Coeur Mining, Inc. (CDE) Earnings Call Transcript & Summary
October 28, 2021
Earnings Call Speaker Segments
Paul DePartout
executiveThanks, and good morning to everyone. It's a pleasure to have you join us for Coeur Mining's call covering the third quarter's earnings. We put out our results once the market closed yesterday, and you can find both the press release and the slides over on our website. I'd also like to note for all of you that forward-looking statements appear in our press release, in the slides, and in certain remarks we make today, and actual outcomes could end up differing from those statements. I'd ask you to look over the cautionary language contained in our press release and presentation, along with the risk factors laid out in our recent 10-Qs and our 2020 10-K. With that, I'll hand things over to the team.
Mitchell Krebs
executiveOkay, thank you, Paul, and good morning to all of you. On the whole, Q3 showed us carrying forward with our approach of putting money into our North American properties to keep reshaping this business around reduced expenses, dependable free cash flow, and robust returns across extended mine lifespans. Beginning with slide 3 in the deck today, I want to call out some important items before I hand things over to the rest of the group. As you can see, this was a quarter marked by a number of major milestones and choices. Outcomes matched what we had projected internally and positioned us for a powerful close to the year while still hitting the production guidance we set at the outset. Mick will walk through operations in greater depth in a moment, but let me briefly address a handful of the main items. Wharf came out on top, posting its second-best operating cash flow and free cash flow since we bought that operation six and a half years back. Palmarejo and Kensington mostly tracked to plan and are poised for robust fourth quarters. Rochester's numbers show consistent advancement even though 38.5 days were dedicated — roughly 45% of the quarter — to crushing and hauling overliner material to the new stage six leach pad ahead of winter. It deserves mention that Rochester's results so far this year include 2.5 months of basically zero stacking on the legacy stage four pad, since the team has been prioritizing work needed for the POA 11 expansion; when it comes to exploration, the findings keep confirming our sustained dedication to these elevated spending levels. We put $20 million into exploration over just this quarter. That dedication to drilling has produced double-digit growth in reserves and resources across recent years, and we're eager to potentially add more growth once again as this year wraps up. Turning to slide 7, it's clear that exploration remains a genuine point of distinction for Coeur. We expect to spend $70 million on exploration during 2021, which comes in almost 40% above the record we achieved a year ago and ranks among the biggest programs anywhere in our sector. We're still positioned to meet our full-year drill footage goals, while spending a touch below what we first planned, which speaks to efficiencies we're capturing from these bigger initiatives. We intend to give another exploration update prior to the year's end, centered on promising new findings at our Nevada properties, at Rochester as well as from the Crown District in Southern Nevada, where plenty of activity keeps happening. Moving to our expansion projects, I'd like to cover a few updates, beginning with the Rochester POA 11 expansion. That project continues to be our number one priority and represents a transformative, fully financed driver of production and cash flow growth for this company. Everything is proceeding smoothly. All told, progress reached 42% complete as of the close of the third quarter. Beyond finishing the overliner crushing for the new stage six leach pad, our team began foundation construction during the quarter for both the Merrill-Crowe plant and the crusher corridor. During our previous conference call, we noted that inflation is affecting the unawarded work that remains, just as most companies have been reporting. On the whole, we consider ourselves lucky that nearly all our contracts were secured before the present surge in costs along with supply and labor interruptions. Through rescoping and rebidding contracts not yet awarded, we are attempting to reduce a portion of these effects, yet our present estimate is that POA 11 construction costs will probably rise by 10%-15% overall. Because of continuing test work and operating experience at Rochester, our technical team has spotted a chance to build in extra operating flexibility through the installation of pre-screens in the new crushing circuit. Detailed engineering has begun, and over the next several months we will assess whether this process improvement is worth implementing. Should we decide to move forward with this opportunity, it might extend the schedule for crusher completion and commissioning by 3 to 6 months. Meanwhile, we intend to put pre-screens on the existing crusher in the first half of next year, which would provide full-scale runtime and experience that we could potentially fold into the new crusher configuration. Now, turning to Silvertip. With today's inflationary conditions and pandemic-caused supply and labor interruptions, launching a new capital project on a faster schedule is hardly ideal, even with zinc and lead prices at multi-year highs. Luckily, our Silvertip expansion and restart remains in its early innings, so we retain considerable flexibility. Although the uncertain macro environment helped push capital estimates above expectations for an accelerated expansion and restart, the quality and prospectivity of the Silvertip deposit is something we know for certain. Exploration results, together with the knowledge and new discoveries our team is producing, have pointed us toward assessing a bigger Silvertip expansion and restart on a potentially slower timetable. To capitalize on such high grade and a significant resource, a 1,750-ton-per-day processing facility probably isn't big enough to maximize Silvertip's value. We will take additional time to assess what a larger design and footprint might mean for economics and overall flexibility; this approach will give us time to keep drilling and hopefully continue growing the resource, let the dust settle on many of these current macroeconomic factors, and let us concentrate on delivering POA 11 without straining the balance sheet. Wrapping up the highlights, we are happy to report that we signed an agreement with Avino Silver & Gold to sell them the La Preciosa project in Durango, Mexico. With their nearby Avino Mine, this transaction provides genuine potential synergies for unlocking value from that asset. From a strategic standpoint, this deal ticks a great many boxes for us when it comes to strengthening how we look on geopolitical risk, the blend of metals we hold, and where our development pipeline sits in terms of timing. Some of that fixed cash consideration can be put to work in the Rochester expansion as well as in our exploration programs, which hold very strong prospects. Through the equity stake we'll hold, plus contingent payments and 2 royalties we're keeping, this transaction delivers considerable upside on the asset. Changing topics, I want to direct your attention briefly to a group of slides beginning at slide 17, which showcase the excellent culture and diversity work happening at Coeur. For an organization to perform at a high level, its culture, strategy, and capabilities must line up — and I believe that's something we've accomplished across the last few years. With that in mind, I want to give a shout-out to Emily Schouten, our head of human resources, for her work on DE&I and for recently earning the industry's Rising Star Award from S&P Global Platts. Our ESG efforts keep getting woven into our strategy and the decisions we make overall. Before Mick gives an overview of our operations, I'd like Hans to build on what I said about Silvertip by walking through the Silvertip exploration results briefly and explaining why we hold such a positive view of its potential. Hans?
Hans Rasmussen
executiveAppreciate that, Mitch, and hello everybody. Silvertip came into our portfolio during late 2017, when we saw that this asset offered terrific upside for expansion. As things stand today, we've outlined nearly 3.5 kilometers of prospective growth through step-out drilling — that's over three times the amount we understood back in 2017, as shown on slide 8. This year, the project is seeing the biggest exploration campaign it has ever had. What's remarkable is that Silvertip makes up about 25% of Coeur's total $70 million budget. The crew on site, under Ross Easterbrook's leadership, has performed exceptionally well in running the 100,000-meter drill program. Because we're drilling from underground, we can explore throughout the entire year and examine various sections of the ore body from multiple directions, and that capability has been essential to the Silvertip growth narrative. Underground drilling during early 2021 resulted in the discovery of the Southern Silver zone's vertical feeder structures along with thick mantle ore zones, and more lately, vertical feeder structures beneath the Discovery South zone; these structures carry substantial potential resource tonnage and show great upside; at present we have two rigs working underground, with plans to bring in a third rig early next year. We also anticipate keeping three surface rigs going to test resource growth toward the south, in the 1.5 km gap separating the Southern Silver and Tour Ridge zones. Thanks to a bigger drilling budget this year, we anticipate continued meaningful growth at Silvertip, which will give our development team the confidence to rightsize the future operation so it matches the potentially larger scale of the ore body. One last thing. Last week the team reported they had cut the best hole ever, with 11 mineralized mantle horizons. That hole sits beneath Silvertip Mountain, roughly 500 meters or 1,500 feet south of the Southern Silver and Camp Creek zones, in a location with no resource shapes currently. This fresh step-out hole is a strong signal of the growth potential we're expecting for 2022 and beyond. I'll hand the call to Mick now. Mick?
Mick Routledge
executiveThank you, Hans. Before we get into how operations performed, I want to give a shout-out to the team for keeping health and safety at the top of the list and for pushing ongoing gains in that area. If you turn to slide 24, it's my pleasure to share that we were recently given the NIOSH Mine Safety and Health Technology Innovations Award in recognition of our cross-functional efforts to respond to COVID-19. It's a real honor for me to be on a team this strong, one that never stops working together and watching out for our people's well-being. Moving now to slide 5 to walk through the operations, beginning with Palmarejo. The team did a fantastic job sustaining elevated throughput and getting the most out of recoveries, which helped make up for some of the weaker grades we've seen as a result of our resequenced mine plan; we've also kept pushing development forward while concentrating on lifting rehabilitation rates throughout the mine, which supports making sure we've properly put the health and safety of our workforce first. Operating costs for the quarter stayed inside guidance, which helped offset weaker realized prices and produced $15 million in free cash flow. At Palmarejo, we're looking for a solid wrap-up to the year, and we can't wait to see how much production growth we can deliver in this fourth quarter. Moving on to Rochester, during the quarter we crushed just under 1.3 million tons of overliner for the new stage six leach pad, which satisfied what POA11 requires. It's worth noting that while we're producing overliner, we weren't crushing material to stack on the legacy stage four leach pad, and that had a knock-on effect on production in the third quarter. Even with that near-term hit to production, all the time, energy, and resources that went into finishing the overliner crushing represented a key step toward wrapping up this expansion project that so many are eager to see completed. Now on to Kensington. Production came in slightly higher for the quarter, since improved grades offset reduced mill throughput brought on by stope sequencing and the availability of drill parts. The good news: we expect more high-grade Jualin material in the months ahead, and the spare parts we need for our stope drills have already arrived, so we're very well positioned for robust production growth in the fourth quarter. Throughout the quarter, the Kensington team did a great job juggling several priorities and keeping costs firmly under control, which helped deliver close to $15 million in free cash flow. Last up, Wharf, and I want to begin by calling out a huge achievement. On October 3, the Wharf team marked one year with no recordable safety incident. That's genuinely remarkable. On the results side, Wharf delivered another excellent quarter, giving us consecutive periods of strong performance. Gold production rose 17%, and cash flow came in as the second-highest since Coeur's acquisition back in 2015. With that, I'll hand the call to Tom.
Thomas Whelan
executiveThank you, Mick. To start, I'd like to provide some additional context regarding the non-cash adjustments that affected our earnings for the third quarter; we recorded a write-off of $26 million related to Mexican VAT refunds, which we firmly believe we are owed. As is the case with numerous other multinational businesses operating in Mexico, we've faced considerable difficulties from SAT and the Mexican courts when it comes to securing these payments; in addition, we recognized a mark-to-market adjustment on our equity investments, largely tied to Victoria Gold; even so, the carrying value of that investment is still higher than what we originally paid. Moving to slide four, let me walk through our consolidated financial results for the quarter in brief. We generated $208 million in revenue, which reflected fairly steady metal sales alongside a lower average realized silver price compared with the second quarter. Operating cash flow came to $22 million, a decrease from the prior quarter, though it was also adversely affected by working capital movements. If we exclude working capital, operating cash flow rose by over 10% on a quarter-over-quarter basis. As is true for most companies, we've encountered cost pressures tied to consumables and labor throughout each of our operations. Because of our sharp focus on controlling costs, we've kept our CAS guidance unchanged at every site, with the exception of Rochester, where we indicated a slight increase. Given the stronger production we expect in Q4, we believe operating cash flow will keep rising as we close out the year. Moving to slide 12 and reviewing the balance sheet, we finished the quarter with roughly $330 million in liquidity, which consists of $85 million in cash along with $245 million available through our revolving credit facility. It's important to note that these figures exclude the $140 million in equity investments carried on our balance sheet. Although we made a modest draw on the revolver, we closed the period with a net debt to EBITDA leverage ratio of 1.4 times. We'll stay committed to our disciplined capital allocation framework and keep our attention on the objective of holding net leverage under 2 times while preserving liquidity of no less than $100 million for the full duration of the Rochester construction period. The added capital expenses at Rochester will create pressure on that objective. That said, we anticipate that the updated schedule for Silvertip, combined with today's strong metals pricing conditions, will position us favorably to sustain a robust and adaptable balance sheet. At this point I'll hand the call back to Mitch.
Mitchell Krebs
executiveThanks, Tom. Prior to opening things up for Q&A, I want to briefly draw attention to slide 13, which lays out what we're focused on in the near term as the year winds down. Since we've reaffirmed production guidance and a solid fourth quarter is now in progress, we have confidence regarding our 2021 results. And in our capacity to bring that momentum forward into the next year. We'll keep reaching for a higher standard and performing at a high level so we deliver consistent results along with organic growth that leads the industry, coming from our balanced portfolio of precious metals assets based in North America. So with that, let's go ahead and take some questions.
Mark Reichman
analystHello, everyone. So, this inquiry could be.
Mitchell Krebs
executiveHey there, Mark.
Mark Reichman
analystRegarding the roles I cover, I've been fielding a growing number of inquiries about sustainability reports, so I was sort of hoping you could expand on Coeur's approach to capping GHG emissions. I mean, plenty of companies are saying, "Well, we're aiming to do better than where we are now." Others are committing to the Paris Agreement. Still others are releasing roadmaps for an eventual route to net zero emissions by 2050. Your broad perspective on your initiatives and the trade-offs involved would be useful.
Mitchell Krebs
executiveYeah, sure. That's a very timely question. I appreciate you raising it. Sitting with us in this room is Casey Nault, our general counsel, who heads up our ESG efforts here. You know, our responsibility report can be found on the website, and we've now produced it for 2 years running. That's a wonderful resource I'd recommend pointing any inquiries you receive toward. In addition, you know, each quarter, I believe we do a genuinely strong job in the quarterly slide decks that go along with these calls of bringing attention to various aspects of our ESG priorities and efforts. I'd describe us, and I think outside parties describe us, as a true leader within our peer group. I'd even say we exceed expectations given our size when it comes to our ESG priorities. We're just now in the first year of having a GHG emissions intensity target that we've publicly announced, which makes us proud. I think you know it's a solid signal of just how committed we are to doing our share, and it aligns with our broader kind of strategy and the emphasis we put on our ESG initiative here. Mark, we'd be glad to arrange any detailed call with you one-on-one alongside any of your interested colleagues to dive deeper into ESG should there be any interest.
Mark Reichman
analystNo, that would be useful. My sense is that the main emphasis is squarely on the climate change piece and the pathway. And then my follow-up question is this: do you expect the support agreement tied to Victoria Gold to be prolonged, or how do you see that playing out?
Mitchell Krebs
executiveYeah. Well, that's a fair question. The date it expires is the thirty-first. Perhaps you noticed, assuming you combed through our disclosures last night during whatever free time you had. Within those disclosures, there's an embedded derivative connected to that support agreement, and we've given it a value of zero, which might be an indirect, roundabout, and possibly wonky method of responding to what you asked regarding how likely we think it is that any value will come out of that agreement.
Mark Reichman
analystAlright, I really appreciate it. I'm going to stop before things get worse.
Mitchell Krebs
executiveAppreciate it, Mark.
Michael Dudas
analystGood morning, Mitch and gentlemen.
Mitchell Krebs
executiveGood morning. Hi.
Michael Dudas
analystMitch, could you expand a bit more about Rochester and the potential pre-screening capital that might or might not be invested? What are a few of the trade-offs, the IRRs, and the timing relative to extending or enhancing the life or cash flow from the project?
Mitchell Krebs
executiveYeah, that's a fair question. I'll have Mick address it. This is an area we've really focused on during the past few months, since we've completed a great deal of test work at that site and while we've kept running the current operation, particularly concerning some of that softer ore we've referenced on earlier earnings calls. We believe this pre-screen idea could deliver significant flexibility for processing that softer ore type in the years ahead. Mick, would you like to go one layer deeper on pre-screens?
Mick Routledge
executiveYeah, absolutely. As you know, that's really common in a mine when the ore body is developing and you're seeing some veins show up. It's really common at other operations too — you install a pre-screen there to strip those veins out, and that does a few things, obviously. It controls the veins going to the back end that we send to the heap leach, which is a good thing, and it helps us control the PSD. It can also help with throughput at certain times. That said, we haven't completed the design on it yet; we're actively working through it. We'll definitely give an update as things move along. Right now, we're taking a close look at it; we're going to aim to put some sort of pilot into the X pit to confirm that the technology we install there fits the ore body we're going to have, and that we get solid learning before any potential implementation at Limerick.
Mitchell Krebs
executiveWe'll have that work, Mike, wrapped up here in the fourth quarter.
Mick Routledge
executiveYeah, expectation is that we'll have some information.
Michael Dudas
analystGot it. So when we consider the rebid along with the reconstituted requirements tied to the capital allocation still left on Rochester, might you give some color on schedule and what's driving it? Clearly, you've already touched on certain forces at play, but is it simply a matter of the contractor, the materials, and the timeline? Everything is just extremely constrained right now. Has COVID created problems when it comes to operating in North Central Nevada and bringing people into the fold?
Mitchell Krebs
executiveI'll kick things off, and after that, Tom, you can continue from that point. On your final comment there, Mike, COVID is unquestionably making labor difficulties worse for contractors. Purely in terms of the pool of workers available, it certainly isn't providing any relief. That, in my view, has worked its way somewhat into certain early proposals we've gotten for a portion of this work that has yet to be awarded. Tom, perhaps you can take it from here and speak a bit about that 10%-15% range we brought up, along with the timing and dynamics Mike was asking about.
Thomas Whelan
executiveRight, of course. When we put both SMPE&I contracts out to bid, our intention was to lock in fixed pricing so we could reduce exposure. What actually occurred is that, in pursuing that risk reduction, and with labor availability so tight plus the other inflationary cost pressures that are genuinely there and that we keep hearing about, we ended up receiving, well, certain proposals that came in way above what made sense. So we made the call to step back, hold discussions, put each of those two contracts out for bid again, bring in a broader set of parties to talk with, and—this is the key part—change how we structure the deal commercially. Rather than sticking with a set price, we're moving toward reimbursable cost combined with shared commercial risk. That effort, once again, is actively in progress, and we're hoping to have it awarded before too long. My expectation is that we'll have considerably more to share on the February year-end call.
Mitchell Krebs
executiveMike, regarding how the rest of the capital is distributed, if that's what you're asking about. As we move through 2022 and into 2023, my expectation is roughly 70% of what's left gets deployed next year, with the balance coming in 2023 as we finish up. Mick, I'd like to offer you the opportunity to chime in, in case there's anything Tom or I didn't cover that you feel Mike should hear.
Mick Routledge
executiveThere are some strong partnerships we've built, including, naturally, the one with Kiewit at Silvertip. That project turned out very successfully, so at this point we're in discussions with similar companies regarding the rebid as well as the fresh approach to carrying out 3A and 3B. Things are progressing favorably in those talks, and everyone will get an update once they conclude. Up to now, we see room in that area to reconsider how those packages are put together.
Mitchell Krebs
executiveIs that useful for you, Mike?
Michael Dudas
analystYeah, that's excellent. Really helpful, Mitch, Tom, Mick. Thanks a lot.
Mitchell Krebs
executiveYeah, of course. Thank you.
Joseph Reagor
analystHello, Mitch and everyone. I appreciate you answering our questions.
Mitchell Krebs
executiveHey there, Joe.
Thomas Whelan
executiveYes. Hello. Appreciate it.
Joseph Reagor
analystA couple of items. The first concerns expenses. There's considerable discussion about whether today's inflationary conditions will persist, speed up, or do something else. What steps are you taking to prepare existing operations so that cost inflation stays as low as possible across the coming 1 or 2 years?
Mitchell Krebs
executiveYes. That term transitory — I suppose it hinges on how you define transitory, correct? What I mean is, we don't truly anticipate some short-term moment, some turning point, at which things necessarily begin to ease back down. We are making preparations and chasing chances to counteract a portion of those effects that might stick around for quite a long time. Tom, would you like to—
Thomas Whelan
executiveOf course.
Mitchell Krebs
executiveLet's expand a bit further on a few of those inflationary elements, and after that, perhaps Mick, you could mention a few of the efforts we're undertaking.
Mick Routledge
executiveYep.
Mitchell Krebs
executiveoperationally to mitigate the impacts.
Mick Routledge
executiveRight.
Thomas Whelan
executiveLabor and consumables are the two main areas that have hit us hard. Once again, take something like diesel — we're observing a 35% rise throughout our U.S. operations, and 20% in Mexico. Luckily, diesel accounts for just 7%-8%. When it comes to labor, pretty much everywhere, especially at Kensington, there's been some strain. All of this puts us at roughly a 5% cost increase. And again, we don't expect — we're currently in our budget cycle — we don't expect that pressure to ease in 2022 whatsoever. We're taking many steps to try our hardest to keep those costs in check; we're quite happy that we can stick with our cost guidance. I believe many of the measures Mick will mention shortly are helping us keep costs level amid this inflationary climate.
Mick Routledge
executiveYes. When it comes to our efforts, we've got a very solid BI business improvement and continuous improvement initiative. There are a range of projects we've been moving through during last year and this year, and we're also giving good attention to next year's portfolio, all aimed at containing costs and making cost improvements, especially in places where fixed costs run high, so we can boost productivity at the same time. In some of those areas, we've made some genuinely encouraging headway this year, most notably at Palmarejo and at Rochester.
Joseph Reagor
analystAlright, appreciate the additional detail. So Mitch, picking up from what was asked before regarding sustainability — and since your team does tend to stay fairly busy with M&A — has there been any consideration around moving the business into battery minerals? First, because holding a critical mineral like that would genuinely strengthen your ESG profile amid the global economic shift. Second, because that space appears to be full of technical talent but perhaps lacks deep mining know-how. Any perspective on that?
Mitchell Krebs
executiveYes, that's a thought-provoking one, and honestly, with all the focus lately on rare earths and battery metals, it's hard not to consider those possibilities. For us right now, though, our plate is extremely full, and executing against those existing priorities is where our attention stays. I suppose you're pointing at something intriguing with the ESG dimension. Given the substantial silver volumes we keep producing — even if that has fallen to 30% or less of revenue — there's a tremendous ESG narrative attached. Its end markets, including solar and electrification, battery storage, and so on and so forth — that is a; we're glad to have it serving as our critical metal contribution. Yet when it comes to branching into other rare earths or battery metals, that simply isn't a priority for us, certainly not in the near term. Never say never, of course, but there are no plans to pursue anything of that sort.
Joseph Reagor
analystAll right, that's reasonable. I'll hand it off.
Mitchell Krebs
executiveYeah. No. Appreciate that, Joe. That's a good one.
Michael Siperco
analystHello there, and I appreciate it a lot, everyone. I want to return to what's happening with the Rochester buildout and when the money will be spent. When I calculate using the updated forecast for Rochester capital expenditures during 2021, the figure I arrive at comes to roughly $60 million to $70 million for Q4, plus approximately $300 million up to the finish, assuming that 10% to 15% increase in costs. Is my calculation correct when I think about somewhere near $200 million during 2022 and $100 million during 2023? Does that sound about right?
Mitchell Krebs
executiveYeah. I think your numbers sync up with that 70%, 30%.
Michael Siperco
analyst70, 30? Right.
Mitchell Krebs
executiveYeah. Yeah.
Michael Siperco
analystAll right, that's helpful. I just wanted to confirm that point. Regarding Silvertip, can you break down the difference between actual costs and what you had anticipated — specifically, what portion stemmed from the faster schedule and what portion came from broader cost inflation? Put another way, if inflationary conditions persist, how much confidence do you have in a more sensible figure while delaying the project?
Mitchell Krebs
executiveSure, that's a fair question. I'll give it a shot, and as I do, I've got Mick and Tom here with me — if I miss anything or get something tangled up, feel free to jump in. What I'd say is this: the faster schedule definitely played a big role, and not just in the sense of compressing building work into what amounts to a pretty narrow window for construction. On top of that, we had to bring in a huge number of contractors to pull it off — far beyond what we could handle at our present capacity. Under that quicker timeline, the fixed costs and the indirect costs were simply going to rise a lot. Another element involved how several of the main infrastructure pieces were designed and how they fit inside the space we already had — those weren't ideal, and they pushed expenses up too. Our view now is that given a bit of breathing room — and of course, we'll keep drilling and expanding the resource — we can watch whether these broader conditions settle down somewhat. That lets us move more deliberately when it comes to footprint and to how we'd ideally arrange the site, which might ease some of those constraints — that's probably the right word — that showed up in the feedback we got late in the third quarter. I realize this isn't a crisp yes-or-no response, but I'm hoping it gives you more background on the forces that nudged us toward the path we're taking now. Mick, Tom — anything either of you would like to tack on?
Mick Routledge
executiveRight. So since we control the schedule, we're able to evaluate which technology to pick, confirm that health, safety, environmental, and hygiene considerations meet best practice standards, and afterward refine that as additional knowledge about the resource comes in. That's a genuinely strong chance for us. As you're aware, the early works have progressed quite smoothly, which means we're reducing project risk along the way. The cleanup at the site has progressed quite smoothly. The decontamination has progressed quite smoothly. On the whole, I'd say our position is a solid one.
Mitchell Krebs
executiveTom, you wanna add on to that?
Thomas Whelan
executiveOnce more, a core point we've kept emphasizing is how vital a robust and adaptable financial position is for the whole Rochester build. You know, this serves as yet another piece of evidence backing the claim that we will maintain a solid and nimble balance sheet all the way through the Rochester expansion. Ed, unless you'd like to chime in, I'll go ahead and note that.
Mitchell Krebs
executiveNo, that's. Does that clear things up?
Michael Siperco
analystYeah, that clears things up. Perhaps building on what you just said, can you — understanding that this is somewhat up in the air, and I suppose part A of my question is when ought we to anticipate a refreshed technical report or additional detail regarding how the project will move forward? Part B is could you provide some sense of how much spending will occur at Silvertip during 2022 and 2023 prior to when you would truly begin the actual construction?
Mitchell Krebs
executiveNow, two fair questions. Mick, I'll ask you to talk about schedule.
Mick Routledge
executiveRight.
Mitchell Krebs
executiveTom, I'd like you to cover spending. Would you prefer to start?
Mick Routledge
executiveYeah. Regarding when the technical report comes out, it's quite probable that lands around the midpoint of next year, though we need to pin that down since we're now adjusting somewhat and reviewing both the updated timeline and this opportunity — after that, we'll discuss it as things move along. That's the most probable timeline for the TR. For the whole project, it's going to hinge on which technology gets picked and what strategy we decide to pursue. To give one illustration, a staged approach could be possible rather than a step change approach. We need to examine what permits each of those alternatives would require, and all of that will be detailed in that upcoming technical report.
Mitchell Krebs
executiveTom, was there something you wanted to revisit?
Thomas Whelan
executiveSure. It really hinges on whether we choose the staged path or the step change path — that decision will shape how much care and maintenance spending shows up in the budget we put out here in early February. The other thing, I'd say, is that the exploration upside has all of us pretty energized. You should keep expecting those exploration levels to keep backing the resource growth. I wish I could give you sharper detail right now, Mike.
Michael Siperco
analystThat's fine, that's fine, it makes sense. Sorry for continuing, but here's one more. You said during the prior quarter that you were considering offtake possibilities as a way to secure funding. Is that process still happening? Are you still weighing that?
Thomas Whelan
executiveYes. That will keep being a component of it. Once more, the trials are progressing, they keep being very encouraging, and there's a lot of interest. Clearly, the schedule has been delayed at this point, but nothing has shifted in terms of that being a major part of the plan to assist in financing Silvertip.
Michael Siperco
analystAll right, fantastic. I swear this is my final question, and it's about something else entirely. Could you say anything about whether Mexico's recent contractor legislation has had any impact on your operations or expenses, or whether it might do so down the road?
Mitchell Krebs
executiveRight, right. So Mike, for our part, that was something we wrapped up in July — we moved employees out of a service company, and honestly it went smoothly. When it comes to paying people at that service company, we've done it the same way we pay everyone, no matter which entity someone works for. Between the old approach and the new one, there's really no significant effect on our costs, on labor costs, on wages, on compensation. Mostly it was an administrative matter, and it finished in July. Nothing has gone wrong or come up since.
Michael Siperco
analystOkay, great. Thanks very much for all the answers.
Mitchell Krebs
executiveNo, thanks for all the good questions.
Mitchell Krebs
executiveHi, Brian.
Brian MacArthur
analystHi. Good morning.
Mitchell Krebs
executiveHey,
Brian MacArthur
analystMike pretty much covered most of what I wanted to ask regarding the schedule at Silvertip and the continuing spend on care and maintenance, and I take it those figures aren't available to us at this point. Perhaps I'll put it another way — at a conceptual level, is the thinking that, you know, to line up with Rochester, we drill during 2022 and 2023, and we aim to be ready for the construction season for a plant of some kind in 2024, with production coming in 2025, and I understand a portion of this could hinge on drilling results. Or are we actually now discussing a scenario where drilling continues for another two or three years and the target becomes 2026? The reason I ask, I suppose, is that this all comes down to what the carrying cost looks like while we're waiting, even though I completely recognize what you're trying to do by sequencing this alongside Rochester.
Mitchell Krebs
executiveYeah. Well, I'll go first. My preference is door number one.
Brian MacArthur
analystAll right. So that is,
Mitchell Krebs
executiveWe'll let the effort determine the timing, and, once more, Brian, you employed that term, in theory. In theory, the notion of doing this in stages is quite logical, where you might begin somewhat earlier and on a smaller scale and let the operation essentially finance its own growth as time goes on. As approvals and ongoing drilling
Brian MacArthur
analystOkay.
Mitchell Krebs
executiveessentially, sketch out the path ahead, you know, for what comes next. Once more, at this stage that's a notion or a leaning; right now effort is being done to determine whether that's the workable route or not. Mick, anything you'd like to—
Mick Routledge
executiveYeah
Mitchell Krebs
executiveAdd to that?
Mick Routledge
executiveAbsolutely, that's the key factor. Naturally, we already hold permits, plus we can amend them so a smaller facility could be constructed. Should we decide on a larger facility, we'd need to reassess those permits along with the footprint, and secure everything required prior to implementing those modifications. There's definitely a leaning toward examining a modular strategy, though we'll evaluate whatever offers the strongest value for Silvertip, and that call will be made once we're prepared.
Mitchell Krebs
executiveBalancing that with balance sheet.
Mick Routledge
executiveExactly
Mitchell Krebs
executivePreserving the flexibility there. Yeah. Good. Does that help, Brian?
Brian MacArthur
analystRight. So I'd imagine that, while you're working through all this, you simply keep pushing hard on the drilling and keep attempting to determine what's truly there, so you can make the call on whether constructing the larger facility makes sense.
Mitchell Krebs
executiveExactly.
Brian MacArthur
analystOkay. That's great. Thanks very much.
Mitchell Krebs
executiveYeah, thank you, Brian.
Mark Reichman
analystThanks. And then for my final question, I was curious about what drove the decision to sell La Preciosa. I realize there's been some pushback out there, but you and David Wolfin go way back, and it looks like Avino is likely going to do everything it can with that asset, plus you kept a stake of some kind. So I just wanted your perspective on that deal and the timing behind it.
Mitchell Krebs
executiveYeah. Appreciate you asking that. With La Preciosa, for quite some time we'd been working to figure out the optimal route to realize value from it. That asset came into the portfolio back when silver was trading around the mid-30s, and at that point it appeared extremely compelling. These days, though, conditions have shifted, and once you factor in after-tax risk-adjusted returns, La Preciosa struggles to stack up against our other possibilities, which are largely located in the Western United States and, to a smaller degree, in Canada. Those were among the considerations at play. Broadly speaking, Mexico has turned into a tougher place to operate a mine, or at least that's what we've encountered when it comes to permitting, security, corruption issues, and the rule of law. The VAT write-off wasn't the reason behind choosing to sell La Preciosa, but it has absolutely been an ongoing frustration and obstacle for us with SAT regarding those VAT refunds, dating back several years now, and that's been yet another drag. And then there's the matter of tax rates in Mexico more broadly compared to-
Mark Reichman
analystMm-hmm.
Mitchell Krebs
executiveSo, moving into other jurisdictions — and especially for us here in the U.S., where we're sitting on substantial tax loss carryforwards — there were many different elements involved in this. That includes the fact that it's mainly a silver asset. As things stand right now, we feel good about the metals mix we've got. I believe taking advantage of that infrastructure right next door at Avino is very logical, and hopefully it gives us a route to unlocking some value from La Preciosa earlier than we could if we went it alone.
Mark Reichman
analystThat's quite useful. Thanks a lot, Mitch.
Mitchell Krebs
executiveYeah, no problem.
Mitchell Krebs
executiveHey there, Ryan.
Ryan Thompson
analystHello again. Thanks for that update, Mitch. I've got one about Rochester. If we look at how things have been running lately, you're putting out roughly 700,000 to 900,000 ounces of silver, plus somewhere around 70,000 to 80,000 ounces of gold, across the last several quarters. You noted that the crusher has been tied up making overliner material for the expansion, among other things. Is it reasonable to figure that Rochester's output for the coming handful of quarters will rise somewhat, now that the crusher is freed up? What's the right way to think about this over, say, the medium term, prior to the expansion coming online?
Mitchell Krebs
executiveSure. I'll kick it off, and then Mick can add to it. Looking at the immediate future, in Q4, even with the record rainfall we just had up in Northern Nevada and California thanks to that bomb cyclone, we're pretty optimistic about this fourth quarter at Rochester, since no overliner is being produced and sent over to stage six. Compared with the recent quarters, it ought to be a pretty clean one. After that, as we move into the start of next year, the one item that shows up on my radar in answer to what you asked, Ryan, is installing those prescreens at the legacy X pit crusher. There will be some downtime tied to that. I'd guess early in the second quarter, in spring.
Mick Routledge
executiveYep, exactly.
Mitchell Krebs
executiveUm-
Mick Routledge
executive2022, correct.
Mitchell Krebs
executiveIf not for that, we'd be in a position to achieve somewhat greater sustained rates for throughput, for crushing, and for stacking, and ideally we'd keep seeing further gains from those interlift liners we installed, along with the MP1000 we brought in earlier in 2021 — sorry, earlier this year. And also those screens that we're going to install there in April of 2021, earlier in that month. That was a long answer. I'm not sure whether I offered you anything useful there. Mick, is there anything you'd like to add to that, or not?
Mick Routledge
executiveYes, absolutely. So the X pit will keep serving as a big-scale trial for Limerick, meaning we're picking up plenty of lessons along the way; throughout 2022 we'll keep fine-tuning the PSD and searching for the right trade-off between throughput and recoveries. The learning will carry on so that once Limerick is up and running we can get it dialed in, lowering the risk on that project and on how it performs; given all that, we anticipate some ups and downs during 2022. On the whole, things ought to be steadier at this point, since the infrastructure is now there, apart from that prescreen going in during Q2.
Ryan Thompson
analystUnderstood. That's really encouraging to hear, and I appreciate the extra detail there. Perhaps just one more from me. Mitch, I picked up on the fact that during your prepared remarks, you never mentioned that you'd be avoiding questions about Victoria. So maybe you could share where things stand right now regarding your current thinking on that investment.
Mitchell Krebs
executiveI do recall making that comment during the previous quarter, but I'm happy to take the question.
Ryan Thompson
analystYeah.
Mitchell Krebs
executiveRyan. No, thank you. Look, back in May we put $117 million into Orion as share consideration, and that has turned out well for us. Its value right now, I believe, sits at roughly $160 million. A nice gain, then — a solid return. Their share price has climbed a lot, whether you measure it across the past three years or just year to date, and I think it's up 50%. Since our purchase of the 18%, it's risen almost 30%. What's driven that, I'd say, is partly the ramp up at Eagle and possibly some speculation around their stock following our May acquisition of the 18%. They've stated openly, I know, that a soft process is underway. Even though we hold 18% and have a real interest, we aren't involved in it. Victoria remains, in our view, an appealing opportunity. It fits the strategy. Recently they released some strong third quarter production figures, we noted. Progress on the ramp up looks good. That's at least a few thoughts and my reaction to what you asked. Does that cover it?
Ryan Thompson
analystYeah, no, that's, yeah, that's fantastic. That's helpful context. I appreciate it. Perhaps I could just slip in one more brief question.
Mitchell Krebs
executiveOf course.
Ryan Thompson
analystCould we hear the latest on the Southern Nevada asset? That area has seen a fair amount of movement recently too. Just let us know what the current thinking and work look like there.
Mitchell Krebs
executiveSure. Hans, you're still with us, so if there's anything I leave out that you want Ryan to hear, jump in; we'll keep drilling at that site. Our land package is something we're very happy with. Anglo's purchase of Corvus strikes us as a strong sign that enthusiasm in that area is justified. That's all a single large system where our drilling is happening; drilling will stay a priority for us, though naturally we're quite keen on finding ways to partner with nearby operators so the pie grows as large as possible, sharing infrastructure, doing everything we can to get the most value. We're eager to have those conversations when the timing is right. For the moment, continuing to drill is the best move available to us. Earlier I noted that an exploration update will come out before this year ends, and it will include fresh results from that area. It goes without saying that our excitement hasn't faded and the potential there is substantial. It's a busy area. Right now it's likely the most thrilling exploration district in Nevada, and that's an excellent spot to be in; we know it well, and we're eager for it to turn into a more visible piece of our future pipeline.
Ryan Thompson
analystGreat, that answers everything I needed, Mitch. Appreciate it.
Mitchell Krebs
executiveAll right, sounds good. Actually, thank you, Ryan.
Mitchell Krebs
executiveAll right, then. Hey, I appreciate the solid questions and the time you've given us today. I suppose we'll do another call along these lines early next year. It's strange to hear myself say that. Wishing everyone a joyful holiday season. That feels odd to say, though I guess that's just where things stand on the calendar. May your holiday season be safe, happy, and healthy. Thanks for spending part of your day with us, and enjoy the rest of it.
Operator
operatorThat brings today's call to a close. We appreciate your joining this presentation. You're free to hang up at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Coeur Mining, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Coeur Mining, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Coeur Mining, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.