DEE Development Engineers Limited (DEEDEV) Earnings Call Transcript & Summary

February 17, 2025

National Stock Exchange of India IN Industrials Machinery earnings 56 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to the Q3 FY '25 Earnings Conference Call of DEE Development Engineers Limited, hosted by Equirus Securities Private Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Vaibhav Shah from Equirus Securities. Thank you, and over to you, sir.

Vaibhav Shah

executive
#2

Yes. Hi. Good morning, everyone. Thank you very much for joining in to the 3Q FY '25 Earnings Call of DEE Development Engineers Limited. I will now hand over the call to Mr. Sanjeev Sancheti, Head, Investor Relations. Thank you, and over to you, sir.

Sanjeev Sancheti

attendee
#3

Thank you, Vaibhav. Good morning, everyone. It is a pleasure to welcome you all to today's call. We are delighted to have the senior management of DEE Development Engineers Limited with us. Joining me today are Mr. Krishnan Lalit Bansal, Chairman and Managing Director; Mr. Pankaj Agarwal, Chief Operating Officer; and Mr. Sameer Agarwal, Chief Financial Officer. Before we begin, I would like to draw your attention to the safe harbor statement included in our earnings update presentation, which is available on both the BSE and NSE website. With that, I now invite Mr. Krishan Lalit Bansal to share his opening remarks. Mr. Bansal, over to you.

Krishan Bansal

executive
#4

Thank you so much, Sanjeev ji. Good morning, everyone, and a warm welcome to all of you. Thank you for joining us today for Q3 FY '25 investor call of DEE Development Engineers Limited. I will take you through the business and operational highlights for the quarter. Before we begin our discussion on the financial results and operational highlights for Q3 and the first 9 months of FY '25, I would like to express our heartfelt appreciation to our shareholders, analysts and stakeholders for being with us today. Your unwavering support and alignment remain instrumental, as we navigate the opportunities and challenges in our industry. We recognize that the company's financial performance this quarter has been challenged with operating income declining by 22.7% year-on-year to INR 162 crores. For the first 9 months of FY '25, operating income stood at INR 541 crores, reflecting a slight decrease of 0.8% year-on-year. The degrowth or slow growth in the revenue are due to the following factors. Firstly, and most importantly, the Palwal facility remained underutilized. This unit was allocated for a INR 139 crore order from a leading Indian oil and gas company for the industry's first propane dehydrogenation plant that's called PDH plant. As this was a pioneering project, a 6-month delay in getting drawings and material approvals from the customer impacted the execution time lines. Originally awarded in October '23, the project was expected to be completed by March 31st, 2025, with a large chunk of revenue coming in Q3 of FY '25. This, however, is now expected to be completed by June 2025 and post -- and part of the revenue will be shifted to the next financial year. Secondly, an international order valued at over INR 51 crores experienced delays due to late revision in the material specifications by the customer, pushing the execution from Q3 FY '25 to Q4 of FY '25. Thirdly, there has been a delay in the execution of INR 60 crores worth of orders from Assam plant. This delay is primarily due to the late delivery of drawings from the client. Additionally, this being our first year of operation in Northeast, it took us longer than anticipated to stabilize operations. However, with -- however, the plant now having been stabilized, we expect to fully utilize the facility in FY '26. Lastly, the commissioning of the new Anjar facility 2 was delayed by over 6 months. The expansion of 9,000 metric ton was successfully commissioned towards the end of January 2025, taking the total capacity to 15,000 metric tons. The delay was primarily caused unprecedented rains in the Kutch region and the unavailability of the construction materials, specifically coal segregate due to a dispute between the mine owners and the state government. [indiscernible] not only resulted in slippage of our revenue, but also significantly impacted our profitability, which led to the company incurring a loss of INR 13 crores in Q3 FY '25. The reason for this are as follows: lean manufacturing at the new Anjar facility 2 got delayed, resulting in significant higher material handling cost than originally envisaged; working capital increased significantly due to increased E&P costs by delay in clearance of drawing by our customers; reduced gross profit due to lower revenue; negative operating leverage resulting in higher fixed overheads. However, with the commissioning of the new plant, problems at customers' end getting sorted. We are back on track. We are on track to [Technical Difficulty] metric ton per annum by 2025 total capacity to 30,000 metric tons. We are also pleased to announce that our high-wall seamless thickness pipe plant is [Technical Difficulty]. We remain on schedule to commence commercial production by January 2026. We are committed to continuously optimize our operations and capitalize on market opportunities. Our primary focus remains on maintaining capital discipline, investing in cutting-edge technologies and upholding sustainable business practices. In light of the current market uncertainties, we will carefully monitor economic trends and adjust our strategy to ensure long-term value creation for all stakeholders. Now, I would like to hand over the call to our CFO, Mr. Sameer Agarwal.

Sameer Agarwal

executive
#5

Thank you, sir. Very good morning, everyone, and thank you for joining the quarter 3 FY '25 earnings call. We would like to guide our stakeholders by sharing our growth targets. We aim to achieve a top line of around INR 1,100 crores in FY '26 with an EBITDA margin in the range of 19% to 20%. The anticipated margin expansion from 9 months FY '25 onwards is attributed to operational leverage and the commissioning of our new Anjar facility 2. This facility will drive cost savings, as it will primarily serve the oil and gas sector, while our Palwal facility will keep focus on meeting the growing demand in the power sector. Additionally, the Anjar facility proximity to Kandla port will reduce logistics costs significantly, as it will be fully dedicated to the oil and gas sector. Thank you, all. Now I open the floor for question-and-answers. Thank you, all.

Operator

operator
#6

[Operator Instructions] The first question is from the line of [ Saumil Shah from Paras Investments ].

Unknown Analyst

analyst
#7

December is about INR 1,400 crores. So by when do you think this order will be...

Operator

operator
#8

I'm sorry to interrupt you sir. Your voice is breaking. Can you please repeat your question?

Unknown Analyst

analyst
#9

Yes, one second. Yes. Sir, our order book as on 31st December is about INR 1,400 crores. So by when do you think this order book will be fully executed?

Krishan Bansal

executive
#10

Normally, our cycle is between 6 months to 18 months for the order book to get executed. And we have a clear-cut target of almost around INR 1,150 crores in this coming fiscal year.

Unknown Analyst

analyst
#11

INR 1,150 crores from the current order book?

Krishan Bansal

executive
#12

Yes.

Unknown Analyst

analyst
#13

Plus the new orders which we will get, that also would be somewhat executed in the coming year.

Krishan Bansal

executive
#14

That's right. That's right. That's right.

Unknown Analyst

analyst
#15

So by -- so in the -- I mean, opening remarks, I think we mentioned INR 1,100 crores revenue target guidance for FY '26?

Sameer Agarwal

executive
#16

Yes.

Unknown Analyst

analyst
#17

Okay. Because you are saying INR 1,150 crores will execute from the current order and plus, we'll get new orders, which would be somewhat executed in FY '26. It should be more than INR 1,150 crores, right?

Sameer Agarwal

executive
#18

Sorry, can you repeat actually your voice -- hello?

Unknown Analyst

analyst
#19

Yes. Hello. Yes. Because in the opening remarks, you said INR 1,100 crores FY '26 guidance of revenue, and now you are saying INR 1,150 crores will be executed from the current order book, and plus, we are getting to get some new orders, which somewhat would be executed in FY '26. So -- much more.

Sameer Agarwal

executive
#20

No, sir. No, no, no, sir. The total revenue expecting we are from FY '26 shall be INR 1,100 crores, which will include the existing order book execution, as well as some of the new orders, which we will be executing during the fiscal '26.

Unknown Analyst

analyst
#21

Okay. And I mean, have we reduced our revenue guidance? Because in one of the interviews, we heard that we are guiding -- we were guiding for a INR 1,300 crore revenue guidance for FY '26?

Sameer Agarwal

executive
#22

No, sir. This is the guidance which we are giving first time. And this is INR 1,100 crores after Q3. And as in Q2 earnings call time, we declared that we shall be giving the guidance for FY '26. So this is the guidance.

Unknown Analyst

analyst
#23

Okay. That I mean, we know that. But in one of the interviews, I think we heard management saying INR 1,300 crores revenue guidance by FY '26 anyways. And sir, I mean, the margins what we are expecting is 19% to 20% on this INR 1,100 crores?

Sameer Agarwal

executive
#24

Yes.

Unknown Analyst

analyst
#25

Okay. Okay. And sir, I mean, one of the -- this propane dehydrogenation plant because of the delay, I mean, how can we -- it affect our revenue? So we didn't have other orders in hand?

Sameer Agarwal

executive
#26

Sir, I mean what you have to consider is that these are very, very large orders, and we have to plan them almost 6 months in advance that we have to execute it and keep our capacity available for that. If you have to switch over to immediately next order, it will be very, very small orders, which we did definitely, but it cannot fulfill the gap, which is INR 139 crores worth of order can create because it's not possible that we shall have all the matching material, we shall have all the drawings for those particular projects, which are in the queue well in advance. So that's the real issue behind it because -- and moreover, let us say, we had that plant. And again, the drawings are not there, we shall neither be able to this project, neither we will be able to do the other project. So we had to keep waiting for the drawings getting cleared. In the meantime, what we did is that we kept on manufacturing the material, which was required for this project. But the revenue conversion started only when the drawings for the final thing started coming in. It is not that we just kept waiting doing nothing. But we kept on producing a lot of raw material, which was required for that particular project in our factory and that is reflecting in our WIP that we were doing continuously work on that. But it was not getting converted into revenue because we couldn't ship it out to the customer because of drawings availability. That is the reason for that. It's not that we are just sitting idle on that.

Unknown Analyst

analyst
#27

Okay. So have we received the drawings in the current quarter and...

Sameer Agarwal

executive
#28

Now all things are cleared. Now all things are cleared. In Q4, we are pushing it very hard. We shall be earning substantial revenue in Q4, and we should be finishing this job in Q1.

Unknown Analyst

analyst
#29

Okay. Okay. So even in this current quarter, we won't be able to expect the full revenue of this project?

Sameer Agarwal

executive
#30

Not full revenue, sir, not full revenue, not full revenue.

Unknown Analyst

analyst
#31

And any guidance for Q4 of this financial year? What would be -- I mean, revenue guidance, so that we can understand FY '25, what we can grow over FY '24?

Sameer Agarwal

executive
#32

So around INR [ 260 crores to INR 270 crores ] of revenue we shall be generating.

Unknown Analyst

analyst
#33

INR 260 crores to INR 270 crores.

Sameer Agarwal

executive
#34

Yes.

Unknown Analyst

analyst
#35

And EBITDA margins.

Sameer Agarwal

executive
#36

So EBITDA margin shall be in the range of overall on an average basis in the range of 15%, 16%.

Unknown Analyst

analyst
#37

On a full year basis.

Sameer Agarwal

executive
#38

Yes.

Unknown Analyst

analyst
#39

Full year basis.

Operator

operator
#40

[Operator Instructions] The next question is from the line of [indiscernible] an Individual Investor. As there's no response, we'll move on to the next question. It's from the line of [ Saumil Shah from Paras Investments ].

Saumil Shah

analyst
#41

Sir, you just mentioned overall yearly basis, we are expecting 15% to 16% [Technical Difficulty]. Is my understanding correct?

Sameer Agarwal

executive
#42

Yes.

Saumil Shah

analyst
#43

Because currently, I think if I am -- if I were to look at, I mean, for FY -- I mean, Q4 of this year, we need to cross 19%, 20% EBITDA margin, only then we can reach to an average of 15%, 16%.

Sameer Agarwal

executive
#44

Yes, that would be there. That would be there. So what we were trying to say is on an average basis for the full year, sir, at least.

Saumil Shah

analyst
#45

So for the current -- so from this quarter onwards, I think we can reach a 19%, 20% EBITDA margins?

Sameer Agarwal

executive
#46

That's right. That's right. That's right.

Saumil Shah

analyst
#47

Okay. Okay. And by -- and till what margins we can -- I mean, expand this as our revenue increases, till where we can go and increase our EBITDA margins?

Krishan Bansal

executive
#48

So since we know that this would be the capacity utilization first time in fiscal '26, so that will -- this year will give us the full view of how things are going in terms of whatever savings, which we have estimated during the expansion of this facility. So hoping whatever [Technical Difficulty] to achieve that. And we are fully on track to achieve this number.

Saumil Shah

analyst
#49

Okay. And by when we can expect the project commissioning of the new this pipe plant?

Krishan Bansal

executive
#50

So that will be starting with effect from 1st January 2026 in operation.

Saumil Shah

analyst
#51

Operations would be from 1st January '26. So any revenue from that project will be only, I mean, by -- maybe by FY '27?

Krishan Bansal

executive
#52

Yes. Sir, just wanted to clarify, this is a backward integration for our power sector jobs. So we will be utilizing the final output of pipe plant, as a raw material for our -- for catering our power sector jobs. So definitely, the profitability shall come in the total turnover part. Rest, it will come as a raw material cost.

Saumil Shah

analyst
#53

Okay. So how much more revenue we can expect from this? I mean, this is a completely -- as you said, it's not a new project completely.

Krishan Bansal

executive
#54

So it's a new project first time we are setting up. And to manufacture the high-wall thickness pipe plant, we shall be procuring the raw material. So I mean, to say once we will convert that raw material into pipe, pipe shall become a raw material for catering our power sector jobs. So I mean to say that the leverage, which we will earn by conversion the raw material to pipe shall be added to our top line.

Saumil Shah

analyst
#55

Okay. And how much -- I mean, how much spend we are doing spending on this project?

Krishan Bansal

executive
#56

INR 90 crores.

Saumil Shah

analyst
#57

Okay. So I mean we are having 2 projects ongoing. I mean because there is one more -- I mean, intimation of INR 260 crores investment, initial INR 150 crores. And so, what is that project?

Krishan Bansal

executive
#58

So sir, it is a second phase of our new Anjar facility expansion. So till now, we have already commissioned the installed capacity of 15,000 metric tons. Going forward, in 9 months, we shall be adding another 15,000 metric tons of capacity in our process piping solution domain.

Saumil Shah

analyst
#59

And we'll be spending around INR 90 crores on that?

Krishan Bansal

executive
#60

No, we will be spending around INR 55 crores because some part of the expansion has already been shown under the capital work in progress.

Saumil Shah

analyst
#61

Okay. And how much asset turnover we can expect on this project?

Krishan Bansal

executive
#62

Pardon, on process piping?

Saumil Shah

analyst
#63

No, no, on the asset turnover, I mean, the spend what we are doing.

Unknown Executive

executive
#64

Asset turnover on the expansion, another 15,000 metric ton expansion, what we are doing, what is the asset turnover? That means how many times will it convert into revenue?

Saumil Shah

analyst
#65

Yes, correct.

Sameer Agarwal

executive
#66

And if the cost is INR 70 crores, then let's assume, then what will be the turnover out of that at a full capacity?

Krishan Bansal

executive
#67

Yes. So around INR 200 crores of revenue if we sell the pipes, as a raw material to any other customer, then INR 200 crores of top line we are expecting from that pipe plant. So the asset turnover is roughly around 2x initially in the first fiscal.

Unknown Executive

executive
#68

So there are 2 questions -- I think, Sameer ji, you need to clarify this because everybody will get confused. There are 2 projects going on. One is for the pipe, where you are increasing the capacity and the second is the backward integration. I think you need to just explain because people will get confused. So please explain very clearly and separately.

Sameer Agarwal

executive
#69

So the high-wall thickness pipe plant shall be the raw material for our power sector jobs. So we are expecting to generate a raw material of around INR 200 crores in the first fiscal post setting up of a plant, as revenue that we will be utilizing to cater the power sector jobs. I hope I'm clear now.

Saumil Shah

analyst
#70

So basically, I'll just summarize from the pipe, the plant on a full capacity utilization, we can generate INR 200 crores of revenue, right?

Sameer Agarwal

executive
#71

Correct.

Saumil Shah

analyst
#72

And the backward integration, which we are doing on that, what is the max capacity -- max revenue potential?

Sameer Agarwal

executive
#73

So as far as the power sector jobs are concerned, we shall be executing it from the Palwal facility. And we have a total capacity to execute jobs between INR 800 crores to INR 1,000 crores of power sector jobs from this plant.

Krishan Bansal

executive
#74

Sir, I will put it in some different way that when both the facilities are operational, which we are saying that by 1st of January or by let us say, 31st of December '25, capability shall be that we shall be able to execute almost around INR 2,500 crores worth of orders. I'm saying it will be our capability to do that.

Saumil Shah

analyst
#75

Okay. At our full capacity.

Sameer Agarwal

executive
#76

At full capacity.

Saumil Shah

analyst
#77

I just wanted to [ got that ]. Yes -- and -- yes. And what is the current debt position on the books?

Sameer Agarwal

executive
#78

INR 390 crores.

Saumil Shah

analyst
#79

This is gross debt, INR 390 crores.

Sameer Agarwal

executive
#80

Yes.

Saumil Shah

analyst
#81

And net debt?

Sameer Agarwal

executive
#82

So net debt is around INR 120 crores.

Saumil Shah

analyst
#83

INR 120 crores net debt?

Sameer Agarwal

executive
#84

Yes.

Saumil Shah

analyst
#85

After reducing cash balance and all.

Sameer Agarwal

executive
#86

Yes.

Operator

operator
#87

The next question is from the line of Kamlesh Jain from Lotus Asset Managers.

Kamlesh Jain

analyst
#88

Sir, just to go back on your guidance for the year. So for the quarter, like you are saying INR 260 crores to INR 265 crores -- INR 260 crores to INR 270 crores. That is a 9% growth over last year. And despite the fact that we are expecting one international order to get executed in this particular quarter, and even on next year, like, say, FY '26, we are guiding INR 1,100 crores. And on one CNBC channel, Mr. Bansal has guided that we would be doing roughly around INR 1,300 crores despite the fact that a lot of orders getting postponed to FY '26. So why we have cut down the guidance, and that is there in the media, like say, it's a video there. So I just want to know about the reasons. And secondly, like say, the delay in execution of some of the orders impact so much that our revenue declines by roughly around 23% year-over-year. And I do understand that there has been some delay on the part of a client. But when we are having such a large order book, then there is no like scope of error for getting revenue down so much year-over-year basis, even quarter-over-quarter basis.

Krishan Bansal

executive
#89

Sir, for that I will -- we have to say that quarter-on-quarter revenues can vary in our type of business. This has been a historical trend also that sometimes Q1 is lean, sometimes Q2 is lean, sometimes Q3 is lean. But normally, we are able to compensate by the end of Q4, whatever we had been projecting. And this is what has been our historical background. But in this particular case, since this order was of very large volume and a very, very specialized materials were required in this and as I told earlier that it was not that we were just idling. We were not doing anything. We were converting the raw material, which was just placed into pipes first and then manufacturing fittings out of that. And then only assembly portion was left out, which was dependent on the availability of the drawings. And the moment the availability of the drawings started, we started executing it on the next day itself. That's why we are saying that we have already built [Technical Difficulty] some portion, but substantial portion is getting booked in Q4 of this particular year. So definitely, there is a slippage of almost a quarter as far as the execution of this job is concerned, but it is from conversion point of view, it is very small. But from revenue point of view, it is very, very large. Hope I'm clear to tell you what I'm trying to say. And if you have something more on this, please ask me, I will be able to respond to that.

Kamlesh Jain

analyst
#90

I do appreciate that. But like sir, even on -- like we are having an order book of roughly around -- if you see this particular quarter of roughly around INR 1,400 crores. And even on the guidance, I just want to know that what level of confidence do we have because majority of the orders, like even for power, it would be from [ PL ], then in oil and gas, it would be largely from major PSU companies. So if the execution slips on their part, then how confident are we on our guidance as well?

Krishan Bansal

executive
#91

Sir, again, I'm saying since this was first of its kind project, that's why it got delayed. Otherwise, once if we are talking of normal power plant jobs or normal oil and gas jobs, we are fully equipped to handle such sort of emergencies. But since this was first of its kind, we were also not very much aware that what could be the pitfalls in this particular job. So that's why it was not possible for us to replace this job with something else. And moreover, again, I will repeat it. It is not that we were just idling. We were just a little under utilization of our capacity, but we were trying to convert the basic raw material into the usable raw material for our job.

Kamlesh Jain

analyst
#92

And lastly, net debt figure, can you provide the figure, including short-term borrowings and everything, not the term debt?

Sameer Agarwal

executive
#93

Sir, it's INR 260 crores and INR 130 crores.

Kamlesh Jain

analyst
#94

Does it include the short-term borrowings, everything?

Sameer Agarwal

executive
#95

Everything. Everything.

Operator

operator
#96

The next question is from the line of [indiscernible], an Individual Investor.

Unknown Analyst

analyst
#97

Am I audible?

Krishan Bansal

executive
#98

Yes. Yes.

Unknown Analyst

analyst
#99

Yes. Sir, it's regarding our BHEL orders. I mean, are we finding any inquiries coming? Like when do we find the inquiries coming like this quarter, next quarter or something like that?

Krishan Bansal

executive
#100

Sir, we are expecting a -- the formal inquiry in the month of April. So that's what we have been discussing. I mean, very, very closely with all those people, who are to do this job. And now they have promised that the inquiry will be available with us in April. Earlier, they had said between February and March, but now they have said it will be given in the month of April and maybe another 3 months to decide the first order.

Unknown Analyst

analyst
#101

Okay. Got it, sir. Sir, the next question is regarding the broad outlook on the oil and gas sector. So like there's a lot of enthusiasm in the upstream sector. So are we finding any like that kind of enthusiasm even in the downstream sector because we generally cater to downstream sector. That's a broad based...

Krishan Bansal

executive
#102

Sir, our forte is only on the downstream side only as of now. We are not on the upstream side. So -- and since huge lot of volume and huge lot of opportunities are available in the downstream side of the project. So we should like to concentrate on that only because we have the infrastructure for that. We have the capabilities for that. But we are talking to practically everybody. You must be aware that Reliance is coming up with huge facilities with almost 4 million dia inch of spools, which will be coming from them. We are talking to Air Products. We are talking to Linde. We are talking to [ Adani Petrochemicals ] also. We are talking to Nayara also These Adani, Nayara and Reliance is the first time we are talking to them on such massive scale, I'm saying. Earlier, we have been doing small, small jobs for Reliance, but we had never worked with Adani, we had never worked with Nayara and all those people are now very keen to get these jobs done in the workshop, and we are in the forefront of it.

Kamlesh Jain

analyst
#103

Got it, sir. So my apologies for this kind of question, sir, like 4 years, 5 years, 10 years down the line, how do we see our -- like the promoter group giving the management to second-generation promoter group, I mean, to handle the company, sir. So are we going to pass it down to the second generation or third generation? Or are we going to manage the company with a qualified business resources? So how is the succession plan going forward? Like it might be any time, which is like 5 years, 10 years down the line. I mean, how are we looking at?

Krishan Bansal

executive
#104

No, no, no. Perfectly fine question, sir. I'm happy that you have asked this question. Let me tell you that we, I will -- principally, I will say that we are already a professionally managed company. I mean major functions are handled by all professionals only. We have departmental heads in all disciplines of our company. We have CEO. We have CFO. They are all professional people, and we have people for strategy. We have people for accounts, we have people for projects, all at Vice President level or Assistant -- Associate Vice President level, General Manager level. Huge lot of management bandwidth is already available with us. However, if you ask specifically, this is how it's going to run. We also have a group trust to manage that in future that also has been formed. But at the same time, my second generation, my co-daughters are fully involved in the business. They are assisting me in taking this company forward.

Operator

operator
#105

[Operator Instructions] The next question is from the line of Aashna from HDFC Asset Management.

Aashna Manaktala

analyst
#106

Sir, I understand that we are giving right now that the guidance that around INR 250 crores of execution is likely to come in Q4 and some INR 1,100 crores of execution is likely to come in '26. Is my understanding correct?

Krishan Bansal

executive
#107

[indiscernible]..

Aashna Manaktala

analyst
#108

Yes. So in this project, now that you are saying that all the issues have now been cleared and it's fully back on execution. For the projects that we are expecting that around now INR 1,400 crores, INR 1,500 crores of execution that might come from today till FY '26. Are there any further such orders where we see that say a similar risk could arise? Or do we have a visibility -- clear visibility that this is an assured revenue to a large extent, which is likely to come.

Krishan Bansal

executive
#109

Ma'am, as of now, whatever order finance is there, they are -- I will put it like that. There is no more of routine orders, which we had been doing earlier. And there is no -- nothing very new in this, which was there in this particular case because the project, which we are talking is it has huge sizes. It has a very special metallurgy. And the licensor involvement was there in everything. Since EIL was also doing it. [indiscernible] is also doing it for the first time. So they were also dependent fully on all each and every approval from their further licensor. That's why it happened. But the present order book, which we are saying is more of a routine job. So we are not seeing any such challenge that shall come in the coming year. And we are quite confident, and we shall be giving you proper information and other things on maybe quarter wise -- quarter basis right in the beginning of [ third ] quarter, and we can have some sort of a call in between also.

Aashna Manaktala

analyst
#110

Understood, sir, and appreciate that. And just to take the clarity now that we have now commissioned our Palwal facility, so we are dedicating our oil and gas execution to Anjar, if I understand, and Palwal will be dedicated to thermal orders now.

Krishan Bansal

executive
#111

That's right. That Palwal is already commissioned. I mean, that's our older plant, and we shall be dedicating it primarily to the power sector jobs. And the new plant, which we call it as Anjar 2 plant shall be dedicated to the oil and gas plant. And again, I would like to tell you that for Anjar plant, the full revenue for the year is already booked from just one customer. So that revenue is assured that -- since we have an order from Dow for almost around INR 350 crores on job work basis and another INR 100 crores have been added for the material portion. So that shall get executed from that plant. And you can say very well that we have the more than full order book just for that plant.

Aashna Manaktala

analyst
#112

Understood, sir. And so, with that, is the understanding correct that the margins should start materially improving now given that you have a dedicated facility for process industries?

Krishan Bansal

executive
#113

Right from Q1. Yes. Right from Q1.

Aashna Manaktala

analyst
#114

Right from Q1. So Q4 will get an impact of spilling over of Q3, and that is where we will get a better operating leverage. But actual...

Krishan Bansal

executive
#115

Yes. That's correct.

Aashna Manaktala

analyst
#116

Okay. So what remains the guidance from '26 onwards for our EBITDA margin?

Sameer Agarwal

executive
#117

So ma'am, we are giving guidance till fiscal 2026. And in the coming 6 months' time, we shall also be giving the guidance for next year.

Aashna Manaktala

analyst
#118

Yes, sir. So what is that '26, we are expecting 17%, 18% margin, right?

Sameer Agarwal

executive
#119

Sorry. In '26...

Aashna Manaktala

analyst
#120

What is the EBITDA margin guidance that we're giving? I wanted to clarify that.

Sameer Agarwal

executive
#121

19% to 20% in fiscal '26. Yes.

Aashna Manaktala

analyst
#122

Okay. Understood. And sir, one last question, like you mentioned that thermal orders inquiries will start coming from April. So by when should we expect them to materialize to actual orders? And again, the execution, if you could talk about that, what would be the time line of that? And so, if the inquiries will start then per from a -- if you could give some guidance [ is it ] per gigawatt terms, how much would it be to begin with? Because BHEL is sitting on a very large order book. So for us, how will that translate to in terms of orders, if you could talk about that?

Krishan Bansal

executive
#123

Ma'am, as I told you, the first inquiry we are expecting in the month of April, and we expect that by June, they will be finalizing the order. And we shall take at least 6 to 7 months' time for the first shipment to happen. So the -- I mean, billing will start in Q4 of the coming fiscal, but that should be major billing, I can only tell you that.

Aashna Manaktala

analyst
#124

Okay. So '26 execution will again largely be dependent on oil and gas and the second half only, we can expect some execution for thermal to begin?

Sameer Agarwal

executive
#125

That's right because we already have that order book for the coming year. So we are not dependent upon these orders. So whatever guidance we are giving, we already have much more order book for that. So there should not be any risk in executing those orders. And if let us say something gets built in quarter 4, it will be just a sort of a bonus or an addition to whatever we are trying to save.

Aashna Manaktala

analyst
#126

Got it, sir. And sir, one last question. In '26, how do we see the order intake panning out? Or if you could talk about the pipeline that we are bidding for right now, barring these thermal orders that we already know?

Sameer Agarwal

executive
#127

Pankaj, if you can respond to this?

Pankaj Agarwal

executive
#128

Yes, sure. Thanks, ma'am, for this question. We have a great pipeline available with us. We are talking about INR 1,700 crores, like which is the -- which I can say it's a low-hanging fruit for us. Those are like in discussion with the customer. But this is including the power business, which we are expecting from BHEL and L&T both.

Aashna Manaktala

analyst
#129

Okay. So how much would you be attributing to thermal in this INR 1,700 crores?

Pankaj Agarwal

executive
#130

We are expecting around INR 600 crores from the power sector. INR 600 to INR 700 crores.

Aashna Manaktala

analyst
#131

Okay. This is for FY '26.

Pankaj Agarwal

executive
#132

Yes.

Sameer Agarwal

executive
#133

Intake.

Pankaj Agarwal

executive
#134

Order intake.

Krishan Bansal

executive
#135

Order intake and it will get executed in Q4 and subsequent time.

Operator

operator
#136

The next question is from the line of Jignesh from [indiscernible] Capital.

Unknown Analyst

analyst
#137

Sorry, sir, I missed the earlier part. But as per the FY '26 execution that you are planning, any major delays that you expect or these are steady state orders that you would be able to execute timely along with any -- without any margin impact.

Krishan Bansal

executive
#138

We already tried to explain that. The order book, which we have, and which is being planned for execution in the coming financial year, they are all routine orders, and we are not expecting any challenge in that, and our margins shall remain intact in those.

Unknown Analyst

analyst
#139

Right. And any chances of that thermal getting delayed by 1 quarter or you see that for Q1, at least we'll get some hint whether we are starting to get any orders.

Krishan Bansal

executive
#140

Q1, we should be surely getting something, sir. Q1, we should be surely getting something. And as a matter of fact, one small order, we are already L1. So we are not right now declaring that, but we are already L1 in one of the orders from BHEL.

Unknown Analyst

analyst
#141

Okay. Sir because if you see in the power sector, there has been kind of slowdown in terms of solar project. So I'm not aware whether I think this thermal would have been bidded out the thermal PPA. So any slowdown you are expecting in thermal, or it is as per the government's plans.

Krishan Bansal

executive
#142

No, absolutely. No, sir. Absolutely, no. Every day, BHEL is getting 1 order or 2 orders every day, I'm saying. And again, I will just like to again inform you that it is not that we are just dependent right now on BHEL or L&T only. We are talking with lot many customers in the international market, where this power sector is growing everywhere. We are talking to a few very new customers, who are going to put up their plant in Saudi and Middle East for thermal only I'm saying. So it is not that we are just dependent upon BHEL and L&T. So there are huge opportunities available in the -- with the other private sector players also in the international market.

Unknown Analyst

analyst
#143

And sir, finally A suggestion like the kind of results that we have seen this quarter, it would be helpful if we, as investors are given some kind of guidance earlier so that we can avoid such shocks.

Krishan Bansal

executive
#144

Sir, it is our mistake. I mean I have no -- I'm sorry for this thing that since we are absolutely new in this field, we were not knowing pretty well that this is how it has to be handled. Otherwise, we are -- I mean, I can assure you from my side that we are one of the most transparent companies. So we shall -- now we have come to know that now how much I mean bad feeling it has generated in the investor community. And I will make sure that everybody has the right information at the right time, even if it is plus or even if it is minus. It is my assurance to you. And it's my 100% conviction that we are 100% on track and we are bound to give the value for your money.

Operator

operator
#145

The next question is from the line of Kamlesh Jain from Lotus Asset Managers.

Kamlesh Jain

analyst
#146

A question for Sameer, ji. Sir, if I see your presentation slide, where it is mentioned that net debt is INR 425-odd crores -- so while a replay to question, you had that INR 130 crores of net debt. So just wanted to know on that because, yes --

Sameer Agarwal

executive
#147

So basically, I told you INR 260 crores is our working capital and INR 125 crores to INR 130 crores is our term debt. That is the -- for our fixed assets.

Kamlesh Jain

analyst
#148

So net debt is -- now net debt is INR 425 crores.

Sameer Agarwal

executive
#149

That includes some [ M&A ] exchange and other things. So that is part of our creditors. We take part of our creditors. As in my understanding, otherwise, you can say if we take that thing in term net, then it will increase. Otherwise, it will be under the creditors. So this is -- and only the matter of understanding.

Kamlesh Jain

analyst
#150

Sir, I am asking just about...

Unknown Executive

executive
#151

No, no, let me -- let me clarify -- let me clarify. The net debt is INR 425 crores. That's -- it includes the INR 21 crores of lease liability. And Sameer ji, this is how the net debt is read. It has to be the common space. It's not what we think it should be read as.

Sameer Agarwal

executive
#152

That I have not included. That's fine.

Unknown Executive

executive
#153

So it is INR 425 crores, which includes INR 21 crores of lease liability.

Operator

operator
#154

The next question is from the line of [ Subesh Singh ], an Individual Investor.

Unknown Analyst

analyst
#155

I'm a simple investor. So my question is also rather simple. I appreciate Chairman, sir's assurances to the investors. But sir, a simple question is that this event that has happened, is there any possibility of it repeating again suddenly like this has happened? Is there any possibility of it repeating again in future? It's a simple question...

Krishan Bansal

executive
#156

I will emphatically said no.

Unknown Analyst

analyst
#157

Okay, sir. We take it, sir. Second question, sir, we have given a guidance of 3 to 5 years -- threefold increase in our revenue in 3 to 5 years. Do we stand by it?

Krishan Bansal

executive
#158

Yes, we stand by that.

Unknown Analyst

analyst
#159

Okay, sir. Sir, last question, third question, last question is we have seen that we have incurred the expenses, but revenue was not realized. So will that happen in Q4 as well?

Sameer Agarwal

executive
#160

No, Q4, we will realize the revenue.

Operator

operator
#161

The next question is from the line of [ Shivanshu Gupta ], an Individual Investor.

Unknown Analyst

analyst
#162

Sir, my question is regarding the tariffs in the U.S. like given the push towards oil sector and energy sector there. So like you as a company, I know capitalize on those opportunities. So in terms of exports of, let's say, steel pipes and what all material that you use in your pipe infrastructure, so what impact do you see from tariffs in the country?

Krishan Bansal

executive
#163

Sir, I will not be able to comment fully on that. But whatever information I have or whatever way we have been working with the U.S. companies because some tariffs are already in place -- are already in place, it has never impacted our business. It has never impacted our business. But I really cannot say you for sure that it will not have any impact in future.

Unknown Analyst

analyst
#164

Okay. And sir, what about the competitors in your sector, like the kind of competitors that you compete with, those are international customers with similar margins or similar order book. [indiscernible] like how do you comment if the tariffs were to impact?

Krishan Bansal

executive
#165

I mean, I don't think we shall be impacted with that. Our -- we are -- since we are following the best cost country or the low-cost country profile. So our labor cost is definitely much cheaper than other people's labor cost. And we win because of our economy only because of our competitive prices only.

Operator

operator
#166

Ladies and gentlemen, this will be our last question. It's from the line of Vaibhav Shah from Equirus Securities.

Vaibhav Shah

executive
#167

So my first question is what has been the overall quantum of order intake for the 9M FY '25 and for the 3Q? And what is the bifurcation of this order intake between, let's say, power, oil and gas and process industries?

Sameer Agarwal

executive
#168

Pankaj, sir, can you throw a light on that?

Pankaj Agarwal

executive
#169

Come again, please? I didn't get the question.

Vaibhav Shah

executive
#170

So sir, what is the -- our overall order intake for 9M FY '25 and for the 3Q? And what is the bifurcation between end user industries that is power, oil and gas and process industries?

Pankaj Agarwal

executive
#171

I just said that we are expecting around INR 1,700 crores orders in the coming financial year. And out of that around say INR 600 crores to INR 700 crores will be from the power sector. And remaining will be from oil and gas sector.

Vaibhav Shah

executive
#172

Sir, this is regarding the historical for the 9M FY '25 and for the quarter, 3Q?

Pankaj Agarwal

executive
#173

Same there because we are expecting this power business from 2 major customers like BHEL and L&T. And BHEL, we are expecting somewhere in June, as Mr. Bansal said. And from August, September, we are expecting from L&T, large order book.

Vaibhav Shah

executive
#174

[Technical Difficulty]. Sir, second question is regarding the -- our mix between sale of products and job works. How it would fare in our outstanding order book?

Pankaj Agarwal

executive
#175

I'm sorry, I don't have the data right now with me. But it would be around INR 300 crores orders like for the job work and remaining is with material now.

Vaibhav Shah

executive
#176

Okay. So sir, I just wanted to have more clarity on my first question. So sir, I was just asking about the -- our overall order intake. So what is our historical split for, let's say, for first 9 months of FY '25 between power, oil and gas and process industries. Order intake for 9M FY '25?

Pankaj Agarwal

executive
#177

You mean first 9 months?

Krishan Bansal

executive
#178

Yes, yes.

Pankaj Agarwal

executive
#179

It would be around 60%, 70% order will be booked within 9 months. And ratio, as I said that we are expecting a major order book from power sector now from BHEL in June, which will be the first quarter and August like from some other customers. So it would be around [Technical Difficulty].

Vaibhav Shah

executive
#180

Sir, basis on the historical order intake for first 9 months...

Krishan Bansal

executive
#181

I think sir, we shall share you the data. He may not be having -- he is asking for the order intake from April to December this year or April to February this year at least.

Pankaj Agarwal

executive
#182

I don't have the data available with me right now, but we'll share with you, sir.

Sameer Agarwal

executive
#183

Wanted to clarify, Vaibhav ji, so by and large orders, which we have booked during the fiscal '25 are from oil and gas sector. So major orders are the PDH order -- sorry, the...

Krishan Bansal

executive
#184

Dow order.

Sameer Agarwal

executive
#185

Dow order and Numaligarh order, which is basically cumulative to INR 700 crores of order book. Besides that, we have other miscellaneous orders and around INR 150-odd crores are from power sector where for the export orders.

Operator

operator
#186

Ladies and gentlemen, that was the last question for today's conference call. I now hand the conference over to the management for their closing comments.

Sameer Agarwal

executive
#187

So thank you, everyone, for joining us, and we are hoping to do whatever we have promised, and we are really thankful to -- for all the stakeholders keeping trust in our company and handholding us an unwavering support throughout our period. Thank you so very much.

Krishan Bansal

executive
#188

Thank you, sir. Thank you so much. So again, one closing remark again from my side that we are fully committed to the growth of the company. We are fully committed to ensure that the value of the stakeholders is met, and there shouldn't be any doubt. And we really apologize for whatever has happened for Q3 and we shall ensure, or we shall assure all of you that you will have the timely information in case of any such eventuality in the coming future, which we do not foresee at all, but still we shall be keeping you abreast of all the developments, which are happening in our company. Thank you so much.

Operator

operator
#189

Thank you. On behalf of Equirus Securities Private Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.

This call discussed

For developers and AI pipelines

Programmatic access to DEE Development Engineers Limited earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.