Core Lithium Ltd (CXO) Earnings Call Transcript & Summary
October 14, 2026
Earnings Call Speaker Segments
Operator
operatorGood day, and thanks for joining the Core Lithium September Quarter Investor Call. Paul Brown, our Managing Director, is the presenter for today. Paul will deliver a short presentation, and after that there will be a Q&A session at the end. <<operator_script>> A copy of today's presentation is available on the ASX as well as the Core Lithium website. With that, I'll hand things over to Paul.
Paul Brown
executiveThank you so much, and good morning to all of you. James Virgo and Chelsea Bates are here with me as well. We'll gladly field any questions once the presentation wraps up. But once again, thank you for being here. It was an extremely active quarter for us. We're genuinely pleased and proud to release our results today and to walk everyone through things in greater detail shortly. Here's a quick refresher on a few of the project's main attributes. Our mine life is long. Funding is complete. Infrastructure is already in place, and we hold several avenues of growth optionality. The operating plan calls for 1.2 million tonnes of throughput and nameplate production of roughly 250,000 -- 257,000 tonnes of SC5 concentrate. We've also made a change since the previous presentation. So we now report on an SC5 basis instead of an SC6 equivalent, as you'll notice in the green highlight. As I said, our funding is complete. That point matters, I believe. We've discussed it a number of times. And clearly, given today's market conditions, it really underscores the initiative we took last year while we were working through our funding process. Our goal was always to be fully funded.
Paul Brown
executiveSo I'm glad to report that we've hit that target, and now we're fully focused, heads down, working hard on the project. So we had $244 million in available sources along with $157 million of restart capital spend. The remaining spend, with free cash flow, will also come out of Grants once we begin shipping. The stage restart brings together near-term output from Grants, where we're developing BP33 alongside the Carlton deposit in reserves plus exploration upside, which we'll discuss with Blackbeard. So we're carrying out both — across both operations and the development of BP33. This quarter was a major milestone in our shift to operations, with plant commissioning underway and first spodumene concentrate produced, and clearly we're on track to reach our next big milestone, which is shipping in the December quarter. BP33 underground development and surface infrastructure keep progressing, with first development ore on track for mid-calendar year '27. We closed the quarter, as I mentioned, with $244 million in available funding, including cash receivables and Tranche 2 of our senior secured, with remaining restart capital of $157 million, which leaves a substantial liquidity buffer, and that's pleasing. Our restart plan hasn't changed since FID. So the scheduled production plan and capital assumptions are still unchanged.
Paul Brown
executiveAll of our key early milestones have been met — securing funding, announcing FID, the contract award, starting mining, beginning development, and producing our first concentrate. The very next milestone is the first shipment of Grants in the December quarter. And clearly, our attention is on the underground development that's ongoing and, naturally, the exploration work currently taking place out of Blackbeard. BP33 development is still on schedule for first development ore in mid-calendar year '27, with steady-state production to follow in mid-calendar year '28. There are some genuinely strong images here, I think. These images show the physical progress made at Grants since FID in late March. And again, we brought NRW on board in May. So considerable advancements have occurred at Grants. That progress speaks to how quickly we mobilized and the team's focus. So we're really pleased with what's been achieved at Grants. Here's another great picture, I think. Our board and some investors were on site, I believe, when we crushed our first ore a few months back. You'll see it in the picture there — we're well advanced on Grants ROM delivery and, obviously, crushed material. But this image, I think, shows the physical progress we've made. And again, we're really pleased to be executing to plan there.
Paul Brown
executiveTurning now to the DMS plant. There has, of course, been plenty of activity in and around it as we approach our first concentrate. I'd like to give a shout out to the team there for a very safe and well-executed upgrade. You can also see the middle image, which shows the last piece of plant we'll install later next year. That's the long lead item for tails capture. But once more, the plant overall, aside from the reflux classifier, has been fully upgraded, and commissioning is well advanced. So here are another couple of good images. These were actually taken on site last month, but you'll see that spodumene is being produced. It looks fantastic. From the moment we turned the plant on, it performed really well after the upgrades. You'll see the picture with the spodumene in the hand there. It's lovely, clean, lovely, glowing green, clean spodumene. So again, really pleased with how the plant is performing and importantly, looking forward to the September quarter -- sorry, the December quarter when we ship our first concentrate. So just moving to BP33. Again, you'll see the aerial image there. And again, just a shout out to the team that is developing BP33.
Paul Brown
executiveSo Develop Global is in the mix there — Beament's team. I mean, the progress being made there has us absolutely delighted. That was definitely among the larger calls we made when we went into FID and past it. The fact that the crew got moving fast and safely, cut our first portal, and clearly the development and the decline are on schedule — we're thrilled about all of that. So the calibre of people who've shown up there has us genuinely pleased. I think there's a lot of talk from us about how tough inflation and skills are in the market. And happily for us, Beament has — he's got a fantastic team ready-made. He runs multiple operations he can draw skills and equipment from, and the relationship we've built there is something we're really enjoying. Once more, that area and the development couldn't make us happier. There are some photos, obviously, of the site too. We've clearly pushed infrastructure along quite a bit. You'll see offices, workshops. We've also got <<inaudible>> on site doing the vent raises. So again, associated infrastructure keeping pace with the development. The progress in these areas has me really pleased as well. So look, we did just put out a result from an exploration perspective at BP33. So again, the program has us really pleased, even though only one hole was released, but the thinking there was that there could be some additional mineralization at the depth we've drilled there.
Paul Brown
executiveAnd of course, we hit roughly 34 meters grading 2.09% lithium oxide, plus another 3.43 meters at 2.44%. So there's substantial high-grade material established at depth. And of course, these results strengthen our confidence in the quality and continuity of the mineralization past the 10.5 million tonnes of resource we already have. Three more holes are still planned. We clearly haven't finished those yet. They're deep holes, but of course, those holes are meant to test the extension down dip and along strike, which supports the potential for future mineral resource growth or a possible upgrade. So turning to Blackbeard. We've got a program of about 12,000 meters planned at Blackbeard because of the, I suppose, the extensive wet we did get in there a bit later than we'd have liked, but the program is still on track. And like I said, we're drilling roughly 12,000 meters. The point of this really was to figure out what might be below the ground. Of course, in the past, we've had an exploration target of roughly 7 million to 10 million tonnes at a reasonable grade, 1.5% to 1.7%. We've only drilled this area to about 200 meters. So of course, this program is meant to go quite a bit deeper, and also, we've only used RC.
Paul Brown
executiveWhat we're doing is a mix of RC plus a bit of diamond drilling. Strategically, I'd say this still represents quite an appealing growth option for us. It sits within 20 kilometers of infrastructure we already have. And like we've mentioned, we hold a reasonable expectation there given the exploration target we published earlier. So drilling continues. We'll keep drilling until the wet arrives. And clearly, we intend to release some results before long. So we're eager to update everybody once those come through. I'll pass things to James now. He can walk us through the quarter and the cash flows and add a little more color on how you're viewing our funding stack.
James Virgo
executiveThanks, Paul. Now on to cash flow. We closed the September quarter holding $200 million in cash, which was up from $182 million at the end of June. In the course of the quarter, we brought in $98 million net of costs — that breaks down as $62 million from convertible notes and $36 million from the senior debt facility. On the outflow side, capital expenditure came to $51 million, mainly tied to the BP33 underground development, the infrastructure that goes with it, and upgrades at the processing plant. We also put $30 million toward site operating costs as mining and processing activities at Grants ramped up ahead of the first shipment in the December quarter. That sits alongside corporate costs, exploration expenditure, and the transaction costs tied to the funding package. Looking ahead, we have $244 million in available funding, which includes undrawn debt and receivables we expect to collect. Importantly, our September quarter cash flow doesn't yet reflect any revenue from near-term production at Grants — roughly 134,000 tonnes of SC product — with the first shipment still on track for the December quarter. Taken together, this gives us a strong funding position to carry our development program through to steady-state production in 2028. I'll hand back to Paul.
Paul Brown
executiveThanks, James. Honestly, I think this slide is great. It was really nice to be able to start the quarter this way. And as you can see, we're carrying out our plan. As James said, the funding package — we're very happy to have gotten that done. And clearly, the costs on those structures are extremely, extremely competitive. And we've definitely got a strong, very supportive funding package led by a consortium with Glencore, InfraVia and Nebari. So look, the — as I said, the funding package, major contracts, logistics chain, portal cut, initial plant upgrades and first concentrate production have all been delivered. And again, we — this has been our goal. We want to build market confidence and do what we say we'll do. Right now, activity is centered on Grants mining, plant optimization, BP33 development, infrastructure construction, offtake and exploration program. We're also examining expansion studies too, which will involve plant upgrade or possible plant upgrades, Carlton and obviously, BP33. The restart schedule, production plan and capital assumptions are unchanged since FID, which again is very pleasing in a fairly tough market, with first shipment the next big milestone, followed by first ore from BP33 in mid-calendar '27. And of course, steady-state production is the aim, still on track for mid-calendar year '28 of BP33.
Paul Brown
executiveFirst, let me say how grateful we are that all of you could join us. Once more, a huge thank-you goes out to the Core Lithium team and to our contracting partners. It has been an enormous quarter for us. As I drove in this morning, I found myself recalling that at this point 12 months ago, our market cap stood at roughly $120-odd million, and we were out seeking funding. So we have truly pushed hard on this front. We did not stand idle during what proved to be a fairly tough lithium winter. We have locked in excellent funding and excellent partners. And from an execution standpoint, certainly, we are delighted with our contracting partners, with Develop, and with everyone else who has pitched in. So once again, we are really pleased with the quarter, and I am happy to take questions now.
Operator
operatorThanks, Paul. <<operator_script>> It seems there aren't any questions. So I'll hand it back to Paul for closing remarks.
Paul Brown
executiveYes. Once more, thank you all for spending time with us. We will definitely reach out to a handful of analysts over the next few days. And again, we appreciate everyone's backing.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Core Lithium Ltd transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Core Lithium Ltd earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Core Lithium Ltd or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.