Cleveland-Cliffs Inc. (CLF) Earnings Call Transcript & Summary

October 24, 2023

New York Stock Exchange US Materials Metals and Mining earnings 56 min

Earnings Call Speaker Segments

Lourenco Goncalves

executive
#1

Thanks, Daryl, and I appreciate all of you being here this morning. Before Celso begins talking about what we delivered in Q3, I'd like to give one more quick note. In August, we told everyone about a possible opportunity for Cleveland-Cliffs that could be exciting and transformative. Since that time, limits have been placed on whatever we're able to say or reveal, so as things stand right now, we can't address the matter; thus, if you're already asking yourself why nothing will be said about it, that's the reason. Now that I've covered that, I'll hand things over to Celso.

Celso Goncalves

executive
#2

Morning, everyone, and thanks for joining. For the third quarter, revenue came in at $5.6 billion, Adjusted EBITDA was $614 million, and GAAP EPS was $0.52. Net tons shipped totaled 4.1 million, and even though the UAW strike hit three automotive customers, our shipments across all automotive customers as a group rose from Q2 to Q3. In fact, Cleveland-Cliffs' steel shipments to automotive in Q3 set a quarterly record. Free cash flow generated during the quarter was $605 million. As we had planned, most of that cash went toward paying down our ABL, which brought net debt to $3.4 billion and pushed total liquidity to a record $4.4 billion; in addition, we gave back roughly $60 million to shareholders through repurchases of 3.9 million shares in the quarter. Now that the ABL balance sits at just $325 million, our capital structure is mostly made up of low-cost fixed-coupon debt instruments, with nothing maturing before 2026. Since we bought ArcelorMittal USA in December 2020, net debt has come down by almost $2 billion, and we've also removed $3.5 billion of pension and OPEB liabilities; combined, that's a 60% cut to net debt and post-retirement liabilities in under three years. Over the past couple of years, we've likewise lowered our diluted share count by 13%, from a peak of 585 million shares down to just 509 million shares as of today. Turning to more detail on Q3, shipments held up well even with slower service center sales in the quarter. The maintenance work we did last year is paying dividends, since our operations have run dependably, which let us hit these solid shipment volumes throughout the year. As I mentioned, despite the UAW strike, automotive steel shipments actually grew sequentially in Q3; that outperformance in automotive steel shipments, together with lower service center shipments, helped offset the quarter-over-quarter shift in average selling prices with a richer mix, which stayed strong above $1,200 per net ton, even after overall index prices declined during the quarter. Our cost reduction results were strong in Q3 as well, with a $31 per net ton improvement quarter over quarter; that was below our earlier guide, purely because of the mix factor, but we'll gladly accept that trade-off given the much higher prices that come with better mix. We look for costs to drop another $15 per net ton in the fourth quarter. Compared with Q3 of last year, we've cut unit costs by $165 per net ton year over year in total; at an annual run rate, that's about $2.7 billion in savings. We expect this strong cost performance to carry into next year; we're pleased to share that our annual metallurgical coal buy will cut 2024 coal costs by $250 million. Those 2024 annual contracts got signed in Q3, and the timing on our negotiations worked out really nicely, since worldwide met coal prices went up soon after that. Beyond the other savings, we've also secured another $150 million in savings on fixed natural gas costs for 2024. So with that, I'll hand things back over to Lourenco.

Lourenco Goncalves

executive
#3

Thanks, Celso. You might remember that we chose to give up some output and deliveries during the prior year so that certain steel mills we bought from ArcelorMittal USA in December 2020 could be brought up to a dependable performance standard. Our largest market is automotive, and going into 2023 we expected demand for automotive steel to be far greater than it had been in 2022. Now jump ahead to Q3: the forecast we had for demand came true, and we have seized that opportunity completely. For Q3, total steel shipments exceeded 4 million net tons — our third quarter in a row at that level — and that happened even though service centers mostly did nothing and weren't out buying actively for the bulk of the quarter. Competing in the U.S. automotive business is incredibly tough. Every steelmaker out there wants automotive as a customer segment. During our yearly contract negotiations, we face offers from a huge number of other suppliers — Korean, Japanese, German, other European firms, plus Mexican joint ventures and Mexican trans shipments. On top of that, competition from EAFs keeps growing, and aluminum substitution remains a persistent threat. From that angle, we enjoy no unfair edge whatsoever. The U.S. imports more steel than any other nation by a wide margin — over 30 million net tons in 2022 by itself. Regardless of whatever shifts occur in how America's integrated blast furnace-based oxygen furnace operations are structured in the market, those competitive pressures exist now and won't go away. What makes Cliffs stand out in automotive is how well we take care of our clients. Quite simply, we outperform others at fulfilling what customers require. In a business as detail-oriented and tailored as automotive, dependable quality, customer service, and hitting just-in-time requirements matter more than anything, and Cliffs delivers on those better than anybody. We've been ready to give up throughput in order to supply the broad range of parts that each individual client requires. We must set aside our precious capacity to match their production forecasts, and we carry inventory on behalf of our automotive customers. Like I've mentioned previously, a steel buyer at some carmaker could swap Cliffs out for a different steel supplier purely to get cheaper steel from that other source for a short period; yet experience shows they return to Cliffs once that buyer, or whoever supervises that buyer, or both the buyer and the supervisor, get replaced by new people. We've watched this play out repeatedly. Cliffs' standing in automotive was earned rather than handed over, and we keep battling all these many competitive pressures daily to preserve and strengthen this reputation grounded in excellence. Because automotive production volumes rose, we actually achieved a fresh company record for direct automotive shipments in the third quarter, beating the two prior strong quarters, and that was despite model year changeovers and everything uncertain that preceded the UAW calling its strike. Up to now, the strike that's hitting several facilities belonging to the Detroit Three hasn't had a material direct effect on our automotive business. At this moment, what the present stoppages are doing to Cliffs is smaller than the blow we took from the chip scarcity and the other supply chain troubles that hit the whole auto industry across 2021 and 2022. It's also worth noting that most of the automotive tonnage we ship doesn't head to the Detroit Three, and that's especially the case for our biggest customer, who isn't among the Detroit Three; actually, demand from those other carmakers has been considerably stronger. Because of that, we still look for Q4 shipments to stay near the 4 million net ton level, even should the UAW strike stretch on for some time. On the flip side, it was the service center segment, not the automotive OEMs, that generated the biggest negative effect tied to the UAW strike during Q3. When expectations of a walkout kept building through July, service centers behaved exactly as they always do when uncertainty appears they drained inventories and stayed on the sidelines. Yet the strike's impact fell far short of what these players had expected, and once again they were caught off guard. The clearest proof of that is how fast our 2 recent price hike announcements got traction in the market. Turning to our yearly automotive negotiations, our October 1 renewals, accounting for roughly 30% of our total annual, annualized auto volumes, proved another win. We preserved key volumes and accepted no price reductions. In fact, through these talks, we managed to put in place the Cliffs H surcharge we talked about last quarter. To recap, Cliffs H is the premium we collect for providing our customers in the United States with steel made using close to 30% scrap in our basic oxygen furnaces along with HBI in our blast furnaces. Our automotive clients, and those in other sectors too, simply cannot obtain that in Europe or in Japan, or in Korea, or in India, or in China. Thanks to how we run our operations, using HBI and getting the most out of scrap, Cliffs ranks among the lowest carbon intensity blast furnace, basic oxygen furnace operations anywhere in the world, and clearly far better than any of today's top 10 largest steel producers globally. Though Cliffs H is a very important first step toward decarbonizing production of sophisticated steel grades, earlier this month we witnessed the most consequential move forward in progressing to the Cliffs H2 Phase, under which we'll bring in hydrogen as a reductant at our blast furnaces. On October 13, through the Bipartisan Infrastructure Law, the White House and the U.S. Department of Energy laid out the plan to dedicate $7 billion to clean hydrogen hubs nationwide, and among the locations selected was Northwest Indiana, the region that matters most to Cleveland-Cliffs. I've mentioned before that what matters isn't the ball's current position — it's where that ball will end up. And where it will end up is hydrogen. The future belongs to hydrogen. Essentially, every bit of carbon emissions in our footprint today stems from fossil fuel-based reductants or energy sources, for which no economically feasible substitute exists. Hydrogen has the ability to alter that, and in the end it will. Cliffs' pledge to purchase a substantial share of output from the Midwest hub was instrumental in the Department of Energy choosing this location. Beyond that, by committing to a major offtake, we ultimately made the hub viable, since we resolved the chicken and egg problem. The hub's very presence ought to draw in other sectors and other applications, among them the feasibility of building hydrogen-fueled vehicles as a clean and workable substitute for battery-powered EVs. The majority of steel companies have concluded that the right course is to spend billions of dollars constructing new EAF-based capacity to recycle scrap whose residual copper content keeps rising. Rather than following that route, here at Cleveland-Cliffs we favor the superior steel quality that blast furnace-based oxygen furnace steel making delivers. What's more, when hydrogen is obtainable and priced competitively, and blast furnaces are already in place, employing hydrogen requires very little capital investment. Just small additions are necessary, such as the new pipeline being installed right now at our Indiana Harbor plant. Choosing hydrogen as our decarbonization pathway distinguishes us from everyone else, and we'll achieve it in a far more cost-effective, quality-driven way. With that said, there's one further key point I want to stress. We value the importance the Biden administration assigns to projects and investments that maintain and expand good-paying, middle-class union jobs. Regulators have taken a tough stance against M&A deals that hurt workers, and rightly so. Many of you have tracked Cleveland-Cliffs over the years and know well how Cleveland-Cliffs collaborates with our union partners, especially the USW, the UAW, and the International Association of Machinists. I'm thankful that President Biden's administration shares our long-term collaborative approach with the unions, and has recognized that Cliffs places workers at the center of our strategic decisions and growth objectives. Finally, one individual who would have been thrilled by these great opportunities is the late international president of the USW, my dear friend, Tom Conway. We held identical views on a vibrant middle class and a resilient American manufacturing sector. All of us at Cleveland-Cliffs grieve the loss of Tom Conway, yet our relationship with the USW will carry on into the future, stronger than ever. We congratulate David McCall on his well-deserved election as international president of the USW. Dave has really been the central figure in the USW when it comes to creating the partnership between our company, Cliffs, and the USW — something that has served as an example both for other businesses and for other parts of the American economy. Together with Dave McCall, we're eager to keep advocating on behalf of our workforce. So with that, I'll hand things back over to Daryl so we can move into Q&A.

Lucas Pipes

analyst
#4

Thanks a lot, operator. Morning, everybody, and congratulations on a strong quarter. Lourenco, I truly appreciated what you said about hydrogen and nice work on that front. I was curious whether you might elaborate a bit on the hydrogen pathway in a couple of respects. So first, once a blast furnace were completely switched over to DRI and the use of hydrogen, where would carbon intensity land, or where would coke intensity land? And second, thinking more strategically, does that alter the way you view the appeal of blast furnace assets? In your prepared remarks you noted that others are placing bets on EAFs. It doesn't appear you're heading that way, and clearly it would be quite interesting to hear your thinking on that given the current context. Many thanks.

Lourenco Goncalves

executive
#5

Appreciate the questions, Lucas, and I appreciate the nice remarks. Let's begin with carbon intensity. Understanding where CO2 gets produced in a blast furnace is quite straightforward; what we charge into a blast furnace as part of the burden includes coal in coke form, and coal in coke form is essentially C. That C, in a C-supersaturated setting, where O2 is rarefied, will produce a great deal of CO; and that CO, carbon monoxide, serves as the reductant that strips oxygen from the pellet, yielding metallic iron. Then, once that chemical reaction takes place, CO2 gets created; therefore the more coke you remove from the blast furnace, the less CO2 you will be producing. That's really all there is to it. Hydrogen goes through a different chemical reaction to eliminate the oxygen. Rather than combining to make CO and afterward CO2, hydrogen will combine to make H2O, and H2O is water as steam. So rather than creating enormous quantities of CO and CO2, you will be creating enormous quantities of steam. Consequently, the more coke you swap out for hydrogen, the more CO2 you remove from the equation. And using direct reduced iron as HBI in a blast furnace happens for one straightforward reason. Whenever you charge HBI, you are no longer charging an oxide—you are charging metallic iron. The overwhelming bulk is FE, not FeO; hence there's no oxygen that needs removing from that share of the burden charged as HBI. So that by itself already lowers how much coke is required, and that explains why our coke rates are so low right now, even without hydrogen, since we charge enormous amounts of HBI. Thus we introduce far less O into the blast furnace, so far less carbon is needed. With hydrogen, we will require still less carbon. Exactly how much less? Only time will reveal, since we have just 1 trial so far, in the smallest blast furnace within our fleet, which is Middletown, and it was a major success; the following one will be a trial at Indiana Harbor Seven, though for that one we will use a great deal of hydrogen since we are constructing a pipeline for it; so we will be the first anywhere in the world to embrace hydrogen as a reductant, and that represents a new route. Will that alter the EAFs? No. EAFs will keep producing less CO2 than the present route, yet EAFs are unable to target a figure that we will achieve using hydrogen. Among other reasons, since the electrodes in EAFs are produced from graphite, and graphite is C. Since hydrogen is a gas while graphite is a solid, you can't produce graphite from hydrogen — that's the reason the electrodes are made of graphite. So my view is that when it comes to turning out particular grades, EAFs have a limited capability. Their capacity to cut CO2 emissions past what they generate now will be constrained, and as things stand, the opportunities involving hydrogen look considerably more compelling over the coming 10 to 20 years. And one additional point: given that we now have full confidence hydrogen will be available, Cleveland-Cliffs will, in Q4, take up a route toward net zero, and it will definitely happen well ahead of 2050. That work is underway. We'll put it out in Q4 of 2023.

Lucas Pipes

analyst
#6

Lourenco, I really appreciate that, and congratulations on it. I've got a couple of quick follow-ups. First, regarding the bid right under USW's Basic Labor Agreement that came to you on August 17 — does that cover all of U.S. Steel, or might non-union assets like Big River Steel fall outside of it? Then second, when it comes to the auto contract talks for annual 2024, could you perhaps offer a few thoughts on what it's like to negotiate in today's environment? Thanks so much.

Lourenco Goncalves

executive
#7

Yeah.

Lucas Pipes

analyst
#8

Let me-

Lourenco Goncalves

executive
#9

I'll begin with the item I can actually address, which is the auto contract. During our prepared remarks we already stated that no price reduction was taken, which means we've managed to hold our pricing at solid levels, and we put Cliffs H into place. That's the full extent of what we'll share; and regarding the remaining part of what you asked, Lucas, we won't say anything further.

Lucas Pipes

analyst
#10

Got it. Lourenco, I really appreciate all the detail, and to both you and the team, wishing you the best.

Lourenco Goncalves

executive
#11

Thank you.

Carlos de Alba

analyst
#12

Yes. Hello, Lourenco and Celso. Regarding what we discussed about hydrogen, I might have a few additional questions. What amount of CapEx do you anticipate it will take when you switch — right, when you modify your blast furnaces so they can handle hydrogen? Also, what does that cost for each blast furnace, or for each ton of steel? And then, are there any constraints, and if there are, roughly what is the limit for replacing coke with hydrogen inside your blast furnaces?

Lourenco Goncalves

executive
#13

Right, so the initial piece — the investment side. As I mentioned during my prepared comments, once the blast furnace is already there, once those 2 years are behind you, once the valves exist, with everything set up, we'll essentially need to construct a pipeline to carry the hydrogen from wherever it gets generated — typically beyond the fence — right up to the blast furnace. That work is underway right now at Indiana Harbor 7. The reason we picked Indiana Harbor 7 is that it represents our high water mark: it's the largest blast furnace, the one consuming the most hydrogen owing to its dimensions. On top of that, it's our flagship unit, our biggest one, the biggest across the Western Hemisphere, so we intend to treat it as a demonstration plant for hydrogen usage. Really, though, that's all there is to it — a pipeline plus a few valves. So our estimate for this CapEx currently sits under $9 million. Pretty minimal, then. And remember as well, this isn't something we're providing at no charge; the expense gets passed on to customers through Cliffs H2, the same way we handle Cliffs H. Should customers genuinely desire green steel — and my belief is they do — they ought to be prepared to pay, and they ought to be prepared to push that along to the consumer or their end users, or whoever; we simply cannot continue discussing this as some theoretical exercise. It feels as though everyone is hoping this whole thing will just disappear. It isn't going to disappear. So if you've got to take it on, if you've got to battle it, you've got to battle it properly. This is a business. We are taking on costs. They're not... When it comes to hydrogen, I'll maintain that the costs won't be enormous, yet any costs we do incur, we'll pass on through Cliffs H. The remaining portion of the question — I promised, but it slipped my mind. Could you repeat it, Carlos?

Carlos de Alba

analyst
#14

Right. It's simply, at what technical threshold or ceiling can you go up to—

Lourenco Goncalves

executive
#15

Oh, okay.

Carlos de Alba

analyst
#16

- You can replace hydrogen with, or coke with hydrogen?

Lourenco Goncalves

executive
#17

Right. That's something I can't give you an answer to at this point. The reason is that coke served a purpose in the blast furnace — actually a few distinct purposes. And naturally, the biggest one involves producing the reductant. As I told Lucas Pipes earlier, that reductant is CO; however, it isn't merely that the CO comes from the coke and acts as the reductant. Another function coke fulfills is supplying heat within the furnace. Keep in mind, you're melting solids and turning liquids into something else, so coke has that job too. Both jobs — reductant and heat source — can be handled by hydrogen; so judged on those two counts, hydrogen is ideal. Yet there's a third function that coke performs in the blast furnace which hydrogen is unable to take over. Coke keeps the burden supported inside the blast furnace in a manner that lets gases move through the furnace and lets chemical reactions take place. For the most part, you don't have pellets in contact with pellets. What you have is pellets in contact with coke, and that structural function within the furnace matters enormously; we can reduce it. We've already been doing so by lowering our coke rate, and we'll keep at it through more HBI and less coke. Still, we haven't found a limit. Right, this is going to be the subject of multiple trials as we begin using it. We're aware it's significantly less — the exact amount I don't know.

Carlos de Alba

analyst
#18

Okay, sounds good. So I just want to make sure I've got this right — apologies — that $9 million investment, or under $9 million that goes into the pipeline, that's for each plant, and it covers the pipe inside the fence, is that correct?

Lourenco Goncalves

executive
#19

Yeah. It's a pipeline that to run from the fence to the furnace.

Carlos de Alba

analyst
#20

To the furnace. All right. Got it.

Lourenco Goncalves

executive
#21

Yes. When you're dealing with a facility on that scale, it's a massive site. We're talking about miles here, so pulling that off isn't minor; that pipeline runs a long way.

Carlos de Alba

analyst
#22

All right, got it; and then just-

Lourenco Goncalves

executive
#23

This is a pipeline. It's not some kind of complicated tech installation or anything of that sort. A pipeline—yes—but a lengthy one, and one designed to transport hydrogen; therefore, particular specs apply. The steel involved is a fairly well-established, clearly specified grade that they'll be employing for that line.

Carlos de Alba

analyst
#24

Okay, that's reasonable. I get it. I appreciate the clarifications. And if I could squeeze in one more thing, regarding the auto price negotiation. You brought up October — is there anything you can share about January? Have those talks kicked off yet, or will they only begin after the auto strike wraps up? Or since the majority of your customers aren't, you know, the Detroit Three, would you go ahead and start negotiating? Have talks already begun with the other OEMs, and when do you think those would wrap up?

Lourenco Goncalves

executive
#25

No, Carlos, the talks are still moving forward, and they don't affect anything related to the strike. Incidentally, regarding the strike, my stance is quite unambiguous. We're well past the halfway mark on this strike. It isn't going to last indefinitely. I don't think this strike will carry on past Q4. Such situations start, reach a high point, and need to conclude. If not, nothing progresses, and it begins to tear things down rather than create anything; so the finish line is much nearer than where this strike started, yet that has zero impact on our talks. The talks continue and are going very well indeed.

Carlos de Alba

analyst
#26

All right. Thank you very much.

Lourenco Goncalves

executive
#27

Thank you.

Timna Tanners

analyst
#28

Yeah. Hey there, good morning, everyone. Trust you're doing okay. I was hoping to dig a little deeper into what we can expect for Q4. I'm aware that you mentioned the $15 per ton in cost savings. You just touched on a few of those auto contracts that start up around October; but is there anything else regarding mix, or how we should be thinking about, you know, some of those other pieces?

Lourenco Goncalves

executive
#29

Okay, so for Q4, the effect on automotive shipments is going to be larger than what we've seen up to this point. Keep in mind, the strike began on September 15, and it's been gaining momentum ever since; as we sit here on October 24, that's now over a month, meaning 24 days of this quarter have been hit by the strike. So compared with Q3, our mix in Q4 is going to look different, since fewer automotive shipments will drag on us somewhat. That being said, consider the service centers. They haven't been purchasing. They made it through Q3 without buying anything. They were like doctors who can't deal with blood. They can't deal with steel; so at this point they have to deal with steel. They have to purchase; that's the reason they received a $100 price hike. Check the box. After that they received another one, of 5%. Check the box, and more is still coming. And it's in their interest to begin purchasing, which by the way they've already done. They're buying much more at this point, because if not, they'll end up buying much more in Q1, and it will cost much more. That's the color I'd like to provide. Celso, would you like to add anything?

Timna Tanners

analyst
#30

Okay.

Celso Goncalves

executive
#31

No, I simply wanted to say something nice, just to wrap up our discussion. Timna, as you know, when we gave guidance, we said costs would come down by $15 compared to the prior quarter, and that reduction in cost is going to help partially make up for the drop in average selling price. But when it comes to shipments, we're going to be at roughly that 4 million ton mark once again in Q4. Then on the mix side, we're going to have less of the value-added product, so to speak. That said, working capital ought to give us a solid tailwind when it comes to free cash flow. My view is that Q4 is going to be something like a low point for EBITDA, yet we'll produce plenty of cash, maybe even more cash than EBITDA in the quarter, and that will back our ongoing capital allocation priorities along with deleveraging, as we keep paying down debt. If the share price stays at these discounted levels, we'll take some of that cash and buy back some shares. That's how I'd suggest thinking about Q4.

Timna Tanners

analyst
#32

All right, that's helpful. You've already addressed part of what I was going to ask next, which concerned an update on how we're thinking about capital allocation. So I'm not sure whether I still need to pose that, but if you have anything to add, that would be appreciated. Moving on, my other question is this: I realize these are relatively minor pieces of your overall mix, but it caught us a bit off guard that volumes for stainless and electrical came in lower. My assumption is that applies to stainless, given that electrical has been sold out and you're carrying additional tons in that area. And regarding the plate side as well, an update on those markets would be very welcome, please.

Lourenco Goncalves

executive
#33

Alright, so here's the thing — what we're observing in our... actually, you raise a really good point there. That's a great observation. What's happening with electrical steels in the U.S. at the moment is quite unsettled. The reason is that you've still got an American market that's using GOES rather than NOES. NOES demand will rise once EV output rises. And right now, that's still at the discussion stage, not the implementation stage. So we're ready — we put money into making a high-performance NOES that we've named MotoMax. So we do have sales, though the volume isn't large, since America's top EV manufacturer builds its cars in China and Germany rather than on American soil. That means no business with them over in China, and none in Germany either. It's possible that changes someday, just not right now. So what we're really doing is holding out for genuine American buyers to purchase more of our MotoMax. Now, on to the NOES side. Demand for NOES keeps outpacing what we can provide, given how much is needed. The catch is that our customers are dealing with every kind of obstacle — trouble bringing on staff, disruptions in the supply chain, and the capacity to move that much tonnage. There's one customer, actually, who's managed to get past all of that — everyone else is lagging. So the issue sits with what happens after the plant, not the plant itself. The plant can now make more since we have the ability to ship NOES over to Zanesville. That means Butler — the site where electrical steels are made — can concentrate entirely on grain-oriented electrical steels. In theory, the demand exists, but those customers have to be capable of absorbing the bigger tonnages. That part isn't our responsibility; it's theirs.

Timna Tanners

analyst
#34

Okay, that's helpful. Thanks very much.

Lourenco Goncalves

executive
#35

Thank you.

Bill Peterson

analyst
#36

Yes, hello, and good morning — I appreciate you taking my questions. There's been plenty of discussion about decarbonization within the auto sector. I was hoping you might give us some detail regarding demand in areas beyond auto, and specifically, what your expectations are for that demand, you know, appearing across the different categories of policy backing — could be the IIJA or the IRA, perhaps, you know, in connection with the solar business, or the CHIPS Act — and how those different pipelines are doing, how they might have shifted since the beginning of the year, and how they might shift over the coming year.

Lourenco Goncalves

executive
#37

Yeah, listen, the largest item so far in 2024 has been the military side. And in a world that currently has conflicts on 2 fronts plus the possibility of a 3rd front over in Asia — that's constantly hanging overhead, involving China and Taiwan along with the South China Sea — we're seeing substantial demand for military applications. There's only so much we can talk about; we're a major provider of steel for military purposes to the DoD, so we won't be able to say a great deal about that. Even so, it has represented a very, very significant share of our business here at Cleveland-Cliffs. Infrastructure is beginning to improve, and so are things tied to alternatives, clean energy sources, especially wind and solar. Solar panels rank among our biggest bright spots within our sales mix. And if I could add a bit more regarding demand. I want to stress once again that demand originating from service centers is recovering and will recover, since either they lack it or they'll shut down; that's the other possibility available to them as well. They're gradually becoming increasingly irrelevant to the supply chain, given that they hold no inventory while prices are falling, and they hold no inventory while prices are climbing, because prices will decline after they rise, they rise. So that's quite a tough spot to find yourself in. So I have real doubts about whether service centers are truly necessary; we've got service centers approaching us, requesting that we rush orders. That's absurd. That goes past ridiculous. Anyway, this is a collection of companies that need to find some kind of religion and alter how they operate. And I think they will, since I'm an extremely optimistic individual, and I think that'll be a major source of supply arriving in Q4 and even more so in Q1.

Bill Peterson

analyst
#38

Yeah, I appreciate that context. Here's another question that's more of a macro nature. So we've come across recent reports indicating that the U.S. and Europe are, you know, talking about the E.U.'s tariff rate quotas and might potentially, you know, permit additional imports. But I suppose, what's your take on how this would affect the U.S. steel market? And what's your perspective on that subject?

Lourenco Goncalves

executive
#39

Yeah, I believe that opportunity has passed for the time being. Those talks wrapped up without reaching a resolution regarding what the European Union asked for. Things have stayed as they were. The TRQs, the tariff rate quotas, remain in effect, and the substitute for the TRQs is Section 232, and Section 232 hasn't been repealed. What's needed globally, Bill, is greater free trade. However, we need greater free trade in both directions. The United States has to send some steel over to Europe. You know, there's a heavily subsidized European Steel Industry, such as the UK, which is run by an Indian company alongside a Chinese company. All we keep hearing about is ever-increasing sums of money provided by the government to decarbonize the British Steel Industry and do this and that. It's simply the government funding the swapping out of equipment, replacing blast furnace BOFs with the EAFs, laying off two-thirds of the workforce and then claiming they're decarbonizing and greening the steel. That's entirely BS, and this amounts to the Chinese exploiting the British; so I think sooner rather than later, we'll manage to export some steel to the U.K., and high quality steel at that, and establish a free trade flow in the opposite direction from the U.S. to Europe. That's my plan.

Bill Peterson

analyst
#40

Alright, that's helpful.

Tristan Gresser

analyst
#41

Hello, thanks for giving me the chance to ask. My first question concerns how you're deploying capital. For several quarters now, I believe the emphasis has been on paying down debt, then giving money back to shareholders, and occasionally doing both simultaneously. So what exactly shifted in how you see the strategy such that big M&A now looks like a more attractive option? Whether or not the bid goes through, how are we supposed to think about Cliffs going forward? Has growth become the main priority? It would be great if you could talk through that strategy a bit.

Celso Goncalves

executive
#42

Yes, of course. Hi there, Tristan. Our priorities for deploying capital have been communicated consistently, and we've brought our debt down significantly. At this point, we believe we've got room to move in other directions—maybe speeding up stock repurchases when conditions are right, or starting a dividend. Paying down debt won't come to an end, but the capital structure we now have gives us room to pursue different paths. On the acquisition side, the flat-rolled sector is still fragmented. We could go after additional consolidation through a number of routes; our track record with M&A has been quite strong. We've made acquisitions at the right moments without paying too much, and that's the approach we'll keep taking moving forward. No matter what we do on the M&A front, our goal for net debt stays at 1x EBITDA across the cycle. Still, we're pleased with where things stand today. We've brought debt down — two quarters in a row now, each with a $500 million cut in net debt. If you look at Q4, you can get a sense of the cash we'll bring in. That cash will keep going toward reducing debt, repurchasing our shares when it makes sense, and pursuing M&A deals aggressively and opportunistically.

Tristan Gresser

analyst
#43

Okay, that's quite straightforward. Thanks. Then perhaps my second question takes a broader view regarding aluminum. I believe you touched somewhat on the danger and the expanding share of the market that aluminum holds versus flat roll. Yes, we would appreciate hearing your perspective on the discussion concerning what lies ahead for steel intensity in automobiles, particularly compared with aluminum. Yeah, that is what I wanted to ask. Thanks.

Lourenco Goncalves

executive
#44

Yeah, see, aluminum has posed a danger to steel for a very long time, and results have been mixed, successes have been mixed. Remember, at one point beverage cans were entirely tin plate, and today they are entirely aluminum. So mark that one down; when it comes to can production, they came out on top. Conversely, regarding cars, they do have some penetration, yet it isn't the massive triumph that folks discuss. We have cases such as the F-150, which was meant to lead to the F-250 at the time, then the F-350, the Explorer, the Expedition, and up to now, only the F-150 has happened. And even with the F-150, here at Cleveland-Cliffs we hold a massive role in the F-150 with high strength, low alloys, structural steels, and all that sits within the vehicle and past the hood. So my aim with the F-150, I think, is removing aluminum, and I think I will, as we move forward. So this is a battle, and we will keep battling; it's one more competitive danger that we must keep taking seriously. And at this point we even have a steel firm that is creating an aluminum firm, so creating an aluminum mill to rival us right here in the United States. So I don't think this will be a home run, but I don't treat these matters casually. We are going to compete, and we are going to win, but we're gonna need to fight. It's a rival, and we will compete.

Tristan Gresser

analyst
#45

Okay, thanks. I really appreciate the additional detail.

Lourenco Goncalves

executive
#46

You're welcome.

Lucas Pipes

analyst
#47

Much appreciated, operator. Thanks for allowing me to ask a second question. Lourenco, I'd like to inquire a bit regarding the expense decreases for 2024. Excellent work when it comes to coal. You brought up that there are reductions in cost, coal among them, and I was curious whether perhaps you might elaborate somewhat on the additional cost drivers that could shift in your favor during 2024. Many thanks.

Lourenco Goncalves

executive
#48

Celso, Celso, take that, Lucas. Please go ahead, Celso.

Celso Goncalves

executive
#49

Right, absolutely. Hi, Lucas. So yes, what we're looking at is additional cost decreases in the coming year, since we'll gain advantages from that fresh coal agreement plus cheaper natural gas for the hedged portion. Also, our starting inventory levels are lower going into 2024. More specifically, regarding Q4, the $15 per ton sequential decline we provided guidance on — that will mostly come from mix, with reduced automotive and a greater amount of lower value-added product, pushed by increased service center demand. That is going to affect costs. And ultimately this effect will flow through inventory. So going forward, you can sort of see how we'll keep seeing cost reductions in Q4 and as we move into next year.

Lucas Pipes

analyst
#50

Alright, that's useful. So would it make sense to begin from a Q4 baseline and then lower energy costs—gas and coal—further from there?

Celso Goncalves

executive
#51

Yeah, that's the right way to think about it.

Lucas Pipes

analyst
#52

Thank you very much, Lourenco and Celso. Again, best of luck.

Lourenco Goncalves

executive
#53

Thanks, Lucas.

Celso Goncalves

executive
#54

Thanks, Lucas.

Carlos de Alba

analyst
#55

Yes, thank you; and still on the subject of costs; so in addition to the really substantial reductions involving coal and natural gas in the coming year, I'm not sure whether Celso or Lourenco could discuss additional efforts that you might be pursuing, whether around productivity or getting labor deployed more efficiently, or any further adjustments to the steelmaking process apart from the raw material savings that you could mention? And should you be able to put numbers to any of those, it would be quite interesting to receive some detail.

Lourenco Goncalves

executive
#56

Right. So, back in the latter portion of 2022, we made a deliberate choice to cut back on volume so we could repair the machinery acquired from ArcelorMittal USA, which was in far rougher condition compared to what came to us via AK Steel. We went into that fully aware it would hurt our numbers. It did hurt them, and from that point forward, we've been showing that solid machinery plus solid employees — a solid union workforce — is capable of turning out a tremendous amount of steel. Three consecutive quarters, in conditions that certainly aren't the liveliest I've ever witnessed — I've definitely seen stronger ones — we've been putting out over 4 million, delivering in excess of 4 million net tons of steel, three quarters running. So far, so good. We've gotten the productivity gains, and this isn't merely productivity from cranking out commodity hot rolled; we turn out every sort of highly sophisticated item for an extremely exacting group of customers that's mostly automotive along with other OEMs. So our productivity level leaves us quite pleased. Then the remaining cost programs all tie back to the reality that we purchase enormous quantities of everything, the way we handled coal. When you buy on a huge scale, suppliers generally treat you well — especially when that large purchaser understands how to purchase. We got coal right. Let's be honest, we timed the closing of that deal flawlessly, since bear in mind, this used to be a mining business. We get commodities, therefore we know how to bargain over these matters. So I won't go deeper into it than that, Carlos, but that's essentially our approach. Celso would like to add something.

Celso Goncalves

executive
#57

Not exactly, Carlos—let me put some numbers around that. Once you factor in all of it—the repair and maintenance on a normalized basis, cheaper inputs, better productivity—those reduced expenses that will carry over into 2024 are going to outweigh whatever rise in labor we might encounter. If we were forced to attach a figure, costs ought to come back to roughly $1,000 per ton during 2024.

Carlos de Alba

analyst
#58

All right. Thank you very much. Appreciate the call.

Celso Goncalves

executive
#59

Thank you.

Lourenco Goncalves

executive
#60

Thanks, Carlos.

Lourenco Goncalves

executive
#61

Thank you, Daryl. It's always a real pleasure to talk about Cleveland-Cliffs with you. We're about to enter the biggest stretch between calls in our whole series, since the upcoming quarter we'll be reviewing is Q4, which lands at the close of the year. That means you likely won't hear from us again until February, and there will be plenty on the agenda when February arrives. So keep watching and stay tuned, since we operate quickly — not everyone moves at that pace, but we keep charging ahead regardless. Your interest in Cleveland-Cliffs means a lot to me, and so do you. I hope you all enjoy a happy Thanksgiving, and since we won't be in touch before then, Merry Christmas as well. Wishing you all the best. Goodbye for now.

Operator

operator
#62

Thanks for joining us; that wraps up today's call. We're glad you could take part. At this point, feel free to drop off the lines. Have a great remainder of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Cleveland-Cliffs Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Cleveland-Cliffs Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Cleveland-Cliffs Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.