executiveThanks, Missy, and hello everybody. Joining us on the call today are Pedro Pizarro, our President and Chief Executive Officer, and Maria Rigatti, our Executive Vice President and Chief Financial Officer. Other members of the management team are also with us. You can find materials for today's call at www.edisoninvestor.com. Those materials include our Form 10-Q, the prepared remarks from Pedro and Maria, and the teleconference presentation. We'll send out our regular business update presentation tomorrow. On this call, we'll be making forward-looking statements regarding the outlook for Edison International and its subsidiaries. Actual results might differ materially from what we currently expect. Important factors that could lead to different results are described in our SEC filings. Please read those carefully. The presentation contains certain outlook assumptions, along with a reconciliation of non-GAAP measures to the closest GAAP measure. When we get to the question-and-answer session, please keep to one question and one follow-up. I'll now hand the call over to Pedro.
Pedro Pizarro
executiveOkay, thanks Sam, and good afternoon to all of you. For the first quarter of 2024, Edison International's core EPS came in at $1.13. We're happy with how the year has begun, and we feel sure in reaffirming our 2024 core EPS guidance range of $4.70 to $5.05. We're also still confident about meeting our long-term EPS growth targets of 5% to 7% spanning 2021 through 2025, and likewise for 2025 to 2028. That confidence stays rooted in the drivers that keep supporting our outlook. Beginning with SCE's legacy wildfires — the utility keeps moving the claims resolution process forward. According to the most recent information we have, which Maria will go into further, our best estimate of losses went up by $490 million, or $333 million after tax. Now that wildfires are a national concern, litigation results beyond California are affecting what it costs to settle claims everywhere. We stay dedicated to reaching ultimate certainty by pushing through this process quickly and pursuing cost recovery; we feel good about the case SCE has built in TKM and will build for Woolsey. Let me repeat that we firmly believe cost recovery is justified and serves the public interest, and we've taken a conservative approach by not factoring the substantial potential into our financial projections. On the operational side, I want to begin by emphasizing Edison's leadership in how the industry is responding to climate change. Wildfires recently seen around the country serve as a sharp reminder of shifting climate conditions, which highlight why we must further strengthen resiliency and adaptation as we move toward a clean energy future. SCE is unmistakably a leader in wildfire mitigation and is passing along its know-how to peers throughout the industry, who are now facing comparable conditions; we've demonstrated that wildfire risk tied to utility infrastructure can be managed. Additionally, our state has significantly boosted resources for fire suppression, including possessing the largest civil aerial firefighting fleet anywhere in the world. Our regulators grasp how important financially healthy utilities are. AB 1054 established constructive prudency standards along with the insurance fund. During the last five years, SCE has put roughly $5 billion of wildfire mitigation-related capital to work and anticipates investing over $6 billion across the coming five years; that investment stands among the highest levels in the utility sector; on Page 3, the numbers and the results are there for you to see. I'll note that SCE has experienced no ignitions caused by covered conductor failure, and the program is widely recognized for how effective it is. Bringing all of this together in terms of what it means for lowering future risk of losses from wildfires — we estimate that risk is 85% to 88% lower than it was pre-2018. Moving to Page 5. Let me draw attention to three key points that make this reduction even more significant. First, physical mitigation is the dominant factor. Rather than depending heavily on operational measures such as power shutoffs or fast curve settings, physical mitigation serves as the main driver of this risk reduction. That matters because it translates into a far lighter burden for customers. Next, SCE's projection is based on the industry-leading model from Moody's RMS, which insurers broadly rely on. That model takes into account complex variables such as terrain, vegetation, historical records, and additional elements to forecast the likelihood of wildfires. Third, in order to gauge loss probabilities in monetary terms, a stochastic model is used. This model performs 50,000 simulations, factoring in possible emissions and fire sizes while also integrating SCE's mitigation strategy. That stands in contrast to the simpler deterministic approaches some other companies and regulators rely on, which examine only prior events. In short, our externally validated, highly rigorous, data-driven method provides a clear view. Thanks to the utility's mitigation work, SCE's risk profile now looks vastly different from what it was before. Focusing specifically on grid hardening, Pages 6 and 7 show how much progress SCE has achieved so far. I'm happy with what our team has accomplished, and I'm eager to see us keep improving so our communities become even safer. SCE anticipates that by the close of 2025, it will be nearing 90% physical hardening for distribution lines located in high fire-risk zones; with more than 7,300 miles already placed underground and over 5,700 overhead miles hardened, SCE's overall hardened mileage exceeds that of every other California IOU combined. We take real pride in these efforts to quickly improve grid safety for SCE's customers. Now shifting to load growth. Following years of fairly flat demand, we expect 2% to 3% annual growth over the next several years, with an inflection point exceeding 3% annual growth starting in 2028; within SCE's service territory, we anticipate this growth will come from continued electric vehicle adoption, rising industrial electrification, and greater building electrification penetration; in California, 1/4 of new cars sold during 2023 were zero emission vehicles, and that pattern is carrying on into 2024. As a further sign of this acceleration, the state has just hit a milestone with over 100,000 public EV chargers now installed across California, and that comes in addition to more than 500,000 at-home chargers. Southern California already hosts a considerable data center footprint; so although we likewise see limited growth potential from that sector, we expect transportation electrification to produce a much larger rise in the region's electricity demand. As our investment levels increase to support economy-wide electrification, affordability stays a top priority. Over the years we have shown cost leadership, which has given us the lowest system average rate among the major California IOUs. This cost-management discipline is an ongoing priority; for instance, we noted previously that the 2025 GRC application contained $41 million in annual O&M savings as an immediate customer benefit. Well, building on that, in SCE's rebuttal testimony filed earlier this month, the utility pinpointed an additional $35 million in annual O&M savings to further reduce the revenue increase. 2024 is very much a year of execution across the business and we are pleased with our start to the year. SCE keeps making substantial investments and making the grid safer year after year. We continue to see constructive regulatory decisions. We're likewise moving closer to a complete settlement of the old wildfire matters. Because of all this, we stay certain about hitting both our short- and longer-range goals. To wrap up, I want to stress again that Edison International is a great way to invest in California's shift toward clean power. Every single day, SCE is strengthening its network for the good of both customers and investors, and the way it carries out wildfire prevention has delivered encouraging outcomes across 5 straight wildfire seasons. California leads when it comes to electrification, cutting carbon and adjusting to the climate. Being a utility that sells only electricity and concentrates on wires, SCE is well placed to zero in on a future that electricity will drive. The industry widely acknowledges how dedicated we are to leading and innovating in clean energy, and that standing has grown even higher as climate change's effects grow more visible. Making sure the grid is dependable, able to bounce back and fully prepared is essential for pulling off the clean energy shift, and it's the central idea behind where we put our money and how we expand; so with that, I'll hand things to Maria for her financial update.
Maria Rigatti
executiveThank you, Pedro, and hello everyone this afternoon. During my remarks, I'll go over our results for the first quarter of 2024, give you an update regarding regulatory matters, and talk about our 2024 EPS guidance. I'd also like to restate how confident we remain about hitting our targets for EPS growth. I'll start with what we saw in the first quarter. EIX posted core EPS of $1.13. Looking at the analysis of quarterly variances versus the prior year that appears on Page 8, you'll notice core earnings rose $0.04, largely driven by increased CPUC revenue that was authorized in Track 4 of the 2021 GRC along with higher authorized rates of return, though this was partly offset by greater interest expense tied to debt used for wildfire claims payments. EIX Parent and Other came in at the same level as the equivalent period a year ago. Now let's look at SCE's forecast for capital and rate base, which you can find on Pages 9 and 10. These figures match what we disclosed last quarter. SCE's 2025 GRC will handle the majority of the capital plan. That rate case covers investments needed to fulfill the essential goals of reliability, resiliency, and readiness to serve customers' needs both now and going forward. This encompasses ramping up conventional distribution grid investments in areas like replacing infrastructure and accommodating load growth, plus ongoing efforts on wildfire mitigation. SCE is experiencing the quickest growth in electricity demand seen in decades. Because of that, the capital plan shows a return to typical levels of infrastructure replacement required for system reliability, along with major investments aimed at supporting load growth, which is driven mostly by transportation electrification. In the first quarter, interveners filed their testimony and recommendations as part of the GRC proceeding. Page 11 lays out the main points; to sum up, the areas Cal Advocates and TURN chose to focus on did not catch us off guard, and we feel confident we'll achieve a solid result for customers. Taken together, what they recommend would amount to rate base growth of roughly 6%, which aligns with the 6% to 8% rate base growth range we project. On the regulatory side, SCE is also moving forward with several other important proceedings, such as the 2022 CEMA, the TKM cost recovery application, and the WMCE application we filed recently. Earlier in this month, SCE got a favorable proposed decision in the 2022 CEMA proceeding. Should it be adopted, it would approve $191 million in revenue to be recovered across 12 months and give full approval to $312 million in capital expenditures. A vote on the PD is set for the CPUC's May 30 meeting; receiving this decision earlier in the year is a major positive, and its approval bolsters our 2024 EPS guidance. In addition, the ALJ and the cost of capital proceeding recently put out a proposed decision that would reject the intervenors' petition for modification, which had tried to suspend the cost of capital mechanism. This outcome matches the intent the CPUC expressed when the cost of capital mechanism was first adopted, and it strengthens both our position on this matter and our view of the constructive regulatory climate in California. Page 12 offers an update on how resolution of SCE's legacy wildfires is progressing, which keeps moving forward. The revision to our estimated losses came mainly from details we received about the Woolsey Fire mediation program. As you'll remember, plaintiffs needed to file their demand by a February deadline to join that program. What those demands showed us is that a much larger number of plaintiffs plan to keep pursuing claims, since far fewer of them have abandoned their Woolsey litigation and, as we've seen, the TKM process. On top of that, settlements reached during the quarter came in above the values we had previously projected. SCE has now wrapped up 97% of TKM individual plaintiff claims and 86% of Woolsey individual plaintiff claims, and we remain on schedule to submit the Woolsey cost recovery application in Q3. Let me reiterate that SCE plans to pursue full recovery of every eligible cost, so this increase will show up in the cost recovery applications. Over in the TKM proceeding, the upcoming steps are intervener testimony due May 29, followed by SCE's rebuttal testimony due June 28. Now to EPS guidance. Our 2024 core EPS guidance and modeling considerations appear on Page 13. We're happy with how the year has begun and feel confident reaffirming the $4.75 to $5.05 range. As Pedro noted, the estimated losses tied to the 2017 and 2018 events went up. Keep in mind that SCE finances the cost of resolving claims through debt, and that debt sits outside its regulatory capital structure. So SCE anticipates issuing more debt, producing roughly $0.02 of additional interest expense in 2024. Even so, we stay confident about hitting our EPS guidance. The financing costs of resolving claims are part of SCE's cost recovery applications. That means this increase will likewise appear in the cost recovery application. On the financing side, I want to emphasize that our equity needs are limited as we keep deploying large amounts of capital and extending our dividend track record. Page 14 shows that the Parent's 2024 financing plan is almost finished, and we've already taken care of our equity needs through internal programs. We also keep our projection of roughly $100 million of equity annually through 2028. On the right side of Page 15, you can see that SCE's robust cash flow generation plus the additional debt funding accretive growth covers almost all our cash needs through 2028. We've considerably bolstered our balance sheet via efficient financing execution as well as regulatory asset recovery of roughly $4 billion across the past 3 years, with approximately $2 billion anticipated through 2025. This capacity to monitor and recoup prior spending is one more constructive aspect of our regulation, which strikes a balance between executing critical work and maintaining strong regulatory oversight. Acknowledging our balance sheet strength, we were glad that last week S&P reaffirmed our credit ratings and stable outlook. Notably, they reduced our FFO-to-debt downgrade threshold to 14% from 15%, pointing to the company's decreasing business risk as the main reason for that move. We take pride in S&P acknowledging the leading part we play in lowering wildfire danger, particularly when climate hazards and credit standards are rising throughout the sector. Finally, let me point out that modeling sensitivities have been supplied so you can measure how recovering costs tied to the 2017 and 2018 incidents affects several important measures. For every $1 billion recovered, our FFO-to-debt ratio would rise by roughly 40 to 50 basis points, while interest expense would drop by $35 million annually. Those advantages aren't just for our owners. In our view, customers stand to gain by possibly sidestepping up to $4.9 billion in surplus financing costs — an obvious victory for affordability as a whole. To wrap up, our assurance about hitting our financial goals stays solid. What supports that assurance both now and over the long haul is our dedication to execution: execution aimed at achieving our earnings objectives; execution to push regulatory matters forward; and execution of our cost control programs, the foundation of SCE's cost leadership and the lowest system average rate among major IOUs in California. That wraps up what I wanted to say, and I'll hand it back to you, Sam.
Sam Ramraj
executiveMissy, please open the call for questions. <<operator_script>>
Nick Campanella
analystTo kick things off regarding that charge — it's probably a relief that the deadline for this mediation program has come and gone, though you pointed out that the litigation backdrop isn't favorable and that settlements are coming in above what was previously projected. Could you share how confident you are that we won't get hit with yet another upward adjustment when we reach the third quarter and clear out the remaining $800 million? Do you view this as the final revision we'll see? Or what's the right way to frame it as we move toward that Q3 cutoff?
Pedro Pizarro
executiveNick, thanks for asking. Let me begin by directing you to what we've disclosed, okay? Our position has consistently been that each quarter, we revisit and evaluate whether reserves need modification, tuning them so that what we deliver represents our best estimate of the best estimate, correct? Our genuine aim is to handle this squarely and fairly, by the buck per cap. As you mentioned, we did clear a fairly significant milestone with Woolsey; now we can examine what actually came through, and we identified those elements we discussed — namely, a smaller decline in total claims along with a greater anticipated level of awards. Going forward, as I mentioned during my remarks, honestly, Nick, genuine certainty will only arrive by pushing through this process as fast as possible, executing it properly and reaching the end. And it makes me quite happy that we're definitely much nearer to the end on TKM, which you could tell from the filing we submitted last year. We're getting close to that key milestone with Woolsey, at which point we'll be prepared to submit our filing, and we remain on schedule to accomplish that during Q3. Each quarter, we'll keep testing things; and we — essentially by definition, if what we're handing you is our best estimate, that means reality has roughly an even likelihood of coming in above or below it, correct? So we'll keep re-evaluating that on a quarterly basis. That said, our priority remains finishing this process and putting it entirely in the rearview.
Maria Rigatti
executiveNick, let me add one more point that reinforces what Pedro said about completion bringing final certainty. Two figures already mentioned on today's call deserve emphasis. The biggest piece of this situation involves individual plaintiffs. Settlements have been reached for 97% of the individual plaintiffs in TKM, and for 86% of the individual plaintiffs in Woolsey. That is precisely why we can also say we remain on schedule for a Q3 filing regarding Woolsey cost recovery.
Nick Campanella
analystThen, when I consider the effects on the balance sheet — and it looks positive that your commitment remains at merely $100 million in equity annually — that isn't shifting. You've just received the 14% to 15% range, as you mentioned regarding FFO-to-debt during your prepared remarks. So, after accounting for this charge, where do you currently fall within those ranges? Also, what factors might drive you upward or downward as we progress through the year and into '25?
Maria Rigatti
executiveCertainly. From the most recent S&P report I've reviewed, they place us at slightly above 14% FFO to debt. Thus, within or exceeding the rational range for their downgrade threshold. Our target remains 15% to 17% FFO to debt. The financing strategy we shared last quarter, and which appears once more in this quarter's materials, aligns with entering that range across the coming several years. We're advancing well on this as claims keep getting resolved behind us, and also as we keep recouping those minimal accounts — $4 billion across the last 3 years, $2 billion additional through 2025; that, combined with the expanding rate base and the capacity to earn on it plus depreciation, and so on, is genuinely propelling us through that. We examined numerous scenarios, and from that we arrived at $100 million of equity each year through 2028.
Michael Lonegan
analystRegarding the Woolsey loss projection, you mentioned a small group of claimants who were granted additional time. Could you elaborate on that and on the level of insight you have into it? Since those losses would presumably be trickier to quantify.
Maria Rigatti
executiveRight. With the February cutoff, the procedure we followed — as we've mentioned once or twice before — is that when individuals submit their details, at times they provide 100% of what we requested, at times they provide fewer items than we requested, and at times they seek more time. Here, additional time was granted to a number of claimants. There are certain facts we possess regarding their claims. We've managed to categorize them. But additional details will come our way once their claim deadlines arrive, which fall across the coming 2 months. Our assessment work mirrors what we carried out during earlier quarters, in which we drew on what we've learned from a wide array of claims. And clearly, since we continue resolving additional claims, our information grows; and we've brought that knowledge to bear on these remaining demands. Once more, further details will reach us regarding them as we move through the following quarter.
Michael Lonegan
analystGreat; and then second for me, you mentioned submitting separate filings for the more than $2 billion of added capital tied to NextGen ERP and the AMI 2.0 initiatives. I'm just curious whether you might — do you have a tighter schedule for the date you intend to submit those filings, and when they might get incorporated into your plan? Also, what amount of extra equity could we reasonably anticipate to fund it?
Maria Rigatti
executiveSure. So our expectation is that the next-gen ERP filing comes in late 2024, and that the AMI, the smart meter filing, would land in 2025. Combined, those 2 represent a couple of billion dollars in capital. When we consider how to fund those additional or added capital needs, we're truly going to — clearly, SCE will always fund in line with its authorized capital structure. And we'll assess where we stand regarding our credit metrics. Like I said, we're expanding robustly into our credit metric range; and provided we can remain within that range, we'll be keeping to a minimum the equity that would otherwise be needed for those added capital opportunities.
Gregg Orrill
analystI wanted to ask whether there's anything specific we should keep an eye on regarding transmission CapEx trends, whether through the Cal ISO planning process or elsewhere, that's on your mind.
Pedro Pizarro
executiveSure. I can take that one to start, and Steve Powell may want to add something too. As you know, over the past several years, Cal ISO has been deeply involved in the long-range planning effort. My sense is that they, together with other stakeholders in the state, understand that a great deal of work lies ahead if the state is going to hit its net zero targets by 2045. Our countdown to 2045 white paper, which came out last fall, showed a fairly substantial statewide investment requirement for the wires needed to make all of this function. Our estimate is that transmission deployment will have to run at 4x the historical pace. So you've now watched Cal ISO work through a few planning cycles over the past couple of years. I believe Maria already touched on this, and it's certainly in our materials, but there's roughly $2 billion of capital tied to around 17 projects where SCE holds the right of first refusal as the incumbent to perform the work; we therefore expect SCE to carry out that work. On top of that, Cal ISO runs a competitive solicitation process for projects that are new rather than extensions of ones already in place. At this point SCE has 1 application pending, and we're waiting to hear back within the current process. Steve, since you and your team deal with Cal ISO, perhaps you can say more about what comes next regarding their ongoing planning efforts.
Steve Powell
executiveRight. So every year the CISO carries out its transmission planning process on an annual basis. As a result, you can expect a plan to be issued annually. In the latest plan, which came out for the '23-'24 cycle, the majority of projects are located in Northern California, though roughly $90 million in incumbent projects were designated for SCE to construct within our service area; so every one of those plans is going to point to further opportunities for us. We will assess whether we take part in upcoming competitive solicitations for those. Over a longer horizon, the CISO also produces a 20-year outlook; and the most recent 20-year outlook, published a couple of years back, indicated that approximately $30 billion of transmission investment would be required across the next 20 years. The CISO is currently in the middle of refreshing that outlook. They recently released some draft information, but the real milestone is a final report in June, which will provide you with more of the 20-year outlook. Even so, it keeps demonstrating that greater and greater resources are needed to meet the clean energy targets, which were supported by an enormous amount of transmission.
Jeremy Tonet
analystI'd like to begin with something broader, I suppose; with summer on the way, could you give us an update on what buyer conditions look like in your territory at present? And I suppose, what are the overall expectations for the season, given all the derisking that has been achieved over time?
Pedro Pizarro
executiveI'll give you a quick response, and then I'll share the actual message I'd like you to take away. The short answer is, based on the most recent material I've seen in print, this appears to be a normal season, perhaps slightly under normal in terms of risk; that isn't the actual message I want you to take away. We understand that going forward, as the climate changes, we will experience growing, rather than shrinking, climate-driven wildfire risk conditions. Yet our Adapting for Tomorrow white paper from a couple of years back indicated roughly a 20% rise in climate-driven wildfire risk through 2050. So the actual headline here is what I discussed in my prepared remarks, all right? How much hardening we've completed. The 85% to 88% risk that we've removed from the table. And that doesn't even count the risk removed from the table because the state has doubled down on its firefighting capabilities. So clearly, it's interesting, and I know investors occasionally ask us how this year looks or how any particular year looks. But honestly, I believe that is less and less the question. And increasingly, what you ought to be asking is how we're continuing to perform in our hardening and our other measures. And I believe we're performing well there.
Maria Rigatti
executiveAnd Jeremy, despite everything we've done to lower the risk, we remain watchful at all times. I just wanted to emphasize that.
Pedro Pizarro
executiveAbsolutely.
Maria Rigatti
executiveWe're not only carrying on with additional grid hardening efforts, but also improving our modeling and exploring emerging technologies. I believe part of what comes through in that S&P report is precisely the sustained focus we bring to each dimension of risk reduction.
Pedro Pizarro
executiveAnd we're applying new tech to that, correct? So, Maria, as you mentioned, it was great to see S&P acknowledge that. Consider PSPS; it has served as a valuable instrument, yet at this point it represents only around 10% of the total risk reduction we achieve. And we keep searching for methods to hone it and reduce any possible effects on customers. Another point I want to mention is that — Steve Powell is taking a key part in this, we're ensuring that our lessons are passed along to others in the sector because this has become — it isn't just an issue for California anymore, it's not a — no longer something confined to the West; it's a matter of national scope. And so we're pleased that via EEI, which as you know I'm serving as chair of EEI until June of this year, but Steve serves as co-chair of a CEO taskforce at EEI, which is assisting in distributing top methods throughout the industry and also fostering conversation about whether we might, in other states or at the federal level, discover a path toward liability protections similar to what we managed to secure in California via AB 1054. So we treat leadership duties here with seriousness. It isn't solely about safeguarding our customers, but also guaranteeing that we pass that along to the remainder of the industry.
Jeremy Tonet
analystUnderstood. That basically addresses what I was going to ask next, but let's stay on it for a moment. At the federal level, are you noticing any momentum in D.C.? And is it realistic that lawmakers could be pushed toward creating some kind of broad yet countrywide framework here? I'm just curious, given how polarized things are politically right now, whether you believe that might become an actual proposal at some stage?
Pedro Pizarro
executiveYeah. So via EEI, we're heavily involved in that effort, with quite a few trips to Capitol Hill. Look, you're correct, passing a federal budget is pretty difficult nowadays, isn't it? So Capitol Hill is a tough place to operate in. That said, this is no longer a problem confined to one state. It involves many states, and they're red, blue, and all shades in between, correct? So I believe there's growing acknowledgment that a challenge exists here requiring a federal fix. We're still working out how to frame it; and — though I'd highlight that other economy-wide risks show there are instances where a federal-level fix exists. Consider how nuclear operating risk gets handled through the Price-Anderson Act, for instance. Steve, I'm aware you've participated in quite a few of those Capitol Hill conversations too. Anything else you'd like to mention?
Steve Powell
executiveAt this moment, I would simply say that our attention has been heavily on teaching people how the danger is changing and what steps the sector is taking to handle that physical danger itself; when it comes to the monetary side, I believe there is — I am aware that various states are handling this differently. We are going to seek out approaches where you can pair what states are doing with efforts at the federal level that might complement them. A few of the items I understand there is interest in on the Hill involve matters such as being able to take out timber. And there are numerous practical items concerning permits and letting utilities efficiently simplify the process so they can complete their work in high-fire zones; regarding more of the monetary answer, once again, I think a great deal remains to be done even just to define what the request is, and that will require time, yet it is most likely to be some mix of state answers with possible federal-level action.
Jeremy Tonet
analystUnderstood, that clears things up nicely. If I may, one brief follow-up for clarification on the plaintiff extension deadline. I believe the deadline mentioned was sometime in the coming months. Should we be watching for a particular date?
Maria Rigatti
executiveAt present, those deadlines fall at various points across the next 2 months, and we'll be sure to keep you updated.
Ryan Levine
analystI might want to ask about how expenses are put together. Your O&M figures appeared to have risen compared with the prior year, and the footnotes indicate that inspection and maintenance expenses came in higher during this quarter. Should we infer anything from that? Or could you offer any detail on what is behind some of the increase in your costs?
Maria Rigatti
executiveSure. Often, a big part of this comes down to the specific point within every quarter when you record the expense. So a portion of it is simply timing variance between one year and the next. That may be influenced by weather — during years with harsher conditions than usual, you'll complete fewer jobs, and then the following year allows for more jobs. So I'd say our cost structure itself isn't really shifting. Actually, we're concentrated on finding ways to genuinely streamline each of those processes and bring the cost down as time goes on. So there's nothing to infer from that.
Ryan Levine
analystThen, regarding wildfire mitigation plans in a wider sense, if this turns into a more nationwide push for utilities across the country, might there be chances to make implementation costs more efficient? Or any changes you'd expect as it grows into something seen throughout the nation?
Pedro Pizarro
executiveLet me offer a few perspectives on that. First, as I believe we mentioned before, Ryan, our group is always searching for ways to sharpen and enhance things, how to apply emerging technologies, and so on. So perhaps a piece of what you're asking stems from — I'll improvise a bit here and you can let me know whether this matches what you have in mind. If you've got technologies that ultimately get rolled out at a much larger scale spanning several states, then in principle, in concept, that could result in some efficiency gains on those expenses. When adoption is wider, it pushes scale higher. Still, speaking from SCE's standpoint, the people there are deeply committed to continuously grinding away, sharpening our understanding of the risk, sharpening how the models fundamentally characterize that risk, and afterward setting and resetting priorities for the capital and O&M dollars we dedicate to cutting that risk even further. Steve, anything to add?
Steve Powell
executiveSure, Ryan. When I reflect on what we've been through and how we're concentrating on keeping things affordable while also making sure we're reducing wildfire danger, that's where it all begins for any utility that's trying to make sound choices about which risk-reduction measures to put in place. Take our situation, for instance: when it comes to strengthening the grid, covered conductor gives us a highly economical option for tackling the exposure we have; another utility might find something different works better. Then when you move into areas such as inspection—what we've accomplished by merging our aerial inspections with our ground inspections means we're sending crews out less often to perform them. The equipment we rely on for that is the kind that, whenever it can help drive our costs lower, and with more and more vendors building those tools, they could get better and we could have additional chances. There are also areas where you start expanding into, say, vegetation management and the way you carry out those inspections. That means detection—whether through LiDAR or satellite—and with the entire sector zeroing in on those, they'll progress more quickly and let us cut the cost; so we'll absolutely pick up knowledge from others, and they'll pick up knowledge from us, as we work to roll out the most efficient wildfire mitigation while driving down what all of them cost.
Pedro Pizarro
executiveOne last point to add, Steve: this isn't solely a question of what we in the industry plus our technology partners are doing — the government also has a part to play. As you may be aware, I served as co-chair of the Electricity Subsector Coordinating Council, a CEO-led body that essentially forms the bridge joining industry and the federal government on physical and cyber security plus resiliency issues. For our sector, DOE serves as the sponsoring agency, and when it comes to thinking through technologies and figuring out how to obtain federal resources, they've partnered with us very effectively. In areas such as vegetation, plenty of work remains, and more progress is needed in dealing with, for instance, the Forest Service or the Bureau of Land Management — though DOE in particular has partnered with us greatly in examining how these sorts of benefits and scale reach every state that needs them; so that partnership will carry on, and it leaves everyone safer.
Sam Ramraj
executiveWe appreciate you being with us. That brings this conference call to a close. Enjoy the remainder of your day. You are free to disconnect at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Edison International transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Edison International earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Edison International or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.