Dominion Energy, Inc. (D) Earnings Call Transcript & Summary

October 30, 2026

New York Stock Exchange US Utilities Multi-Utilities earnings 35 min

What were the key takeaways from Dominion Energy, Inc.'s October 30, 2026 earnings call?

In the third quarter of fiscal year 2026, Dominion Energy reported operating earnings of $1.28 per share and GAAP earnings of $1.30 per share, reflecting a solid performance driven by favorable weather and higher-than-expected RNG 45Z credit income. Management has raised full-year guidance to the top half of the original range, indicating confidence in continued strong performance. Key highlights include robust electric sales growth of 3.4% and significant progress on the Coastal Virginia Offshore Wind (CVOW) project, which is now 85% complete.

What topics did Dominion Energy, Inc. cover?

  • Revenue Growth Acceleration: Dominion Energy experienced strong sales with a weather-normalized electric sales growth of 3.4% across its service areas. Management noted, 'all 10 of the DOM zones' summer peak demand days have occurred in 2026.'
  • Coastal Virginia Offshore Wind Project Progress: The CVOW project is approximately 85% complete, with 44 turbines installed, representing over 640 megawatts of capacity. Management stated, 'CVOW installation has been significantly derisked and continues to make progress against its schedule and cost objectives.'
  • Guidance Update: Management has raised its full-year operating EPS guidance to the top half of the original range due to better-than-budgeted sales and weather. They stated, 'we now expect full year results to be in the top half of our original guidance range.'
  • NextEra Energy Merger Progress: The merger with NextEra Energy is progressing through regulatory approvals, with hearings scheduled in Virginia and South Carolina. Management expressed confidence, stating, 'we remain confident that our position goes beyond the statutory standard.'
  • Data Center Demand: Dominion continues to see robust demand from data center customers, with over 54 gigawatts of capacity in various stages of contracting. Management highlighted, 'we've added over 6 gigawatts of contracts or 13% since the end of last year.'

What were Dominion Energy, Inc.'s October 30, 2026 results?

  • Operating EPS: $1.28
  • GAAP EPS: $1.30
  • Electric Sales Growth: 3.4%
  • CVOW Completion: 85%
  • Data Center Capacity: 54 gigawatts
  • Millstone Savings: $900 million

Dominion Energy's strong quarterly results and positive guidance adjustments signal a robust operational performance, particularly in the context of the CVOW project and growing data center demand. However, regulatory challenges related to the NextEra merger present uncertainties that investors should monitor closely as the company progresses through the approval process.

Earnings Call Speaker Segments

David McFarland

executive
#1

Good morning, everyone, and thanks for being with us on Dominion Energy's third quarter 2026 earnings call. The earnings materials, which include today's prepared remarks, contain forward-looking statements and estimates that carry various risks and uncertainties. For a discussion of factors that could cause results to differ from management's estimates and expectations, please see our SEC filings, including our most recent annual report on Form 10-K and our quarterly reports on Form 10-Q. This morning, we'll cover some measures of our company's performance that differ from those recognized by GAAP. You'll find reconciliations of our non-GAAP measures to the most directly comparable GAAP financial measures, which we can calculate, in the earnings release kit. I'd encourage you to visit our Investor Relations website to review the webcast slides as well as the earnings release kit. With us on today's call are Bob Blue, Chair, President, and Chief Executive Officer; Steven Ridge, Executive Vice President and Chief Financial Officer; and other members of senior management. I'll now hand the call over to Steven.

Steven Ridge

executive
#2

Thanks, David, and good morning, everyone. Three top priorities continue to guide us: first, meeting our financial commitments reliably; second, keep reaching key construction milestones on the Coastal Virginia Offshore Wind project; and third, arriving at regulatory outcomes in a constructive way that demonstrates our ability to work with regulators and stakeholders so that customers and shareholders both benefit. As we'll cover today, we continue to succeed on these priorities, further extending our track record of consistent, high-quality execution. My remarks will address financial results. Bob's remarks will provide updates on the NextEra Energy combination, CVOW, and other business items. Starting with the Q3 figures on slide 3: operating earnings for the third quarter reached $1.28 per share, which includes 5 cents from RNG 45Z credits plus another 5 cents due to weather that outperformed normal patterns. GAAP results for the quarter stood at $1.30 per share. You can find a breakdown of earnings drivers versus the same period last year in Schedule 4 of the earnings release kit, while Schedule 2 of that kit summarizes every adjustment bridging operating and GAAP results. Now regarding our outlook: operating EPS so far this year has gotten a lift from sales exceeding budget, more favorable weather than usual, and 45Z credit income surpassing what we anticipated, along with solid execution across both finance and operations. After factoring in a conservative view of weather for the rest of the year, plus possible chances to reduce risk in future financial results, we now anticipate full-year results will come in within the upper half of the range we originally guided. Year-over-year drivers for the fourth quarter are included in the appendix of today's materials for your reference. In addition, we are reaffirming all remaining financial guidance we previously gave on our fourth quarter earnings call, which covers credit, dividend, and long-term growth guidance. Moving to slide 4 on financing, our financing plan advanced considerably this quarter—we completed multiple planned transactions and kept managing the balance sheet in line with our strong credit guidance. In September, the Virginia State Corporation Commission gave approval to our fuel securitization financing petition, which carries a balance of roughly $900 million and helps reduce near-term fuel-related effects on customer bills. Briefly on sales: we keep seeing robust sales across our service areas, with LTM weather-normal electric sales growth of 3.4% for DEV and DESC combined. Also, every one of the DOM zone's 10 summer peak demand days has fallen in 2026, and DESC reached a new all-time electric peak in August. Now on slide 5: since we last updated you, demand has stayed strong and lasting among our differentiated, high-quality, low-risk data center customers in several Virginia localities. We're integrating them properly — shielding current customers from cost shifts and reducing stranded cost risk by using the large load framework the Virginia State Corporation Commission approved in our latest I&E review, which keeps these customers paying their fair share of the investments needed for their growth. Right now, the capacity we have at data centers across different stages of contracting stands above 54 gigawatts, and more than 12 gigawatts of that amount is covered by electric service agreements. To put it in perspective, since the close of last year we've signed contracts totaling over 6 gigawatts, which is a 13% increase. That figure includes $0.05 from RNG 45Z credits along with $0.05 from weather that came in better than usual. So to wrap up, I have strong confidence in our ability to deliver on the financial plan. That plan was built to be appropriately conservative — though not overly so — so it can absorb unforeseen difficulties that may come up; having said that, Bob, I'll turn the call over to you.

Bob Blue

executive
#3

Thank you, Steven. On slide 6, I'll begin with safety. Through September, the OSHA recordable injury rate among our employees was 0.41, which remains well below the industry average. Safety is our top core value, and we continually strive to bring workplace injuries down to zero. Turning to the combination we announced with NextEra Energy: as we explained in May, this transaction represents a truly transformational opportunity. It unites two world-class utilities with a combined 238 years of industry experience, enabling us to serve millions of regulated customers across four states even better. Going forward, we believe that together we can accomplish much more for our customers than either company could on its own. Back in mid-September, NextEra and Dominion rolled out a bigger set of benefits for Virginia — one that puts customers first and sets the Commonwealth up as a global energy leader. Under that proposal, residential bill credits last twice as long, energy bill assistance grew by $100 million, and a $100 million fund for workforce development was added. It also pledged to bring at least 1,000 new jobs to the Commonwealth, to construct a new co-headquarters tower in Richmond paid for by shareholders, and to back Virginia companies through a Virginia supplier program worth $1 billion a year over five years. Looking further out, customers and communities gain from a stronger company — one with the scale and capabilities to buy, build, finance, and operate critical energy infrastructure more efficiently, which helps support reliability, affordability, and economic growth. In Virginia, testimony has come in from the parties, and we'll respond to it through rebuttal testimony that's due on November 2nd. Evidentiary hearings get underway on November 17th, with a final order expected by January 11th of next year. In the end, the case will be decided by the State Corporation Commission on the basis of the record before it and the legal standard: whether the proposed transaction would impair or jeopardize adequate service to the public at just and reasonable rates. Put another way, the question is whether the deal will do customers no harm. We're confident we've satisfied that standard. We've actually gone beyond what's required, putting forward substantial advantages when it comes to affordability for customers, employment within our service territory, and building out the energy resources that are needed. Down in South Carolina, testimony has come in from intervening parties, and we'll respond to it via rebuttal testimony that's due on November 18th. Hearings get underway December 8th, and a final order is expected by January 29th, 2027. Over in North Carolina, hearings kick off on February 23rd, 2027. Slide 7 lays out the schedules for both proceedings. All the federal approvals we need have been submitted and are moving along. We still anticipate completing the transaction during the back half of 2027. I'm extremely enthusiastic about bringing these two companies together, and we'll keep everyone informed with further updates as we move through the regulatory review. Now let's look at offshore wind on slide 8. CVOW is advancing well—the project stands at about 85% complete, and all nacelles, towers, and blades have finished fabrication. To date we've installed 44 turbines, representing more than 640 megawatts of generating capacity, and the 45th turbine is going in right now. Installation still takes about two days on average from jack-up to jack-down, in line with our assumptions. The pace of turbine installation in July and August came in as expected, but September and October fell short because of a mix of weather and Charybdis maintenance work, and that maintenance was finished earlier this month. Crucially, these effects fell within the kinds of risks we had in mind when we added schedule contingency last quarter. We have used up part of that contingency, but our outlook is unchanged; we still expect the project to be completed by the end of 2027, with the third and final offshore substation energized by year-end 2026. On the cost side, our current budget is still $11.65 billion, and that includes $123 million of unused contingency. We continue to see significant customer value as well. The project's LCOE remains far under the statutory threshold and is also beneath the range we had envisioned in our initial filing, and we estimate that CVOW will generate approximately $5 billion in fuel savings for customers during its first decade of operation. Our overall perspective on the project is unchanged. CVOW installation has been substantially de-risked and continues to advance on schedule and within cost targets while providing considerable long-term customer value. I'll now turn to other business updates, which appear on slide 10. In mid-October, we submitted our Virginia Integrated Resource Plan update, which contained multiple potential generation build portfolios crafted to satisfy strong growth in customer demand. Relative to the preferred plan we put forward last year, we've accelerated and added 4 gigawatts of solar along with 2 gigawatts of battery storage. The key point is that our preferred plan serves customer needs, safeguards reliability of the system, and keeps electricity affordable, with average monthly residential bills projected to increase roughly 2.3% per year. Energy storage keeps playing a larger part in Virginia, in our view. The IRP we filed recently is an update — a snapshot in time — yet it already shows a meaningful boost in storage compared with the plan we had before. Also important: Virginia passed major storage legislation this year, which establishes much higher targets for short-duration and long-duration storage alike. As use cases keep expanding and the technology keeps improving, we anticipate storage will take on a growing role. We're actively assessing short-duration battery storage along with emerging long-duration technologies, looking at them through the lens of reliability, affordability, and customer need. Over the longer term, the proposed combination with NextEra Energy would unite considerable capabilities and experience in energy storage. That, we believe, puts the combined company in an exceptionally strong position to deploy storage at scale as the technology matures and system needs evolve. Last, on Millstone, in September the Connecticut Department of Energy and Environmental Protection gave an update on the zero-carbon energy request for proposals, indicating it plans to announce a decision later this year. The current power purchase agreement at this facility has brought customers enormous benefits—cheaper costs and much less volatility. Although the deal was signed in 2019 at a price above what market forecasts suggested back then, it is expected to save customers more than $245 million this year—with $200 million of that already realized so far this year—in addition to over $200 million in customer savings last year. Based on today's forward curves, cheaper energy prices ought to generate customer savings in Connecticut above $900 million over the contract's 10-year term. Our focus stays on securing a constructive outcome for the facility, which has provided tremendous value and generated bill reductions for Connecticut customers under its existing contract; we will keep providing updates as developments occur; so with that, let me wrap up our remarks on slide 11 by restating our concentration on three top priorities: consistently meeting our financial commitments; continuing to reach major construction milestones on the Coastal Virginia Offshore Wind project; and securing constructive regulatory outcomes showing we can collaborate with regulators and stakeholders to produce results benefiting customers and shareholders alike. We stay dedicated to supplying reliable, affordable, and increasingly clean power to our customers. With that, we're ready for your questions.

Shahriar Pourreza

analyst
#4

Hey, guys. Good morning.

Bob Blue

executive
#5

Morning, Shar.

Shahriar Pourreza

analyst
#6

Morning, Bob. So Bob, when we look at this deal and the staff, there are 57 conditions—can you tell us where the biggest gaps are between you and the staff? What's the deal breaker for you? Is it the ring-fencing? Or the dividend restrictions? Can any of those gaps be closed before the hearings next month? And then, one last thing, maybe you could comment on the governor's intervention, which looks like a bit of excess across. How's that dialogue going? Thanks.

Bob Blue

executive
#7

Shar, great question. Out of those 57 conditions, a good number were ones we had already put forward voluntarily—I think that's important to keep in mind. As John mentioned on NextEra's call about a week ago, our focus remains on the statutory standard of no harm. The judges will adhere to that; we'll submit our rebuttal testimony on Monday, and we look forward to the hearing starting November 17th. We continue to be confident that our position exceeds the statutory standard and will bring benefits—not merely no harm—to Virginia customers, employees, and communities. It will keep our company locally led, still regulated by the SCC, and fully accountable to them. John said on their call that the judges at the SCC will follow the law. We couldn't have hoped for a better outcome than that, and Monday is when we'll present the testimony in our rebuttal.

Shahriar Pourreza

analyst
#8

Understood. So just on the governor — how are those discussions going? I suppose I don't want to call it behind closed doors, but is what we see in public different from the conversations you're having in private?

Bob Blue

executive
#9

The governor is taking part as an intervenor in the case, which she clearly has every right to do, and we welcomed that intervention. We're involved in the case through the filings we submit. Naturally we speak with parties where it makes sense, but honestly what we're concentrated on at the moment is the testimony we file on Monday, and making sure all of us stay very focused on the no-harm legal standard.

Shahriar Pourreza

analyst
#10

Understood. Great. So finally, Bob, regarding CVOW, we clearly observed a fairly healthy decrease in the LCOE down to 62 dollars. Clearly, much of that came from RECs dropping to 38. I suppose, what are you observing in the REC market that's causing that, and would you consider 38 to be sustainable?

Steven Ridge

executive
#11

Shar, this is Steve; predicting the price is difficult. We clearly reflect it each quarter when we update the filing and are very transparent about it. What we're observing is supply and demand tightening, somewhat as one might expect. Keep in mind that a big share of those RECs must come from Virginia resources, so that clearly serves as an extra constraint, which drives prices upward. Keep in mind, the way that calculation works is that we offset the LCOE with revenue from those REC-generated sales by CVOW; that's the reason you see that price decline; we've watched it fluctuate. It was somewhat higher; now it has come back down somewhat lower in terms of the LCOE. I believe the key point is we still believe CVOW will deliver substantial value to our customers.

Shahriar Pourreza

analyst
#12

Understood. That's great. Thanks, everyone. We'll talk again in roughly 7 days. Much appreciated.

Nick Campanella

analyst
#13

Hi there, good morning. Good

Bob Blue

executive
#14

morning.

Nick Campanella

analyst
#15

Perhaps sticking with the merger topic, a comparable question specifically about South Carolina. What reactions have there been to the testimony that came in there recently? Does a route exist to resolve South Carolina, and do you have any views on the bill credit — 4 years as opposed to 2 years? Thanks.

Bob Blue

executive
#16

Nick, my response will mirror what I said regarding Virginia. Over there, we are in the middle of that regulatory process. We keep working our way through it. All of you have the procedural schedules before you. The next step for us is to file our rebuttal testimony and afterward proceed into the hearing. Our belief remains that we have put forward a very strong package in South Carolina, just as we did in Virginia, and we look forward to the chance to show that to the commission. Naturally, we engage with parties across every state and every regulatory proceeding we are part of, trying to reach a good outcome.

Nick Campanella

analyst
#17

Thank you. So perhaps we can turn to Millstone. I recall you mentioned on the slides that a decision could potentially come by year-end. Could you remind everyone of the broad timeline? Will term and price be settled by then, or is it simply that Millstone might have been chosen as part of this broader process? Maybe just a small mark-to-market on those discussions? Thanks.

Bob Blue

executive
#18

Hi, Nick. We feel encouraged and are constructively engaged with the parties involved in that process. It's a bit hard to say with certainty what sort of thing would be public at the end of the year; we definitely don't want to speak for the regulators or get ahead of them in this case. I do think by the end of the year we'll feel we have a somewhat better sense of where that process is heading; then, of course, whenever we have announcements to make, we'll be eager to make them public to folks.

Nick Campanella

analyst
#19

All right. Thank you.

Bob Blue

executive
#20

Thanks, Nick.

Bob Blue

executive
#21

Hi there, Paul.

Anthony Crowdell

analyst
#22

Is this better? Are you able to hear me now? My apologies — does this do the trick?

Bob Blue

executive
#23

Yes, that's working. We were beginning to be a bit concerned for a moment.

Anthony Crowdell

analyst
#24

I realize that, I believe Paul is out trick-or-treating, and he's likely collecting his final candy right now.

Bob Blue

executive
#25

It's good to hear that you held off until the call had finished.

Anthony Crowdell

analyst
#26

I’ve got just one brief question. You folks have given a lot of clarity around CVOW. You keep reducing the risk on it. I believe it’s 85% complete. I think this may be more of a sector-wide question. The sector is now getting close to construction on some large generating projects. You folks have obviously worked all the way through this project, which may be one of the bigger ones underway across the country. So how should investors think about execution risk across the sector as we begin to see utilities take on larger generating units? You folks have worked all the way through it. You keep reducing the risk on it. I’m not sure whether it’s lessons learned or something else, but what would you tell us we should focus on as you folks succeed with CVOW and we now see other utilities follow this path?

Bob Blue

executive
#27

That’s an excellent question, Anthony, and I wouldn’t confine our experience only to CVOW. It hasn’t been very long since we completed some sizable combined cycles here in Virginia. What we focus on is having a project construction team with experience that works with contractors we know well. They understand which risks to examine. Our board has grown quite comfortable asking us questions about the risks we ought to be focused on. Not surprisingly, those often line up around what your potential labor constraints are, how the supply chain looks, and being familiar with all of that is really valuable. At least in our case, we take comfort from the fact that we have an experienced team that has handled big projects, not only on the gen side, by the way, but on the transmission side of the house as well, because we’ve done an awful lot of that work over the last few years. So put that experienced team together with strong counterparties where we have confidence in the supply chain, and then finally familiarity with the permitting process. I think we all know that these projects can face challenges when permits get off track, and so having the relationships necessary in order to work your way through the permitting process is critical as well.

Anthony Crowdell

analyst
#28

That covers everything from my side. Thank you very much, everyone. I'll see you all at EEI.

Bob Blue

executive
#29

Thank you, Anthony.

Carly Davenport

analyst
#30

Hey there, good morning. Really appreciate you taking the questions. Perhaps to circle back to CVOW, we're grateful for the time — the jack-up to jack-down duration is coming in as you'd expected. I suppose, could you help us consider the remaining elements that might affect the total schedule, and how you see those developing over the coming months, particularly as we factor in weather and similar things heading toward year-end?

Bob Blue

executive
#31

Apart from the jack-up to jack-down period, the additional things we consider and have pinpointed include weather, maintenance, transit, and load-out time. We've built in assumptions about weather. Clearly, we can't control that. Then regarding the other elements, our load-out durations keep getting better. Where we're headed on the project determines our transit times, and the team, I believe, has assembled a really solid schedule to keep those transit times to a minimum, so we're erecting turbines near one another instead of crisscrossing the project. Maintenance is something we factor in, and all of it improves somewhat as we progress. If you consider, Carly, everything we've accomplished on this project, we become considerably quicker as we proceed. Just to give you a handful of statistics about installation time. Our initial 10 turbines required an average of 69 hours apiece to install. The following 25 required an average of 45 hours, which represents a 35% improvement. Then the latest nine averaged 38 hours, a 45% improvement versus the first 10. We're getting better at turbine installations the same way we got better on monopile timing, the same way we got better on transition piece timing. As I said, we keep getting quicker on the port turns. Naturally, we do fewer of those since we load four turbines per trip. We're becoming faster at that too. I think our plan is solid on transit time, and whatever maintenance we need to perform, if we've done it previously, it will go quicker the next time, as we've discovered along the way.

Steven Ridge

executive
#32

Carly, I think that's a totally fair question. Let me try to put some numbers behind what I believe you're driving at, building on the great answer Bob just gave: take the last three months — that stretch was about 91 days. Weather hit 14 of those days, and the vessel maintenance we talked about consumed roughly 36, so we wound up installing approximately 13 turbines over about 41 usable days, which comes out to roughly 3.2 calendar days per turbine — again, a bit above the two, because transit time isn't included in that figure. Looking ahead, we have around 425 calendar days left before the close of '27 to put in the remaining 132 turbines, which also happens to work out to 3.2 days each. What really matters, as Bob pointed out, is the time jack-up and jack-down consume — our base case assumes two days, but as he mentioned, the most recent 9 have been closer to 1.5 days. At 1.5 days, the remaining turbine installation could be finished in roughly 200 days. At two days per turbine, you'd be looking at 265. We expect approximately 33 load-outs at the port, each taking around four days, for 130 days in total. Tallying it up — 427 days, 200 to 265 days for turbine installation, 130 days of port turns — leaves somewhere between 30 and 95 days for weather, maintenance, and any additional time required at the more difficult turbine installation sites. That should give people a sense of how much contingency the plan holds from a timing perspective, and that's where our confidence comes from — together with what Bob explained, namely that with every round of construction, the process gets faster each time.

Carly Davenport

analyst
#33

That's really useful background—thanks. My next question is just a housekeeping one. Looking at the 4Q drivers, it seems O&M went from being a negative to a positive. Is there anything specific you'd call out as the reason, and does that tell us anything about O&M trends in 2027?

Steven Ridge

executive
#34

No, Carly, nothing in particular. We reexamine those drivers every quarter, of course, to capture the most current view of the forecast. I'd note that we guided to the top half, and I believe I mentioned in my prepared remarks that this factors in some conservatism regarding November and December weather, along with possible chances to de-risk financial performance. That lever will be there for us as we move through the final two months of the year, so we land solidly at our guidance—the updated guidance—and also take the steps needed to de-risk future years.

Carly Davenport

analyst
#35

That's crystal clear. Thanks a lot for making the time.

Paul Zimbardo

analyst
#36

Hello again, I'm here once more. I believe Anthony was at my door ringing the bell for trick-or-treating.

Steven Ridge

executive
#37

It's nice to hear your voice, Paul.

Paul Zimbardo

analyst
#38

No, thanks so much, and I get that the previous answer involved a lot of math. Let's hope this one's simpler. Could you walk us through the nuclear uprate opportunities — mainly the regulated fleet, but the unregulated asset as well — and sort of where things stand as you look into some of these possible expansions?

Bob Blue

executive
#39

Paul, that's a good question. We believe there are some limited opportunities at Millstone, as we've mentioned previously. On the regulated fleet side, we've completed quite a bit of uprate work through the years. What we're focused on for the regulated fleet is the investment required for subsequent license renewal. We're adding another 20 years to those plants' operating lives; that's really where the effort is concentrated at the moment. We're always on the lookout for uprate opportunities where they make sense and where we can carry them out safely within the proper safety margins.

Paul Zimbardo

analyst
#40

Got it on that point. So my final question concerns Virginia, specifically the new IRP. I believe you brought up the 4 gigawatts plus the 2 gigawatts of incremental pull forward. If you could just outline what effect that might have on the capital plan and rate base growth, any detail along those lines would be useful. Thanks.

Steven Ridge

executive
#41

Sure thing, Paul. When you compare 2025's IRP with the most recent IRP, it basically raises the battery capacity on the system roughly fourfold through 2034. To illustrate, battery stood at 850 megawatts for 2030 through '34 in the 2025 IRP; by the 2026 update, that figure is 3.3 gigawatts. The capital cycle involved spans roughly a two-year period, during which you're deploying that capital ahead of the actual COD. Naturally, as we move forward and bring '31 into our five-year plan, we'll be adding one more year of not only the battery capital opportunity that already existed, but in fact this expanded battery capital opportunity. We've characterized it as each gigawatt representing somewhere around $2.5 billion to $3 billion of opportunity. Bear in mind, a portion of the IRP would sit under a PPA structure. Clearly, that portion wouldn't go into our rate base, yet most of it falls under self-build, in line with the Virginia Clean Economy Act. As I see it, looking ahead, there's a highly significant chance for capital enhancement so as to satisfy the legislative and policy intent of the state.

Paul Zimbardo

analyst
#42

All right, no, I appreciate it. That is extremely clear and thorough. Thanks.

Nick Amicucci

analyst
#43

Morning, everyone. Apologies — I just wanted to circle back to the merger briefly, if that's all right. One item stood out as a point of contention in the SCC staff testimony, and I was hoping to get some clarity so I can understand it properly. When it comes to the ring-fencing and that bankruptcy-remote special-purpose vehicle, what exactly are they after there? I get the protection angle for Dominion, but how should we be thinking about that structure?

Bob Blue

executive
#44

I completely get why that question comes up, but like I said, we're moving through the regulatory process right now — rebuttal testimony gets filed on Monday, and then there's a hearing only a few weeks out. Through that process we'll keep putting forward what we believe is a very strong package, and I hope you can appreciate why I'd rather not get into the specifics on the Friday ahead of our rebuttal filing.

Nick Amicucci

analyst
#45

That's quite fair. Then I also just wanted to walk through the funding requirement as we look ahead toward 2027 — how much flexibility is there if we see some load acceleration and a possible delay in any closing?

Steven Ridge

executive
#46

Nick, are you asking about our 20 — about where our 2027 financing needs could land and how that might be affected?

Nick Amicucci

analyst
#47

If we look at this specifically from the equity issuance angle.

Steven Ridge

executive
#48

Yeah. During our fourth-quarter call, we provided a five-year outlook, and we said that from an equity standpoint at least, it was heavily weighted toward the back end, more or less in the final couple of years of our plan. I don't want to get ahead of our updates to the forecast, but broadly speaking, we viewed '27 and '28 as comparatively lighter equity years, and nothing I've seen points to that necessarily being different.

Nick Amicucci

analyst
#49

Great. Thanks.

Steven Ridge

executive
#50

You bet. Thank you.

Bob Blue

executive
#51

Appreciate all of you making time to be on today's call, and enjoy the rest of your day. Thank you.

Operator

operator
#52

That brings us to the end of this conference. We appreciate your joining today's presentation. You are welcome to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Dominion Energy, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Dominion Energy, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Dominion Energy, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.