Cardinal Infrastructure Group Inc. (CDNL) Earnings Call Transcript & Summary

November 12, 2026

NASDAQ US Industrials Construction and Engineering earnings 31 min

Earnings Call Speaker Segments

Tiffany Gidley

executive
#1

Good morning, everyone, and welcome to Cardinal's Third Quarter 2026 Earnings Conference Call. With me today are Jeremy Spivey, our Chairman and Chief Executive Officer, Benji Wood, our Chief Operating Officer, and Mike Rowe, our Chief Financial Officer. Please see the earnings release and presentation issued this morning, which are available in the Investor Relations section of our website. This call will include certain non-GAAP financial measures. Definitions and reconciliations to the most comparable GAAP measures can be found in our earnings release. This call will also include forward-looking statements subject to risks and uncertainties that could cause actual results to differ materially. Additional information about these risks is available in our SEC filings. Cardinal undertakes no obligation to publicly update or revise any forward-looking statements, except as required by law; with that, I'll turn the call over to Jeremy.

Jeremy Spivey

executive
#2

Thanks, Tiffany, and good morning to everyone. This quarter our revenue rose 65% to $202 million, yet adjusted EBITDA margin for the third quarter dropped to 4.2%, far short of what we had expected. That decline mainly came from revised project estimates, pricing pressure in residential, lower initial bid margins on some commercial and industrial projects, and increased costs for fuel and transportation. Mike will walk through the detailed financial bridge, but let me be straightforward. These results are unacceptable, and they show plainly that we must get better at estimating, managing, and executing projects throughout Cardinal. As a second-generation operator with over 30 years of experience in this industry, I understand what strong project execution demands, and I know when our standards need to rise. So we are taking a number of actions to do exactly that. Our Chief Operating Officer, Benji Wood, is a fourth-generation operator with over 30 years of experience and a proven record of success leading ALGC. Benji will now play a more direct role in setting and implementing consistent operating standards across the Cardinal platform, with emphasis on project selection, estimating, project reviews, and accountability. We will also bring in an experienced independent third-party advisor to help implement these operational changes and to assess our estimating and project review processes. Separately, together with Hughes Brothers, we chose to postpone the proposed acquisition. We still see Hughes Brothers as a strong strategic fit, and our near-term focus is on strengthening the platform we already have, and we will revisit Hughes at the appropriate time. We believe the right priority today is to strengthen execution across our existing operations and to capture the benefits of the businesses we have already acquired. We also stay focused on capital allocation. With the balance sheet as strong as it is, our board of directors has authorized a share repurchase program of up to $50 million of our Class A common stock over the next 12 months. While our third quarter performance revealed areas where our execution and operating processes must improve, we have made meaningful progress this year in building a more diversified, vertically integrated platform; we expanded our self-performance capabilities, added complementary services in Atlanta, and brought an asphalt plant online in the Carolinas. Our strategy remains intact. Our immediate priority is strengthening execution and building the operating discipline and supporting infrastructure needed to turn growth into more consistent profitability. With that, I'll hand the call over to Benji to discuss the operational changes we're making.

Benji Wood

executive
#3

Thanks, Jeremy. What I'm focused on right away is taking the operating practices that proved successful at ALGC and applying them across the wider Cardinal platform. Our operating priorities involve better project selection, better project execution, and accountability; several actions have already been identified and are in motion. First, project selection and estimating are being tightened by applying more consistent standards for bid review, adding greater management oversight, and being more selective about project risk and expected returns. Second, project management and field execution are being strengthened through project reviews that happen more often and are more rigorous, standardized estimates to complete, and identifying and escalating changes in productivity, schedule, scope, and expected profitability at an earlier point. Third, operating accountability is being strengthened by applying consistent standards for estimating, reporting, and financial control across the platform. The purpose of these changes is to give us earlier visibility into how projects are performing and let us act sooner when a project departs from plan. We'll put them in place while we keep investing in our employees and safety programs, bringing more discipline and consistency across the Cardinal platform. With that, I'll hand the call to Mike.

Mike Rowe

executive
#4

Thanks, Benji. I'll quickly go over the financial results, the balance sheet, and the outlook. In the third quarter, revenue rose 65% to $202 million, up $80 million, and $24 million of that came from organic growth. Backlog came in at $816 million. The revenue growth and backlog showed demand stayed strong across the platform. Still, that growth didn't turn into acceptable profitability during the quarter: adjusted EBITDA was $9 million versus $21 million last year, and adjusted EBITDA margin fell to 4.2% from 17.5%. Gross profit for the third quarter was $11 million, which produced a gross margin of 5.4%, compared with 15.9% a year earlier. As Jeremy mentioned, on an adjusted EBITDA margin basis, project estimate revisions explained roughly 6.5 percentage points of the decline. Residential pricing pressure and lower initial bid margins on certain commercial and industrial work explained about 3.6 points, and higher fuel and transportation costs accounted for about 3.5 points. Other factors offset these impacts by roughly 0.3 points, which left a 13.3 percentage point decline in adjusted EBITDA margin. G&A rose to $15 million in the third quarter. That increase reflected acquired businesses, stock-based compensation, acquisition-related costs, and investment in personnel, systems, and infrastructure to support growth and the greater complexity of the organization. Net loss for the quarter was $11 million, versus $10 million of net income in the same period in 2025. On year-to-date results, revenue for the first nine months of 2026 grew 92%, or $286 million, to $596 million. Organic growth contributed $144 million, about half of the increase, and acquired businesses accounted for the rest. Gross margin was 11.5% versus 15.4% in the prior year period, mainly reflecting higher fuel and transportation costs, residential pricing pressure, and lower initial bid margins on certain commercial and industrial projects, along with project estimate revisions recorded in the third quarter. Net income for the first nine months was $12 million, compared with $26 million in the prior year period. Adjusted EBITDA rose to $63 million from $56 million last year, while adjusted EBITDA margin declined to 10.6% from 17.9%. We finished the quarter with $335 million in cash and cash equivalent and about $136 million of net cash, plus substantial additional borrowing capacity. Net cash provided by operating activities was $30 million for the first nine months of 2026, and capital expenditures were $42 million. Turning to our outlook: given how large the project estimate revisions recorded this quarter were and the work underway to strengthen project-level forecasting, we are withdrawing the full-year 2026 revenue and adjusted EBITDA margin guidance we previously issued. While we currently expect fourth-quarter adjusted EBITDA to improve from the third quarter, we are not providing a specific revenue or margin outlook. What we need to focus on first is getting the required project reviews finished, making our forecasting processes stronger, and building more confidence in when the work in our portfolio will land and how profitable it will be; having said that, I'll hand the call back over to Jeremy.

Jeremy Spivey

executive
#5

Thanks, Mike. There's a leadership change I'd like to tell you about as well. Mike Rowe is going to step down from his role as Chief Financial Officer, and he'll stay on at Cardinal to help make the transition a smooth one. Spencer Stuart has been brought in to run a thorough search for the person who will take over from him. I'd like to express my appreciation to Mike for what he has contributed to Cardinal and for his dedication to helping with the transition. Let me end on this note. Vertical integration, diversification across end markets, and acquisitions remain at the heart of our long-term strategy, backed by disciplined capital allocation. At this moment, our priorities are plain: sharpen execution, give projects greater visibility, and turn our growth into profitability that is more consistent. We recognize that credibility has to be earned through execution and through results that are demonstrated. Delivering those results is what our management team is concentrated on. With that, operator, please open the line for questions.

Keith Hughes

analyst
#6

Thanks; regarding that project estimate hit, the one that hurt margins most, could you say which regions were affected, or which regions took more of that negative impact during the quarter?

Jeremy Spivey

executive
#7

Hi Keith, good morning — Jeremy here. A small number of projects in the Carolinas were the main reason for those revisions. To be more specific, we saw a $13.2 million revision of cost estimates, and that represents roughly 6.5 points of the gross margin decline. Part of that involved some items connected to those revisions, with fuel and transportation costs running higher than in third quarter 2025. Within that, 61% of the estimate revision comes from 10 projects. Put even more simply, three projects made up 50% of the estimate revision. So it's a handful of projects, and the issue is confined to the Carolinas.

Keith Hughes

analyst
#8

Are those residential projects, or are they more commercial? Or how would you characterize them — especially the three that appear to be the most problematic here.

Jeremy Spivey

executive
#9

Yeah, the three were residential projects.

Keith Hughes

analyst
#10

Residential. All right. This is my last question. We discussed a few adjustments now that Benji has become involved in pricing. Could you walk us through, from a structural standpoint, how that operates? Do you run a quicker cost review compared with revenue, or in what way do the separate steps combine to make that occur?

Jeremy Spivey

executive
#11

Let me tell you, three areas have our attention: project selection and estimating, oversight at the project level, and accountability. Bid reviews are being tightened so that expected profitability, resource requirements, and execution risks get a better evaluation before we commit to new projects. We are stepping up how often and how rigorously project reviews happen, which lets us spot overruns or shifts in estimated profitability sooner than was possible in the past. The new ERP and the visibility it provides help with this, and at the same time we are realigning leadership in that area to back the resources, so that going forward there is clear ownership of project performance.

Keith Hughes

analyst
#12

Okay. Thank you.

Brian Brophy

analyst
#13

Yeah. Thanks. Good morning. Just to follow up on that conversation about projects with estimate revisions. Could you give us, I guess, a bit more color on when those projects are expected to be completed, or the cadence of those expected completion dates? Thanks.

Jeremy Spivey

executive
#14

Yeah. Most of these projects on the revision are over 75% complete projects, so they will be completed either this fiscal year or early Q1.

Brian Brophy

analyst
#15

Okay, that helps. So if we look at backlog for a moment, it declined on a sequential basis and book-to-bill came in below one. That seems like the first occurrence in quite some time. What's driving that, I suppose? Is residential the main factor, or is something else involved? Do you have any view on when backlog might start rising again? Thanks.

Jeremy Spivey

executive
#16

Yes. Thank you, Brian. For our business, Q3 has traditionally been a sluggish period for new awards, since most project owners prefer not to launch new projects during the winter months. Backlog rose 26% year-over-year, reaching $815.5 million. We're also being more selective about the new work we go after, especially in the Carolinas, where pricing competition has grown fiercer. Still, if we look at the historical annual pattern, Q3 tends to be slow for us, and we usually see activity improve in late Q4 and beginning in Q1.

Brian Brophy

analyst
#17

Thanks for that. I'll make sure to share it.

Louie DiPalma

analyst
#18

Jeremy, Benji, and Mike, good afternoon. Jeremy and Benji, the two of you have spent several decades in this industry. Is the problem that came up in the third quarter about execution, or did something suddenly happen across the spring and summer that altered the industry's economic structure? Is it tied to higher costs for labor or materials, or are Pulte, Lennar, and D.R. Horton, along with other customers, pricing contracts in a different way? Or is it because certain isolated projects are now carrying a negative gross margin, and things will get better once these troublesome projects are finished?

Jeremy Spivey

executive
#19

Yeah. Thank you, Louie. Good morning. I'll address part of that, and if Benji needs to jump in, he can. Execution definitely isn't the whole story, right? But any execution impact is unacceptable to us. Particularly in soft markets where margin compression exists in residential and elsewhere, we have to perform at a top level. When we talk about that, it's the only thing we know we control, and we're focused on fixing it and improving it. Fuel and transportation are causing a substantial amount of impact. Our visibility in Q2 and going into Q3 wasn't where it is now. We were transitioning ERP systems. We now have a lot of tools that let us see things we couldn't see before, where the impacts were coming from, how they were arriving, where they were, and we have that now; we're getting a tremendous amount. Many of these estimate adjustments relate to fuel and transportation going forward. It was impacted earlier, so we have to account for that. Going forward, on the remaining cost to complete, we have to account for that. We are getting. The residential market is soft. There's a significant amount of margin compression in the Carolinas, and I'll let Benji speak to Atlanta, but we're going to keep seeing that throughout 2027 unless things change with rates and there are some geopolitical resolutions. I'll let Benji talk about that.

Benji Wood

executive
#20

Yeah. Hey, Louie. I’m basically going to repeat what Jeremy said. It’s a bit of everything. There’s macro movement out there in the market that has kept going all year. Fuel has been a steady pressure increase that hasn’t eased. As everybody knows, fuel really works its way through the whole system. The visibility is going to help manage it going forward, and then just focusing in on project selection and setting ourselves up for winning jobs and then executing on the job as well is going to put us on a better path.

Louie DiPalma

analyst
#21

All right. When we talk about the soft residential market, does that take in the residential projects in the Atlanta region as well as the Carolinas? Is the weakness, at least as of now-

Benji Wood

executive
#22

Yes, I believe what you're seeing is a softer resi market across the wider Southeast region, correct? I don't believe it's specific to Carolina or Atlanta. I believe it's a wider macro shift. It isn't the worst market, it's simply a softening market.

Jeremy Spivey

executive
#23

Right. But, Louie, let me add one more thing to that: once interest rates hit in Q3, we saw softness speed up. It had been wavering through most of Q2, with hopes of a rebound if fuel prices and some other things moved our way, and that didn't happen, and rates went up, so the softness just accelerated, and we believe it has stabilized for the time being, though if rates keep rising, who knows what happens?

Louie DiPalma

analyst
#24

Great. So when you bid on these new projects and your costs come in higher, is the result simply that margins get squeezed, or do you still believe you can produce positive EBITDA on these residential market projects under the new conditions?

Jeremy Spivey

executive
#25

Yes, Louie, we can, and part of what we've done involves returning to basics and setting out the projects we bid on along with the margin we expect to earn from them. We lost sight of that somewhat, and some of the processes we're carrying out, with oversight of project estimating and operating processes, are meant to bring better consistency and visibility regarding the projects we were awarded and to ensure we have a floor on the projects we've agreed to execute for our clients.

Louie DiPalma

analyst
#26

Great, that helps. Thanks, all.

Brent Thielman

analyst
#27

Great, thank you. I suppose we should acknowledge that the bar is low given how the third quarter turned out, but near term, what supports the confidence that adjusted EBITDA will improve from one quarter to the next? Really, the question is which headwinds ease for you during the current quarter?

Jeremy Spivey

executive
#28

We believe the revision already reflects what we know to be true; we expect adjusted EBITDA to strengthen sequentially in Q4 versus Q3. What we are doing on operations and execution should only reinforce that. We remain firmly committed to it.

Brent Thielman

analyst
#29

All right. So I suppose this is a follow-up — Jeremy or Benji, I think — regarding the new business that was booked during the quarter, how do we become comfortable, and recognize that you're working through, or pretty much through, some of what we'll call legacy work? How do we become comfortable with the bid margins tied to what you picked up in the current quarter?

Jeremy Spivey

executive
#30

Sure. Brent, I believe the big issue on our side was visibility and having the ability to obtain real-time data that lets us make decisions on active projects so we can move through them efficiently and mitigate any downside risk along the way. That absence of visibility for a period had an impact, and we believe we now have the tools, through our new system, to head things off and get real-time feedback on the projects we currently have ongoing. Nothing has changed in how we conduct business. I mean, we must return to the basics, and we must lean on more structured data, now that it is available to us, so we can make decisions and mitigate any potential downside risk.

Brent Thielman

analyst
#31

All right. If there's room for one more, this one's specifically about ALGC — could you talk about how it has done relative to the mid-20s EBITDA margins the business posted back when it was acquired? Did it hit those thresholds, or did it not?

Jeremy Spivey

executive
#32

Yeah. I mean, look, ALGC has delivered in line with what we expected from them. Rising fuel and transportation costs have weighed on them. A softening market on both residential and C&I has also had an impact, but they are executing at a high level. We're actually taking some elements of ALGC's method for estimating, project reviews, and accountability and spreading them further. A third-party advisor will help us sharpen those processes, make them consistent, and roll them out throughout all of Cardinal. We also intend to rely on them as a framework when bringing future acquisitions on board. So we're gaining quite a few positives from ALGC; they're facing temporary headwinds, and once those clear, they'll return to operating the way they did before — and ideally surpass that, thanks to the integration model we bring.

Brent Thielman

analyst
#33

Thanks.

Kevin Gainey

analyst
#34

Morning, Jeremy, Mike, Benji. With all the changes you're making, I wanted to ask how you're handling the acquisition of Allied Paving this quarter — how has it gone so far, and how is that integration coming along?

Benji Wood

executive
#35

Hi, Kevin. Benji here. The Allied integration is going really well in Atlanta right now; we partnered with Allied for years, and plenty of familiarity and synergy is already coming through from that, so at a high level, things are moving along as planned.

Kevin Gainey

analyst
#36

On the backlog, I'd like to ask how much of that you expect to come through during the next 12 months. How are you thinking about what share of that work is still in this low margin piece, and what share of the new work would be better?

Mike Rowe

executive
#37

What we show in September for backlog is the 815. Of that, 640 was signed, and 175 was letter intents with issued contracts pending execution. For the current projects, the 12-month conversion estimate is scheduled, but we aren't giving any 2027 guidance on how we think that will fall into the backlog, will fall into 2027.

Kevin Gainey

analyst
#38

All right. And then last thing, if you have any further specifics regarding Hughes Brothers, and whatever expenses might come with that during Q4.

Jeremy Spivey

executive
#39

From Hughes, we don't anticipate any cost effect in Q4. That deal has been pushed back; we keep speaking with Hughes daily, or at least weekly; for us they're a priority, though clearly there are certain things we need to sort out on our side before they can be brought into the fold.

Kevin Gainey

analyst
#40

Great. Thanks for taking our questions.

Jeremy Spivey

executive
#41

Thank you.

Noah Levitz

analyst
#42

Thanks, guys. I wanted to ask: given that you're seeing softness in the residential market, and it sounds like that could last, you came in with a pretty healthy mix toward residential after IPO. Does that change your view at all on the resi versus C&I mix over the long term, pursuing more C&I?

Jeremy Spivey

executive
#43

Our priority is to keep focusing on diversification. We're prioritizing the work that we believe will give us the best opportunity with the best client. As we look toward 2027, and even as we finish Q4, we're focusing on the diversification process. We're building new relationships with a lot of the general contractors that carry these C&I projects. Naturally, given the state of the market right now, C&I is more abundant. I would expect, and we've seen it here in Q2 and Q3, and then in Q4 and probably in the next year, that our project, our end market mix leans more toward the C&I space for the foreseeable future.

Noah Levitz

analyst
#44

Got it. So since this was the first full quarter with the asphalt plant up and running, I just wanted to verify — did everything come in as expected on insourcing and the cost savings side? Thanks.

Jeremy Spivey

executive
#45

Yes, and I think we'll have more to say about it in quarters to come, since it only came online this quarter, but it's been a remarkable addition to what we run here, particularly for Aviator. I mean, the amount of asphalt they've put down from that plant is incredible. The models we're running have us really enthusiastic about what it will bring us, along with the payback and the long-term accretion to our operations. Yes, we're excited and there's more to come on that, but right now it's running at full plane.

Noah Levitz

analyst
#46

Great. So just one final quick question. Back in April, you picked up that big data center award. It's been a while since you've discussed it, but I'd like to follow up and hear how it's progressing, and what does the pipeline look like for those or other mission-critical kinds of opportunities for you folks? Thanks.

Jeremy Spivey

executive
#47

Clearly, that transport end market we're focused on offers a solid opportunity for us, and we're not just in Atlanta, but also in the Carolinas and a few other states where we're seeking opportunities. The one we have right now, we're still in phase one. A substantial revision was made to the phase one plan, and we had a change order that's either pending or executed at this point, but it represents a 50% increase over the original contract. The anticipated phase two, as I understand it, is to start or to be awarded and to start in March, April, so late Q1, early Q2 of next year. We're doing great. The customer's happy. We've built some good relationships, not only with that customer, but with some other trades who help support the work we do there, so hopefully we'll have opportunities with them on future projects in other markets.

Noah Levitz

analyst
#48

Great, thanks a lot.

Jeremy Spivey

executive
#49

Thank you. I appreciate everyone taking time out of your day. I'd like to briefly recognize our employees for all the hard work and commitment they keep showing. We're aware there's work ahead of us, and I have full confidence that our team can stay focused and put the needed changes in place. We've delivered quality, complex infrastructure projects for our clients throughout the Southeast, and we'll keep doing so. Thanks again, and I hope each of you has a wonderful day.

Operator

operator
#50

Alright, everyone, that brings today's conference call to a close. Thanks so much for joining us. You're free to disconnect now, and we hope you have a wonderful day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Cardinal Infrastructure Group Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Cardinal Infrastructure Group Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Cardinal Infrastructure Group Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.