Good morning, everyone, and thanks for joining the Champion Iron first-quarter 2024 results conference call. Right now every line is muted for listening only. After the presentation, there will be a question-and-answer session. <<operator_script>> At this point I'll hand the conference over to Michael Marcotte. Michael, the floor is yours.

Michael Marcotte

executive
#2

Thanks, operator, and thanks to all of you for being on this call about our Q1 results for fiscal 2024. We're sorry we got started a bit late — we ran into a small technical problem. Before we begin, I'd like to point everyone to our website, championiron.com, where the presentation we'll be going through today is available. We'll also be making forward-looking statements during this call. You can review your MD&A for details on those forward-looking statements as well as the risks and assessments, which are also posted on our site. Now, unless we say otherwise, every figure discussed on this call is in Canadian dollars. With me today is our CEO, David Cataford, who will handle the formal presentation for the webcast. After that, we'll open things up for Q&A at the end. Also here with us are Alexandre Belleau, our COO, and Donald Tremblay, our CFO. I'll now hand things over to David for the formal portion. Thank you, David.

David Cataford

executive
#3

Hello, everyone. Many thanks for your patience during that lengthy five-minute wait ahead of the call starting. I'm very glad to share the results for the quarter we just completed. As you've likely seen, it was something of a mixed quarter, though I believe we performed well, and I'm extremely proud of the teams for having steered us through these forest fires. What we faced, in fact, was among the biggest forest fires of the last 100 years, both in Quebec and across Canada. Even so, I'd say the results remain fairly positive given what occurred. We'll get into more detail on the forest fire factors shortly. Still, I think that, looking at the quarter, the standout item is clearly the 3.4 million tons we produced, which reached above 90% of nameplate capacity at Bloom Lake. The ramp-up, then, is proceeding as planned. We'll talk about costs as well, but they were trending lower once you set aside the volatility from logistics problems during the quarter. And I'm very pleased with how the teams handled all of this. Turning to the financial results, they were clearly affected by our inability to ship out every ton produced, but those tons sit stockpiled at the site, and we'll be able to follow the plan to bring them to market.

David Cataford

executive
#4

Looking at the environment, I'm very proud to report that once more we had a quarter free of any major environmental issues. Since Bloom Lake was re-commissioned back in 2018, we've done an excellent job of keeping the environment safe, and we've invested significant CapEx over recent years to ensure we can keep operating that way safely for decades ahead. On the community side, I'm also very happy — as you've likely seen in previous quarters, we've announced that we work very closely with our local communities and with First Nations, but recognition from our peers is always good. The Mining Association of Quebec and the Federation of Quebec Chambers of Commerce both named us the best company working with local communities this year, so we're very proud of that. And that won't just help us keep operating — it will also help us a great deal when we consider potential growth initiatives. Because as you know, these days it's very important for companies, especially mining companies, to work with their local communities. Turning to the industry: in the past quarter, you probably saw the iron ore price dip a little, roughly an 11% decrease for P-62 and P-65.

David Cataford

executive
#5

We also observed sea freight rising roughly 16% in the quarter, since volumes out of Brazil picked up after seasonal factors affected production — but freight rates remain well below last year's peak. So we're still in a range that supports substantial margins on our material, and as we ramp toward nameplate capacity and reduce tons from Bloom Lake, we expect to capture the full high-grade premium for our product. On forest fires: as noted on the highlights page, major fires in Quebec affected production — though the impact was somewhat smaller. The fire stayed fairly distant from the mine, but for a period it prevented us from hauling explosives and fuel. Naturally, those are the first items cut off from roads when fires threaten nearby routes. That forced us to make choices about how we ran the mine so we could conserve fuel and avoid halting production, though it did create minor disruptions at site that slightly affected our output.

David Cataford

executive
#6

We're still pleased with the 3.4 million tons we produced, though things could have gone somewhat better had the forest fires not affected us. Looking at where the real effect came from, it was mainly tied to logistics. So the QNS&L, the rail line that IOC runs, was down for a period and then operated more slowly as it ramped back up and rebuilt the infrastructure the forest fires had destroyed. The track itself wasn't affected, but communication systems in certain areas along the rail were affected. That said, we're very glad to be able to report, first, that the fires never came near our actual operations, so our equipment was unaffected. And second, everyone in the local communities stayed safe. There were evacuations in areas close to the city and close to the port, but people have since gone back home, and their homes were unaffected apart from moving out and moving back in. As for the effect of the rail stoppage and the reduced rail capacity for a short stretch, that led us to stockpile approximately 1.3 million tons of our high-grade material at Bloom Lake.

David Cataford

executive
#7

All of this is material at the same specification as our output, so approximately 66.2% is fully sellable material. However, as it currently sits stockpiled at Bloom Lake, once our third-party carriers get their rolling stock and start moving it into production, we do believe we can steadily reduce this material over the coming quarters. Looking at operations, as we said, we're very proud to have achieved record production of 3.4 million tons and we're on track to reach our full nameplate capacity run-rate in the near future. We're also very pleased with how the mine is progressing. Now that we've received the majority of the mining equipment needed to deliver all of our tons — one drill is still outstanding — that will let us remove certain contractors at our site who are costing us somewhat more. But looking at the trucks and the loading equipment, we do have enough equipment to deliver on our mine plan, which is the ore and the waste MBR needed to achieve full nameplate capacity. You can probably see that iron recovery is a little below our target.

David Cataford

executive
#8

We can optimize this once full nameplate capacity has been achieved. It's very hard to do that kind of optimization while we're in ramp-up mode, since the equipment has to be tweaked once we reach our full run rate. Some modifications will also be needed. These are at the operations level, not at the CapEx level, but operationally there are things to adjust so we can maximize iron recovery, and we see no reason why we wouldn't be able to get there once we've had full nameplate capacity. We do believe the equipment and the design will let us reach full recovery. On revenues, they were mainly impacted by the fact that we had roughly 1 million tons fewer sales than we should have had in the quarter, mostly tied to the forest fires, but we'll get the full benefit of that in the coming quarters as we bring this material to our clients. Looking at costs, this is where I think the teams did a great job, even though we were navigating through those forest fires. Higher production had a positive effect on our costs, cutting them significantly and bringing us closer to our sub-$70 target in the short term.

David Cataford

executive
#9

Also, if we look at prices for diesel and explosives, both came down during the quarter. Explosives fell roughly 10%, and diesel dropped a bit more than that. That has likewise contributed to easing the price. The area where we took a hit this quarter was the volume effect at the port. At the port, we carry fixed costs each quarter, and those were spread across 2.5 million tons rather than across approximately 3.4 to 3.5. That was one of the factors that hurt our costs. The second factor is the inventory build. We had to shift inventory at the site, which generated some additional cost in the quarter, though we do believe we can bring our cost down over the coming quarters once we resolve the logistics problems tied to this quarter. There is another area where we took a hit this quarter. You likely noticed that at the end of March we had locked in a price of $140 per ton, and that price came down very quickly once the last quarter closed. The final price we realized for this material was approximately $123. That produced a negative impact of roughly $35 million, because we had about 2 million tons on the water, and since this was spread across only 2.6 million tons in the quarter, that created a negative impact of about $13.5 million per ton.

David Cataford

executive
#10

Looking at this quarter, the price we booked came in around 121, and over the past weeks we've observed somewhat higher prices. So if conditions remain as they currently are, we ought to see a positive provisional price adjustment when this quarter wraps up. But once more, stepping back a bit and considering what we delivered — again this quarter, we came in at roughly the P-65 index. So across a longer stretch of time, we essentially always capture the P-65 benchmark, and that is what we aim for. There's some short-term noise, yet on yearly results we do secure the full P-65 index. On the cash side, cash declined somewhat during the quarter, largely because our sales came in far below what we had anticipated. We paid the dividend this quarter, roughly $52 million, and there were some sustaining expenditures tied to the work at Bloom Lake for Phase 1 and also at two, plus the work we've now begun on the DR pellet feed project. Turning to our balance sheet, we remain very well positioned to keep pursuing our growth initiatives.

David Cataford

executive
#11

And as we walk through these different growth initiatives on the upcoming slides, you'll be able to see that there is meaningful value creation for shareholders in the years ahead. We just discussed operations. Taking a bit of a step back and looking at the market, and more specifically at DR-grade material: what we see right now is increasingly more subsidies from governments worldwide aimed at converting blast furnaces into electric arc furnaces. We've now seen Germany join that journey of converting from blast furnaces to electric arc furnaces, but that still raises the question of where the feed will come from. And when we look at various assumptions about where the market will be, most assumptions, even conservative ones, see DRI material growing from 5% to roughly about 25% of the market by 2050. That's a substantial increase in DRI needed to supply these electric arc furnaces. And when we ask where else the material can come from — realistically, there won't be sufficient scrap to supply all of these, and especially not enough scrap of high enough quality.

David Cataford

executive
#12

This model also bakes in a pretty meaningful share of blast furnaces equipped with carbon capture, and where that ends up, we'll have to see. But no matter how that plays out, we do expect a substantial rise in DRI over the years ahead. If we try to size what will be needed by 2050, it comes to roughly an extra 350 million tons per year of high-purity iron ore for DRI production. For some perspective, that works out to about 40 new average-scale mines of high-grade material, or roughly 20 mines comparable to Bloom Lake. And keep in mind that getting a new high-grade line up and running takes somewhere between 12 to 15 years in this day and age. I mean, 2050 is basically tomorrow, and we haven't seen any projects of scale announced that could produce this kind of material. So without any other projects beyond the one we're working on at a scale the market has seen announced, there's going to be demand for roughly about 20 Bloom Lakes down the road. So we view that as a very positive potential for Champion shareholders to benefit from higher premiums on this high-grade-type material.

David Cataford

executive
#13

That's basically the route we're taking to generate additional value for shareholders. And when you look at the growth initiatives we have, they're designed either to raise the quality of what we've got at Bloom Lake, or to get the most value possible out of the material we produce, or potentially to bring new tons of DR-grade into the market. How do we get there? Well, we currently have two major feasibility studies underway. We remain on track to deliver them by the close of this calendar year — so by the end of December 2023. One is the pellet plant at Pointe-Noire, the feasibility study for building an 8 million ton per year pellet plant there. The other is the Kami project, which would give us roughly about 8 million tons per year of DR-grade material from the Kami asset. So those are the two projects whose feasibility studies we're working on and should be able to deliver by the end of this year. Looking at our growth initiative, this is the DR pellet feed project that lifts our material to 69% — essentially the highest grade material anywhere in the world — and lets our clients decarbonize their operations while also gaining from higher productivity at the same time.

David Cataford

executive
#14

Looking at this project, we remain on track to deliver it by August of 2025. So we began placing orders for long lead items, and we worked on detailed engineering over the quarter. And we remain very confident that we can hit this timeline. The one piece still missing before we can officially announce delivery of this project in August 2025 is a full investment decision. And for that, we need the Quebec government to allocate power to our project. When you look at the criteria for obtaining power here in Quebec, at a high level what the government has said is that we need a solid relationship with our local communities, and it has to benefit those local communities. And as we said earlier on the call, we've just been recognized as the top company in Quebec when it comes to community relations. It also needs to decarbonize, and as we've previously disclosed, this project will help our clients decarbonize by roughly about 5 million tons of CO2 emissions per year. So we've largely ticked that box. It needs to create value for Quebec, which this also does.

David Cataford

executive
#15

Basically, we secured just about every box. If you look at the schedule for securing power allocation here in Quebec, the government initially said it would happen in June, and then it slipped to July. But realistically, Hydro-Quebec's new CEO starts on August 1, so our expectation is that it will probably be August or September. We ought to get some official word on it around then, and after that we should be in a position where our Board can make a full investment decision, which would let us move ahead and deliver this project by August of 2025. With that said, I want to thank all of our staff, who have done an incredible job navigating these challenging times. And the fact that we were still able to post positive results in such a challenging quarter, even with the impact we felt, is quite a testament to the skills we have within our Company — not only to deliver projects, but also to deliver on our operations. So with that said, I'd like to hand things over to the Q&A portion of the call.

Operator

operator
#16

Orest Wowkodaw from Scotiabank has our first question. You have the floor.

Orest Wowkodaw

analyst
#17

Hello, and good morning. Clearly this was a challenging quarter operationally because of the wildfire situation. Could you provide a little more detail on how operations are shaping up for the quarter we're in now? Specifically, I'd like to know whether rail and logistics were fully back to capacity at the start of July, or whether some of those effects are still—possibly affecting the current month?

David Cataford

executive
#18

Yes. Thanks, Orest, for that question. So there have been a few minor effects still, so the rail isn't yet at full — at its full capacity. I mean, the rails are running, and I don't see any reason why we wouldn't be in a position to deliver all the tons being produced this quarter. It's more a matter of reducing the inventory and the backlog, which is something we're definitely aiming for. Another one of the effects is, as you can imagine, summer is normally when the rail does its shutdowns so it can carry out maintenance — they didn't do that during the fires. So that still needs to happen. So there could be some potentially small effects on delivery of material. But at a normal run-rate, I feel it's back to the point where we were able to bring down all the tons being produced, and we're working closely with IOC to make sure that over the coming quarters we can bring down that backlog so we can sell this material to our clients.

Orest Wowkodaw

analyst
#19

Thanks. Just to be clear, does that mean you aren't anticipating destocking the inventory during this current quarter, and that it's likely pushed out one quarter — did I get that right?

David Cataford

executive
#20

Right, that's accurate. I don't expect much of the inventory to come off in tonnage terms during this quarter. My view is that it'll happen across the coming several quarters, when we can work down the Bloom Lake inventory.

Orest Wowkodaw

analyst
#21

All right, thanks so much.

David Cataford

executive
#22

Much appreciated, Orest.

Operator

operator
#23

Thanks. Our following question comes from Lucas Pipes at B. Riley Securities. You can proceed.

Lucas Pipes

analyst
#24

Thanks so much, operator. Morning, everyone. I'd also like to say congratulations on steering through the quarter's difficulties so effectively. David, I have a longer-term question. Your growth profile looks appealing, with several projects, and how are you thinking about reducing commercial risk on those? Is offtake required, is a fixed price required? I'd value your perspective there. And if you could take us through it project by project — how you approach securing the economics, or whether that's even needed — I'd be grateful. Thanks a lot.

David Cataford

executive
#25

Thanks for raising that, Lucas. As you can likely tell, our balance sheet is in fairly solid shape, and one benefit all shareholders have is that Management Directors hold more than 11% of the business. So whenever we make decisions, we're completely aligned with every one of our shareholders, since we ourselves are major shareholders. And the reason I bring this up is that locking in fixed prices in a setting where we're seeing a massive gap between supply and demand, with that gap running in our favor, doesn't strike me as making a lot of sense right now — not to lock into long-term prices, because we have some potential prepayments for future premiums. Those are things we will certainly examine, but I think the first step for us really is getting all of these feasibility studies done, so we can assess the cost and the value accretion for our shareholders across all of these projects. Then we'll be able to weigh them one against another and see which one makes the most sense. But if we look at projects such as the DR pellet feed, which costs us roughly $350 million, in a normal environment we should be able to finance that fully out of cash flows.

David Cataford

executive
#26

Locking into fixed prices doesn't strike us as offering much benefit. As for potential offtake, we're happy with the arrangement we currently have with our partners — that's where the bulk of our earnings come from, and we collaborate with those partners to help lower costs, or to identify the right customers. Still, looking at the demand that exists in the market today, if our Company were the sort that signs a great many MOUs, we could sell many times over the tonnage we're presently set to produce with the DR-pellet feed. What we're actually doing, though, is moving projects and possible partnerships forward. We just got back from Germany — you've likely heard that the German government is also subsidizing the switch to electric arc furnaces, meaning the conversion of blast furnaces into electric arc furnaces. We stay quite close to our Japanese customers and are doing considerable work in the Middle East. And once you total up all the prospective clients, the demand we have far exceeds what we're actually going to produce.

Lucas Pipes

analyst
#27

That's really useful. So David, maybe just to wrap this up — you shouldn't really view offtake as something that has to be in place before a project decision, right?

David Cataford

executive
#28

That is right.

Lucas Pipes

analyst
#29

Alright, that’s quite useful, thanks. Now, regarding the near-term view of the market: there’s plenty of conjecture around Chinese steel output in the second half. People are asking whether stimulus is needed to keep Chinese steel production at present levels if forceful stimulus does not materialize. How do you expect your business would be affected? And how do you think the iron ore market as a whole would be affected? Thanks for sharing your view on that.

David Cataford

executive
#30

Yeah, thank you for that question. So, looking at how things stand in China right now, they are prioritizing economic growth far more than climate-related factors in steelmaking, and we do believe that will return. At present, the premium for high grade looks quite low, but should some potential pressure arise — you have probably noticed this too in China — they are constructing increasing numbers of large blast furnaces while building fewer of the small ones. So if you consider productivity at these furnaces, even if some production might potentially be shut down, we do think that could deliver positive news for the high-grade premium. We are watching it very closely. We have seen some — I mean, looking at China across the past few years, it seems every day brings a different headline. But realistically, considering the quantity of steel tons being produced, a significant number of tons is being produced. And right now they are even exporting tons. So we see the market in China as pretty healthy. Is stimulus needed to potentially raise the price in the short term?

David Cataford

executive
#31

Still, we believe that given the kind of material we produce and the appetite for that material, we’re relatively shielded in a situation where they cut back on tons coming from China.

Lucas Pipes

analyst
#32

Thanks, that's useful. One quick technical follow-up on that point. Where the bigger blast furnaces are concerned, how does higher-grade ore help from a technical standpoint?

David Cataford

executive
#33

Having a bigger blast furnace makes it somewhat harder to load in a great deal of lower-grade material—you can do it, but your productivity drops considerably, and your cost for each ton of steel rises. There's always a trade-off: how much are you prepared to spend on higher-grade material so the furnace runs more productively, versus purchasing lower-grade material to bring costs down. Still, looking at today's conditions, this is typically what we've observed in Japan, and we've seen it in other regions of China as well. Larger blast furnaces, once built, really do benefit from a substantial share of high-grade material in order to hit their productivity levels.

Lucas Pipes

analyst
#34

That’s really helpful. David, keep it up. I’ll hand it over now. Thanks a lot, and good luck.

David Cataford

executive
#35

Thanks, Lucas. And just to build on that point, when you've got one large blast furnace compared with a handful of others, you don't want to realign it very frequently. So you also want to get as many tons as possible out of each reline of that blast furnace. That's usually one more reason why high-grade material tends to be favored by these large blast furnaces.

Lucas Pipes

analyst
#36

That’s quite clear. I appreciate the explanation.

Operator

operator
#37

Thanks. Our following question is from Alexander Pearce at BMO.

Alexander Pearce

analyst
#38

Thanks, everyone. So, to add to that first question, really. Could you provide a bit more detail on those rehandling costs you mentioned for when we begin drawing down their stockpile? It sounds like that happens later in the year, but perhaps you could give us some sense of the order of magnitude there.

David Cataford

executive
#39

Yes, thank you for asking that. On rehandling costs, we can provide something like a blended rate, since approximately half of the tonnage we have on site sits stockpiled directly beside the load out facility. Handling that material is therefore quite cheap — all it takes is a loader to feed it into a new system we constructed over the past years, which lets us re-handle it very efficiently. As for material located somewhat farther from the site, we estimate a few dollars per ton to transport it back. It is somewhat hard to predict which tons will be moved first. Naturally, those close to the plant will be the initial ones we move, because should another event occur, we want the ability to restock there. So those go first, and then step by step, we will begin relocating material situated a bit farther from the plant as well.

Alexander Pearce

analyst
#40

Alright, that’s really useful, thanks. On the second question, since there’s obviously a chance of restrictions affecting that line in the near term, how does the IOC arrangement function when it comes to priority over tons—would they be given priority, or would you be given priority, if we just saw another problem like this one?

David Cataford

executive
#41

From our perspective, and in the discussions we're having with IOC, it's been quite a solid partnership right from the start. They've consistently been very accommodating regarding both their site and ours. They do have some backlog too, but there's no scenario in which they would move only their material. They also face certain return restrictions at the port in any case, so moving just their tons wouldn't make much sense. And you have to keep in mind as well that it crosses two provinces. So it's a common carrier governed by the Canadian Transport Act. And as a common carrier there are obligations to be able not just to supply yourself, along with some fairly strict mechanisms tied to that. So I don't believe it needs to reach that point, since it's always been a very good partnership, and we feel we'll be able to work with IOC to bring down our tons there at a decent rate over the coming quarters.

Alexander Pearce

analyst
#42

Perfect. Appreciate it, David.

David Cataford

executive
#43

Much appreciated, sir.

Operator

operator
#44

Gordon Lawson from Paradigm has the next question for you.

Gordon Lawson

analyst
#45

Morning, and nice work on a strong quarter. I’d like to confirm that I understood correctly regarding the government’s ruling for the direct feed plant. Was it August 2025 that you mentioned?

David Cataford

executive
#46

Correct — the plant is being delivered. Yes.

Gordon Lawson

analyst
#47

Yes. All right, I was just curious — how at ease are you with the idea of still signing off on CapEx and placing orders for long lead items ahead of that decision being reached?

David Cataford

executive
#48

At this point, we expect that the CapEx we've approved should let us reach the point where the government makes its announcement. That takes us comfortably to the end of September. So we're fairly confident an official answer will come by then. And as you know, we're a pretty creative company. We've also got some plans in place, even if that doesn't happen now.

Gordon Lawson

analyst
#49

Alright, thanks a lot — that's much appreciated.

David Cataford

executive
#50

Thanks, Gordon.

Operator

operator
#51

Moving on to our next question, which comes from Craig Hutchison at TD Securities.

Craig Hutchison

analyst
#52

Hi guys, good morning. Regarding the capability to deliver 50 million tons — I think last quarter you mentioned that your plan was to kind of have it up and running in August. It sounds like you have all the upstream equipment minus one drill; is that still the case? Do you guys think you can get up to full capacity here at this site in August?

David Cataford

executive
#53

Yeah, thanks for asking, Craig. We had given some hints about that over the previous quarters. Our confidence remains that we can get to full nameplate capacity in the near term. Now, given the minor disruptions tied to the forest fires, will that happen in August or September? What I mean is, we believe we are essentially at that point. We are above 90% at present. Conditions have moved in a positive direction since the quarter closed. So I genuinely believe we are close to achieving that run-rate at full nameplate capacity.

Craig Hutchison

analyst
#54

That figure above 90% — that's referring to Phase 2 specifically, correct, rather than the full 15 million tons?

David Cataford

executive
#55

We're at 90% on the overall figure. If you take 3.4 million tons against that — roughly 3.75 that has to be done each quarter — we're above it at 90%, yes.

Craig Hutchison

analyst
#56

All right. Perhaps focusing only on the DR project: your team has been on the road a fair amount since January for that study. Is there any better sense of how the pricing mechanism will work? As I recall, you mentioned before it might go something like this — you take the DR pellet, then possibly deduct what it costs to prepare the pellet, and then there's some kind of traction from that point. But given where the market stands now, and how things have shifted beneath this material, any added clarity on how that pricing mechanism could unfold going forward would be useful. Thank you.

David Cataford

executive
#57

Yeah, thanks for that question, Craig. So that's still unresolved, with many of the clients at the moment. So we're exploring creative approaches to be able to price that. And the last thing we want is to hurt ourselves down the road. So we still have quite a bit of time to be able to settle those over the next two years. But the way we're still seeing it as a portion of that DR pellet feed material, plus an increase for the ethane units for our material. When we look at that feasibility study and the number that we have, we still feel that a conservative number when we look at the potential that we're seeing. And what's interesting as well, as you probably have EV announcements from Cliffs wanting to get paid for their ADPi-type material and green steel. So when we look at other potentials out of Germany, we're seeing also some premiums being announced. So something that was not there last year, we're starting to see now and this is just the beginning. So we do feel that a lot of these higher-grade material producers will want to make sure that they get the full benefit for this material over the next year.

David Cataford

executive
#58

That may change down the road, but the numbers we’re seeing in the feasibility study strike us as pretty conservative.

Craig Hutchison

analyst
#59

Thanks a lot, everyone.

David Cataford

executive
#60

Thanks, Craig.

Operator

operator
#61

Thanks. <<operator_script>> Our following question comes from Dalton Baretto at Canaccord.

Dalton Baretto

analyst
#62

Thanks. Hi, good morning everyone. David, I’ve got a somewhat bigger-picture question for you, given your high-grade strategy, the quality of your wider portfolio, and where your valuation stands today. Are you seeing any interest from larger miners or steelmakers when it comes to a strategic investment? And then Part B, I suppose, is this: would you be open to such an investment if it came at a premium to market? Thank you.

David Cataford

executive
#63

Yes, thank you for that question. I believe the area drawing the greatest attention right now is, if we take the Kami project as an example, a lot of parties are eager to lock up this kind of higher-grade material, and that's where we've seen substantial interest in projects such as Kami. So we genuinely believe a partnership scenario could be developed. We've consistently stated that this is a project we wouldn't necessarily pursue alone, and that our aim was to bring in a partner to make it happen. So that is certainly something we're considering for the growth into our project. Then, if you consider the DR pellet feed side, and I draw a small comparison with lithium: a few years back, everyone understood lithium would be needed. Everyone understood it would carry a meaningful premium, yet hardly anyone was investing or paying meaningful premiums for it. Today we're witnessing more and more elements of a panic mode. There are companies with three holes in the ground that are valued at, I mean, pretty high amounts. So that is definitely something — definitely something we're observing in the DR market.

David Cataford

executive
#64

Looking at the DR market, we're really only at the start of the demand growth we expect near term. And no new supply is coming online. The one difference I'd point to between lithium and DR material is that you can find lithium pretty much anywhere. DR-grade material is very restricted in terms of where around the world you can actually produce it at reasonable costs. And maybe as a last point, consider a project like Bloom Lake. The replacement value of that asset today is probably above roughly $6 billion-$6.5 billion U.S. And if you look at our market cap today, we do feel there's still considerable room for it to grow. So would we consider a partnership at these sorts of levels, when you look at the Company, I do think it wouldn't be accretive for our shareholders at this time. It depends on what you mean by significant premium. So it's something we can definitely evaluate, but I wouldn't see something at that level getting done at any point in the short term.

Dalton Baretto

analyst
#65

Thanks very much — that's helpful.

David Cataford

executive
#66

Thanks, Dalton.

Operator

operator
#67

Our following question is from Lucas Pipes of B. Riley Securities.

Lucas Pipes

analyst
#68

Much appreciated, operator. Thanks for allowing my follow-up question. The earlier question covered almost precisely what I had intended to ask, so I'll attempt a slightly different angle. David, when you consider the majors, do they feel a sense of urgency about shifting into higher-grade material? And if that's the case, which key regions worldwide are they concentrating on — is Eastern Canada at the top of that list, or perhaps lower down? I'd value hearing how you believe the industry currently ranks Eastern Canada. Thank you.

David Cataford

executive
#69

Yes, thank you for that question, Lucas. I find DR grade material to be a genuinely fascinating topic. You see, we're a subset of iron ore, and unfortunately iron ore has been basically the most useful metal over the past — let's call it a few thousand years. So it doesn't quite carry that sexiness you'll find with lithium or cobalt or some of these other elements. When you look at how critical minerals get defined around the world, you see governments at both local and federal levels maintaining their own lists of critical minerals, and what we're observing from the majors is that they're typically attempting to enter this market. If you look at some of the bigger iron ore producers, they're heavily weighted toward iron ore. And what we're seeing is that they appear to want to move in a more diversified direction. So we're not seeing a great deal of investment in the actual iron ore space. One area that had some potential and was looking to do it was Russia and Ukraine. But you've seen over the past year now that this has been significantly impacted, and it's probably going to take quite some time before they can imagine ramping that portion up. So we're not seeing a lot of focus on this apart from, let's say, a Vale that is definitely working towards that as well.

David Cataford

executive
#70

Beyond that, though, we aren't really seeing much interest. So, is Eastern Canada a great location for producing grade material? I would say yes. What's unfortunate for others is that over the last five years, we've acquired essentially the equivalent of 10 Bloom Lakes in resources across the area and secured all of what we consider the best areas for developing new mines. So we've essentially captured a big chunk of what's possible in this region. So when you combine what IOC has with Arcelor and what we have, not much remains for other projects to find potential in the area. So we do believe we've positioned Champion very well to benefit from this key area, which is Eastern Canada. But perhaps to answer your question, we haven't seen that much interest from the other miners, though I can say we've had a lot of interest when I look at the steelmaking companies. More and more are coming to visit Bloom Lake and coming to visit the area. There's growing interest in seeing how they can benefit from this high-grade type material within their operations.

David Cataford

executive
#71

So that's the space where I'd say we're starting to see the majors enter.

Lucas Pipes

analyst
#72

That's really useful. I appreciate the extra detail once more. Good luck.

David Cataford

executive
#73

Much appreciated once more, Lucas.

Operator

operator
#74

Thank you. That brings us to the end of the question-and-answer session, so I'll hand things over to Michael now.

David Cataford

executive
#75

Yes, so apologies — it'll be David for the moment, since Michael hasn't taken my spot yet. But realistically, I want to express thanks to everyone for joining today's call. I'd also like to thank all those who have helped Bloom Lake achieve the results you witnessed this quarter, particularly our staff in the local communities. I genuinely believe we have the right team to navigate the various challenges that may come our way over the next years, and that we also have the team in place to deliver on our growth initiatives and create significant value for our shareholders. Reporting our results is always a pleasure. And I look forward to speaking with all of you at the end of the next quarter. Have a great end of summer, everyone.

Operator

operator
#76

That brings today’s conference call to a close, everyone. We appreciate your taking part, and we ask that you kindly disconnect your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Champion Iron Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Champion Iron Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Champion Iron Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.