executiveThanks, and hello everyone. Good morning to you all. It's great to have you on Coeur Mining's call covering our first quarter results. We put those numbers out following the close of trading yesterday, and you can find both the press release and the slides over on our Web site. Before we go further, I want to note that forward-looking statements are part of what you'll hear in our press release, the slides, and some remarks today, and actual outcomes could turn out differently. I'd ask you to look over the cautionary statements in that press release and presentation, along with the Risk Factors laid out in our first quarter 10-Q and 2019 10-K; with that, I'll hand things over to Mitch.
Mitch Krebs
executiveThank you, Paul. On this call with me are Tom Whelan and Terry Smith, as well as a number of other people from the management team. Ahead of getting into the quarter, I want to give a quick update on COVID-19. Starting in early March, we set two goals for steering our way through the effects of this worldwide pandemic: safeguarding the health and welfare of our coworkers, their families, our contractors, and the communities in which we run operations, and doing everything possible to keep our business running without interruption. As of today, we've recorded zero positive cases of COVID 19 at any location in the company. During the early part of last month, we implemented a set of controls and procedures aimed at managing and restricting who can access our operations, carefully screening both employees and visitors, and lowering the danger of exposure and transmission via various social distancing measures plus sanitizing and cleaning protocols. Everyone in our offices is now working remotely, and all travel deemed nonessential has been stopped; we keep re-evaluating these procedures as circumstances change and new information becomes available. The degree of involvement, backing, and outreach shown by our staff toward communities in Western South Dakota, Northern Nevada, Southeast Alaska, Chihuahua Mexico and British Columbia has been genuinely moving. Slides 15 through 17 showcase a number of the efforts our employees are making. When it comes to keeping the business running, all 3 of our U. S. assets are still operating with only minor adjustments or interruptions. Operations and exploration at our Palmarejo mine were halted in line with the decree that Mexico issued in late March. Our Silvertip operation in British Columbia safely halted mining and processing work shortly before the COVID-19 outbreak, and every activity currently underway at the site, including our drilling program, continues there. We stay in close touch with our suppliers as well as our smelter and refinery customers, and so far we haven't seen any major interruptions. As is true for many businesses, we've acted to raise how often and through which channels we communicate, strengthen our liquidity position, and prepare as thoroughly as we can for a broad array of possible scenarios ahead. On the whole, I believe our approach is working well for us throughout these extraordinary times. By concentrating on running a balanced set of assets situated in North America, with special emphasis on the U. S. , we are lowering our overall risk exposure. Our move across the last several years toward a greater share of gold and a smaller share of silver has eliminated a considerable amount of volatility and left us favorably positioned for today's conditions. Our group of organic growth projects gives investors attractive near, medium and long-term growth, and our dedication to a higher, sustained level of exploration, especially close to our current assets, offers our stockholders exposure to upside potential from new discoveries as well as chances for high return mine life extensions resulting from successful reserve and resource growth. And last, our U. S. listing and location, together with our liquidity and access to capital, are important differentiators, particularly in times such as these. So now let's move to our results. When you look at the quarter as a whole, it came in right where we thought it would, and that was largely driven by how well Palmarejo performed, along with our Kensington gold mine up in Alaska. The strength at those two sites made up for a softer quarter at Wharf and Rochester, which was what we had anticipated, and we still expect both of those mines to produce better results over the rest of the year. I talked about our pipeline of growth projects, and the two near term opportunities with the biggest impact are the Rochester expansion and the possibility of restarting Silvertip. Over at Rochester, we hit a significant milestone on schedule for the POA 11 expansion project, getting the record of decision from the Bureau of Land Management just last month. Our plan is to speed up work in the latter part of this year and wrap up this key project by late 2022; we're likewise on track to put out an updated technical report during the fourth quarter that includes a refreshed capital estimate, an optimized mine plan and an economic analysis. Then at Silvertip, a pre-feasibility study looking at a possible mill expansion is currently in progress, and we anticipate having some results around mid year. Drilling at Silvertip began just last month, and we stay optimistic about what that program will produce. Last of all, on the exploration side, the other major pieces of our 2020 exploration program, which is the biggest in the 92 year history of our company, are getting off to solid starts. Most of what we invested in near mine exploration during the first quarter went toward Palmarejo and Kensington, and our biggest single allocation for resource expansion drilling was directed at the Sterling and Crown deposits down in Southern Nevada; we intend to give a mid year exploration update later in the year, since these programs are so large and so important to the company. With all that said, I'll now hand things over to Terry.
Terry Smith
executiveThanks, Mitch, and good morning, everybody. On Slide 6, we highlight how each of our operations performed on the production side during the quarter, along with our outlook for the rest of the year. Let's begin with Palmarejo. Throughput rose more than 25% compared to a year ago, and better recovery rates from a number of optimization initiatives helped push gold production up quarter-over-quarter. As we had expected, silver output fell because grades in our mine plan were lower during the first quarter. Stronger gold recoveries and throughput, together with a modestly higher gold price, combined to produce more than 20 million of free cash flow at Palmarejo. It's also worth noting that once the suspension in Mexico is lifted, we'll be well positioned to ramp back up safely and efficiently. Moving on to Rochester. On our previous call, we noted that crusher production was off to a strong start early in the year. I'm pleased to share that crusher performance this quarter came in 11% above our target and 33% above the fourth quarter. We've now rebuilt the momentum on our leach pad that we lost late last year, but we haven't yet realized the benefit of better ore replacement rates and restocked metal inventories, since during the first quarter we were operating on deeper sections of the pad. We anticipate production will improve in the second quarter and rise steadily over the rest of the year. Before I turn to Kensington, let me add some color to what Mitch said earlier about our expansion plans at Rochester; we intend to spend approximately $30 million to $35 million on the expansion this year, covering a mix of procurement and early stage workloads. We already have several purchase agreements in place for these items, including crushing and process equipment. Our third-party EPCM contractor, SNC-Lavalin, has advanced detailed designs to roughly 50% completion to-date. We're also running a targeted drilling program, which we're optimistic will help us upgrade our mine plan as we work towards an updated technical report at the end of the year. Now let's turn to Kensington. Production was on budget for the quarter, as we saw positive grade reconciliation at the Kensington main deposits. Financial performance stayed strong, with unit costs down 5% to under $930 per ounce, which helped generate just over $14 million in free cash flow during the quarter. We managed to produce just over 2,500 ounces from Jualin at an average grade of 0.33 ounce per ton, or 11.3 grams per ton, and we now expect Jualin to make up 15% to 20% of Kensington's production for the full year. We expect a slightly weaker second quarter because of fewer anticipated Jualin tons, but we expect Kensington will deliver another strong year for the company. At Wharf, adverse weather hurt first quarter pressure performance, leading to weaker than expected production levels. We've mobilized the third party crusher contractor to accelerate our placement rates, and help us catch up on and deliver on our full year plan. Just to remind everyone, we intend to raise our strip as the year goes on, though we anticipate it going back to the historical level in 2021. Before I hand things over to Tom, I want to express gratitude to our employees for rising to the occasion through this challenging time. Even with the added strain and distractions, we posted a strong quarter on the safety front. Our attention stays fixed on the work in front of us. We're grateful for all your efforts and your ongoing commitment to this company. Tom will now walk through the quarter's financial highlights.
Tom Whelan
executiveThank you, Terry. As shown on Slide 10, our balance sheet is in very good shape, with nothing coming due in the near term and liquidity exceeding $250 million. Thanks to better margins, our LTM EBITDA rose 44%, reaching $195 million, compared with $135 million only 12 months earlier. The higher EBITDA, together with the debt reduction steps we took in 2019, brought our total and net debt leverage ratios to 1.8 times and 1.5 times, respectively, at the close of the quarter. We have been running a range of scenario planning exercises to assess how COVID-19 might affect our business, with a particular emphasis on liquidity. We've run through a lot of different situations — everything from gold and silver price movements to figuring out what the short-term halt at Palmarejo might mean, along with other potential downside cases — all to map out a range of possible financial results. Our view is that having a wide array of choices available is the smart approach, since it lets us get the most financial flexibility during this period of unmatched volatility and uncertainty. Based on what our analysis showed, we've taken these main actions so that we're in a strong position no matter which downside scenario plays out. The first was establishing foreign currency hedges, which secures the operating cash flow gains we'd budgeted for. The second came after the quarter closed: we pulled down an additional $100 million from our revolving credit facility. Then, point three: we put together an in-house roster of areas where we could push back CapEx and exploration spending. And point four: we set up an at-the-market equity program worth $100 million, which gives us a possible liquidity source should we need one. Up to now, no capital projects or exploration investments have been deferred, and we don't anticipate trimming these important internal growth efforts unless particular downside scenarios started looking probable. Moving on to Slide 5 and our financial results: we figured Q1 would be the softest quarter for us in 2020, so exceeding our internal budget for operating cash flow and free cash flow feels good. Looking at our Q1 performance, adjusted EBITDA came in at $47 million — a 79% gain compared with Q1 2019. Our 2020 exploration programs got off to a solid start, and operating cash flow was slightly negative at $8 million. That figure was affected by when the annual Mexican EBITDA tax fell, company-wide annual bonus payouts, and inventory accumulating on the leach pads at Wharf and Rochester. Another factor that weighed meaningfully on our first-quarter 2020 results was the pause in active mining and processing at Silvertip. During this quarter, Silvertip consumed $32 million in free cash flow. As the site shifts its attention toward exploration, pre-feasibility work, and routine maintenance activities, we anticipate that amount will shrink considerably in future periods. We project recurring carrying costs of $4.5 million each quarter, which is lower than the $6 million we had guided toward at the start of the year. Costs for exploration and pre-feasibility are still tracking with what we previously estimated. There's one more thing to mention regarding Silvertip. With zinc and lead prices falling so sharply in the first quarter of 2020, plus the sizable rise in 2020 benchmark treatment charges for zinc and lead concentrates that got locked in during March 2020, we still feel good that pausing operations temporarily was the right call. Before I turn things over to Mitch, I'd like to point everyone to Slide 11, where our hedging program is laid out. We kept capitalizing on gold's strength by putting more price protection in place. As you can see, our zero-cost collar gold hedges now stretch to cover part of 2020 output, with a $1,600 floor. Like I said before, we also put some foreign currency hedges in place for the coming years. Our hedging program is designed to support the cash flow we generate and help pay for key internal growth initiatives — most notably the Rochester POA 11 extension, which we anticipate funding through a combination of self-generated cash flow and borrowings under our revolver. At this point I'll turn things back over to Mitch.
Mitch Krebs
executiveThank you, Tom. To bring things to a close quickly, Slide 12 addressed a number of the main goals we have for the rest of this year. Naturally, keeping our workforce, their loved ones, and people in the areas where we operate healthy stays at the very top of that list while we keep steering our way through the COVID-19 situation; we stay hopeful regarding our exploration efforts and the outcomes we anticipate seeing across this year. We also anticipate watching Rochester's output climb, driven by the greater crushing and placement rates that the team keeps achieving. Everyone here is eager about what the future holds for growth in our operations, since POA 11 is positioned to build momentum over the second half. I'm likewise energized by the effort currently being done on the pre-feasibility study at Silvertip, and we can't wait to bring you those results at a later point this year. And last, we'll keep building on our solid safety and environmental track record as we work toward consistent operating and financial results. With that said, let's go ahead and take any questions.
Michael Dudas
analystGood morning, Mitch, and hello to everyone. It's reassuring to hear that each of you is remaining safe and healthy. To start, I'd like to ask about Palmarejo. Could you share a bit more about what we should anticipate from the government, considering reports that the COVID situation is being prolonged, and what alternative measures have been taken there to mitigate that, and how — for that first item? Then, secondly, after you get approval, how quickly do you think you could ramp back up? And thirdly, with mining having been halted repeatedly there, what carrying costs ought we to anticipate for Q2?
Mitch Krebs
executiveI'll kick things off, and then, Tom, I'd like you to chime in as well. As for the wider picture in Mexico, let me take you back. On March 31st, the Mexican government issued the emergency decree concerning limits on businesses deemed non essential. We subsequently received further clarification on April 6th, which spelled out that, pursuant to that decree, mining for precious metals did not qualify as an essential business. Consequently, on April 7th, we announced we would initiate the process of temporarily halting operating activities at Palmarejo. That decree was formally prolonged earlier this week through May 30th. That said, some regions with minimal COVID-19 impact will be allowed to reopen on May 18th, and at present Palmarejo sits inside one of those areas with little to no COVID-19 impact. So we'll more or less target around May 18th. But in the interim, along a somewhat distinct path, we submitted an application for exemption from the decree under guidelines issued by the secretary of mines, and that's more or less a case by case process, whereby they accept the applications, discuss them with public health officials to determine whether mines may restart before those May dates. So we'll continue pushing on that front, while simultaneously getting ourselves ready for a restart, more or less worst case hopefully in the middle of May. Much like the ramp down takes two or three weeks, there will be a similar two or three week ramp up process to bring us back up and running whenever we do receive the green light, whether that's May 18th or sooner. And that's more or less how we're viewing it. Regarding the effect on costs, obviously that depends heavily on when we can restart, so that we can determine how many days we weren't producing, and we're also weighing roughly $25 million in related expenses. But Tom, would you like to elaborate further on that regarding the potential impact?
Tom Whelan
executiveSo, we've discussed this and looked at a lot of different situations, and for what we figure is roughly a 30 day shutdown — that seems like the best guess we can make right now — the figure I'd go with is $10 million in reduced free cash flow for Palmarejo over the course of the year. We'd like to dig into how we arrived at that: it's basically an estimate of losing 1/12 of revenue; we believe operating costs can be cut by 50%, or clearly we can halt the drilling, which means less CapEx — that's to give you a few numbers for how you get to that 10 million. But there's another point I'd like to remind everyone of: the peso has really lost value at this point; and as was said, we've put some hedges in place. Roughly 50% to 60% of our costs are in Mexican pesos; so because of those hedges, we've essentially secured about the same level of lost free cash flow from operations; so just to give you a feel, we'll obviously return with a clearer picture at Q2, but hopefully that hands you some numbers to work with.
Michael Dudas
analystTom, that's ideal. I appreciate it. And Mitch, thanks for your input on that, and I hope the 18th arrives quickly rather than slowly. My next question concerns Kensington. Let me get this straight. It seems that during the second half, you'll be putting significantly more ore through Jualin. So will that blend come to 15% or 20%, and is that across the 12 month span, or — meaning the mix might be considerably greater in the back half of the year. Should we view it that way?
Mitch Krebs
executiveFor the first quarter, Terry, remind me of the figure, under 10, correct…
Terry Smith
executiveYes.
Mitch Krebs
executiveWhen it comes to what it added, Mike, a big part of that traces back to COVID-19 and having enough people available to work — quite a few of our employees at Kensington fly in from the lower 48 on their set rotations, and that hurt worker availability at Jualin during the first quarter, especially in March. That explains why the first quarter came in somewhat under what we anticipate for later quarters. I actually see it as a good sign that, with just 9% or so of the tons originating from Jualin, it still delivered a strong quarter on its own. So my hope is that with somewhat greater contribution across the remainder of the year, the results will show it.
Michael Dudas
analystAnd then last, Terry, perhaps returning to the scenario analysis, or possibly the hedging piece. So I figure that given you've been running this gold hedge program through recent quarters, you'll keep thinking it over as markets evolve, and with larger collar balances, I'd figure. And in a scenario sense, considering what might be spent on deferrals and so on, it sounds as though you believe your liquidity is adequate and that you can push through this without deferring any of the significant work underway; but what — would it simply be price movement, or worries about that, or Palmarejo being unavailable for multiple months? Might those be among the adverse scenarios that would affect that?
Terry Smith
executiveYeah. I'll begin, and then Tom, you can jump in with our views regarding the market and the hedging program we've been executing. A $1,600 floor beneath a substantial portion of our gold output helps considerably in making sure we have enough cash flow from Rochester and other sources to finance that expansion project. That project has very little ability to be postponed or shifted, since as we build up the stage four leach pad, a moment arrives when that pad reaches capacity and we must have this new pad completed and ready for stacking, which is roughly late 2022. So, we're proceeding on that foundation and according to that timeline, and with our revolver plus cash flow, particularly encouraged by that $1,600 downside, we take considerable comfort that it will be enough. Now, should Mexico take longer than all of us hope and anticipate, that naturally makes the figures somewhat tighter, yet we remain comfortable that liquidity will be adequate. And then, Mike, on a separate though related matter. I brought up Silvertip and the pre-feasibility study and the possible restart scenario. You know, that's a project where we hold substantial flexibility regarding whether and when we might ever move on it. And so clearly we were considering, and keeping in mind, not just relative returns across these projects, but how they fit in sequence and swap into our financial ability to deliver on that. But Rochester is plainly the highest priority. Tom, anything regarding the hedging you'd like to add?
Tom Whelan
executiveYeah, I want to emphasize again, Mitch, that we're absolutely aiming for that $1,600 floor. And what's great about approaching it through layering is that timing the market isn't our goal — and clearly, the longer you wait, the greater the upside we can capture. Also, just to remind everyone, back in March, gold fell under 1,500 while silver slipped beneath 12; so we really need to guard against losses to make sure there's enough money for POA 11, like Mitch said. What I mean is, with that schedule, we truly don't have much room to shift that capital spending around.
Joseph Reagor
analystSo I suppose the first thing on my mind is that Rochester scenario, where you'd be putting in those extra leach pads. To get started on that, would the whole amount of capital need to be available right away, or could you move forward with just some portion on day one and still feel at ease?
Mitch Krebs
executiveJoe, I'd say it's the second option, in the sense that on day one we've got the revolver balance. Yet the cash flow coming out of Rochester, plus what the other operations generate, will naturally arrive gradually across 2021 and 2022, serving as an additional important funding source. So it would come about as we proceed. Tom, is there anything you'd like to add there?
Tom Whelan
executiveNo, you hit the mark once more. Joe, we believe we have available both the free cash flow our mines produce internally and the borrowing room under the revolver. Given the scenarios we've modeled, we feel fairly confident in our capacity to finance POA 11.
Joseph Reagor
analystAnd another thing about Rochester — a large chunk of the output drop there ties back to tonnage. Then in Q1 that picked up again, though it likely won't show up until Q2, since you're building inventory back. That said, does the ore composition differ at all compared with, say, mid last year through today? For instance, have you fellas seen any shifts even if the model suggests things ought to be okay? Is there anything geologically distinct regarding the ore being mined right now?
Mitch Krebs
executiveTerry, would you like to take that one?
Terry Smith
executiveJoe, I appreciate you asking that. No, nothing stands out as substantially changed across the stretch you have in mind. A big advantage we get at Rochester is simply consistency. There are, I'd say, some variations when it comes to hardness. We do observe differences in drilling and effects on crushing tied to hardness, but there's nothing geologically or mineralogically that's distinct.
Joseph Reagor
analystSo with that in mind, and based on how I understand the high pressure grinding work you're doing — in plain terms — the only thing left between you folks and reaching your target is time.
Mitch Krebs
executiveThat seems reasonable to me. Each time we place HPGR crushed material on a liner, or close to one, the recovery results we observe match what all the test work had pointed to. So that's definitely reassuring and confirms things. As you said, Joe, it comes down to timing — not just getting ounces down through the deeper parts of that stage four pad, but also accumulating that tonnage. So the stacking rates and placement rates the crew on site has done well at getting back up to speed. To a significant degree, blasting in the pit has helped considerably in boosting crusher performance. Still, we're pleased with what we're seeing at HPGR, and you're correct — it's more a matter of time, a function of time, than anything else.
Joseph Reagor
analystJust one more thing regarding Silvertip. Is there anything left to pay, or did you folks complete the last contingent payments during Q1?
Mitch Krebs
executiveThat's right — we took care of it, and there's nothing further outstanding at this point.
Brian MacArthur
analystI've got 3 short things to ask. Returning to what Tom mentioned regarding layering: you stated there were 99,000 ounces during 2021, yet the press release only handed us 56.5 thousand across the first half plus the second half. Is it fair for me to presume those remaining ounces got layered in equally between the first half and the second half?
Mitch Krebs
executiveTom, would you like to take that one?
Tom Whelan
executiveAffirmative, that's correct. There's likely somewhat greater concentration in the opening six months, though once we finish the program, the aim would be an even distribution.
Brian MacArthur
analystThere are 56 — you were nice enough to provide us 56.5 thousand ounces for the prices in the press release — and I noticed you have as much as 99, as you mentioned during your presentation. Then, regarding the $100 million draw on the revolver, I understand that drawing 200 means paying more in fees or whatever. My assumption is that the $100 million was basically meant to guarantee cash for financing Rochester. Naturally, you'd want a buffer in case things went wrong. Is that roughly how you arrived at a hundred — you ran all your testing, did your analysis, and a hundred just looked like the right figure? And I presume you could have taken 150 or 200, maxed it out, and ended up with more cash on the balance sheet. Is that roughly the thinking behind where the $100 million came from?
Mitch Krebs
executiveYou're certainly headed in the right direction. Tom, would you like to provide…
Tom Whelan
executiveWe ran through a number of various situations, and the last, so a few remarks. First, this crisis differs from '08. This isn't a banking crisis. It's an economic crisis. So, we talked with every bank and simply confirmed there were no limitations on being able to draw on the revolver, and so this had nothing to do with that. But it was merely — we viewed it as a precautionary step just to ensure we had some cash available if a few of these downside scenarios were to occur. I mean the wish is that we'll never have to draw on it; and once more, I'd just repeat right at this point in time, we have no plan to halt any CapEx or exploration once more at the $1,700 goal. We're feeling actually fairly good. But the last thing you want to do is sit on your laurels and get caught short at a moment like this. We've never witnessed times like this and so we simply thought it was a sensible thing to do.
Brian MacArthur
analystYeah, that completely makes sense, and plenty of other businesses have taken the same step. My assumption was that's the source of that figure rather than — well, one could make the case that to be absolutely certain, you draw down the entire 200 million, I suppose that's the point of debate…
Tom Whelan
executiveWe felt as well, once more, we've discussed every one of the actions we took in reply to COVID-19, and it simply didn't seem to us that pulling the full amount matched up with all the risk mitigation that has taken place. And our sense was it would likely convey the wrong message there, since as you note we had the option to draw the entire sum, but it simply didn't sit right with us.
Brian MacArthur
analystThen for my third one, regarding Silvertip — like you said, with TCRCs climbing while prices fall, you made that final payment of 25 million. On the impairment testing side, what's the overall way of thinking about it? My assumption is you'll hold off until the new study arrives, since at that point you'd have a revised long-term plan, and perhaps there's no need to do what — not that I'm claiming you are. I was simply wondering if that required testing this quarter.
Tom Whelan
executiveOnce more, the assumptions behind our impairment analysis assumed a 2022 restart. So when we consider where prices will sit over the long term, I believe the 10-K disclosed the zinc and lead figures we applied, returning to something closer to a longer-term view. Therefore, no matter what occurs with zinc and lead pricing across the coming 18 months, it won't affect the impairment's size.
Adam Graf
analystA few things I wanted to ask about. First, regarding Rochester — the trial you're aiming to have done by year-end: can you remind us whether Lincoln or Wilco will be part of it, or does that belong to the following Rochester trial?
Mitch Krebs
executiveWhat we'd do is refresh the capital, and after that comes a mine plan built to be improved and enlarged, with the hope of bringing in a portion of those East Rochester ounces located beneath the former stage one and stage two pads, plus some extra material out of Lincoln Hill — though nothing at all from Wilco or from Gold Ridge, which lies further west than Lincoln Hill.
Adam Graf
analystCould you also provide some detail regarding any advancements during the first quarter in exploration work at Preciosa, Sterling, and Crown?
Mitch Krebs
executiveHans, would you like to address that?
Hans Rasmussen
executiveAdam, regarding La Preciosa, our engineers are still reviewing the revised geologic and resource model, and a meeting is actually scheduled for the end of next week where we'll go over it. So at some point in May, we should have a far clearer picture of our plans there. At the Crown and Sterling projects, we began with 3 rigs turning — 2 at the Crown area and 1 at Sterling. The Crown area had a big truck grade, and it's among the grades being tested in a new geophysical target. Given how well that target has performed, we've now brought our smaller RC rig up there and kept drilling on this target. It's named seahorse — I'm not certain whether we've included it on any of our maps — but it sits roughly 1.5 miles north of the SNA resource, in a spot with no previous drilling, and it's a geophysical target. So we've stayed quite busy with 1 rig up there; the truck rig was sent home, and we're still drilling around the Sterling area. At Sterling, a core rig will be brought in beginning Sunday, and that core rig will begin the infill large diameter core we intend to use for metallurgical work, engineering work, and to examine a pick design at Sterling itself. Crown and Sterling both have produced some nice upside hits in the drill results, which we'll discuss in our midyear updates, in places we didn't expect. So those are results I can disclose when we issue that news release, and hopefully with that news release, we'll have somewhere around 5 to 10 holes to report in those new zones. So things are going really well at Crown and Sterling.
Mitch Krebs
executiveAnd Hans, regarding what makes up the bulk of this year's program, Palmarejo and Kensington are the largest pieces. At Palmarejo, of course, the drills are not currently turning, though 10 rigs sit there prepared to start up again. So we're eager for that program and what comes out of it. Kensington, too, will give us some solid results to discuss in a mid year update. And then Rochester and Wharf are each weighted more toward the middle of the back half of the year; so plenty of positive developments have been happening across many locations.
Hans Rasmussen
executiveCorrect — Silvertip only began operations around the latter half of March, and currently has 3 rigs running. By the midpoint of Q2, that figure will reach 5 rigs, and from what we can see, conditions there appear quite favorable as well.
Adam Graf
analystCould you give us a refresher on Palmarejo? Are we mainly trying to convert resources or grow them?
Hans Rasmussen
executiveAt the start of this year, we leaned a little more toward conversion, simply because of how our yearly resource and reserve figures get calculated. Our data usually gets cut off at the end of June. So when you look at what we've spent on fleet drilling or meters drilled, those are presently weighted somewhat more toward infill work tied to reserve and resource conversion. That said, it matters a great deal that we locate some fresh veins and new clavos to move into within a couple of years, so for the rest of this year you'll notice the emphasis will mostly be on expansion. We're turning up some intriguing-looking material that, as Mitch mentioned, has us with 10 rigs lined up to kick off and drill hard in some new zones north of Independencia and East of Independencia, where we have solid intercepts we'll discuss in the mid year report.
Mitch Krebs
executiveAlright, thank you. We’re grateful that all of you made time for us today, and we’re eager to connect with you once more during the summer — when, hopefully, circumstances will have gotten back to usual — to go over what we report for the second quarter. Until then, please take care of yourselves and remain well. And once more, thank you for being here. Goodbye.
Operator
operatorThis call is finished now. We appreciate your participation in today’s presentation. You’re welcome to leave the line at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Coeur Mining, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Coeur Mining, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Coeur Mining, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.