantoverde Optimized is our next one. The IRR — the returns on it — are incredibly strong. And the cash flow it delivers to us is tremendous. So essentially, we have everything lined up and waiting for it. All we need now is the permit, and we anticipate receiving it, as we've previously stated, around midyear. We expect the execution phase to take roughly somewhere between 9 months and 12 months. And as Cashel noted, we've actually already achieved some days of throughput at approximately 45,000 tons a day. So it's simply a matter of getting the equipment in place so we can sustain that level. So I'd feel quite uneasy about launching another project while our efforts are concentrated on ramping up one. Mantoverde Optimized is clearly a much smaller and much simpler project. That's why we're now indicating the sanctioning window will likely open around the middle of next year. But I've listed all the criteria we want to see in place, though that doesn't automatically mean we'll make the call to move ahead.

John MacKenzie

executive
#28

Nothing is pushing us to make a construction call right now. What we're saying is that everything will be in place — at this moment, the studies exist, the permits exist. Detailed engineering is moving along well, which in my view is essentially best practice when it comes to making sure we deliver on budget and on schedule. Lining up the financing, ensuring the project is optimized. I came across a study recently indicating that across major mining projects, firms typically leave roughly $0.5 billion of NPV unclaimed because they fail to properly optimize the project design. So, we intend to capture every penny from this. We're therefore doing a fair amount of work on whether it's infrastructure optimization or process flow optimization, simply making sure every aspect has been put through a rigorous review. And after all of that is complete, we're then at a point where at any moment, I'd be comfortable with the Board being approached to make a decision on that project. But other factors exist too. We have to consider the remainder of our portfolio, how much cash is being generated.

John MacKenzie

executive
#29

Are we at ease with how every one of our assets is doing, and clearly with the macro backdrop too? That said, it isn’t always true that tough periods are a poor moment for launching a project. At times those are the very best moments to begin and develop a project with the aim of actually carrying it through into the recovery. So we need to weigh all of those parameters carefully and then reach a decision that genuinely serves the best interests of the company and its shareholders. And as I mentioned, I believe that window will open midway through next year, though nothing obliges us to act at that stage.

Orest Wowkodaw

analyst
#30

I appreciate the additional detail.

Operator

operator
#31

The following question is from Dalton Baretto at Canaccord. You may proceed.

Dalton Baretto

analyst
#32

Appreciate you taking my questions. Perhaps I could pick up right where Orest left off on that same thread regarding timing. And I realize you just mentioned that nothing is really forcing your hand to make the sanction decision on that date. Do you have any view on which other projects may be moving forward and whether securing contractors and so forth could actually be a worry at that point?

John MacKenzie

executive
#33

Yes, that’s a good question, Dalton. And obviously that’s among the criteria we factor in when all is said and done — inside that region, the number of top-tier contractors, top-tier engineers, and so on is limited. I believe we’re quite lucky that a project team is already in place whose members brought many decades of experience with them before joining Mantoverde. At this point they’ve been working side by side as a team at Mantoverde for the last 3 years. And so we’re going to move over and do the very same thing at Santo Domingo. So I think our position is much stronger than most. We’ve already identified, more or less, the suppliers and contractors most likely to be involved in that project. And that gives us plenty of confidence. But clearly we do have to confirm what the wider environment looks like, what availability exists, and frankly, I think today’s economic volatility will probably increase further. In fact, I’d say Santo Domingo leads the pack on readiness for development in Chile. So we’re essentially set to pull the trigger, if not right now, only because we’re continuing with detailed engineering and a few government items we’d prefer to have settled before launching a project.

John MacKenzie

executive
#34

That said, I'd argue we're substantially further along than nearly every other project in that area. And my sense is that the macro volatility we're seeing right now will lead plenty of companies to more or less put their projects on hold. So I genuinely believe we'll probably be, as I mentioned, out in front of the group when it comes to getting hold of every resource required to build that project.

Dalton Baretto

analyst
#35

Great, thank you John. As my follow-up, I’ll remain on Santo Domingo and perhaps ask a question with two parts about the JV process. First, I believe in the past you’ve mentioned possibly a straight equity partner as opposed to an infrastructure sharing agreement. So I’m wondering whether there’s any reason both deals couldn’t be done. Then part B: as you move forward with this, how do you intend to factor the upside from Sierra Norte and the oxides and so on into pricing? Thank you.

John MacKenzie

executive
#36

Both of those are excellent questions, and yes, absolutely. Every option needs to be on the table. I think I touched briefly on our thinking around how to optimize the project. Part of that involves examining every element of infrastructure. If we can strike agreements to use infrastructure that already exists instead of constructing our own, that could potentially deliver a better economic and risk result for us than doing everything ourselves. That deserves a proper evaluation. Ideally, I would say you would normally aim for a single partner, but I have worked in plenty of JVs that involved multiple partners. It really comes down to having the right kind of shareholders' agreement, the right JV agreement, and the right JV governance so that everything runs very smoothly. So I honestly don't see any reason we couldn't combine both an equity-type partner and an infrastructure partner. All of those options are going to get looked at, I think. And as I've said before, I think, the process we're going through isn't a conventional sale process where you essentially run an auction, sell it, and then walk away.

John MacKenzie

executive
#37

Clearly, we're going to be working alongside our partners in this district for something like the next 30 years, 40 years, 50 years. So we really do need to think very carefully about how we structure that relationship and ensure it's something that works not merely this month but holds up over the coming multiple decades. On your question about how we build in that future value that's going to be created — we need to give that thought. Obviously, it's very hard to get the same amount of technical work lined up at one moment. Right now, we clearly have a technical report out there. That's our base case feasibility. We have several other opportunities that we believe carry very high probability, but they sit further back along the development — the technical development — curve. So that's work still to be done. And I think when we get into the final negotiations with a partner, that will form part of the conversation about how we think about value for those projects.

Dalton Baretto

analyst
#38

Perfect, thank you John. I'll rejoin the queue.

Operator

operator
#39

Ralph Profiti with Stifel has the next question. You can go ahead.

Ralph Profiti

analyst
#40

Thank you, operator, and good afternoon, everyone. I'd like to return to Mantoverde, which came in above design during January and March, and that actually featured a single day exceeding 45,000 tons per day. This raises a question for Cashel and John: is the underlying base actually above 32,000 tons a day? And might there be benefits to checking not just whether that base is higher, but whether it holds steady at a greater throughput before Mantoverde Optimized and then mid-2025? Perhaps this simply comes down to whether scaling up could be possible following MVO. Still, I'm curious whether there's any benefit to testing whether that rate — that steady rate — sits at an elevated level.

John MacKenzie

executive
#41

Thanks for that question, Ralph. I’ll have Cashel address it.

Cashel Meagher

executive
#42

Yes. Hi Ralph. Yes, I believe you've got the right idea. At present, the permit we hold essentially lets us average 32,000 tons per day, and we anticipate receiving that DIA modification around the middle of this year. And on paper, the new permit sets the throughput rate at an average of 45,000 tons a day. That said, we can peak as high as 55,000 tons a day. So it has been quite encouraging to watch how the crushing and grinding circuit performs, and also the capacity currently installed at our tailings, which now and then lets us reach the volumetric level needed to mill beyond 40,000 tons a day. So, although sustaining an average of 45,000 tons a day is going to take the $150 million in capital, half of that amount is in fact the mining fleet that delivers the ore. So that's one of the constraints we face. But it does give us a chance to beat the sort of guidance we issued. The midpoint would have implied 30,500 tons a day for this year. We are already running above that throughput guidance in our first quarter. And once that permit arrives, it would give us the chance to find out whether we can push higher, perhaps into the mid or high-30s.

Cashel Meagher

executive
#43

That said, we still have to see how it plays out, and having that available down the road is a strong option for us, plus a strong opportunity relative to the guidance we've stated.

Ralph Profiti

analyst
#44

Alright. Yes. That's great. Really useful. I'd also like to return to Mantos Blancos. Your presentation mentioned that milling variability has been cut considerably recently. I'm looking at the non-throughput KPIs, sort of benchmarking how things are performing there, and wondering if you can help me grasp whether those fall within spec — items like tons per day and mill availability.

Cashel Meagher

executive
#45

Yes, that's correct. Yep. My apologies, John. Correct — the response is affirmative. At Mantos Blancos, we're essentially achieving all of our targets. The team has performed remarkably well. And part of the credit for that goes to the asset integrity program and system we've been putting in place, along with how that management group has embraced it. So we're now applying the same approach at Pinto Valley. Pinto Valley is a larger and more complex mine. Still, Mantos Blancos demonstrates how an old asset can be turned around and made dependable, achieving the availability needed to reach the throughput design and hit those plant utilization and plant availability figures that we set out as our ambitions when this asset integrity program began. So we're extremely pleased with how it has been progressing.

Ralph Profiti

analyst
#46

That's great. Thanks. Those responses were quite useful.

Operator

operator
#47

Daniel Morgan of Barrenjoey has the next question. You may proceed.

Dan Morgan

analyst
#48

Hello John and Cashel. For my first question, I was wondering if you'd be open to giving us an update on April across the operations. April has now come to a close, of course, so I'd like to know whether you could share throughput figures for the various assets, and perhaps also recovery at Mantoverde.

John MacKenzie

executive
#49

Cashel, this one falls to you.

Cashel Meagher

executive
#50

Yeah. So where metal balances are concerned, recoveries can’t really provide those just yet, since we receive data every day — so we do get a sense of the direction they’re moving — but we don’t have our metal balances. That tends to be a lagging metric that arrives a week or 2 weeks into the following month. That said, I can say more or less that our Q1 performance has been repeated in April, and throughputs are reaching design capacities in the way we did in Q1 at Mantos Blancos and Mantoverde. And of course, nobody mentions Cozamin, but it’s steady as it goes and keeps performing as designed. The way I’d describe Pinto Valley is that we’ve had a couple of unplanned events again where we had a little — while we exited Q1 at 53,000 tons a day, we rolled back maybe to about 50,000 tons a day in April. So — but the plant is up and running again now. So, a bit of a stutter step there at Pinto Valley, but the other assets are performing as designed.

Dan Morgan

analyst
#51

Alright, thanks so much — that's really useful. One more question: I see that at Mantoverde, the guidance for cathode costs sits at $4.10 to $4.40 per pound. Clearly, with the global economy less certain and the copper outlook also more uncertain as things stand today, I'm curious about what would happen if you chose to potentially stop producing cathode. Is that the actual cost of cathode, or is it just worth noting that site costs, including sulfides obviously, are much lower and that overall you're generating cash at the site? I'm basically trying to figure out how you'd run the business in a lower copper price environment, should we see one. Thank you.

John MacKenzie

executive
#52

Yeah, that's a great question. And I'd say right now, the bulk of our cash flow is clearly going to come from the sulfides. We genuinely have the flexibility, if we decide to, to scale back oxide output should we conclude it won't earn a margin. Of course, Mantoverde's first quarter carried higher costs simply because we were working in some lower grade zones and we had maintenance work. But there's another risk mitigation step we took: our budgeting process told us Mantoverde cathodes would land in roughly that range we referenced. So we actually follow a broad general policy of not hedging copper, except when it clearly serves risk mitigation while a project is being built or when we have production that is very high cost. This year, that applied to Mantoverde's cathode. So we've hedged the large majority of that output using zero cost collars, I believe spanning $4.15 to $4.85 or $4.90. That way we've effectively secured the margin we're earning there and/or secured protection against losing money on that production.

John MacKenzie

executive
#53

And as we start to develop the sulfides, we're also discovering that we're unlocking somewhat more oxide, which opens up opportunity for us too. So that's something we keep a constant eye on. One of the constraints we face is that, more or less every year, we have to lock in our asset — our asset purchases, sulfuric acid purchases, that is. So once that's done, that's kind of — not fully, we don't lock in all of it. Roughly two-thirds gets locked in. But what it does mean is that's the volume of oxide production we've sort of committed to for the coming 12 months. But clearly, that's the biggest cost component in producing that copper. And so we can have a fairly solid sense of what it will cost us and therefore make sure we sort of shield ourselves on the downside, while keeping the upside for ourselves when it comes to opportunity for some extra margin. Raman, I don't know whether there's anything you'd like to add to that?

Raman Randhawa

executive
#54

No. Daniel, I think what you were really asking at first was whether that guidance range is on a sort of incremental basis. It’s sort of sharing the mining costs. So if you actually were to sort of shut off the oxide, that isn’t on a true incremental basis. So some mining costs get split between oxide and sulfide cash costs. And if you ran only the sulfide, you’d see that cost rise slightly. So on an incremental basis, the actual cash costs are probably a bit lower than the guidance, just on an allocation basis.

Dan Morgan

analyst
#55

Yes. Thanks. Precisely — what you both landed on is exactly the answer I was hoping for. I appreciate it.

Operator

operator
#56

Kate McCutcheon of Citi has the next question. The line is yours.

Kate McCutcheon

analyst
#57

Hello there, and good evening. Just a few quick questions for you. So the Cores payment came through this quarter, and you noted the Minto obligations for this year. Could you please identify any additional cash outflows expected across the year? And also, how do those Minto outflows look across the year, roughly?

John MacKenzie

executive
#58

Raman, would you like to handle that question?

Raman Randhawa

executive
#59

Yeah, I’d say Cores was a significant item, and there was also that ENAMI royalty we repurchased during this quarter. For the remainder of the year, we really don’t expect any other sizable one-time items. With Minto, I believe the near-term figure over the next 12 months comes to roughly USD17 million to USD18 million. So you split that across four quarters, right. That works out to something like $4 million or $5 million showing up. Beyond that, you shouldn’t anticipate any further one-offs.

Kate McCutcheon

analyst
#60

All right, great. And then regarding that MVO throughput opportunity you mentioned earlier during the call, before that CapEx gets spent, together with the permitting — I believe you're anticipating that around midyear. May is almost upon us. Could you share any update on the timing, or tell us where things stand with that process?

John MacKenzie

executive
#61

Yes, that is a solid question. And perhaps I will turn to Cashel just to speak — I believe we feel quite confident about it. But Cashel, would you like to just walk through roughly where we stand in that permitting process?

Cashel Meagher

executive
#62

Yes. So we've been through a few rounds of Q&A — I believe two exchanges with the administrative agencies that are handling the approvals. Typically, we were told that under the process, because we filed it around mid to late May, it was supposed to take 12 months. But we've been telling everyone June or July — the middle of the year — simply because things sometimes take longer than they should. So we're still expecting it. All our indications and communications with the various authorities point to it coming as expected in the middle of the year, and we've answered all their queries and questions. So we look forward to receiving it and then being able to utilize the installed capacity we have, along with the modifications and some of the metrics we see out of MVO, which is a terrific return on the capital we will employ.

Kate McCutcheon

analyst
#63

Alright, thanks.

Operator

operator
#64

The following question is from Goldman Sachs, and it's Emerson Verrier. You have the floor.

Emerson Verrier

analyst
#65

Good afternoon, and thanks for taking the question. I actually have two questions here. The first concerns Pinto Valley. If I do a quick back-of-the-envelope calculation, for that mine to hit the high end of guidance on Q1 cash costs, you'd need to be operating at the low end of the guided cost range during the quarters ahead. So I'd just like to get a sense of how we should think about Pinto Valley's Q1 cash cost relative to guidance. Is it more probable that we'll see that number land at the top end of guidance, and even then, taking into account the possible cost pressure coming from the tariff discussion? That's my first question. My second one is about cash flow generation. You just noted that net debt rose slightly on a quarter-over-quarter basis, and working capital was cited as one of the drivers. So I'd just like to understand whether that working capital dynamic ought to improve going forward. And then, given the production ramp-up and lower costs, we should at last see net debt coming down ahead. Thank you.

John MacKenzie

executive
#66

Thank you, Emerson. On that first question, I'd like Cashel to take it. For Pinto Valley, I think the reason we have confidence in the cost really comes down to a matter of grade and throughput, and I'll have Cashel speak to that. After that, I'll turn to Raman to answer regarding what we expect when it comes to reducing the working capital figure.

Cashel Meagher

executive
#67

Yes. So with Pinto Valley, it comes down to volume. Grade is one of the major variables, and also one of the chances we have to bring the cost per pound down. The grade we're mining in Q1 is the lowest we budgeted for any point this year, and from there it rises. Along with that, plus better throughput, we expect unit costs to decline and land inside the guidance range. So that's roughly what we've been indicating. I'm aware that when we issued guidance, we gave a single figure covering 12 months, yet the grade does follow a profile. We've also said that the incremental gains we make as the year progresses will lift throughput at Pinto Valley. Together, those two things will pull unit costs down.

Raman Randhawa

executive
#68

And regarding net debt, the largest swing this quarter—even though it rose somewhat—was those one-time items involving Cores and ENAMI. So excluding those, net debt stayed flat. Working capital then varies by quarter. Mantoverde sulfides are obviously new as far as sales go this year. There are a few different customers they're sold to, and some of them have what you'd call a longer sales leg. But I think what you'd see this quarter is us obviously receiving that buildup of receivables. So you should see that kind of ebb and flow, but it ought to swing back to positive this quarter.

Emerson Verrier

analyst
#69

Okay, thanks a lot, everyone.

Operator

operator
#70

Dalton Baretto with Canaccord has the next question in the queue — go right ahead.

Dalton Baretto

analyst
#71

Yes, and thanks for the follow-up. I’ll keep this brief. We saw Mitsubishi Materials sell their stake in another mine up in BC back to one of your peers, and I’m just wondering whether there’s an opportunity for you to buy back their stake in Mantoverde. Thank you.

John MacKenzie

executive
#72

Yes. Thanks, Dalton. Well, we hold a right of first offer to buy their stake if they ever decide to sell it. Mantoverde, I think, is a truly outstanding asset. So naturally, we would very much like to raise our shareholding to the highest level we possibly could. That said, I would note that MMC has been a genuinely excellent partner. And we really can't speak for them about whether they might have any plans to exit their stake. In my conversations with them, certainly, they say this asset is the most core one in their portfolio. They're extremely pleased with it. So I think the partnership has been truly excellent, and my suspicion is that it will carry on for a long time ahead.

Dalton Baretto

analyst
#73

Thanks a lot, John. Appreciate it.

Operator

operator
#74

That brings us to the end of the question-and-answer session. At this point, I'll hand things back to John MacKenzie. Go ahead, John.

John MacKenzie

executive
#75

Thanks, operator. Serving as Capstone Copper's Chief Executive Officer over these last 3 years has truly been an honor. After tomorrow's AGM, I'm looking forward to carrying on serving the company and all its stakeholders in my new role as Chair of the Board of Directors. Cashel is stepping into the CEO position at Capstone, and I have complete confidence that his experience and capabilities will guide our company through the coming phase of transformational growth. We're eager to bring you our Q2 results in late July. In the meantime, please stay safe, and don't hesitate to contact Daniel, Michael or Claire with any additional questions. Thank you for your ongoing support, and have a good day.

Operator

operator
#76

That brings us to the end of today’s conference call, everyone. We appreciate all of you taking part. You’re welcome to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Capstone Copper Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Capstone Copper Corp. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Capstone Copper Corp. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.