Compañía de Minas Buenaventura S.A.A. (BVN) Earnings Call Transcript & Summary

April 28, 2023

New York Stock Exchange US Materials Metals and Mining earnings 36 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, ladies and gentlemen, and welcome to the Compañía de Minas Buenaventura First Quarter 2023 Earnings Results Conference Call. [Operator Instructions] And please note that this event is being recorded. I would now like to introduce your host for today's call, Mr. Gabriel Salas, Investor Relations. Mr. Salas, you may begin.

Gabriel Salas

executive
#2

Good morning, everyone, and thank you for joining us today to discuss our first quarter 2023 results. Today's discussion will be led by Mr. Leandro Garcia, Chief Executive Officer. Also joining our call today, and available for your questions, are Mr. Daniel Dominguez, Chief Financial Officer; Mr. Juan Carlos Ortiz, Vice President of Operations; Mr. Aldo Masa, Vice President of Business Development and Commercial; Mr. Alejandro Hermoza, Vice President of Sustainability; Mr. Renzo Macher, Vice President of Projects; Mr. Juan Carlos Salazar, Geology and Explorations Manager; Mr. Roque Benavides, Chairman; and Mr. Raul Benavides, Director. Before I hand out our call over, let me first touch on a few items. On Buenaventura's website, you will find our press release that was posted yesterday after market close. Please note that today's remarks include forward-looking statements that are based on management's current views and assumptions. While management believes that its assumptions, expectations and projections are reasonable in the view of the currently available information, you are cautioned not to place undue reliance on these forward-looking statements. I encourage you to read the full disclosure concerning forward-looking statements within the earnings results press release issued on April 27, 2023. Let me now turn the call to Mr. Leandro Garcia.

Leandro Raggio

executive
#3

Thank you, Gabriel. Good morning to all, and thank you for attending this conference call. We are pleased to present the results for the first quarter 2023 from Compañía de Minas Buenaventura. We have prepared a PowerPoint presentation, which is available on our web page. Before we go further, please take a moment to review the cautionary statement shown on Slide #2. Moving on to Slide 3. Highlights were as follows: First quarter '23 EBITDA from direct operations was $51.6 million compared to the $86.9 million reported in the first quarter of '22. EBITDA results do not include $300 million from the sale of Buenaventura's stake in Yanacocha. First quarter '23 EBITDA, including associated company reached $181.9 million compared to the $233.7 million in the first quarter of '22. Again, EBITDA results do not include the $300 million from the sale of Buenaventura's stake in Yanacocha. First quarter '23 net income from continuing operations reached $72.2 million compared to USD 134.7 million net income from continuing operations for the same period in 2022. El Brocal ore mine from its open pit was stockpiled during the first quarter of 2023 and was not treated during the quarter. Underground mine production increased to 9,350 tons per day during the first quarter '23, compared to the 7,100 tons per day in the first quarter 2022, as part of the ramp-up to reach 10,000 tons per day during 2023. This stockpiled lead and zinc ore will be treated at El Brocal's processing plant in the second quarter of 2023. Buenaventura's cash position reached $173.5 million as of March 31, 2023. Net debt increased to $556.8 million with an average maturity of 3.1 years. First quarter '23 capital expenditures were $36.2 million compared to $19.9 million for the same period in 2022. First quarter 2023 CapEx includes $9.7 million related to the San Gabriel project and $8.8 million related to Yumpag project. On March 24, 2023, Cerro Verde announced a total dividend distribution of $250 million. Buenaventura will receive $49 million relative to its stake in Cerro Verde on April 28, 2023. During the first quarter of this year, operations at Julcani were suspended for 10 days in February 2023 related to antigovernment protests, which adversely impacted production and mine development. Operations were fully reestablished on February 16, 2023. The company plans to recover this production in subsequent quarters and expect to meet 2023 production guidance. Moving on to Slide 4, our financial highlights. Total revenues during the first quarter were $186 million, which is 20% lower in the comparison to the first quarter of 2022. As we mentioned before, our EBITDA from direct operations for first quarter 2023 was $52 million in comparison to $87 million during the first quarter of 2022. Again, these figures exclude the Yanacocha transaction effect. Also, our net income from continuing operations for the first quarter of 2022 (sic) [ 2023 ] was $73 million in comparison to a net income from continuing operations of $135 million during the same period in 2022. The CapEx increased to $36 million in the first quarter of 2023 compared to the $20 million in the first quarter of 2022. Moving on to Slide 5, attributable production. Total gold attributable production in the first quarter of 2023 was 39,000 ounces, 21% lower than the figure reported in the same quarter of the previous year. This decrease is mainly explained by La Zanja mining operation suspension since the fourth quarter of '22, and lower production at Coimolache, as mining and ore, stockpiling were temporarily suspended in the fourth quarter 2022. Silver attributable production for this quarter was 1.1 million ounces, which shows a decrease of 38% compared to the figure reported on the first quarter of 2022. This decrease in production was primarily due to the El Brocal underground mine being the sole producing mine during the first quarter of 2023, as with the adverse impact of the 10-day suspension of activities at Julcani due protest, as described. Finally, our copper attributable production for the first quarter of the year was close to 29,000 metric tonnes, a 7% increase compared to the same period in 2022. Moving on to Slide 6, all-in sustaining cost and cost applicable to sales. The all-in sustaining cost from our direct operations in the first quarter of 2022 -- 2023, sorry, increased by 44% to USD 1,924 per ounce of gold. The cost applicable to sales for the first quarter of 2023 were as follows: For gold, USD 1,124 per ounce, which is almost equal to a year ago; for silver, USD 21.5 per ounce, which is 41% higher than a year ago; for lead, USD 1,394 per metric tonne, which is 1% higher than a year ago; for copper, USD 6,738 per metric tonne, which is 2% higher in comparison to a year ago. Finally, in the case of zinc, the cost applicable to sales was USD 1,966 per metric tonne, which is 31% lower than a year ago. Moving on to Slide 7, our pipeline of projects update. Here, we are presenting in one snapshot the current development level for each of our projects. Moving on to Slide 8, our projects. In the case of Yumpag, our Brownfield project, we are focused on development of main ramps and exploration tunnels. Updated geological model suggests the opportunity to increase minable grade with less mining development. Environmental permit for underground exploration granted in February 2023. The environmental permit for mining expected on May 2023. In the case of San Gabriel, our greenfield project, we have finished the organic contract. The beta is to start in May, and definite campsite to start in July. Authority admitted the power line Environmental Impact Assessment, currently programming the third workshop by the third quarter of 2023. Working with the regional government on road maintenance and right-of-way, which we have reached an agreement with Corire community on oil transport fees. Thank you for your attention, and I will hand the call back to the operator to open the line for the questions. Operator, please go ahead.

Operator

operator
#4

[Operator Instructions] Our first question today comes from Carlos De Alba from Morgan Stanley.

Carlos de Alba

analyst
#5

First question is at El Brocal, the stockpiles that you accumulated in Q1, how much under your process this quarter -- you are processing this quarter? Can you offer some color as to how much volumes of lead and zinc will be sold during the second quarter from these stockpiles? Or would you really expect to see the volumes really coming only in the third quarter, given that the processing will take place during the second quarter? And my second question has to do with the balance sheet and the free cash flow. The free cash flow in the last several quarters has been, for the most part, negative, and your debt has increased. Net debt has increased and the maturity is only 3.1 years. And so how do you -- how are you going to address this situation? We're getting more and more questions from investors that are concerned about the balance sheet. And Cerro Verde is paying dividends, but probably not as much as we would have thought. So yes, just any comments maybe, Daniel, on how you're going to address the situation. What are the plans that the company has in order to improve the balance sheet, that would be great.

Leandro Raggio

executive
#6

Thank you, Carlos, for your questions. First, in terms of El Brocal, maybe Juan Carlos will give more color to the answer. But the thing is, the order that we have the stockpile there, we have a plan to pass through the plant during the year. In terms of the free cash flow, we have some strategies of how to pass this negative quarter in terms of free cash flow. However, this third quarter has been characterized because of the using of working capital. We have used more working capital. We have not treated the ore, for example, in El Brocal. And that -- Daniel will give you, for sure, more information about how -- which are our -- the strategies for this coming year and all the projects we have in a row. And finally, the dividend of Cerro Verde, we already have received the first part of the dividend. We expect, for sure, during the year, normally, Freeport declare dividends one in March and the second as an advance in October. So we should expect an additional dividend during the year. Please, Juan Carlos, if you can give more color to Carlos.

Juan Ortiz Zevallos

executive
#7

Sure. Sure. We end up the first quarter of 2023 in El Brocal with an average of 200,000 tons of ore in a stockpile. The focus was on stripping the properties of this phase that we are mining in the open pit. In the coming quarters, we will increase that volume [ loss ] of stockpile up to around 1 million tons in the third quarter, and then coming down by the end of the year to finalize this year with around 400,000 tons of ore in a stockpile. By the first quarter of 2024, we will complete the processing of this material. The material is mainly polymetallic with some areas that contain copper. Because we're getting closer and closer to the underground mine that is mainly copper. This is pretty much the same transition that we see in the open pit. The volumes of zinc and lead that we are going to be producing are in line with our guidance for the year. So it's only the sequence of mining up to September and the sequence of processing, all the way down to the last quarter of this year and first quarter of 2024. So at the first quarter of 2024, we will finalize the processing of the outstanding stockpiles all from the open pit in El Brocal.

Daniel Dominguez Vera

executive
#8

The second part of the -- answer of the question from Carlos. Thank you, Carlos, for your question. Yes, temporarily, we are having a deterioration of our leverage ratio. It's over 3x right now. But we believe this will be reducing in the following quarters when we have a better EBITDA. During last year, the second EBITDA of 2022, which is counted within the period of this ratio, we had a very low EBITDA. And we believe in the second half -- second quarter and the third quarter, with El Brocal improving operation with -- after treating the stockpile that Juan Carlos mentioned, we are going to recover the EBITDA. Meanwhile, to be able to fund Yumpag and San Gabriel, we are going to use our own cash. But also, we are going to raise a temporary facility that we have already committed with local banks. This could be up to between $50 million and $100 million. This will permit us to fund temporarily our obligations in Yumpag and San Gabriel. And we will see if we need to extend this -- the maturity of this loan. However, we believe that with the dividends from Cerro Verde, that we will receive at the end of the year, after starting Uchucchacua and Yumpag in the third and fourth quarter, we will be able to finish the year with a leverage ratio of below 3.5x. For next year, we're having Uchucchacua and Yumpag working full capacity and a better -- and having a better EBITDA, we think that the leverage ratio should go down to levels of 3x.

Carlos de Alba

analyst
#9

And just one question on the working capital in the quarter. Leandro alluded to that. But actually, the biggest negative impact that we can see is not on inventories. It is on trade and other accounts payables, almost $80 million negative impact. Any particular reason why such a big delta in that line?

Leandro Raggio

executive
#10

Yes, Carlos. As you remember, last year, we experienced the same situation. In December, we registered a big amount of bills from contractors, basically at El Brocal and Tambomayo. These were registered at the end of the year and were paid during the first quarter of the year. So this is a temporary effect as well.

Operator

operator
#11

And our next question comes from Tanya Jakusconek from Scotiabank.

Tanya Jakusconek

analyst
#12

I actually have 3. Just for Daniel, can -- Daniel, I know at your Investor Day and your materials, you gave guidance for Cerro Verde dividend to be about $120 million per annum for you for the next sort of 3 years. Is that still a good number for us to use?

Daniel Dominguez Vera

executive
#13

Yes, Tanya. We think that with the levels of the copper price right now, Cerro Verde is generating a very important cash flow. We believe that the amount of dividend should be between $100 million and $120 million per year.

Tanya Jakusconek

analyst
#14

Okay. And then, Daniel, there's been no change to your capital cost guidance that you provided earlier this year?

Daniel Dominguez Vera

executive
#15

Not at this point in time. We are still evaluating any effect at San Gabriel. But at this point in time, we maintain the same level of CapEx for this year.

Tanya Jakusconek

analyst
#16

Okay. So can I just come back to San Gabriel? And then my final question is actually back to El Brocal. But just on San Gabriel, you mentioned that we have -- so you've done the camps. You're doing the power line EIA. And then we have the third workshop. I thought we were totally permitted on this project. Can you remind me what the third workshop is? And am I getting a permit with this third workshop? I'm just very confused.

Leandro Raggio

executive
#17

Thank you, Tanya, for your question. The permit we mentioned last year was the construction permit. But well, here with us is Renzo Macher, our Vice President of Projects, so he can explain in detail the following part.

Renzo Macher

executive
#18

Yes. So as Leandro were saying, we do have the construction permits and environmental permits for the mine. What we are talking here is about the permit for the power line. We do have -- the process of this is, first, we get all the land. We already have all that. We have the design ready done, and now it's about the environmental impact assessment of the line, which is different than the environmental impact assessment for a mine. So it's a different regulation. So it's 2 different permits.

Tanya Jakusconek

analyst
#19

Okay. Sorry, I misunderstood. I had assumed we had all of the permits to go. So this is just a power line permit and that you're doing the consultation with the communities, is how I'm understanding it. And that's going to be happening in Q3 '23. When are you expecting the power permit then?

Renzo Macher

executive
#20

All right. [ After that ] -- that's a different regulation, yes. Towards the end of the year, we're going to have the construction permit for the power line.

Tanya Jakusconek

analyst
#21

Okay. All right. Is that the last permit I need? Because you have the construction, you have the environmental. This power permit, is that pretty much it in terms of the big permits?

Renzo Macher

executive
#22

Yes. There's a lot of operation permits, small permits and -- yes, but the biggest one, yes.

Tanya Jakusconek

analyst
#23

Yes. No, I understand the permits here and there, but the bigger ones. Okay. And is the power line permit on the -- a critical on the time line to get into production by mid-2025?

Renzo Macher

executive
#24

No, it is not.

Tanya Jakusconek

analyst
#25

No?

Renzo Macher

executive
#26

No. No, we do have like a 6-month lead in there, free time.

Tanya Jakusconek

analyst
#27

Okay. So you could start up with generators as sort of what I understand?

Renzo Macher

executive
#28

Yes. It is always optimal to do it with the power line, but yes.

Tanya Jakusconek

analyst
#29

Yes. Okay. for sure, for sure. Okay. And then maybe for Daniel, again. Sorry, Daniel. Just my understanding on El Brocal and how we should model it in our model, so I get the right cash flow coming out of this asset for you. Should I just be thinking this year like until Q3, we are mining like the copper from the underground? And then the lead and zinc stockpile, which you're increasing the stockpile from 200,000 tons to 1 million, should I be thinking that, that then starts to -- majority of it gets -- come off in Q4? So that get processed, and revenue comes in Q4 and Q1 of next year. Is that the majority of the revenue coming out from that stockpile, and the copper just comes and goes through this year? So 2 things. Copper's revenue coming through the entire year, where the lead and the zinc is coming in Q3 -- sorry, Q3, Q4 and Q1 of next year. Is that how I should think about it?

Leandro Raggio

executive
#30

Yes. Maybe Juan Carlos can explain the process of how we are going to explore work with El Brocal. Please, Juan Carlos.

Tanya Jakusconek

analyst
#31

Just so I know the revenues and the cash flow is coming through quarterly.

Juan Ortiz Zevallos

executive
#32

How can you apply that, Tanya? The processing of the polymetallic core is starting now in April. The speed at which we are mining is higher than the processing rate. That's the reason that we are start building up some additional stockpile. But at the same time, we are processing the ore. In that situation, we will reach a peak of about 1 million tons of stockpile by the third quarter, then we stopped the mining of the open pit, and we start processing the outstanding stockpile. And as I mentioned, that the stockpile will be completely processed by the first quarter of 2024. But we started now in April. We started the processing of the polymetallic ore. So the revenue coming from the zinc and lead concentrates is starting now in April, and it will continue up to the first quarter of next year.

Tanya Jakusconek

analyst
#33

Okay. Okay. And that's -- if the lead and zinc is already in your 2023 guidance you gave us in your prerelease, so I should think about that lead and zinc, whatever the guidance is, to be now sold from Q2 to year-end.

Juan Ortiz Zevallos

executive
#34

That's correct. That's correct.

Tanya Jakusconek

analyst
#35

Okay. That makes sense to me. I really appreciate you taking my questions.

Operator

operator
#36

[Operator Instructions] Our next question is a follow-up from Carlos De Alba from Morgan Stanley.

Carlos de Alba

analyst
#37

Just on Yumpag, if I may ask. Where do you guys stand in terms of the permits? And what is sort of the deadline that you internally have to receive these permits and still be able to ramp up the operations in the fourth quarter or start ramping up the operations in the fourth quarter or later this year?

Leandro Raggio

executive
#38

Carlos, let me ask you which permits do you refer? Yumpag? Uchucchacua?

Carlos de Alba

analyst
#39

Uchucchacua, really, Uchucchacua.

Leandro Raggio

executive
#40

Okay. Okay. Well, maybe Alejandro -- we are in line what we have talked -- explained to the market. We are in line with our times. But however, Alejandro can give you the details of which will be the time frame of -- in order to restart Uchucchacua and begin Yumpag. Please Go ahead, Alejandro.

Alejandro Hermoza

executive
#41

Yes. Thank you, Carlos. Okay, we have 2 different situations. Uchucchacua has no major issues in terms of permits. We just have to, on due time, do the procedures to restart the operations. So that's not a major issue. On the Yumpag side, what we have -- we're on the final stage of getting the approval for the environment assessment study that the main environmental permit that we have. And we should be able to get that approval. We should have gotten already, but we should get it by May. Within May, we should get that approval. After that, we need to go into the Ministry of Mines to get the construction permit. And it should take us a few months, a few months more. It's just an issue of bringing all the facts together, and we should have a permit for the first phase of the project that would be by the -- on time as it was scheduled.

Carlos de Alba

analyst
#42

Okay. And sorry, just, when would you expect to get the construction permit for Yumpag?

Leandro Raggio

executive
#43

Juan Carlos?

Juan Ortiz Zevallos

executive
#44

Yes. We expect to have the -- we already are developing the mine, Carlos. We are running the ramps, running the accesses. With the license that we expect to have in May, in 4 or 6 weeks down the road, we will start to develop the ore body. In May, we will start hitting the ore body and start making gallery through the ore bodies. They are very high-grade areas, about 20 to 25 ounces of silver. So we will start developing that. In order to transport the ore from the Yumpag area, first kilometers to the processing plant of Uchucchacua, we'll need an additional permit. And we expected to have it by the end of this year, 2023, or the first quarter of 2024. Of course, we are doing our best to try to speed it up and try to get the permit by the last quarter of the year 2023. So to put this 23, 25 ounces of silver into our balance sheet by the end of the year. That's Yumpag. And in parallel, we are doing some development -- new developments underground in Uchucchacua mine to access new areas that we have discovered in the last 12 months, 18 months. And there are a different blend of silver, lead and zinc, more now into the -- probably seeing lead than silver. So more polymetallic ore, good value. And probably, we will start -- we are doing now the developing of these stocks. We are producing some small stockpiles of ore so far. And we expect to start the production of the processing plant in Uchucchacua by October. So pretty much the 2 operations, Yumpag and Uchucchacua, by the end of the year, we start turning into production.

Carlos de Alba

analyst
#45

And just one, just to clarify, the construction permit in Yumpag that you still need is really just for the transportation of the ore to the Uchucchacua plant?

Juan Ortiz Zevallos

executive
#46

Yes. It's a permit actually for -- because of the -- we have all the permits for the mine development, for the camps, for the power line for the access road is ongoing, is mostly done. But for transportation between the Yumpag site to the processing plant of Uchucchacua, 12 kilometers along the highway, we need to get an additional permit and also for processing and commercialization of the concentrate that we'll be producing. So that's the final permit that we will require to put them officially into production.

Leandro Raggio

executive
#47

Carlos, let me add that we are somehow more positive with the government attitude for the permitting. We think they have identified the bureaucracy and the difficulties the mining industry is facing these days. And they are somehow involved and very worried, and they're trying to do their best to accelerate all the permitting. So we are very optimistic that we are going to be granted of all the permitting we need to continue the operations and restart operations and start the Yumpag, okay?

Operator

operator
#48

And ladies and gentlemen, that will conclude today's question-and-answer session. I'd now like to turn the floor back over to Mr. Garcia for closing remarks.

Leandro Raggio

executive
#49

Thank you. Thank you for attending this conference call. I have to mention that yesterday we have our seventh anniversary as Compañía de Minas Buenaventura. And we are very proud to be part of this family. And we have to go further with our efforts to getting all our projects and all our work for our company, for our collaborators, for our contract. Thank you very much, and have a good day.

Operator

operator
#50

Ladies and gentlemen, that will conclude Buenaventura's First Quarter 2023 Earnings Results Conference Call. We would like to thank you again for your participation. You may now disconnect your lines.

For developers and AI pipelines

Programmatic access to Compañía de Minas Buenaventura S.A.A. earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.