Central Asia Metals plc (CAML) Earnings Call Transcript & Summary
March 29, 2022
Earnings Call Speaker Segments
Operator
operatorHello, and welcome to the Central Asia Metals presentation of our full-year results. I'll now pass things over to our CEO, Nigel Robinson. Over to you.
Nigel Robinson
executiveThanks, and good morning, everyone — 2021, the year ended 31 December 2021, was a record year for Central Asia Metals. If you flip through the slides — the usual disclaimer. Slide two shows where our operations sit. I believe most of you are aware we run assets in Kazakhstan and in North Macedonia. In Kazakhstan, we turn out pure cathode copper through an in-situ dump leach operation that includes an SXEW processing facility. Sasa is a more conventional underground mine for zinc and lead. A few of the highlights from this morning's announcement — as I said, we're delighted. These are record results for Central Asia Metals. During 2021 we brought in record revenue of $235.2 million, and the related EBITDA — that stands for earnings before interest, tax, depreciation, and amortization — came to $141.5 million, roughly $46 million higher than the prior year, which works out to a 60% margin. That carried through into the cash flow we produced: just under $104 million. That figure matters, since it forms the basis for the dividend we return to shareholders. For the full year of 2021, that dividend comes to GBP 0.20. This morning we're declaring a final dividend of GBP 0.12, and once you add the GBP 0.08 paid in Q4 last year, that totals GBP 0.20 — a yield of roughly 7%-8% against the current share price.
Nigel Robinson
executiveThat represents the largest annual dividend we've ever paid, reflecting those robust financial results, and Gavin Ferrar will walk through more specifics on that shortly. Turning to the balance sheet, it remains a strong one. We finished the year with net cash of $22.7 million. As everyone is aware, each year we've been repaying the debt taken on for the Sasa acquisition in late 2017. That debt now stands at $33 million, and by August of this year we expect it to be fully repaid. A handful of other points worth noting. Production was solid — very good output at Kounrad, slightly more than 14,000 tons. At Sasa, zinc and lead came in a bit under guidance owing to challenging ground conditions we encountered. Even so, we delivered 22,167 tons of zinc — pardon me — and 27,202 tons of lead. A performance to be proud of. Together with those favorable commodity prices, it made for a very strong financial showing. We're somewhat disappointed on LTIs. Four occurred at Sasa last year, none at Kounrad, and across this stretch we've recorded roughly five LTIs over the past three years. There are lessons to take from that. The final highlight, and a significant one, is our announcement of a 17% cut in greenhouse gas emissions.
Nigel Robinson
executiveWe'll have more on that shortly. Let me move us to slide four. What's our purpose? What do we do here at CAML? Our purpose is to generate base metals — metals that are essential to modern living — profitably and within a safe and sustainable environment for every one of our stakeholders. Not only shareholders, but all stakeholders. The three metals we're currently involved in — copper, zinc, and lead — each have a solid future given where the world is heading, both when it comes to decarbonization and, more simply, through the use of zinc in galvanizing products. Take lead itself, which is arguably the least sexy of our three metals — it's something that will still be used over the long term as electric vehicles take off, since lead acid batteries continue to play a crucial role in electric vehicles. That's our purpose. Now if you turn to slide five, you'll see a diagram showing how our purpose feeds into the way we deal with our stakeholders, how we manage risks within the business, how we manage our success as a management team, and also how it ties into the company's strategy — both the short-term strategy and the longer-term strategy.
Nigel Robinson
executiveOur short-term plan rests on three main pillars: putting sustainability first, aiming for low costs paired with high margins, and making sure capital gets allocated prudently. As we move through the presentation, we'll address every one of those elements of the short-term strategy. Clearly, the longer-term strategic aim is to expand the business beyond the two operations we run today, and we'll get to that too near the end of the presentation. Now a bit more on prioritizing sustainability. That's slide six. Moving quickly to slide seven and the five pillars underpinning our sustainability goals. Those are: creating value through stewardship, keeping health and safety strong, putting focus on our people, looking after the environments where we operate, and unlocking value for our community. Five key pillars, and tied to them are the UN Sustainable Development Goals — we now tick the boxes for, I believe, roughly five or six of those, as you can see, next to the pillars of our sustainability framework. Moving on to say a little more about each one, slide eight now. Health and safety performance. I noted already that, disappointingly, we recorded four LTIs last year.
Nigel Robinson
executiveWe've taken some lessons away from those incidents. The workforce has been retrained as a result, and we're eager for this year to bring improvements to how we operate on site. All of those occurred at Sasa. Over at Kounrad, it's now been more than 1,300 days since our most recent LTI, and that achievement in particular makes us very proud. COVID-19 is no longer a significant concern for us at the site. At Kounrad, almost 100% of the staff have had three vaccine doses. At Sasa, the figure is somewhat lower — 48% of employees are now fully vaccinated against COVID-19. As we speak, there are no COVID-19 cases on site. Our group LTIFR, the frequency rate of LTIs, stood at 1.69, and we've set ourselves a target of improving that by 15% on a rolling five-year average. Management's rewards are tied to their health and safety performance. Moving to slide nine, which covers caring for the environment. I'm delighted this morning to share a few specific targets in that area that we've been working on throughout the past year. Our climate change strategy has been developed. We're initially reporting towards TCFD when our sustainability report comes out later this year. Board approval for the Kounrad solar project. We also now have 100% renewable energy in North Macedonia.
Nigel Robinson
executiveGoing forward, the next steps involve examining scenario analysis for climate change during 2022, with reporting on that taking place in 2023; after that, we'll turn to our Scope 3 emissions and report those in 2024. To add a bit more to my earlier comment regarding the 17% reduction — that figure rests mainly on the renewable energy we've now secured, and we hold a contract for it in North Macedonia. Over a full year, this will work out to roughly a 35% cut in our greenhouse gas emissions. Down at the bottom of slide nine, in the water flow chart — or waterfall chart, I should say — you can see how we plan to reach the 50% reduction target we've set, measured against 2020 levels, by 2030. There's still some work left in a couple of areas, but for much of it we're confident that target can be met by 2030. A couple of other targets: water use matters greatly in mining, and we're committing to a 75% reduction in surface water abstraction by 2026, thanks to the work underway on site through the cut and fill project and the way we're staffing the processing facility there.
Nigel Robinson
executiveIn the same way, regarding tailings, once more, via the cut and fill project, we’re committing that 70% of tailings will be stored in a more environmentally friendly manner—dry stack tailings and paste backfill—from 2026 onward. Finally, and certainly not least, a few elements of environmental care that we’ve been working on during the past year. The river remediation is now finished following the TSF4 incident in September 2020. We’re doing some work on how we will retire the assets in 2034 and 2037 at Sasa and Kounrad. That is a long way off, I know, but as a responsible corporate citizen, we’re examining what work has to be done and how much money must be set aside in provisions on the balance sheet to actually look after the assets once we’ve stopped operating. Moving now to slide 10. We’ve placed a lot of focus and attention on taking care of the local communities, both at Sasa and at Kounrad. You can see the facts and figures there. We spent about half a million dollars last year, and money has been set up in those foundations that has been transferred from the operation into the foundation itself, which is a separate legal entity tasked with looking after various objectives and development plans for that local community.
Nigel Robinson
executiveYou can see a handful of examples of this at both Sasa and Kounrad. Moving on, the final slide I have here, on sustainability — slide 11 — looks at our people. Across the group we now have more than 1,000 employees, and we have devoted considerable effort to managing them well, along with the governance of the operations. Diversity is a central theme, and on site we have established committees to examine ways of making the workplace better for a more diverse workforce. The actions emerging from those committees are items we will be progressing during 2022. Following on from that, we will then set targets for female employees to be interviewed for eligible roles. Then, in 2025, at group level we are aiming for a 25% rise in female employees. Diversifying the workforce is something we are working hard at. I am also very pleased that this morning we announced Louise Wrathall will be joining the Central Asia Metals Board following the AGM on May the 26th. On training and development, we are directing effort into training our staff better. I think this may be an area where we have not placed sufficient focus previously, particularly at Sasa, and we intend to address it — through health and safety training, equipment training, and softer skills like management training and how people take responsibility for what they are tasked to do over the course of any working day.
Nigel Robinson
executiveActually, 99% of the people who work for us come from the nations where we operate, and that's a point of real pride for us. Finally — and this matters just as much as anything else — governance. For us, robust governance is a priority. Back in 2021, we put together a social assessment procedure, designed to support our suppliers and give us a stronger code of conduct, so we can be sure we're partnering with the right suppliers and that they're meeting the standards we're comfortable with. In 2021 we also built an online Governance and Stewardship program, and over the course of this year it will be rolled out to employees and suppliers. With that, I'll pass things to Gavin, who'll walk us through another of our strategic objectives — the push for low costs and high margins.
Gavin Ferrar
executiveThanks, Nigel. Now let's move to slide 13. It's clear that in 2021 we were working within a favorable macroeconomic setting — a mix of the COVID-19 pandemic itself, a certain amount of recovery from it, the stimulus programs tied to it, and vaccine rollouts all helping to bring about improvements in the economic climate. The push toward green economies gave support to metal prices, and combined with those stimuli I mentioned a moment ago, everything pushed the copper price upward: for us, the average copper price received rose by just over 50%, zinc prices went up over 30%, and lead prices increased just over 20% in terms of the prices we received. Looking at those charts on that slide, it's evident the gains were in fact even stronger during the second half of the year — which is encouraging as we look ahead too. Treatment charges — the costs we incur to convert the concentrates that Sasa produces into metal — gave us a 15% decrease year on year in 2021, and the outlook for 2022 also looks favorable for us on that front. Moving to page 14, we can see how that macroeconomic backdrop has really fed a lot of positives into the income statement.
Gavin Ferrar
executiveTo build on what Nigel mentioned before, we recorded revenue of $235.2 million, which is a 38% rise year-on-year, and that flows through the income statement to an 83% growth in profit before tax, reaching $109.3 million, along with EBITDA of $141.5 million — a 48% gain versus the prior period. EBITDA margins came in at 60%, also higher than 56%. Earnings per share, which as Nigel noted earlier feed into the dividend, nearly doubled to $0.4769 per share. Looking at the segmental analysis, Kounrad's revenue was certainly up, benefiting from those copper prices — revenue rose 50%, essentially tracking the copper price, while EBITDA climbed 62% year-on-year. At Sasa, we again saw a 25% revenue increase and a 36% EBITDA increase, from $42.3 million in 2020 to $57.5 million in 2021. Moving to page 15, you can see how that EBITDA has developed year-on-year. Once more, on the left-hand side, commodity prices performed very strongly, pushing up revenue from copper, lead and zinc. On treatment charges, we see the benefit I mentioned earlier. Then, on the other side of the equation, we're seeing some increases in our cost of sales, which I can discuss a little, plus royalties, which have risen as a consequence of those higher commodity prices.
Gavin Ferrar
executiveThere are significant hedge losses in there. We put hedges in place at the start of the year. We have no intention of hedging at all for 2022, but that's mainly because we ended up beating our own expectations at the close of 2020 when we made the decision to establish those hedges. Let me stay on cost of sales for a moment. What's flowing through there includes some unfavorable FX movements, the royalties I referred to earlier, and on top of that we're seeing inflation in consumables and reagents too. Let's go to page 16, if we could. Kounrad C1 copper cash cost, once again, sits right at the low end of the industry range, at $0.57 per pound, which is up from $0.51. As I mentioned earlier, you're able to see that reagent costs have risen somewhat. That came partly from higher costs of the reagents themselves, but also from greater reagent consumption. When we moved onto the Western dumps on their own during the winter of 2021, we wound up using somewhat more of what we call organic slicks and SK than we had anticipated. The metallurgists have grasped that issue and have now mitigated against it, so we don't anticipate that increase happening again. It has stabilized.
Gavin Ferrar
executiveSalaries and electricity — again, that's a theme we see right across the industry, honestly. Energy costs are rising, and on top of that there are salary increases, tied to those inflationary pressures. Kounrad still delivers an 80% EBITDA margin, which is a fantastic result, and as you'll remember, we also came in ahead of guidance from our production announcement. We turned out a bit more than 14,000 tons of copper there. Slide 17, Sasa. Here I wanted to flag a couple of things, because the picture gets a little murky once you convert from lead into zinc equivalents. Costs are up $0.13. If we break that $0.13 per pound increase down, $0.08 of it comes from relative lead and zinc price movements. We did run into some production issues, which we discussed at the production announcement, and those led to a $0.05 rise in unit costs. On cost inflation, again, we're seeing higher electricity costs, some reagent costs, and wages climbing there too in response to the sort of global pressures, $0.03 a pound. That's offset by those lower treatment charges at $0.03. Looking at the unit cost per production in the table itself, you can see $39.2 per ton in 2020, rising to $44.1 per ton run of mine at Sasa.
Gavin Ferrar
executiveAdverse currency swings account for 27% of that rise. On-site cost discipline was quite solid overall. You can see realization costs declining, and as for total dollar costs, we're up only $200,000 in overall dollar terms for the thing. Yes, that comes against a backdrop of somewhat lower production. Turning to CapEx on slide 18. Group CapEx landed at $14.7 million, just under the original guidance range of $15 million-$17 million. Obviously it will be higher than 2020, since we've incurred a great deal of spending on that cut and fill project. We've put $5.9 million against the cut and fill project, which Nigel will cover in more detail later. Just to flag that $4.3 million of prepayments have been made on CapEx. $2.4 million relates to that cut and fill project, $1.5 million at Sasa and $0.4 million at Kounrad. These mostly respond to anticipated cost increases, so we're laying down plenty of deposits on equipment items, and also pulling some of that CapEx forward into 2021 to guard against cost inflation in 2022.
Gavin Ferrar
executiveWhen it comes to the cut and fill project payments, there are three main elements involved. First is the Central Decline, which is currently underway. We've spent $3.6 million on it, and $2.4 million of that went toward equipment. Next is Capital Development at $1.2 million. Then the Paste Backfill plant, where $3.2 million has been spent so far. There's some detail in there — generally pumps, thickeners, and some of the pipes that we're going to put underground to move the paste backfill into the voids. Then there's the dry stack tailings, on which we've spent $1.5 million, and as Nigel mentioned, that's a key part of our ESG thrust as well. In future, we'll be converting from surface wet tailings into largely dry stack tailings. On sustaining CapEx, there are the usual items in there. Underground development and some new items of equipment at Sasa, and then the anode replacement program at Kounrad, plus dripper pipes. As you know, we feed those dripper pipes over the dumps. That was the large expenditure there, $1.2 million, because we also instituted what we call an intermediate leach solution process, which effectively recycles the solutions across the dumps. Moving on to slide 19. As Nigel mentioned earlier, the balance sheet is in really good shape now that we're net cash. Cash balance at the end of the year, $59.2 million.
Gavin Ferrar
executiveAs you can see, the assets have gone up, but depreciation has gone up as well, since we're now including the full allocation of TSF4 in there. Gross debt, as Nigel mentioned, is $33 million. Of that, $23.4 million is the Traxys corporate debt, which we expect to have paid off in early H2 this year. The remainder is overdraft facilities we hold with North Macedonia banks locally there. We did speed up the debt repayments through 2021. Normally we pay $38.4 million per year. We paid an extra $10 million, since we're in a decent cash position there to accelerate that debt service. Those of you with an eagle eye might spot that provisions on the balance sheet have increased, and that ties to what Nigel mentioned earlier regarding the asset retirement obligations. We've now completed updated and refreshed studies for Sasa. Regarding the closure plan there, that has raised that provision on the balance sheet. Last but not least, the cash flow statement on cash flow on page 20. Cash generated from operations, clearly benefiting from those commodity prices I mentioned earlier. Income tax $21.6 million, and CapEx of $14.7 million. Dividends of $38.9 million paid through the year.
Gavin Ferrar
executiveAs I said before, that repayment of borrowings brought the closing cash balance to $59.2 million. The key number is the $103.8 million of free cash flow we generated, which is defined as net operating cash flow less sustaining CapEx. We haven't actually included the current full CapEx in that calculation. The dividend Nigel announced earlier is about 45%, which is slightly up on all of our previous dividend payments within that policy. With that, I'll hand back to Nigel to talk you through the operations.
Nigel Robinson
executiveThanks, Gavin. Now a brief run through how operations went in 2021. If you go to slide 21, lots of you will no doubt have come across this image previously. It's the aerial shot of our open pit along with the dumps on the eastern and western sides. Our current estimate is that roughly 126,000 tons of recoverable copper are left, and as you can see it spread out there, the bulk now sits in the western dumps. Indeed, during last year, 85% of production came from the west and 15% from the east. Moving on to slide 22. This is another standard slide that we've relied on for many years. Up in the top right-hand corner you'll find our yearly copper output. Output has held fairly steady since 2016, giving us a six-year stretch at roughly the 30,500 ton level. During last year, as I mentioned earlier, 14,041 tons of copper came out, and for this year our guidance range is 12,500 to 13,500 tons. At the bottom there's the usual leach curve, and on every one of the cells we track, we're tracking those leach curves as expected. The leach period is naturally longer in the west than in the east, so roughly 400 to 500 days in the western dumps, where most of our activity is concentrated at present.
Nigel Robinson
executiveWe also see greater dump height and copper recovery averaging 35%-42% in the west. Every one of those elements has been incorporated into the 126,000 tons of recoverable copper I cited a moment ago. Moving on once more, the final slide concerns Kounrad. What stands out is simply how large the leaching operation is, as the table on the right-hand side makes clear. Over the years, as you can see, we have raised the figures — or the kilometers — of dripper pipes set up across the dumps. The average area being leached has grown, and so has the total material under leach, to the point that by last year, at any single time, 64 hectares were under leach. Roughly 37 of those were in the west and about 27 in the east, and we have installed slightly more than 7,300 km of this dripper pipe, laid down in order to irrigate the dumps. Those are just a handful of statistics. Output performance has been fairly standard, you know, and it is now optimized through 2034, which is the life of mine. Sasa is a very different kind of operation — an underground zinc and lead mine, yet a profitable one. We acquired it in November 2017. From that time through the end of last year, it has produced $245 million of EBITDA for us.
Nigel Robinson
executiveAs Gavin mentioned earlier, the debt we took on to buy that asset will be repaid this August. Reserves and resources extend through 2037. That was slide 24 — my mistake. Turning to slide 25, here are a few figures on last year's performance. As I noted earlier, it's fair to say Sasa had a rather tough year. We encountered difficult ground conditions at the 990 and 910 levels — the two areas where we operate — and that meant fewer headings were available, plus greater dilution from the blend of stoping and development work. That showed up in our production, which fell short of guidance and was somewhat disappointing. We've factored that into this year's guidance to account for some of those poor ground conditions. What I think it does is justify our shift to cut and fill mining over the coming years. Output last year came to 22,167 tons of zinc in concentrate and 27,202 tons of lead in concentrate. The table on the right-hand side gives you the head grade — somewhat lower for both head grades, zinc and lead alike — which carried through into the actual recoveries, which likewise came in a bit below what we had anticipated the previous year.
Nigel Robinson
executiveAt the bottom, you'll find our guidance for this year: 20,000 to 22,000 tons of zinc in concentrate and 27,000 to 29,000 tons of lead in concentrate. Ore mined will range from 790,000 to 810,000 tons. That gives you a quick rundown of operations. Turning to the final leg of our strategic objectives — our immediate strategic objectives — one of them was prudent capital allocation. Capital allocation has four aspects, and coming back to Sasa, that's a key part of it. What are we investing at Sasa to improve that mine and extend its life out to 2037 — both in terms of a safer mining operation, more environmentally friendly management of the waste itself, and a more efficient method of actually recovering the metal within the ore body? That particular project, the cut and fill project, has three components. There's the Central Decline, and the purpose of the Central Decline is to make far more efficient access to the ore body as we go below 910 level down to 830 level. It'll be used for the reticulation piping in the future. It'll give better ventilation. It will ultimately, depending on a cost-benefit analysis, maybe allow us to move over to electric vehicles to access the ore body.
Nigel Robinson
executiveThe tunnel is a bit bigger. Its dimensions are 4.5 by 4.5, so those electric vehicles will fit. As I mentioned, access to the main ore body becomes much more efficient going forward, and we cut down on transport kilometers when hauling ore back up to surface. That's one piece of it. Paste backfill formed the first component of the cut and fill Project, so the plan covers doing the paste backfill along with the piping, which is called reticulation. All of that was in our original plans from the start, and it's well advanced right now. Then there's the dry stack tailings side. Again, the plant — we've felt fairly comfortable about how it's going to be engineered for quite a while. The landform, I'd say, is something we've pushed ahead on considerably over the course of the past year, both in terms of working with the authorities on what they require, and in our own understanding of what's needed on the civil engineering side for managing water on it, its lining, and where we're actually going to put that dry stack tailings, which, again, wasn't specifically known at the outset. I think we've advanced that quite considerably over the course of the last year.
Nigel Robinson
executiveWork on the paste backfill and dry stack tailings plants is now going to wrap up in 2023. The Paste Backfill plant's construction will be finished in Q1 2023. After that, we'll move ahead with building the dry stack tailings plant, and during the course of 2023 both of those operations will be complete. As we've said all along, we'll begin transitioning into cut-and-fill mining starting next year at the 830 level. We're also announcing that on the cut and fill Project, beyond this year and into 2023, we estimate roughly another $10 million of CapEx. That figure is really a combination of sustaining CapEx on the process plant expansion, the dry stack tailings landform I just referred to — and we now have a better understanding of what's required there — plus the capitalized work in the Central Decline, this new decline we're building, which will offset some of the costs we would have incurred on the other capital development needed in the actual ore body. A bit more detail, slide 28, cut and fill Project. There are just a few diagrams there showing you what we're doing. As for the Paste Backfill plant itself, all the major plant components have now been ordered. All the civils and structural steels have been ordered.
Nigel Robinson
executiveWe’ve got a contractor in place. The thickener and flocculant plant have been ordered, along with the continuous mixer and the displacement pumps, and we’ve ordered most of the reticulation pipework needed to go into the actual voids and the mining itself. Completion of construction for the paste Backfill plant, as I said earlier, will be at the end of Q1 2023. We’ll move into commissioning in Q2 2023. On dry stack tailings, Knight Piésold has finished their design, and we’ve finished the plant design with Metso Outotec. We now have construction drawings for stacking the tailings, which will be in the old tailings facility, TSF 1 and 2, just outside where most of the buildings for the plant itself are. It’s quite a constricted area, but we now have detailed designs and plans for how we’re going to manage that. Up to about 4 million tons of tailings will be placed in that area over the coming years out to 2037. Just moving away from Sasa now and capital allocation on slide 29. Obviously something we’ve got a good track record on is dividends and also debt repayments now effectively. The dividends, we’ve already mentioned it, GBP 0.20 for 2021, a final dividend of GBP 0.12, and that’s 45% of the free cash flow.
Nigel Robinson
executiveSo that brings the cumulative dividends distributed since the company began paying them 10 years back, in 2012, to a fraction under $257 million, or £1.32. Deleveraging has come up already, and at the year-end our corporate debt facility balance stood at $23.4 million, and adding a $9 million overdraft gives total debt of $33 million at year-end, which should be cleared partway through this year. The final point concerns capital allocation — in many respects the toughest item to tackle and the greatest challenge for us as a management team — namely how we achieve growth. How do we take the success of Kounrad and the success achieved at Sasa and make certain the next opportunity we buy turns out to be a similar success? With the debt paydown period behind us, far more effort and energy is going into this. Debt capacity will be greater. Our cash balance will grow as dividends are paid in line with policy, but surplus cash will sit in treasury, and we will keep a strong share price so we can go out and locate that next opportunity.
Nigel Robinson
executiveLiquidity scale is still something we keep in mind. Obviously, the world has grown a bit more volatile. There's political risk out there, ESG risk. That said, I believe we have a robust platform to grow from. Our balance sheet is strong. The places where we intend to expand the business are those we already operate in. Copper would be ideal, though we're also open-minded about other metals that are essential for modern living. We'll be examining everything across the spectrum, from early stage exploration all the way through to production. That's quite a broad topic in many ways, but it's something we assess on a case-by-case basis, and we feel we now have a good window to make the next move. Last, though certainly not least, the outlook. I think we've shown that we do have a strong, sustainable business. What we do is produce metals that are essential for modern living, safely and sustainably. We just reported some excellent results for 2021, both in terms of EBITDA and free cash flow. That cash flow has been used to announce a record dividend for ourselves of GBP 0.20. We're in a net cash position at the year-end, and we are now looking for growth opportunities, as I've just mentioned.
Nigel Robinson
executiveLooking ahead, we anticipate a robust environment for metal prices—or perhaps I should say a strong metal price backdrop—for the remainder of this year. As everyone is aware, there's considerable macroeconomic uncertainty globally, and effectively we simply have to navigate around it. The world has undeniably grown more hazardous. We intend to pay down our corporate debt, and we're making progress on our climate change scenario analysis, and we'll wrap up with our ARO work at Kounrad. The work at Sasa is already complete. Those are the items we're focused on, and that represents the outlook for the Central Asia Metals business. With that said, I'll return the call to the operator and open the floor for any questions.
Operator
operatorThank you. Should you wish to pose a question over the phone, please indicate by hitting star one on your keypad. Kindly make sure your mute is switched off so that your signal can get through to our equipment. Once more, that's star one to ask a telephone question. Our first question today comes from Peter Mallin-Jones of Peel Hunt. Please go ahead.
Peter Mallin-Jones
analystGood morning, gentlemen. Congratulations on setting even more records across the board and on another dividend beat.
Nigel Robinson
executiveThanks, Peter.
Peter Mallin-Jones
analystCompared with what the street was expecting, for sure. If I may be so bold, I wanted to press you a bit on capital allocation. Clearly, as you know, the debt facility — the Sasa facility in particular — is going to wind down later this year. You already hold a fairly substantial cash position.
Nigel Robinson
executiveMm-hmm.
Peter Mallin-Jones
analystI'm curious how management—and potentially the board as well—is weighing things: how much of a cash cushion would you aim to build up so you can seize opportunities when they come along, versus distributing a larger share of the surplus cash you expect to generate?
Nigel Robinson
executiveMm-hmm.
Peter Mallin-Jones
analystAs time goes on. I'm just trying to get a read on where that balance stands right now and how it might change across the next year or two, just to get a feel for, you know, how quickly that cash pile could actually begin building up.
Nigel Robinson
executiveOkay, so perhaps I’ll take a first crack at that, and then pass things to Gavin for the CFO response. First of all, thank you, Peter, for the kind remarks. Yes, it’s a good problem to have, I’d say. As a board, I don’t believe we’ve formally settled this yet, and a strategy session is coming up, since we’re in the fortunate position of reducing the debt. My own view is that there’s really no necessity—and we’ve received feedback on this—to make a change to our dividend policy. The 30%-50% range, I think, provides some flexibility. It delivers a healthy dividend, as we saw this morning. The remainder, the other 50%, we intend to retain inside the business until it’s needed for an acquisition or some kind of acquisition, an asset, or M&A work. With a strengthening treasury, I certainly couldn’t tell you a cap—when would we say let’s pay back because we’ve reached the balance we want. I don’t think that’s the situation. I think we’re now in a window where we need to use that benefit and that platform to acquire the next asset.
Nigel Robinson
executiveHonestly, I don’t see us spending that additional cash that gets generated. Of course, that depends entirely on our cost discipline and on where commodity prices sit. Using it to go past the 50% payback isn’t something I see us doing, since I doubt that’s what investors would really want from us. To my mind, paying a solid dividend while also expanding the business is an appealing mix. We have to be candid with ourselves: right now the growth piece isn’t there, and we need that growth piece too. So the money has to be deployed sensibly. And while we deploy it sensibly — judging opportunities one at a time — we can also be very much on the front foot, in the sense that we won’t jeopardize the dividend. In that respect, we’ve safeguarded the dividend through the two operations by keeping them running. We’re able to pay a solid dividend and put the remainder really toward growing the business. That’s my perspective on it. Does that address your question, Peter? Does it?
Peter Mallin-Jones
analystYeah. No, I’m just trying to get a sense of how you’re weighing the buildup of cash against how much you’d be willing to pay out through a higher dividend, and then perhaps borrow more, because, you know, that cash wasn’t on the balance sheet at that specific moment when the transaction was being done. That was really just an attempt to get some color.
Nigel Robinson
executiveMm-hmm.
Peter Mallin-Jones
analystAppreciate it. Those were all the questions I had. Thanks.
Nigel Robinson
executiveThanks, Peter. Yeah.
Operator
operatorOur following question comes from Richard Hatch at Berenberg. Go right ahead.
Richard Hatch
analystYeah, thank you very much. Yeah, good morning, Nigel and team, and congratulations on a really strong set of numbers. I have a few questions. First, just on the timing of the cut and fill Project at Sasa.
Nigel Robinson
executiveYeah.
Richard Hatch
analystDo you now have every permit required to move that project forward, or is the permitting process still ongoing? I just recall you mentioned a couple of delays.
Nigel Robinson
executiveYeah.
Richard Hatch
analystRegarding the release, I just want to clarify that.
Nigel Robinson
executiveYeah.
Richard Hatch
analystHere’s where we stand on that.
Nigel Robinson
executiveNo, no — Richard, the response there is no, we haven't done so as of now. I believe we understand exactly what is required, and we understand the route to obtaining those things. The item that is the linchpin for the whole effort is the environmental and social impact assessment. We have at this point a clear path forward agreed with the ministry regarding how we will carry that out and deliver it. It's fair to say that has caused a delay of three months. Where we had ideally been aiming to hold public hearings and complete everything else required by the end of April, May, that will probably now look like July, August timing, which is what we're currently planning for. We have a certain commitment from the ministry that they will work very closely alongside us to help us deliver on that. They are conscious that time is money and that we need to get on with this. That is effectively a three-month delay. Everything then follows from that. A lot of the other permits we require, such as a construction permit, come from local authorities, and we have a good relationship with the local authorities to get that done in a very, you know, very quick fashion, effectively. The plan now is to obtain the EIA, as I say, which'll be July time, end of July time, and then we'll carry out as much preparation work on site as we can before going into getting the constructor to start pouring concrete and getting the building up and running before, you know, say, winter sets in December.
Nigel Robinson
executiveWe have a fairly clear view on how we'll do that and how we move the permitting forward to achieve that. So you then get construction completion at the end of Q1 next year, and then a commissioning period, and then we're into cut and fill mining. The key one from the profile that we've got for transitioning over to cut and fill mining is the Paste Backfill plant, and therefore the dry stack tailings plant is less important in some ways 'cause we plan to do that in next year, but it has no impact on the transition over to cut and fill because we've got the flexibility of where we place our waste, which is either TSF4, the dry stack eventually from the end of 2023 or Paste Backfill. I think we have a clear idea what we need, and it has caused a three-month delay in terms of the understanding in country, and to be fair, our own understanding of what was required on how to do the dry stack tailings in many ways. The whole EIA covers both paste backfill and dry stack tailings, and it's never been done before in North Macedonia.
Nigel Robinson
executiveSo because of that, the ministry and us have gone back and forth a good deal, with plenty of working meetings just to grasp the issue and reach agreement, and to land on a compromise about how we actually run that facility. What we put forward initially versus what they had in mind — and we've now arrived at that compromise regarding this geosynthetic clay liner that will line the dry stack tailings, and it's been designed, and that has led to a slight delay. At least at this point we have clarity on what's required.
Richard Hatch
analystOkay, thanks, Nigel. If the EIA doesn’t come through by July, does that mean we could be looking at more delays — or am I misreading that?
Nigel Robinson
executiveRichard, you’re being very pessimistic.
Richard Hatch
analystAs far as that goes.
Nigel Robinson
executiveI mean, obviously we are.
Richard Hatch
analystNo, I wouldn't say that — I'm an optimist. But my analysis runs too long. I'm just focused on the critical path.
Nigel Robinson
executiveRight. That has been the critical path from the start, and it still is. Even a delay of three months is never a good thing, is it? Let's be honest about it. But in my role as CEO, I'm fairly pleased, since we now enjoy solid working relationships and we have a clear direction, which leaves me feeling more confident today. It could turn out to be four months. Obviously I can't guarantee that, because it depends on the ministry, and at times they are a law unto themselves. You know, we now have a clear path toward what is actually required for the dry stack tailings, and that gives me greater confidence in the timelines I'm discussing with you.
Richard Hatch
analystOkay, got it. Thanks. Regarding Sasa, could you update us on how the mine has been performing so far this year, specifically with respect to ground conditions? I know that's something you've had to contend with over the past year, but it does look like you've been taking a proactive approach to managing it. I'd be interested to hear where things stand quarter to date. Are you at least able to make progress on some of the difficulties that created headwinds last year?
Nigel Robinson
executiveYeah, I really do think Scott is performing well. There’s a solid team at the site. In my view, they are handling things effectively. In the guidance we provided this year, I believe you’ll see it simply reflects that there is additional development work. With these difficult ground conditions—where you have, you know, collapsing ground and so on—and we have to carry out more development and more ceiling reinforcement, so to speak, we have permitted and included that in this year’s guidance. So at this point we know what is needed. We are making good progress in the first quarter. I mean, clearly I am not reporting Q1 results, but we are advancing well toward meeting our production guidance, you know, for Q1 of this year. I am confident that we have, you know, the skills at the site and the people at the site, the geotechnical engineers now, to handle that. Yeah. As I mentioned earlier, I think it justifies that starting next year we will begin transitioning to cut and fill. The issues we have run into, you know, we will mitigate, because cut-and-fill will let us do that by supporting the ground instead of letting it cave, which creates a few problems for us as we go deeper in the mine.
Nigel Robinson
executiveYeah, I believe we're handling that pretty effectively.
Richard Hatch
analystOkay, got it. Thanks. The final question relates to costs and CapEx. Gavin, I appreciate that you touched somewhat on inflation. What options do you have available to counter inflation at the mine? Could you provide any sort of guidance regarding what we ought to be factoring in, on an absolute basis where costs are concerned, for our 2022 numbers? And regarding that, the modest adjustment to the Sasa schedule — what sort of steer are you able to give us on CapEx for 2023?
Gavin Ferrar
executiveRichard, that's quite a few questions packed in there. So, on the inflation side—yeah, like I mentioned before, we are seeing pressure when it comes to reagent costs. Take copper sulfate, for instance: we use some of that at the plant, and copper prices have climbed. We also use steel in the mills, and everyone is aware steel prices have risen. The big one, though, is really energy. That's the hard one to call, especially given the geopolitical situation. At Sasa we have a price locked in through midyear, and we've already begun renegotiating it. As you're aware, it's entirely renewables now too, and that gives us an advantage in those talks. On wage inflation, it generally tracks inflation in the country. We're budgeting roughly 8%-10% in Kazakhstan and 4%-5% in North Macedonia. Turning to CapEx—well, I believe it's on the slide here. For 2022, we're looking at $28 million-$30 million, and about 11 to 13 of that is sustaining. The remainder is the cut and fill project. For 2023, we aren't providing guidance on those numbers yet. But I think we should have largely finished all of the cut and fill spending this year and next year.
Gavin Ferrar
executiveThat'll be our guide on that.
Richard Hatch
analystOkay, thanks a lot. That's appreciated.
Gavin Ferrar
executiveI believe the point is that the year referenced is the moment when.
Richard Hatch
analystYes. Everything's fine. My apologies.
Gavin Ferrar
executiveApologies. What we originally guided to was $18 million to $19 million for capital on the cut and fill Project. What's pretty clear, I think, is that at that point we didn't yet know precisely how we would go about drying and stacking the tailings landform — that's fair to say. We now have a better handle on it, so we'll be working through those costs, including how much the liner will cost and the dry stack tailings landform, and those will be incurred next year. That accounts for the modest increase we have next year. On top of that, there are all the capital development costs we're incurring on the Central Decline. In many respects, a good deal of that offsets what you'd have spent on sustaining capital at any mine. In any given year, we'd announce sustaining CapEx at Sasa of, say, $10 million to $12 million. Well, roughly $3 million or $4 million of that in any single year would be capital development costs. That gets offset and superseded by what we're going to spend on the Central Decline as it becomes the main access into the ore body.
Richard Hatch
analystYeah. That's great. Everything's fine. Congratulations once more, and nice work on that tremendous dividend. Many thanks.
Gavin Ferrar
executiveAlright. Thank you, Richard.
Operator
operatorOur following question comes from Alexander Pearce at BMO. The line is yours.
Alexander Pearce
analystGreat. Morning, everyone. I'll stay with Sasa there, and on costs obviously — could you give us a bit more detail on how your power costs have moved year to date, and how you expect that to change going forward? Have you seen any impacts from power costs on your customers as well?
Nigel Robinson
executiveOn the power costs side, Alex, I'd say we have definitely experienced increases. So, in 2020 we paid $0.064 per kWh, and by 2021 those went up to $0.104 per kWh. That is a pretty big jump. And that rise comes off a really low base, too. We essentially rebased the negotiation period. Rather than negotiate in the middle of winter, when costs run high, we shifted it to roughly the spring/summer period, when costs are a bit lower. That's basically what drives that increase. I can't say what it will be next year. As I mentioned, we're in the middle of negotiations, but there is clearly pressure on those prices. As for how this affects our customers, that's a fair question. We've seen some zinc smelters in Europe especially shut down in reaction to higher energy prices. Both of our European customers on the zinc side are quite robust and keep taking material with no problems at all, and they pay on time. We have no concerns about them. Then the third customer, on the lead side, again, that's a customer with a very strong balance sheet.
Nigel Robinson
executiveFrom them, we anticipate zero problems whatsoever. On that front, there’s nothing to worry about.
Alexander Pearce
analystAll right, that's excellent. I appreciate it.
Operator
operatorJust a quick reminder — if you'd like to ask something over the phone, hit star one to signal us. Our next question comes from Oliver O'Donnell at VSA Capital. Go ahead, please.
Oliver O'Donnell
analystGood morning, Nigel and Gavin. Thank you both for the presentation. I have two questions, if I may. First, could you provide any insight into treatment charges? They have been rather volatile throughout the year and appear to be returning to where they stood around this time last year, and I wonder whether that is affecting your negotiations at all. Second, at Kounrad, the notes mention some discussion of opening up a scenario involving about 2,000 tons of copper-
Nigel Robinson
executiveUh-huh.
Oliver O'Donnell
analystWe're returning to older zones where leaching has already occurred.
Nigel Robinson
executiveYeah.
Oliver O'Donnell
analystWithin that 126,000 ton number, are they getting better recoveries, or is there a somewhat different figure we ought to consider over the long run? Thank you.
Nigel Robinson
executiveI'll take the second part of the question, and if you don't mind, Oliver, I'll let Gavin handle the treatment charges. On Kounrad, we're simply attempting to be innovative there, Oliver. What those 2,000 tons means is, if you checked your pack and looked at the aerial-view slides of Kounrad — I'm just trying to locate quickly which slide that is. It's slide 21. There's a zone labeled nine to 10 on the eastern dumps, and the railway line running past Mynaral in that area constrained it fairly significantly. We're relocating some ore and placing it onto nine to 10. Simply by moving it and blending it, we can then leach that area and obtain additional material at a fairly low cost, honestly. Moving the ore itself, I believe, costs roughly $300,000. Clearly, given the current copper price and the costs we face, it appears a sensible move. In the same way, we've done this on certain slopes. On some of the dumps, we've shifted a few of the slopes to see whether recoveries can be improved.
Nigel Robinson
executiveIn terms of what the authorities require and what we report to them, that's how we've always operated. What we manage to internally is somewhere between, like, 45%, I think, and 50%, 52% in the eastern dumps. In some of the areas where we've been leaching for nearly 10 years now with this rest and rinse — that's what we'd call it — we're seeing slightly higher recoveries beyond that level. You know, it can get a bit. You know, we shouldn't read too much into it, as Nick would always say — we're not cutting cheese here or whatever he used to say, something along those lines. It's not an exact science. What we try and do is just be creative and see can we leach for a bit longer on a dump that may have reached 50% recovery, but we might squeeze out 52%, 53% without, you know, minimal incremental cost to do that. Certainly no CapEx costs generally, apart from, you know, the incremental cost that we might incur. We look at that on a case-by-case basis. It doesn't mean that the eastern dumps are gonna generate another 100,000 tons of copper or anything like that.
Nigel Robinson
executiveThere are only slight gains to be had from the copper we have already recovered. We'll go ahead with that, as, you know, so it states on that slide, eastern dumps, 8,000 tons. We might get 12,000 tons back since we're being creative, but it would be around that magnitude, Ollie, honestly. We'll take the same approach once we move across to the western dumps. Right now, we have a plan. We stick to that plan. Wherever we're able to extract a little extra copper, we'll simply try to examine it and see whether we can shift some of the ore and attempt to leach it a bit further. We gave that a go in another area, and it didn't succeed. It isn't always a success, but given the cost involved, it's worth attempting.
Oliver O'Donnell
analystThanks a lot — that’s helpful.
Nigel Robinson
executiveRegarding treatment charges, Ollie, the contract windows we operate on run each year from April 1 through March 31. As it stands, we have already secured our treatment charges for the stretch starting April 1, 2022 and running through March 2023. Honestly, we foresee no volatility in the pricing of our treatment charges before that point arrives. Now, you've observed spot treatment charges reacting to a wide range of factors out there. There has definitely been an uptick in China, particularly on the zinc side of things. Again, I don't believe that touches us, since all of our zinc material has been allocated. During earlier years, we held some material back and directed it toward the spot market for lead concentrates. Once more, on lead we are fully allocated through the end of March 2023. We anticipate no volatility in that area. I mentioned a 15% decrease year-on-year in treatment charges from 2020 to 2021, and I was describing a favorable sort of 2022. That suggests, I suppose, that the terms being secured in this round are superior to what we had before. Our expectation is that this holds at least all the way to the end of March 2023.
Oliver O'Donnell
analystThat’s great. Thank you so much.
Operator
operatorJust a quick reminder—hit star one if you'd like to get in the queue. Right now, no additional phone questions have come in, so I'll turn things back over to our host for any extra comments or closing remarks.
Nigel Robinson
executiveAll right. Well, if nothing else is coming in, I really appreciate everyone taking the time today. As I mentioned, we're very pleased to be reporting these results this morning. Financially, it was a strong year for us, and we're looking forward to more in the year ahead, and to keeping everyone updated on our progress with the cut and fill projects as well as our business development efforts, as we work to grow the company in what is a fairly volatile world we're all living in right now. Thank you all for your time. We'll stay in touch.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Central Asia Metals plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Central Asia Metals plc earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Central Asia Metals plc or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.