Cochin Shipyard Limited (COCHINSHIP.NS) Earnings Call Transcript & Summary
February 14, 2020
Earnings Call Speaker Segments
Operator
operatorWelcome to the conference call of Cochin Shipyard Limited arranged by Concept Investor Relations to discuss its Q3 and 9-month FY '20 results. We have with us today Shri, Jose V. J., Director Finance; Mr. Sivaram Narayana Swamy, Deputy General Manager, Business Development; Shri. Shibu John, Deputy General Manager, Finance; Shri. HariKumar. K., Deputy General Manager, New Projects; and Shri, Syamkamal N., Company Secretary. [Operator Instructions] Please note this conference is recorded. I would now like to hand over the floor to Mr. Shri. Jose V. J., Director Finance for the opening remarks. Thank you, and over to you, sir.
V. Jose
executiveHello? Am I audible?
Operator
operatorYes, sir, you're audible.
V. Jose
executiveHello? Yes. My name is Jose, Director Finance. I have with me, Mr. Rajesh also, GMBD, GM Business Development. Rajesh will give you a brief overview of the overall performance.
Rajesh Gopalakrishnan
executiveYes. Good morning, everyone. Welcome to the CSL con call. Let me just give you a quick update on the latest, and then we move on to taking specific queries. I'm sure by now, all of you would have seen the numbers. The investor presentation is being uploaded today so that you will get more details there. But just to update on the operations front, things have generally been going okay on the -- on both the shipbuilding as well as the ship repair front. On the shipbuilding front, as you are all aware, the key project is, of course, the aircraft carrier, which is slated to go out for sea trials during the first half of this year, and so significant ramp-up and work progress on that vessel. We have recently delivered almost around 12 out of the 16 fishing vessel orders that we had taken, the smaller one. The RO-RO and RO-Pax order from IWAI for 12 -- 10 vessels out of which, 8 are already delivered and are being shortly transported from Kochi to Kolkata because they are being put to use in the National Waterway #1 and 2. The last 2 are being -- are constructed in CSL and that will be put to use in Kochi, that is National Waterway #3. As regards to the floating border outpost, the 9 floating border outpost that we are constructing for the Ministry of Home Affairs, steel cutting has commenced and the ASW contract, which was signed with the Navy for 8 Anti-Submarine Warfare Corvette that -- it's moved into the design phase. As regards ship repair, we'd like to update you that things are generally going well, both in Kochi, which is the main yard. Operations -- ship repair operations in Bombay have picked up, we've completed more than 20 projects in Bombay. We are glad to inform that ship repair operations at the Kolkata facility, which is named CKSRU, that is, CSL Kolkata Ship Repair Unit, has commenced. 2 vessels have already been completed. It's commenced towards the latter part of October. And we're also glad to report that agreement for commencement of operation and maintenance of the Marine Dockyard in Port Blair has also been executed and -- with the administration -- Andaman & Nicobar administration. So there, again, it would be ship repair. As regards to the major infrastructure projects, we also want to update you that work is progressing, and the construction of the new dry dock is expected to be completed by mid '22, and as well as the international ship repair facility, which is coming up in Willingdon Island is also scheduled for completion by mid-2022. That's about a quick update on what we have from our side. We can detail out further as we move forward, and we are ready to -- moving to the question-and-answer session. But prior to that, I would also request my Director of Finance, Mr. Jose to just update you on the latest figures that we have put out.
V. Jose
executiveYes. See, you would have seen the financial results uploaded in the exchanges, with the total turnover is up by 24% on a Q1 to Q1 and PBT is up by around 17%, and PAT is 22%, primarily because of the lower write-off PAT, so 22%. Now we can take on questions.
Operator
operator[Operator Instructions] The first question is from the line of Sandeep Tulsiyan from JM Financial.
Sandeep Tulsiyan
analystSir, first question is pertaining to the revenue guidance that we had given of 12% to 14% for the current financial year. Saying that ship repair out of that, maybe around INR 650 crores. If you could just give an update on the same because we are much ahead of that run rate at 20% for 9-month, but are falling a little bit behind on the ship repair side.
V. Jose
executiveYes. Sandeep, Jose here. Sandeep, regarding the top line, ship repair we'll be doing around instead of INR 650 crores, we'll be doing around only INR 610 crores this year. Because -- primarily because last year, we had that retaining Vikramadity, it was a one-off case. That ship alone contributed around INR 240 crores, that is not there. Above that, this year, the Q3, IAC was to be dropped in ship repair for almost 45 days. So we could not use that dock for the ship repair facility. So these two are the reason for the final reduction in the ship repair turnover. Otherwise, the turnover are -- see, though we have guided earlier 12%, overall, it will be around 14% to 15% on an annual basis.
Sandeep Tulsiyan
analystGot it. Second question was actually pertaining to the new orders. So a couple of quarters back, we had mentioned there were 2 orders, which is pollution control vessel worth about INR 900 crores and there was a large floating dock order that we had spoken about, this order was also about INR 450 crores odd. So what is the update on these 2? Have you won? Or has competition has won these orders, can you just help us on that?
Rajesh Gopalakrishnan
executiveYes, Sandeep, Rajesh this side. Actually, those are still here, right? We had bid for these 2. And the technical evaluation, TECA has been completed in the first case on the submersible pontoon by the Indian Navy. And the TECA for the pollution control vessels, 2 of them, has also been completed by the coast guard. So we are now waiting for the price bid opening date. And then -- and that is when we would know who would win the bid. But we have crossed the TECA stage on both these as of now.
Sandeep Tulsiyan
analystOkay, okay. So other than these two, if you could also, sir, highlight, which other orders are there where Cochin Shipyard is bidding or where at least the tender documents are out?
Rajesh Gopalakrishnan
executiveYes. In fact, I can -- I'll just quickly take you through before for other projects, which we have already submitted the bid or will be submitting shortly. We have bid for 8 Fast Patrol Vessels of the coast guard. The total value is, I believe, estimated to be around INR 600 crores for these 8 vessels. But then the TECA is yet to start for that. We have also bid for 12 air cushion vessels. These are normally called hovercraft, and this is towards the Indian Coast Guard, and that is roughly INR 550 crore estimate there. And here, the technical evaluation has already started. We have also just last week submitted a bid for 6 new generation missile vessels to the Indian Navy, which is a relatively bigger order because these 6 vessels ideally the AoN taken by the Navy is close to INR 13,600 crores, and we have submitted. All these bids, which I'm talking about are on competitive basis, where all other major yards in the country are also participating. In the NGMER, the New Generation Missile Vessel, HSL has not submitted, but our MDL, Goa, CSL, L&T and GRSE have submitted their bids. There are 2 other upcoming bid submissions, which will be done during the course of this month and next. One is multi-purpose vessel for the Indian Navy, 4 of them that is close to INR 2,800 crores to INR 3,000 crores order. And 1 survey training vessel for the Indian Navy, which is around, I believe, INR 750 crores. And these 2 bids are yet to be submitted, but we would be participating.
Sandeep Tulsiyan
analystGot it. Sir, my last question is, on the ship repair side, now we've also acquired the balance stake in Hooghly Cochin Shipyard. And we also have now all the other facilities, which are generating -- started generating revenues. So maybe not for this year, but for FY '21, if you could highlight facility by facility, how much revenue-generating potential do you see in all the facilities that you've undertaken?
Rajesh Gopalakrishnan
executiveYes, Sandeep, before I pass it on to Jose for -- to give you some indications there, just a quick clarification there. See, if you take today's CSL, the main facility is in Kochi, there's Cochin Shipyard Limited, the main yard, where we do both shipbuilding and ship repair. We have the new dry dock coming up within the existing premises, where we propose to do both shipbuilding and ship repair. Next is, we have the international ship repair facility, which is being constructed in Willingdon Island, which is again in Cochin, so just right across the channel from where we are currently, which is predominantly a ship repair facility. Now moving outside Cochin, we have Bombay, which is called CMSRU, the CSL Mumbai Ship Repair Unit, which is pure ship repair. Again, Kolkata there is CKSRU, again, pure-play ship repair. But in Kolkata, we have the HCSL yard, which is Hooghly Cochin Shipyard Limited, which is a fully wholly-owned subsidiary of CSL. As you have mentioned, we have taken over the remaining stake. But that would be predominantly new building facility for inland water vessels. We might be able to do some repairs of inland water vessels there, but that facility is predominantly meant for new building because we have the Netaji Subhas Dock for repairs in Kolkata. And the Andaman facility, again, is pure-play ship repair, so that is just for an overall idea of what it is. And maybe on the overall estimates from each of these, I would presume [ DF ] might be able to guide you there.
V. Jose
executiveYes, Sandeep. Mumbai will be fully become operational only by FY '22. So we are expecting around INR 120 crores from Mumbai in FY '21. This year, we may do around 75% there, but next year, we may do it around 120%. And Kolkata, as Rajesh mentioned, because we have just started, and we have to find out the market there because now, as of now, there is no market there, but -- so we are not putting any amount there as of now. Overall, we may achieve around INR 700 crores to INR 750 crores since next year from ship repair altogether. And ISR will also become operational only by FY '22, by around May FY '22. So FY '21, overall, will be around INR 700 crores to INR 750 crores.
Operator
operatorThe next question is from the line of Aditya Mongia from Kotak Securities.
Aditya Mongia
analystI had a few questions on the shipbuilding business of yours. Firstly wanted to get a sense of how much contribution are we expecting from the IAC [ PSG ] in '21 in terms of execution?
V. Jose
executiveCan you repeat?
Rajesh Gopalakrishnan
executiveThis is not clear. Could you please repeat?
Aditya Mongia
analystSure. So for the 2 key projects that you have on the shipbuilding side, which is GRSE and ASW Corvette order, how much are we building in, in terms of execution for this and next year?
V. Jose
executiveYes. See, IAC, from FY '21 around INR 2,500 crores will come from IAC. And from ASW [indiscernible] FY '21, because ASW construction will start only by mid-FY '21, because we signed the contract on April 30, '19. And construction has to start from 18 months from the date of signing the contract. So it will be June '21. So around June, July, we start the construction. So around INR 600 crores will be from ASW.
Rajesh Gopalakrishnan
executiveSee, right now, ASW is in the design phase and the design drawing approvals and phase is going on. The steel procurement and major initial procurements will also happen. But we start booking revenues when we actually move into physical construction, that is 18 months from the date of contracted plan. So that is why this is the case.
Aditya Mongia
analystGot that, sir. Sir, on the bid -- contract, which you already won, what kind of growth visibility do we have on shipbuilding revenues for FY '21?
V. Jose
executive'21, other than IAC and ASW, there are other small vessels also, which we are currently under construction. So that will -- so altogether we take that also is around INR 3,900 crores will be the total shipbuilding turnaround for FY '21.
Aditya Mongia
analystYou said INR 3,000 crores? Sorry, I didn't get the number.
V. Jose
executiveAround INR 3,900 crores.
Aditya Mongia
analystGot that. And sir, given that we are now moving out of IAC in revenues in FY '21, but do you see the project mix changing in a manner that margins should be different in FY '21 for shipbuilding segment? Or do you expect the similar strength in margin to continue?
V. Jose
executiveSee, IAC will be the -- though the delivery of IAC is scheduled in FY '21, actually, the ship -- the delivery will be -- turnover will be there up to FY '24. Because after delivery, the ship will be here for another 2 years because phase 3 contract of IAC, the total consideration cost around INR 2,400 crore is for predelivery activity, that will be the -- now delivery as we have scheduled it February '21 -- mid '21, then post-delivery for the trials of the arms and ammunition the ship will be here. So we can see revenue from IAC till FY '24.
Aditya Mongia
analystSure. So the margin profile should be steady in FY '21 for the shipbuilding segment? Do you see any project mix variations happening?
V. Jose
executiveNo, FY '21, IAC will be in peak. So the margin will be in the same range.
Operator
operatorThe next question is from the line of Jonas Bhutta from PhillipCapital.
Jonas Bhutta
analystCongrats on a great set of numbers. Sir, I joined the call a bit late, so I don't know if you've already given the breakup of your shipbuilding revenue for the current quarter broken up between IAC and non-IAC and within IAC cost-plus or fixed price lease?
V. Jose
executiveYes, Jonas. Jose here. The total shipbuilding turnover [indiscernible] quarterly INR 747 crores.
Operator
operatorSir, sorry to interrupt, this is the operator. Sir, your voice -- I mean, you were not audible. Can you speak a little louder, please?
V. Jose
executiveYes. See, for the -- am I audible now?
Operator
operatorYes, sir.
V. Jose
executiveOkay. Total shipbuilding turnover for the quarter is INR 747 crores, out of that, INR 635 crores is from IAC and INR 112 crores from non-IAC. And ship repair is INR 149 crores. So the total turnover put together shipbuilding and ship repair, it is INR 896 crores.
Jonas Bhutta
analystAnd within the IAC INR 630 crores, cost plus would be how much? INR 450 crores?
V. Jose
executiveYes, cost plus is INR 371 crores and fixed price INR 264 crores. So total INR 635 crores.
Jonas Bhutta
analystOkay. And for the current year, based on what you've been guiding us at the start of the year, do you think that you will close the year higher than what you thought about in terms of IAC revenue? Because at that time, you had broadly given us a guidance of closer to INR 2,000 crores to INR 2,100 crores. Does that still stay? Or you expect some higher revenue in this project?
V. Jose
executiveAround that level, but it can go up to INR 2,200 crores also.
Jonas Bhutta
analystOkay. So then Q4 will be quite weak? Is that a correct assumption? I mean, just against the INR 630 crores that you've done in the current quarter, about INR 350 crores odd in the fourth quarter?
V. Jose
executiveYes, yes, yes.
Jonas Bhutta
analystOkay. And for next year, you've guided for almost INR 2,500 crores on the IAC?
V. Jose
executiveYes.
Jonas Bhutta
analystOkay. Fair enough. And I don't know, sir, if you've given the breakup of the ship repair revenue. So this year, you're expecting almost INR 50 crores coming out of Bombay. I heard that you've shipped out -- you've repaired almost 20-plus vessels so far. Do you think that we'll reach to that number by year-end as in INR 50 crores revenue out of Bombay?
V. Jose
executiveMumbai -- the total turnover from Mumbai this year will be around INR 70 crores, INR 75 crores.
Jonas Bhutta
analystINR 75 crores?
V. Jose
executiveYes, INR 75 crores.
Jonas Bhutta
analystOkay. And including that INR 75 crores, you'll do INR 610 crores as for revenue?
V. Jose
executiveCorrect, correct.
Jonas Bhutta
analystOkay, okay. And that same number, the comparable number, which is INR 610 crores minus INR 75 crores, so roughly INR 550 crores will become INR 750 crores next year? Or what is the comparable number of Cochin yard, sir, excluding Bombay or any other things, sir, like-to-like number for next year?
V. Jose
executiveYes. See, this year, it is around INR 535 crores. Next year it will be around INR 570 crores.
Jonas Bhutta
analystOkay. And INR 100 crores out of Bombay?
V. Jose
executiveYes. Around INR 100 crores to INR 120 crores from Mumbai next year.
Jonas Bhutta
analystOkay. And ISRS starts contributing or no, next year?
V. Jose
executiveNext year, only from FY '22 onwards.
Jonas Bhutta
analystOnly from FY '22? Got it. And lastly, sorry, it's 2 more questions quickly. Rajesh, I missed out on one of the programs where you've already bid. One was the hovercrafts project, which is about INR 550 crores. Then was the NGMV, which is INR 13,000 crores. The first one, which was about INR 600 crores, what was that, sir?
V. Jose
executiveThat was 8 fast petrol vessels for coastguard.
Jonas Bhutta
analystOkay. And lastly, sir, just wanted your comments on the recent interview by the Chief of Defense staff, sir, that he gave at the DefExpo where he almost clearly mentioned that we may not need another aircraft carrier. And if he's in charge of sort of determining the priorities of defense spending, what is your take on that, sir?
Rajesh Gopalakrishnan
executiveJonas, honestly, we have no comment there. What -- there is also no official or formal thing that has been initiated on the carrier, but there have been informal discussions. And at least from what we gather, the senior levels, the top level in the Navy seem to be extremely confident and come to ask all as well during the Expo and he was keenly listening to the readiness of the new dry dock, which is coming up in CSL, which is specifically the dock floor loading and things like that have been designed for our next-generation carrier. So during those interactions, we didn't sort of feel anything negative, but we are unable to comment on some -- on what he has stated. We feel that the country would need a third carrier because that's what's been the logic all through. So we're just waiting.
Operator
operatorThe next question is from the line of Anuj Jain from ValueQuest Capital.
Anuj Jain
analystSir, you mentioned that for IAC, there is some order book for post-delivery activities. Can you quantify that portion of order book?
V. Jose
executiveThat is from the fixed price part, it's around INR 825 crores. And there will be some associated cost plus also, that will be around the INR 2,000, INR 2,500 crores.
Anuj Jain
analystOkay, okay. So that means like after FY '21, starting FY '22, there will be like huge drop in shipbuilding revenues, right?
V. Jose
executivePardon me? Can you repeat the question?
Anuj Jain
analystStarting FY '22, when the IAC will be completed or will be delivered, there will be like a huge drop in shipbuilding revenues?
V. Jose
executiveNot huge drop because IAC revenue will peak in FY '21. We are expecting around INR 2,500 crores. Thereafter, for the next 3 years the revenue from IAC will taper down, maybe around INR 1,700 crores to next year -- FY '22 around INR 1,700 crores, FY '23 around INR 1,300 crores like that, it will taper down.
Anuj Jain
analystOkay. Understood. And sir, in the fixed price part of the order, how is the cost escalation works? Like what would be the cost for -- the loss for cost escalation?
V. Jose
executiveHello?
Rajesh Gopalakrishnan
executiveHello?
Anuj Jain
analystHello?
Rajesh Gopalakrishnan
executiveYes. Can you hear -- hello? Did you get that?
Anuj Jain
analystYes, I can hear you. Can you hear me, sir?
Rajesh Gopalakrishnan
executiveYes. We can hear you. Yes.
Anuj Jain
analystSo my question is, in the fixed price part of the project, who bears the cost escalation part?
V. Jose
executiveIn fixed price, there is no cost escalation. I was referring to cost-plus contract.
Anuj Jain
analystThat is -- this is the second question, sir, like in case of, let's say, for IAC, if there has been any cost escalation due to the delay of the project, who bears that cost?
V. Jose
executiveNo, see, all materials required for the projects are under cost-plus for IAC. The fixed price is solely relating to our labor, overhead and profit. So there is no value for that, we will not get any escalation, it is a fixed price. But in the case of material, if there is an escalation, it is automatically covered under us also.
Anuj Jain
analystUnderstood, understood. And sir, last question regarding the ship repair margins. What are the sustainable levels for the ship repair margins?
V. Jose
executiveAround -- now we are getting a margin of around 22% to 23%.
Rajesh Gopalakrishnan
executiveAt the EBIT level, right?
V. Jose
executiveAt EBIT level. So when we are starting all the places where ship repair operations, it can come down to around 21% to 22%.
Operator
operatorThe next question is from the line of [ Manoj Shah ] from [indiscernible] Investment.
Unknown Analyst
analystMy question is with respect to the -- your -- can you comment on the receivables? Like as we know that there's a short crunch at the government level. So even at their defense projects. So as we are hearing the other con calls, like in IRCTC and all, so there is a delay from the government on making payments. So can you comment on the receivable positions?
V. Jose
executiveYes. See, as you rightly said, there is some cash crunch in the government level. But see, now we are doing that IAC project for the Indian Navy. For that, it is actually -- it is a funded project by the Navy because we get advanced payments. As of now, there is no issue for that. Even now, we have around INR 400 crores to INR 500 crores in our bank account as advanced payment given by Navy. So there is no issue in the IAC front. And in the case of ASW contract also, so far whatever stage we're in we have raised invoices, we have already received the money. So far, no issue. But in ship repair front, ship repair, we are doing around 50% -- 50% to 70% from Navy, there we have some outstandings are there around INR 250 crores are due from Navy as of today.
Unknown Analyst
analystOkay. And do you see a similar situation continuing, I suppose, till the March, maybe post April you expect some better payout of money?
V. Jose
executiveYes, I think till March, the situation will be like that. But -- because in ship repair we are facing some problem in realizing the money from the Navy till March.
Operator
operator[Operator Instructions] The next question is from the line of Aditya Mongia from Kotak Securities.
Aditya Mongia
analystSir, just some bookkeeping questions. On the backlog front [Technical Difficulty]
V. Jose
executiveHello? You came in broken, could you please repeat?
Aditya Mongia
analystSure. What's the overall backlog at this point of time and the share of IAC [indiscernible] right now?
V. Jose
executiveBacklog?
Aditya Mongia
analystYes, sir.
V. Jose
executiveFor fixed price, it's around -- one second. Fixed price is around INR 2,850 crores, and the cost was around INR 4,250 crores.
Aditya Mongia
analystAnd sir, within this, how much is IAC [indiscernible]?
V. Jose
executiveIAC is INR 2,750 crores.
Aditya Mongia
analystOkay. So this doesn't include the post-delivery part of the order for IAC?
V. Jose
executiveThat's also included in this. This includes the post-delivery part also. This is the total remaining as of December 31, balance order book on IAC. Hello?
Operator
operatorAs there is no response from the current participant, I have muted the line. [Operator Instructions] The next question is from the line of Jonas Bhutta from PhillipCapital.
Jonas Bhutta
analystSo sir, from FY '22, once the ISRF goes live and dry dock also sort of gets commissioned by the end of that year, so in FY '23, what is the likely depreciation that you might have to provide for, for both these assets put together, the sum total?
V. Jose
executiveJust one second, Jonas. It will be around INR 180 crores.
Jonas Bhutta
analystINR 180 crores?
V. Jose
executiveYes.
Jonas Bhutta
analystOkay. So effectively, you will have to generate at least EBITDA worth INR 200 crores to at least offset the hit on this. So if you can guide us with, how do you intend to do that? Or you think that for a couple of years, you might actually not reach to that number, and that would be actually a drag on our financials sort of maybe a couple of years?
Rajesh Gopalakrishnan
executiveJonas, as regards to ISRF, what we would probably do at that point in time since it's just across the channel, we would see what type of projects we can divert to that facility because ship repair, as of today, as you probably are aware, our dry docks are fully booked, and we have lots of customers waiting for 3 to 4 months or even 6 months at times to get a dry dock slot. So we are hopeful of populating ISRF. Although at this point of time, it may not be appropriate for me to give you a figure, we would definitely want to put some good results there. If that the facility takes off, we get a good start. So that's what the primary plan would be. In the meantime, we are also looking out for some -- whether we can get some good conversion projects, which we can feed into the main facility, which would also, in turn, help us divert more vessels into the ISRF.
Jonas Bhutta
analystOkay, okay. So the original plan was that ISRF can do half of what the existing yard can do. So if you do like 80, 90 ships at the existing yard that can do about 30, 40?
Rajesh Gopalakrishnan
executiveActually, that yard at full peak operation, which means maybe a few years after it gets up and running, it is designed to take around 70-odd vessels. Actually, the only thing is those are relatively smaller vessels because the ship lift system, there is a max of 150 length and 25-meter wide. So the small and medium vessels would actually, we would like to handle it there and we move on to the bigger and the commercial vessels on the -- and conversions on the main yard.
Jonas Bhutta
analystSo the peak revenue from that based on a 70-ship projection should be about INR 350-odd crores?
Rajesh Gopalakrishnan
executiveYes. Around that level, Jonas.
Jonas Bhutta
analystSo that even at peak levels, sir can give you a 20% EBITDA, 25% EBITDA can give you just about INR 70 crores, INR 80 crores?
V. Jose
executiveYes, no. With that, see, we need to take some large orders like we have asked -- Rajesh mentioned, by FY '23, the revenue from IAC will taper down, so in the meantime, we have to pick up some other large orders, like now when IAC -- the ASW will be at peak during FY '23. And by that time, some vessels like now we have submitted bid for NGMV, a New Generation Missile Vessel, that order value is around INR 13,600 crores. So some large vessel has to come in that point of time. Unless we grow the -- top line is grown, then we'll not be able to sustain.
Rajesh Gopalakrishnan
executiveSee, Jonas, actually, if you look at the total bids that we have submitted or we are going to submit over the next -- up to maybe March 2020, it will, at least on the Navy or Coast Guard estimates, this is working out to around INR 17,000 crores of bids that we've put in. So we would definitely pray that we get some of it.
V. Jose
executiveAnd we are also expecting that LPD, the landing platform -- what is that, LPD, landing...
Rajesh Gopalakrishnan
executiveDock.
V. Jose
executivePlatform dock.
Rajesh Gopalakrishnan
executiveThat will get retendered shortly, that's what we hope.
Jonas Bhutta
analystOkay. And so you will compete with L&T on that?
V. Jose
executiveNaturally.
Rajesh Gopalakrishnan
executiveWe wouldn't let any competitive bid go by -- pass by without putting an effort into it, definitely not.
Jonas Bhutta
analystSure. And that -- what is the tentative size of LPD, sir, because I thought it was scaled down from 4 units to 2 units or something like that?
V. Jose
executiveIt is around INR 4,500 crores.
Rajesh Gopalakrishnan
executiveNow when it comes out as a reseller, we are not sure how it is going to come out, especially with the budget constraints. But initially, the package size was 4.
Jonas Bhutta
analystPackage size was 4. Okay. Fine. And lastly, sir, on the Mumbai ship repair yard, sir, we had plans of scaling our capabilities to do -- to repair combat ships that could substantially increase our scope at the yard. So where are we on that particular strategic index?
Rajesh Gopalakrishnan
executiveSee, as we think we are putting in place the weapons and sensors group, the recruitment of specialists is -- actually has already commenced. We are also in discussions with the Navy to see what -- how best we can try to start off with at least a small package or something. And let's hope we'll be able to breakthrough shortly.
Operator
operatorThe next question is from the line of Aditya Mongia from Kotak Securities.
Aditya Mongia
analystYes, sir, am I audible to you?
V. Jose
executiveYes, yes.
Rajesh Gopalakrishnan
executiveYes, yes.
V. Jose
executiveCarry on.
Aditya Mongia
analystAs we were discussing on the call, so you're talking about 2% is coming up, one is INS Sagar, which can give you maybe INR 70 crores, INR 80 crores profitability at these levels, and the other one is in dry dock, wherein the visibility of the next aircraft carrier is lacking. Now for the newer dry dock, what are the other potential businesses, so I understand that both ship repair and shipbuilding can happen. But are there any opportunities that you can think through in the absence of the next aircraft carrier happening? What kind of business can the dry dock do?
Rajesh Gopalakrishnan
executiveYes. Let me just explain that a bit. See, the -- while we have actually construed the construction in a manner that the new dry dock can take sort of dock floor loading that a new carrier would demand, which in turn, makes it fully dry dock in India that can actually do a next-generation aircraft carrier. The fact remains that the discussion for a new dry dock commenced in CSL way back in 2004 when even the first aircraft carrier was just in the design stage. So I just wanted to sort of convey that the new dry dock was not -- has not come up solely because of the aircraft carrier. And that would also be evident from the design of that dry dock. If you actually have seen or have a look at the design, it is probably the first test dry dock in the world. And what we mean by that is at the entrance of the dock, we have kept the width at 75 meters, and 100, 110-meter into the dock, we bring down the width to 65 meters because for any shipbuilding, even if it is a large-scale LNG or even bigger tankers or bulk carriers or whatever sort of commercial vessels, the width requirement is not more than, say, 50, 55 or whatever. So why we have done this is because if you actually trace back our history, CSL used to do a lot of rig revamp and upgrades. So -- but then towards the early part of 2000, the classification societies came out with a rule regulation requirement that these jack-up rigs needed to go into dry dock, which was not -- earlier which was not there. So we could actually do these rig revamps and upgrades alongside. Hello?
Aditya Mongia
analystListening to you sir.
Rajesh Gopalakrishnan
executiveYes. Now there is a dock requirement, dry dock requirement for these rigs. Now no dock in India can accommodate these rigs except, I believe the Pipavav dry dock can do so, but there are some -- what I understand, there are some other technical issues regarding draft and things like that, which is posing a problem and the yard is also today, not doing well financially. So what is happening is whatever rigs are operating off -- Bombay offshore and Indian Oil offshore are being towed to Dubai or Singapore or -- for dry docking. So our dock could actually be uniquely posted in India where too much towing and mobilization costs may not be spent. And we would, therefore, hope to become competitive service provider for rig and repairs and revamp because the width we've kept is 75 at end-to-end and rigs are typically around 64-meter wide, the ones that normally operate in the Indian offshore. That is one of the key businesses that we would look. And maybe 5, 10 minutes back, I had also mentioned about CSL going out and starting to look for conversion. So conversions is an area that we feel could bring in larger revenues. And that is something that our marketing team will start focusing on by the time the new dry dock is in place. And of course, as you mentioned, commercial ship repairs are the larger type, which we currently are not into because we are not able to provide dry dock slot. As I told you, the dry dock slots in CSL are currently booked for a few months in advance. And typically, commercial vessels, they normally want short notice dry dock slots. They may not be able to plan more than 1 month ahead. So there are a lot of other businesses that we are also looking into. So those things, we would definitely, what do you say, activate in a fast track manner. So we would not like be sitting back and waiting for an IAC, for sure.
Aditya Mongia
analystJust again, a clarification. This is, again, on IAC, if the order backlog is INR 2,500 crores, and that's the kind of revenue number that you are thinking through next year, there wouldn't be any contribution coming from IAC into 2022, right?
V. Jose
executiveNo. IAC -- contribution from IAC will come up FY '24.
Aditya Mongia
analystRight. [Technical Difficulty] There would be nothing in terms of revenues from FY '22, right?
V. Jose
executiveFY?
Aditya Mongia
analystFY '22.
V. Jose
executiveFrom IAC?
Aditya Mongia
analystYes.
V. Jose
executiveSee, FY -- post-delivery activities will be there during FY '22. So definitely revenue from IAC will be there in FY '22.
Operator
operatorSir, sorry to interrupt. Aditya, there is a lot of disturbance in the line, and we can't hear you.
Aditya Mongia
analystYes. I'm done with my question.
Operator
operatorThe last question is from the line of Giriraj Daga from KM Visaria Family Trust.
Giriraj Daga
analystJust on the IAC question only first, like we are talking about INR 7,100 crores total outstanding orders, fixed price plus cost plus including phase 3, and we are guiding about like INR 2,500 crores in FY '21 and some about INR 350 crores, INR 400 crores in the fourth quarter. So we'll be left with about INR 4,000 crores, which will be booked over a period of 3 years, right, '22, '23 and '24?
V. Jose
executiveYes, yes.
Giriraj Daga
analystWould it be more or less equally spread there? Or FY '22 will be higher and then '23 and '24 will be lower there?
V. Jose
executiveFY '23 and '24 will be lower. It will taper down.
Giriraj Daga
analystIt will taper down. So maybe like 40%, 45% in the '22 and the remaining balancing '23 and '24?
V. Jose
executiveYes, yes. That's right.
Giriraj Daga
analystOkay. Second question is on the like ship repair side, just like whatever happening in the world in terms of like the movement of ships are getting stalled because of the China issue. Are you getting some inquiries for the ship repair for time being, like -- are the ship companies looking for repair? Are they, let's utilize this time in repairing side of it? Are we seeing anything like that?
V. Jose
executiveBasically nothing with -- what is worth mentioning, but this has been discussed internally, and our commercial team is in touch with clients as well as service providers worldwide because there are certain areas, specific areas, which are getting it late because of the new sulfur cap and the regulations that are coming in force. There are a lot of conversions or upgradations on the scrubbers and ballast water treatment systems that are happening right now, most of it which are happening in China. So we feel we might be able to pull off a few -- redirect a few orders from there. So that is something that we are already looking at and trying to see what can be done.
Giriraj Daga
analystBut we have capabilities like for this scrubber and...
V. Jose
executiveYes, yes. We already -- we have capabilities. We already have certain tie-ups for this.
Giriraj Daga
analystBut any order on that or in our current order book?
V. Jose
executiveNot yet.
Operator
operatorThank you. Due to time constraints, we shall end this call. I would now like to hand over the call to the management for their closing comments.
V. Jose
executiveOnce again, on behalf of CSL, let me thank all of you for having joined us today. We hope to keep interacting with you as we normally do periodically. And we look forward to your support. And as you probably have seen, all efforts are on from our side to keep the performance going. Certain other initiatives within the yard are also on. So we hope to come back to you with good result. Thank you very much.
Operator
operatorThank you all for being a part of the conference call. If you need any further information or clarification, please mail at gauarv.g@conceptir.com. Ladies and gentlemen, this concludes the conference for today. Thank you for joining us and you may now disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Cochin Shipyard Limited transcript — plus 255,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Cochin Shipyard Limited earnings transcripts and 255,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.