Dwight Gardiner
executiveOkay, good morning everyone, and thanks for joining the Drax 2019 Full Year Results Presentation. I'll begin with an operational review. Then I'll hand things over to Andy Skelton, our CFO, who'll take you through the financial review, and after that I'll return at the end to update you on our biomass strategy. As you know, our purpose is to enable a zero-carbon, lower-cost energy future, and our strategy is built to support it. It has 3 legs: building a long-term future for sustainable biomass, being the leading provider of power system stability, and giving our customers control of their energy. Late last year we added another ambition: becoming a carbon-negative company by 2030. With the right regulatory framework and government support, I have absolute confidence that we can achieve it. Over a year of significant change for Drax, we delivered strong performance. The group increased adjusted EBITDA by 64% to GBP 410 million. Within that, our hydro and gas generation assets contributed GBP 114 million, above the top end of our guidance range of GBP 90 million to GBP 110 million. We remain significantly cash generative, delivering GBP 413 million in net cash from operating activities.
Dwight Gardiner
executiveAnd across the past 3 years, we've generated over GBP 1 billion in net cash. We beat our 2x net debt to adjusted EBITDA goal, coming in at 1.9x, and dividends per share rose 13%. On operations, we expanded our biomass self-supply business while cutting costs. Our CO2 emissions fell 47% compared with 2018, and we did very well in the system support markets. Lastly, the final part of the presentation will cover our strategic progress on biomass. Good progress is being made on our biomass investments and on developing BECCS. Alongside today's results, we made another very significant announcement, the end of coal generation at Drax Power Station. That's a major milestone on the journey to becoming a carbon-negative company. Over the course of 10 years, we will have gone from reporting emissions of more than 22 million tonnes of CO2 per year to 0. Having not received the Capacity Market contract in the T-3 auction in January on our coal units, we've consulted with the government over the last month before making this decision. While very much in line with the U.K. government's objective of achieving net-zero by 2050, it's not an easy day for many of the Drax Power Station.
Dwight Gardiner
executiveWe’ll also be coordinating closely with staff and their representatives in the weeks and months ahead. Between 200 and 230 roles are going to be impacted by the closure, and this marks the following stage in reshaping Drax Power Station so it can operate safely and economically beyond 2027. Although we’re continuing to finalize the financial impact during the first half of this year, we wanted to provide an initial estimate. Closure costs are expected to fall somewhere between GBP 25 million and GBP 35 million. Savings on ongoing operating expense will range from GBP 25 million to GBP 30 million — GBP 35 million annually, once those are finished at some point next year. The carrying value of the affected assets is roughly GBP 240 million. We also hold approximately GBP 100 million in coal inventories, which we anticipate using before the closure. That will likely cause a modest short-term rise in coal generation this year before it drops back to 0 next year. By switching Drax Power Station from coal to sustainable biomass, we’re now nearing completion of Western Europe’s largest decarbonization project. Thanks to a mix of effective government policy, technological innovation from our team, and support from our shareholders, Drax has cut its CO2 intensity by more than any other major utility in Europe.
Dwight Gardiner
executiveAnd I think that same mix could let Drax turn into the first company in the world to be carbon-negative by using BECCS to remove CO2 from the atmosphere and speed up the U.K.'s route to net-zero. And in the same way that we're producing appealing returns for shareholders from what we've invested in renewable biomass, I think negative emissions will in the end be a very appealing financial opportunity too. That whole story wouldn't hold up if our biomass weren't sourced sustainably. We remain 100% dedicated to that, and we're also pressing ahead as the science, the understanding and the regulation change. Since our Capital Markets Day in November last year, our Independent Advisory Board has convened and published its first report. The point of it is to push back on our sustainability practices and policies so that we stay in line with best practice. The IAB, chaired by a former Chief Science Adviser to the U.K. government, Sir John Beddington, observed that the criteria we set for cutting the carbon emissions of our biomass were drawn up to mirror what a landmarked Forest Research report titled Carbon Impacts of Biomass Consumed in the EU found, and that those criteria are a faithful reading of it. In case you're unfamiliar with Forest Research, a wide range of stakeholders right across the spectrum see them as a solid guide for making sure sustainability is achieved.
Dwight Gardiner
executiveThere's a lot of material on our website about this topic, and I'd really urge all of you to take a look. At the heart of everything we do sits safety, sustainability and good governance. Our safety results remain solid, though we keep working hard to strengthen behaviors and reduce the count of recordable incidents. On ESG more broadly, we were delighted that Norges recently acknowledged the pledges Drax has made to cut its carbon emissions by moving from coal to renewables. Norges had previously left Drax out of its investment universe, and it has now confirmed that Drax will be included. That reflects our biomass transformation, and I think this morning's announcement about our coal plans gives further proof of our dedication to lowering emissions as we work toward becoming a carbon-negative business. In the same way, we take pride in the innovative ESG funding facility we established last year. The price of that funding is tied directly to our CO2 emissions, which means we'll be financially rewarded for doing the right thing and moving off coal. Last, we care deeply about the communities in which we operate. Zero Carbon Humber, our cluster working with government to deliver CCS infrastructure to the Humberside, could save 55,000 heavy industrial jobs that would otherwise be at risk in a net-zero world.
Dwight Gardiner
executiveRelatedly, we announced the Zero Carbon Skills Task Force today. Together with government, trade unions, other sectors and businesses in the North, we'll set up a task force so people can capitalize on the skills and opportunities that come as the U.K. moves toward a net-zero carbon economy. Now let me discuss how each of our 3 divisions performed, beginning with Generation. Adjusted EBITDA was strong at GBP 408 million, 76% higher than 2018. After a tough first quarter, when bad weather in the Southeast of the U.S. limited biomass generation, we ended the year strongly, with record generation in November and December. Our new hydro and gas generation assets did extremely well, delivering GBP 114 million of EBITDA, above our guidance of GBP 90 million to GBP 110 million. The acquisition pleases me greatly, as it is delivering financially and fits very much with our strategy of being the leader in system support in the U.K. We are now the fourth largest generator in the U.K., with a multi-technology portfolio spread across the country. Finally, I'd like to note that although biomass sits very much at the core of what we do, it is notable that over 25% of our Generation earnings come from hydro and thermal.
Dwight Gardiner
executiveAdding our hydro and thermal assets has substantially expanded Drax's part in backing the U.K. system. The value we earn from flexibility rose in 2019 to GBP 129 million, up from GBP 79 million in 2018. As the chart shows, the wider flexibility market — for which the service cost is a reasonable proxy — has expanded 30% across the last 2 years. That is something we are well placed to gain from. Our assets sit in good locations, from Scotland through Yorkshire down to the Southeast and Brighton, helping to move power around the grid. And this market is shifting in ways we think will bring us fresh opportunity. In January, National Grid put inertia and reactive power out to tender — 2 important ancillary services. We won one of those contracts by using one of the units we have at Cruachan. That contract runs 6 years, and we expect it to deliver roughly GBP 5 million of incremental EBITDA to Drax. Historically, those non-generation services came from large-scale rotating plant such as coal and gas. When such plant generated baseload power, the services would naturally be supplied at the same time. Given the change in the generation mix, we expect the system operator to take more actions to supply these important non-generation services.
Dwight Gardiner
executiveAnd it says something that the system operator, for the first time, is now actively tendering for longer-term contracts. We anticipate more tenders like this later in the year and going forward. Our Pellet Production business keeps growing at a good clip. EBITDA rose more than 50%, driven by a mix of higher output and lower cost. Following a tough first half caused by poor weather in the Southeast of the U.S., we lifted production by 4% year-on-year. By combining more sawmill residues with better logistics, we cut the net cost by $5 per tonne. Those initiatives, which came in over the course of the year, if actually looked at on a full year basis, should deliver $17 per tonne this year. As you know, we're also in the process of expanding our production at our 3 existing sites by 350,000 tonnes, and we are evaluating options for up to another 500,000 tonnes through satellite plants. Our Customer business had a challenging year as it moves to focus on future earnings growth. EBITDA for the year was down to GBP 17 million versus GBP 28 million the year before. I would say that within that GBP 17 million, there are about GBP 8 million of restructuring costs.
Dwight Gardiner
executiveThose expenses have enabled us to bring Haven and Opus together, which puts us in a position to spread best practice throughout the Customer business. Our push toward more profitable customers is paying off, since we raised margin per megawatt hour even as we kept adding customer meters. We've brought on some fairly interesting and appealing customers too, so the quality of the portfolio we hold feels quite good to us. Our handling of bad debt has improved considerably, which let us cut bad debt expense from GBP 31 million in 2018 down to GBP 18 million last year. For our Customer business, 2020 will be a year to concentrate on profitability by lowering its cost to serve, achieving operational excellence and further raising customer quality, and we expect that to drive higher margins and less bad debt. With that, I'll hand things over to Andy for the financial review.
Andy Skelton
executiveThanks, Will, and good morning, everyone. I'll begin with a summary on Slide 15. The financial performance for 2019 has been strong. We delivered adjusted EBITDA of GBP 410 million, which is in line with consensus and represents year-on-year growth of 64%. The integration of the hydro and gas assets has been completed successfully, and they have performed strongly, delivering GBP 114 million of adjusted EBITDA, above the top end of the guidance range of GBP 90 million to GBP 110 million. We remain strongly cash generative, and we have delivered over $1 billion of net cash from operating activities, with an average conversion rate of over 120% in the last 3 years. After adjusting for the delayed receipt of Capacity Market payments, we delivered a net debt to adjusted EBITDA ratio of 1.9x. That is ahead of our guidance of around 2x. Adjusted earnings per share of 29.9p has grown significantly from 10.4p in the prior period. The Board has proposed a final dividend of 9.5p per share, giving a full year dividend of 15.9p per share, a total cost of GBP 63 million. This represents a 13% year-on-year increase on a pence per share basis. We believe this level of dividend is sustainable through the business cycle, and we expect that it can increase further over time as our strategy delivers high future levels of EBITDA and cash.
Andy Skelton
executiveNow let's turn to Slide 16 and walk through how adjusted EBITDA growth was delivered during the period. Within our Pellet Production business, adjusted EBITDA came in at GBP 32 million, up GBP 11 million, or 52%, for the year. We are seeing solid progress on our cost reduction program, which is set to generate savings of $35 per tonne across expanded self-capacity of roughly 1.85 million tonnes by the end of 2022. That program contributed a GBP 14 million benefit during the period, which more than offset the hit from restricted raw material availability in the first quarter. The cost achieved was $161 per tonne, versus $166 per tonne in the prior period. Further gains in pellet production costs remain a key focus area and a meaningful opportunity for additional EBITDA improvement. In Generation, EBITDA reached GBP 408 million, an increase of GBP 176 million, or 76%, for the year. Of that, GBP 114 million came from hydro and thermal gas generation. The other GBP 62 million of increase at Drax Power Station reflects indexation of the biomass subsidies along with the benefit and the power price captured by running 4 biomass units flexibly across the year.
Andy Skelton
executiveUnder the ROC scheme, we have flexibility to maximize output across the 3 ROC units within an annual cap. So after the impact of restricted supplies in the first quarter, that let us generate at higher levels over the rest of the year, especially to optimize output during the higher-priced winter months. And as Will mentioned, November and December were back-to-back record months for generation on the biomass units. The advantage of the wider generation base is clear, with our hydro operations performing strongly and the provision of system support services that are not exposed to commodity prices. So the value from flexibility rose GBP 50 million in the period to GBP 129 million. Of this, around GBP 30 million relates to buybacks on coal and constraint management activities that we do not expect to recur in 2020. Adjusted EBITDA of GBP 17 million for our Customers business fell GBP 11 million year-over-year. Restructuring costs and investments in next-generation systems and the smart meter rollout came to around GBP 15 million. That's a GBP 9 million increase year-on-year. And we expect these equivalent costs to be around GBP 5 million in 2020. The restructuring costs relate to integrating our Opus and Haven businesses, where we believe they will drive alignment of decision-making, effective market segmentation and will deliver operational efficiencies.
Andy Skelton
executiveInvestments in next-generation systems, smart meters included, back our goal of boosting operating leverage. The new ERP system — spanning finance, procurement and financial reporting — has now been rolled out successfully in Haven and in Opus. We did hit some snags implementing our customer care and billing system, and that project is on hold at present. Our Customer portfolio keeps expanding and its quality keeps getting better, with customer meters up 6% and names like Severn Trent Water and Ford Motor Company added during the year. Meanwhile, margin per megawatt hour has risen as we concentrate on the quality of business. The 8% volume decline for the year mirrors that focus, along with the effect of a mild winter. Last, we've kept up positive momentum in lowering bad debt expense as a percentage of revenue. The GBP 18 million expense in the period gained from a GBP 3 million credit tied to resolving legacy balances and came in GBP 13 million below the prior period, which a one-off GBP 3 million expense related to our SME business had affected. Still, as we stay focused on managing bad debt, our smart meter rollout investments will help a great deal.
Andy Skelton
executiveWe still see room for better performance and earnings in our Customer business in the years ahead. Then lastly, corporate and other costs rose by GBP 16 million during the period, which partly reflects the larger size of the group following our purchase of the hydro and gas assets. Over the year, we also raised investment to back innovation work, including broadening our biomass fuel envelope and supporting what we are doing on BECCS. On top of that, after the acquisition, we took on some onetime costs to put a new organization structure in place that we will -- believe will let us carry out our strategy more effectively. The run rate of those costs came down in the second half of the year. And looking ahead to 2020, we expect to spend more on innovation while keeping corporate costs at a similar level. So turning to Slide 17, which gives a further breakdown of adjusted EBITDA across the group. Our Generation business is made up of Drax Power Station plus our hydro and gas businesses. The power station is the biggest, delivering GBP 294 million of EBITDA from 14 terawatt hours of generation. Coal accounted for only 0.6 terawatt hours, or 4% of the power station's output for the year, and that is a good proxy for how much coal contributed to the power station's EBITDA.
Andy Skelton
executiveOnce the coal units formally shut down by September 22, our Generation business is going to be made up of sustainable biomass, hydro, and thermal gas — and all of those have the flexibility to run in the power market as well as in providing system support services, where we expect growth in the future. Our biomass units generate more than 12% of the U.K.'s renewable electricity, backed by index-linked ROC and CfD contracts and supported by a robust hedging policy. They give us a strong base of high-quality earnings and cash flows. Our hydro business accounts for 18% of the adjusted EBITDA. As for our Cruachan pump storage asset, operating it in the growing system support market underpins a high level of earnings visibility both today and over the longer term. The contribution from the newly acquired assets means 2x cover on our dividend from sources not related to biomass. So, moving to Page 18. We've delivered a net debt to adjusted EBITDA ratio of 1.9x, which is ahead of the guidance we gave of around 2x. And that's when adjusting for the capacity market payments that have now been received. I'll cover capital investments and debt service costs shortly. So on this slide, I'd like to highlight that the effective rate of tax of 17% in the period benefits from relief arising from the U.K.
Andy Skelton
executiveOn the patent box regime: we still expect our effective tax rate to sit marginally under the U.K. headline rate. The GBP 10 million of cash outflows during the year are simply payments on account made in the period. We generated roughly GBP 50 million of working capital and other inflows in the period. That figure includes an inflow of about GBP 54 million from selling ROCs under a standard ROC sale and purchase agreement; an inflow of GBP 84 million tied to rebasing certain foreign currency exchange contracts inside our multibillion-dollar derivatives portfolio — that rebasing had no impact on EBITDA; an inflow of GBP 50 million from improvements in payable terms; an offsetting inventory outflow of GBP 68 million, half of it from building up biomass supplies ahead of the first quarter of this year after the restricted supplies seen at the start of last year; and, obviously, an outflow related to capacity market income, where payments were deferred until the first quarter of this year. Our long-term target of a net debt to adjusted EBITDA ratio of around 2x remains in place. And although the cycle may bring fluctuations, our strong cash conversion gives us the ability to delever quickly.
Andy Skelton
executiveTurning to Slide 19, capital expenditure for the year came to GBP 172 million, and that figure includes GBP 59 million of maintenance spend. At Drax Power Station there were 2 planned biomass outages, one of which was the first for unit 4 after its conversion to biomass. For 2020, we expect maintenance CapEx to land between GBP 60 million and GBP 70 million. The GBP 15 million of CapEx on the acquired assets covers an interim inspection at Shoreham, and that inspection made it possible for the plant to return to service during the more valuable winter period. That inspection work supports the option for a turbine upgrade, which we anticipate will be part of the 2020 CapEx spend, and 2020 also includes a planned outage at Damhead Creek. Our strategic investments of GBP 67 million take in around GBP 20 million in our Pellet Production business, supporting the target of cutting cost and raising the volume of biomass self-supply. That covers the LaSalle railway spur, which brings transportation costs down, and the beginning of the expansion of our 3 pellet plants. At the power station, we spent GBP 13 million to deliver the first of a 3-unit, 3-year high-pressure turbine upgrade program with Siemens. The second turbine upgrade is due to be delivered in 2020.
Andy Skelton
executiveThis investment also helps us toward our goal of lowering the cost of biomass generation. During 2020, we anticipate that spending tied to our self-supply objectives will rise considerably, including roughly GBP 40 million for the 350,000-tonne pellet plant expansions, lifting capacity to approximately 1.85 million tonnes by the close of the first half of 2021. As Will noted, we are looking at possibilities for satellite plants as well as broadening our fuel envelope. Regarding satellites, capacity could grow by as much as 500,000 tonnes, with roughly 40,000 tonnes coming from each plant at a cost between $10 million and $15 million. We anticipate developing the first one in 2020. These investments provide appealing returns ahead of 2027 that comfortably exceed our cost of capital. Now let's move to Slide 20. At our latest Capital Markets Day, we set out a target of growing biomass self-supply capacity to 5 million tonnes by 2027, alongside a 30% cut in the cost of biomass to GBP 50 per megawatt hour. In order to achieve that 30% reduction, we described plans for $35 per tonne in cost savings across our self-supply capacity by the end of 2022. That works out to $64 million in equivalent cost savings, and I want to give you an update on how we are progressing.
Andy Skelton
executiveIn the year, Pellet Production EBITDA came to GBP 32 million, and that figure got a boost of $19 million, or GBP 14 million, from savings tied to projects finished in 2019. Among those is the LaSalle railway spur, up and running in May; the Hunt Forest sawmill co-location, which went live in the first quarter at LaSalle, where the volumes under our offtake agreements for sawmill residues have been climbing all year; and also the work at LaSalle to decommission the woodyard. A further lift came from a full year's run rate on moving our head office in the States from Atlanta to Monroe. For 2020, we expect the annual run rate from these already-delivered projects to reach $26 million. That leaves $38 million still to come by 2022, and it will arrive through the 350,000-tonne expansion at LaSalle, Amite and Morehouse, which as I said should wrap up in the first half of '21; the woodyard decommissioning work at Amite and Morehouse, where we have already done a similar exercise and captured the savings at LaSalle; sawmill co-locations at Amite and Morehouse, repeating the benefit of the Hunt Forest co-location agreement already in place at LaSalle; then completion of the chambering yard at the Port of Baton Rouge; and lastly, greater use of dry shavings.
Andy Skelton
executiveNow let's turn to Slide 21. Across the past 2 years, our ability to raise capital has improved substantially, and at the same time we've kept a solid balance sheet in place to back our strategy. During May, we added a $200 million tap onto the existing fixed rate November '25 U.S. bonds, and once that was swapped back into sterling, it came with an effective interest rate of approximately 5%. Then in July, we finished refinancing the GBP 400 million that remained outstanding under the acquisition bridge facility, putting in place new -- 2 new senior debt facilities. The first of these was a GBP 375 million private placement agreement, and the second was a GBP 125 million ESG facility agreement. That GBP 375 million private placement with infrastructure lenders contains facilities whose maturities run from 2024 by extending out to 2029. The GBP 125 million ESG facility reaches maturity in 2022, though it carries a mechanism that adjusts our margin according to Drax carbon emissions measured against an annual benchmark, which reflects the commitment we continue to show toward cutting carbon emissions as part of our wider purpose. Taken together, these facilities pushed the group's debt maturity profile out past 2027 at a cost sub-3% and brought the group's overall cost of debt down to below 4%. Following the acquisition of our hydro and gas assets, the quality of our enlarged generation portfolio keeps helping to mitigate business risk.
Andy Skelton
executiveThe business produces high-quality earnings and generates robust cash. That reduced business risk means we can obtain credit more cheaply. It supports how we trade, and it holds up even when the commodity cycle hits its low points. We have shown we can tap a broad spread of debt markets, and we will keep looking at additional ways to fine-tune our debt structure. Now let's turn to Slide 22. Our capital allocation decisions are made with discipline, and we still view our approach as having 4 stages. First comes keeping a strong balance sheet, which for us means target net debt to adjusted EBITDA of around 2x. After that, we keep investing in the core business so our strategy gets delivered. Third is a dividend that is sustainable and growing. The 13% increase for the year on a pence per share basis fits with that goal, though how much growth there is precisely will differ year-to-year, depending on the operating environment and what the business needs to invest. Last, we look at a broad range of development projects throughout the group, which come with attractive returns but might need substantial future investment, as set out at our Capital Markets Day, particularly regarding the aim of cutting pellet costs and growing capacity.
Andy Skelton
executiveAll the way through, we'll keep up financial discipline and make sure our capital structure stays prudent. The recent BBB flat investment-grade rating from DBRS backs this up and gives further confirmation that our business risk has improved. So finally, moving on to Slide 23 and summing up. In Pellet Production, our focus is on cutting cost and growing the capacity of biomass self-supply. That demands strong performance from the pellet plants so we maximize the value of the cost savings from projects completed in 2019. We also have to deliver on the ongoing projects as outlined earlier, including the 350,000-tonne expansion of our existing plants. Beyond this, we're stepping up investment in innovation to support our continuing work on BECCS and development of a wider fuel basket. In Generation, our contracted position for 2020 is strong. And we need to keep delivering excellent operational performance while maximizing the value we deliver through system support services across our asset base. As we finalize plans for the closure of coal, we estimate the cost of closure to be GBP 25 million to GBP 35 million. We expect to provide for these costs in 2020 and that the cash outflows will happen through 2022. We estimate the OpEx run rate savings of GBP 25 million to GBP 35 million per annum once complete.
Andy Skelton
executiveAs we wrap up the plans for shutting down the coal units, we will be taking a look at the carrying value of the affected assets, which we estimate at roughly GBP 240 million. Out of that amount, approximately GBP 140 million will have been depreciated through 2025. The rest of those assets get depreciated across useful lives running out to 2039. We anticipate using up the coal inventory balance, which sits at about GBP 100 million, by the point when commercial coal generation comes to an end. Within our Customer business, our attention is on the quality of the business as well as on pushing operational efficiency and securing earnings growth going forward. So to sum up, during 2019 we performed strongly relative to our financial targets, and we advanced and built out our strategic plans, which puts us in a good position for the opportunities that lie ahead. With that said, I will turn things back over to Will.
Dwight Gardiner
executiveThanks, Andy. I'd now like to provide an update on the biomass strategy. At our Capital Markets Day, we introduced the new biomass strategy. I've given a summary of it here, including the ambition of building the largest low-cost sustainable biomass supply chain in the world. As a reminder, the aim is to raise self-supply to 5 million tonnes and to bring the cost of biomass generation down to GBP 50 per megawatt hour. All of this rests on our world-leading sustainability policy, on building biomass trading capability, and on developing carbon-negative technologies. In our view, the strategy brings multiple benefits. First, it will make biomass generation at Drax Power Station viable without subsidy. Second, it will create a world-leading biomass supply business with substantial value in its own right. Third, it will put us in position to deliver negative emissions at scale. Let me also remind you of a few details of the plan. Over the next 7 years, between now and 2027, we will lift self-supply from roughly 1.5 million tonnes today to 5 million tonnes, while at the same time cutting the cost of biomass power generation to GBP 50 per megawatt hour from around GBP 75 today.
Dwight Gardiner
executiveWe'll accomplish this through a number of approaches. To start, there's a set of upgrades and expansions at the plants we already operate, which Andy laid out, delivering $35 a tonne, or GBP 13 per megawatt hour, in cost savings along with 1.85 million tonnes by 2022. Second, we're growing our self-supply via satellite plants, where we're examining 500,000 tonnes of new capacity. Third, we're reviewing other appealing investment possibilities that could bring further additional capacity. And fourth, we're considering widening our fuel envelope to take in other fuel types, such as bagasse. Lastly, we're exploring a set of innovations that we might potentially deploy across the supply chain to cut cost, be that modifications to fuel or modifications to logistics. Let me give you a quick update on BECCS. To begin, as a reminder, Drax will play one specific role in the entire carbon capture and storage value chain. What we'll do, then, is capture the CO2. To achieve that, we're examining several distinct options for carrying out the carbon capture. The first entails deploying proven amine-based technologies that can deliver, and have been proven to deliver, carbon capture at scale today.
Dwight Gardiner
executiveThey have been in this industry for more than 30 years, and 2 reference plants in North America each capture over 1 million tonnes annually. The second option we have already discussed is that our trials with C-Capture are ongoing, and in time we expect that approach could cost less than those amine-based technologies. That process is progressing well, and right now we are testing the technology at a carbon capture testing facility in Norway that is recognized worldwide. And as we said before, with the right backing from government, we could have BECCS running at scale and delivering negative emissions in the second half of this decade. Another point I wanted to raise is that we have set up a carbon capture innovation hub at the Drax Power Station and are collaborating with start-ups to look into using CO2 in plastics and in animal feeds as well. And we are also starting to hold discussions with large-scale users who are exploring the production of synthetic fuels using a combination of CO2 that we capture and hydrogen that in the end might be produced at or near the Drax Power Station. In 2019, we launched Zero Carbon Humber, a partnership with Equinor and National Grid that is committed to decarbonizing the U.K.'s most carbon-intensive industrial cluster around the Humber through BECCS, CCS and, ultimately, hydrogen technology.
Dwight Gardiner
executiveBy doing that, we can seize the chance to capture and store, I should clarify, a larger volume of CO2 than any other location in the U.K. — over 40 million tonnes annually by 2045. There's also an opportunity for us to protect 55,000 industrial jobs and to generate new green jobs within a strategically vital industrial hub in the North. From the time of the launch, we have collaborated intensively with several industrial players across the region to build a comprehensive plan for the CCUS network, connecting with numerous CO2-emitting businesses there and enabling us to gain economies of scale in transport and storage. Industrial cluster decarbonization is a key policy focus for the present government, and we anticipate substantial funding announcements throughout 2020, such as the GBP 800 million pledged in the conservative election manifesto and roughly GBP 132 million for the Industrial strategy Challenge Fund, which might help advance the Zero Carbon Humber. And let me discuss briefly what we believe will occur, including some key milestones for CCS and BECCS during this year. So at the start of the year, the political situation is far more stable than it has been for quite a while.
Dwight Gardiner
executiveThe government is dedicated to the North of England, and it's dedicated to net-zero as well. We're collaborating closely with Kwasi Kwarteng, the Energy Minister, and we're enthusiastic about what we see on the horizon during this year. Let me point out a few key events we're anticipating. First comes an energy white paper, due in the first quarter, which should refresh the government's vision for CCUS and for negative emissions, responding to the Climate Change Committee's net-zero report. In the budget — the spring budget, due in a couple of weeks — we anticipate the government will announce GBP 800 million, or rather at least GBP 800 million, in fresh funding for CCS infrastructure and, crucially, how it will be distributed. Right now it isn't exactly clear how they plan to spend that, and I'll gladly take questions about it shortly. Later in the year, the Treasury will publish its net-zero review, setting out innovative new approaches to generating the investment needed to deliver net-zero. And finally, this builds on ongoing engagement with industry across 2020. As you'll recall, this process got underway early last year.
Dwight Gardiner
executiveWe anticipate that in Q4, the government will release more specifics regarding the investment framework for CCUS, potentially including draft versions of the support contract types that would be offered for carbon capture and storage. All this effort will come to a head at COP 26, where we see a very substantial chance for the U.K. to assume a world-leading stance on carbon capture and on negative emissions too. One key point to add: no one has done more work than we have on BECCS to grasp its potential — that is, how much could be achieved globally, along with its costs. And we hold a very strong belief that it can have a meaningful global effect on climate change — in other words, the quantity of negative emissions could be quite substantial. And second, that we can provide those negative emissions at a cost substantially below what is currently seen publicly. So, if you look at the Climate Change Committee's report, which calls for roughly 50 million tonnes of negative emissions from BECCS, those figures rest on their cost estimate. If we can achieve it for substantially less than that, we think the opportunity could at minimum be that large or considerably larger.
Dwight Gardiner
executiveAs you'd expect, we'll share that work with the government while they develop their own positions on future negative emissions. So to sum up, we have a clear purpose, and our strategy has 3 legs built to deliver it. And I believe exciting opportunities exist in every one of those areas. First, on biomass, we can achieve significant cost reduction and capacity expansion as we deliver those, and that's a critical objective for us this year. Consistent with that biomass strategy, we're working hard to make significant progress on BECCS so that it becomes a reality at the Drax Power Station in the mid-2020s. Thirdly, we have attractive opportunities to invest in providing power system stability. Again, we expect tenders -- more tenders for those types of investments later this year, and new opportunities to potentially build synchronous compensators or to convert existing assets to synchronous compensators. Again, we expect that later this year. And finally, in our Customer business, we're very focused on driving future earnings through operational excellence and cost control. So thank you very much, and I'm happy to take -- probably Andy is more happy.
Dwight Gardiner
executiveWe’re glad to take questions from anyone.
Elchin Mammadov
analystElchin Mammadov from Bloomberg Intelligence here, with 3 questions if I may. First, could you possibly provide your guidance for 2020 earnings? You touched on the leverage ratio, but I'd like it in terms of EBITDA, EBIT, or net income. My second question concerns CCS, which you just brought up. Given current energy prices, what level of support do you believe commercial-scale CCUS requires — whether expressed as pounds per tonne of CO2 or per megawatt hour? And lastly, what is your perspective on the upcoming T-4 capacity auction? Prices have, after all, been declining, so I'm curious to hear your thoughts.
Dwight Gardiner
executiveAlright. Perhaps I’ll have Andy handle the first one, and then I can cover the remaining two.
Andy Skelton
executiveYeah, so earlier this week we put out the company's take on where consensus stands right now. And just to flag it, that figure came in at GBP 433 million.
Dwight Gardiner
executiveRegarding CCS, the Climate Change Committee report mentioned a cost — BECCS runs around GBP 150 per tonne of negative emissions, correct? And like I said, I believe we can achieve that at a considerably lower figure, right? Third point regarding T-4: it would be foolish of me to hand you any kind of forecast. What I mean is, I think auction demand is weaker. More newbuild capacity has come in. There are some — possibly certain nuclear assets could act differently from what we anticipated. So my answer would be, it's anyone's guess. Clearly, GBP 6.44 was not an appealing level from a new project's perspective. And we'll keep going — perhaps to elaborate a little on what may lie behind the question, we still believe we hold 6 highly attractive projects: the 2 combined cycles plus the 4 open cycles. The Drax Power Station project is presently paused pending the judicial review, and that project has not been entered into the T-4. But we'd be seeking — once more, we'll hold off until the right returns are available to make those projects appealing.
Dwight Gardiner
executiveMark?
Mark Freshney
analystMark Freshney here from Crédit Suisse, with two questions. First off, regarding the forward hedge position, it looks really robust. You mentioned a buyback benefit of GBP 30 million. Given power prices at present, there must be considerable upside from trading that book across the year. So would that be part of your GBP 433 million expectation, or the GBP 433 million consensus? And then second, on cash flow conversion. Andy, you talked about an average of, I believe, 120% cash conversion. Obviously, there's monetization of the coal stocks, which you said would occur this year, and you've provided a figure. But what else is available? Should we anticipate any further positive working capital flows?
Andy Skelton
executiveAlright. First, regarding the hedge position, just to note that this was a market consensus we published, not a forecast from us. But on the hedge position, you're correct, we're very well hedged for 2020. I believe it's around GBP 54, so substantially better than current commodity prices. However, our ability to benefit from that is reflected in our expectations for next year. On cash conversion, you're right that at 120% cash conversion, you can't keep doing that without delivering additional working capital benefits. Looking to next year, I think, broadly, the working capital we should expect to be neutral. Primarily, we have to offset the rebasing activities we did this year. We also have — we have an inflow from the capacity market, which will help in that regard, and we have the inventory balances on the coal that we'll consume before closure. But next year, I'd expect working capital to be broadly neutral.
Dwight Gardiner
executiveJust to talk to you, Mark. First, I think that GBP 30 million Andy mentioned came from a mix of the coal buybacks plus the constrained contracts that won't happen again. And I'd say that with the coal trading strategies, being flexible will be tougher for us because of the need we have to work through that coal stock.
Martin Young
analystMartin Young here, from Investec. A couple of questions, if I may. First, on shutting the coal units at Drax, and those figures you published. On OpEx, with GBP 25 million to GBP 35 million of savings, is the right way to view it that a modest portion lands in 2022, with the full run rate arriving in 2023? Then, regarding the indications you gave on depreciation — specifically the GBP 140 million tied to assets being depreciated by 2025 — should we now effectively expect roughly GBP 25 million of depreciation savings each year starting from 2020? That was question one. Question two concerns the wide set of investment options you have, both here and across in the U.S. Looking specifically at the OCGTs and the CCGTs, would it be fair to say those are potentially slipping down the ranking, while expansion of Cruachan and everything you plan to do with biomass gets higher priority and a stronger likelihood of being realized?
Dwight Gardiner
executiveWould you like to start us off with the first question?
Andy Skelton
executiveYes. Regarding when those savings land, the cost reductions come from redundancy, from pension costs, and then from certain site rectification and normalization costs. Right now the coal units are an integral part of the station. So once you stop running the coal units, making them safe and getting the station to work with 4 units carries some cost to deliver that. But mainly, as coal generation ends in '21, that's when headcount will begin to come down, and the savings get delivered from there. Some will come before, but mostly from '21 through '22. On depreciation, if you think of GBP 140 million being depreciated over 6 years, do the math, it's around GBP 25 million. The balance is over 20 years. That adds another GBP 5 million. So you're at roughly GBP 30 million a year of depreciation savings if we were to impair the full GBP 240 million that we need to review.
Martin Young
analystIs there a chance of that taking place at this point, in 2020?
Andy Skelton
executiveSo, we anticipate wrapping up the review in 2020, as we finalize the closure plans after today's announcement. Once that's done, savings will begin from that point forward. There could be some depreciation expense during the year up until the moment we make that decision.
Dwight Gardiner
executiveNow regarding your second question about the range of options we have. I think maybe I'll take a moment to explain how we, as a Board, approach this topic, since really multiple factors feed into the evaluation. Obviously, one is purpose-driven — how do the various investments fit with that. Then there are strategic considerations — are they in line with our strategy. And another one is, clearly, returns, size and risk, correct? So when I look at the pellet expansion strategy, I think it satisfies all of those criteria very well. The risk, I would say, is very attractive, given that we have a known customer, and so on. So very attractive from a risk standpoint. They are also moderately sized, which I think makes them interesting as well. And the returns are very attractive, and they fundamentally support our purpose, right? When I look at things such as the Cruachan expansion, that too is consistent with all of those, except that it would be a large investment and one that probably would need some kind of government framework for it to work, correct?
Dwight Gardiner
executiveThen, when I look at those open cycles, I'd say they line up quite well with our approach of being the top provider of system stability and support. Each of them, again, is of a reasonably moderate size. So I think the risk here is fairly manageable. The real challenge lies in securing the appropriate kind of support within the capacity market so that the returns become appealing, correct? Combined cycles, I'd note, are — in certain respects, probably different in character because of how large they are. Once more, we believe there are appealing opportunities in that area, along with appealing potential returns, contingent on where the Capacity Market lands. To sum up, I suppose you've likely formed your assessment by now. What I mean is, if you weigh all of those factors, the way you're approaching it is probably consistent with our own thinking.
Iain Turner
analystIain Turner here from Exane. On the coal closure, I'd like to understand why the decision has been taken at this point, and why not hold off until the T-4 auction in case prices rise. And then, what does that imply regarding the future of those units? You've mentioned conversion, but clearly there is the judicial review on that. So does this mean you'll essentially be demolishing these units? Or will they remain in place awaiting a decision on a possible CCGT conversion or additional biomass conversion?
Dwight Gardiner
executiveI mean, honestly, when we weighed the probable results, the kind of risk we'd be taking on, and the contract level they'd be asking for, the economics of the decision were pretty clear. And once you factor in some of the other stakeholder issues, it felt to us like this was very much the right moment to act. It's important to say, though, that this wasn't taken lightly at all. As I mentioned, we've had good talks with government. We'll be holding thorough, extensive discussions with our unions and other employee representatives so that we back our people through this in the proper way. But we felt it was the right moment both for us and for the system to move away from coal, correct? Honestly, another key factor behind it is that we have 4 units that run on biomass, right? So the power station does have a future through 2027, and I'm fairly confident past that as well, right? As for what we do with those units now, the first step is — well, probably 3 steps, right? First, we'll operate them through 2021 in the same way we do today, right?
Dwight Gardiner
executiveAnd we still need to work through that coal stock. From March '21 through September of 2022, we'll be on hand if the system requires us. As everyone knows, no Capacity Market event has occurred up to now. So we'll be prepared should one arise, though I doubt it's a probable occurrence. Even so, we'll be there to meet our obligations. The following stage is that we'll then make them safe, correct? That means ensuring we handle them properly, shutting down whatever requires shutting down, and managing the assets so they're genuinely safe, though they won't be taken apart right away. From there onward, several possibilities exist — repowering remains one of them. Certainly, we're examining it, on the assumption that the judicial review turns out the way we anticipate and our planning permission holds. So that clearly remains an opportunity. Another interesting point is that when this stability tender appeared, one option available is to take a coal-fired power station, in effect disconnect the generator, convert it into a synchronous compensator, and operate it to deliver no megawatts whatsoever — just inertia reactive power.
Dwight Gardiner
executiveThat's definitely another area we'll be examining too, and we anticipate additional tenders along those lines. Fraser, go ahead.
Fraser McLaren
analystThis is Fraser McLaren calling from Bank of America, and I have a couple of questions if I may. First, regarding supply: I'd like to hear how you see things developing on that front. I think it's reasonable to say the situation hasn't gone quite according to plan, so what has actually shifted? And does it remain necessary as part of the group? Second, you mentioned some news flow you're anticipating from the government. When exactly do you expect them to address the carbon tax itself, what do you believe that will involve, and how does that result connect to whether BECCS can remain viable?
Dwight Gardiner
executiveAll right, sure. So let's think about the supply business first, okay? Regarding supply, I'd like to begin with its back end. Basically, as I mentioned, what our supply business does is give customers control over their energy and let them provide things like demand-side response or other forms of system support services as that market grows. From a strategic standpoint, that part remains something we have a lot of confidence in. We want to hold a position on both the demand side and the supply side as the system changes over time. For instance, we're putting substantial effort into managing electric vehicles, and we already have our first customers there; in effect, the initial step involves installing EV infrastructure for those customers. Then, as time goes on, the possibility of managing B2G-type services strikes us as a rather interesting angle. The second element, which I see as a growing leg of that business, is more about how, strategically, we can assist customers in reaching their own ESG objectives, correct?
Dwight Gardiner
executiveSo I'd say that's pretty appealing for certain players who themselves have a really robust ESG agenda, to collaborate with us in a straightforward manner to supply power that's renewable or carbon-free and/or gas. But additionally, as we get somewhat more -- if we progress further toward turning into a company with negative emissions, they also -- we're having fascinating conversations with them about the way we might share that ambition of ours with them on those terms, correct? When I examine operations, how we did, once more, we haven't performed to the level I'd have preferred. Rather let down by that in certain respects. The -- what took place there? I believe there are a couple of factors. As I'd put it, combining the 2 businesses, Haven and Opus, likely wasn't as simple as we'd have hoped. Certain outside forces have proven rather challenging and items such as last year, the mutualization of ROC payments, for instance, sort of the -- I mean the price gap hasn't affected us. Yet again, conditions for supplying electricity and supplying gas haven't been all that favorable, weather, there's an entire set of various factors, right? What gets me most enthusiastic is Paul, who's present somewhere around here, who's now at the helm of that business, with a very sharp focus on the ways we can deliver via operational excellence.
Dwight Gardiner
executiveSo here's an example of what we did at Haven: we implemented something we refer to as 4E, which basically stands for excellence every day. And in practice, that initiative gets the frontline people more engaged in figuring out how we address customer problems, right? That's producing some quite interesting results at Haven, and we're now going to extend it over to Opus, right? So there are a number of elements we have to get right, and that covers debt management, where we're improving, and it touches cost to serve, where we also need to deliver further improvements. But once more, the last thing I'd mention is that, when you look at top-line growth and customer growth in that business, it's still — I believe we have a very appealing portfolio, right? As Andy said, Ford Motor Company, Severn Trent. We completed a very interesting deal with Budweiser, under which we're essentially running a channel-style arrangement with them for pubs. So I think there are definitely appealing opportunities there. So that would be supply, neutral from the government. Carbon tax, could come at the spring budget, could come later.
Dwight Gardiner
executiveObviously, this matters a great deal to us. In the near term, people have been discussing substituting the EU ETS with a measure such as a GBP 18 tax. So I believe that's -- I don't wish to -- my crystal ball isn't reliable on this, so no genuine forecasts will come from me. Over the long run, the notion that U.K. and European carbon prices would ultimately converge strikes me as economically the logical outcome. How might that occur? Take, for instance, whether a U.K. ETS exists -- meaning the U.K. Emissions Trading System -- that is linked in some manner to the European version. That would be what we'd prefer, whether linked or combined. Now, how these negotiations unfold across the next year is anybody's guess. But economically, I do believe that's where the logic ought to lead you, correct? Again, if we're going to be part of the European system, and even without a link, power prices, because of interconnectors, should be affected by where European taxes go regardless, right? And my expectation is very clear that European ETS prices will climb significantly should they intend to reach their net-zero target by 2050 as well.
Dwight Gardiner
executiveThat's what I'll say on that point. So on BECCS viability — perhaps we should look at this in a wider context. I mean, if the U.K. and the rest of the world are going to reach net-zero by 2050, some mechanism has to exist through which carbon emissions are either taxed or regulated so that they become less attractive, right? By the same token, sound economic logic would suggest the reverse should hold as well — namely, that negative emissions get incentivized, right? In my view, a tax or a government levy is the most sensible route to achieve that. None of that has happened yet, but I'm firmly convinced that if the world is going to get there, it must be in place, right? So an economic logic must exist that supports BECCS and supports reaching net-zero, and that's what we would expect to take part in. Exactly how it will happen? To be determined.
Dominic Nash
analystIt's Dom Nash from Barclays, and I've got a couple of questions, please. You've set a goal of cutting biomass costs by GBP 50 per megawatt hour, and I believe the aim there was subsidy-free generation. But at that level, you'd only be a mid-merit peaking power station. You wouldn't necessarily be willing that hard. Your subsidy that contend in 2027 — when does the conversation with the government begin? Or when will we start hearing about whether there's going to be an extension of the subsidy to boost output, particularly in light of whether you're going to go down about this route? Then the follow-up on that is that you obviously — you've got plans — you're talking 2.2 million tonnes of pellet in; if you had done the 2 extensions and the satellite plants, you still will build out another sort of 2.8 million tonnes. When will we get clarity on when you're going to press a button on that?
Dwight Gardiner
executiveAll right, perhaps I'll go with those. I mean, in my view, the single most effective route for the government to support keeping the Drax Power Station running longer is through BECCS, correct? So the conversations we're currently holding with them center on exactly that — what mechanisms could incentivize negative emissions. And perhaps we understate the point that the majority of negative emissions technologies — direct air capture being the other clear example — don't generate power at all. They consume enormous amounts of it. That gives strong economic reasoning for why keeping Drax Power Station, with negative emissions, at the heart of the U.K. system over a long period makes a great deal of sense, right? So that's point one. Point two is that this is becoming so — and that will be over the next year or 2. Meanwhile, I'm already in talks with certain suppliers. I mean, we don't call attention to this, but obviously, if I approach a supplier and tell them I can offer a contract through 2027, the window for that payback is narrowing, right? So that's beginning to come up as an issue. The other one concerns capital providers, right? I mean, clearly, we will — we have a sense of how the equity market views things, but as for the debt markets, I mean, we're pushing our debt profile out past 2027.
Dwight Gardiner
executiveHowever, when we carry out refinancings, we also have to be able to answer those questions. So it isn't far off. That said, from my conversations with the government, I believe the best option, or the best answer for everybody at this point, is BECCS, though it will take 1 or 2 years before we get there — I think we ought to resolve it. And your second question was...
Dominic Nash
analyst<<inaudible>>
Dwight Gardiner
executiveOh, sorry, that's fine. So I think when we discuss this, roughly half of the puzzle already exists. Well, there are 3 pieces. The existing capacity — I think we've got solid plans in place there. The second piece involves potentially additional pellets. I mean, let's say, out of that 5 million, between — I was — I think of it as roughly between 2 million and 3 million on pellets and between 2 million and 3 million potentially on other kinds of viable fuels. So my — we are going to bring it to the Board for a final investment decision. As for the satellite plants, we're also going to return to them this year and discuss bagasse and potentially a bagasse pelleting plant. And so I would hope to come to you at mid-year with a discussion of both of those topics and more — the beginnings of greater clarity on how we reach that 5 million. Yes?
Alexander Wheeler
analystAlex Wheeler here from RBC, with a couple of questions if I may. First, regarding the flexibility value of GBP 129 million: once we strip out the GBP 30 million that Andy has already noted won't repeat this year, how do you see that underlying figure trending from here? Second, on the coal assets, will those be sold along with the coal capacity market contracts? Would that be something you'd consider doing?
Dwight Gardiner
executiveI think with the first one, once you strip out that GBP 30 million, you land at roughly GBP 100 million, compared with about GBP 90 million in the prior year. What I'd say is — over the longer run, I should note — we do expect growth in that market. There's no doubt about it, right? And that growth will come both from more balancing market activity and potentially more contracted activity, as we've described. A few of the items we submitted into that stability pathfinder tender were genuine investment projects where capital actually gets deployed by us. The returns look attractive, and we see solid opportunities for earnings there. I'd frame it this way: by its very nature, this is a volatility play, right? So you shouldn't expect a straight line. Which means certain years might be — or rather, we would anticipate certain years will outperform others, right? On the — I've lost track of the second question, my apologies.
Alexander Wheeler
analystRegarding the coal capacity market contracts.
Dwight Gardiner
executiveOh, alright. So yes, that does exist. Those transfers are technically permitted. And I believe it's occurred on at least 1 other occasion. Buyers aren't plentiful. So we'll attempt it. Should it make economic sense, we'll go ahead with it, though I'm not holding my breath.
Adam Forsyth
analystAdam Forsyth at Longspur here. I'd like to hear a bit about what you've learned from the tender in the synchronous market. In your view, is participation broad enough that the pricing can serve as a sensible benchmark for tenders from here on? And if that's the case, in what way would it underpin additional investment at Cruachan, especially in light of what you said about the need for a government framework? How do you see that playing out? Would grid reform be enough on that front — would reform of grid charges be enough?
Dwight Gardiner
executiveI'm going to tread carefully on this one, perhaps. The thing is, it isn't really clear to us precisely how that tender was structured, or precisely how the winners ended up being picked, correct? So we've done a great deal of reverse engineering to try to figure it out. There's obviously a price dimension — I mean, if you look at price per megawatt or per half hour of availability, I think a lot of the answers come out of that, but it isn't exact, right? So there's a locational component that's playing a role, and frankly, I know we don't yet fully grasp it — I'm certain of that. And we would welcome — we'd want — we would ask grid for greater visibility and transparency, since that would be a help. So to answer your question about whether there's enough information for a kind of certainty or genuine clarity on pricing, I'm not sure we're there yet. Still, it has been useful, because having that tender has definitely made a big difference in moving us toward a more transparent picture, yes. So when I think about the kinds of investments we might make, the other issue is that the tender of the contract is a 6-year deal, right?
Dwight Gardiner
executiveSo I could — I could look at adjusting assets that already exist, such as a coal plant. And we're discussing investments in the small tens of millions range, where I might be able to earn a return over 6 years and make it work. But again, we put one of those in and it didn't win. So it is — but it is — that's not far away, shall we say, right? And if we had more time, and when we have more time, I would expect that we will try to do that type of thing again. Doing an expansion of Cruachan, so what we call a Cruachan 2, adding more turbines, et cetera, that is a very, very big project, which will not earn a return in 6 years. And this is not — this revenue would not be sufficient for that. So that's the kind of thing why I say we need a framework. If we want to do that, we would need to have a really bilateral discussion with the government, U.K. or Scottish government, on how that might work. Anything else? Thank you all for coming, and we'll be around if you wanted to ask any questions in private.
Dwight Gardiner
executiveI appreciate it.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Drax Group plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Drax Group plc earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Drax Group plc or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.