Coeur Mining, Inc. (CDE) Earnings Call Transcript & Summary
May 11, 2023
Earnings Call Speaker Segments
Mitchell Krebs
executiveHello, everyone. Prior to getting started, I'd ask you to take note of the cautionary language regarding forward-looking statements contained in today's slide deck, and to review the SEC filings posted on our website. I'll begin with the key highlights found on slide three, and after that I'll hand the call to Mick and Tom. We came in a bit above what had been expected, and the reason was robust beginnings to the year at Palmarejo, Rochester, and Wharf, which made up for a softer quarter at our Kensington mine. As we've noted before, weather and one-time payments tend to make the first quarter our weakest of the year. On the whole, we're still positioned to meet our guidance for the full year, and that guidance assumes a considerably better second half. The improved second half we anticipate comes largely from the ramp-up at our Rochester mine in Nevada following its expansion; construction there is still expected to finish around the middle of the year. Right now we're in the midst of the last quarter of heavier capital spending as we make the final push toward completion, and our balance sheet is in good shape to fund whatever spending is left. With the finish line at Rochester now visible, that marks an important inflection point for the company, since we expect capital outflows to shrink, silver and gold output to climb, and cash flow to start rising. The Rochester expansion has been a major investment for the company and will create one of the biggest open pit heap leach operations anywhere in the world. The team has performed remarkably, particularly given all they've had to work through. Work on the project began in May of 2020, moved forward during COVID-related restrictions, dealt with ongoing logistical and supply chain problems, contended with inflation at decades-high levels along with labor shortages, and more recently ran into one of the harshest winters Northern Nevada has seen in recent years. Even with all of that, the team reached mechanical completion at the Merrill Crowe processing facility ahead of schedule in the first quarter, and what's even more striking, the project is now nearing 2 million hours with no lost time incident. Let me spend a few minutes on exploration. At Kensington, the development and drilling program we launched in the middle of last year is still at an early stage, yet it's producing the results we wanted: adding near-term mine life, speeding up the pace of underground development, and pinpointing new targets for drilling down the road. After a striking 56% rise in gold reserves during 2022 that extended mine life by a year and a half, recent drilling points to additional extensions of several new zones at Upper Kensington, a good sign for further gains in mine life. Over at Silvertip, during the first quarter the team drilled the longest hole ever at that site, coming in at roughly 1 km. Looking at the results, especially over the last 250 m or so, we've observed more intrusive porphyry showing up, which points to a heat source being nearby. It's also worth noting that we're encountering indications of additional critical minerals — indium, germanium, and gallium among them — as we keep improving our broader geologic understanding of the deposit. We think the eventual size and character of the Silvertip deposit is really exciting and holds substantial potential value. That said, our immediate priorities are getting Rochester successfully commissioned and ramped up, producing free cash flow, and bringing down leverage on the balance sheet. We see this as the correct order of priorities, and it will allow the Silvertip team time to keep growing and gain a better grasp of this world-class ore body. Continued exploration wins at Kensington and Silvertip highlight how well our multi-year drilling programs have worked — programs into which we've put roughly $245 million across the last five years to lengthen mine lives and build a pipeline for future growth. That spending yielded about 2 million gold equivalent oz of reserves along with slightly more than 4 million gold equivalent oz of resources; those ounce additions, achieved at a moment when a large part of the industry was putting too little into exploration, amount to gains of 34% in reserves and 60% in resources. Before I hand things to Mick, let me briefly address the recent amendments to the Mexican Mining Law. We're still working through what the full impact will be. It has clearly provoked strong opposition and will probably face legal challenges. The changes seem to apply to new concessions rather than existing ones such as those at Palmarejo; as the regulations backing these changes take shape over the coming months, we will of course keep talking with the government. Let me also quickly note our newly released ESG report, which lays out the results we're delivering to preserve Coeur's standing as a leader in advancing environmental, social, and governance practices. I'll now hand the call over to Mick.
Michael Routledge
executiveThanks, Mitch. Before we get into how operations performed, I'd like to briefly build on what Mitch said regarding ESG. We never lose sight of our mission to seek a higher standard, and we remain dedicated to safe operations, best-in-class governance, responsible environmental stewardship, and cultivating solid ties with the communities in which we work. The figures contained in the most recent ESG report confirm that commitment. At Coeur, our three-year trailing average for Total reportable injury frequency rate fell 18% during 2022, reaching a record low. We delivered an 8.5% decrease in GHG emissions intensity against the baseline, keeping us on track to fulfill our stated target of a 35% reduction in net GHG emissions intensity by the close of next year. These milestones, along with numerous others achieved during the year, speak not only to our dedication to ESG principles but also underscore the overall enhancement across every aspect of our business. Shifting to our quarterly results, we're happy with how the year has begun and anticipate that the company's 2023 production will carry a significant weighting toward the second half, in line with the production guidance we gave earlier this year. We guided toward a seasonally weaker first half in 2023 for the reasons Mitch outlined earlier. Delving further into the quarter on slide six and beginning with Palmarejo. Output surpassed expectations during the quarter, owing to elevated silver grades and a particularly robust contribution from La Nación. Softer diesel prices, combined with mill feed optimization work that produced lower consumable usage, pushed operating costs down for the quarter. A strengthening peso created some upward cost pressure late in the quarter. On the whole, operating costs fell 10% for gold and 2% for silver. Palmarejo remains focused on mining and plant efficiency initiatives intended to cut costs further and boost recoveries while maximizing mining rates. Turning to Rochester, production that beat forecasts stemmed from the ongoing favorable residual impact of the solution breakthrough seen in the prior quarter, along with the continuing advantage of site slope irrigation on Pad IV. As Mitch noted, weather defined Rochester's first quarter. Rain, snow, and dramatic temperature fluctuations across the Western U.S. challenged the team from beginning to end. Going forward, we expect sustained strength in metals recoveries to counter reduced weather-related ore placement in the first quarter, which should keep Rochester on course for 2023 gains. Even with the weather, we kept placing additional ore on new Pad VI, with plans to place more than 2 million tons on Pad VI prior to commencing the pre-leaching process near the end of the second quarter, positioning the mine for a robust third quarter as previously covered. As the most recent photos of POA 11 construction show, the project is presently at peak activity levels. With mechanical completion of the new Merrill Crowe facility achieved, our attention now turns to ramping up the system, leading to first solution through the Merrill Crowe, anticipated around the close of the current quarter. Moving forward with the fresh crusher circuit is still our most important path item. Construction of steel and placement of equipment for the pre-screen is currently progressing nicely, and we continue making solid headway on building the conveyor, plus installing piping and electrical systems throughout the full crusher corridor, which stretches a mile. Bad weather impacted almost all parts of this project in the quarter, which limited how well the team could relocate machinery, supplies, and staff. Those problems have created certain strain on the total capital cost we expect, and we now think this project will land at the upper end of our guidance range, near $670 million. Every component and piece of material needed for assembling the crusher has arrived on-site, and we don't expect any adjustment to when the overall construction will finish. Shifting to Kensington, we saw a sluggish beginning to the year there, and having fewer drills, bolters, and less availability at the paste plant caused mine sequencing troubles, resulting in decreased gold output for the quarter. The team is effectively working to make up ground on paste placement, which is helping heading availability improve; we expect to recover the bulk of what was lost across the coming two quarters. Finally, regarding Wharf, performance came in somewhat better than planned, since quarter one gained from higher-grade material that was put in place sooner in the year. The crew at that site is excelling at keeping costs in check. Together with a drop in diesel prices, costs per own were below what we had projected. Since three mains are running well and Kensington is putting in strong effort to close the gap across the next couple of quarters, we stay at ease with our 2023 production guidance of 320,000 oz to 370,000 oz of gold along with 10 million oz-12 million oz of silver. Having said that, I'll hand the call to Tom.
Thomas Whelan
executiveThanks, Mick. I'll move rapidly through the first quarter's financial numbers, then give you a picture of where our finances stand as the Rochester expansion enters its final stretch. Slide four lays it out: gold output came in below the prior-year level, yet revenue ended up basically unchanged from the first quarter of 2022, since we got a lift from better metals pricing. Now to costs, on slide six — three of our four biggest cost categories showed evidence of softening, and that makes us hopeful inflation is at last cooling off. One more thing worth flagging: the first quarter's results include a pair of one-time annual payments adding up to $23 million, tied to the annual EBITDA mining tax in Mexico and the company-wide 2022 annual incentive payouts, and both of those weighed on our financial results. On to slide seven. We've said all along that this stretch at Rochester marks the point of maximum capital intensity. Right now we're at the peak of the peak — the most investment-heavy stretch — with close to $1 million spent per day at Rochester during the first half of 2023. As of March 31st, roughly $634 million, which works out to about 95% of total expected project costs, had been committed, and about $560 million had been incurred. Everything we've done over the past couple of years to proactively manage the balance sheet has gotten the company ready for this point. Slide 12 shows total liquidity of $382 million, plus we have a substantial layer of downside price risk mitigation in place for the rest of 2023 through our metals hedges. We're confident these moves give us the flexibility we need to finish the Rochester expansion while also moving forward other key near-term growth catalysts, such as the development and drilling program under way at Kensington. I'll hand the call back to Mitch now.
Mitchell Krebs
executiveThanks, Tom. Before we get into Q&A, I'd like to take a moment to walk through slide 14, which lays out what matters most to us for the rest of the year. After roughly 3 years of effort, we've finally reached the edge of a significant inflection point. Finishing the remaining work at Rochester safely and efficiently, then successfully ramping it up in the second half of the year, stands as our obvious and essential objective for the balance of the year. Beyond Rochester, we also have to produce results throughout the rest of the portfolio while putting money into high-value exploration priorities, particularly at Kensington, so that we're positioned for stronger returns as those new ounces get monetized in future periods. Over at Silvertip, we'll keep deepening our knowledge of this prospective deposit and try to grow it further in size before we take another look at the best way to unlock maximum value from that asset. Two last quick items. I'd like to point out that this year marks Coeur's 95th year since incorporation. Few companies are lucky enough to still be here celebrating 95 years. Coeur's lengthy history as an American mining company fills us with pride, and we're eager to see what comes next. One more celebration happening at the company this year: Wharf's 40th year of operation. A single employee, Mark Schmalling, has spent all 4 decades working at Wharf, so this year he marks his 40th work anniversary. Back in 1983, Mark held employee number one status at Wharf, right before the mine started operating with an initial mine life of 3 to 5 years. Jump to the present, and Wharf's mine life now sits at 8 years, 3 years more than when we bought it in 2015 from Goldcorp. Congratulations to Wharf and to Mark. Thank you; with that, let's go ahead and open it up for questions.
Mark Reichman
analystMorning — appreciate you taking my question.
Mitchell Krebs
executiveYes. Hello there, Mark.
Mark Reichman
analystFirst thing I want to ask about — you folks didn't give us any costs applicable to sales figures for 2023, at least where Rochester is concerned. Now that you've got roughly 3 months of Rochester under your belt and can look at those numbers, on an adjusted basis for both gold and silver, what's your thinking for the rest of the year regarding Rochester's costs applicable to sales, given what the first quarter showed?
Mitchell Krebs
executiveSure. The first quarter came in as planned. There's going to be considerable noise across the coming 2 quarters, and that's really what's driving the choice to hold off on issuing cost guidance for Rochester until this summer. Tom, could you walk us through a handful of those moving pieces — the noise you mentioned?
Thomas Whelan
executiveOf course.
Mitchell Krebs
executiveWhich is what we're going to witness over the coming two quarters in Rochester?
Thomas Whelan
executiveAbsolutely.
Mitchell Krebs
executiveMark, you should look for our guidance to come out together with the Q2 numbers. There are a couple of main things on our minds: specifically, the source of all the gold, and where Silvertip production will originate across the coming three quarters. To illustrate, a significant share of our gold is being recovered from Stage IV residuals — meaning the ounces and tons that were put down in the prior year. During this quarter, we're seeing a blend. About fifty percent of the tons were put on the former Stage IV leach pad, while the other fifty percent went onto the present Stage VI leach pad, which Mick is actively ramping up, pre-commissioning, and commissioning throughout the second quarter. Looking ahead, every ton we place will be going onto VI. Once more, keep in mind those ounces, or tons, will be originating from the Stage IV, ex-pit crusher. Naturally, near the middle of the year, once the entire package is finished, we'll begin to see tons arriving from the new crusher. So again, look for guidance — a complete guidance — to go along with the second quarter.
Mark Reichman
analystAll right, that's useful. I've got one more thing on that. When it comes to Rochester, and I realize, you know, sort of how this tonnage is being, you know, arranged and everything, we're going to see some unevenness in the quarterly figures going forward. Would you sort of anticipate that the third quarter will be your best one where Rochester is concerned? How are you sort of approaching the quarterly pattern versus the yearly guidance at Rochester?
Mitchell Krebs
executiveYeah, that's a fair question. Like Tom mentioned, the first quarter got a lift from some of that carryover coming off the old Stage IV. That's going to weaken somewhat in the second quarter. When we get to the third quarter, we'd anticipate a fairly solid jump upward as a result of starting to leach that new ore from VI, the recently stacked material on VI, which really ought to produce a higher — with the third quarter being the top quarter of the year, production-wise, coming out of Rochester thanks to that sort of early burst in ounces. At the same time, we'll be, sort of as fast and systematically as we can, increasing the crushing rates from the crusher over the latter half of the year to attempt to finish the year, you know, as near to that run rate of 30+ million tons per year for crushing and stacking. Mick, is there anything I left out that could assist in answering Mark's question?
Michael Routledge
executiveYeah, I mean, really it boiled down to completing the heap leach and Merrill Crowe builds and having them ready, pre-commissioned, and then we're looking at commissioning around the close of this quarter. That is what mainly drives the third quarter flush. At the same time, we keep moving forward with the crush at Corridor, and we're getting it set to begin delivering those tons. We'll have roughly 2 million tons in place when pre-leaching kicks off, and as we laid out in the materials, we're almost at that point today, and according to the plan we anticipate having about 3 million tons by the time we start up the Merrill Crowe. As of right now, everything is proceeding according to plan.
Mark Reichman
analystThat is quite useful. Many thanks.
Mitchell Krebs
executiveYes, Mark, I appreciate it.
Michael Siperco
analystAppreciate it, and thanks for fielding my questions, everyone. Perhaps I could just build on what was asked regarding the ramp up at Rochester. Perhaps I'm missing something. I do hear you saying Q3 ought to be the strongest — but if going forward, every bit of the ore sits on that new pad, wouldn't we anticipate a steady climb through the close of the year and then on into 2024? Where am I getting it wrong? My apologies.
Mitchell Krebs
executiveNo, that's fine. Mick, do you want to take that?
Michael Routledge
executiveWhile we're building the foundation of the heap leach pad, prior to starting operations, we need to place a coarser size fraction in it so the French drain functions properly. Essentially, several million tons of material get loaded there before any cyanide leach irrigation is applied. Once that process begins, you'll get a wave of extra ounces in Q3, though it will fall back as we complete construction of the crusher — the main crusher, the limit crusher — and then bring it in. As you know, any large scale capital project of this kind comes with a ramp-up curve. We anticipate driving up that ramp-up curve throughout the second half of the year. In doing so, more and more tons will be loaded onto the heap leach pad. That will build steadily, Michael, no question. We ought to see a lift in Q3. It'll dip back down somewhat, and then a gradual ramp up will occur through the end of the year and into 2024.
Michael Siperco
analystRight, so the leach cycle is quicker for that first material you're applying, and then, as it builds up, you'll move into what's more like the standard leach cycle. Is that how it should be understood?
Michael Routledge
executiveUsually, the greatest advantage from your material on the pad comes during the initial 60 to 90 days.
Michael Siperco
analystCorrect.
Michael Routledge
executiveYeah, that's going to apply to every bit of the material we've put down. When things are running as usual, you'd be laying that down on an ongoing basis, and then watching each of those blocks come off. Here, everything goes in prior to us beginning. It all hits you in one go, and after that, you're back to the standard cycle.
Michael Siperco
analystAll right, all right, that’s clear. Thanks for that. If I can pivot for a moment and ask about liquidity. It’s very clear in the presentation, based on my calculations and I think obviously yours too, that you have plenty of capacity under the facility and cash available to finish Rochester and the ramp-up. Could you just remind us of any important covenants tied to the facility? Anything that might stop some kind of drawdown in a worst-case situation? And any other levers you could choose to use, or might want to use soon, regarding the balance sheet?
Mitchell Krebs
executiveThat's not a bad question at all — it's a reasonable one. Like you pointed out, Mike, where we stand right now, we feel fairly at ease about the balance sheet given our position at Rochester. To bring everyone up to speed, that revolver comes in at $390 million. Against it sit $30 million of LCs, so that leaves $360 million in capacity. When the first quarter closed, we had 60 drawn, meaning $300 million remains available. The covenant that really matters here is the net debt-to-EBITDA ratio of 4.5x. We do have some cushion as we work through what is genuinely this pivotal quarter right now, before things begin stepping down in the second half of the year. As for other levers available to us, the hedging we've put in place has served as a genuinely important risk mitigant. There are additional items too — we've executed some opportunistic exchanges on certain senior notes as they traded lower. That opened a window for inbound holders seeking liquidity on those notes. We completed only a modest number of those, I believe right after the first quarter ended. That illustrates these incremental tools we still possess at this point, which we need to keep managing in a comfortable manner through this critical final quarter. Tom, is there anything I missed that you'd want to add?
Thomas Whelan
executiveYeah. No, no.
Michael Siperco
analystOkay, great.
Mitchell Krebs
executiveGreat.
Michael Siperco
analystPerhaps, if I may pivot once more, I swear I'll hand it over after this; regarding Kensington, you touched on some of what hurt output during the quarter. Could you discuss what the remedy looks like? Is there anything further that has to be done? Are additional machines needed? Does development call for extra time? Was it simply that availability which weighed on throughput? What's your expectation for how output will build through the remainder of the year, consistent with guidance?
Mitchell Krebs
executiveYeah. Mick, do you wanna answer Mike's question?
Michael Routledge
executiveYes. Absolutely, you've identified it correctly—most of those effects stemmed from the way we framed things in the documentation. The real offset, though, is what we mentioned regarding this multi-year development initiative through which we intend to extend the life of Kensington, and we're bringing in certain development contractor groups to assist with that effort early in the year. As you're aware, getting new personnel integrated occasionally requires some time, so it took them a bit of time to get going and build momentum, but we wanted that done in a very safe and very effective manner. At this point we're seeing them fully integrated, and they're completing the work according to the plan. That represents a significant offset for us going forward, since as they develop, they're advancing toward zones that could deliver extra stocks and opportunities for us across the year to recover and return to that plan for Kensington.
Mitchell Krebs
executiveTo add on to what Mick said, Rochester clearly draws plenty of focus as a catalyst for growth in the near term, and rightly so. A great deal is happening at Kensington when it comes to that development and drilling program. My sense is that we're invested. This year, Kensington represents the biggest slice of our exploration budget. A sizable amount of underground development capital is involved, and that genuinely positions Kensington as a medium-term catalyst of that sort for us. Near-term growth will certainly be substantial out of Rochester, no question. As we keep carrying out that program at Kensington, continue adding to that mine life, and open up further underground flexibility and working areas, Kensington will arrive following Rochester and create a pleasant medium-term wave of growth from that asset. Plenty is happening up there, with many moving pieces, just as Mick was hinting at.
Michael Siperco
analystAlright. Alright, that's good. Over the short term, what you're observing in, I guess, April and May gives you confidence in that guidance figure for the entire year. Would that be a fair way to put it?
Mitchell Krebs
executiveThose difficulties were still affecting April. Our expectation is that once we move through the latter half of this quarter, and then through Q3 and afterward, that's when we'll truly begin to see ourselves making up that ground. Is that a fair way of putting it?
Michael Routledge
executiveYes, definitely. During the coming two quarters, and naturally, thanks to the strength of our portfolio, Rochester is performing very well. We're making progress, and we will maintain a solid mix of attention among the locations, to help Kensington climb back up that curve.
Michael Siperco
analystOkay, fantastic. Thanks again for taking my questions.
Mitchell Krebs
executiveNo, thank you, Mike. I appreciate that.
Mitchell Krebs
executiveAlright, well, we're grateful that all of you could join us this morning. Thanks, and we're looking forward to talking with everyone once more this summer, when we'll go over what we report for the second quarter. Thanks once more, and enjoy the rest of your day.
Operator
operatorThat wraps up this conference. We appreciate you joining us for today's presentation. You're welcome to hang up at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Coeur Mining, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Coeur Mining, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Coeur Mining, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.