Edison International (EIX) Earnings Call Transcript & Summary
May 2, 2023
Earnings Call Speaker Segments
Sam Ramraj
executiveThanks, Ted, and hello, everybody. Joining us on this call are Pedro Pizarro, our President and Chief Executive Officer, along with Maria Rigatti, Executive Vice President and Chief Financial Officer; other members of the management team are also with us. You can find materials for today's call at www.edisoninvestor.com. Those materials include our Form 10-Q, remarks that Pedro and Maria have prepared, and the teleconference presentation. Our regular business update presentation will go out tomorrow. On this call, we'll be making forward-looking statements regarding the outlook for Edison International and its subsidiaries. There could be material differences between actual results and what we currently expect. Factors that are important and could lead to different results are described in our SEC filings. We ask that you read those carefully. Certain outlook assumptions are included in the presentation, along with a reconciliation of non-GAAP measures to the closest GAAP measure. When we get to the question-and-answer session, please keep to 1 question and 1 follow-up. Pedro, I'll hand the call over to you now.
Pedro Pizarro
executiveMuch appreciated, Sam, and good afternoon to everyone. For the first quarter of 2023, Edison International's core EPS came in at $1.09. Our start to the year has pleased us, and we have confidence as we reaffirm guidance for 2023 core EPS of $4.55 to $4.85. Likewise, we stay confident about achieving our long-term target for EPS growth of 5% to 7% across 2021 to 2025. Maria is going to walk through our financial results and outlook. The main point I want to convey today is that we keep seeing many positives both near term and long term, and those have us enthusiastic about what lies ahead for our company. What SCE is doing to maintain and reinforce the electric grid, lower wildfire danger and make carbonization possible via electrification is badly needed across California, and it is expanding our chances to invest. Looking further out, our Pathway 2045 analysis points to the ongoing transmission and distribution investment required for the grid to evolve. California regulators are acknowledging this. Back in 2021, the California ISO put out a 20-year plan that estimated roughly $30 billion in transmission investments required through 2040, which lines up with our Pathway analysis. Just a handful of weeks back, CAISO issued its Draft 2022 to 2023 Transmission Plan, reflecting its present view of system needs across the coming 10 years. In that draft plan, 46 transmission projects are called for, with an estimated total cost of $9.3 billion. More than $2 billion of that consists of proposed incumbent projects for SCE, while over $5 billion consists of FERC Order 1000 competitive projects located within Southern California that SCE can compete for. Nearer term, SCE keeps carrying out its Wildfire Mitigation Plan with diligence, and it has cut the probability of losses from catastrophic wildfires by 75% to 80% relative to pre-2018 levels, mostly through grid hardening measures that let the utility lower risk while continuing to deliver electricity to our customers. Once more I want to thank the many of you who came to see us in person at our headquarters and heard straight from a number of our leaders regarding the utility's accomplishments and continuing efforts. During March, SCE submitted its 2023 to 2025 WMP to the Office of Energy Infrastructure Safety. Page 3 shows the plan's highlights. Safety for the public, customers, workers and first responders stays our #1 priority. Throughout 2023, the utility is continuing to build on work already done while concentrating on 5 key areas. Those are: continuing grid hardening, increasing targeted undergrounding work in severe risk areas, continuing to lower PSPS impacts, extending aerial fire suppression funding to year-round and pushing further in technological advancements. Covered conductor, SCE's flagship grid hardening program, continues to be its key mitigation measure. Between 2023 and 2025, more than 2,850 additional miles of covered conductor are going to be installed. By the close of 2025, SCE anticipates having replaced over 7,200 miles, or roughly 3/4 of overhead distribution power lines in high fire risk areas, with covered conductor. SCE also intends to finish roughly 100 miles of undergrounding by 2025, responding to elevated danger from distinctive local conditions in specific locations, and aims to bury 600 miles in total before 2028 wraps up. Furthermore, to put out fires fast no matter what sparks them and to safeguard the neighborhoods SCE serves, the utility keeps working alongside the LA County Fire Department, Orange County Fire Authority and Ventura County Fire Department to grow their firefighting capacity. As the WMP points out, this backing now extends to aerial fire suppression throughout the entire year via the Quick Reaction Force, which consists of the globe's biggest fire suppression helicopters featuring special nighttime firefighting abilities. The WMP adapts over time, with its emphasis on pushing technological progress forward to uncover fresh methods of lowering wildfire danger. SCE constantly creates new strategies and works together with fellow utilities, with academia and with the energy sector to make our community safer. The WMP calls attention to technologies including the Rapid Earth Current Limiter, Early Fault Detection and the use of artificial intelligence that will keep enhancing our full set of wildfire mitigation tools. Returning to the long-term deal, transportation electrification stands as a major factor behind SCE's grid investment and behind making customer bills manageable. Well, we're not merely discussing regulatory policies or long-range projections here — we're watching customers genuinely begin to embrace and take up EVs right now, among them operators of medium- and heavy-duty vehicle fleets. SCE moved early, and today it offers the nation's biggest collection of transportation electrification programs run by an investor-owned utility, with more than $800 million in approved funding for its Charge Ready programs, which encompass a program targeting the medium- and heavy-duty segment. Momentum and customer interest have definitely grown, and we're starting to witness vehicle availability gains in the heavy-duty segment, with additional options now able to be ordered. SCE is presently collaborating with close to 200 sites to potentially back approximately 4,000 medium and heavy-duty vehicles. Customers running heavy-duty vehicles are asking for more powerful chargers, which produces bigger load requests that might call for extra distribution system upgrades so that sufficient capacity exists. SCE keeps talking with these customers to grasp when and where such vehicles will show up, making sure the grid is prepared. Past transportation electrification, building electrification represents yet another vital chance to cut greenhouse gas emissions. SCE has put forward a $677 million program to help speed up adoption of the electric heat pumps, and the CPUC is reviewing that right now. I'll wrap up by observing that even while SCE pours significant investment into the grid to keep the utility and the state on course for decarbonization and electrification efforts, affordability always stays top of mind. SCE's enduring culture of actively chasing and upholding productivity gains and cost control practices has let it achieve the lowest system average rate among California investor-owned utilities. A couple of things we've done lately: there's the settlement agreement still pending with TURN and Cal Advocates that would shift us to a model where customers fund wildfire self-insurance, plus SCE's operational excellence program — that one covers more than 600 ideas coming from employees, bringing capital efficiency along with O&M benefits. Work planning, procurement and technology are among them, as Page 4 shows. On top of that, we'll keep hunting for fresh chances in digitization, automation, and generative artificial intelligence to push customer interactions, asset data quality and back-office efficiencies even further. As implementation speeds up across 2024 and afterward, those expected benefits ought to grow step by step, which helps affordability for SCE's customers even more. With that, Maria is going to give her financial report.
Maria Rigatti
executiveThank you, Pedro, and good afternoon to all of you. During my remarks today, I'll cover the results for the first quarter, our guidance for 2023 EPS, the 2023 financing plan, and a few other financial matters. Turning to the first quarter of 2023, EIX reported core EPS of $1.09. As the year-over-year quarterly variance analysis on Page 5 shows, SCE's first quarter earnings rose mainly because of GRC attrition year escalation. That gain was partly offset by higher net interest expense, which was driven by increased interest rates tied to funding payments for 2017 and 2018 wildfire claims. At EIX Parent and Other, we saw a negative variance of $0.04 stemming from higher interest expense at the holding company. Now I'd like to talk about SCE's capital and rate base forecast, which appears on Pages 6 and 7; these figures match what we disclosed last quarter. SCE will submit its 2025 GRC application in mid-May, and at that point we will refresh our capital and rate base projections and carry them forward through 2028. In the years ahead, SCE will keep investing in wildfire mitigation and expanding its grid work to serve its customers' needs while also supporting California's leading role in building a carbon-free economy. You can observe this stepped-up investment beginning in our projections for 2025 capital spending, which comes in just under $7 billion. For context, just 6 years ago, our annual CapEx was below $4 billion. Let me give you a quick update on the 2017 and 2018 wildfire and mudslide events. As Page 8 outlines, during the first quarter, SCE resolved roughly $148 million in individual plaintiff claims. This ongoing progress in settling claims allows us to move further along in resolving these historical events. Of course, as we move toward full resolution, we keep gaining more and more information. Every quarter, we factor in our cumulative experience as we refine the best estimates. As a result, SCE raised the best estimate by $90 million. Even more importantly, with this progress, the utility remains confident it will file the TKM cost recovery application in the third quarter of this year. Our message is very clear: SCE will pursue full CPUC cost recovery, excluding amounts forgone under the agreement with the Safety Enforcement Division or already recovered. SCE will present its strong, compelling case that it operated its system prudently and that authorizing full cost recovery serves the public interest. Moving to guidance. Page 9 presents our 2023 EPS guidance along with the key assumptions for modeling purposes. We're pleased with how we've started the year and are confident in reaffirming our 2023 core EPS guidance of $4.55 to $4.85. Progress on the parent company's 2023 financing plan is shown on Page 10. In March, we issued $500 million of junior subordinated notes, which provided $250 million of equity content. The transaction came in line with our expectations, and we were pleased to see strong investor support for this offering, which was significantly oversubscribed. We anticipate producing around $100 million in equity via internal initiatives, which aligns with the $300 million to $400 million equity component outlined in our financing strategy. Another financing milestone: only last week, SCE finalized a securitization for the remaining piece of the $1.6 billion in AB 1054 capital expenditures. For the $775 million offering, SCE experienced quite strong investor participation, leading to a cost-effective deal for SCE's customers and enabling the utility to pay off an existing term loan, which further strengthens its credit profile. Kindly go to Page 11; alongside rising investor backing, our improving business and credit standing is being mirrored in the outlooks from rating agencies. During February, Moody's raised EIX and SCE's credit ratings by 1 notch, citing reduced wildfire risk for SCE. Also, last week, Fitch lifted EIX and SCE's credit ratings by 1 notch, pointing to the substantial drop in major wildfires associated with SCE's equipment after 2018, even with heightened wildfire activity across California in 2020 and 2021, plus continued work to boost system resilience while reducing dependence on and how often public safety power shutoffs occur. Page 12 offers an update regarding the CPUC cost of capital mechanism. Should the 12-month average of the Moody's Baa utility bond index go above 5.37% by the end of September, SCE will submit a Tier 2 advice letter to apply the adjustment to the 2024 ROE. That adjustment would equal half the gap between the average and 4.37%. The mechanism likewise revises the authorized cost of debt and preferred equity. As of April 25, the measurement period average sits near 5.7%; we'll keep tracking the cost of capital mechanism, which might deliver meaningful upside to 2024 earnings if it is triggered. Going forward, we reaffirm our 5% to 7% EPS growth rate guidance spanning 2021 through 2025, equating to 2025 EPS of $5.50 to $5.90. My management team and I remain completely dedicated to achieving this goal. We'll share an update on our EPS growth rate projections through 2028 during our Q2 earnings call. Given robust rate base growth as the core driver, together with the considerable investment required in our electric grid, we stay optimistic regarding the company's growth prospects, near term and long term alike; that wraps up my comments. Sam?
Sam Ramraj
executiveTed, could you please start the Q&A portion? Just a quick note — we’d ask that you keep to one question plus one follow-up, so that everyone waiting gets a chance to ask something.
Angie Storozynski
analystAll right. So to start with, regarding how those 2017 and 2018 claims got resolved — nothing further has been wrapped up beyond what you told us in the fourth quarter update, correct?
Maria Rigatti
executiveNot at all, Angie — Maria here. During this quarter, roughly $148 million in extra claims actually got resolved by us. So resolving more claims has indeed been happening on our end. Each quarter, we give a report on how much has been settled. Demand pace did ease somewhat in the prior quarter. Even so, our position remains quite strong, and for the TKM events, our initial cost recovery application will be submitted in Q3.
Angie Storozynski
analystAll right, that works. And after that, regarding the SCE GRC application you're going to submit in May, are you intending to presume positive load growth when you put that filing together?
Pedro Pizarro
executiveWe'll be submitting it in roughly another 1.5 weeks. As I believe we mentioned during the prior quarter, load growth is starting to accelerate, and the rate case does include certain assumptions. Once we submit it, you'll be able to see them, but load growth assumptions are indeed part of the rate case. Steve Powell, is there anything you'd like to add on that point?
Steve Powell
executiveI suppose, when we're — setting aside the load growth topic, what you'd anticipate seeing in the rate case is a spotlight on everything we've got to get done on the grid, both to serve customer demand at present and the load growth that electrification and other factors might bring. So reliability will be a central piece of that, which includes examining infrastructure replacement work that's been scaled back across the past several years while we've been handling far more wildfire mitigation; accordingly, you'll find additional wildfire mitigation efforts in there, encompassing both the ongoing covered conductor program and our shift toward some targeted undergrounding, plus continued adaptation investments, and naturally, addressing what we anticipate as load growth that, from now through 2035, should average roughly 2% annually; that, in turn, will spur grid investments; and naturally, throughout all of this, it's about ensuring we approach it with affordability in mind, weighing the grid investments that are necessary against what customers need when it comes to affordability.
Angie Storozynski
analystAlright. One final thing I'd like to ask Maria about. With every one of those credit upgrades and the lower wildfire risk, have you noticed — and look, I could probably check this myself, but have you noticed a real narrowing in your credit spreads? I'm just curious whether the rest of the industry is in fact experiencing a rise in what they pay to borrow. Are you actually witnessing a reversal of that risk premium that puts you in a stronger spot than others in the industry?
Maria Rigatti
executiveAbsolutely. So Angie, I'd say that for quite some time, we've experienced the opposite, correct, in that a sizable gap existed between us and where other players in the industry stand. We've communicated that to the commission too; we are observing a bit of an uptick. I believe there remains room to get better, and that's among the items we're extremely focused on as time goes on; but some of these recent upgrades have delivered certain benefits.
Shar Pourreza
analystPedro, during your prepared comments you brought up the CAISO transmission plan and the CapEx opportunities tied to it. I just want to make sure I understand — none of that has been factored into the 5% to 7% growth guidance you're currently giving? And perhaps linking this to CAISO AB 538, which would expand CAISO into a western RTO, does that create additional tailwinds for transmission development in that area?
Pedro Pizarro
executiveYeah. Regarding the first portion of your question, no, those aren't included in our '21 to '25 EPS growth rate. And actually, it's likely those projects would still be at an early stage of development come 2025, given that CAISO is only identifying them at this point. As you're aware, Shar, one difficulty is that transmission development today can stretch out over a decade, mostly due to the approval, permitting, and signing processes. So we're also watching efforts at both the federal and state levels aimed at speeding up permitting and signing. That covers the transmission side. As for your question on Western regional market expansion, we're keeping an eye on the bell; we're in fact quite supportive of the idea of a broader CAISO serving as a platform for a Western regional market. Naturally, the demo will be in the details; and we want to ensure that such an expansion, if and when it occurs — and hopefully it does — is carried out with all the appropriate safeguards in place so that the right benefits flow to California as well as to customers in other states. And you asked if that might add tailwinds — and my view is that a bigger market will open up greater opportunities to reduce the cost of the clean energy transition, and will enable better resource sharing throughout the west. So fundamentally, I believe the primary benefit would be offering a platform that supports greater affordability for California customers and customers throughout the West. And as we noted in our remarks, we're mindful of affordability, and it's something we keep focusing on heavily. So anything along the lines of a Western regional market that helps lower the cost of the transition is a positive, in that it creates more room in our rates either to minimize rates or to give rate room for all the other projects that matter here. Whether a western regional market would translate into more transmission projects, for SCE in the end, that's somewhat harder to say. And I believe the primary benefit is that cost reduction for customers.
Shar Pourreza
analystUnderstood. And then finally, it's clear you folks have just wrapped up the financing plan, yet a cash pay convertible market is kind of taking shape, and a number of peers have already accessed it. A few of them don't even require equity. The interest cost baked into yours sits above 6%, clearly much steeper than what this market offers. Is there any interest on your side in that? And might it be somewhat accretive to the plan you have now?
Maria Rigatti
executiveYes. Shar, this is Maria. So what we've financed so far lines up with what we told you on the prior call regarding the full $1.4 billion; and the junior subordinated notes were designed for the equity content. The remaining equity content, we intend to handle via our internal programs. That's one aspect of it. As for the debt financing we still need to arrange for the rest of the year, we'll evaluate every option available; we aim to be efficient. We want to weigh all the costs, the all-in cost of pursuing that, and factor in both the near term and the longer-term potential costs tied to it; but we'll keep everything on our radar.
Ryan Levine
analystTo follow up on a few of the transmission remarks or inquiries: regarding the initial FERC Order 1000 transmission projects, from a timeline perspective, at what point do you expect the company will probably move forward on those?
Pedro Pizarro
executiveRyan, your audio is breaking up somewhat. Could you say the question again? Perhaps it's a poor phone connection or something like that.
Ryan Levine
analystRegarding those FERC Order 1000 transmission lines, from a timing perspective, when do you expect the company will move on those opportunities?
Pedro Pizarro
executiveRight; so the starting point is really the time line CAISO adheres to as it finalizes the transmission plan and then eventually moves projects through that competitive process. I'm not sure we have a definite schedule as of yet. But Steve, do you know of anything more specific right now?
Steve Powell
executiveYeah. I believe — so within the draft plan, 4 projects were pinpointed as being qualified for competition. The draft plan still needs to be finalized and approved by them; and as for the bidding windows, my understanding is that a few of those windows open as early as the start of summer and carry into the fall; so the bidding for project evaluation is more toward the latter part of this year in terms of when bidders would be submitting on those projects.
Ryan Levine
analystAll right, and for the next question, perhaps directed at Maria. If those projects ended up being consolidated into one, how would you think about funding the additional capital, considering that it has a longer duration?
Maria Rigatti
executiveRight; so if SCE submits a bid and comes out on top, we'll fund it just as we would fund our typical rate base investments, Ryan. So that will happen through our usual process. My sense is that we'll have plenty of chances to cover the whole amount.
Gregg Orrill
analystPerhaps only a brief question regarding the heat pumps investment that's still pending. I'm simply curious how long you'd anticipate that initiative taking to disburse the funds, that $677 million.
Pedro Pizarro
executiveWhat we put forward was structured across 5 years. I believe it's either a 4- or 5-year, 4-year initiative; and just as a reminder, within it we proposed deploying roughly 0.25 million heat pumps; we also suggested bringing about 1/3 of the customers receiving heat pumps along with home upgrades toward broader electrification, so they become electrification-ready. Roughly 90% of this initiative aims at residential customers, and a substantial share of that focuses on low income and disadvantaged communities. It's still moving through the PUC process, so we're looking at approximately 4 years or so of deployment time line once the PUC approves.
Julien Dumoulin-Smith
analystOkay, I'd like to go back to what was said regarding the upcoming update. When you did the — clearly, it's mid-May, and we have this rate base update on the way. From the prepared remarks, it sounded as though you were hinting at possibly extending the earnings outlook during the second quarter call. Could you confirm that, and just give us some background on the assumptions you have in mind there, such as the base year and so on, but even more specifically, how do you view the EPS trajectory perhaps in relation to the rate base that you're going to put out here in mid-May?
Maria Rigatti
executiveAll of those are excellent questions, Julien. Let me address them starting with timing. So when the rate case gets filed in mid-May, at that time we will give an update regarding capital spend and rate base, and that will run through 2028. So that aligns with the schedule of the general rate case itself. Then on the Q2 call, we will add our EPS projections through 2028 on top of that. So your remaining questions are truly great, but we'll put all of that into motion on the Q2 call.
Pedro Pizarro
executiveSo keep watching.
Julien Dumoulin-Smith
analystUnderstood. All right. Got it. And the base year is going to be moved ahead by 2 years?
Maria Rigatti
executiveWe'll cover every one of those specifics once we reach the Q2 call.
Sam Ramraj
executiveAlright, thanks for being with us; that wraps up this call. Enjoy the remainder of your day, and please take care, everybody. You're free to hang up now.
Operator
operatorThank you for your participation. You may disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Edison International transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Edison International earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Edison International or any ticker on your watchlist.